JP6170733B2 - Progress management support device, progress management support method, and program - Google Patents
Progress management support device, progress management support method, and program Download PDFInfo
- Publication number
- JP6170733B2 JP6170733B2 JP2013110218A JP2013110218A JP6170733B2 JP 6170733 B2 JP6170733 B2 JP 6170733B2 JP 2013110218 A JP2013110218 A JP 2013110218A JP 2013110218 A JP2013110218 A JP 2013110218A JP 6170733 B2 JP6170733 B2 JP 6170733B2
- Authority
- JP
- Japan
- Prior art keywords
- work
- charge
- unit
- amount
- pattern
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Description
本発明は、進捗管理支援装置、進捗管理支援方法およびプログラムに関する。 The present invention relates to a progress management support device, a progress management support method, and a program.
ソフトウェアなどの開発手法として、開発の初期段階でプロジェクト全体の計画を立案し、立案した計画に従って開発作業を進めていく手法がある。例えば、クリティカルパス法では、プロジェクト完了までの全作業を分析してクリティカルパス(最も時間を要する経路)を検出し、プロジェクト全体が完了するまでの期間の遅延を防止する。
しかしながら、実際のソフトウェア開発においては、仕様変更や、要因変更、社会的技術の変更などが生じ、初期段階において全ての要因を見通して適切な計画を立案することは困難である。
As a development method for software and the like, there is a method in which an overall project plan is made at an early stage of development, and development work is advanced in accordance with the planned plan. For example, in the critical path method, all work up to the completion of a project is analyzed to detect a critical path (the route that takes the most time), and a delay in the period until the entire project is completed is prevented.
However, in actual software development, specification changes, factor changes, social technology changes, and the like occur, and it is difficult to make an appropriate plan in view of all the factors in the initial stage.
これに対して、繰り返し開発または反復開発と呼ばれる手法が提案されている。繰り返し開発は、ソフトウェア等の開発対象を幾つかの部分に分割し、部分毎に設計や実装(コーディング)や試験などの各工程を行う手法である。また、プロジェクトの初期段階では初期計画を立案し、プロジェクトの進展に伴って具体的な計画を立案する。
ここで、繰り返し開発において、工程別の生産を制限なく行うと、ボトルネックの前工程にて作りすぎが発生し、仕掛品の在庫が過剰になってしまう。仕掛品の在庫が過剰な状態は変化に弱く、要求変更があった場合の不利益が大きい。例えば、ソフトウェアを分割した各部分の設計を行ったが、実装がボトルネックとなって進展していない状態で、ある部分が不要になった場合や仕様変更が生じた場合、該当部分の設計作業が無駄になってしまう。
On the other hand, a technique called iterative development or iterative development has been proposed. Iterative development is a technique in which a development target such as software is divided into several parts, and each process such as design, implementation (coding), and testing is performed for each part. In addition, an initial plan is drawn up at the initial stage of the project, and a specific plan is drawn up as the project progresses.
Here, in the repeated development, if production for each process is performed without limitation, over-production occurs in the process before the bottleneck, and the work-in-process inventory becomes excessive. Excess work-in-progress inventory is vulnerable to change, and there is a large penalty for changing requirements. For example, if you designed each part that divided the software, but the implementation has not progressed as a bottleneck, if a part becomes unnecessary or specification changes occur, the design work for that part Will be wasted.
そこで、WIP(Work In Progress)を制限することで、仕掛品の在庫量を調整することが考えられる。例えば、ソフトウェア等を分割した各部分について設計作業を実行可能な状態であっても、実行する設計作業の作業量を制限することで、設計済みだか実装前の状態にある仕掛品の在庫量を減らすことが考えられる。 Therefore, it is conceivable to adjust the inventory of work in progress by limiting WIP (Work In Progress). For example, even if it is in a state where design work can be executed for each part obtained by dividing software, etc., by limiting the work amount of the design work to be executed, it is possible to reduce the inventory amount of work in progress that has been designed or is in the pre-implementation state. It can be reduced.
また、特許文献1に記載の進捗管理支援装置を繰り返し開発に適用することで、生産活動においてボトルネックが発生したことを把握し得る。特許文献1に記載の進捗管理支援装置では、ラベル定義表記憶部が、複数の工程における作業が含まれる生産活動において工程毎に対応するラベルと、ラベルに対応する工程の前工程に対応するラベルとが対応付けられたラベル定義表を予め記憶する。また、進捗表記憶部が、複数のラベル毎に、ラベルに対応する工程における残作業量と、工程における作業が完了したか否かを示す完了情報とが対応付けられた進捗表を記憶する。また、入力部は、残作業量と完了情報との入力を受付け、進捗表記憶部に記憶させる。また、残作業量算出部は、複数のラベル毎に、ラベルに対応する工程の前工程として対応付けられたラベルをラベル定義表から読み出し、読み出したラベルに対応する完了情報を前記進捗表から読み出す。完了情報が、作業が完了したことを示す場合、残作業量算出部は、ラベルに対応する残作業量を読み出す。一方、完了情報が、作業が完了していないことを示す場合、残作業量算出部は、ラベルに対応する残作業量を読み出さない。そして、出力部は、複数のラベル毎に、残作業量算出部によって読み出された残作業量を出力する。
Further, by repeatedly applying the progress management support device described in
上記のように、特許文献1に記載の技術を用いれば、生産活動においてボトルネックが発生したことを把握し得る。ボトルネックが発生したことを把握することで、仕掛品の在庫量増大を検知して計画の見直し等を行う契機とすることができる。
さらに、仕掛品の在庫量が増大してから検知するのではなく、在庫量の増大を抑制することができれば、より好ましい。
As described above, if the technique described in
Furthermore, it is more preferable if the increase in the inventory quantity can be suppressed rather than detecting after the inventory quantity of the work in progress increases.
仕掛品の在庫量の増大の抑制に関して、上述したように、WIPを制限することで、仕掛品の在庫量を調整することが考えられる。しかしながら、提案されているWIPを制限する手法では、どのタイミングでどのようにWIPを制限するか具体的に示されていない。このため、工程を管理する担当者の経験等に基づいてWIPの制限を行っており、担当者の経験やスキルによってはプロジェクトを適切に進められないおそれがある。 Regarding the suppression of the increase in the work-in-process inventory, as described above, it is conceivable to adjust the inventory in-process by limiting the WIP. However, the proposed method of limiting WIP does not specifically indicate how and at what timing the WIP is limited. For this reason, WIP is limited based on the experience of the person in charge of managing the process, and there is a possibility that the project cannot be appropriately advanced depending on the experience and skill of the person in charge.
本発明は、このような事情を考慮してなされたものであり、その目的は、個人の経験やスキルに頼らずに仕掛品の在庫の増大を抑制することのできる進捗管理支援装置、進捗管理支援方法およびプログラムを提供することにある。 The present invention has been made in consideration of such circumstances, and its purpose is to provide a progress management support apparatus and progress management capable of suppressing an increase in the inventory of work in progress without depending on personal experience and skills. To provide a support method and program.
この発明は上述した課題を解決するためになされたもので、本発明の一態様による進捗管理支援装置は、作業全体が複数の部分に分割されており、所定の順序で実行される複数の工程が前記部分毎に含まれるプロジェクトを担当する複数の担当者に対して、所定の単位期間における担当者の工程への割り振り案を出力する進捗管理装置であって、前記単位期間における担当者の工程への割り振りの複数パターンのうち、前記単位期間における前記割り振りのパターン毎の実行可能な作業の量の予測の工程間の比が、前記単位期間の開始時に前記所定の順序を保つとした場合に実行可能な状態にある作業の量の見積の工程間の比に最も近似するパターンを、前記割り振り案として選択するパターン選択部を具備することを特徴とする。 The present invention has been made to solve the above-described problems, and a progress management support device according to an aspect of the present invention includes a plurality of steps in which the entire work is divided into a plurality of parts and executed in a predetermined order. Is a progress management device that outputs, to a plurality of persons in charge of a project included in each part, a plan for assigning a person in charge to a process in a predetermined unit period, the process of the person in charge in the unit period among a plurality patterns of allocation to, when the ratio between the forecast of the process viable amount of work for each pattern of the allocation definitive in the unit period, was kept the predetermined order at the start of the unit period the closest pattern to the ratio between the process of estimation of the amount of work that the executable state, characterized by comprising a pattern selector for selecting as said allocation proposal.
また、本発明の一態様による進捗管理支援装置は、上述の進捗管理支援装置であって、前記実行可能な状態にある作業の量の見積の工程間の比を、合計が担当者数に等しくなる値にて求める作業量比算出部を具備し、前記パターン選択部は、前記単位期間における担当者の工程への割り振りの複数パターンのうち、工程毎の担当者数と、前記作業量比算出部が当該工程について算出した値との差の大きさの、全工程についての合計が最も小さくなるパターンを、前記割り振り案として選択する、ことを特徴とする。 The progress management support apparatus according to an aspect of the present invention is the progress management support apparatus described above, wherein the ratio between the processes for estimating the amount of work in the executable state is equal to the number of persons in charge. The pattern selection unit calculates the number of persons in charge for each process and the ratio of the amount of work among a plurality of patterns assigned to the processes of persons in charge in the unit period. The pattern in which the sum of all the processes with the magnitude of the difference from the value calculated by the section for the process is the smallest is selected as the allocation plan.
また、本発明の一態様による進捗管理支援装置は、上述の進捗管理支援装置であって、前記実行可能な状態にある作業の量の工程毎の見積を、当該工程の作業の量の見積もりと、前記単位期間における当該工程の作業の量の実績との比に基づいて修正する見積修正部を具備し、前記パターン選択部は、修正後の前記実行可能な状態にある作業の量の見積の工程間の比に基づいて、前記割り振り案を選択する、ことを特徴とする。 A progress management support apparatus according to an aspect of the present invention is the above-described progress management support apparatus, wherein an estimate of the amount of work in the executable state for each process is an estimate of the amount of work in the process. , Including an estimate correction unit that corrects based on the ratio of the amount of work of the process in the unit period, and the pattern selection unit estimates the amount of work in the executable state after correction. The allocation plan is selected based on a ratio between processes.
また、本発明の一態様による進捗管理支援装置は、上述の進捗管理支援装置であって、前記見積修正部は、前記実行可能な状態にある作業の量の工程毎の見積を、実際に行われた作業量の、予測された作業量に対する割合を示すベロシティ実積率で除算することで、当該見積を修正する、ことを特徴とする。 A progress management support apparatus according to an aspect of the present invention is the progress management support apparatus described above, wherein the estimate correction unit actually performs an estimate for each process of the amount of work in an executable state. The estimate is corrected by dividing the divided work amount by the actual velocity product ratio indicating the ratio of the work amount to the predicted work amount.
また、本発明の一態様による進捗管理支援方法は、作業全体が複数の部分に分割されており、所定の順序で実行される複数の工程が前記部分毎に含まれるプロジェクトを担当する複数の担当者に対して、所定の単位期間における担当者の工程への割り振り案を出力する進捗管理装置の進捗管理方法であって、前記単位期間における担当者の工程への割り振りの複数パターンのうち、前記単位期間における前記割り振りのパターン毎の実行可能な作業の量の予測の工程間の比が、前記単位期間の開始時に前記所定の順序を保つとした場合に実行可能な状態にある作業の量の見積の工程間の比に最も近似するパターンを、前記割り振り案として選択するパターン選択ステップを具備することを特徴とする。 In the progress management support method according to one aspect of the present invention, the entire work is divided into a plurality of parts, and a plurality of persons in charge of a project including a plurality of steps executed in a predetermined order for each part. A progress management method for a progress management device that outputs an allocation plan to a person-in-charge process in a predetermined unit period, and among the plurality of patterns of allocation to a person-in-charge process in the unit period, the ratio between the step of predicting the amount of work that can be done for each pattern of the allocation definitive the unit period is in an executable state when a keep said predetermined order at the start of the unit period working A pattern selection step of selecting, as the allocation plan, a pattern that most closely approximates the ratio between the estimation processes.
また、本発明の一態様によるプログラムは、作業全体が複数の部分に分割されており、所定の順序で実行される複数の工程が前記部分毎に含まれるプロジェクトを担当する複数の担当者に対して、所定の単位期間における担当者の工程への割り振り案を出力する進捗管理装置としてのコンピュータに、前記単位期間における担当者の工程への割り振りの複数パターンのうち、前記単位期間における前記割り振りのパターン毎の実行可能な作業の量の予測の工程間の比が、前記単位期間の開始時に前記所定の順序を保つとした場合に実行可能な状態にある作業の量の見積の工程間の比に最も近似するパターンを、前記割り振り案として選択するパターン選択ステップを実行させるためのプログラムである。 In the program according to one aspect of the present invention, the entire work is divided into a plurality of parts, and a plurality of persons in charge of a project in which a plurality of steps executed in a predetermined order are included in each part. Te, the computer as a progress management device for outputting the allocation plan for personnel steps in a predetermined unit period, among the plurality of patterns of allocation to personnel step in the unit period, the allocation definitive in the unit period Between the steps of estimating the amount of work in an executable state when the ratio between the steps of predicting the amount of work that can be performed for each pattern is maintained in the predetermined order at the start of the unit period This is a program for executing a pattern selection step of selecting a pattern that is closest to the ratio as the allocation plan.
この発明によれば、個人の経験やスキルに頼らずに仕掛品の在庫の増大を抑制することができる。 According to this invention, it is possible to suppress an increase in the inventory of work-in-progress without depending on personal experience and skill.
以下、図面を参照して、本発明の実施の形態について説明する。
図1は、本発明の一実施形態における進捗管理支援装置の機能構成を示す概略ブロック図である。同図において、進捗管理支援装置100は、表示部110と、操作入力部120と、記憶部130と、制御部160とを具備する。制御部160は、パターン選択部161と、予測ベロシティ算出部162と、実績ベロシティ算出部163と、実行可能作業量見積部164と、作業量比算出部165と、見積修正部166と、パターン評価値算出部167とを具備する。
Embodiments of the present invention will be described below with reference to the drawings.
FIG. 1 is a schematic block diagram showing a functional configuration of a progress management support apparatus according to an embodiment of the present invention. In the figure, the progress
進捗管理支援装置100は、作業全体が複数の部分に分割されており、所定の順序で実行される複数の工程が部分毎に含まれるプロジェクトを担当する複数の担当者に対して、所定期間(後述する単位期間)における担当者の工程への割り振り案を出力する。例えば、進捗管理支援装置100は、対象プロジェクト(進捗管理支援装置100が扱う対象となっているプロジェクト)の進捗に応じて、当該プロジェクトの担当者が実行するべき工程を単位期間毎に提案する。進捗管理支援装置100は、例えばコンピュータにて構成される。
ここで、進捗管理支援装置100を適用するプロジェクトの前提条件として以下を想定する。
(前提1)実行すべき作業の全体が幾つかの部分に分割されており、各部分は複数の工程を含んでいる。工程には前後関係のあるものがあり、1つの部分について前工程を完了するまで後工程を実行することができない。
The progress
Here, the following is assumed as a precondition of a project to which the progress
(Premise 1) The entire work to be executed is divided into several parts, and each part includes a plurality of steps. Some processes have a context, and a subsequent process cannot be executed until the previous process is completed for one part.
例えば、ソフトウェア開発プロジェクトにおいて行うべき作業の全体が、開発対象となっているソフトウェアの機能毎に分割されている。担当者は、機能毎に設計工程と、実装工程と、試験工程とを行う。ある機能の設計工程を完了するまで、当該機能の実装工程を実行することはできない。また、ある機能の実装工程を完了するまで、当該機能の試験工程を実行することはできない。 For example, the entire work to be performed in the software development project is divided for each software function to be developed. The person in charge performs a design process, a mounting process, and a test process for each function. Until the design process of a certain function is completed, the mounting process of the function cannot be executed. Further, the test process for the function cannot be executed until the mounting process for a certain function is completed.
以下では、ソフトウェアの開発プロジェクトにおいて行うべき作業の全体が、ソフトウェアの機能毎に分割されている場合を例に説明する。但し、本発明の適用範囲はソフトウェア開発に限らない。また、作業の全体の分割方法は機能毎の分割に限らない。
なお、以下では、「機能」における「工程」を「作業」と称する。例えば、機能1の工程Aと、機能1の工程Bと、機能2の工程Aとは、それぞれ1つの作業として扱われる。
In the following, an example will be described in which the entire work to be performed in a software development project is divided for each software function. However, the scope of application of the present invention is not limited to software development. Further, the method of dividing the entire work is not limited to the division for each function.
Hereinafter, “process” in “function” is referred to as “operation”. For example, the
(前提2)1つの作業は1人の担当者が実行する。特に、複数の担当者が共同して1つの作業を行うことはない。
(前提3)各担当者のスキルにばらつきがあり、担当者毎に実行可能な工程が決まっている。
例えば、ある担当者は、ソフトウェアの設計、実装、試験共に行える。一方、他のある担当者は、設計や実装を行うことはできるが試験を行うことはできない。
(Premise 2) One task is executed by one person in charge. In particular, a plurality of persons in charge do not work together.
(Premise 3) The skill of each person in charge varies, and the process that can be executed is determined for each person in charge.
For example, a person in charge can design, implement, and test software. On the other hand, some other person in charge can design and implement, but not test.
(前提4)担当者が作業を行う時間について、1単位となる期間が設定されている。1人の担当者が実行する工程は、1つの期間について1つの工程に制限される。
例えば、1日の作業時間が7時間に設定されており、この7時間を1単位となる期間とする。各担当者は、1日のうちに1つの工程のみを実行する。従って、機能1の設計作業を完了した担当者は、当日の作業にて引き続き機能2の設計作業を行うことはあるが、同じ日に機能1の構築作業を行うことはない。
なお、以下では、1単位となる期間において担当者が実行する工程を「WIP」(Work In Progress)と称する。また、以下では、1単位となる期間を、「単位期間」または単に「期間」と称する。
(Assumption 4) A period of one unit is set for the time for the person in charge to work. The process performed by one person in charge is limited to one process for one period.
For example, the working time per day is set to 7 hours, and this 7 hours is set as a unit period. Each person in charge executes only one process in one day. Therefore, the person in charge who has completed the
Hereinafter, the process performed by the person in charge in a period of one unit is referred to as “WIP” (Work In Progress). In the following, a period of one unit is referred to as “unit period” or simply “period”.
(前提5)機能毎(作業全体を分割した部分ごと)に優先度が設定されている。各担当者は、WIPに応じた作業のうち、実行可能(着手可能)な状態にある作業を、優先度の高い順に実行する。また、各担当者は、マルチタスクは行わない。従って、1人の担当者が一時に行う作業の数は1つに制限される。担当者は、少なくとも単位期間内においては、自らが実行中の作業を完了するまで他の作業を行わない。
例えば、WIPにより実装工程を実行する担当者は、設計作業が完了して着手可能となっている実装作業(他の担当者が実行中の作業を除く)のうち、機能の優先度が最も高い実装作業を実行する。
(Premise 5) A priority is set for each function (each part obtained by dividing the entire work). Each person in charge executes work in an executable (startable) state among works according to WIP in descending order of priority. Each person in charge does not perform multitasking. Accordingly, the number of operations performed by one person in charge at a time is limited to one. The person in charge does not perform other work at least within the unit period until the work in progress is completed.
For example, the person in charge of executing the mounting process by WIP has the highest function priority among the mounting work (except work currently being executed by other persons in charge) that can be started after completing the design work. Perform implementation work.
(前提6)単位期間満了前に作業を完了した担当者は、実行可能な作業(WIPに従って実行可能で、前工程の作業が完了しており、かつ、他の担当者が実行していない作業)があれば、優先度の高い順に作業を実行する。これを単位期間満了まで繰り返す。
(前提7)担当者は、自らの実行する工程に実行可能な作業がない場合、対象プロジェクトにおける作業を行わない。この場合、担当者は、例えば対象プロジェクト以外の業務を行う。対象プロジェクトとの関係では、当該担当者のリソース時間は、実行可能な作業ができるまで待ち時間として費やされる。
担当者は、単位期間満了前に作業を完了し、実行可能な作業がない場合も、対象プロジェクトにおける作業を行わない。
(Assumption 6) The person in charge who completed the work before the expiration of the unit period is an executable work (work that can be executed according to WIP, the work of the previous process has been completed, and the work is not performed by other persons in charge. ), Work is performed in order of priority. This is repeated until the unit period expires.
(Premise 7) The person in charge does not perform the work in the target project when there is no work that can be performed in the process to be executed. In this case, the person in charge performs work other than the target project, for example. In relation to the target project, the resource time of the person in charge is spent as a waiting time until work that can be performed is completed.
The person in charge completes the work before the expiration of the unit period, and does not work on the target project even if there is no work that can be performed.
表示部110は、担当者が実行するべき工程の提案を表示する。例えば、表示部110が、液晶パネルまたは有機EL(Organic Electro Luminescence)パネルなどの表示画面を有して、担当者が実行するべき工程の提案など各種画像を表示するようにしてもよいが、これに限らない。例えば、表示部110がスピーカを有して、担当者が実行するべき工程の提案を音声にて通知するようにしてもよい。
なお、以下では、表示部110が、工程毎に当該工程を実行すべき担当者の人数を表示する場合を例に説明するが、これに限らない。例えば、表示部110が、担当者毎に、当該担当者の実行すべき作業を表示するようにしてもよい。
The
Hereinafter, a case where the
操作入力部120は、例えばキーボードなどの入力デバイスを有し、進捗管理支援装置100のユーザが行う入力操作を受け付ける。特に、操作入力部120は、担当者毎に実行可能な工程の情報や、機能毎の優先度の情報や、作業毎の作業量の見積情報などの初期情報の入力を受け付ける。また、操作入力部120は、作業の進捗情報の入力を受け付ける。
記憶部130は、操作入力部120が入力を受け付けた初期情報や作業の進捗情報など、各種情報を記憶する。記憶部130は、進捗管理支援装置100の具備する記憶デバイスにて構成される。
The
The
制御部160は、進捗管理支援装置100の各部を制御して各種処理を実行する。制御部160は、例えば、進捗管理支援装置100の具備するCPU(Central Processing Unit、中央処理装置)が、記憶部130からプログラムを読み出して実行することで構成される。
パターン選択部161は、単位期間における担当者の工程への割り振りの複数パターンのうち、単位期間に実行可能な作業の量の予測の工程間の比が、実行可能な状態にある作業の量の見積の工程間の比に最も近似するパターンを、割り振り案として選択する。
The control unit 160 controls each unit of the progress
The
ここで、上記の前提3のように、各担当者のスキルにばらつきがあり、担当者毎に実行可能な工程が決まっている。従って、工程毎に実行可能な担当者数が異なっており、このことが、ボトルネックとなる工程が発生する要因となる。例えば、試験工程を実行可能な担当者が1人しかいない場合、試験工程がボトルネックとなり、仕掛品(ここでは、作業に着手されているが未完成の機能)の在庫量が増大するおそれがある。このため、実行可能な作業の数では実装作業の数の方が試験作業の数よりも多くても、仕掛品の在庫量増大を抑制する観点から、当該担当者が試験作業を優先的に行うべき場合が考えられる。
Here, as in the
そこで、パターン選択部161は、各担当者が実行可能な工程に基づくWIPの各パターンのうち、実行可能な状態にある作業量に応じたパターンを、担当者の工程への割り振り案として選択する。これにより、進捗管理支援装置100は、試験を実行可能な担当者に試験工程を実行するよう提案するなど、担当者を工程に適切に割り振って仕掛品の在庫量増大を抑制し得る。
Therefore, the
また、パターン選択部161は、単位期間における担当者の工程への割り振りの複数パターンのうち、工程毎の担当者数と、作業量比算出部165が当該工程について算出した値との差の大きさの、全工程についての合計が最も小さくなるパターンを、割り振り案として選択する。
具体的には、作業量比算出部165は、実行可能な作業量の見積の工程毎の合計について、全体の値が担当者数に等しくなるように工程間の比を算出する。作業量比算出部165が算出した比に応じて担当者が作業を実行することで、特定の工程に偏ることなく作業を行うことができ、仕掛品の在庫量増大を抑制し得る。
In addition, the
Specifically, the work amount
但し、上記の前提4から、工程毎の作業者を小数単位で割り当てることはできない。また、作業量比算出部165が算出した比は、各担当者の実行可能な工程を反映したものではない。例えば、試験を実行可能な作業者が1人しかいないにもかかわらず、作業量比算出部165が算出した比において試験工程の値が2以上となる場合が考えられる。
However, from the
そこで、パターン選択部161は、工程毎に作業者の人数を整数にて割り当てたWIPのパターンのうち、作業量比算出部165が算出した比に最も類似していると評価されるパターンを選択する。
これにより、進捗管理支援装置100(パターン評価値算出部167およびパターン選択部161)は、作業量比算出部165が算出した値とWIPの各パターンにおける担当者数との差の大きさを工程毎に算出し、全工程についての合計が最も小さくなるパターンを選択するという簡単な処理にて、割り振り案を選択することができる。
Therefore, the
As a result, the progress management support apparatus 100 (the pattern evaluation
また、見積修正部166が作業実績に応じて作業量の見積の修正(補正)を行い、パターン選択部161は、実行可能な状態にある作業の量の、修正後の見積の工程間の比に基づいて、担当者の工程への割り振り案を選択する。
このように、パターン選択部161が、修正された作業量の見積に基づいて担当者の工程への割り振り案を選択することで、より適切なパターンを割り振り案として選択することができ、仕掛品の在庫量増大を、より抑制し得る。
In addition, the
Thus, the
予測ベロシティ算出部162は、パターン選択部161が選択したWIPのパターンに基づいて、予測ベロシティを工程毎に算出する。ここでいう予測ベロシティとは、単位期間に実行可能な作業量の見積を示す値である。
実績ベロシティ算出部163は、単位期間における作業実績に基づいて、当該単位期間における実績ベロシティを工程毎に算出する。ここでいう実績ベロシティとは、単位期間に実行された作業量を、予測ベロシティとの対比において示す値である。
The predicted
The actual
実行可能作業量見積部164は、実行可能な状態にある作業の量の見積を工程毎に算出する。より具体的には、実行可能作業量見積部164は、未完了の作業のうち(前作業が完了して)実行可能となっている作業について、作業量の見積を工程毎に合計する。
作業量比算出部165は、実行可能作業量見積部164が算出し、見積修正部166が作業実績に応じて修正した、実行可能な状態にある作業の量の見積の工程間の比を、合計が担当者数に等しくなる値にて求める。上記のように、パターン選択部161は、作業量比算出部165が算出した比に基づいて、単位期間における担当者の工程への割り振り案を選択する。
The executable work
The work amount
見積修正部166は、実行可能な状態にある作業の量の工程毎の見積を、当該工程の作業の量の見積もりと、単位期間における当該工程の作業の量の実績との比に基づいて修正する。より具体的には、見積修正部166は、実績ベロシティ算出部163が算出した実績ベロシティを、予測ベロシティ算出部162が算出した予測ベロシティで除算して、ベロシティ実績率を算出する。ここでいうベロシティ実績率は、実際に行われた作業量の、予測された作業量に対する割合である。そして、見積修正部166は、作業量の見積をベロシティ実績率で除算することで、作業量の見積を修正する。上記のように、パターン選択部161は、見積修正部166が修正した作業量の見積に基づいて、単位期間における担当者の工程への割り振り案を選択する。
The
パターン評価値算出部167は、パターン選択部161が担当者の工程への割り振り案を選択するための、WIPのパターン毎の評価値を算出する。具体的には、パターン評価値算出部167は、作業量比算出部165が算出した値とWIPの各パターンにおける担当者数との差の大きさを工程毎に算出し、全工程についての合計をパターン毎に算出して、パターン毎の評価値とする。
The pattern evaluation
次に、図2〜図8を参照して、進捗管理支援装置100が行う処理を例に基づいて説明する。
図2は、担当者が実行可能な工程の例を示す説明図である。同図の例において、作業を行う担当者は、担当者a、b、cの3人である。担当者aは、工程BやCを実行することはできないが、工程Aを実行することはできる。担当者bは、工程Cを実行することはできないが、工程AやBを実行することはできる。担当者cは、工程A、B、Cのいずれも実行することができる。
Next, processing performed by the progress
FIG. 2 is an explanatory diagram illustrating an example of a process that can be executed by a person in charge. In the example of the figure, there are three persons in charge, who are the persons in charge, a, b and c. The person in charge a cannot execute the processes B and C, but can execute the process A. The person in charge b cannot execute the process C, but can execute the processes A and B. The person in charge c can execute any of the processes A, B, and C.
図3は、図2に示す担当者が実行可能な工程に基づいて得られるWIPのパターンの例を示す説明図である。図3のパターン1では、担当者a、b、c共に工程Aを実行する。パターン2では、担当者aと、担当者b、cのいずれか一方とが工程Aを実行し、担当者b、cのうち他方は、工程Bを実行する。パターン3では、担当者aとbとが工程Aを実行し、担当者cが工程Cを実行する。パターン4では、担当者aが工程Aを実行し、担当者bとcとが工程Bを実行する。パターン5では、担当者aが工程Aを実行し、担当者bが工程Bを実行し、担当者cが工程Cを実行する。
FIG. 3 is an explanatory diagram showing an example of a WIP pattern obtained based on a process executable by the person in charge shown in FIG. In the
例えば、操作入力部120が、図2の例のように担当者が実行可能な工程の情報を含む担当者情報の操作入力を受けて、記憶部130が当該担当者情報を記憶する。そして、制御部160(例えばパターン選択部161)は、記憶部130から担当者情報を読み出して、図3の例のように可能なWIPのパターンを求める。
以下では、可能なWIPのパターンを示す情報を「WIPパターンリスト」と称する。制御部160は、得られたWIPパターンリストを記憶部130に記憶させる。
なお、操作入力部120がWIPパターンリストの入力操作を受け、記憶部130が当該WIPパターンリストを記憶するようにしてもよい。
For example, the
Hereinafter, information indicating possible WIP patterns is referred to as a “WIP pattern list”. The control unit 160 causes the
The
図4は、初回の単位期間についてパターン選択部161が選択するWIPのパターンの例を示す説明図である。同図の例において、パターン選択部161は、図3のパターン2を選択している。初回の単位期間についてパターン選択部161が選択するパターンは、前工程を有していない最上流の工程をWIPに含んでいればよい。図2〜図8に示す例では、工程Aが最上流の工程となっており、パターン選択部161は、工程Aに担当者を割り当てるパターン2を選択している。
FIG. 4 is an explanatory diagram illustrating an example of a WIP pattern selected by the
パターン選択部161は、最上流の工程をWIPに含むパターン(図3の例では全てのパターン)の中から、初回の単位期間についてのWIPのパターンをランダムに選択する。あるいは、パターン選択部161が、進捗管理支援装置100のユーザが予め指定したパターンを選択するなど、所定のパターンを選択するようにしてもよい。
The
パターン選択部161が選択したWIPのパターン(ここではパターン2)に基づいて、予測ベロシティ算出部162が予測ベロシティを算出する。具体的には、予測ベロシティ算出部162は、式(1)に基づいて予測ベロシティを算出する。
予測ベロシティ = WIP × 単位期間の長さ ・・・(1)
Based on the WIP pattern (
Predicted velocity = WIP x length of unit period (1)
すなわち、予測ベロシティ算出部162は、工程毎に、WIPのパターンにて当該工程に割り当てられている担当者の人数と、単位期間の長さ(図2〜図8に示す例では7時間とする)とを乗算することで、工程毎に実行可能な延べ時間を予測ベロシティとして算出する。
図4の例では、工程Aの担当者数が2人であることから、工程Aの予測ベロシティは2×7=14となっている。また、工程Bの担当者数が1人であることから、工程Aの予測ベロシティは1×7=7となっている。一方、工程Cには担当者が割り当てられていないため、工程Cの予測ベロシティは0×7=0となっている。
That is, for each process, the predicted
In the example of FIG. 4, since the number of persons in charge of process A is 2, the predicted velocity of process A is 2 × 7 = 14. Further, since the number of persons in charge of process B is one, the predicted velocity of process A is 1 × 7 = 7. On the other hand, since no person in charge is assigned to the process C, the predicted velocity of the process C is 0 × 7 = 0.
図5は、初回の単位期間における作業の実行状況の例を示す説明図である。図2〜図8に示す例では、担当者が実行すべき作業の全体が、機能1〜機能6の機能毎に分割されている。また、機能1〜6には、それぞれ優先度1〜6が設定されている。ここでは、優先度の数が小さいほど優先度が高いことを示す。
各機能(作業の全体を機能毎に分割した各部分)は、いずれも工程A、B、Cの3つの工程を含んでいる。機能と工程との組み合わせにて特定される各作業の初期見積は、期間1見積の各欄に示す値となっている。例えば、機能1の工程A、B、Cにおける作業の量は、それぞれ、7時間分、3時間分、10時間分と見積もられている。
FIG. 5 is an explanatory diagram illustrating an example of a work execution status in the first unit period. In the example shown in FIGS. 2 to 8, the entire work to be performed by the person in charge is divided into
Each function (each part obtained by dividing the entire work for each function) includes three processes A, B, and C. The initial estimate of each work specified by the combination of the function and the process is a value shown in each column of the
また、初回の単位期間(期間1)における作業の実績が、期間1実績の各欄に示されている。図5の例では、図4に示すWIPのパターンに従って、工程Aと工程Bとが実行されている。
図5において、作業実績は、作業量の見積との対比にて示されている。例えば、機能2の工程Aにおける作業では、3時間分の作業量の見積のうち3時間分の作業が実行されている。従って、機能2の工程Aは完了している。
Moreover, the results of work in the first unit period (period 1) are shown in each column of
In FIG. 5, the work performance is shown in comparison with the work amount estimation. For example, in the work in the process A of the
機能2の工程Aが完了することで、工程Aの後工程である工程Bが実行可能となる。そこで、工程Bを担当する担当者は、機能2の工程Bを実行している。機能2の工程Bにおける作業では、1時間分の作業量の見積のうち1時間分の作業が実行されている。従って、機能2の工程Bは完了している。
一方、機能3の工程Bでは、10時間分の作業量の見積のうち3時間分の作業が実行されている。従って、機能3の工程Bでは、10時間分の作業量の見積のうち7時間分の作業が残っている。
By completing step A of
On the other hand, in the process B of the
期間1満了時の残作業の見積が、期間2見積の各欄に示されている。例えば、機能2の工程A、工程Bにおける作業は、いずれも上述したように完了しており、残作業が無いことを示す「−」となっている。一方、機能3の工程Bでは、残りの作業量の見積を示す「7」(初期見積における7時間分の作業量)となっている。
また、期間2見積の各欄において、実行可能な状態にある作業がハッチングにて示されている。期間1満了時(従って、次の単位期間である期間2の開始時)において、機能1の工程A、機能2の工程C、機能3の工程B、機能4の工程A、機能5の工程A、機能6の工程Aにおける各作業が、実行可能な状態となっている。
Estimated remaining work at the end of
In each column of the
進捗管理支援装置100のユーザは、単位期間満了毎に、当該単位期間における作業量の実績(図5の例では、期間1実績の各欄の値)を入力する。そして、制御部160(例えば、実行可能作業量見積部164)が、単位期間開始時における作業量の見積から作業量の実績を減算することで、残作業量の見積(図5の例では、期間2見積の各欄の値)を算出する。
あるいは、進捗管理支援装置100のユーザが、単位期間満了毎に、当該単位期間における作業量の実績に代えて、あるいは加えて、当該単位期間満了時における残作業量の見積を入力するようにしてもよい。
The user of the progress
Alternatively, each time the unit period expires, the user of the progress
図6は、作業量比算出部165が算出する作業量比の例を示す説明図である。同図における初回WIPと予測ベロシティとは、いずれも、図4と同様である。
また、実績ベロシティの各欄には、実績ベロシティ算出部163が工程毎に算出する実績ベロシティの値が示されている。実績ベロシティ算出部163は、式(2)に基づいて実績ベロシティを算出する。
実績ベロシティ = Σ実績作業量 ・・・(2)
FIG. 6 is an explanatory diagram illustrating an example of the work amount ratio calculated by the work amount
In each column of the actual velocity, the actual velocity value calculated by the actual
Actual velocity = Σ Actual work amount (2)
すなわち、実績ベロシティ算出部163は、工程毎に、作業量の見積との対比にて示される作業量の実績値を合計することで、工程毎の実績ベロシティを算出する。
図6の例では、実績ベロシティ算出部163は、図5の各機能の工程Aにおける作業実績(期間1実績の各欄に示す値)を合計して、工程Aの実績ベロシティを7+3+1+3=14と算出している。また、実績ベロシティ算出部163は、図5の各機能の工程Bにおける作業実績を合計して、工程Bの実績ベロシティを1+3=4と算出している。また、実績ベロシティ算出部163は、図5の各機能の工程Cにおける作業実績を合計して、工程Cの実績ベロシティを0と算出している。
In other words, the actual
In the example of FIG. 6, the actual
また、ベロシティ実績率の各欄には、見積修正部166が工程毎に算出するベロシティ実績率が示されている。見積修正部166は、式(3)に基づいてベロシティ実績率を算出する。
ベロシティ実績率 = 実績ベロシティ/予測ベロシティ ・・・(3)
Each velocity actual rate column indicates a velocity actual rate calculated by the
Velocity performance rate = Actual velocity / Predicted velocity (3)
すなわち、上述したように、見積修正部166は、工程毎に、実績ベロシティ算出部163が算出した実績ベロシティを、予測ベロシティ算出部162が算出した予測ベロシティで除算して、工程毎のベロシティ実績率を算出する。
但し、予測ベロシティが0の場合、見積修正部166は、ベロシティ実績率を0とする。図6の例では、工程Cの予測ベロシティが0になっており、見積修正部166は、工程Cのベロシティ実績率を0としている。
That is, as described above, the
However, when the predicted velocity is 0, the
図6の実行可能作業量の各欄には、実行可能作業量見積部164が工程毎に算出する実行可能作業量が示されている。実行可能作業量見積部164は、式(4)に基づいて実行可能作業量を算出する。
実行可能作業量 = Σ実行可能な作業の見積量 ・・・(4)
ここでいう見積量は、作業量の見積である。すなわち、実行可能作業量見積部164は、工程毎に、単位期間満了時の残作業量の見積において、実行可能な作業の見積量を合計して、工程毎の実行可能作業量を算出する。
In each column of the executable work amount in FIG. 6, the executable work amount calculated by the executable work
Executable work amount = Σ Estimated amount of work that can be executed (4)
The estimated amount here is an estimate of the amount of work. That is, the feasible work
図6の例では、実行可能作業量見積部164は、図5において期間2見積の各欄に示される残作業量の見積のうち、ハッチングにて示される実行可能な作業の見積量を合計して、工程Aの実行可能作業量を1+2+3=6と算出している。また、実行可能作業量見積部164は、工程Bの実行可能作業量を3+7=10と算出している。また、実行可能作業量見積部164は、工程Cの実行可能作業量を3(機能2の工程Cにおける作業量)と算出している。
In the example of FIG. 6, the feasible work
図6の修正後作業量の各欄には、見積修正部166が工程毎に算出する修正後作業量が示されている。ここでいう修正後作業量は、残作業量の見積を作業実績に応じて修正した値である。見積修正部166は、式(5)に基づいて修正後作業量を算出する。
修正後作業量 = 実行可能作業量 / ベロシティ実績率 ・・・(5)
すなわち、見積修正部166は、工程毎に、実行可能作業量をベロシティ実績率で除算することで、工程毎の修正後作業量を算出する。
但し、ベロシティ実績率が0の場合、見積修正部166は、残作業量の見積を修正しない。図6の例では、工程Cのベロシティ実績率が0になっており、見積修正部166は、工程Cの実行可能作業量をそのまま修正後作業量としている。
In each column of the post-correction work amount in FIG. 6, the post-correction work amount calculated by the
Work volume after correction = Executable work volume / Velocity performance ratio (5)
That is, the
However, when the velocity performance rate is 0, the
図6の作業量比の各欄には、作業量比算出部165が算出する工程間の作業量比が示されている。作業量比算出部165は、式(6)に基づいて作業量比における各工程の値を算出する。
作業量比 = (修正後作業量 / Σ修正後作業量)×担当者数 ・・・(6)
In each column of the work amount ratio in FIG. 6, the work amount ratio between processes calculated by the work amount
Work volume ratio = (work volume after correction / work volume after Σ correction) x number of persons in charge (6)
すなわち、作業量比算出部165は、修正後作業量の工程間の比を、合計が担当者数に等しくなる値にて求める。図6の例では、工程A〜Cの作業量比を合計した値は、小数の丸め込みによる誤差はあるものの、作業者数3に等しいと見做せる値となっている。
In other words, the work amount
図7は、パターン選択部161が選択するWIPの例を示す説明図である。同図において、図3に示すWIPのパターン1〜パターン5が示されている。加えて、図7では、パターン評価値算出部167が算出する各パターンの評価値が示されている。パターン評価値算出部167は、式(7)に基づいてWIPのパターンの評価値をパターン毎に算出する。
評価値 = Σ|WIP − 作業量比| ・・・(7)
FIG. 7 is an explanatory diagram illustrating an example of WIP selected by the
Evaluation value = Σ | WIP−Work amount ratio | (7)
すなわち、パターン評価値算出部167は、工程毎に、WIP(WIPのパターンにて当該工程に割り当てられている担当者数)と作業量比との差の絶対値を求め、得られた差の絶対値を工程について合計することで、WIPのパターンの評価値を算出する。
図7の例では、同図に示す各パターンにおける工程毎の作業者数と、図6に示す作業量比とに基づいて得られる評価値が示されている。
パターン選択部161は、パターン評価値算出部167が算出した評価値に基づいて、評価値の最も小さいパターンを、次の単位期間における担当者の工程への割り振り案として選択する。図7の例では、パターン選択部161は、評価値の最も小さいパターン4を選択している。
That is, the pattern evaluation
In the example of FIG. 7, evaluation values obtained based on the number of workers for each process in each pattern shown in FIG. 7 and the work amount ratio shown in FIG. 6 are shown.
Based on the evaluation value calculated by the pattern evaluation
図8は、パターン選択部161が選択したWIPのパターンに応じた作業の実行状況の例を示す説明図である。同図の期間1見積の各欄の値、期間1実績の各欄の値、および、期間2見積の各欄の値は、いずれも、図5に示すものと同じである。
一方、期間2実績の各欄には、2回目の単位期間(期間2)における作業の実績が示されている。図8の例では、パターン選択部161が選択したパターン4(図7)に従って、工程Aと工程Bとが実行されている。
FIG. 8 is an explanatory diagram illustrating an example of an execution status of work according to the WIP pattern selected by the
On the other hand, each column of
ここで、期間2では、パターン4に従って、工程Aに1人の担当者が割り当てられ、工程Bに2人の担当者が割り当てられている。これにより期間2では、特に工程Bの作業が進捗しており、工程Bの実績ベロシティが3+7+4=14となっている。
工程Bの作業が進捗することで、期間2の開始時に比較的多かった工程Bの実行可能作業量が、期間2の終了時に減少している。具体的には、期間2の開始時において工程A、B、Cの実行可能作業量がそれぞれ6、10、3であったのに対し、期間2の終了時においては、それぞれ0、3、19となっている。
このように、進捗管理支援装置100が提案するWIPのパターンを採用することで、実行可能な作業の特定の工程への集中を解消し得る。この点において、進捗管理支援装置100が提案するWIPのパターンを採用することで、ボトルネックの発生を回避する、あるいは、ボトルネックが大きくなる前に解消することができる。
Here, in the
As the work of process B progresses, the executable work amount of process B, which was relatively large at the start of
In this way, by adopting the WIP pattern proposed by the progress
次に、図9を参照して、進捗管理支援装置100における情報の流れについて説明する。
図9は、進捗管理支援装置100における情報の流れの例を示す説明図である。記憶部130は、同図に示す各情報を記憶する。図9において、操作入力部120は、初期情報として、担当者情報とプロジェクト基本情報と初期の作業見積との操作入力を受ける。
Next, the flow of information in the progress
FIG. 9 is an explanatory diagram illustrating an example of information flow in the progress
担当者情報は、各担当者に関する情報であり、担当者毎の識別情報(担当者ID)と、当該担当者が実行可能な工程を示す情報(担当者スキル)とを含む。
プロジェクト基本情報は、対象プロジェクトの基本事項に関する情報であり、単位期間の長さを示す情報(図9の例では、1日の稼働時間、すなわち、担当者が1日に実行可能な作業時間)を含む。
The person-in-charge information is information relating to each person in charge, and includes identification information (person-in-charge ID) for each person in charge and information (step-in-person skill) indicating processes that can be executed by the person in charge.
The basic project information is information related to the basic items of the target project, and is information indicating the length of the unit period (in the example of FIG. 9, the operation time of one day, that is, the work time that the person in charge can execute on one day). including.
作業見積は、残作業量の見積を示す情報であり、単位期間を特定する情報(期間ID)と、機能毎の識別情報(機能ID)と、工程毎の識別情報(工程ID)と、特定された単位期間の開始時における各作業の見積量(見積時間)と、各作業の状態を示す情報(ステータス)とを含む。なお、見積時間、ステータスとして、それぞれ、機能IDおよび工程IDに対応付けて当該機能の当該工程における作業の見積時間、ステータスが示される。また、ステータスの示す作業の状態には、実行不可(前工程の作業の完了待ち)、実行可能、実行中、および、実行完了がある。 The work estimate is information indicating an estimate of the remaining work amount, and information for specifying a unit period (period ID), identification information for each function (function ID), identification information for each process (process ID), and specification The estimated amount (estimated time) of each work at the start of the given unit period and information (status) indicating the state of each work. As the estimated time and status, the estimated time and status of the work in the process of the function are shown in association with the function ID and the process ID, respectively. The status of the work indicated by the status includes execution impossible (waiting for completion of work in the previous process), execution possible, execution in progress, and execution completion.
なお、機能の優先度は、例えば機能IDにて示される。例えば、機能IDに識別番号含まれ、小さい識別番号ほど優先度が高いことを示す。
また、工程の前後関係は、例えば工程IDにて示される。例えば、工程IDに識別番号が含まれ、小さい識別番号ほど上流の工程を示す。
なお、初期の作業見積は、初回の単位期間の開始時における作業量の見積を示す。従って、初期の作業見積は、初回の単位期間を示す期間IDを含む。
The function priority is indicated by, for example, a function ID. For example, an identification number is included in the function ID, and the smaller the identification number, the higher the priority.
Further, the process context is indicated by, for example, a process ID. For example, the process ID includes an identification number, and a smaller identification number indicates an upstream process.
The initial work estimate indicates an estimate of the work amount at the start of the first unit period. Therefore, the initial work estimate includes a period ID indicating the initial unit period.
制御部160は、担当者情報に基づいて、図3を参照して説明したWIPパターンリストを生成する。WIPパターンリストは、WIPの各パターンの識別情報(WIPパターンID)と、当該パターンにおいて各工程に割り当てる作業者数を示す情報と(図9の例では、工程A、工程B、工程Cの各々におけるWIPの値)とを含む。 The control unit 160 generates the WIP pattern list described with reference to FIG. 3 based on the person-in-charge information. The WIP pattern list includes identification information (WIP pattern ID) of each pattern of WIP, information indicating the number of workers assigned to each process in the pattern (in the example of FIG. 9, each of process A, process B, and process C) Value of WIP).
そして、パターン選択部161が、WIPパターンリストのいずれかのパターンを、単位期間における担当者の工程への割り振り案として選択する。上述したように、パターン選択部161は、初回の単位期間については例えばランダムにWIPのパターンを選択する。また、パターン選択部161は、2回目以降の単位期間については、各パターンの評価値に基づいて評価値の最も小さいパターンを選択する。
Then, the
次期WIPパターンは、パターン選択部161が選択したWIPのパターンを示す情報である。表示部110が次期WIPパターンを表示し、担当者は次期WIPに従って作業を実行する。
また、予測ベロシティ算出部162が、次期WIPパターンと、プロジェクト基本情報の示す単位期間の長さとに基づいて、工程毎の予測ベロシティを算出する。
The next WIP pattern is information indicating the WIP pattern selected by the
Also, the predicted
単位期間が満了すると、操作入力部120は、当該単位期間における作業実績の入力を受ける。作業事績は、単位時間に行われた作業量を示す情報であり、期間IDと、機能IDと、工程IDと、実績作業時間と、ステータスとを含む。
期間IDと、機能IDと、工程IDと、ステータスとは、作業見積の場合と同様である。作業実績時間は、期間IDにて特定された単位期間において実行された作業量を作業毎に示す。作業実績時間として、機能IDおよび工程IDに対応付けて当該機能の当該工程における作業について行われた作業量が示される。
実績ベロシティ算出部163は、作業実績に基づいて、図6を参照して説明した実績ベロシティを工程毎に算出する。
When the unit period expires, the
The period ID, function ID, process ID, and status are the same as in the case of work estimation. The work performance time indicates the work amount executed in the unit period specified by the period ID for each work. As the work performance time, the amount of work performed for the work in the process of the function is shown in association with the function ID and the process ID.
The actual
また、制御部160(例えば実行可能作業量見積部164)は、作業実績に基づいて作業見積を更新する。具体的には制御部160は、図5を参照して説明したように、単位期間開始時の残作業量から実行された作業量を減算して、単位期間満了時の残作業量を算出する。
そして、実行可能作業量見積部164は、作業見積に基づいて、図6を参照して説明した実行可能作業量を工程毎に算出する。
In addition, the control unit 160 (for example, the executable work amount estimation unit 164) updates the work estimate based on the work results. Specifically, as described with reference to FIG. 5, the control unit 160 subtracts the amount of work performed from the amount of remaining work at the start of the unit period, and calculates the amount of remaining work when the unit period expires. .
Then, the executable work
また、見積修正部166は、図6を参照して説明したように、予測ベロシティと実績ベロシティとに基づいてベロシティ実績率を工程毎に算出し、ベロシティ実績率に基づいて実行可能作業量を修正した修正後作業量を工程毎に算出する。
そして、作業量比算出部165は、図6を参照して説明したように、修正後作業量に基づいて工程間における作業量比を算出する。
Further, as described with reference to FIG. 6, the
Then, as described with reference to FIG. 6, the work amount
さらに、パターン評価値算出部167は、図7を参照して説明したように、作業量比に基づいて、WIPパターンリストに含まれる各パターンの評価値を算出する。評価値リストは、パターン評価値算出部167が算出した各パターンの評価値を示すリストである。
そして、パターン選択部161が、評価値リストに基づいて、WIPパターンリストのいずれかのパターンを、単位期間における担当者の工程への割り振り案として選択する。
Further, as described with reference to FIG. 7, the pattern evaluation
Then, the
次に、図10を参照して、進捗管理支援装置100の動作について説明する。
図10は、制御部160が行う処理の手順の例を示すフローチャートである。
同図の処理において、制御部160は、操作入力部120が受ける操作入力にて初期情報を取得する(ステップS101)。
次に、制御部160(例えばパターン選択部161)は、初期情報として取得した担当者情報に基づいて、WIPパターンリストを生成する(ステップS102)。
そして、パターン選択部161が、初回の単位期間におけるWIPのパターンとして、WIPパターンリストのいずれかのパターンを選択する(ステップS103)。
Next, the operation of the progress
FIG. 10 is a flowchart illustrating an example of a procedure of processing performed by the control unit 160.
In the process of FIG. 5, the control unit 160 acquires initial information by an operation input received by the operation input unit 120 (step S101).
Next, the control unit 160 (for example, the pattern selection unit 161) generates a WIP pattern list based on the person-in-charge information acquired as the initial information (step S102).
Then, the
次に、予測ベロシティ算出部162は、ステップS103でパターン選択部161が選択したWIPのパターンと、初期情報の示す単位期間の長さとに基づいて、工程毎に予測ベロシティを算出する(ステップS111)。
そして、制御部160は、操作入力部120が作業実績の入力を受けるのを待ち受ける(ステップS112)。
Next, the predicted
And the control part 160 waits for the
単位期間が満了して操作入力部120が作業実績の入力を受けると、実績ベロシティ算出部163が、作業実績に基づいて工程毎に実績ベロシティを算出する(ステップS113)。
そして、見積修正部166は、予測ベロシティと実績ベロシティとに基づいて、工程毎にベロシティ実績率を算出する(ステップS114)。
When the unit period expires and the
Then, the
また、実行可能作業量見積部164は、作業見積に基づいて、実行可能作業量を算出する(ステップS115)。
そして、見積修正部166は、ステップS114で得られたベロシティ実績率に基づいて実行可能作業量を修正した修正後作業量を工程毎に算出する(ステップS116)。
Further, the executable work
Then, the
次に、作業量比算出部165が、修正後作業量に基づいて、工程間の作業量比を算出する(ステップS117)。
そして、パターン評価値算出部167が、作業量比に基づいて、WIPパターンリストに含まれる各パターンの評価値を算出する(ステップS118)。
そして、パターン選択部161が、WIPパターンリストに含まれる各パターンの評価値に基づいて、いずれかのパターンを、次の単位期間における担当者の工程への割り振り案として選択する(ステップS119)。
Next, the work amount
Then, the pattern evaluation
Then, the
次に、制御部160は、全期間が終了したか否かを判定する(ステップS120)。全ての作業を終了した場合や、対象プロジェクトの予算が尽きた場合など、対象プロジェクトの終了事由の発生にて全期間終了となる。
ステップS120において、全期間が終了してはいないと判定した場合(ステップS120:NO)、ステップS111へ戻り、次の単位期間における処理を引き続き行う。
一方、ステップS120において、全期間が終了したと判定した場合(ステップS120:YES)、図10の処理を終了する。
Next, the control unit 160 determines whether or not the entire period has ended (step S120). When all work is completed or when the budget of the target project is exhausted, the entire period ends when an event of termination of the target project occurs.
In step S120, when it is determined that the whole period has not ended (step S120: NO), the process returns to step S111, and the process in the next unit period is continued.
On the other hand, if it is determined in step S120 that the entire period has ended (step S120: YES), the processing in FIG. 10 ends.
以上のように、パターン選択部161は、単位期間における担当者の工程への割り振りの複数パターンのうち、単位期間に実行可能な作業の量の予測の工程間の比が、実行可能な状態にある作業の量の見積の工程間の比に最も近似するパターンを、割り振り案として選択する。
このように、実行可能な状態にある作業量に応じたパターンを選択することで、パターン選択部161は、実行可能な作業の特定の工程への集中を解消させるパターンを選択することができる。この点において、進捗管理支援装置100が提案するWIPのパターンを採用することで、ボトルネックの発生を回避する、あるいは、ボトルネックが大きくなる前に解消することができ、仕掛品の在庫の増大を抑制することができる。
As described above, the
In this way, by selecting a pattern according to the amount of work in an executable state, the
また、作業量比算出部165は、実行可能な状態にある作業の量の見積の工程間の比(作業量比)を、合計が担当者数に等しくなる値にて求める。そして、パターン選択部161は、単位期間における担当者の工程への割り振りの複数パターンのうち、工程毎の担当者数と、作業量比算出部165が当該工程について算出した値との差の大きさの、全工程についての合計が最も小さくなるパターンを、割り振り案として選択する。
これにより、進捗管理支援装置100は、作業量比算出部165が算出した値とWIPの各パターンにおける担当者数との差の大きさを工程毎に算出し、全工程についての合計が最も小さくなるパターンを選択するという簡単な処理にて、割り振り案を選択することができる。
Further, the work amount
As a result, the progress
また、見積修正部166は、実行可能な状態にある作業の量の工程毎の見積(実行可能作業量)を、工程毎の作業の量の見積もりと実績との比(ベロシティ実績率)に基づいて修正する。そして、パターン選択部161は、実行可能な状態にある作業の量の、修正後の見積の工程間の比に基づいて、担当者の工程への割り振り案を選択する。
このように、パターン選択部161が、修正された作業量の見積に基づいて担当者の工程への割り振り案を選択することで、より適切なパターンを割り振り案として選択することができ、仕掛品の在庫量増大を、より抑制し得る。
Further, the
Thus, the
次に、図11〜図19を参照して、進捗管理支援装置100の提案するWIPのパターンに基づいて作業を行った場合と、当該パターンに基づかずに作業を行った場合とを、例に基づいて比較する。
図11は、担当者が実行可能な工程の、もう1つの例を示す説明図である。同図の例において、作業を行う担当者は、担当者a、b、cの3人である。担当者a、bは、いずれも、工程Bを実行することはできないが、工程Aや工程Cを実行することはできる。担当者cは、工程Cを実行することはできないが、工程Aや工程Bを実行することはできる。
Next, referring to FIGS. 11 to 19, a case where the work is performed based on the WIP pattern proposed by the progress
FIG. 11 is an explanatory diagram showing another example of a process that can be executed by a person in charge. In the example of the figure, there are three persons in charge, who are the persons in charge, a, b and c. Neither the person in charge a or b can execute the process B, but can execute the process A or the process C. The person in charge c cannot execute the process C, but can execute the process A and the process B.
図12は、図11に示す担当者が実行可能な工程に基づいて得られるWIPのパターンの例を示す説明図である。図12のパターン1では、担当者a、b、c共に工程Aを実行する。パターン2では、担当者aとbとが工程Aを実行し、担当者cが工程Bを実行する。パターン3では、担当者a、bのいずれか一方と、担当者cとが工程Aを実行し、担当者a、bのうち他方は、工程Cを実行する。パターン4では、担当者cが工程Aを実行し、担当者bとcとが工程Cを実行する。パターン5では、担当者a、bのいずれか一方が工程Aを実行し、担当者cが工程Bを実行し、担当者a、bのうち他方は、工程Cを実行する。パターン6では、担当者cが工程Bを実行し、担当者aとbとが工程Cを実行する。
FIG. 12 is an explanatory diagram showing an example of a WIP pattern obtained based on processes that can be executed by the person in charge shown in FIG. In the
図13は、進捗管理支援装置100の提案するWIPのパターンに基づかずに作業を行った場合の、作業の実行状況の例を示す説明図である。同図の例では、実行可能な作業を実行可能になった順に実行した場合の例を示している。
期間1の開始時において、機能1〜機能6の工程Aがそれぞれ実行可能となっている。そこで、担当者a、b、cは、優先度の高い順に、それぞれ、機能1の工程A、機能2の工程A、機能3の工程Aを実行する。
FIG. 13 is an explanatory diagram illustrating an example of an execution state of work when the work is performed without being based on the WIP pattern proposed by the progress
At the start of the
期間1の開始時から3時間が経過して、担当者bが機能2の工程Aにおける作業を完了すると、当該担当者bは、期間1の開始時に実行可能になっており未着手の作業のうち優先度の最も高い、機能4の工程Aにおける作業を実行する。
これにより、期間1の満了時(従って、期間2の開始時)における残作業量の見積は、期間2見積の各欄に示されようになる。
When 3 hours have elapsed since the start of
Thereby, the estimate of the remaining work amount at the expiration of period 1 (and therefore at the start of period 2) is shown in each column of
担当者aは、機能1の工程Aにおける作業を期間1の満了時に完了しており、期間2では、まず、期間1の開始時に実行可能になっていた機能5の工程Aにおける作業を行う。
また、担当者bは、機能4の工程Aにおける作業を期間1の満了時に完了しており、期間2では、まず、期間1の開始時に実行可能になっていた機能6の工程Aにおける作業を行う。
一方、担当者cは、機能1の満了時に実行していた機能3の工程Aにおける作業を、期間2においても引き続き行う。
The person in charge a completes the work in the
The person in charge b completes the work in the
On the other hand, the person in charge c continues the work in the process A of the
期間2の開始時から2時間が経過して、担当者aが機能5の工程Aにおける作業を完了した際、当該担当者aが実行可能な機能A、Cのいずれの作業も実行可能になっていない。このため、担当者aは作業を行わず、実行可能な作業の発生を待ち受ける。
また、期間2の開始時から3時間が経過して、担当者bが機能6の工程Aにおける作業を完了した際、当該担当者bが実行可能な機能A、Cのいずれの作業も実行可能になっていない。このため、担当者bは作業を行わず、実行可能な作業の発生を待ち受ける。
When the person in charge a completes the work in the process A of the
In addition, when the person in charge b completes the work in the
また、期間2の開始時から3時間が経過して機能3の工程Aにおける作業を終了した担当者cは、実行可能な作業のうち優先度の最も高い、機能1の工程Bにおける作業を実行する。
さらに3時間が経過して、担当者cが機能1の工程Bにおける作業を完了すると、機能1の工程Cにおける作業が実行可能となる。そこで、担当者aは、機能1の工程Cにおける作業を実行する。また、機能1の工程Bにおける作業を完了した担当者cは、機能2の工程Bにおける作業を実行する。
これにより、期間2の満了時(従って、期間3の開始時)における残作業量の見積は、期間3見積の各欄に示されようになる。
Further, the person in charge c who has completed the work in the
When 3 hours elapse and the person in charge c completes the work in the process B of the
Thereby, the estimate of the remaining work amount at the expiration of period 2 (and therefore at the start of period 3) is shown in each column of
図13の期間3見積では、機能1〜機能6のいずれも、工程Aにおける作業は完了している。一方、工程Cにおける作業の完了した機能はない。
従って、機能1〜機能6のいずれも仕掛品となっており、要求変更があった場合の不利益が大きい。例えば、期間3の開始時において、機能4〜機能6の何れかに仕様変更が生じた場合、当該機能について行った工程Aの作業が無駄になってしまうおそれがある。
In the
Therefore, all of the
一方、図14は、進捗管理支援装置100の提案するWIPのパターンに基づいて作業を行った場合の、作業の実行状況の例を示す説明図である。
同図の例の期間1では、WIPのパターンに従って、担当者aとbとが工程Aに割り当てられ、担当者cが工程Bに割り当てられている。期間1において、担当者aは、機能1の工程Aにおける作業を実行する。また、担当者bは、機能2の工程Aにおける作業を実行する。
一方、期間1の開始時において、工程Bのいずれの作業も実行不可能な状態にある。このため、担当者cは、作業を行わずに実行可能な作業の発生を待ち受ける。
On the other hand, FIG. 14 is an explanatory diagram illustrating an example of an execution state of work when the work is performed based on the WIP pattern proposed by the progress
In the
On the other hand, at the start of
期間1の開始から3時間が経過して機能2の工程Aにおける作業を完了した担当者bは、機能3の工程Aにおける作業を行う。また、機能2の工程Aにおける作業が完了したことで、機能2の工程Bにおける作業が実行可能になる。そこで、担当者cは、機能2の工程Bにおける作業の実行を開始する。
これにより、期間1の満了時(従って、期間2の開始時)における残作業量の見積は、期間2見積の各欄に示されようになる。
The person in charge b who has completed the work in the process A of the
Thereby, the estimate of the remaining work amount at the expiration of period 1 (and therefore at the start of period 2) is shown in each column of
期間2では、担当者a、b、cが、それぞれ、工程C、A、Bに割り当てられている。これに従って、担当者aは、機能2の工程Cにおける作業を行い、当該作業を完了すると、機能1の工程Cにおける作業を行っている。
また、担当者bは、機能3の工程Aにおける作業を行い、当該作業を完了すると、機能4の工程Aにおける作業を行っている。
In the
In addition, the person in charge b performs the work in the
また、担当者cは、機能1の工程Bにおける作業を行い、当該作業を完了すると、機能3の工程Aにおける作業の完了を待って、機能3の工程Bにおける作業を行っている。
これにより、期間2の満了時(従って、期間3の開始時)における残作業量の見積は、期間3見積の各欄に示されようになる。
図14の期間3見積では、機能5、6のいずれも未着手であり、また、機能4については、作業が1時間行われたのみである。
従って、機能4〜6の何れかに要求変更があった場合でも、不利益が小さい。
In addition, the person in charge c performs the work in the process B of the
Thereby, the estimate of the remaining work amount at the expiration of period 2 (and therefore at the start of period 3) is shown in each column of
In the
Therefore, even if there is a request change in any of the
図15は、図13の例の期間1の開始時における作業の状況を示すグラフである。図13の期間1見積の各欄に示すように、期間1の開始時には、工程Aにおける6つの作業は全て実行可能な状態にあり、作業量の見積の合計は29となっている。また、工程B、Cにおけるいずれの作業も実行不可能な状態にあり、作業量の見積の合計は、それぞれ、14、26となっている。
なお、図14の例の期間1の開始時における作業の状況は、図13と同じである。従って、図15は、図14の例の期間1の開始時における作業の状況を示すグラフでもある。
FIG. 15 is a graph showing the status of work at the start of
14 is the same as that in FIG. 13 at the start of
図16は、図13の例の期間1の満了時における作業の状況を示すグラフである。図13の期間2見積の各欄に示すように、期間1の満了時(期間2の開始時)には、工程Aにおける作業のうち2つが実行可能な状態にあり、作業量の見積の合計は5となっている。また、工程Aにおける作業のうち、14時間分が実行完了となっており、3時間分が実行中となっている。
FIG. 16 is a graph showing the work status at the time of expiration of
また、期間2の開始時には、工程Bにおける作業のうち3つが実行可能な状態にあり、作業量の見積の合計は8となっている。また、工程Bにおける作業のうち、6時間分が実行不可となっており、3時間分が実行中となっている。
また、期間2の開始時には、工程Cにおけるいずれの作業も実行不可能な状態にあり、作業量の見積の合計は16となっている。
At the start of
In addition, at the start of the
図17は、図13の例の期間2の満了時における作業の状況を示すグラフである。図13の期間3見積の各欄に示すように、期間2の満了時(期間3の開始時)には、工程Aにおけるいずれの作業も完了しており、見積量の合計は29となっている。
また、期間3の開始時には、工程Bにおける作業のうち4つが実行可能な状態にあり、作業量の見積の合計は10となっている。また、工程Bにおける作業のうち、4時間分が実行完了となっている。
また、期間3の開始時には、工程Cにおける作業のうち1つが実行可能な状態にあり、作業量の見積の合計は3となっている。また、工程Bにおける作業のうち、13時間分が実行不可能となっており、9時間分が実行中となっている。
FIG. 17 is a graph showing the work status when the
In addition, at the start of
At the start of
工程Bにおける実行可能な作業の数は、図15、図16、図17で、それぞれ、0、3、6となっている。このように、図13の例では、実行可能な作業が工程Bに集中しており、工程Bがボトルネックになっている。 The numbers of operations that can be performed in the process B are 0, 3, and 6 in FIGS. 15, 16, and 17, respectively. In this way, in the example of FIG. 13, the work that can be performed is concentrated in the process B, and the process B is a bottleneck.
図18は、図14の例の期間1の満了時における作業の状況を示すグラフである。図14の期間2見積の各欄に示すように、期間1の満了時(期間2の開始時)には、工程Aにおける作業のうち3つが実行可能な状態にあり、作業量の見積の合計は9となっている。また、工程Aにおける作業のうち、10時間分が実行完了となっており、6時間分が実行中となっている。
FIG. 18 is a graph showing the work status at the time of expiration of
また、期間2の開始時には、工程Bにおける作業のうち1つが実行可能な状態にあり、作業量の見積の合計は3となっている。また、工程Bにおける作業のうち、1時間分が実行完了となっており、10時間分が実行不可となっている。
また、期間2の開始時には、工程Cにおける作業のうち1つが実行可能な状態にあり、作業量の見積の合計は3となっている。また、工程Cにおける作業のうち、23時間分が実行不可となっている。
At the start of
Further, at the start of the
図19は、図14の例の期間2の満了時における作業の状況を示すグラフである。図14の期間3見積の各欄に示すように、期間2の満了時(期間3の開始時)には、工程Aにおける作業のうち2つが実行可能な状態にあり、見積量の合計は5となっている。また、工程Aにおける作業のうち、10時間分が実行完了となっており、3時間分が実行中となっている。
FIG. 19 is a graph showing the work status at the end of
また、期間3の開始時には、工程Bにおける作業のうち実行可能な作業はない。また、工程Bにおける作業のうち、4時間分が実行完了となっており、7時間分が実行不可能となっており、2時間分が実行中となっている。
また、期間3の開始時には、工程Bにおける作業のうち実行可能な作業はない。また、工程Bにおける作業のうち、3時間分が実行完了となっており、13時間分が実行不可能となっており、6時間分が実行中となっている。
In addition, at the start of
In addition, at the start of
図13の例と異なり、図14の例では、実行可能な作業の数が集中しているのは、初期状態(期間1の開始時)における工程Aのみである。この点において、図14の例ではボトルネックは発生していない。
このように、進捗管理支援装置100の提案するWIPのパターンに基づかずに作業を行う例においてボトルネックが発生しているのに対し、進捗管理支援装置100の提案するWIPのパターンに基づいて作業を行う例ではボトルネックは発生していない。すなわち、進捗管理支援装置100の提案するWIPのパターンに従うことで、ボトルネックの発生が抑制されている。
Unlike the example of FIG. 13, in the example of FIG. 14, the number of work that can be performed is concentrated only in the process A in the initial state (at the start of the period 1). In this regard, no bottleneck has occurred in the example of FIG.
As described above, the bottleneck is generated in the example in which the work is performed based on the WIP pattern proposed by the progress
なお、過去のプロジェクトと担当者が同一である場合、当該過去のプロジェクトにおけるデータを用いて実績ベロシティを算出するようにしてもよい。この点について図20および図21を参照して説明する。
図20は、実績ベロシティ算出部163が過去のプロジェクトにおけるデータを用いて算出した実績ベロシティの例を示す説明図である。
Note that when the past project and the person in charge are the same, the actual velocity may be calculated using the data in the past project. This point will be described with reference to FIGS. 20 and 21. FIG.
FIG. 20 is an explanatory diagram showing an example of the actual velocity calculated by the actual
同図の例において、初回の単位期間におけるWIP(初回WIP)は、図4の場合と同様、例えばWIPパターンリストからランダムに選択される。
また、過去平均実績は、工程毎に、過去のプロジェクトにおける実績ベロシティを、工程に割り当てられた担当者の人数で除算して得られる。すなわち、実績ベロシティ算出部163は、式(8)に基づいて過去平均実績を算出する。
過去平均実績 = 過去の実績ベロシティ / 担当者数 ・・・(8)
In the example of FIG. 4, WIP (initial WIP) in the first unit period is selected at random from, for example, a WIP pattern list, as in the case of FIG.
In addition, the past average result is obtained by dividing the actual velocity in the past project by the number of persons in charge assigned to the process for each process. That is, the actual
Past average result = Past result velocity / Number of persons in charge (8)
例えば、過去のプロジェクトにおける実績ベロシティが、工程A、B、Cについてそれぞれ14、7、0であり、工程A、B、Cに割り当てられた担当者の人数が、それぞれ2人、1人、0人である場合、過去平均実績は、図20に示すようになる。
なお、過去のプロジェクトにおける実績ベロシティが複数ある場合、実績ベロシティ算出部163が、最新の実績ベロシティに基づいて過去平均実績を算出するようにしてもよい。あるいは、実績ベロシティ算出部163が、過去のプロジェクトにおける実績ベロシティの各々について過去平均実績を算出し、得られた過去平均実績の平均を取るようにしてもよい。
For example, the actual velocity in the past project is 14, 7, and 0 for the processes A, B, and C, respectively, and the number of persons in charge assigned to the processes A, B, and C is 2, 1, and 0, respectively. In the case of a person, the past average results are as shown in FIG.
When there are a plurality of actual velocities in the past project, the actual
また、実績ベロシティの各欄には、今回のプロジェクトの初回の単位期間における実績ベロシティが示されている。
また、次期平均実績は、工程毎に、今回のプロジェクトにおける実績ベロシティを、工程に割り当てられた担当者の人数で除算した値と、過去平均実績との平均を取って得られる。すなわち、実績ベロシティ算出部163は、式(9)に基づいて次期平均実績を算出する。
次期平均実績=(過去平均実績 + 実績ベロシティ/WIP)/2 ・・・(9)
In each column of actual velocity, actual velocity in the first unit period of this project is shown.
Further, the next average performance is obtained by taking the average of the value obtained by dividing the performance velocity in the current project by the number of persons in charge assigned to the process and the past average performance for each process. That is, the actual
Next term average result = (Past average result + Result velocity / WIP) / 2 (9)
また、実績ベロシティ算出部163は、工程毎に、次期平均実績を単位期間の長さで除算してベロシティ実績率を算出する。すなわち、実績ベロシティ算出部163は、式(3)に代えて式(10)に基づいてベロシティ実績率を算出する。
ベロシティ実績率 = 次期平均実績 / 単位期間の長さ ・・・(10)
実績可能作業量、修正後作業量、作業量比の求め方は、図6の場合と同様である。
The actual
Velocity performance rate = next average performance / length of unit period (10)
The method for obtaining the actual work amount, the post-correction work amount, and the work amount ratio is the same as in FIG.
図21は、図20で得られた作業量比に基づいてパターン選択部161が選択するWIPの例を示す説明図である。図21に示すWIPのパターンの評価値の算出方法は、図7の場合と同様である。また、パターン選択部161が評価値に基づいてWIPのパターンを選択する方法も、図7の場合と同様である。
FIG. 21 is an explanatory diagram illustrating an example of WIP selected by the
見積修正部166がベロシティ実績率を算出すると、実績ベロシティ算出部163は、過去平均実績の値を次期平均実績の値に更新する。これにより、見積修正部166は、今回の単位期間で算出した次期平均実績の値を、次の単位期間において過去平均実績の値として用いて、新たに次期平均実績を算出する。
When the
以上のように、見積修正部166は、実行可能な状態にある作業の量の工程毎の見積(実行可能作業量)を、複数の単位期間における工程毎の作業の量の実績に基づいて修正する。
これにより、パターン選択部161は、担当者が緊急の業務を処理して一時的に作業を行えなかった場合など、一時的な変動要因の影響を低減させて、安定的にWIPのパターンを選択することができる。
As described above, the
As a result, the
なお、進捗管理支援装置100の全部または一部の機能を実現するためのプログラムをコンピュータ読み取り可能な記録媒体に記録して、この記録媒体に記録されたプログラムをコンピュータシステムに読み込ませ、実行することにより各部の処理を行ってもよい。なお、ここでいう「コンピュータシステム」とは、OSや周辺機器等のハードウェアを含むものとする。
また、「コンピュータシステム」は、WWWシステムを利用している場合であれば、ホームページ提供環境(あるいは表示環境)も含むものとする。
また、「コンピュータ読み取り可能な記録媒体」とは、フレキシブルディスク、光磁気ディスク、コンパクトディスク等の可搬媒体、コンピュータシステムに内蔵されるハードディスク等の記憶装置のことをいう。さらに「コンピュータ読み取り可能な記録媒体」とは、インターネット等のネットワークや電話回線等の通信回線を介してプログラムを送信する場合の通信線のように、短時間の間、動的にプログラムを保持するもの、その場合のサーバやクライアントとなるコンピュータシステム内部の揮発性メモリのように、一定時間プログラムを保持しているものも含むものとする。また上記プログラムは、前述した機能の一部を実現するためのものであっても良く、さらに前述した機能をコンピュータシステムにすでに記録されているプログラムとの組み合わせで実現できるものであっても良い。
Note that a program for realizing all or part of the functions of the progress
Further, the “computer system” includes a homepage providing environment (or display environment) if a WWW system is used.
The “computer-readable recording medium” refers to a portable medium such as a flexible disk, a magneto-optical disk, and a compact disk, and a storage device such as a hard disk built in the computer system. Furthermore, the “computer-readable recording medium” dynamically holds a program for a short time like a communication line when transmitting a program via a network such as the Internet or a communication line such as a telephone line. In this case, a volatile memory in a computer system serving as a server or a client in that case, and a program that holds a program for a certain period of time are also included. The program may be a program for realizing a part of the functions described above, and may be a program capable of realizing the functions described above in combination with a program already recorded in a computer system.
以上、この発明の実施形態を図面を参照して詳述してきたが、具体的な構成はこの実施形態に限られるものではなく、この発明の要旨を逸脱しない範囲の設計変更等も含まれる。 The embodiment of the present invention has been described in detail with reference to the drawings. However, the specific configuration is not limited to this embodiment, and includes design changes and the like within a scope not departing from the gist of the present invention.
100 進捗管理支援装置
110 表示部
120 操作入力部
130 記憶部
160 制御部
161 パターン選択部
162 予測ベロシティ算出部
163 実績ベロシティ算出部
164 実行可能作業量見積部
165 作業量比算出部
166 見積修正部
167 パターン評価値算出部
DESCRIPTION OF
Claims (6)
前記単位期間における担当者の工程への割り振りの複数パターンのうち、前記単位期間における前記割り振りのパターン毎の実行可能な作業の量の予測の工程間の比が、前記単位期間の開始時に前記所定の順序を保つとした場合に実行可能な状態にある作業の量の見積の工程間の比に最も近似するパターンを、前記割り振り案として選択するパターン選択部を具備することを特徴とする進捗管理支援装置。 The entire work is divided into a plurality of parts, and a process of a person in charge in a predetermined unit period for a plurality of persons in charge of a project in which a plurality of processes executed in a predetermined order are included in each part. A progress management device that outputs an allocation plan to
Among a plurality patterns of allocation to personnel step in the unit period, the ratio between the prediction step of the amount of work that can be done for each pattern of the allocation definitive in the unit period, the at the start of the unit period Progress comprising a pattern selection unit that selects, as the allocation plan, a pattern that most closely approximates the ratio between processes for estimating the amount of work that can be executed when the predetermined order is maintained Management support device.
前記パターン選択部は、前記単位期間における担当者の工程への割り振りの複数パターンのうち、工程毎の担当者数と、前記作業量比算出部が当該工程について算出した値との差の大きさの、全工程についての合計が最も小さくなるパターンを、前記割り振り案として選択する、ことを特徴とする請求項1に記載の進捗管理支援装置。 A work amount ratio calculation unit for obtaining a ratio between processes for estimating the amount of work in an executable state, which is obtained by a value in which the total is equal to the number of persons in charge,
The pattern selection unit is a size of a difference between the number of persons in charge for each process and a value calculated by the work amount ratio calculation unit for the process among a plurality of patterns of allocation of the person in charge to the process in the unit period. The progress management support apparatus according to claim 1, wherein a pattern having the smallest sum for all processes is selected as the allocation plan.
前記パターン選択部は、修正後の前記実行可能な状態にある作業の量の見積の工程間の比に基づいて、前記割り振り案を選択する、ことを特徴とする請求項1または2に記載の進捗管理支援装置。 An estimate correction unit that corrects the estimate of the amount of work in an executable state for each process based on the ratio between the estimate of the amount of work in the process and the actual amount of work in the unit during the unit period Comprising
The said pattern selection part selects the said allocation plan based on ratio between the processes of estimation of the quantity of the work in the said executable state after correction, The Claim 1 or 2 characterized by the above-mentioned. Progress management support device.
前記単位期間における担当者の工程への割り振りの複数パターンのうち、前記単位期間における前記割り振りのパターン毎の実行可能な作業の量の予測の工程間の比が、前記単位期間の開始時に前記所定の順序を保つとした場合に実行可能な状態にある作業の量の見積の工程間の比に最も近似するパターンを、前記割り振り案として選択するパターン選択ステップを具備することを特徴とする進捗管理支援方法。 The entire work is divided into a plurality of parts, and a process of a person in charge in a predetermined unit period for a plurality of persons in charge of a project in which a plurality of processes executed in a predetermined order are included in each part. A progress management method of a progress management device that outputs an allocation plan to
Among a plurality patterns of allocation to personnel step in the unit period, the ratio between the prediction step of the amount of work that can be done for each pattern of the allocation definitive in the unit period, the at the start of the unit period A progress comprising a pattern selection step of selecting, as the allocation plan, a pattern that most closely approximates the ratio between the steps of estimating the amount of work that can be executed when the predetermined order is maintained Management support method.
前記単位期間における担当者の工程への割り振りの複数パターンのうち、前記単位期間における前記割り振りのパターン毎の実行可能な作業の量の予測の工程間の比が、前記単位期間の開始時に前記所定の順序を保つとした場合に実行可能な状態にある作業の量の見積の工程間の比に最も近似するパターンを、前記割り振り案として選択するパターン選択ステップを実行させるためのプログラム。 The entire work is divided into a plurality of parts, and a process of a person in charge in a predetermined unit period for a plurality of persons in charge of a project in which a plurality of processes executed in a predetermined order are included in each part. To the computer as the progress management device that outputs the allocation plan to
Among a plurality patterns of allocation to personnel step in the unit period, the ratio between the prediction step of the amount of viable tasks for each pattern of the allocation definitive in the unit period, the at the start of the unit period A program for executing a pattern selection step of selecting, as the allocation plan, a pattern that most closely approximates the ratio between processes for estimating the amount of work that can be executed when a predetermined order is maintained .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2013110218A JP6170733B2 (en) | 2013-05-24 | 2013-05-24 | Progress management support device, progress management support method, and program |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2013110218A JP6170733B2 (en) | 2013-05-24 | 2013-05-24 | Progress management support device, progress management support method, and program |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2014229205A JP2014229205A (en) | 2014-12-08 |
JP6170733B2 true JP6170733B2 (en) | 2017-07-26 |
Family
ID=52128968
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2013110218A Active JP6170733B2 (en) | 2013-05-24 | 2013-05-24 | Progress management support device, progress management support method, and program |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP6170733B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102312308B1 (en) * | 2020-04-06 | 2021-10-14 | (주)앱닥터 | Project mediation system, server and method thereof |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08231012A (en) * | 1995-02-28 | 1996-09-10 | Fujitsu Ltd | Production process controlling device |
JP2006085213A (en) * | 2004-09-14 | 2006-03-30 | Inter Db:Kk | Management system for work schedule |
JP4995846B2 (en) * | 2008-01-23 | 2012-08-08 | パナソニック株式会社 | Mounting condition determination method |
JP5442524B2 (en) * | 2010-04-13 | 2014-03-12 | 株式会社神戸製鋼所 | Schedule creation method, schedule creation program, and schedule creation device |
JP2012160007A (en) * | 2011-01-31 | 2012-08-23 | Japan Post Service Co Ltd | Work management system, work management method and work management program |
JP5901171B2 (en) * | 2011-07-28 | 2016-04-06 | 三菱重工業株式会社 | Production management device, production planning method and production planning program |
-
2013
- 2013-05-24 JP JP2013110218A patent/JP6170733B2/en active Active
Also Published As
Publication number | Publication date |
---|---|
JP2014229205A (en) | 2014-12-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Liu et al. | Online multi-workflow scheduling under uncertain task execution time in IaaS clouds | |
US9477521B2 (en) | Method and system for scheduling repetitive tasks in O(1) | |
US9715408B2 (en) | Data-aware workload scheduling and execution in heterogeneous environments | |
US8793693B2 (en) | Apparatus and method for predicting a processing time of a computer | |
US8266622B2 (en) | Dynamic critical path update facility | |
EP2905702B1 (en) | Real-time multi-task scheduling method and device | |
JP6025154B2 (en) | System, method and program for managing a project | |
US8589203B1 (en) | Project pipeline risk management system and methods for updating project resource distributions based on risk exposure level changes | |
US8484060B2 (en) | Project estimating system and method | |
US20140343999A1 (en) | Risk-aware project scheduling techniques | |
JP6254712B2 (en) | Method and apparatus for predicting changes in feature information | |
US9883037B1 (en) | Systems and methods in an electronic contact management system to estimate required staff levels for multi-skilled agents | |
US9483247B2 (en) | Automated software maintenance based on forecast usage | |
CN106775932B (en) | Real-time workflow scheduling method triggered by random event in cloud computing system | |
JP2016194736A (en) | Project execution planning support method, project execution planning support program, and project execution planning support system | |
JP6550980B2 (en) | Scheduling method, information processing apparatus and scheduling program | |
US8458004B2 (en) | Dynamically pooling unused capacities across an organization to execute atomic tasks | |
JP2012185645A (en) | Work shift creation support device and program | |
US10037511B2 (en) | Dynamically altering selection of already-utilized resources | |
JP6170733B2 (en) | Progress management support device, progress management support method, and program | |
Zhang et al. | An enhanced priority-based scheduling heuristic for DAG applications with temporal unpredictability in task execution and data transmission | |
US20150134312A1 (en) | Evaluation of Service Delivery Models | |
US20160140482A1 (en) | Critical Path Scheduling with Drag and Pull | |
JP5653333B2 (en) | Schedule creation method, schedule creation program, and schedule creation device | |
Couch | Performance Robust Project Scheduling Polices for Naval Ship Maintenance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20160425 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20170310 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20170321 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20170522 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20170606 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20170703 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6170733 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |