JP6429973B1 - How to dig a sliding back anchor and shield machine - Google Patents

How to dig a sliding back anchor and shield machine Download PDF

Info

Publication number
JP6429973B1
JP6429973B1 JP2017205125A JP2017205125A JP6429973B1 JP 6429973 B1 JP6429973 B1 JP 6429973B1 JP 2017205125 A JP2017205125 A JP 2017205125A JP 2017205125 A JP2017205125 A JP 2017205125A JP 6429973 B1 JP6429973 B1 JP 6429973B1
Authority
JP
Japan
Prior art keywords
anchor
girder
screw rod
shield
shield machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017205125A
Other languages
Japanese (ja)
Other versions
JP2019078048A (en
Inventor
正勝 関山
正勝 関山
黒松 克郎
克郎 黒松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nikken Lease Kogyo Co Ltd
Original Assignee
Nikken Lease Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nikken Lease Kogyo Co Ltd filed Critical Nikken Lease Kogyo Co Ltd
Priority to JP2017205125A priority Critical patent/JP6429973B1/en
Application granted granted Critical
Publication of JP6429973B1 publication Critical patent/JP6429973B1/en
Publication of JP2019078048A publication Critical patent/JP2019078048A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

【課題】スライド式バックアンカーの移動や位置決めの為に、新たなジャッキを設ける必要の無い手段を提供すること。
【解決手段】シールドジャッキYと接続する複数のアンカー桁10を少なくとも含むバックアンカーAと、アンカー桁10と不動点Cとの間に介設する位置調整部B(ネジ棒30、支圧柱40、規制具50)とを少なくとも具備するスライド式バックアンカーである。シールドジャッキYの伸縮作業時には、各アンカー桁10が受ける掘進推力または土圧を、規制具50、ネジ棒30、支圧柱40の順に不動点Cへと伝達する。移動したアンカー桁10では取り残された規制具50を元の位置に戻して、その他のアンカー桁10の移動時の反力受け体とする。
【選択図】図1
An object of the present invention is to provide a means that does not require a new jack for moving or positioning a sliding back anchor.
A back anchor A including at least a plurality of anchor beams 10 connected to a shield jack Y, and a position adjusting unit B (a screw rod 30 and a support column 40 interposed between the anchor beam 10 and a fixed point C). , A sliding back anchor having at least a restricting tool 50). During expansion / contraction work of the shield jack Y, the digging thrust or earth pressure received by each anchor girder 10 is transmitted to the fixed point C in the order of the restricting tool 50, the screw rod 30, and the bearing column 40. In the moved anchor girder 10, the remaining restriction tool 50 is returned to its original position, and is used as a reaction force receiver when the other anchor girder 10 is moved.
[Selection] Figure 1

Description

本発明は、シールド機の初期掘進に用いるスライド式バックアンカーおよびそのスライド式バックアンカーを用いたシールド機の掘進方法に関する。   The present invention relates to a slide-type back anchor used for initial excavation of a shield machine and a shield machine excavation method using the slide-type back anchor.

シールド掘進機の初期掘進時において、シールド機の前進に伴う反力を受けるための方法として、以下の先行技術文献に記載の技術が知られている。   Techniques described in the following prior art documents are known as methods for receiving a reaction force accompanying the advance of the shield machine during the initial excavation of the shield machine.

特開2012−41748号公報JP 2012-41748 A 特開2013−133682号公報JP 2013-133682 A

佐藤工業株式会社「センターホールジャッキ方式のシールド発進方法」http://www.satokogyo.co.jp/technology/detail.php?id=23&parent_id=2&category_id=23Sato Kogyo Co., Ltd. “Center Hall Jack Method Shield Start Method” http://www.satokogyo.co.jp/technology/detail.php?id=23&parent_id=2&category_id=23

これらの文献に記載のスライド式バックアンカーは、シールドジャッキの反力を受けるためのバックアンカーの移動に、シールドジャッキとは別のジャッキを新たに設けなければならず、これらのジャッキの設置に時間を要したり、作業空間が占められたりする問題が生じていた。   In the slide type back anchor described in these documents, a jack other than the shield jack must be newly provided for the movement of the back anchor to receive the reaction force of the shield jack, and it takes time to install these jacks. And the problem that the work space is occupied has arisen.

よって、本発明は、スライド式バックアンカーの移動や位置決めの為に、新たなジャッキを設ける必要の無い手段の提供を目的の1つとする。   Therefore, an object of the present invention is to provide a means that does not require a new jack for moving or positioning the sliding back anchor.

上記課題を解決すべくなされた本願の第1発明は、シールド機の掘進に用いるスライド式バックアンカーであって、シールド機のシールドジャッキと直接又は間接的に接続する複数のアンカー桁を少なくとも含んでなる、バックアンカーと、前記アンカー桁と不動点との間に介設し、シールド機の掘進方向に対して前記アンカー桁を位置決め自在に構成する、位置調整部と、を少なくとも具備し、前記アンカー桁が、掘進方向に貫通して互いに連通する、挿通孔、を少なくとも有し、前記位置調整部が、掘進方向を長手方向として、前記挿通孔に挿通する、ネジ棒と、掘進方向を長手方向とする、支圧柱と、前記ネジ棒に螺合して、螺合位置より後方へのアンカー桁の後退を規制可能な、規制具と、を少なくとも具備し、前記ネジ棒および支圧柱は、互いの前端側を直接又は間接的に接続し、前記ネジ棒の後端側は、解放し、前記支圧柱の後端側は、前記不動点と接続してあり、前記アンカー桁が受ける掘進推力または土圧を、規制具、ネジ棒、支圧柱、不動点の順に伝達することを特徴とする。
また、本願の第2発明は、前記第1発明において、移動対象以外のアンカー桁のうち少なくとも何れか1つのアンカー桁において、シールドジャッキの伸縮状態を問わずに、移動対象のアンカー桁を支持する、支持面を有することを特徴とする。
また、本願の第3発明によれば、前記第1発明または第2発明において、前記アンカー桁同士で、支圧柱およびネジ棒を共有していることを特徴とする。
また、本願の第4発明は、前記第1発明乃至第3発明のうち何れか1つの発明において、前記アンカー桁の前方に、シールドジャッキの後端と接続する伝達桁を設けてあることを特徴とする。
また、本願の第5発明は、前記第1発明乃至第4発明のうち何れか1つの発明に記載のスライド式バックアンカーを用いたシールド機の掘進方法であって、(a)複数のアンカー桁の後退を、規制具で規制する工程、(b)複数のアンカー桁のうち少なくとも何れか1つのアンカー桁に接続するシールドジャッキを伸長して、シールド機の前進を行う工程、(c)移動対象のアンカー桁に接続するシールドジャッキを縮長して、移動対象以外のアンカー桁で土圧を受けながら、移動対象のアンカー桁を前方に引き寄せる工程、(d)移動対象のアンカー桁に挿通してあるネジ棒上の規制具の前方への螺合を進めて、前記(a)の状態へと戻す工程、を少なくとも含むことを特徴とする。
The first invention of the present application to solve the above problems is a sliding back anchor used for excavation of a shield machine, and includes at least a plurality of anchor beams connected directly or indirectly to a shield jack of the shield machine. Comprising at least a back anchor and a position adjusting unit interposed between the anchor girder and a fixed point so as to be capable of positioning the anchor girder with respect to a digging direction of a shield machine. The girder has at least an insertion hole penetrating in the digging direction and communicating with each other, and the position adjusting unit is inserted into the insertion hole with the digging direction as a longitudinal direction, and a screw rod and the digging direction in the longitudinal direction At least a support column and a restricting tool that can be screwed into the threaded rod to restrict the backward movement of the anchor beam from the threaded position. The columns are connected directly or indirectly to the front end sides of each other, the rear end side of the screw rod is released, and the rear end side of the bearing column is connected to the fixed point, and the anchor beam The digging thrust or earth pressure received by is transmitted in the order of a restricting tool, a screw rod, a supporting column, and a fixed point.
Further, in the second invention of the present application, in the first invention, at least any one anchor girder other than the movement target supports the anchor girder to be moved regardless of the expansion / contraction state of the shield jack. And a support surface.
According to the third invention of the present application, in the first invention or the second invention, the anchor beam and the screw rod are shared by the anchor beams.
According to a fourth invention of the present application, in any one of the first to third inventions, a transmission beam connected to a rear end of a shield jack is provided in front of the anchor beam. And
According to a fifth aspect of the present invention, there is provided a shield machine excavation method using the sliding back anchor according to any one of the first to fourth aspects, wherein: (a) a plurality of anchor beams (B) a step of extending a shield machine by extending a shield jack connected to at least one of the plurality of anchor beams, and (c) a moving object. (D) Inserting the anchor girder to be moved forward while reducing the length of the shield jack connected to the anchor girder, and receiving the earth pressure at the anchor girder other than the object to be moved, (d) It includes at least a step of advancing screwing of a restricting tool on a certain screw rod to the state of (a).

本発明によれば、以下に記載する効果のうち、少なくとも何れか1つの効果を奏する。
(1)シールドジャッキを接続するアンカー桁(バックアンカー)の位置決めをネジ棒に螺合する規制具で行うため、シールドジャッキ以外のジャッキ(センターホールジャッキなど)を必要としない。
よって、ジャッキや油圧機構の設置時間の低減や、作業スペースの確保に繋がる。
(2)仮セグメントの構築が不要である。
(3)前記(1)(2)により、狭い立坑内でのシールド掘進が可能となる。
(4)シールドジャッキは元々独立して動作可能に構成してあるため、初期掘進時の方向制御も容易である。
(5)アンカー桁同士で支圧柱およびネジ棒を共有することで、バックアンカー周辺のスペースをより確保できる。
(6)アンカー桁が常にその他のアンカー桁で支持されるため、アンカー桁を安定して支持できる。
According to the present invention, at least one of the effects described below is achieved.
(1) Since the anchor girder (back anchor) to which the shield jack is connected is positioned with a restricting tool screwed onto the screw rod, a jack other than the shield jack (such as a center hole jack) is not required.
Therefore, the installation time of the jack and the hydraulic mechanism can be reduced and the work space can be secured.
(2) Construction of a temporary segment is unnecessary.
(3) According to the above (1) and (2), shield excavation in a narrow shaft is possible.
(4) Since the shield jack is originally configured to be operable independently, the direction control during the initial excavation is also easy.
(5) By sharing the bearing column and the screw rod between the anchor beams, it is possible to secure more space around the back anchor.
(6) Since the anchor beam is always supported by other anchor beams, the anchor beam can be supported stably.

実施例1に係るスライド式バックアンカーの全体構成を示す概略側面図。1 is a schematic side view showing an overall configuration of a sliding back anchor according to Embodiment 1. FIG. バックアンカーの構造を示す概略正面図。The schematic front view which shows the structure of a back anchor. アンカー桁と、ネジ棒および支圧柱との位置関係を示す概略断面図。The schematic sectional drawing which shows the positional relationship of an anchor girder, a screw rod, and a support column. シールド機の掘進方法の手順を示す概略図(1)。Schematic (1) which shows the procedure of the excavation method of a shield machine. シールド機の掘進方法の手順を示す概略図(2)。Schematic (2) which shows the procedure of the excavation method of a shield machine. 実施例2に係るスライド式バックアンカーにおいてバックアンカーの構成を示す概略図。Schematic which shows the structure of a back anchor in the slide type back anchor which concerns on Example 2. FIG.

以下、図面を参照しながら、本発明の実施形態について説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

<1>全体構成(図1)
図1では、発進立坑内からシールド機を初期掘進させる際に、本発明に係るスライド式バックアンカーを用いた例を示している。
スライド式バックアンカーは、シールド機Xの後方に設置する構造体である。
スライド式バックアンカーは、シールドジャッキYと直接または間接的に接続するバックアンカーAと、前記バックアンカーAの位置を調整する位置調整部Bと、を少なくとも具備する。
バックアンカーAは、シールド機Xの掘進推力や、シールド機Xが受ける土圧を、シールドジャッキYと直接又は間接的に接続する複数のアンカー桁10を少なくとも含んで構成する。
また、位置調整部Bは、前記アンカー桁10を個別に移動および位置決め可能に構成するための、ネジ棒30、支圧柱40、規制具50を少なくとも含んで構成する。
以下、各構成要素の詳細について説明する。
<1> Overall configuration (Fig. 1)
FIG. 1 shows an example in which the slide-type back anchor according to the present invention is used when the shield machine is initially excavated from the starting vertical shaft.
The sliding back anchor is a structure that is installed behind the shield machine X.
The sliding back anchor includes at least a back anchor A that is directly or indirectly connected to the shield jack Y, and a position adjusting unit B that adjusts the position of the back anchor A.
The back anchor A includes at least a plurality of anchor beams 10 that directly or indirectly connect the shield machine X with the excavation thrust of the shield machine X and the earth pressure received by the shield machine X.
Further, the position adjusting unit B includes at least a screw rod 30, a supporting column 40, and a restricting tool 50 for configuring the anchor beam 10 so as to be individually movable and positionable.
Details of each component will be described below.

<2>アンカー桁(図1〜図3)
アンカー桁10は、シールドジャッキYの伸縮時において、シールド機Xによる掘進推力やシールド機Xが受ける土圧を直接または間接的に受けるための部材である。
アンカー桁10は、バックアンカーをシールドジャッキのグループ毎に分割してなり、これらのアンカー桁10に接続するシールドジャッキYを個別に動作することで、アンカー桁10を個別に移動させることができる。
本実施例では、図2に示すように、バックアンカーAを、矩形形状の桁材を一辺毎に分割した4つのアンカー桁(上側アンカー桁10a、下側アンカー桁10b、および2つの横側アンカー桁10c、10d)で構成している。
<2> Anchor girder (FIGS. 1 to 3)
The anchor girder 10 is a member for directly or indirectly receiving the excavation thrust by the shield machine X and the earth pressure received by the shield machine X when the shield jack Y is expanded and contracted.
The anchor girder 10 is formed by dividing the back anchor into groups of shield jacks, and the anchor girder 10 can be moved individually by individually operating the shield jacks Y connected to the anchor girders 10.
In this embodiment, as shown in FIG. 2, the back anchor A is divided into four anchor girders (upper anchor girder 10a, lower anchor girder 10b, and two lateral anchors) obtained by dividing a rectangular girder on each side. Digits 10c and 10d).

<2.1>伝達桁の設置(図1,2)
本実施例では、図1,2に示すように、各アンカー桁10の前方側にそれぞれ伝達桁20(20a〜20d)を設けており、各伝達桁20にシールドジャッキYの後端を接続している。
よって、本実施例での各アンカー桁10は、各伝達桁20を介してシールド機Xの掘進推力等を間接的に受ける構造を呈している。
<2.1> Installation of transmission girder (Figs. 1 and 2)
In this embodiment, as shown in FIGS. 1 and 2, transmission girders 20 (20 a to 20 d) are provided on the front side of the anchor girders 10, and the rear ends of the shield jacks Y are connected to the respective transmission girders 20. ing.
Therefore, each anchor girder 10 in the present embodiment has a structure that indirectly receives the digging thrust or the like of the shield machine X via each transmission girder 20.

<2.2>挿通孔の形成(図2,3)
各アンカー桁10(10a〜10d)には、前後方向(掘進方向)に貫通してなる、挿通孔11(11a〜11d)を設けている。
図2に示すように、挿通孔11は、各アンカー桁10の長手方向の両端に、上下方向に間隔を空けて二箇所設けてある。
挿通孔11の径は、後述するネジ棒30よりも大きな径とする。
よって、本実施例では、1つのアンカー桁10の長手方向の端部に二箇所ずつ設けてあり、1つのアンカー桁10で計四箇所の挿通孔11を有する態様としている。
<2.2> Formation of insertion holes (Figs. 2 and 3)
Each anchor girder 10 (10a to 10d) is provided with an insertion hole 11 (11a to 11d) that penetrates in the front-rear direction (digging direction).
As shown in FIG. 2, two insertion holes 11 are provided at both ends in the longitudinal direction of each anchor beam 10 with a space in the vertical direction.
The diameter of the insertion hole 11 is larger than a screw rod 30 described later.
Therefore, in this embodiment, two places are provided at each longitudinal end of one anchor girder 10, and one anchor girder 10 has a total of four insertion holes 11.

<2.3>貫通孔の形成(図2,3)
また、各アンカー桁10(10a〜10d)には、前記挿通孔11の間に、前後方向(掘進方向)に貫通してなる、貫通孔12(12a〜12d)を一箇所設けている。
挿通孔12の径は、後述するネジ棒30よりも大きな径とする。
よって、本実施例では、1つのアンカー桁10に対し、長手方向の端部に一箇所ずつ計二箇所の貫通孔12を有する態様としている。
<2.3> Formation of through holes (Figs. 2 and 3)
In addition, each anchor beam 10 (10a to 10d) is provided with one through hole 12 (12a to 12d) that extends through the insertion hole 11 in the front-rear direction (digging direction).
The diameter of the insertion hole 12 is larger than a screw rod 30 described later.
Therefore, in this embodiment, one anchor girder 10 has a total of two through holes 12 at one end in the longitudinal direction.

<3>ネジ棒(図1,3)
ネジ棒30は、後述する規制具50を介してシールド機Xの掘進推力等を、支圧柱40に伝達するための要素である。
ネジ棒30(30a〜30d)は、掘進方向を長手方向とする、ネジ溝を有する部材で構成し、例えばPC鋼棒などを用いることができる。
図1に示すように、ネジ棒30の前端側は、別途設けた接続板31に固定してあるナット(図示せず)などに締結しており、ネジ棒30の後端側は、解放端としている。
この接続板31は、図示しない部材で載置または吊り下げておき、落下を阻止しておいてもよい。
そして、図3に示すように、ネジ棒30はアンカー桁10の両端に設けてある挿通孔11にそれぞれ挿通してある。
<3> Screw rod (Figs. 1 and 3)
The screw rod 30 is an element for transmitting the digging thrust and the like of the shield machine X to the support column 40 via a restricting tool 50 described later.
The screw rod 30 (30a to 30d) is formed of a member having a screw groove whose longitudinal direction is the digging direction, and for example, a PC steel rod can be used.
As shown in FIG. 1, the front end side of the screw rod 30 is fastened to a nut (not shown) fixed to a connection plate 31 provided separately, and the rear end side of the screw rod 30 is a release end. It is said.
The connection plate 31 may be placed or suspended by a member (not shown) and prevented from falling.
As shown in FIG. 3, the screw rods 30 are respectively inserted into the insertion holes 11 provided at both ends of the anchor beam 10.

<4>支圧柱(図1,3)
支圧柱40は、ネジ棒30および不動点Cと接続して、シールド機Xの掘進推力等を不動点Cまで伝達するための要素である。
支圧柱40(40a〜40d)は、掘進方向を長手方向とする、柱部材で構成する。
図1に示すように、支圧柱40の前端側は、前記したネジ棒30の前端側を固定してある接続板31と接続しておき、支圧柱40の後端側は、立坑内の不動点Cに固定しておく。
そして、図3に示すように、支圧柱40は、アンカー桁10の両端に設けてある貫通孔12にそれぞれ挿通してある。
<4> Bearing column (Figs. 1 and 3)
The supporting column 40 is an element for connecting the screw rod 30 and the fixed point C and transmitting the digging thrust and the like of the shield machine X to the fixed point C.
The bearing column 40 (40a to 40d) is formed of a column member whose longitudinal direction is the digging direction.
As shown in FIG. 1, the front end side of the support column 40 is connected to the connecting plate 31 to which the front end side of the screw rod 30 is fixed, and the rear end side of the support column 40 is connected to the shaft. The fixed point C is fixed.
As shown in FIG. 3, the support column 40 is inserted through the through holes 12 provided at both ends of the anchor beam 10.

<5>規制具(図3)
規制具50は、ネジ棒30に螺合することによって、ネジ棒30を挿通してあるアンカー桁10の後退を規制するための部材である。
図3に示すように、規制具50(50a〜50d)は、ネジ棒30に螺合可能で、前記挿通孔11よりも大径のナットなどを用いることができる。
この規制具50を、ネジ棒30の解放端側から螺合し、アンカー桁10の背後近傍の位置に留めておけば、アンカー桁10が後退しようとしても、規制具50がアンカー桁10と干渉することとなり、当該規制具50の螺合位置よりも後方に向かってアンカー桁10が移動できなくなる。
<5> Regulator (Fig. 3)
The restricting tool 50 is a member for restricting the backward movement of the anchor beam 10 inserted through the screw rod 30 by being screwed into the screw rod 30.
As shown in FIG. 3, the restrictor 50 (50 a to 50 d) can be screwed into the screw rod 30, and a nut having a larger diameter than the insertion hole 11 can be used.
If the restricting tool 50 is screwed from the open end side of the screw rod 30 and is held at a position near the back of the anchor girder 10, the restricting tool 50 interferes with the anchor girder 10 even if the anchor girder 10 tries to retreat. As a result, the anchor girder 10 cannot move rearward from the screwing position of the restriction tool 50.

<6>シールド機の直進時の手順(図4、5)
前記したスライド式バックアンカーを用いたシールド機の掘進方法において、シールド機Xを直進させる場合の手順例について説明する。
なお、図4,5では、説明の便宜上、奥側に見えるシールドジャッキYや、アンカー桁10、伝達桁20などの図示を省略している場合がある。
<6> Procedure when the shield machine goes straight (Figs. 4 and 5)
In the shield machine excavation method using the sliding back anchor described above, an example of a procedure when the shield machine X goes straight will be described.
4 and 5, illustration of the shield jack Y, the anchor beam 10, the transmission beam 20, and the like that are visible on the back side may be omitted for convenience of explanation.

<6.1>工程(a):初期状態(後退規制状態)(図4(a))
図4(a)では、全てのアンカー桁10(10a〜10d)の背後に規制具50(50a〜50d)が螺合してある状態であり、バックアンカーAの後退が規制されている状態である。
<6.1> Step (a): Initial State (Backward Restricted State) (FIG. 4 (a))
In Fig.4 (a), it is in the state in which the control tool 50 (50a-50d) is screwed behind all the anchor girders 10 (10a-10d), and the retreat of the back anchor A is controlled. is there.

<6.2>工程(b):シールド機の前進(図4(b))
この状態から、全てのシールドジャッキYの伸長を開始すると、シールド機Xは直進方向に掘進する。
このとき、各シールドジャッキYの伸長に伴って生じるシールド機Xの掘進推力は、各アンカー桁10から、当該アンカー桁10の後方に設けた規制具50、ネジ棒30、支圧柱40、不動点Cの順に伝達することになる。
よって、シールド機Xの掘進推力は、最終的に不動点Cまで伝達され、バックアンカーAは反力受け部として機能することとなる。
<6.2> Step (b): Advance of shield machine (FIG. 4B)
When the extension of all the shield jacks Y is started from this state, the shield machine X digs in the straight direction.
At this time, the digging thrust of the shield machine X generated along with the extension of each shield jack Y is generated from each anchor girder 10, the restricting tool 50 provided behind the anchor girder 10, the screw rod 30, the bearing column 40, and the immobility. It is transmitted in the order of point C.
Therefore, the excavation thrust of the shield machine X is finally transmitted to the fixed point C, and the back anchor A functions as a reaction force receiving portion.

<6.3>工程(c):アンカー桁の引き寄せ(図4(c))
全てのシールドジャッキYを伸長してある状態から、各アンカー桁10のシールドジャッキYの縮長作業を行い、個別にアンカー桁Yの引き寄せ(前進)作業を行う。
これは、全てのアンカー桁10を同時に引き寄せると、シールド機Xが受ける土圧を受けることができなくなり、シールド機Xのバックリングが生じるためである。
この引き寄せるアンカー桁10を、移動対象のアンカー桁と定義し、その他のアンカー桁10を、移動対象以外のアンカー桁と定義する。
<6.3> Step (c): Pulling the anchor beam (FIG. 4C)
From the state where all the shield jacks Y are extended, the length reduction work of the shield jack Y of each anchor girder 10 is performed, and the anchor girder Y is drawn (advanced) individually.
This is because if all the anchor beams 10 are pulled at the same time, the earth pressure received by the shield machine X cannot be received and buckling of the shield machine X occurs.
The attracting anchor digit 10 is defined as an anchor digit to be moved, and the other anchor digits 10 are defined as anchor digits other than the movement target.

[横側アンカー桁の引き寄せ]
図4(c)は、4つのアンカー桁(10a〜10d)のうち最も手前側にある横側アンカー桁10cの引き寄せ作業を行った状態を示している。
このとき、残る3つのアンカー桁(上側アンカー桁10a、下側アンカー桁10b、横側アンカー桁10d)は、まだ同じ位置に留まっている状態であり、各規制具50(50a,50b,50d)によって、後退が規制されている状態である。
よって、移動対象のアンカー桁(横側アンカー桁10c)の引き寄せ作業時にシールド機が受ける土圧は、移動対象以外のアンカー桁(上側アンカー桁10a、下側アンカー桁10b、横側アンカー桁10d)が受けて、これらのアンカー桁10の背後にそれぞれ設けた規制具50(50a,50b,50d)、ネジ棒30(30a,30b,30d)、支圧柱40(40a,40b,40d)、不動点Cの順に伝達して受けることとなる。
[Pulling side anchor girder]
FIG.4 (c) has shown the state which pulled the horizontal anchor girder 10c in the front side among the four anchor girders (10a-10d).
At this time, the remaining three anchor girders (upper anchor girder 10a, lower anchor girder 10b, and lateral anchor girder 10d) are still in the same position, and each restricting tool 50 (50a, 50b, 50d). Is a state in which the backward movement is restricted.
Therefore, the earth pressure received by the shield machine during the pulling work of the anchor girder for movement (lateral anchor girder 10c) is the anchor girder other than the movement object (upper anchor girder 10a, lower anchor girder 10b, horizontal anchor girder 10d). In response, the restrictors 50 (50a, 50b, 50d), the screw rods 30 (30a, 30b, 30d), the bearing columns 40 (40a, 40b, 40d), which are provided behind the anchor beams 10, are immobile. It is transmitted and received in the order of point C.

[横側アンカー桁と規制具との離隔]
また、引き寄せた横側アンカー桁10cに挿通してあるネジ棒30cに螺合してある規制具50cは、そのままの位置に取り残された状態となる。
[Separation between side anchor girder and restrictor]
Further, the restricting tool 50c screwed into the threaded rod 30c inserted through the pulled lateral anchor girder 10c is left in the same position.

<6.4>工程(d):規制具の前進(図5(a))
前記したとおり、引き寄せた横側アンカー桁10cに挿通してあるネジ棒30cに螺合してある規制具50cは、そのままの位置に取り残されており、このままでは横側アンカー桁10cの後退は規制されていない状態である。
そこで、横側アンカー桁10cの後方で取り残されていた規制具50cについてネジ棒30c上での螺合をすすめて、再度横側アンカー桁10cの背後まで規制具50cを移動させる。
この状態となれば、横側アンカー桁10cが受ける力を規制具50cに伝達可能な状態へと復帰することができる。
<6.4> Step (d): Advancement of Regulator (FIG. 5 (a))
As described above, the restricting tool 50c screwed into the threaded rod 30c inserted through the pulled lateral anchor girder 10c is left in the same position, and the retraction of the horizontal anchor girder 10c is restricted as it is. It is a state that has not been done.
Therefore, the restriction member 50c left behind the lateral anchor beam 10c is screwed on the screw rod 30c, and the restriction member 50c is moved to the back of the lateral anchor beam 10c again.
If it will be in this state, it can return to the state which can transmit the force which the side anchor girder 10c receives to the control tool 50c.

<6.5>残るアンカー桁への繰り返し(図5(b))
残る上側アンカー桁10a、下側アンカー桁10b、横側アンカー桁10dについて、上記行程(c)(d)を進めることで、最終的に全てのアンカー桁10(10a〜10d)を前進させれば、次のシールドXによる掘進作業に向けて、行程(a)(b)を進めることができる。
<6.5> Repeat to remaining anchor girder (Fig. 5 (b))
For the remaining upper anchor beam 10a, lower anchor beam 10b, and lateral anchor beam 10d, if all the anchor beams 10 (10a to 10d) are finally advanced by proceeding the above steps (c) and (d), The steps (a) and (b) can be advanced toward the next excavation work by the shield X.

<7>シールド機の曲進時の手順(図示せず)
なお、図示しないが、シールド機Xを何れかの方向に曲げて掘進する場合には、適宜曲げる方向のアンカー桁10についてシールドジャッキYの伸長と縮長を行っていくなどして方向調整が可能である。
<7> Procedures for turning the shield machine (not shown)
Although not shown, when bending the shield machine X in any direction, the direction can be adjusted by extending or shortening the shield jack Y for the anchor beam 10 in the appropriate bending direction. It is.

<8>その他(横側アンカー桁の支持構造)
なお、図4(c)では、説明の便宜上、シールドジャッキYの伸縮長を長くして、横側アンカー桁10cとその他のアンカー桁10(10a,10b,10d)とを大きく離隔させた状態として、図示しないレール部材などでそれぞれアンカー桁を支持するよう構成しているが、例えば、シールドジャッキYの伸縮長を各アンカー桁10の前後幅よりも短くすれば(図示せず)、下側アンカー桁10bの上面は、引き寄せた横側アンカー桁10cを常に支持する支持面を有する状態とすることができる。
同じように、横側アンカー桁10c,10dに上側アンカー桁10aを支持する支持面を有する状態としておけば、如何なる順番でアンカー桁10の引き寄せ作業を行ったとしても、アンカー桁10が不安定な位置に置かれることがない。
<8> Others (support structure for side anchor girders)
In FIG. 4C, for convenience of explanation, the extension length of the shield jack Y is increased, and the lateral anchor beam 10c and the other anchor beam 10 (10a, 10b, 10d) are separated from each other. The anchor girders are configured to be supported by rail members (not shown). For example, if the expansion / contraction length of the shield jack Y is shorter than the front and rear width of each anchor girder 10 (not shown), the lower anchor The upper surface of the girder 10b can have a support surface that always supports the pulled lateral anchor girder 10c.
Similarly, if the lateral anchor girders 10c and 10d have a support surface for supporting the upper anchor girders 10a, the anchor girders 10 are unstable regardless of the order in which the anchor girders 10 are pulled. Will not be placed in position.

<9>まとめ
このように、本発明に係るスライド式バックアンカーによれば、シールド機の掘進とバックアンカーの移動にシールドジャッキを用いるため、ジャッキや仮セグメントなどの追加設備が必要ない。
また、これらの追加設備の設置スペースが解放されるため、狭い立坑内での初期掘進時に有益である。
<9> Summary As described above, according to the slide type back anchor according to the present invention, since the shield jack is used for the excavation of the shield machine and the movement of the back anchor, no additional equipment such as a jack or a temporary segment is required.
Moreover, since the installation space of these additional facilities is released, it is useful at the time of initial excavation in a narrow shaft.

本発明の第2実施例について、図6を参照しながら説明する。   A second embodiment of the present invention will be described with reference to FIG.

<1>ネジ棒と支圧柱の共有(図6)
本発明では、アンカー桁10同士で、ネジ棒30および支圧柱40を共有するように構成してもよい。
図6に、第2実施例に係るスライド式バックアンカーAのアンカー桁10周辺の構造を示す。
図6では、上側アンカー桁10aおよび下側アンカー桁10bを前方側とし、横側アンカー桁10c、10dを後方側として、これらの挿通孔11を重ね合わせるように、各アンカー桁10を配置している。
そして、重なった挿通孔11にネジ棒30や支圧柱40を挿通して、バックアンカー全体の四隅で、ネジ棒および支圧柱を共有している。
このとき、前方側のアンカー桁10a,10bと、後方側のアンカー桁10c,10dを接触する状態とする場合には、前方側のアンカー桁用の規制具50a,50bが干渉しないよう、後方側の挿通孔11c,11dの径の一部を規制具の径よりも大きくしておけばよい。
なお、本実施例の態様では、シールドジャッキYの縮長によるアンカー桁10の引き寄せ作業は、前方側のアンカー桁10a,10bを先行して進めてから、後方側のアンカー桁10c,10dをその後進める必要がある。
<1> Sharing of screw rod and bearing column (Fig. 6)
In the present invention, the anchor bar 10 may be configured to share the screw rod 30 and the bearing column 40 with each other.
FIG. 6 shows a structure around the anchor beam 10 of the sliding back anchor A according to the second embodiment.
In FIG. 6, each anchor beam 10 is arranged so that these insertion holes 11 are overlapped with the upper anchor beam 10 a and the lower anchor beam 10 b as the front side and the lateral anchor beams 10 c and 10 d as the rear side. Yes.
Then, the screw rod 30 and the support column 40 are inserted through the overlapping insertion holes 11, and the screw rod and the support column are shared at the four corners of the entire back anchor.
At this time, when the front anchor beam 10a, 10b and the rear anchor beam 10c, 10d are brought into contact with each other, the rear anchor beam regulators 50a, 50b are prevented from interfering with each other. A part of the diameter of the insertion holes 11c, 11d may be made larger than the diameter of the restricting tool.
In the embodiment, the pulling operation of the anchor beam 10 by the contraction of the shield jack Y is performed by moving the anchor beams 10a and 10b on the front side first and then moving the anchor beams 10c and 10d on the rear side thereafter. It is necessary to proceed.

<2>アンカー桁同士の支持
また、本実施例では、アンカー桁10a,10bと、アンカー桁10c,10dとで前後関係が生まれるため、両方の横側アンカー桁10c,10dに上側アンカー桁10aの移動の如何を問わずに支持可能な支持面13c,13dを設けている。(符号13dは図示せず)
よって、上側アンカー桁10aの引き寄せ作業の際に、横側アンカー桁10c、10dでもって上側アンカー桁10aを支えておくことができる。
同様に、下側アンカー桁10bにも、横側アンカー桁10c,10dを支持するための支持面13bを設けておくと、両方の横側アンカー桁10c、10dの引き寄せ作業の際に、下側アンカー桁10bでもってこれらのアンカー桁10c、10dを支えておくことができる。
<2> Support of Anchor Girder In addition, in this embodiment, the anchor girder 10a, 10b and the anchor girder 10c, 10d have a front-rear relationship, so the upper anchor girder 10a is connected to both lateral anchor girders 10c, 10d. Support surfaces 13c and 13d that can be supported regardless of movement are provided. (Reference numeral 13d is not shown)
Therefore, the upper anchor beam 10a can be supported by the lateral anchor beams 10c and 10d when the upper anchor beam 10a is pulled.
Similarly, if the lower anchor beam 10b is provided with a support surface 13b for supporting the horizontal anchor beams 10c and 10d, the lower anchor beam 10c and 10d can be moved to the lower anchor beam 10c and 10d. These anchor beams 10c and 10d can be supported by the anchor beam 10b.

<3>まとめ
このように、本実施例に係るスライド式バックアンカーによれば、ネジ棒および支圧柱を共有することで、これらの点数を削減し、バックアンカー周辺のスペースをより確保できる効果が得られる。
<3> Summary As described above, according to the sliding back anchor according to the present embodiment, by sharing the screw rod and the supporting column, it is possible to reduce these points and to secure more space around the back anchor. Is obtained.

A バックアンカー
10 アンカー桁
11 挿通孔
12 貫通孔
13 支持面
20 伝達桁
B 位置調整部
30 ネジ棒
31 接続板
40 支圧柱
50 規制具
X シールド機
Y シールドジャッキ
C 不動点
A Back anchor 10 Anchor girder 11 Insertion hole 12 Through hole 13 Support surface 20 Transmission girder B Position adjustment part 30 Screw rod 31 Connection plate 40 Bearing column 50 Regulator X Shield machine Y Shield jack C Fixed point

Claims (5)

シールド機の掘進に用いるスライド式バックアンカーであって、
シールド機のシールドジャッキと直接又は間接的に接続する複数のアンカー桁を少なくとも含んでなる、バックアンカーと、
前記アンカー桁と不動点との間に介設し、シールド機の掘進方向に対して前記アンカー桁を位置決め自在に構成する、位置調整部と、を少なくとも具備し、
前記アンカー桁が、
掘進方向に貫通して互いに連通する、挿通孔、を少なくとも有し、
前記位置調整部が、
掘進方向を長手方向として、前記挿通孔に挿通する、ネジ棒と、
掘進方向を長手方向とする、支圧柱と、
前記ネジ棒に螺合して、螺合位置より後方へのアンカー桁の後退を規制可能な、規制具と、を少なくとも具備し、
前記ネジ棒および支圧柱は、互いの前端側を直接又は間接的に接続し、
前記ネジ棒の後端側は、解放し、
前記支圧柱の後端側は、前記不動点と接続してあり、
前記アンカー桁が受ける掘進推力または土圧を、規制具、ネジ棒、支圧柱、不動点の順に伝達することを特徴とする、
スライド式バックアンカー。
It is a sliding back anchor used for digging a shield machine,
A back anchor comprising at least a plurality of anchor beams connected directly or indirectly to a shield jack of a shield machine;
A position adjusting unit interposed between the anchor beam and the fixed point, and configured to position the anchor beam freely with respect to a digging direction of a shield machine,
The anchor beam is
Having at least an insertion hole that penetrates in the digging direction and communicates with each other,
The position adjusting unit is
A threaded rod inserted through the insertion hole, with the direction of digging as the longitudinal direction,
A bearing column whose longitudinal direction is the digging direction;
A screw that is screwed into the screw rod, and is capable of restricting the backward movement of the anchor beam backward from the screwing position.
The screw rod and the supporting column connect the front end sides of each other directly or indirectly,
The rear end side of the screw rod is released,
The rear end side of the bearing column is connected to the fixed point,
The excavation thrust or earth pressure received by the anchor girder is transmitted in the order of a restriction tool, a screw rod, a supporting column, and a fixed point,
Sliding back anchor.
移動対象以外のアンカー桁のうち少なくとも何れか1つのアンカー桁において、シールドジャッキの伸縮状態を問わずに、移動対象のアンカー桁を支持する、支持面を有することを特徴とする、
請求項1に記載のスライド式バックアンカー。
In at least any one anchor girder other than the moving object, it has a support surface that supports the anchor girder of the moving object regardless of the expansion / contraction state of the shield jack,
The sliding back anchor according to claim 1.
前記アンカー桁同士で、支圧柱およびネジ棒を共有していることを特徴とする、
請求項1または2に記載のスライド式バックアンカー。
The anchor girders share a bearing column and a screw rod,
The sliding back anchor according to claim 1 or 2.
前記アンカー桁の前方に、シールドジャッキの後端と接続する伝達桁を設けてあることを特徴とする、
請求項1乃至3のうち何れか1項に記載のスライド式バックアンカー。
In front of the anchor beam, a transmission beam connected to the rear end of the shield jack is provided,
The slide type back anchor according to any one of claims 1 to 3.
請求項1乃至4のうち何れか1項に記載のスライド式バックアンカーを用いたシールド機の掘進方法であって、
(a)複数のアンカー桁の後退を、規制具で規制する工程、
(b)複数のアンカー桁のうち少なくとも何れか1つのアンカー桁に接続するシールドジャッキを伸長して、シールド機の前進を行う工程、
(c)移動対象のアンカー桁に接続するシールドジャッキを縮長して、移動対象以外のアンカー桁で土圧を受けながら、移動対象のアンカー桁を前方に引き寄せる工程、
(d)移動対象のアンカー桁に挿通してあるネジ棒上の規制具の前方への螺合を進めて、前記(a)の状態へと戻す工程、
を少なくとも含むことを特徴とする、
シールド機の掘進方法。
A method for digging a shield machine using the sliding back anchor according to any one of claims 1 to 4,
(A) a step of restricting the retreat of the plurality of anchor beams with a restricting tool;
(B) extending the shield jack connected to at least one of the plurality of anchor beams to advance the shield machine;
(C) a step of contracting the shield jack connected to the anchor girder to be moved and drawing the anchor girder to be moved forward while receiving earth pressure with the anchor girder other than the moving girder;
(D) a step of advancing screwing of the restricting tool on the screw rod inserted through the anchor girder to be moved back to the state of (a);
Including at least
How to dig shield machines.
JP2017205125A 2017-10-24 2017-10-24 How to dig a sliding back anchor and shield machine Active JP6429973B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017205125A JP6429973B1 (en) 2017-10-24 2017-10-24 How to dig a sliding back anchor and shield machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017205125A JP6429973B1 (en) 2017-10-24 2017-10-24 How to dig a sliding back anchor and shield machine

Publications (2)

Publication Number Publication Date
JP6429973B1 true JP6429973B1 (en) 2018-11-28
JP2019078048A JP2019078048A (en) 2019-05-23

Family

ID=64480531

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017205125A Active JP6429973B1 (en) 2017-10-24 2017-10-24 How to dig a sliding back anchor and shield machine

Country Status (1)

Country Link
JP (1) JP6429973B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6956449B2 (en) * 2019-04-16 2021-11-02 株式会社大一商会 Pachinko machine

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4311411A (en) * 1979-04-21 1982-01-19 Kabushiki Kaisha Iseki Kaihatsu Koki Pipe jacking apparatus
JP2510302Y2 (en) * 1990-03-19 1996-09-11 株式会社小松製作所 Propulsion device for small diameter tube propulsion machine
JP2536489Y2 (en) * 1990-03-19 1997-05-21 株式会社小松製作所 Propulsion device for small-diameter pipe thrusters
JPH1130091A (en) * 1997-07-10 1999-02-02 Sato Kogyo Co Ltd Transferable back anchor device and shield departure method by use thereof
JP2002213179A (en) * 2001-01-18 2002-07-31 Tokyoto Gesuido Service Kk Device and method for jacking body in starting opening
JP2012041748A (en) * 2010-08-19 2012-03-01 Hirosawa Machinery Co Ltd Mobile back anchor and shield starting method using the same

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4311411A (en) * 1979-04-21 1982-01-19 Kabushiki Kaisha Iseki Kaihatsu Koki Pipe jacking apparatus
JP2510302Y2 (en) * 1990-03-19 1996-09-11 株式会社小松製作所 Propulsion device for small diameter tube propulsion machine
JP2536489Y2 (en) * 1990-03-19 1997-05-21 株式会社小松製作所 Propulsion device for small-diameter pipe thrusters
JPH1130091A (en) * 1997-07-10 1999-02-02 Sato Kogyo Co Ltd Transferable back anchor device and shield departure method by use thereof
JP2002213179A (en) * 2001-01-18 2002-07-31 Tokyoto Gesuido Service Kk Device and method for jacking body in starting opening
JP2012041748A (en) * 2010-08-19 2012-03-01 Hirosawa Machinery Co Ltd Mobile back anchor and shield starting method using the same

Also Published As

Publication number Publication date
JP2019078048A (en) 2019-05-23

Similar Documents

Publication Publication Date Title
JP6429973B1 (en) How to dig a sliding back anchor and shield machine
US4746096A (en) Apparatus for driving an elongate member through the ground
US8790041B2 (en) Device for applying a push or pull action on tubes to be laid underground for overcoming water courses or obstacle of other type
US4095436A (en) Method of, and apparatus for, controlling the advance of a tunnel drive shield
JP2007303142A (en) Construction management method, construction management device and construction management program for shield tunnel
JP4125213B2 (en) Excavation method for pile work and its excavation equipment
JP4616018B2 (en) Buried pipe propulsion device
JP2014201915A (en) Earth-retaining wall structure and construction method of earth-retaining wall structure
KR102028547B1 (en) Construction method of messer shield
JP6876203B2 (en) Equipment and methods for continuously digging tunnels
EP2150673B1 (en) Method of quarrying dimensional stone, and line drilling apparatus
KR20180043057A (en) Pier dicplacement recovering method for incremental launching method and pier dicplacement recovering method therewith
JP4206054B2 (en) Shield drilling assembly simultaneous construction method
JP4896549B2 (en) Structure setting method
EP2434057B1 (en) Equipment for drilling secant holes
JP4327683B2 (en) How to bury underground structures
KR100900995B1 (en) Messer shield excavator apparatus for curved tunnel excavation and excavation method using the same
JP6827622B1 (en) How to dig a sliding back anchor and excavator
KR101664817B1 (en) A Safety Device Using Install Retaining Panel
JP2005139734A (en) Drilling machine available in drift, and movable drilling machine available in drift, using the same
JPS6228276B2 (en)
EP3696365B1 (en) Rock drilling arrangement, rock drilling rig and drilling method
JPH08284578A (en) Expansion guide shell for drilling device
KR102120652B1 (en) Pile constructiom method using movable reaction force structure and underground column wall therewith
KR102570388B1 (en) Wall Structure with Controlling Vertical Bending Moment using Preloading Jack Apparatus

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20171026

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20181023

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20181030

R150 Certificate of patent or registration of utility model

Ref document number: 6429973

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250