JP5705031B2 - Buried pipe reconstruction method - Google Patents

Buried pipe reconstruction method Download PDF

Info

Publication number
JP5705031B2
JP5705031B2 JP2011123317A JP2011123317A JP5705031B2 JP 5705031 B2 JP5705031 B2 JP 5705031B2 JP 2011123317 A JP2011123317 A JP 2011123317A JP 2011123317 A JP2011123317 A JP 2011123317A JP 5705031 B2 JP5705031 B2 JP 5705031B2
Authority
JP
Japan
Prior art keywords
existing concrete
pipe
steel joint
crushing
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2011123317A
Other languages
Japanese (ja)
Other versions
JP2012251330A (en
Inventor
蒲田洋
Original Assignee
株式会社推研
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社推研 filed Critical 株式会社推研
Priority to JP2011123317A priority Critical patent/JP5705031B2/en
Publication of JP2012251330A publication Critical patent/JP2012251330A/en
Application granted granted Critical
Publication of JP5705031B2 publication Critical patent/JP5705031B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、地中に埋設されて老朽化した既設埋設管を新しい埋設管に改築するための埋設管改築工法に関し、特に連結部に鋼製継輪を有するコンクリート埋設管の改築工法に関する。   The present invention relates to a buried pipe reconstructing method for reconstructing an existing buried pipe that has been buried and aged into a new buried pipe, and more particularly to a method for reconstructing a concrete buried pipe having a steel joint at a connecting portion.

特開2006−291565号公報には、コンクリート部分を破砕しつつ鉄筋を露出させ、露出した鉄筋をカッターで細断するカッターヘッドを用いてコンクリート及び鉄筋からなる既設埋設管を破砕し、新設管を順次設置する埋設管改築工法が開示されている。   JP-A-2006-291565 discloses a new pipe by crushing an existing buried pipe made of concrete and reinforcing bar using a cutter head that exposes the reinforcing bar while crushing a concrete portion, and chops the exposed reinforcing bar with a cutter. The buried pipe reconstruction method to be installed sequentially is disclosed.

また、特開2002−349756号公報には、更新を要する既設埋設管の始端位置に発進坑を、同終端位置に到達坑を掘削し、前記発進坑内に設置した推進装置に既設埋設管の管端外周に接触して推進し、既設埋設管の単位長以上に推進した段階で既設埋設管の内側を把持し既設埋設管を運搬する機構を介し、既設埋設管を単位長毎に破砕せず更新管の内部を通し前記発進坑内に回収すると共に、埋設管を推進装置終端に継足すことにより新旧の埋設管を入れ替える既設埋設管の更新方法が開示されている。   Japanese Patent Laid-Open No. 2002-349756 discloses that a start pit is excavated at the start position of an existing buried pipe that needs to be updated, a reaching pit is excavated at the end position, and the pipe of the existing buried pipe is installed in the propulsion device installed in the start pit. Protrusions contacting the outer circumference of the end, and when propelled beyond the unit length of the existing buried pipe, the existing buried pipe is not crushed per unit length via a mechanism that grips the inside of the existing buried pipe and transports the existing buried pipe. A method for renewing an existing buried pipe is disclosed in which the old and new buried pipes are replaced by collecting the buried pipe through the inside of the updated pipe into the starting pit and by connecting the buried pipe to the end of the propulsion device.

特開2006−291565号公報JP 2006-291565 A 特開2002−349756号公報JP 2002-349756 A

しかしながら、特開2006−291565号公報に開示された埋設管改築工法においては、鉄筋は切断可能であるが、厚み4〜6mmの鋼製継輪を備えた既設コンクリート管の改築では、鋼製継輪を切断することができないという問題を有する。   However, in the buried pipe reconstruction method disclosed in Japanese Patent Laid-Open No. 2006-291565, the rebar can be cut, but in the reconstruction of an existing concrete pipe having a steel joint having a thickness of 4 to 6 mm, There is a problem that the ring cannot be cut.

また、特開2002−349756号公報に開示された埋設管改築工法においては、既設コンクリート管を単位長毎に破砕せず更新管の内部を通し前記発進坑内に回収するため、既設コンクリート管を切断する単位長さは発進立坑の直径により左右されるため、効率良く既設コンクリート管の回収が実施できないという問題を有する。   Further, in the buried pipe renovation method disclosed in Japanese Patent Application Laid-Open No. 2002-349756, the existing concrete pipe is cut through the inside of the renewal pipe without being crushed for each unit length, so that the existing concrete pipe is cut. Since the unit length to be determined depends on the diameter of the starting shaft, there is a problem that the existing concrete pipe cannot be efficiently recovered.

本発明は、上記従来の問題を解決するものであって、改築する既設コンクリート管及び地山を安定化させ、効率良く鋼製継輪を備えた既設コンクリート管の改築が可能な埋設管改築工法を提供することを目的とする。   The present invention solves the above-described conventional problems, stabilizes existing concrete pipes and grounds to be reconstructed, and enables the rebuilding of existing concrete pipes equipped with steel joints efficiently. The purpose is to provide.

本発明の埋設管改築工法は、前記課題を解決するために、地下に埋設された既設コンクリート管の始端位置と終端位置に発進立坑と到達立坑を掘削する工程と、発進立坑にカッターヘッドを備えた掘進機を配置する工程と、既設コンクリート管の鋼製継輪を発進立坑側から順次除去する鋼製継輪除去工程と、鋼製継輪を除去した空隙部分を地山保護材により保護する鋼製継輪除去跡空隙保護工程と、掘進機を発進させ、鋼製継輪が除去され地山保護材が充填された既設コンクリート管を順次破砕、除去する既設コンクリート管破砕除去工程と、既設コンクリート管破砕除去工程の進展に応じて新設管を推進埋設する新設管推進埋設工程と、を有することを特徴とする。 In order to solve the above problems, the buried pipe reconstruction method of the present invention includes a step of excavating a start shaft and a reaching shaft at the start end position and the end position of an existing concrete pipe buried underground, and a cutter head on the start shaft The step of arranging the excavator, the steel joint removal step of removing the steel joints of the existing concrete pipe in order from the start shaft side, and the gap part from which the steel joints have been removed are protected by natural ground protective materials. a steel Tsugiwa remove traces gap protection step, the shield machine is starting, the steel Tsugiwa is removed sequentially crush the existing concrete pipe mound protective material is filled, and the existing concrete pipe crushing step of removing, the existing And a new pipe propulsion embedding process for propelling and embedding new pipes in accordance with the progress of the concrete pipe crushing and removing process.

また、本発明の埋設管改築工法は、鋼製継輪除去工程で、回転刃の向きが可変で軸方向及び周方向に移動可能な胴切りカッター装置を用い、鋼製継輪の周方向及び軸方向に切断して鋼製継輪を切断除去することを特徴とする。   Further, the buried pipe reconstruction method of the present invention is a steel joint removal process, in which the rotating blade direction is variable and a barrel cutter device that can move in the axial direction and the circumferential direction is used. The steel joint ring is cut and removed by cutting in the direction.

また、本発明の埋設管改築工法は、鋼製継輪除去工程で、作業員が既設コンクリート管内に入り切断、破砕工具を用いて実施することを特徴とする。   Moreover, the buried pipe reconstruction method of the present invention is characterized in that, in the steel joint removal process, an operator enters the existing concrete pipe and cuts and uses a crushing tool.

また、本発明の埋設管改築工法は、鋼製継輪除去工程、鋼製継輪除去跡空隙保護工程、既設コンクリート管破砕除去工程及び新設管推進埋設工程を圧気下で実施することを特徴とする。   Further, the buried pipe reconstruction method of the present invention is characterized in that the steel joint removal process, the steel joint removal trace void protection process, the existing concrete pipe crushing removal process, and the new pipe propulsion embedding process are performed under pressure. To do.

また、本発明の埋設管改築工法は、既設コンクリート管破砕除去工程で、掘進機の掘進切羽前方の既設コンクリート管内に移動可能な土圧調整板を設置することを特徴とする。   The buried pipe reconstruction method of the present invention is characterized in that a movable earth pressure adjusting plate is installed in the existing concrete pipe in front of the excavation face of the excavator in the existing concrete pipe crushing and removing step.

地下に埋設された既設コンクリート管の始端位置と終端位置に発進立坑と到達立坑を掘削する工程と、発進立坑にカッターヘッドを備えた掘進機を配置する工程と、既設コンクリート管の鋼製継輪を発進立坑側から順次除去する鋼製継輪除去工程と、鋼製継輪を除去した空隙部分を地山保護材により保護する鋼製継輪除去跡空隙保護工程と、掘進機を発進させ、鋼製継輪が除去され地山保護材が充填された既設コンクリート管を順次破砕、除去する既設コンクリート管破砕除去工程と、既設コンクリート管破砕除去工程の進展に応じて新設管を推進埋設する新設管推進埋設工程と、を有することにより、鋼製継輪を予め除去し、除去跡を地山保護材により地山を保護することにより通常のカッターヘッドを有する掘進機で継輪部分跡も含めて既設コンクリート管を破砕除去することが可能となる。
鋼製継輪除去工程で、回転刃の向きが可変で軸方向及び周方向に移動可能な胴切りカッター装置を用い、鋼製継輪の周方向及び軸方向に切断して鋼製継輪を除去することにより、鋼製継輪の切断除去を効率良く実施することが可能となる。
鋼製継輪除去工程で、作業員が既設コンクリート管内に入り切断、破砕工具を用いて実施することにより、鋼製継輪の除去を状況に応じて臨機応変に実施することが可能となる。
鋼製継輪除去工程、鋼製継輪除去跡空隙保護工程、既設コンクリート管破砕除去工程及び新設管推進埋設工程を圧気下で実施することにより、地山からの漏水等を防止しドライな環境で埋設管改築作業を実施することが可能になる。
既設コンクリート管破砕除去工程で、掘進機による掘進切羽前方の既設コンクリート管内に移動可能な土圧調整板を設置することにより、掘進機による既設コンクリート管破砕除去の際発生する切羽圧力の変動を小さくして、安定した施工が可能になる。
Excavating start and end shafts at the start and end positions of existing concrete pipes buried underground, placing excavators equipped with cutter heads at the start shafts, and steel links for existing concrete pipes a steel Tsugiwa removal step of sequentially removing from the starting pit side, and steel Tsugiwa remove traces gap protection step of protecting the gap portion obtained by removing the steel Tsugiwa by natural ground protection member, thereby starting the excavator, The existing concrete pipe crushing and removing process that sequentially crushes and removes the existing concrete pipe that has been removed from the steel joints and filled with ground protection material, and the new pipe that is propelled and buried according to the progress of the existing concrete pipe crushing and removing process A pipe propulsion embedding process, removing steel joints in advance, and protecting the ground with a ground protection material, and removing the traces including the part of the joints in the excavator with a normal cutter head The The set concrete pipes it is possible to crush removed.
In the steel joint removal process, the rotating blade direction is variable and the cutter cutter is movable in the axial and circumferential directions, and the steel joint is removed by cutting in the circumferential and axial directions of the steel joint. This makes it possible to efficiently cut and remove the steel joint.
In the steel joint removal process, when the worker enters the existing concrete pipe and cuts and performs using a crushing tool, the steel joint removal can be performed flexibly according to the situation.
By implementing the steel joint removal process, the steel joint removal trace clearance protection process, the existing concrete pipe crushing removal process, and the new pipe propulsion embedding process under pressure, water leakage from natural ground is prevented and a dry environment It becomes possible to carry out buried pipe reconstruction work.
By installing a movable earth pressure adjusting plate in the existing concrete pipe in front of the excavation face by the excavator in the existing concrete pipe crushing and removal process, fluctuations in the face pressure generated when excavating the existing concrete pipe is removed are reduced. Thus, stable construction becomes possible.

本発明の実施形態を示す図である。It is a figure which shows embodiment of this invention. 本発明の実施形態を示す図である。It is a figure which shows embodiment of this invention. 本発明の実施形態を示す図である。It is a figure which shows embodiment of this invention. 本発明の実施形態を示す図である。It is a figure which shows embodiment of this invention. 本発明の実施形態を示す図である。It is a figure which shows embodiment of this invention. 本発明の実施形態を示す図である。It is a figure which shows embodiment of this invention. 本発明の実施形態を示す図である。It is a figure which shows embodiment of this invention.

本発明の埋設管改築工法を図により説明する。図1は、本発明の埋設管改築工法の実施形態を示す概略図である。   The buried pipe reconstruction method of the present invention will be described with reference to the drawings. FIG. 1 is a schematic view showing an embodiment of the buried pipe reconstruction method of the present invention.

既設コンクリート管3は鉄筋コンクリート製でその連結部に厚さ4〜6mmの鋼製継輪5が設置されている。改築すべき既設コンクリート管3の始端位置と到達位置に発進立坑1と到達立坑2を掘削する。   The existing concrete pipe 3 is made of reinforced concrete, and a steel joint 5 having a thickness of 4 to 6 mm is installed at the connecting portion. The starting shaft 1 and the reaching shaft 2 are excavated at the starting position and the reaching position of the existing concrete pipe 3 to be reconstructed.

発進立坑1に掘進機6を設置する。掘進機6は、掘進機本体7の前面に駆動モータ8で回転駆動する面板9が設置され、面板に複数のローラビット10が回転自在に配置される。掘進機6の詳細については後述する。発進立坑1には、掘進機6の既設コンクリート管破砕除去工程の進展に伴い新設管4を敷設するための元押ジャッキ16が設置される。   The excavator 6 is installed in the start shaft 1. In the excavator 6, a face plate 9 that is rotationally driven by a drive motor 8 is installed on the front surface of the excavator main body 7, and a plurality of roller bits 10 are rotatably arranged on the face plate. Details of the excavator 6 will be described later. In the start shaft 1, a main push jack 16 for laying the new pipe 4 is installed as the existing concrete pipe crushing and removing process of the excavator 6 progresses.

改築工事において、鋼製継輪除去工程で地山が一時期露出し地下水が浸入する恐れがある場合、到達立坑2に圧気ロック13を設置する。その場合、掘進機6後部にエアロックドアを有する圧気胴11を設置し、地上に設置した給気設備14から給気管15を通して圧力空気が供給して改築する既設コンクリート管3内を圧気状態にする。地下水の浸入の問題の無い改築工事においては圧気状態にしなくても良い。   In the renovation work, if the ground is exposed for a period of time in the steel joint removal process and there is a risk of infiltration of groundwater, a pneumatic lock 13 is installed in the reaching shaft 2. In that case, the pressure cylinder 11 having an air lock door is installed at the rear part of the excavator 6, and the inside of the existing concrete pipe 3 which is renovated by supplying pressurized air from the supply equipment 14 installed on the ground through the supply pipe 15 is brought into a pressurized state. To do. In renovation work without problems of ingress of groundwater, it is not necessary to be in a pressurized state.

掘進機6による既設コンクリート管破砕除去工程の前に、既設コンクリート管3の連結部に設置された掘進機6では切断除去が困難な鋼製継輪5の除去工程を順次実施する。鋼製継輪除去工程は、作業員が既設コンクリート管3内に入り、各種工具を用いて切断除去しても良い。除去された鋼製継輪5は、掘進機6を通して発進立坑1側に搬送しても良いが、設備の少ない到達立坑2側から搬送するのが望ましい。   Prior to the crushing and removing process of the existing concrete pipe by the excavating machine 6, the removing process of the steel joint 5 that is difficult to cut and remove by the excavating machine 6 installed at the connecting portion of the existing concrete pipe 3 is sequentially performed. In the steel joint removal step, an operator may enter the existing concrete pipe 3 and cut and remove it using various tools. The removed steel joint 5 may be transported to the start shaft 1 side through the excavator 6, but is desirably transported from the reach shaft 2 side with few facilities.

図2、図3及び図4は、鋼製継輪除去工程をより効率良く実施するために胴切りカッター装置17を用いる実施形態を示す。胴切りカッター装置17は軸方向の前後に所定間隔をおいて配置される一対の支柱部材18を備えている。支柱部材18は、図4に示されるように油圧などにより伸縮自在とされる左右の垂直部19と、左右の垂直部19を連結する水平部20を備えている。左右の垂直部の上下端には、既設コンクリート管3の内壁に押圧され支柱部材18を固定するための接地部21が設けられる。左右の垂直部の下端には、胴切りカッター装置17を既設コンクリート管3内で移動可能にするため出没自在な移動輪(図示せず)を設けても良い。   FIGS. 2, 3 and 4 show an embodiment in which the body cut cutter device 17 is used to perform the steel joint removal process more efficiently. The body cutting cutter device 17 includes a pair of support members 18 disposed at a predetermined interval in the front and rear in the axial direction. As shown in FIG. 4, the column member 18 includes left and right vertical portions 19 that can be expanded and contracted by hydraulic pressure and the like, and a horizontal portion 20 that connects the left and right vertical portions 19. At the upper and lower ends of the left and right vertical portions, grounding portions 21 are provided for fixing the column members 18 that are pressed against the inner wall of the existing concrete pipe 3. At the lower ends of the left and right vertical portions, a movable wheel (not shown) that can be moved in and out may be provided in order to make the body cutting cutter device 17 movable in the existing concrete pipe 3.

前後の支柱部材18の水平部20間を軸方向に伸縮可能な水平連結部材22で連結する。水平連結部材22にカッター保持部材23が周方向駆動手段24により周方向に回動自在に設置される。カッター保持部材23には周方向に伸縮自在にカッター25が設置される。カッター保持部材23には、カッターの向きを変えるため回動自在にされる。また、カッター保持部材23には、カッター25を回転駆動するカッター駆動手段を備えている。   The horizontal portions 20 of the front and rear support members 18 are connected by a horizontal connecting member 22 that can extend and contract in the axial direction. A cutter holding member 23 is installed on the horizontal connecting member 22 so as to be rotatable in the circumferential direction by a circumferential driving means 24. A cutter 25 is installed on the cutter holding member 23 so as to be stretchable in the circumferential direction. The cutter holding member 23 is rotatable to change the direction of the cutter. The cutter holding member 23 is provided with a cutter driving means for driving the cutter 25 to rotate.

胴切りカッター装置17による鋼製継輪5の除去工程は、先ず、支柱部材18をカッター25が鋼製継輪5の位置に来るよう移動する。次に支柱部材18の垂直部19を伸ばし上下の接地部21を既設コンクリート管3の内壁に押圧し胴切りカッター装置17を固定する。次に、カッター保持部材23を回動させ、カッターの向きが図3の位置になるようにする。カッター25を周方向に押し付けながら回転駆動すると共に、周方向駆動手段24により周方向に移動させ、鋼製継輪5の軸方向の両端部を既設コンクリート管3と一緒に切断する。   In the removing process of the steel joint 5 by the body cutter cutter 17, first, the column member 18 is moved so that the cutter 25 comes to the position of the steel joint 5. Next, the vertical part 19 of the column member 18 is extended, and the upper and lower grounding parts 21 are pressed against the inner wall of the existing concrete pipe 3 to fix the drum cutter 17. Next, the cutter holding member 23 is rotated so that the orientation of the cutter becomes the position shown in FIG. The cutter 25 is rotationally driven while being pressed in the circumferential direction, and is moved in the circumferential direction by the circumferential driving means 24, and both end portions in the axial direction of the steel joint ring 5 are cut together with the existing concrete pipe 3.

鋼製継輪5の両端部切断が終了すると、カッター保持部材23を回動させ、カッターの向きが図2の位置になるようにする。カッター25を周方向に押し付けながら回転駆動すると共に、水平連結部材22の伸縮手段を駆動してカッター25を軸方向に移動させ、鋼製継輪5を軸方向に切断する。鋼製継輪5の軸方向の切断は、両端部が切断された鋼製継輪5が除去しやすい幅となるように設定する。1か所の鋼製継輪除去工程が終了すると、胴切りカッター装置17を、次の鋼製継輪5の除去位置に移動する。   When the cutting of both ends of the steel joint ring 5 is completed, the cutter holding member 23 is rotated so that the orientation of the cutter is in the position shown in FIG. The cutter 25 is rotated while being pressed in the circumferential direction, and the telescopic means of the horizontal connecting member 22 is driven to move the cutter 25 in the axial direction, thereby cutting the steel joint ring 5 in the axial direction. The cutting in the axial direction of the steel joint 5 is set so that the steel joint 5 having both ends cut is easily removed. When one steel joint removal process is completed, the body cutter device 17 is moved to the next steel joint 5 removal position.

胴切りカッター装置17による鋼製継輪除去工程が終了すると、鋼製継輪5が除去された空所に地山保護材30を充填し固化させる工程を実施する。鋼製継輪除去跡空隙保護工程を図5により説明する。   When the steel joint removal step by the body cutting cutter device 17 is completed, a step of filling and solidifying the ground protection material 30 in the empty space from which the steel joint 5 has been removed is performed. The steel joint removal trace clearance protecting process will be described with reference to FIG.

鋼製継輪5が除去された空所の既設コンクリート管3の内壁に型枠27を型枠支持部材28を介して設置する。型枠27が設置された鋼製継輪5が除去された空隙に地山保護材供給管29から地山保護材30を供給し充填し固化させる。地山保護材30としては速硬性のセメントミルク等を用いる。充填された地山保護材30が固化後、型枠27を撤去する。
鋼製継輪除去跡空隙保護工程で、地山保護材としてセメントミルクなどを用いる替りに前もって用意した山留ピースなどを用いることもよい。
A mold 27 is installed via a mold support member 28 on the inner wall of the existing concrete pipe 3 in the empty space from which the steel joint 5 has been removed. A natural ground protective material 30 is supplied from a natural ground protective material supply pipe 29 to the gap from which the steel joint 5 provided with the mold 27 is removed, and is filled and solidified. As the natural ground protection material 30, a fast-curing cement milk or the like is used. After the filled ground protection material 30 is solidified, the mold 27 is removed.
Instead of using cement milk or the like as a natural mountain protective material, it is also possible to use a pre-prepared mountain piece or the like in the steel joint removal mark void protecting step.

鋼製継輪除去工程と鋼製継輪除去跡空隙保護工程は、続く既設コンクリート管破砕除去工程で掘進機6による既設コンクリート管3の破砕に先行して実施される。地山保護材30の固化の時間を考慮し、鋼製継輪除去工程と鋼製継輪除去跡空隙保護工程を掘進機6の掘進切羽から既設コンクリート管3の2又は3本の前方の連結部で先行実施するのが望ましい。また、掘進機6による既設コンクリート管破砕除去工程に先立ち、改築する既設コンクリート管3の全ての鋼製継輪5に対して鋼製継輪除去工程と鋼製継輪除去跡空隙保護工程を実施しても良い。   The steel joint removal process and the steel joint removal trace clearance protection process are performed prior to the crushing of the existing concrete pipe 3 by the excavator 6 in the subsequent existing concrete pipe crushing and removing process. Considering the solidification time of the ground protection material 30, the steel joint removal process and the steel joint removal trace clearance protection process are connected from the excavation face of the excavator 6 to the front of two or three existing concrete pipes 3. It is desirable to carry out in advance in the department. Prior to the existing concrete pipe crushing and removing process by the excavator 6, a steel joint removal process and a steel joint removal trace clearance protecting process are performed on all steel joints 5 of the existing concrete pipe 3 to be renovated. You may do it.

次に、既設コンクリート管破砕除去工程に用いる掘進機6の一実施形態を図6、図7により説明する。   Next, an embodiment of the excavator 6 used in the existing concrete pipe crushing and removing step will be described with reference to FIGS.

掘進機6は円筒形の掘進機本体7の前端に中央開口31を有するリング状の面板9を備えている。掘進機本体7の外周には先端部が掘進機本体の前端より前に延びる山留円筒部材32が設置される。山留円筒部32の先端にスリットカッター33を設置する。リング状の面板9には複数のローラビット10が回転自在に配置されカッターヘッドを構成する。リング状の面板9は、掘進機本体7内に設置した駆動モータ8により回転駆動する。ローラビット10は既設コンクリート管3及び地山に押圧されながらリング状の面板9の回転に伴い自転し、既設コンクリート管、地山及び地山保護材30を掘削する。鋼製継輪5が除去され、その空隙に地山保護材30が充填固化されているので、掘進切羽を安定化させて効率よく既設コンクリート管破砕除去工程を実施することが可能となる。   The excavator 6 includes a ring-shaped face plate 9 having a central opening 31 at the front end of a cylindrical excavator main body 7. On the outer periphery of the excavator main body 7, a mountain retaining cylindrical member 32 whose front end extends before the front end of the excavator main body is installed. A slit cutter 33 is installed at the tip of the Yamadome cylindrical portion 32. A plurality of roller bits 10 are rotatably arranged on the ring-shaped face plate 9 to constitute a cutter head. The ring-shaped face plate 9 is rotationally driven by a drive motor 8 installed in the excavator main body 7. The roller bit 10 rotates with the rotation of the ring-shaped face plate 9 while being pressed by the existing concrete pipe 3 and the natural ground, and excavates the existing concrete pipe, natural ground and natural ground protective material 30. Since the steel joint ring 5 is removed and the ground protection material 30 is filled and solidified in the gap, it is possible to stabilize the digging face and efficiently carry out the existing concrete pipe crushing and removing step.

掘進機6による既設コンクリート管破砕除去工程で、掘進機6の掘進切羽前方の既設コンクリート管3内に土圧調整板35を移動自在に設置する。土圧調整板35は、掘進機6による既設コンクリート管3の破砕作業に伴う切羽の偏圧や局部圧に対応し既設コンクリート管3内を前後動することにより切羽を安定させる機能を有する。   In the crushing and removing process of the existing concrete pipe by the excavator 6, the earth pressure adjusting plate 35 is movably installed in the existing concrete pipe 3 in front of the excavation face of the excavator 6. The earth pressure adjusting plate 35 has a function of stabilizing the face by moving back and forth in the existing concrete pipe 3 in response to the partial pressure and local pressure of the face accompanying the crushing work of the existing concrete pipe 3 by the excavator 6.

リング状の面板9に形成された中央開口31は、ローラビット10で切断、破砕された既設コンクリート管及び地山等の掘削物を掘進機本体7内に取り込むためと、作業員が鋼製継輪除去工程及び鋼製継輪除去跡空隙保護工程において、既設コンクリート管3内に出入する際の出入り口として機能することもできる。   The central opening 31 formed in the ring-shaped face plate 9 is used by an operator to take in existing excavated objects such as concrete pipes and grounds that have been cut and crushed by the roller bit 10 into the excavator main body 7, so It can also function as an entrance / exit when entering / exiting into the existing concrete pipe 3 in the wheel removal step and the steel joint removal removal space protection step.

掘進機本体7内に取り込まれた掘削物は、掘削物搬送手段34を介して発進立坑1から坑外に搬送される。掘進機本体7の後部には、圧気胴11、セミシールド胴12を連結する。圧気胴11及びセミシールド胴12の連結の前後は逆であっても良い。圧気胴11は、改築作業中既設コンクリート管3内を圧気状態にするためのものであり前後に少なくとも2枚のエアロックドア(図示せず)を備えている。セミシールド胴21にはセミシールドジャッキ(図示せず)を備えており、掘進機本体7を掘進切羽側に押圧すると共に、掘進機本体7の掘進方向を制御する機能を有している。しかし、圧気胴11及びセミシールド胴12は必要に応じて設置するものであり、地山からの地下水の浸入の恐れが無い場合や、掘進機本体7の掘進切羽への押圧を元押しジャッキ16のみで施工できる場合は省略することが可能である。   The excavated matter taken into the excavator main body 7 is conveyed from the start shaft 1 to the outside of the excavation through the excavated material conveying means 34. A pressure air cylinder 11 and a semi-shield cylinder 12 are connected to the rear portion of the excavator main body 7. Before and after the connection of the pressure cylinder 11 and the semi-shield cylinder 12 may be reversed. The pressure cylinder 11 is for bringing the inside of the existing concrete pipe 3 into a pressurized state during the reconstruction work, and includes at least two air lock doors (not shown) at the front and rear. The semi-shield barrel 21 is provided with a semi-shield jack (not shown), and has a function of pressing the excavator main body 7 toward the excavation face and controlling the excavation direction of the excavator main body 7. However, the pressure cylinder 11 and the semi-shield cylinder 12 are installed as necessary. When there is no fear of intrusion of groundwater from the natural ground, or when the press to the digging face of the digging machine main body 7 is pushed, the jack 16 It can be omitted if it can be constructed only with

既設コンクリート管破砕除去工程の進展に伴い、新設管推進埋設工程を実施する。新設管推進埋設工程は、発進立坑1に設置した元押しジャッキ16により実施する。   Along with the progress of the existing concrete pipe crushing and removal process, the new pipe promotion and embedding process will be implemented. The new pipe propulsion embedding process is performed by the main push jack 16 installed in the start shaft 1.

以上のように本発明の埋設管改築工法によれば、鋼製継輪を予め除去し、除去跡に鋼製継輪除去跡空隙保護工程で地山保護材を充填固化することで既設コンクリート管及び地山を安定化させ、通常のカッターヘッドを有する掘進機で既設コンクリート管を破砕除去することが可能となる。   As described above, according to the buried pipe remodeling method of the present invention, the existing concrete pipe is obtained by removing the steel joint in advance and filling the removed trace with solid ground protection material in the steel joint removal trace void protecting step. In addition, the ground can be stabilized and the existing concrete pipe can be crushed and removed by an excavator having a normal cutter head.

1: 発進立坑、2:到達立坑、3:既設埋設管、4:新設管、5:鋼製継輪、6:掘進機、7:掘進機本体、8:駆動モータ、9:面板、10:ローラビット、11:圧気胴、12:セミシールド胴、13:圧気ロック、14:給気設備、15:給気管、16:元押しジャッキ、17:胴切りカッター装置、18:支柱部材、19:垂直部、20:水平部、21:接地部、22:水平連結部材、23:カッター保持部材、24:周方向駆動手段、25:カッター、26:カッター駆動手段、27:型枠、28:型枠支持部材、29:山留材供給管、30:地山保護材、31:中央開口、32:山留円筒部、33:スリットカッター、34:掘削物搬送手段、35:土圧調整板   1: start shaft, 2: reach shaft, 3: existing buried pipe, 4: new pipe, 5: steel joint, 6: excavator, 7: excavator body, 8: drive motor, 9: face plate, 10: Roller bit, 11: Pressure cylinder, 12: Semi-shield cylinder, 13: Pressure lock, 14: Air supply equipment, 15: Air supply pipe, 16: Main push jack, 17: Body cutting cutter device, 18: Strut member, 19: Vertical Part: 20: horizontal part, 21: grounding part, 22: horizontal connecting member, 23: cutter holding member, 24: circumferential driving means, 25: cutter, 26: cutter driving means, 27: mold, 28: mold Support member, 29: mountain retaining material supply pipe, 30: ground protection material, 31: central opening, 32: mountain retaining cylindrical part, 33: slit cutter, 34: excavated material conveying means, 35: earth pressure adjusting plate

Claims (5)

地下に埋設された既設コンクリート管の始端位置と終端位置に発進立坑と到達立坑を掘削する工程と、
発進立坑にカッターヘッドを備えた掘進機を配置する工程と、
既設コンクリート管の鋼製継輪を発進立坑側から順次除去する鋼製継輪除去工程と、
鋼製継輪を除去した部分に地山保護材を充填し固化させる鋼製継輪除去跡空隙保護工程と、
掘進機を発進させ、鋼製継輪が除去され地山保護材が充填された既設コンクリート管を順次破砕、除去する既設コンクリート管破砕除去工程と、
既設コンクリート管破砕除去工程の進展に応じて新設管を推進埋設する新設管推進埋設工程と、
を有することを特徴とする埋設管改築工法。
Excavating start and end shafts at the start and end positions of existing concrete pipes buried underground;
A step of arranging an excavator equipped with a cutter head on the start shaft;
Steel joint removal process for removing steel joints of existing concrete pipes sequentially from the start shaft,
The steel joint removal removal gap protection process that fills and solidifies the ground protection material in the part from which the steel joint has been removed ,
An existing concrete pipe crushing and removing step of starting the excavator, crushing and removing the existing concrete pipes in which the steel joints are removed and the ground protection material is filled,
A new pipe propulsion embedding process for propelling and embedding new pipes according to the progress of the existing concrete pipe crushing and removing process,
A buried pipe reconstruction method characterized by having
鋼製継輪除去工程で、回転刃の向きが可変で軸方向及び周方向に移動可能な胴切りカッター装置を用い、鋼製継輪の周方向及び軸方向に切断して鋼製継輪を切断除去することを特徴とする請求項1に記載の埋設管改築工法。   In the steel joint removal process, the steel blade is cut by cutting the steel joint in the circumferential direction and axial direction using a cutting cutter that can move in the axial direction and circumferential direction with the direction of the rotary blade being variable. The buried pipe reconstruction method according to claim 1, wherein the buried pipe reconstruction method is removed. 鋼製継輪除去工程で、作業員が既設コンクリート管内に入り切断、破砕工具を用いて実施することを特徴とする請求項1に記載の埋設管改築工法。   The buried pipe reconstruction method according to claim 1, wherein in the steel joint removal step, an operator enters the existing concrete pipe and performs cutting and crushing using a cutting tool. 鋼製継輪除去工程、鋼製継輪除去跡空隙保護工程、既設コンクリート管破砕除去工程及び新設管推進埋設工程を圧気下で実施することを特徴とする請求項1ないし3のいずれか1項に記載の埋設管改築工法。   4. The steel joint removal process, the steel joint removal trace clearance protection process, the existing concrete pipe crushing removal process, and the new pipe propulsion embedding process are performed under pressure. The buried pipe reconstruction method described in 1. 既設コンクリート管破砕除去工程で、掘進機の掘進切羽前方の既設コンクリート管内に移動可能な土圧調整板を設置することを特徴とする請求項1ないし4のいずれか1項に記載の埋設管改築工法。   5. The buried pipe reconstruction according to claim 1, wherein a movable earth pressure adjusting plate is installed in the existing concrete pipe in front of the excavation face of the excavator in the existing concrete pipe crushing and removing step. Construction method.
JP2011123317A 2011-06-01 2011-06-01 Buried pipe reconstruction method Active JP5705031B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011123317A JP5705031B2 (en) 2011-06-01 2011-06-01 Buried pipe reconstruction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011123317A JP5705031B2 (en) 2011-06-01 2011-06-01 Buried pipe reconstruction method

Publications (2)

Publication Number Publication Date
JP2012251330A JP2012251330A (en) 2012-12-20
JP5705031B2 true JP5705031B2 (en) 2015-04-22

Family

ID=47524383

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011123317A Active JP5705031B2 (en) 2011-06-01 2011-06-01 Buried pipe reconstruction method

Country Status (1)

Country Link
JP (1) JP5705031B2 (en)

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2704462B2 (en) * 1990-11-07 1998-01-26 新日本製鐵株式会社 Replacement method of existing pipe by non-cutting and its equipment
JPH04366080A (en) * 1991-06-12 1992-12-17 Nippon Steel Corp Existing pipe exchanging method without open excavating and its device
JP4152935B2 (en) * 2004-10-29 2008-09-17 株式会社アルファシビルエンジニアリング Reconstruction method and equipment for existing pipes
JP4587219B2 (en) * 2005-07-13 2010-11-24 株式会社推研 Pressure excavation machine for renewal of existing concrete pipe and renewal method of existing concrete pipe using it.

Also Published As

Publication number Publication date
JP2012251330A (en) 2012-12-20

Similar Documents

Publication Publication Date Title
US3917010A (en) Small diameter horizontal tunneling machine
JP5705031B2 (en) Buried pipe reconstruction method
JP4734541B2 (en) Method of recovering shield machine and shield machine using the method
JP4646138B2 (en) Existing concrete pipe crushing machine
JP4943362B2 (en) Equipment and method for removing and refilling existing buried pipes
JP5291024B2 (en) Direct cast concrete method
JPH0489992A (en) Existing pipe duct enlarging method and shield excavation device used with the method
JP4771174B2 (en) Tunnel closing method and tunnel closing device
JP5773489B2 (en) Non-crushing type buried pipe reconstruction method and non-crushing type buried pipe rebuilding machine
JP3963566B2 (en) Cutter head and obstacle cutting method
JP5599346B2 (en) Tunnel excavator for renewal of existing pipes
JP6746483B2 (en) Tunnel machine
JP6783132B2 (en) Tunnel boring machine
JP3649536B2 (en) Cutter head and tunnel excavator
JP2008002070A (en) Tunnel excavator, reaming tunnel excavator and excavating method
JP4718990B2 (en) Method of retaining soil near tunnel face
JP3891645B2 (en) Embedded pipe dismantling method and equipment
JP3891644B2 (en) Embedded pipe dismantling method and equipment
JP2015134998A (en) Non-destructive underground pipe renovation device and non-destructive underground pipe renovation method using device
JP4499931B2 (en) Shield excavator and shield excavation method
JP4904580B2 (en) Tunnel closing method and tunnel closing device
JP4731307B2 (en) Cutter head of tunnel excavator
JPS6126461Y2 (en)
JP6746484B2 (en) Tunnel machine
JPH0224486A (en) Construction of large-diameter tunnel and ring-cut type excavator

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140512

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150114

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150121

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150128

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150218

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150224

R150 Certificate of patent or registration of utility model

Ref document number: 5705031

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250