JP5755786B1 - Construction method for joints - Google Patents

Construction method for joints Download PDF

Info

Publication number
JP5755786B1
JP5755786B1 JP2014183650A JP2014183650A JP5755786B1 JP 5755786 B1 JP5755786 B1 JP 5755786B1 JP 2014183650 A JP2014183650 A JP 2014183650A JP 2014183650 A JP2014183650 A JP 2014183650A JP 5755786 B1 JP5755786 B1 JP 5755786B1
Authority
JP
Japan
Prior art keywords
pile
joint
improved pile
constructing
stirring shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2014183650A
Other languages
Japanese (ja)
Other versions
JP2016056581A (en
Inventor
上野 一彦
一彦 上野
丈夫 浅沼
丈夫 浅沼
幸彦 徳永
幸彦 徳永
辰男 長津
辰男 長津
車田 佳範
佳範 車田
伸弘 本多
伸弘 本多
寿一 伊勢
寿一 伊勢
大西 常康
常康 大西
博文 田口
博文 田口
滋 久保
滋 久保
祥二 東
祥二 東
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toa Corp
Toray Engineering Co Ltd
Penta Ocean Construction Co Ltd
Takenaka Civil Engineering and Construction Co Ltd
Shimizu Corp
Fudo Tetra Corp
Original Assignee
Toa Corp
Penta Ocean Construction Co Ltd
Takenaka Civil Engineering and Construction Co Ltd
Toyo Construction Co Ltd
Shimizu Corp
Fudo Tetra Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toa Corp, Penta Ocean Construction Co Ltd, Takenaka Civil Engineering and Construction Co Ltd, Toyo Construction Co Ltd, Shimizu Corp, Fudo Tetra Corp filed Critical Toa Corp
Priority to JP2014183650A priority Critical patent/JP5755786B1/en
Application granted granted Critical
Publication of JP5755786B1 publication Critical patent/JP5755786B1/en
Publication of JP2016056581A publication Critical patent/JP2016056581A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

【課題】空打ちをして後行改良杭を打設する際、打ち継ぎ目地にせん断力が発生することがなく、また、空打ち時の適正な加水量と固化材の割増量を設定する方法を提供する。【解決手段】深層混合処理機を進行方向にオーバーラップ部を有するように移動して連続する改良杭を構築する打ち継ぎ目地の施工方法において、進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭17aを構築し、直前の先行改良杭の固化前に、オーバーラップ部18を有するように空打ちをして固化材を拡散させ、空打ちの跡に後行改良杭17bを構築し、空打ち時に、水を吐出してオーバーラップ部の固化剤を拡散し、空打ち跡の後行改良杭の構築時に、固化材を割増して打設する。【選択図】図1[PROBLEMS] To set a proper amount of water added and an additional amount of a solidified material at the time of blanking without generating a shearing force at the joint at the time of blanking and placing a follow-up improved pile. Provide a method. In a joint joint construction method for constructing a continuous improved pile by moving a deep mixing processor so as to have an overlap portion in a traveling direction, a stirring shaft having a plurality of axes in a direction orthogonal to the traveling direction. Is used to build the preceding improved pile 17a, and before solidification of the immediately preceding advanced pile, the solidified material is diffused by blanking so as to have the overlap portion 18, and the subsequent improved pile 17b is traced to the trace of the blanking. In the case of idle driving, water is discharged to diffuse the overlapping agent in the overlap portion, and the solidified material is additionally installed at the time of construction of the post-improvement pile. [Selection] Figure 1

Description

本発明は、セメント系などの固化材を使用した原位置地盤改良工法において、隣接する改良杭間の打ち継ぎ目地に所定の強度が得られるように構築するための打ち継ぎ目地の施工方法に関するものである。   The present invention relates to a joint joint construction method for constructing so that a predetermined strength can be obtained at a joint joint between adjacent improved piles in an in-situ ground improvement method using a solidified material such as cement. It is.

セメント系の固化材を用いた原位置地盤改良工法の1つとして深層混合処理工法が知られている。この深層混合処理工法は、図13に示すように、改良しようとする地盤19に、撹拌軸11の先端に掘削刃14を備えた深層混合処理機を直立させ、撹拌軸11を電動モータ12で回転させながら掘削刃14で地盤19を掘削し、注入管15の先端から固化材16を吐出し、撹拌翼13で地盤19を撹拌しながら固化材16を地盤19に混合し、所定の深さまで改良杭17を造成し、撹拌軸11を逆回転して引き抜き、引き抜いた後、深層混合処理機を改良杭17の略直径分だけ移動して上記動作を繰り返して連続する壁等を構築する方法である。   As one of the in-situ ground improvement methods using a cement-based solidified material, a deep mixing method is known. In this deep mixing treatment method, as shown in FIG. 13, a deep mixing treatment machine having an excavating blade 14 at the tip of the stirring shaft 11 is made upright on the ground 19 to be improved, and the stirring shaft 11 is moved by an electric motor 12. While rotating, the ground 19 is excavated with the excavating blade 14, the solidified material 16 is discharged from the tip of the injection pipe 15, and the solidified material 16 is mixed with the ground 19 while stirring the ground 19 with the stirring blade 13, to a predetermined depth. A method for constructing a continuous wall or the like by constructing an improved pile 17 and rotating the stirring shaft 11 in the reverse direction and pulling it out, and then moving the deep mixing processor by the approximate diameter of the improved pile 17 and repeating the above operation. It is.

この深層混合処理工法において、先行改良杭17aと後行改良杭17bを確実に一体化するためには、図13(d)に示すように、固化材16の水和反応が進行する前にオーバーラップ部18が生じるように施工し、順次連結して改良杭17の壁を構築することが要求される。
オーバーラップ部18が生じるように構築するには、先行改良杭17aを構築してから後行改良杭17bを構築するまでの待機時間(接合間隔)は、可能な限り短くする必要がある。具体的には、この接合間隔を通常は、24時間以内とすることが好ましく、最大でも48時間以内として管理されている。
In this deep mixing treatment method, in order to reliably integrate the preceding improved pile 17a and the succeeding improved pile 17b, as shown in FIG. 13 (d), the overhang before the hydration reaction of the solidified material 16 proceeds. It is required to construct the wall of the improved pile 17 by constructing so that the wrap portion 18 is generated and sequentially connecting them.
In order to construct so that the overlap portion 18 is generated, it is necessary to shorten the standby time (joining interval) from the construction of the preceding improved pile 17a to the construction of the subsequent improved pile 17b as much as possible. Specifically, this joining interval is usually preferably within 24 hours, and is managed within 48 hours at the maximum.

しかし、台風などの荒天待機により工事が中断し、接合のための管理された接合間隔以内では工事の再開が不可能になる場合がある。特に、海上工事においては、作業船を退避させる必要があることから、接合間隔が7日を超えることがある。   However, the construction may be interrupted due to stormy weather such as a typhoon, and the construction may not be resumed within a controlled joining interval for joining. In particular, in offshore construction, since it is necessary to evacuate the work boat, the joining interval may exceed 7 days.

接合間隔が管理時間以上になると、先行改良杭17aの固化が進行するため、オーバーラップ部18が生じるように深層混合処理機を貫入することが不可能になる。このような場合には、図13(b)に示すように、先行改良杭17aと後行改良杭17bを点接触するように打設せざるを得ず、打ち継ぎ目地20が点又は線接触状態で形成されるので、改良壁としての一体性の評価が困難であり、また、設計図書で定めた改良率(改良面積)を満足させることはできない。
そこで、図13(c)に示すように、先行改良杭17aと後行改良杭17bとの隙間部分に高圧噴射工法等により固化改良材21を打設し、一体性の向上を図る工法がある。しかし、このような対策では、深層混合処理機以外の機械を用い、かつ、固化改良の作業が増えるため、大幅な施工コストの増加、工程の遅延が生じるという問題がある。
When the joining interval is equal to or longer than the management time, solidification of the advanced improvement pile 17a proceeds, so that it becomes impossible to penetrate the deep mixing processor so that the overlap portion 18 is generated. In such a case, as shown in FIG. 13 (b), the leading improved pile 17a and the succeeding improved pile 17b have to be placed so as to make point contact, and the joint joint 20 has point or line contact. Since it is formed in a state, it is difficult to evaluate the integrity as an improved wall, and the improvement rate (improved area) defined in the design book cannot be satisfied.
Then, as shown in FIG.13 (c), there exists the construction method which drives the solidification improvement material 21 by the high-pressure injection construction method etc. in the clearance gap part between the preceding improvement pile 17a and the subsequent improvement pile 17b, and improves an integrity. . However, such measures use a machine other than the deep-mixing processor and increase the work of solidification improvement, resulting in a significant increase in construction cost and a delay in the process.

接合間隔が管理時間以上になると予測される場合に、待機直前の改良杭17に使用する固化材16として遅硬セメントや遅延材を使用して固化の進行を抑え、接合間隔を長くする方法がある。この方法は、図13(c)に示す方法に比較してコストや作業工程に与える影響は少ないが、予め遅硬セメント、遅延材の他に、これらを添加する装置を用意しておかなければならない。しかも、得られる遅延効果も3〜5日程度と限界がある。   When it is predicted that the joining interval will be longer than the management time, there is a method of using a slow-hardening cement or retarding material as the solidifying material 16 used for the improved pile 17 immediately before standby to suppress the progress of solidification and lengthening the joining interval. is there. This method has less impact on the cost and work process than the method shown in FIG. 13 (c), but in addition to the slow-hardening cement and retarding material, a device for adding these must be prepared in advance. Don't be. Moreover, the delay effect obtained is limited to about 3 to 5 days.

これらの方法以外に、深層混合処理機の空打ちにより打ち継ぎ目地20を結合する方法が提案されている(特許文献1、2及び3)。
特許文献1に記載の方法は、図10(a)に示すように、第1番目のパイルAは、撹拌翼の回動範囲内に地盤改良材を噴出又は吐出させるとともに、回転軸を回転させつつ下降及び上昇させることにより造成する。次に、第2、第3のパイルB,Cを順次部分的にオーバーラップさせて造成する。パイルCを造成した後、次のパイルDを直ちに造成できないときには、図10(b)に示すように、パイルDが造成される位置において、地盤改良材は供給しないで回転軸を回転しながら下降及び上昇させて、撹拌翼による撹拌を行う。このようにして空打ち部bを形成すると、パイルCのオーバーラップ部分aの地盤改良材は、回転翼の回動範囲である空打ち部bまで拡散され、濃度が薄くなる。図10(c)に示すように、後に空打ち部bにパイルDを造成する。
In addition to these methods, methods have been proposed in which the joints 20 are joined by idle driving of a deep mixing processor (Patent Documents 1, 2, and 3).
In the method described in Patent Document 1, as shown in FIG. 10 (a), the first pile A causes the ground improvement material to be ejected or discharged within the rotation range of the stirring blade, and the rotation shaft is rotated. It is created by lowering and raising it. Next, the second and third piles B and C are formed by partially overlapping one after another. When the next pile D cannot be created immediately after the pile C is created, as shown in FIG. 10 (b), the pile is lowered while rotating the rotating shaft without supplying the ground improvement material at the position where the pile D is created. Then, the mixture is raised and stirred by a stirring blade. When the blank portion b is formed in this manner, the ground improvement material in the overlap portion a of the pile C is diffused to the blank portion b that is the rotation range of the rotary blade, and the concentration becomes low. As shown in FIG. 10 (c), a pile D is formed in the blanking portion b later.

特許文献2に記載の方法は、図11(a)に示すように、2軸の深層混合処理機10を進行方向に並べて改良杭17を形成する場合、第Iの工程では、進行方向の内側の回転軸のみ改良杭17を形成し、外側の回転軸では固化材16を吐出しないで撹拌部のみの空打ちbを形成する。次いで、深層混合処理機を移動して第IIの工程では、内側の回転軸で先の撹拌部のみの空打ちbの位置に改良杭17を形成し、外側の回転軸で撹拌部のみの空打ちbを形成する。以下、順次深層混合処理機10を移動させて連続壁を形成する。図11(b)は、3軸の深層混合処理機10を使用し、内側の2軸に改良杭17を形成し、外側の1軸に撹拌部のみの空打ち部bを形成する例を示し、図11(c)は、4軸の深層混合処理機10を使用し、内側の3軸に改良杭17を形成し、外側の1軸に撹拌部みの空打ち部bを形成する例を示し、図11(d)は、4軸の深層混合処理機10を使用し、内側の2軸に改良杭17を形成し、外側の2軸に撹拌部のみの空打ち部bを形成する例を示している。   In the method described in Patent Document 2, when the improved pile 17 is formed by arranging the biaxial deep mixing processors 10 in the traveling direction as shown in FIG. 11A, in the first step, the inner side in the traveling direction is used. The improved pile 17 is formed only on the rotating shaft, and the blanking b of only the stirring portion is formed on the outer rotating shaft without discharging the solidified material 16. Next, in the second step by moving the deep mixing processing machine, the improved pile 17 is formed at the position of the blanking b of only the previous stirring unit on the inner rotating shaft, and only the stirring unit is empty on the outer rotating shaft. Strike b is formed. Thereafter, the deep-mixing processor 10 is sequentially moved to form a continuous wall. FIG.11 (b) shows the example which uses the 3 axis | shaft deep mixing processing machine 10, forms the improvement pile 17 in the inner 2 axis | shaft, and forms the blanking part b only of a stirring part in the outer 1 axis | shaft. FIG. 11 (c) shows an example in which an improved pile 17 is formed on the inner three shafts, and an empty portion b of the stirring portion is formed on the outer one shaft, using the four-axis deep mixing processor 10. FIG. 11 (d) shows an example in which a deep pile processing machine 10 with four axes is used, an improved pile 17 is formed on the inner two axes, and an empty portion b having only a stirring portion is formed on the outer two axes. Is shown.

特許文献3の第2頁左下欄には、図10または図11に示すような空打ち部を形成する場合において、掘削時に、水又は貧配合の固化材16(低比重)の注入を行い、再度の掘削時に注入される高比重の固化材16との置換を行うことが記載されている。   In the lower left column of the second page of Patent Document 3, in the case of forming a blanking portion as shown in FIG. 10 or FIG. 11, during excavation, water or poor solidified material 16 (low specific gravity) is injected, It is described that replacement with the solidified material 16 having a high specific gravity injected at the time of another excavation is performed.

特公平3−59210号公報Japanese Patent Publication No. 3-59210 特開平6−173252号公報JP-A-6-173252 特開平4−143310号公報JP-A-4-143310

特許文献1及び2に示す方法では、空打ちによりオーバーラップ部18の固化材16を拡散させ、濃度を薄めて固化させることで、後行改良杭17bの打設が可能になるとしている。
しかし、これらの従来の方法では、掘削する進行方向が直列の1列であるため、空打ちによる固化材16の拡散が不十分なことが多く、オーバーラップ部18が残った固化材16により不完全に固結して、後行改良杭17bの打設の際に深層混合処理機10が図12(b)に示すように残った固化部分によって中心点がO1からO2に跳ねられ、後行改良杭17bの芯が先行改良杭17aに対してずれる等の支障をきたす場合があった。
また、掘削する進行方向が直列の1列であるため、図12(a)に示すように、隣接する先行改良杭17aと後行改良杭17bに水平方向の外力が作用すると、打ち継ぎ目地20を境にせん断(ずれや回転)力が発生し易いため、構造上の弱点となる恐れがあるという問題があった。
さらに、特許文献3には、空打ち時に水を加えることが記載されているが、この水を加える量は、土質にもよるが少なすぎると固化が進んで空打ちの効果が得られず、多すぎると強度発現率が急激に落ち、適正な加水量が望まれていた。
In the methods shown in Patent Documents 1 and 2, the solidified material 16 of the overlap portion 18 is diffused by idle driving, and the concentration is reduced and solidified, so that the succeeding improved pile 17b can be driven.
However, in these conventional methods, the advancing direction of excavation is a single line in series, so that the solidified material 16 is often insufficiently diffused by idle driving, and the solidified material 16 with the overlapped portion 18 remaining is not suitable. When solidified and the subsequent improved pile 17b is laid, the center of the deep mixing machine 10 is jumped from O1 to O2 by the remaining solidified portion as shown in FIG. In some cases, the core of the improved pile 17b may be hindered from being displaced with respect to the preceding improved pile 17a.
Further, since the traveling direction of excavation is one line in series, as shown in FIG. 12A, when a horizontal external force acts on the adjacent preceding improved pile 17a and the succeeding improved pile 17b, the joint 20 There is a problem that a shear (displacement or rotation) force is likely to occur at the boundary, which may cause a weak point in the structure.
Furthermore, Patent Document 3 describes that water is added at the time of emptying, but the amount of this water added depends on the soil, but if it is too small, solidification proceeds and the effect of emptying cannot be obtained. If the amount is too large, the strength expression rate drops rapidly, and an appropriate amount of water has been desired.

本発明は、空打ち部を形成して後行改良杭17bを打設する際、先行改良杭17aとの芯がずれる等の支障をきたすことがなく、また、打ち継ぎ目地20を境にせん断(ずれや回転)力が発生することのない打ち継ぎ目地の施工方法を提供することを目的としている。
さらに、本発明は、空打ち時の適正な加水量を設定する方法と固化材の適正な割増量を設定する方法を提供することを目的としている。
The present invention does not cause troubles such as misalignment of the core with the preceding improved pile 17a when the idle improved pile 17b is driven by forming the blanking portion, and shearing is performed at the joint 20 as a boundary. The object is to provide a method for constructing joints that do not generate any (displacement or rotation) force.
Furthermore, an object of the present invention is to provide a method for setting an appropriate amount of water at the time of emptying and a method for setting an appropriate extra amount of a solidified material.

本発明による打ち継ぎ目地の施工方法は、深層混合処理機10の撹拌軸11を回転させながら掘削刃14で地盤19を掘削し、注入管15の先端から固化材16を吐出し、撹拌翼13で撹拌混合し、改良杭17を造成し、撹拌軸11を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部18を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸11を用いて先行改良杭17aを構築する工程と、
直前の先行改良杭17aの固化前に、オーバーラップ部18を有するように空打ち部17cを形成して固化材16を拡散させる工程と、
空打ち部17cの跡に後行改良杭17bを構築する工程と
からなることを特徴とする。
In the joint joint construction method according to the present invention, the ground 19 is excavated by the excavating blade 14 while rotating the agitation shaft 11 of the deep mixing processor 10, the solidified material 16 is discharged from the tip of the injection pipe 15, and the agitating blade 13. After stirring and mixing, the improved pile 17 is formed, the stirring shaft 11 is pulled out, the deep mixing machine is moved so as to have the overlap portion 18 in the traveling direction, and the above operation is repeated to construct a continuous wall and the like. In the construction method of joint joints to
The step of constructing the preceding improved pile 17a using the stirring shaft 11 having a plurality of axes in the direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile 17a, a step of forming the blank portion 17c so as to have the overlap portion 18 and diffusing the solidified material 16,
And a step of constructing the succeeding improved pile 17b on the trace of the empty portion 17c.

前記空打ち部17cを形成する工程時に、固化材16に代えて水を吐出して直前の先行改良杭17aのオーバーラップ部18を拡散する。
水の吐出量は、最低限先行改良杭17aの構築時における固化材16の量とする。
また、水の吐出量は、粘性土土壌の場合、固化処理土1mに対し15%を限度とし、強度発現率が水を吐出しない場合の90%を下回らない範囲とする。
During the step of forming the blank portion 17c, water is discharged instead of the solidified material 16, and the overlap portion 18 of the preceding improved pile 17a is diffused.
The amount of water discharged is at least the amount of the solidified material 16 at the time of construction of the advance improvement pile 17a.
In addition, in the case of clay soil, the amount of water discharged is limited to 15% with respect to 1 m 3 of the solidified soil, and the strength expression rate is within a range not lower than 90% when water is not discharged.

前記空打ち部17cの跡に後行改良杭17bを構築する工程は、先行改良杭17aよりも固化材16を割増して直前の先行改良杭17aと空打ち部17cの跡に構築した後行改良杭17bとのオーバーラップ部18における境界の打ち継ぎ目地20の強度を上昇させるようにする。   The process of constructing the succeeding improved pile 17b on the trace of the blanking portion 17c is a subsequent improvement in which the solidifying material 16 is added more than the preceding improved pile 17a and constructed on the trace of the preceding preceding improved pile 17a and the blanking section 17c. The strength of the joint 20 at the boundary of the overlap portion 18 with the pile 17b is increased.

固化材16の割増しは、先行改良杭17aの構築時の1.2倍を上限とする。
空打ち部17cを形成する工程時に固化材16に代えた水の吐出量は、粘性土土壌の場合、固化処理土1mに対し15%を限度とし、強度発現率が水を吐出しない場合の90%を下回らない範囲とし、かつ、空打ち部17cの跡に後行改良杭17bを構築する工程時に固化材16を割増す量は、先行改良杭17aの構築時の1.2倍を上限として直前の先行改良杭17aと空打ち部17cの跡に構築した後行改良杭17bとのオーバーラップ部18における境界の打ち継ぎ目地20の強度を上昇させるようにする。
The surplus of the solidifying material 16 is 1.2 times the upper limit when the preceding improved pile 17a is constructed.
In the case of cohesive soil, the amount of water discharged in place of the solidifying material 16 during the step of forming the empty portion 17c is limited to 15% with respect to 1 m 3 of the solidified soil, and the strength expression rate is not when water is not discharged. The amount that does not fall below 90% and the amount of the solidified material 16 added during the process of constructing the succeeding improved pile 17b on the trace of the blank portion 17c is 1.2 times the upper limit of the preceding improved pile 17a. As described above, the strength of the joint 20 at the boundary of the overlap portion 18 between the immediately preceding improved pile 17a and the subsequent improved pile 17b built on the trace of the blank portion 17c is increased.

請求項1記載の発明によれば、深層混合処理機の撹拌軸を回転させながら掘削刃で地盤を掘削し、注入管の先端から固化材を吐出し、撹拌翼で撹拌混合し、改良杭を造成し、撹拌軸を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭を構築する工程と、
直前の先行改良杭の固化前に、オーバーラップ部を有するように空打ち部を形成して固化材を拡散させる工程と、
空打ち部の跡に後行改良杭を構築する工程とからなるので、
空打ち部を形成して後行改良杭を打設する際、先行改良杭との芯がずれる等の支障をきたすことがなく、また、打ち継ぎ目地を境にせん断(ずれや回転)力が発生することのなく、打ち継ぎ目地の強度を上昇させることができる。
また、空打ち部を形成する工程時に固化材に代えて水を吐出して直前の先行改良杭のオーバーラップ部の固化材を拡散するようにしたので、オーバーラップ部の固化の進行を確実に抑えることができる。
さらに、水の吐出量は、最低限先行改良杭の構築時における固化材の量としたので、直前の先行改良杭のオーバーラップ部の固化材を押し出して水と置換され、固化の進行を抑えることができる。
According to the first aspect of the present invention, the ground is excavated with the excavating blade while rotating the stirring shaft of the deep mixing processor, the solidified material is discharged from the tip of the injection pipe, and the agitating blade is stirred and mixed. In the construction method of the joint joint which constructs and pulls out the stirring shaft, moves the deep mixing treatment machine so as to have an overlap part in the traveling direction and repeats the above operation to construct a continuous wall, etc.
A step of constructing a preceding improved pile using a stirring shaft having a plurality of axes in a direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile, a step of forming a blank portion so as to have an overlap portion and diffusing the solidified material,
Because it consists of the process of constructing a follow-up improved pile on the trace of the empty part,
When forming a follow-up improved pile by forming an empty portion, there is no hindrance such as misalignment with the preceding improved pile, and there is a shear (displacement and rotation) force at the joint joint. Without generating, it is possible to increase the strength of the joint.
In addition, since the solidified material of the overlapped portion of the immediately preceding improved pile was diffused by discharging water instead of the solidified material during the process of forming the blanking portion, the progress of solidification of the overlapped portion was ensured Can be suppressed.
In addition, since the amount of water discharged is the amount of solidified material at the time of construction of the advanced improvement pile at the minimum, the solidification material of the overlapped portion of the previous advancement improvement pile is pushed out and replaced with water, suppressing the progress of solidification be able to.

請求項2記載の発明によれば、深層混合処理機の撹拌軸を回転させながら掘削刃で地盤を掘削し、注入管の先端から固化材を吐出し、撹拌翼で撹拌混合し、改良杭を造成し、撹拌軸を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭を構築する工程と、
直前の先行改良杭の固化前に、オーバーラップ部を有するように空打ち部を形成して固化材を拡散させる工程と、
空打ち部の跡に後行改良杭を構築する工程とからなるので、
空打ち部を形成して後行改良杭を打設する際、先行改良杭との芯がずれる等の支障をきたすことがなく、また、打ち継ぎ目地を境にせん断(ずれや回転)力が発生することのなく、打ち継ぎ目地の強度を上昇させることができる。
また、空打ち部を形成する工程時に固化材に代えて水を吐出して直前の先行改良杭のオーバーラップ部の固化材を拡散するようにしたので、オーバーラップ部の固化の進行を確実に抑えることができる。
水の吐出量は、粘性土土壌の場合、固化処理土1m に対し15%を限度とし、強度発現率が水を吐出しない場合の90%を下回らない範囲としたので、東京湾粘土の地盤で最良の打ち継ぎ目地の施工方法を実施できる。
According to the invention of claim 2 , the ground is excavated with the excavating blade while rotating the agitation shaft of the deep mixing treatment machine, the solidified material is discharged from the tip of the injection pipe, and the agitation blade is agitated and mixed. In the construction method of the joint joint which constructs and pulls out the stirring shaft, moves the deep mixing treatment machine so as to have an overlap part in the traveling direction and repeats the above operation to construct a continuous wall, etc.
A step of constructing a preceding improved pile using a stirring shaft having a plurality of axes in a direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile, a step of forming a blank portion so as to have an overlap portion and diffusing the solidified material,
Because it consists of the process of constructing a follow-up improved pile on the trace of the empty part,
When forming a follow-up improved pile by forming an empty portion, there is no hindrance such as misalignment with the preceding improved pile, and there is a shear (displacement and rotation) force at the joint joint. Without generating, it is possible to increase the strength of the joint.
In addition, since the solidified material of the overlapped portion of the immediately preceding improved pile was diffused by discharging water instead of the solidified material during the process of forming the blanking portion, the progress of solidification of the overlapped portion was ensured Can be suppressed.
Discharge rate of the water in the case of cohesive soil soil, the limit of 15% based solidification soil 1 m 3, the strength expression rate was in the range of not less than 90% when no discharge of water, the Tokyo Bay Clay The best joint joint construction method can be implemented.

請求項3記載の発明によれば、深層混合処理機の撹拌軸を回転させながら掘削刃で地盤を掘削し、注入管の先端から固化材を吐出し、撹拌翼で撹拌混合し、改良杭を造成し、撹拌軸を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭を構築する工程と、
直前の先行改良杭の固化前に、オーバーラップ部を有するように空打ち部を形成して固化材を拡散させる工程と、
空打ち部の跡に後行改良杭を構築する工程とからなり、
前記空打ち部を形成する工程時に固化材に代えて水を吐出して直前の先行改良杭のオーバーラップ部を拡散するようにし、
水の吐出量は、最低限先行改良杭の構築時における固化材の量とし、水の吐出量は、粘性土土壌の場合、固化処理土1m に対し15%を限度とし、強度発現率が水を吐出しない場合の90%を下回らない範囲としたので、請求項1記載の発明の効果に加えて東京湾粘土の地盤で最良の打ち継ぎ目地の施工方法を実施できる。
According to the invention of claim 3 , the ground is excavated with the excavating blade while rotating the stirring shaft of the deep mixing processor, the solidified material is discharged from the tip of the injection pipe, and the agitating blade is stirred and mixed. In the construction method of the joint joint which constructs and pulls out the stirring shaft, moves the deep mixing treatment machine so as to have an overlap part in the traveling direction and repeats the above operation to construct a continuous wall, etc.
A step of constructing a preceding improved pile using a stirring shaft having a plurality of axes in a direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile, a step of forming a blank portion so as to have an overlap portion and diffusing the solidified material,
It consists of the process of constructing a follow-up improved pile on the trace of the empty part,
Instead of solidifying material in the process of forming the idle portion, water is discharged to diffuse the overlap portion of the immediately preceding improved pile,
The amount of water discharged is at least the amount of solidified material at the time of construction of the advanced improvement pile. In the case of clay soil, the amount of water discharged is limited to 15% with respect to 1 m 3 of solidified soil , and the strength expression rate is Since the range is set so as not to fall below 90% when water is not discharged, in addition to the effect of the invention according to claim 1, the best construction method for joint seams can be implemented on the ground of Tokyo Bay clay.

請求項4記載の発明によれば、深層混合処理機の撹拌軸を回転させながら掘削刃で地盤を掘削し、注入管の先端から固化材を吐出し、撹拌翼で撹拌混合し、改良杭を造成し、撹拌軸を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭を構築する工程と、
直前の先行改良杭の固化前に、オーバーラップ部を有するように空打ち部を形成して固化材を拡散させる工程と、
空打ち部の跡に後行改良杭を構築する工程とからなるので、
空打ち部を形成して後行改良杭を打設する際、先行改良杭との芯がずれる等の支障をきたすことがなく、また、打ち継ぎ目地を境にせん断(ずれや回転)力が発生することのなく、打ち継ぎ目地の強度を上昇させることができる。
また、前記空打ち部の跡に後行改良杭を構築する工程は、先行改良杭よりも固化材を割増したので、直前の先行改良杭と空打ち部の跡に構築した後行改良杭とのオーバーラップ部における境界の打ち継ぎ目地の強度を上昇させることができる。
According to invention of Claim 4 , excavating the ground with a drilling blade while rotating the stirring shaft of the deep mixing processor, discharging the solidified material from the tip of the injection pipe, stirring and mixing with the stirring blade, In the construction method of the joint joint which constructs and pulls out the stirring shaft, moves the deep mixing treatment machine so as to have an overlap part in the traveling direction and repeats the above operation to construct a continuous wall, etc.
A step of constructing a preceding improved pile using a stirring shaft having a plurality of axes in a direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile, a step of forming a blank portion so as to have an overlap portion and diffusing the solidified material,
Because it consists of the process of constructing a follow-up improved pile on the trace of the empty part,
When forming a follow-up improved pile by forming an empty portion, there is no hindrance such as misalignment with the preceding improved pile, and there is a shear (displacement and rotation) force at the joint joint. Without generating, it is possible to increase the strength of the joint.
In addition, since the process of constructing the succeeding improved pile on the trace of the blanking portion has increased the solidification material than the preceding improved pile, the succeeding improved pile constructed on the trace of the preceding preceding improved pile and the blanking portion and It is possible to increase the strength of the joint at the boundary in the overlap portion.

請求項5記載の発明によれば、請求項4記載の発明の効果に加えて、固化材の割増しは、先行改良杭の構築時の1.2倍を上限としたので、打ち継ぎ目地を設けた場合でも、打ち継ぎ目地なしの圧縮強さを得ることができる。
According to the invention described in claim 5 , in addition to the effect of the invention described in claim 4, the increase of the solidified material is limited to 1.2 times that at the time of construction of the preceding improved pile, so a joint joint is provided. Even in this case, it is possible to obtain a compressive strength without joints.

請求項6記載の発明によれば、深層混合処理機の撹拌軸を回転させながら掘削刃で地盤を掘削し、注入管の先端から固化材を吐出し、撹拌翼で撹拌混合し、改良杭を造成し、撹拌軸を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭を構築する工程と、
直前の先行改良杭の固化前に、オーバーラップ部を有するように空打ち部を形成して固化材を拡散させる工程と、
空打ち部の跡に後行改良杭を構築する工程とからなるので、
空打ち部を形成して後行改良杭を打設する際、先行改良杭との芯がずれる等の支障をきたすことがなく、また、打ち継ぎ目地を境にせん断(ずれや回転)力が発生することのなく、打ち継ぎ目地の強度を上昇させることができる。
また、前記空打ち部を形成する工程時に固化材に代えた水の吐出量は、粘性土土壌の場合、固化処理土1m に対し15%を限度とし、強度発現率が水を吐出しない場合の90%を下回らない範囲とし、かつ、空打ち部の跡に後行改良杭を構築する工程時に固化材を割増す量は、先行改良杭の構築時の1.2倍を上限として直前の先行改良杭と空打ち部の跡に構築した後行改良杭とのオーバーラップ部における境界の打ち継ぎ目地の強度を上昇させるようにしたので、東京湾粘土の地盤等において、直前の先行改良杭のオーバーラップ部の固化材を押し出して水と置換され、固化の進行を抑えることができる。しかも、打ち継ぎ目地を設けた場合でも、打ち継ぎ目地なしの圧縮強さを得ることができる。
According to the invention described in claim 6 , the ground is excavated with the excavating blade while rotating the stirring shaft of the deep mixing processor, the solidified material is discharged from the tip of the injection pipe, and the agitating blade is stirred and mixed. In the construction method of the joint joint which constructs and pulls out the stirring shaft, moves the deep mixing treatment machine so as to have an overlap part in the traveling direction and repeats the above operation to construct a continuous wall, etc.
A step of constructing a preceding improved pile using a stirring shaft having a plurality of axes in a direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile, a step of forming a blank portion so as to have an overlap portion and diffusing the solidified material,
Because it consists of the process of constructing a follow-up improved pile on the trace of the empty part,
When forming a follow-up improved pile by forming an empty portion, there is no hindrance such as misalignment with the preceding improved pile, and there is a shear (displacement and rotation) force at the joint joint. Without generating, it is possible to increase the strength of the joint.
In addition, in the case of cohesive soil, the amount of water discharged in place of the solidified material during the step of forming the idle portion is limited to 15% with respect to 1 m 3 of the solidified soil , and the strength expression rate does not discharge water. The amount of additional solidification material during the process of constructing a follow-up improved pile at the site of an unsettled portion is the upper limit of 1.2 times that of the preceding improved pile. The strength of the joint seam at the boundary of the overlap between the preceding improved pile and the succeeding improved pile built on the trace of the empty cast is increased. The solidified material in the overlap portion is extruded and replaced with water, and the progress of solidification can be suppressed. Moreover, even when a joint is provided, it is possible to obtain a compressive strength without a joint.

本発明による打ち継ぎ目地の施工方法の実施例1を示す工程図である。It is process drawing which shows Example 1 of the construction method of the joint joint by this invention. 一般的な4軸の深層混合処理機による深層混合処理工法の説明図である。It is explanatory drawing of the deep mixing process method by a general 4-axis deep mixing processor. 東京湾で採取した海成粘土の物性を表わす図である。It is a figure showing the physical property of marine clay collected in Tokyo Bay. 配合試験(1)の結果を表わす図である。It is a figure showing the result of a compounding test (1). 加水率と強度発現率のグラフである。It is a graph of a hydrolysis rate and an intensity expression rate. 配合試験(2)の結果を表わす図である。It is a figure showing the result of a compounding test (2). 圧縮強さの平均値とセメント添加量の関係を示すグラフである。It is a graph which shows the relationship between the average value of compressive strength, and cement addition amount. 打ち継ぎ目地を有する供試体の圧縮試験結果を表わす図である。It is a figure showing the compression test result of the test body which has a joint joint. 本発明の他の実施例を示すもので、(a)は、実施例2の説明図、(b)は、実施例3の説明図、(c)は、実施例3の説明図である。The other Example of this invention is shown, (a) is explanatory drawing of Example 2, (b) is explanatory drawing of Example 3, (c) is explanatory drawing of Example 3. FIG. 特許文献1に表された従来の深層混合処理工法の説明図である。It is explanatory drawing of the conventional deep-layer mixing processing method represented by patent document 1. FIG. 特許文献2に表された従来の深層混合処理工法の説明図である。It is explanatory drawing of the conventional deep-layer mixing processing method represented by patent document 2. FIG. 従来の工法の問題点の説明図である。It is explanatory drawing of the problem of the conventional construction method. 従来の深層混合処理工法の説明図である。It is explanatory drawing of the conventional deep-layer mixing processing method.

本発明打のち継ぎ目地の施工方法は、深層混合処理機の撹拌軸11を回転させながら掘削刃14で地盤19を掘削し、注入管15の先端から固化材16を吐出し、撹拌翼13で撹拌混合し、改良杭17を造成し、撹拌軸11を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部18を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸11を用いて先行改良杭17aを構築する工程と、
直前の先行改良杭17aの固化前に、オーバーラップ部18を有するように空打ち部17cを形成して固化材16を拡散させる工程と、
空打ち部17cの跡に後行改良杭17bを構築する工程と
からなる。
According to the construction method of the joint according to the present invention, the ground 19 is excavated by the excavating blade 14 while rotating the stirring shaft 11 of the deep mixing processor, the solidified material 16 is discharged from the tip of the injection pipe 15, and the stirring blade 13 is used. After stirring and mixing, the improved pile 17 is formed, and the stirring shaft 11 is pulled out, and then the deep mixing processing machine is moved so as to have the overlap portion 18 in the traveling direction, and the above operation is repeated to construct a continuous wall and the like. In the construction method of joint joints,
The step of constructing the preceding improved pile 17a using the stirring shaft 11 having a plurality of axes in the direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile 17a, a step of forming the blank portion 17c so as to have the overlap portion 18 and diffusing the solidified material 16,
And a step of constructing a follow-up improved pile 17b on the trace of the blank portion 17c.

空打ち部17cを形成する工程時に固化材16に代えて水を吐出して直前の先行改良杭17aのオーバーラップ部18を拡散する。
水の吐出量は、最低限先行改良杭17aの構築時における固化材16の量とする。
水の吐出量は、粘性土土壌の場合、固化処理土1mに対し15%を限度とし、強度発現率が水を吐出しない場合の90%を下回らない範囲とする。
Water is discharged instead of the solidified material 16 during the step of forming the blank portion 17c, and the overlap portion 18 of the immediately preceding advanced pile 17a is diffused.
The amount of water discharged is at least the amount of the solidified material 16 at the time of construction of the advance improvement pile 17a.
In the case of clay soil, the amount of water discharged is limited to 15% with respect to 1 m 3 of the solidified soil, and the strength expression rate is within a range not lower than 90% when water is not discharged.

空打ち部17cの跡に後行改良杭17bを構築する工程は、先行改良杭17aよりも固化材16を割増して直前の先行改良杭17aと空打ち部17cの跡に構築した後行改良杭17bとのオーバーラップ部18における境界の打ち継ぎ目地20の強度を上昇させる。
固化材16の割増しは、先行改良杭17aの構築時の1.2倍を上限とする。
The process of constructing the succeeding improved pile 17b on the trace of the blanking portion 17c is the subsequent improving pile constructed by adding the solidifying material 16 to the previous improved pile 17a and building the trace of the preceding precedent improved pile 17a and the blanking section 17c. The strength of the joint 20 at the boundary in the overlap portion 18 with 17b is increased.
The surplus of the solidifying material 16 is 1.2 times the upper limit when the preceding improved pile 17a is constructed.

空打ち部17cを形成する工程時に固化材16に代えた水の吐出量は、粘性土土壌の場合、固化処理土1mに対し15%を限度とし、強度発現率が水を吐出しない場合の90%を下回らない範囲とし、かつ、空打ち部17cの跡に後行改良杭17bを構築する工程時に固化材16を割増す量は、先行改良杭17aの構築時の20%を上限として直前の先行改良杭17aと空打ち部17cの跡に構築した後行改良杭17bとのオーバーラップ部18における境界の打ち継ぎ目地20の強度を上昇させる。 In the case of cohesive soil, the amount of water discharged in place of the solidifying material 16 during the step of forming the empty portion 17c is limited to 15% with respect to 1 m 3 of the solidified soil, and the strength expression rate is not when water is not discharged. The amount that does not fall below 90% and the amount of the solidified material 16 added during the process of constructing the succeeding improved pile 17b on the trace of the blanked portion 17c is immediately before the upper limit of 20% when the preceding improved pile 17a is constructed. The strength of the joint 20 at the boundary at the overlap portion 18 between the preceding improved pile 17a and the trailing improved pile 17b constructed on the trace of the blanking portion 17c is increased.

本発明による実施例1では、図2に示すような縦方向(進行方向に直交する方向)に2軸、横方向(進行方向と同じ方向)に2軸の4軸の深層混合処理機を用いて行う本発明の打ち継ぎ目地の施工方法を説明する。
図2において、
(a):改良しようとする地盤19に、撹拌軸11の先端に掘削刃14を備えた深層混合処理機を直立させる。
(b):撹拌軸11を電動モータ12で回転させながら掘削刃14で地盤19を掘削し、注入管15の先端から固化材16を吐出し、撹拌翼13で地盤19を撹拌しながら固化材16を地盤19に混合する。
(c):所定の深さまで改良杭17を造成する。
(d):撹拌軸11を逆回転して引き抜く。
(e):引き抜いた後、深層混合処理機をオーバーラップ部18を見込んで移動して上記動作を繰り返して連続する壁等を構築する
In Example 1 according to the present invention, a four-axis deep mixing processor having two axes in the vertical direction (direction orthogonal to the traveling direction) and two axes in the lateral direction (the same direction as the traveling direction) as shown in FIG. 2 is used. A method for constructing the joint according to the present invention will be described.
In FIG.
(A): A deep-mixing processing machine having an excavating blade 14 at the tip of the stirring shaft 11 is placed upright on the ground 19 to be improved.
(B): The ground 19 is excavated by the excavating blade 14 while the stirring shaft 11 is rotated by the electric motor 12, the solidified material 16 is discharged from the tip of the injection pipe 15, and the solidified material is stirred while the ground 19 is stirred by the stirring blade 13. 16 is mixed with the ground 19.
(C): The improved pile 17 is created to a predetermined depth.
(D): The stirring shaft 11 is reversely rotated and pulled out.
(E): After pulling out, the deep layer processing machine is moved in anticipation of the overlap portion 18 and the above operation is repeated to construct a continuous wall or the like.

前述したように、この深層混合処理工法において、先行改良杭17aと後行改良杭17bを確実に一体化するためには、固化材16の水和反応が進行する前にオーバーラップ部18が生じるように移動して施工し、順次連結して改良杭17の壁を構築することが要求される。
オーバーラップ部18が生じるように構築するには、先行改良杭17aを構築してから後行改良杭17bを構築するまでの待機時間(接合間隔)は、可能な限り短くする必要がある。具体的には、この接合間隔を通常は、24時間以内とすることが好ましく、最大でも48時間以内として管理されている。
As described above, in this deep mixed processing method, the overlap portion 18 is generated before the hydration reaction of the solidified material 16 proceeds in order to reliably integrate the preceding improved pile 17a and the subsequent improved pile 17b. Therefore, it is required to construct the wall of the improved pile 17 by sequentially connecting and constructing.
In order to construct so that the overlap portion 18 is generated, it is necessary to shorten the standby time (joining interval) from the construction of the preceding improved pile 17a to the construction of the subsequent improved pile 17b as much as possible. Specifically, this joining interval is usually preferably within 24 hours, and is managed within 48 hours at the maximum.

待機時間(接合間隔)が管理時間を超える可能性がある場合における本発明の打ち継ぎ目地の施工方法を図1に基き説明する。
図1の(I)において、4軸の深層混合処理機10により先行改良杭17aが打設形成されたものとし、この後、台風の接近などで、先行改良杭17aに連続する後行改良杭17bの構築まで管理時間を超える恐れがあるものとする。このような場合、連続する後行の位置に点線で示すような空打ち部17cを形成するための位置決めをする。このとき、改良杭17は4本の円柱の連続として構築されるので、先行と後行の改良杭17の間に空洞が生じないようなオーバーラップ部18のできる位置とする。
The joint joint construction method of the present invention in the case where the standby time (joining interval) may exceed the management time will be described with reference to FIG.
In FIG. 1 (I), it is assumed that the advanced improvement pile 17a is driven and formed by the four-axis deep mixing processor 10, and then the subsequent improvement pile that continues to the advance improvement pile 17a due to the approach of a typhoon or the like. It is assumed that the management time may be exceeded until the construction of 17b. In such a case, positioning is performed for forming the blank portion 17c as indicated by the dotted line at the succeeding subsequent position. At this time, since the improved pile 17 is constructed as a series of four cylinders, the overlapped portion 18 is formed so that no cavity is formed between the preceding and subsequent improved piles 17.

(II)において、前工程で位置決めされた場所に固化材16を注入せずに撹拌軸11を回転させて先行のオーバーラップ部18と一緒に地盤を拡散(空打ち)して空打ち部17cとし、固化材16を希釈化させてオーバーラップ部18部分の固形化を防止する。この空打ち時に固化材16の代わりに水を吐出する。水を吐出する注入管15は、オーバーラップ部18を拡散するための注入管15b1と注入管15b2だけとし、オーバーラップ部18を含まない注入管15b3と注入管15b4は、水の吐出を行わない。水の吐出は、深層混合処理機の貫入のときだけ行い、引き抜き時には必要がない。水の吐出は、先行して打設されたセメントスラリーを押し出し、水で置換することを目的としているため、水の吐出量は、セメントスラリーと同量を最低吐出量とする。ただし、粘性土の地盤19の場合、吐出水は、粘性土と混合されるだけで排水、置換されない。吐出水の撹拌混合によるセメントスラリーの希釈効果に期待することになる。このとき、吐出水の量を増やし過ぎると、粘性土が必要以上に乱され、後行改良杭17bを施工する際に、必要な固化強度が得られなくなる。従って、粘性土の場合は、吐出水量は、処理土1mに対して体積比で15%を限度とする。詳細は、後述する。 In (II), the stirrer 11 is rotated without pouring the solidified material 16 into the position positioned in the previous step, and the ground is diffused (empty) together with the preceding overlap portion 18 to idle the portion 17c. Then, the solidifying material 16 is diluted to prevent the overlapping portion 18 from being solidified. Water is discharged instead of the solidified material 16 at the time of this idle driving. The injection tube 15 that discharges water includes only the injection tube 15b1 and the injection tube 15b2 for diffusing the overlap portion 18, and the injection tube 15b3 and the injection tube 15b4 that do not include the overlap portion 18 do not discharge water. . The water is discharged only when the deep-mixing machine is penetrated, and is not necessary at the time of drawing. The discharge of water is intended to extrude the previously placed cement slurry and replace it with water. Therefore, the discharge amount of water is the same as that of the cement slurry, and the minimum discharge amount. However, in the case of the soil 19 of the clay soil, the discharged water is only mixed with the clay soil and is not drained or replaced. It is expected to dilute the cement slurry by stirring and mixing the discharged water. At this time, if the amount of discharged water is excessively increased, the viscous soil is disturbed more than necessary, and the necessary solidification strength cannot be obtained when the subsequent improved pile 17b is constructed. Therefore, in the case of cohesive soil, the amount of discharged water is limited to 15% in volume ratio with respect to 1 m 3 of treated soil. Details will be described later.

(III)空打ち部17cを形成すると、オーバーラップ部18部分が弧状に切り取られた先行改良杭17aが得られる。 (III) When the blanking portion 17c is formed, the preceding improved pile 17a in which the overlap portion 18 is cut out in an arc shape is obtained.

(IV)空打ち部17cの箇所への後行改良杭17bの施工は、先行改良杭17aと同様手順で打設する。このとき、固化材16の添加量は、質量比で1.2倍を上限とした範囲で割り増す。この後行改良杭17bの打設が終了すると、2箇所に円弧状の凹部を有する打ち継ぎ目地20が形成される。打ち継ぎ目地20には、進行方向に対して直交する位置に2箇所の円弧状の凹部ができるが、隣接する撹拌軸11の回転方向が互いに逆方向であるから、打ち継ぎ目地20において、図12(a)(b)で示したようなせん断力発生や回転軸ずれなどによる不具合は発生しない。固化材16の割増の根拠については、後述する。 (IV) Construction of the follow-up improved pile 17b at the spot of the blanking portion 17c is performed in the same manner as the preceding improved pile 17a. At this time, the addition amount of the solidifying material 16 is increased in a range in which the mass ratio is 1.2 times the upper limit. When the placement of the subsequent improved pile 17b is completed, joints 20 having arc-shaped concave portions at two locations are formed. The joint 20 has two arc-shaped concave portions at positions orthogonal to the traveling direction. However, since the rotation directions of the adjacent stirring shafts 11 are opposite to each other, Problems due to the generation of shearing force and rotational axis deviation as shown in 12 (a) and (b) do not occur. The basis for the increase in the solidifying material 16 will be described later.

前記図1(II)において、粘性土の場合の吐出水量は、処理土1mに対して体積比で15%を限度とした理由は、次の通りである。
東京湾で採取した海成粘土(東京湾粘土)の物性は、図3に示す通りである。
配合試験(1)は、図1の東京湾粘土の含水比をw=128.6%(=液性限界)に調整したものを母材料として母材量1mに対してセメントを粉体で150kg/mの割合で添加して直径5cm、高さ10cmの固化処理土供試体を作成した。これをケース1とし、このケース1に対して外割体積比で5%の水を加えたものをケース2、以下同様に、ケース1に対して外割体積比で10%,15%、20%、30%の水を加えたものをそれぞれケース3,4,5,6とした。各ケースで作成した固化処理土供試体は、材令28日で圧縮試験を実施して圧縮強さを求めた。図4は、その試験結果である。
図4において、強度発現率とは、各ケースの一軸圧縮強さの値を、ケース1の圧縮強さの値で除して百分率とした値である。
In FIG. 1 (II), the reason why the amount of discharged water in the case of cohesive soil is limited to 15% by volume with respect to 1 m 3 of treated soil is as follows.
The physical properties of marine clay (Tokyo Bay clay) collected in Tokyo Bay are as shown in FIG.
In the blending test (1), the water content of the Tokyo Bay clay in FIG. 1 was adjusted to w = 18.6% (= liquid limit), and the cement was powdered with respect to the base material amount of 1 m 3 as the base material. A solidified soil specimen having a diameter of 5 cm and a height of 10 cm was prepared by adding 150 kg / m 3 . This is referred to as Case 1, and 5% water is added to Case 1 in an external volume ratio. Case 2 is the same, and 10%, 15%, 20 %, 30% water was added to cases 3, 4, 5, and 6, respectively. The solidified soil specimens prepared in each case were subjected to a compression test on the 28th day of the material age to determine the compression strength. FIG. 4 shows the test results.
In FIG. 4, the strength expression rate is a value obtained by dividing the uniaxial compressive strength value of each case by the compressive strength value of Case 1 as a percentage.

図5は、図4に表した加水率と強度発現率の関係を表わしたグラフである。
この図5から加水率が15%で強度発現率は90%であり、これより加水率が増すと急激に強度発現率が低下する傾向にあり、従って、東京湾粘土の場合、加水率の上限値を15%とした。逆に、母材にもよるが、強度発現率は90%以下にならない範囲で加水率の上限値を設定することが望ましい。
FIG. 5 is a graph showing the relationship between the water addition rate and the strength expression rate shown in FIG.
From FIG. 5, the water development rate is 15% and the strength expression rate is 90%, and when the water addition rate is increased, the strength development rate tends to decrease sharply. The value was 15%. On the contrary, although depending on the base material, it is desirable to set the upper limit of the water addition rate within a range where the strength expression rate does not become 90% or less.

前記図1(IV)において、固化材16の添加量は、質量比で1.2倍を上限とした範囲で割り増すとした理由は、次の通りである。
東京湾で採取した海成粘土(東京湾粘土)の物性は、図3に示す通りである。
配合試験(2)では、図1の東京湾粘土の含水比をw=128.6%(=液性限界)に調整したものを母材料として母材量1mに対し、セメント添加量を120、150、180、210、240kg/mの5水準として直径5cm、高さ10cmの固化処理土供試体を作成し、材令28日において一軸圧縮試験を実施し、圧縮強さとセメント添加量の関係を求めた。図6は、その試験結果である。
In FIG. 1 (IV), the reason why the addition amount of the solidifying material 16 is increased within a range where the mass ratio is 1.2 times the upper limit is as follows.
The physical properties of marine clay (Tokyo Bay clay) collected in Tokyo Bay are as shown in FIG.
In the blending test (2), the water content of the Tokyo Bay clay shown in FIG. 1 was adjusted to w = 18.6% (= liquid limit), and the amount of cement added was 120 to 1 m 3 of the base material. , 150, 180, 210, 240 kg / m 3 , 5 cm in diameter and 10 cm in height solidified soil specimens were prepared, and a uniaxial compression test was conducted on the 28th day of the material age. Sought a relationship. FIG. 6 shows the test results.

図6に示す圧縮強さの平均値とセメント添加量の関係を図7に示す。この図7により、セメント添加量xと圧縮強さyの関係は、
y=23.689x−2141.6 (1)
と求めることができる。この図7からセメント添加量xと圧縮強さyの関係は略正比例していることが分かる。
FIG. 7 shows the relationship between the average value of compressive strength shown in FIG. 6 and the amount of cement added. From FIG. 7, the relationship between the cement addition amount x and the compressive strength y is
y = 23.689x-2141.6 (1)
It can be asked. It can be seen from FIG. 7 that the relationship between the cement addition amount x and the compressive strength y is substantially directly proportional.

配合試験(3)を実施した。この配合試験(3)は、配合試験(2)における180kg/mのケースについて、本発明の打ち継ぎ目地の施工方法を模擬して人為的に打ち継ぎ目地20を設けた直径5cm、高さ10cmの固化処理土供試体を作成した。このとき、待機時間(打ち継ぎ間隔)を0,3,5,7,28日の5水準として5ケース分作成した。この供試体を用いた圧縮強度試験により材令28日及び91日について、待機時間(打ち継ぎ間隔)と圧縮試験の関係を調べた結果を図8に示す。 A blending test (3) was conducted. In this blending test (3), the case of 180 kg / m 3 in the blending test (2) was simulated with the joint joint construction method of the present invention, and the joint joint 20 was artificially provided with a diameter of 5 cm and a height. A 10 cm solidified soil specimen was prepared. At this time, five cases were created with the standby time (joining interval) set to five levels of 0, 3, 5, 7, and 28. FIG. 8 shows the results of investigating the relationship between the waiting time (joining interval) and the compression test for the material age 28 days and 91 days by the compression strength test using this specimen.

この図8において、強度比とは、各ケースの平均の圧縮強さを、ケース1(打ち継ぎ目地20なし)の平均圧縮強さで除した値である。即ち、打ち継ぎ目地20の有無による強度発現率を表わしている。この結果より、打ち継ぎ目地20があると、圧縮強さは、0.72〜1.00倍の間で低減することが明らかになった。そこで、打ち継ぎ目地20を設ける場合は、圧縮強さが低減することを見越した圧縮強さを目指し、セメント添加量を割り増すことが必要である。ケース1の圧縮強さを強度比で除した値を目標強度とする。
次に、前記式(1)を用いて目標強度に対応するセメント添加量を求める。このセメント添加量をケース1のセメント添加量180kg/mで除した値がセメント割増率となる。図8に示すように、セメント割増率は、1.00〜1.17となった。このことから打ち継ぎ目地20を設ける際は、安全性を考慮して、最も圧縮強さが低減するケースに合わせて、セメント添加量を1.2倍(≒1.17)とすることが望ましい。
In FIG. 8, the strength ratio is a value obtained by dividing the average compressive strength of each case by the average compressive strength of case 1 (without joint 20). That is, the strength expression rate with or without the joint 20 is shown. From this result, it became clear that the compressive strength decreases between 0.72 and 1.00 times when the joint 20 is present. Therefore, when the joint 20 is provided, it is necessary to increase the amount of cement added with the aim of compressive strength in anticipation of reducing the compressive strength. A value obtained by dividing the compressive strength of case 1 by the strength ratio is defined as a target strength.
Next, the amount of cement added corresponding to the target strength is obtained using the above formula (1). A value obtained by dividing the cement addition amount by the cement addition amount of 180 kg / m 3 in case 1 is the cement extra rate. As shown in FIG. 8, the cement premium rate was 1.00 to 1.17. Therefore, when providing the joint 20 for the joint, it is desirable that the cement addition amount is 1.2 times (≈1.17) in consideration of safety in accordance with the case where the compressive strength is most reduced. .

前記実施例1では、図2に示すような縦方向(進行方向に直交する方向)に2軸、横方向(進行方向と同じ方向)に2軸の4軸の深層混合処理機を用いた本発明の打ち継ぎ目地の施工方法を説明した。
しかし、これに限られるものではなく、本発明は、打ち継ぎ目地20において、図12(a)(b)で示したようなせん断力発生や回転軸ずれなどによる不具合が発生しないようにするため、進行方向に対して直交する方向に2箇所以上の円弧状の凹部ができるような深層混合処理機10が用いられる。このような処理機を用いると、隣接する撹拌軸11の回転方向が互いに逆方向であるから、縦方向(進行方向に直交する方向)に複数軸であればよい。したがって、横方向(進行方向と同じ方向)は単軸であっても複数軸であってもよい。
In the first embodiment, a book using a four-axis deep mixing processor having two axes in the longitudinal direction (direction orthogonal to the traveling direction) and two axes in the lateral direction (the same direction as the traveling direction) as shown in FIG. The construction method of the joint joint of the invention has been described.
However, the present invention is not limited to this, and the present invention is to prevent the occurrence of problems due to the generation of shearing force and rotational axis deviation as shown in FIGS. 12A and 12B in the joint 20. A deep mixing treatment machine 10 is used in which two or more arc-shaped concave portions are formed in a direction orthogonal to the traveling direction. When such a processing machine is used, the rotation directions of the adjacent stirring shafts 11 are opposite to each other, and therefore, it is sufficient that the number of axes is plural in the vertical direction (direction orthogonal to the traveling direction). Accordingly, the lateral direction (the same direction as the traveling direction) may be a single axis or a plurality of axes.

具体的には、図9(a)は、縦方向(進行方向に直交する方向)に2軸、横方向(進行方向と同じ方向)に1軸の2軸の深層混合処理機10を用いた例を示しており、工程Iでは、先行改良杭17aを形成した後、水を吐出しながら空打ち部17cを形成しておき、工程IIにおいて、固化材16の添加量を割り増しして後行改良杭17bを打設する。   Specifically, FIG. 9A uses a biaxial deep mixing processor 10 that has two axes in the longitudinal direction (direction orthogonal to the traveling direction) and one axis in the lateral direction (the same direction as the traveling direction). An example is shown, and in the process I, the advance improvement pile 17a is formed, and then the blanking portion 17c is formed while discharging water, and in the process II, the addition amount of the solidifying material 16 is increased and the subsequent process is performed. An improved pile 17b is placed.

図9(b)は、縦方向(進行方向に直交する方向)に3軸、横方向(進行方向と同じ方向)に1軸の3軸の深層混合処理機10を用いた例を示しており、工程Iでは、先行改良杭17aを形成した後、水を吐出しながら空打ち部17cを形成しておき、工程IIにおいて、固化材16の添加量を割り増しして後行改良杭17bを打設する。   FIG. 9B shows an example in which a three-axis deep mixing processor 10 having three axes in the vertical direction (direction orthogonal to the traveling direction) and one axis in the horizontal direction (the same direction as the traveling direction) is used. In Step I, after forming the advancement improvement pile 17a, the blanking portion 17c is formed while discharging water, and in Step II, the added amount of the solidifying material 16 is increased and the subsequent improvement pile 17b is driven. Set up.

図9(c)は、縦方向(進行方向に直交する方向)に2軸、横方向(進行方向と同じ方向)に4軸の8軸の深層混合処理機10を用いた例を示しており、工程Iでは、先行改良杭17aを形成した後、水を吐出しながら空打ち部17cを形成しておき、工程IIにおいて、固化材16の添加量を割り増しして後行改良杭17bを打設する。   FIG. 9C shows an example in which an eight-axis deep mixing processor 10 having two axes in the vertical direction (direction orthogonal to the traveling direction) and four axes in the horizontal direction (the same direction as the traveling direction) is used. In Step I, after forming the advancement improvement pile 17a, the blanking portion 17c is formed while discharging water, and in Step II, the added amount of the solidifying material 16 is increased and the subsequent improvement pile 17b is driven. Set up.

以上の実施例以外でも、進行方向に対して直交する方向に2箇所以上の円弧状の凹部ができるようにすればよく、横方向(進行方向と同じ方向)の軸の数は単軸であっても複数軸であってもよい。   In addition to the embodiments described above, it is only necessary to form two or more arc-shaped recesses in the direction orthogonal to the traveling direction, and the number of axes in the lateral direction (the same direction as the traveling direction) is uniaxial. Or a plurality of axes may be used.

10…深層混合処理機、11…撹拌軸、12…電動モータ、13…撹拌翼、14…切削刃、15…注入管、16…固化材、17…改良杭、17a…先行改良杭、17b…後行改良杭、17c…空打ち部、18…オーバーラップ部、19…地盤、20…打ち継ぎ目地、21…固化改良材。   DESCRIPTION OF SYMBOLS 10 ... Deep mixing processing machine, 11 ... Stirring shaft, 12 ... Electric motor, 13 ... Stirring blade, 14 ... Cutting blade, 15 ... Injection pipe, 16 ... Solidification material, 17 ... Improvement pile, 17a ... Advance improvement pile, 17b ... Subsequent improvement pile, 17c ... empty casting part, 18 ... overlap part, 19 ... ground, 20 ... joint joint, 21 ... solidification improvement material.

Claims (6)

深層混合処理機の撹拌軸を回転させながら掘削刃で地盤を掘削し、注入管の先端から固化材を吐出し、撹拌翼で撹拌混合し、改良杭を造成し、撹拌軸を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭を構築する工程と、
直前の先行改良杭の固化前に、オーバーラップ部を有するように空打ち部を形成して固化材を拡散させる工程と、
空打ち部の跡に後行改良杭を構築する工程とからなり、
前記空打ち部を形成する工程時に固化材に代えて水を吐出して直前の先行改良杭のオーバーラップ部を拡散するようにし、
水の吐出量は、最低限先行改良杭の構築時における固化材の量としたことを特徴とする打ち継ぎ目地の施工方法。
Excavate the ground with a drilling blade while rotating the stirring shaft of the deep mixing treatment machine, discharge the solidified material from the tip of the injection pipe, stir and mix with the stirring blade, create an improved pile, pull out the stirring shaft, In the construction method of the joint joint that moves the deep mixing treatment machine so as to have an overlap portion in the traveling direction and constructs a continuous wall by repeating the above operation,
A step of constructing a preceding improved pile using a stirring shaft having a plurality of axes in a direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile, a step of forming a blank portion so as to have an overlap portion and diffusing the solidified material,
Ri Do and a step of constructing a trailing improved pile remains idle driving portion,
Instead of solidifying material in the process of forming the idle portion, water is discharged to diffuse the overlap portion of the immediately preceding improved pile,
A joint joint construction method characterized in that the amount of water discharged is at least the amount of solidified material at the time of construction of the advanced improvement pile .
深層混合処理機の撹拌軸を回転させながら掘削刃で地盤を掘削し、注入管の先端から固化材を吐出し、撹拌翼で撹拌混合し、改良杭を造成し、撹拌軸を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭を構築する工程と、
直前の先行改良杭の固化前に、オーバーラップ部を有するように空打ち部を形成して固化材を拡散させる工程と、
空打ち部の跡に後行改良杭を構築する工程とからなり、
前記空打ち部を形成する工程時に固化材に代えて水を吐出して直前の先行改良杭のオーバーラップ部を拡散するようにし、
水の吐出量は、粘性土土壌の場合、固化処理土1m に対し15%を限度とし、強度発現率が水を吐出しない場合の90%を下回らない範囲としたことを特徴とする打ち継ぎ目地の施工方法。
Excavate the ground with a drilling blade while rotating the stirring shaft of the deep mixing treatment machine, discharge the solidified material from the tip of the injection pipe, stir and mix with the stirring blade, create an improved pile, pull out the stirring shaft, In the construction method of the joint joint that moves the deep mixing treatment machine so as to have an overlap portion in the traveling direction and constructs a continuous wall by repeating the above operation,
A step of constructing a preceding improved pile using a stirring shaft having a plurality of axes in a direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile, a step of forming a blank portion so as to have an overlap portion and diffusing the solidified material,
It consists of the process of constructing a follow-up improved pile on the trace of the empty part,
Instead of solidifying material in the process of forming the idle portion, water is discharged to diffuse the overlap portion of the immediately preceding improved pile,
In the case of clay soil, the amount of water discharged is limited to 15% with respect to 1 m 3 of the solidified soil, and the joint strength is characterized in that the strength expression rate does not fall below 90% when water is not discharged. Ground construction method.
深層混合処理機の撹拌軸を回転させながら掘削刃で地盤を掘削し、注入管の先端から固化材を吐出し、撹拌翼で撹拌混合し、改良杭を造成し、撹拌軸を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭を構築する工程と、
直前の先行改良杭の固化前に、オーバーラップ部を有するように空打ち部を形成して固化材を拡散させる工程と、
空打ち部の跡に後行改良杭を構築する工程とからなり、
前記空打ち部を形成する工程時に固化材に代えて水を吐出して直前の先行改良杭のオーバーラップ部を拡散するようにし、
水の吐出量は、最低限先行改良杭の構築時における固化材の量とし、
水の吐出量は、粘性土土壌の場合、固化処理土1m に対し15%を限度とし、強度発現率が水を吐出しない場合の90%を下回らない範囲としたことを特徴とする打ち継ぎ目地の施工方法。
Excavate the ground with a drilling blade while rotating the stirring shaft of the deep mixing treatment machine, discharge the solidified material from the tip of the injection pipe, stir and mix with the stirring blade, create an improved pile, pull out the stirring shaft, In the construction method of the joint joint that moves the deep mixing treatment machine so as to have an overlap portion in the traveling direction and constructs a continuous wall by repeating the above operation,
A step of constructing a preceding improved pile using a stirring shaft having a plurality of axes in a direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile, a step of forming a blank portion so as to have an overlap portion and diffusing the solidified material,
It consists of the process of constructing a follow-up improved pile on the trace of the empty part,
Instead of solidifying material in the process of forming the idle portion, water is discharged to diffuse the overlap portion of the immediately preceding improved pile,
The amount of water discharged is the amount of solidified material at the time of construction of the advanced improvement pile at the minimum,
In the case of clay soil, the amount of water discharged is limited to 15% with respect to 1 m 3 of the solidified soil, and the joint strength is characterized in that the strength expression rate does not fall below 90% when water is not discharged. Ground construction method.
深層混合処理機の撹拌軸を回転させながら掘削刃で地盤を掘削し、注入管の先端から固化材を吐出し、撹拌翼で撹拌混合し、改良杭を造成し、撹拌軸を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭を構築する工程と、
直前の先行改良杭の固化前に、オーバーラップ部を有するように空打ち部を形成して固化材を拡散させる工程と、
空打ち部の跡に後行改良杭を構築する工程とからなり、
前記空打ち部の跡に後行改良杭を構築する工程は、先行改良杭よりも固化材を割増して直前の先行改良杭と空打ち部の跡に構築した後行改良杭とのオーバーラップ部における境界の打ち継ぎ目地の強度を上昇させるようにしたことを特徴とする打ち継ぎ目地の施工方法。
Excavate the ground with a drilling blade while rotating the stirring shaft of the deep mixing treatment machine, discharge the solidified material from the tip of the injection pipe, stir and mix with the stirring blade, create an improved pile, pull out the stirring shaft, In the construction method of the joint joint that moves the deep mixing treatment machine so as to have an overlap portion in the traveling direction and constructs a continuous wall by repeating the above operation,
A step of constructing a preceding improved pile using a stirring shaft having a plurality of axes in a direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile, a step of forming a blank portion so as to have an overlap portion and diffusing the solidified material,
It consists of the process of constructing a follow-up improved pile on the trace of the empty part,
The process of constructing a follow-up improved pile on the trace of the blanked portion is an overlap portion between the preceding improved pile and the follow-up improved pile constructed on the trace of the blanked portion by increasing the solidification material more than the preceding improved pile. A joint joint construction method characterized by increasing the strength of the joint joint at the boundary .
固化材の割増しは、先行改良杭の構築時の1.2倍を上限としたことを特徴とする請求項記載の打ち継ぎ目地の施工方法。 5. The method for constructing joints according to claim 4 , wherein the additional amount of the solidifying material is set to 1.2 times the upper limit when the preceding improved pile is constructed. 深層混合処理機の撹拌軸を回転させながら掘削刃で地盤を掘削し、注入管の先端から固化材を吐出し、撹拌翼で撹拌混合し、改良杭を造成し、撹拌軸を引き抜いた後、深層混合処理機を進行方向にオーバーラップ部を有するように移動して上記動作を繰り返して連続する壁等を構築する打ち継ぎ目地の施工方法において、
連続構築する進行方向と直交する方向に複数軸を有する撹拌軸を用いて先行改良杭を構築する工程と、
直前の先行改良杭の固化前に、オーバーラップ部を有するように空打ち部を形成して固化材を拡散させる工程と、
空打ち部の跡に後行改良杭を構築する工程とからなり、
前記空打ち部を形成する工程時に固化材に代えた水の吐出量は、粘性土土壌の場合、固化処理土1m に対し15%を限度とし、強度発現率が水を吐出しない場合の90%を下回らない範囲とし、かつ、空打ち部の跡に後行改良杭を構築する工程時に固化材を割増す量は、先行改良杭の構築時の1.2倍を上限として直前の先行改良杭と空打ち部の跡に構築した後行改良杭とのオーバーラップ部における境界の打ち継ぎ目地の強度を上昇させるようにしたことを特徴とする打ち継ぎ目地の施工方法。
Excavate the ground with a drilling blade while rotating the stirring shaft of the deep mixing treatment machine, discharge the solidified material from the tip of the injection pipe, stir and mix with the stirring blade, create an improved pile, pull out the stirring shaft, In the construction method of the joint joint that moves the deep mixing treatment machine so as to have an overlap portion in the traveling direction and constructs a continuous wall by repeating the above operation,
A step of constructing a preceding improved pile using a stirring shaft having a plurality of axes in a direction orthogonal to the direction of continuous construction;
Before solidifying the immediately preceding advanced improvement pile, a step of forming a blank portion so as to have an overlap portion and diffusing the solidified material,
It consists of the process of constructing a follow-up improved pile on the trace of the empty part,
In the case of cohesive soil, the amount of water discharged in place of the solidified material during the step of forming the empty portion is limited to 15% with respect to 1 m 3 of the solidified soil , and the strength expression rate is 90 when water is not discharged. %, And the amount of additional solidification material during the process of constructing a follow-up improved pile at the site of an empty cast part is 1.2 times the upper limit of the preceding improved pile as the upper limit. A joint joint construction method characterized in that the strength of the joint joint at the boundary in the overlap part between the pile and the follow-up improved pile built on the trace of the blank joint part is increased .
JP2014183650A 2014-09-09 2014-09-09 Construction method for joints Active JP5755786B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014183650A JP5755786B1 (en) 2014-09-09 2014-09-09 Construction method for joints

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014183650A JP5755786B1 (en) 2014-09-09 2014-09-09 Construction method for joints

Publications (2)

Publication Number Publication Date
JP5755786B1 true JP5755786B1 (en) 2015-07-29
JP2016056581A JP2016056581A (en) 2016-04-21

Family

ID=53759611

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014183650A Active JP5755786B1 (en) 2014-09-09 2014-09-09 Construction method for joints

Country Status (1)

Country Link
JP (1) JP5755786B1 (en)

Also Published As

Publication number Publication date
JP2016056581A (en) 2016-04-21

Similar Documents

Publication Publication Date Title
JP2007162337A (en) Soil improving apparatus and liquefaction preventing method
JP5755786B1 (en) Construction method for joints
JP2000073354A (en) Preparating method of ground improving body and preparating method of continuous walls
JP2012246730A (en) Method for constructing earth retaining wall
JP5281213B1 (en) Core material and soil cement continuous wall method using the same
JP4796197B2 (en) Ground improvement body construction apparatus and ground improvement body construction method
JP3158053U (en) Ground improvement body construction equipment
JP2014066010A (en) Method of ground improvement around pile head
JP2008111240A (en) Method of constructing underground wall
CN103939020B (en) A kind of antiwind drilling bit of deep submerged agitation pile
JP4964018B2 (en) Ground improvement method
JP5759151B2 (en) Displacement-reducing ground improvement method
JPH07103550B2 (en) Pile or continuous wall and its construction method
JP6724200B1 (en) Excavator
JPH06136743A (en) Underground construction method for development of wall body and its device
JP4836680B2 (en) Reinforcement method of existing revetment structure by mechanical mixing deep mixing method
JP2003213679A (en) Construction method of pile hole, excavating rod and excavating head
JP7231273B1 (en) ground improvement method
JP2014047482A (en) Ground improvement device, surplus soil discharge inhibitor of ground improvement device, and ground improvement method
JP2008057254A (en) Soil improving apparatus
JP2002275885A (en) Earth retaining construction method using steel pipe, and device thereof
KR20160109395A (en) Agitating road for excavating using soil earth cement mixing method and mixing agitator using the same
JPH06136741A (en) Ground improving method and its device
JP2008308900A (en) Device and method for forming underground pile
JP2010255381A (en) Soil improving apparatus and soil improving machine equipped with the same

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150507

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150527

R150 Certificate of patent or registration of utility model

Ref document number: 5755786

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250