JP5529620B2 - Process control device - Google Patents

Process control device Download PDF

Info

Publication number
JP5529620B2
JP5529620B2 JP2010108075A JP2010108075A JP5529620B2 JP 5529620 B2 JP5529620 B2 JP 5529620B2 JP 2010108075 A JP2010108075 A JP 2010108075A JP 2010108075 A JP2010108075 A JP 2010108075A JP 5529620 B2 JP5529620 B2 JP 5529620B2
Authority
JP
Japan
Prior art keywords
work
change
efficiency
unit
data storage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2010108075A
Other languages
Japanese (ja)
Other versions
JP2011181058A (en
Inventor
豊裕 梅田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP2010108075A priority Critical patent/JP5529620B2/en
Publication of JP2011181058A publication Critical patent/JP2011181058A/en
Application granted granted Critical
Publication of JP5529620B2 publication Critical patent/JP5529620B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、作業工程(スケジュール)を管理するための装置に関し、特にその作業工程の表示にガントチャートを用いるものにおいて、前記作業工程を変更(修正)する手法に関する。   The present invention relates to an apparatus for managing a work process (schedule), and more particularly to a method for changing (correcting) the work process in a case where a Gantt chart is used to display the work process.

生産ラインでの作業工程の管理等には、従来から、前記ガントチャートが広く用いられている。そのガントチャートは、縦軸に工程や人員を、横軸に時間を配し、それらの関係を、作業開始時期を前縁とし、作業終了時期を後縁とした矩形領域(帯)で表すようにしたものであり、どの作業工程にどれだけの時間が掛るのかを、容易に認識することができるようになっている。   Conventionally, the Gantt chart has been widely used for managing work processes in a production line. The Gantt chart has processes and personnel on the vertical axis and time on the horizontal axis, and the relationship is represented by a rectangular area (band) with the work start time as the leading edge and the work end time as the trailing edge. Therefore, it is possible to easily recognize how much time is required for which work process.

ところが、処理ワークの増加などによる作業工程の変更や割込みは珍しくなく、そのような場合に、作業工程を前記ガントチャート上で変更(修正)するにあたって、特許文献1では、通常、前記のように作業時間が矩形領域(帯)で表示される複数の各作業工程の内、作業者が一部をマウスやキーボードなどの入力操作手段で移動させることで行われている。その後、変更後の割り付けを基に、作業工程全体を再シミュレーションし、再度ガントチャートを表示し、変更(修正)の影響を確認し、不都合があれば、上記の変更(修正)、シミュレーション、確認を繰返すことで、作業工程の変更や改善が行われている。   However, it is not uncommon to change or interrupt the work process due to an increase in processing work. In such a case, in changing (correcting) the work process on the Gantt chart, in Patent Document 1, normally, as described above. The work time is performed by the operator moving a part of the work steps displayed in a rectangular area (band) with an input operation means such as a mouse or a keyboard. After that, based on the assignment after the change, re-simulate the entire work process, display the Gantt chart again, check the effect of the change (correction), and if there is any inconvenience, change (correction), simulate, and check the above By repeating the above, the work process is changed or improved.

しかしながら、上述の従来技術では、各作業工程の作業時間はマスターテーブルに予め定められており、作業者は割り付け方(作業の順序や利用する設備)のみを変更することが前提となっている。このため、そのような作業工程の変更(修正)が収まらない、すなわち規定の時間内に完了できない(納期に間に合わない)ケースもあり、そのような場合は、ネックとなる作業工程の見直しが必要になる。具体的には、経験の浅い作業者からベテランの作業者に変更したり、作業者を増加したり、或いは作業を行う装置を省エネ運転からハイパワー運転に切換えるなどして、その作業工程の能率を向上し、作業時間を短縮することである。このような対策を採用する場合、この従来技術では、前記マスターテーブルを変更しなければならず、極めて時間が掛り、迅速な対応を取ることが困難である。   However, in the above-described conventional technology, the work time of each work process is determined in advance in the master table, and it is assumed that the worker changes only the way of assignment (work order and equipment used). For this reason, there are cases where such work process changes (corrections) do not fit, that is, they cannot be completed within the prescribed time (not in time for delivery). In such cases, it is necessary to review the work process that becomes a bottleneck. become. Specifically, the efficiency of the work process can be improved by changing from an inexperienced worker to an experienced worker, increasing the number of workers, or switching the equipment to perform work from energy-saving operation to high-power operation. Is to improve the working time. In the case of adopting such a countermeasure, in this conventional technique, the master table must be changed, which is extremely time consuming and it is difficult to take a quick response.

そこで、特許文献2では、前記ガントチャート上で、前記矩形領域(帯)を縦に並べて表示することで、作業者に変更(修正)に伴う作業工程の重複を分り易く表示している。これによって、前記重複期間で一方が隠れてしまうことがないので、実際の作業時間を正確に把握することができ、作業を行う装置の能力に対する違反(過剰な負荷)や、能力を高めるべき期間を容易に確認できるようになっている。   Thus, in Patent Document 2, the rectangular regions (bands) are displayed vertically on the Gantt chart, so that the operator can easily understand the overlap of work steps associated with the change (correction). As a result, since one side is not hidden in the overlap period, the actual work time can be accurately grasped, a violation (excessive load) with respect to the ability of the apparatus to perform the work, or a period in which the ability should be increased Can be easily confirmed.

特開2002−251507号公報JP 2002-251507 A 特開2009−230382号公報JP 2009-230382 A

上述の従来技術では、作業工程が重複していることは分るものの、その対策として、重複している工程の少なくとも一方の能率を高め、作業時間を短縮してその重複の解消を図っても、矩形領域(帯)の幅は変化せず、このため実際の作業開始時期および作業終了時期が明確にならず、現場への作業指示に困難がある。また、作業工程毎に、その作業時間は様々であり、前記の作業工程の重複を表示するだけでは、どの作業工程をどれだけ能率を上げたら(作業時間を短縮したら)、作業時間をどれだけ詰められるか等を、正確に見積もることができず、作業能率の向上を図るべき対策の必要な作業工程を容易に判断することができない。   In the above-mentioned conventional technology, although it can be seen that the work process is duplicated, as a countermeasure, it is possible to improve the efficiency of at least one of the duplicated processes, shorten the work time, and eliminate the duplication. The width of the rectangular area (band) does not change, so the actual work start time and work end time are not clear, and it is difficult to give work instructions to the site. In addition, the work time varies from work process to work process. By simply displaying the duplication of the work process described above, how much work process is improved (how much work time is reduced), how much work time is needed. It is not possible to accurately estimate whether or not it is packed, and it is not possible to easily determine a work process that requires measures to improve work efficiency.

本発明の目的は、作業者が各作業工程での現在の能率を容易に認識することができる工程管理装置を提供することである。   An object of the present invention is to provide a process management apparatus that allows an operator to easily recognize the current efficiency in each work process.

本発明の工程管理装置は、複数の各作業工程を、作業開始時期を前縁とし、作業終了時期を後縁とした矩形領域で表すガントチャートによって表示手段に表示し、前記作業工程を管理する装置において、前記各作業工程における能率を前記矩形領域の高さで表し、前記表示手段に与えるガントチャート表示データ作成部と、前記作業工程の変更を受付ける入力操作部と、予め作成された作業工程表に対して、前記入力操作部によって変更が受付けられた作業工程の作業時間帯を変更する作業割り付け変更部と、予め作成された作業工程表に対して、前記入力操作部によって変更が受付けられた作業工程の前または後の少なくとも一方側の所定範囲の作業工程について、前記能率の変更対象の作業工程として指定する能率変更工程指定部と、前記作業割り付け変更部によって割り付けられた作業工程の順で作業を行った場合に、前記各作業工程間に予め定められた工程間隔を維持するように、前記能率変更工程指定部によって指定された作業工程に対して、前記矩形領域の面積がその作業工程に必要な一定の作業量となるように、前記矩形領域の作業時間を伸縮させるとともに前記能率を変更し、かつその作業工程をシフトさせ、該変更後の作業工程表を再作成して前記ガントチャート表示データ作成部に与える工程調整部と備えることを特徴とする。
The process management apparatus of the present invention displays a plurality of work processes on a display means by a Gantt chart represented by a rectangular area with a work start time as a leading edge and a work end time as a trailing edge, and manages the work processes. In the apparatus, the efficiency in each work process is represented by the height of the rectangular area, and a Gantt chart display data creation part that is given to the display means, an input operation part that accepts the change of the work process, and a work process created in advance A change is accepted by the input operation unit with respect to a table, a work allocation change unit that changes a work time zone of a work process that has been accepted by the input operation unit, and a work process table created in advance. An efficiency change process designating unit that designates the work process in a predetermined range before or after the work process as a work process to be changed in efficiency; The work process designated by the efficiency changing process designating unit so as to maintain a predetermined process interval between the work processes when work is performed in the order of the work processes assigned by the work assignment changing unit. On the other hand, the working time of the rectangular area is expanded and contracted, the efficiency is changed, and the working process is shifted so that the area of the rectangular area becomes a constant work amount necessary for the working process, recreate the working process table after the change, characterized in that it comprises a step adjustment unit to be supplied to the Gantt chart display data producing unit.

上記の構成によれば、複数の各作業工程を、作業開始時期を前縁とし、作業終了時期を後縁とした矩形領域で表すガントチャートによって表示手段に表示し、前記作業工程を管理するにあたって、前記表示手段で表示される前記ガントチャートの表示データを作成するガントチャート表示データ作成部が、前記各作業工程における能率、すなわち単位時間当りの作業量を前記矩形領域の高さで表す。   According to the above configuration, each work process is displayed on the display means by a Gantt chart represented by a rectangular area with the work start time as the leading edge and the work end time as the trailing edge, and the work process is managed. The Gantt chart display data creating unit for creating the display data of the Gantt chart displayed by the display unit represents the efficiency in each work process, that is, the work amount per unit time by the height of the rectangular area.

したがって、作業者は各作業工程での現在の能率を、視覚的に容易に認識することができる。これによって、予め作成された作業工程に、納期の変更や他の作業の割込みが生じるなどして、作業工程を修正(調整)する必要が生じた場合に、どの工程の作業能率を向上して、作業時間をどれだけ詰められるか等、前記作業工程の修正(調整)に、容易かつ短時間で対応することができる。また、各作業工程での能率を視覚的に認識できることから、作業能率の向上を図るべき対策の必要な作業工程を容易に判断することもできる。   Therefore, the worker can easily visually recognize the current efficiency in each work process. This improves the work efficiency of any process when it becomes necessary to modify (adjust) the work process due to a change in delivery time or interruption of other work in a work process created in advance. It is possible to easily and quickly cope with correction (adjustment) of the work process, such as how much work time can be reduced. Further, since the efficiency in each work process can be visually recognized, it is possible to easily determine a work process that requires a countermeasure to improve the work efficiency.

好ましくは、前記工程調整部は、現在の作業工程データを記憶する工程データ記憶部と、前記能率変更工程指定部で指定された作業工程を記憶する能率変更工程データ記憶部と、前記作業割り付け変更部で変更された作業割り付けを記憶する割り付け変更データ記憶部と、前記能率変更工程データ記憶部および割り付け変更データ記憶部を参照し、割り付け変更データで指定された作業工程の順で作業を行った場合に、各作業工程の矩形領域の面積がその作業工程に必要な一定の作業量となるように、かつ予め定められた工程間隔を維持するように、能率変更工程データで指定される作業工程における前記能率を変更する能率変更値計算部と、前記能率変更値計算部で求められた能率変更データを記憶する能率変更データ記憶部と、前記工程データ記憶部および能率変更データ記憶部を参照し、各作業工程をシフトさせた変更後の作業工程表を再作成し、決定の場合に前記工程データ記憶部に記憶させるシミュレーション部とを備え、前記ガントチャート表示データ作成部は、前記能率変更データ記憶部を参照し、能率変更後の作業工程の能率に対応して、前記矩形領域の高さを変更して、前記表示手段に与えるチャート高さ補正部を備えることを特徴とする。
Preferably, the process adjustment unit includes a process data storage unit that stores current work process data, an efficiency change process data storage unit that stores a work process designated by the efficiency change process designation unit, and the work assignment change. The work was performed in the order of the work processes specified by the assignment change data with reference to the assignment change data storage section for storing the work assignment changed in the department, the efficiency change process data storage section and the assignment change data storage section. In such a case, the work process specified by the efficiency change process data so that the area of the rectangular area of each work process becomes a fixed work amount necessary for the work process, and a predetermined process interval is maintained. An efficiency change value calculation unit for changing the efficiency in step, an efficiency change data storage unit for storing efficiency change data obtained by the efficiency change value calculation unit, and the step A data storage unit and an efficiency change data storage unit, re-create the changed work process table that has shifted each work process, and comprises a simulation unit to store in the process data storage unit in the case of determination, The Gantt chart display data creation unit refers to the efficiency change data storage unit, changes the height of the rectangular area according to the efficiency of the work process after the efficiency change, and gives the chart height to the display means It is characterized by comprising a thickness correction unit.

上記の構成によれば、入力操作部から、前記作業工程の追加や時間帯の変更等を受付けると、作業割り付け変更部が、予め作成された作業工程表に対して、変更が受付けられた作業工程の作業時間帯を変更する一方、能率変更工程指定部が、経験の浅い作業者からベテランに変更したり、作業者を増加するなどして、前記能率を変更できそうな作業工程の候補を受付ける。続いて、工程調整部が、前記作業割り付け変更部によって割り付けられた作業工程の順で作業を行った場合に、前記各作業工程間に予め定められた工程間隔を維持するように、前記能率変更工程指定部によって指定された作業工程に対して、前記矩形領域の面積がその作業工程に必要な一定の作業量となるように、前記矩形領域の作業時間を伸縮させるとともに前記能率を変更し、かつその作業工程をシフトさせ(作業開始および終了時刻をずらす)、該変更後の作業工程表を再作成する。   According to the above configuration, when the addition of the work process or the change of the time zone is accepted from the input operation part, the work assignment change part is a work whose change is accepted with respect to the work process table created in advance. While changing the work time zone of the process, the efficiency change process designating section changes candidates from inexperienced workers to veterans, increasing the number of workers, etc. Accept. Subsequently, when the process adjustment unit performs work in the order of the work processes assigned by the work assignment change part, the efficiency change is performed so as to maintain a predetermined process interval between the work processes. For the work process designated by the process designating unit, the work area of the rectangular area is expanded and contracted and the efficiency is changed so that the area of the rectangular area becomes a constant work amount necessary for the work process, And the work process is shifted (work start and end times are shifted), and the changed work process table is recreated.

したがって、前記作業工程の追加や時間帯の変更等が生じても、その変更された作業工程付近の工程の能率を変更することで、該変更に容易に対応することができる。前記シミュレーションの結果、納期を満足する等で、その作業工程表で決定の場合、作業工程データ記憶部に登録するとともに、その作業工程によるガントチャートを表示手段に表示し、以後の工程管理を行えばよい。   Therefore, even if the work process is added or the time zone is changed, the change can be easily handled by changing the efficiency of the process in the vicinity of the changed work process. If the result of the simulation satisfies the delivery date, etc., and the decision is made in the work process chart, it is registered in the work process data storage unit, and a Gantt chart according to the work process is displayed on the display means to perform subsequent process management. Just do it.

また、本発明の工程管理装置では、前記チャート高さ補正部は、変更後の矩形領域の高さを、変更前の能率値に対する変更後の能率値の比を、変更前の矩形領域の高さに乗ずることで決定することを特徴とする。   Further, in the process management apparatus of the present invention, the chart height correction unit calculates the height of the rectangular area after the change, the ratio of the efficiency value after the change to the efficiency value before the change, and the height of the rectangular area before the change. It is characterized by determining by multiplying the size.

上記の構成によれば、能率値の変更の大きい作業工程と、小さい作業工程との違いを明確にすることができる。   According to said structure, the difference between a work process with a large change of an efficiency value and a small work process can be clarified.

したがって、前記能率の向上を人員の増加で対応するような場合に、いつ頃、どの程度必要かを視覚的に容易に認識することができる。   Therefore, when the improvement in efficiency is dealt with by increasing the number of personnel, it is possible to visually recognize when and how much is necessary.

さらにまた、本発明の工程管理装置では、前記能率変更値計算部は、前記能率変更工程データで指定された全作業工程における所要時間が一定のままで、前記割り付け変更データで指定された作業工程の増加分を吸収するように、前記能率を変更することを特徴とする。   Furthermore, in the process management apparatus according to the present invention, the efficiency change value calculation unit is configured such that the required time in all work processes specified by the efficiency change process data remains constant, and the work process specified by the allocation change data. The efficiency is changed so as to absorb the increased amount.

上記の構成によれば、作業工程の移動や割込みによる変更(修正)を行うにあたって、その影響が、前記能率の変更対象の作業工程以外に及ばないようにすることができる。   According to said structure, when performing a change (correction | amendment) by a movement or interruption of a work process, the influence can be made not to affect other than the work process of the said efficiency change object.

また、本発明の工程管理装置では、前記各作業工程における能率の変更量の上限を記憶する能率変更上限データ記憶部をさらに備え、前記能率変更値計算部は、変更後の能率を計算し、その計算結果が前記能率変更上限データ記憶部における上限値を超えている場合には、上限値を適用することを特徴とする。   The process management device of the present invention further includes an efficiency change upper limit data storage unit that stores an upper limit of the efficiency change amount in each work process, and the efficiency change value calculation unit calculates the efficiency after the change, When the calculation result exceeds the upper limit value in the efficiency change upper limit data storage unit, the upper limit value is applied.

上記の構成によれば、前記能率変更値計算部は、変更後の能率(処理時間)を計算してみて、その計算結果が能率変更上限データ記憶部に記憶される上限を超えており、したがって作業能率の向上に限界がある場合には、変更後の能率をその限界値とする。   According to said structure, the said efficiency change value calculation part calculates the efficiency (processing time) after a change, The calculation result exceeds the upper limit memorize | stored in an efficiency change upper limit data storage part, Therefore If there is a limit to the improvement of work efficiency, the changed efficiency is set as the limit value.

したがって、実行可能な範囲で、工程の修正が可能となる。   Therefore, the process can be corrected within the feasible range.

さらにまた、本発明の工程管理装置では、前記シミュレーション部は、前記能率変更値計算部で前記変更後の能率に上限値が適用された場合には、当該作業工程以降の工程の開始および終了時刻を遅らせることで、変更後の作業工程表を再作成することを特徴とする。   Furthermore, in the process management apparatus of the present invention, when the upper limit value is applied to the efficiency after the change by the efficiency change value calculation unit, the simulation unit starts and ends the process after the work process. It is characterized by re-creating the work process table after the change by delaying.

上記の構成によれば、前記シミュレーション部は、能率変更後の作業工程表を再作成するにあたって、変更対象の作業工程の能率を上限まで拡大した上で、以降の工程については、その開始時刻および終了時刻を遅らせる。   According to the above configuration, the simulation unit, when re-creating the work process table after the efficiency change, expands the efficiency of the work process to be changed to the upper limit, and for the subsequent processes, the start time and Delay the end time.

したがって、変更対象の作業工程の能率を上限まで拡大した上で、前記能率変更工程データで指定された全作業工程における所要時間内に収まらない場合は、その所要時間を延長することになるので、前記能率の向上に制限がある場合でも、高い柔軟性で工程の修正が可能になる。   Therefore, after expanding the efficiency of the work process to be changed to the upper limit, if it does not fall within the required time in all the work processes specified in the efficiency change process data, the required time will be extended, Even when the improvement in efficiency is limited, the process can be modified with high flexibility.

また、本発明の工程管理装置では、前記各作業工程における能率の変更量の上限を記憶する能率変更上限データ記憶部と、前記能率変更値計算部で計算された能率が前記上限値を超えているか否かから、前記能率変更工程指定部による前記能率変更工程の割付けの可否を判断し、割付けが不可能な場合は、前記能率変更工程指定部に、前記能率変更工程を追加させる割付け変更可否判断部とをさらに備えることを特徴とする。   In the process management apparatus of the present invention, the efficiency change upper limit data storage unit that stores the upper limit of the efficiency change amount in each work process, and the efficiency calculated by the efficiency change value calculation unit exceeds the upper limit value. Whether or not the efficiency change process can be assigned by the efficiency change process designating unit. If the allocation is impossible, the efficiency change process designating unit adds the efficiency change process. And a determination unit.

上記の構成によれば、前記能率変更工程指定部によって指定された能率変更の対象となる処理開始時刻が最も早い工程の開始時刻から、処理完了時刻が最も遅い工程の完了時刻までの時間幅内で、追加の工程を割込ませるにあたって、割付け変更可否判断部は、前記能率変更値計算部で計算された各工程の能率の拡大幅が、能率変更上限データ記憶部に記憶されているそれぞれの工程における能率の上限を超えているかどうかから、能率変更の対象となる作業工程の割付けの妥当性を判断する。その結果、必要な拡大幅が上限を超えている場合、すなわち割付け不可能な場合は、前記能率変更工程指定部に前記能率変更工程を追加させ、同様の判定を行う。   According to the above configuration, within the time span from the start time of the process having the earliest process start time specified by the efficiency change process specifying unit to the completion time of the process having the latest process completion time. Then, in interrupting the additional process, the allocation change permission determination unit, the expansion width of the efficiency of each process calculated in the efficiency change value calculation unit, each stored in the efficiency change upper limit data storage unit The validity of the allocation of the work process that is the target of the efficiency change is judged from whether or not the upper limit of the efficiency in the process is exceeded. As a result, when the necessary expansion width exceeds the upper limit, that is, when allocation is impossible, the efficiency changing process is added to the efficiency changing process designating unit, and the same determination is performed.

したがって、能率変更の対象となる作業工程を事前に細かく指定しなくても、最低限の変更工程数で、実行可能な作業工程表を作成することができる。   Therefore, it is possible to create an executable work process table with the minimum number of change processes, without specifying the work process to be changed efficiently in advance.

本発明の工程管理装置は、以上のように、複数の各作業工程を、作業開始時期を前縁とし、作業終了時期を後縁とした矩形領域で表すガントチャートによって表示手段に表示し、前記作業工程を管理するにあたって、前記表示手段で表示される前記ガントチャートの表示データを作成するガントチャート表示データ作成部が、前記各作業工程における能率を前記矩形領域の高さで表す。   The process management apparatus of the present invention, as described above, displays each of the plurality of work processes on the display means by a Gantt chart represented by a rectangular area with the work start time as the leading edge and the work end time as the trailing edge, In managing a work process, a Gantt chart display data creation unit that creates display data of the Gantt chart displayed by the display means represents the efficiency in each work process by the height of the rectangular area.

それゆえ、作業者は各作業工程での現在の能率を、視覚的に容易に認識することができる。これによって、予め作成された作業工程に、納期の変更や他の作業の割込みが生じるなどして、作業工程を修正(調整)する必要が生じた場合に、どの工程の作業能率を向上して、作業時間をどれだけ詰められるか等、前記作業工程の修正(調整)に、容易かつ短時間で対応することができる。また、各作業工程での能率を視覚的に認識できることから、作業能率の向上を図るべき対策の必要な作業工程を容易に判断することもできる。   Therefore, the worker can easily visually recognize the current efficiency in each work process. This improves the work efficiency of any process when it becomes necessary to modify (adjust) the work process due to a change in delivery time or interruption of other work in a work process created in advance. It is possible to easily and quickly cope with correction (adjustment) of the work process, such as how much work time can be reduced. Further, since the efficiency in each work process can be visually recognized, it is possible to easily determine a work process that requires a countermeasure to improve the work efficiency.

本発明の実施の一形態に係る工程管理装置の電気的構成を示すブロック図である。It is a block diagram which shows the electric constitution of the process management apparatus which concerns on one Embodiment of this invention. 本発明の実施の一形態に係るガントチャートの表示の変更方法を説明するための図であり、初期状態を示す。It is a figure for demonstrating the change method of the display of the Gantt chart which concerns on one Embodiment of this invention, and shows an initial state. 本発明の実施の一形態に係るガントチャートの表示の変更方法を説明するための図であり、能率変更工程およびその能率値の指定の様子を示す。It is a figure for demonstrating the change method of the display of the Gantt chart which concerns on one Embodiment of this invention, and shows the mode of designation | designated of the efficiency change process and its efficiency value. 本発明の実施の一形態に係るガントチャートの表示の変更方法を説明するための図であり、変更後の様子を示す。It is a figure for demonstrating the change method of the display of the Gantt chart which concerns on one Embodiment of this invention, and shows the mode after a change. 本発明の実施の一形態に係るガントチャートの表示の変更方法を説明するためのフローチャートである。It is a flowchart for demonstrating the change method of the display of the Gantt chart which concerns on one Embodiment of this invention. 本発明の実施の他の形態に係る工程管理装置の電気的構成を示すブロック図である。It is a block diagram which shows the electric constitution of the process management apparatus which concerns on other embodiment of this invention. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、初期状態から作業割り付けの変更を指示した状態を示す。It is a figure for demonstrating the change method of the work process which concerns on other embodiment of this invention, and shows the state which instruct | indicated the change of work allocation from the initial state. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、作業割り付けの変更中の状態を示す。It is a figure for demonstrating the change method of the work process which concerns on other form of implementation of this invention, and shows the state under change of work assignment. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、作業割り付けの変更およびそれに伴う能率変更工程の指定の様子を示す。It is a figure for demonstrating the change method of the work process which concerns on other form of implementation of this invention, and shows the mode of designation | designated of the change of work allocation and the efficiency change process accompanying it. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、変更後の様子を示す。It is a figure for demonstrating the change method of the work process which concerns on other embodiment of this invention, and shows the mode after a change. 本発明の実施の他の形態に係る作業工程の変更方法を説明するためのフローチャートである。It is a flowchart for demonstrating the change method of the work process which concerns on other embodiment of this invention. 本発明の実施のさらに他の形態に係る工程管理装置の電気的構成を示すブロック図である。It is a block diagram which shows the electric constitution of the process management apparatus which concerns on the further another form of implementation of this invention. 本発明の実施のさらに他の形態に係る作業工程の変更方法を説明するための図であり、初期状態から作業割り付けの変更を指示した状態を示す。It is a figure for demonstrating the change method of the work process which concerns on the further another form of implementation of this invention, and shows the state which instruct | indicated the change of work allocation from the initial state. 本発明の実施のさらに他の形態に係る作業工程の変更方法を説明するための図であり、作業割り付けの変更中の状態を示す。It is a figure for demonstrating the change method of the work process which concerns on the further another form of implementation of this invention, and shows the state in the middle of work assignment change. 本発明の実施のさらに他の形態に係る作業工程の変更方法を説明するための図であり、作業割り付けの変更およびそれに伴う能率変更工程の指定の様子を示す。It is a figure for demonstrating the change method of the work process which concerns on the further another form of implementation of this invention, and shows the mode of designation | designated of the change of work allocation and the efficiency change process accompanying it. 本発明の実施のさらに他の形態に係る作業工程の変更方法を説明するための図であり、能率変更工程の再指定の様子を示す。It is a figure for demonstrating the change method of the work process which concerns on other form of implementation of this invention, and shows a mode of re-designation of an efficiency change process. 本発明の実施のさらに他の形態に係る作業工程の変更方法を説明するための図であり、変更後の様子を示す。It is a figure for demonstrating the change method of the work process which concerns on other form of implementation of this invention, and shows the mode after a change. 本発明の実施のさらに他の形態に係る作業工程の変更方法を説明するためのフローチャートである。It is a flowchart for demonstrating the change method of the work process which concerns on further another form of implementation of this invention. 本発明の実施の他の形態に係る工程管理装置の電気的構成を示すブロック図である。It is a block diagram which shows the electric constitution of the process management apparatus which concerns on other embodiment of this invention. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、初期状態を示す。It is a figure for demonstrating the change method of the work process which concerns on other embodiment of this invention, and shows an initial state. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、初期状態から作業割り付けの変更を指示した状態を示す。It is a figure for demonstrating the change method of the work process which concerns on other embodiment of this invention, and shows the state which instruct | indicated the change of work allocation from the initial state. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、作業割り付けの変更中の状態を示す。It is a figure for demonstrating the change method of the work process which concerns on other form of implementation of this invention, and shows the state under change of work assignment. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、作業割り付けの変更およびそれに伴う能率変更工程の指定の様子を示す。It is a figure for demonstrating the change method of the work process which concerns on other form of implementation of this invention, and shows the mode of designation | designated of the change of work allocation and the efficiency change process accompanying it. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、能率変更工程の再指定の様子を示す。It is a figure for demonstrating the change method of the work process which concerns on other embodiment of this invention, and shows the mode of re-designation of an efficiency change process. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、能率変更工程の再々指定の様子を示す。It is a figure for demonstrating the change method of the work process which concerns on other form of implementation of this invention, and shows a mode that the efficiency change process is designated again. 本発明の実施の他の形態に係る作業工程の変更方法を説明するための図であり、変更後の様子を示す。It is a figure for demonstrating the change method of the work process which concerns on other embodiment of this invention, and shows the mode after a change. 本発明の実施の他の形態に係る作業工程の変更方法を説明するためのフローチャートである。It is a flowchart for demonstrating the change method of the work process which concerns on other embodiment of this invention.

(実施の形態1)
図1は、本発明の実施の一形態に係る工程管理装置1の電気的構成を示すブロック図である。この工程管理装置1は、後述の図2〜図4で示すように、複数の各作業工程を、作業開始時期を前縁とし、作業終了時期を後縁とした矩形領域で表すガントチャートによって表示手段21に表示し、前記作業工程を管理する装置である。
(Embodiment 1)
FIG. 1 is a block diagram showing an electrical configuration of a process management apparatus 1 according to an embodiment of the present invention. As shown in FIGS. 2 to 4 to be described later, the process management apparatus 1 displays a plurality of work processes by a Gantt chart that is represented by a rectangular area having a work start time as a leading edge and a work end time as a trailing edge. It is an apparatus that displays on means 21 and manages the work process.

この工程管理装置1は、大略的に、前記表示手段21を備える表示部2と、入力操作部3と、工程調整部4と、ガントチャート表示データ作成部5とを備えて構成される。前記表示部2は、前記表示手段21と、後述する各種の信号に応答して、液晶ディスプレイなどから成る前記表示手段21を表示駆動する出力インタフェイス22とを備えて構成される。前記入力操作部3は、マウスやキーボードなどから成る入力手段31と、作業者による前記入力手段31への入力操作を所定の入力の信号に変換する入力インタフェイス32とを備えて構成される。   The process management apparatus 1 is generally configured to include a display unit 2 including the display unit 21, an input operation unit 3, a process adjustment unit 4, and a Gantt chart display data creation unit 5. The display unit 2 includes the display unit 21 and an output interface 22 that displays and drives the display unit 21 including a liquid crystal display in response to various signals described below. The input operation unit 3 includes an input unit 31 including a mouse and a keyboard, and an input interface 32 that converts an input operation to the input unit 31 by an operator into a predetermined input signal.

前記工程調整部4は、現在の作業工程データを記憶する工程データ記憶部41と、初期の作業工程データを作成する初期工程作成部42と、前記入力手段31からの入力操作に応答し、後述するように能率を変更すべき作業工程を指定する能率変更工程指定部43と、前記入力手段31からの入力操作に応答し、前記能率の変更値を指定する能率指定部44と、前記能率変更工程指定部43で指定された作業工程および前記能率指定部44で指定された能率の変更値を記憶する能率変更データ記憶部45と、前記工程データ記憶部41および能率変更データ記憶部45を参照し、能率変更後の作業工程表を再作成するとともに、決定の場合に前記工程データ記憶部41に記憶させるシミュレーション部46とを備えて構成される。   The process adjustment unit 4 responds to an input operation from the input means 31 and a process data storage unit 41 that stores current work process data, an initial process creation unit 42 that creates initial work process data, and will be described later. An efficiency changing process specifying unit 43 for specifying a work process whose efficiency should be changed, an efficiency specifying unit 44 for specifying a change value of the efficiency in response to an input operation from the input means 31, and the efficiency changing Refer to the efficiency change data storage unit 45 for storing the work process specified by the process specification unit 43 and the change value of the efficiency specified by the efficiency specification unit 44, and the process data storage unit 41 and the efficiency change data storage unit 45. In addition, the operation process table after the efficiency change is re-created, and the simulation unit 46 is configured to be stored in the process data storage unit 41 in the case of determination.

注目すべきは、本実施の形態では、前記ガントチャート表示データ作成部5は、前記工程データ記憶部41に記憶されている作業工程データを前記表示手段21にガントチャートで表示させるためのデータを作成するにあたって、前記能率変更データ記憶部45を参照し、能率変更後の作業工程の能率に対応して、矩形領域の高さを変更して、前記表示手段21に与えることである。   It should be noted that in the present embodiment, the Gantt chart display data creation unit 5 displays data for displaying the work process data stored in the process data storage unit 41 on the display unit 21 in a Gantt chart. In creating, referring to the efficiency change data storage unit 45, the height of the rectangular area is changed according to the efficiency of the work process after the efficiency change, and is given to the display means 21.

図2〜図4は、そのガントチャートの表示の変更方法を説明するための図である。本実施の形態では、作業工程(リソース)は縦軸で示すように5工程、作業時間は横軸で示し、作業すべきワーク(ロット)は参照符号A,B,C,D,Eの5つとする。そして、同じ作業工程でも、ワークの量などによって作業時間は異なる(図2の例では、40分から220分)。また、ワーク間および隣接作業工程間には、ワークの交換や引き渡しなどのために、規定の時間間隔(リードタイム)が設定されており、最短で、ワークの交換には10分、ワークの引き渡しには30分が規定されている。また、ワークの納期は、作業工程の開始時刻からの相対時間で与えられており、三角の指標で示すように、ワークA,B,C,D,E毎に、620分、700分、880分、930分、1080分となっている。   2-4 is a figure for demonstrating the change method of the display of the Gantt chart. In the present embodiment, the work process (resource) is represented by 5 processes as indicated by the vertical axis, the work time is represented by the horizontal axis, and the work (lot) to be worked is indicated by reference numerals A, B, C, D and E. I will. Even in the same work process, the work time varies depending on the amount of work and the like (in the example of FIG. 2, from 40 minutes to 220 minutes). In addition, a specified time interval (lead time) is set between workpieces and between adjacent work processes for workpiece exchange and delivery, etc., and the workpiece delivery takes 10 minutes at the shortest. 30 minutes is specified for Moreover, the delivery date of the work is given as a relative time from the start time of the work process, and as shown by the triangular index, 620 minutes, 700 minutes, 880 for each work A, B, C, D, E. Minutes, 930 minutes and 1080 minutes.

先ず、図2は、前記初期工程作成部42で作成されたままの作業工程を示すガントチャートである。ワークA,B,C,D,E毎に、それぞれ異なる作業時間に、ワークの交換時間およびワークの引き渡し時間が積み上げられて、完了時間となっていることが理解される。ただし、作業時間が長くなる工程(図2〜図4の例では工程3)では、自工程の処理が終了するまで、前工程(工程2)の完了品を受け入れられないので、これらの工程間の引き渡し時間は、ワークを処理するに連れて長くなっている。   First, FIG. 2 is a Gantt chart showing the work process as created by the initial process creation unit 42. It is understood that the workpiece replacement time and the workpiece delivery time are accumulated at different work times for each of the workpieces A, B, C, D, and E, and the completion time is obtained. However, in the process in which the work time becomes long (process 3 in the example of FIGS. 2 to 4), the completed product of the previous process (process 2) cannot be accepted until the processing of the self process is completed. The delivery time is longer as the workpiece is processed.

そして、図2の例では、最先で、かつ比較的作業量の少ないワークAおよび最終で、比較的納期に余裕のあるワークEについては、納期に間に合っているけれども、それら以外のワークB,C,Dについては、納期遅れを生じている。   In the example of FIG. 2, the first work, the work A with a relatively small work amount, and the last work E, which has a relatively long delivery time, are in time for delivery, but the other works B, For C and D, there is a delay in delivery.

この状態で作業者は、ガントチャートを見渡し、納期遅れの解消に効果的であり、かつ能率向上の余地があると思われる作業工程を、入力手段31から指定する(図3の例では、前記のワークB,C,Dを指定)。その指定に応答して、能率変更工程指定部43は、能率変更工程を指定するデータを作成し、能率変更データ記憶部45に与えるとともに、出力インタフェイス22に与え、これによって表示手段21での表示は、図3で示すように、その変更対象となる作業工程が変色表示される。或いは点滅や、図3において参照符号α1で示すような枠掛け表示などが行われてもよい。   In this state, the operator looks over the Gantt chart, and designates a work process that is effective in eliminating the delay in delivery time and has room for improvement in efficiency from the input means 31 (in the example of FIG. Specify workpieces B, C, and D). In response to the designation, the efficiency changing process designating unit 43 creates data for designating the efficiency changing process and gives it to the efficiency changing data storage unit 45 and also gives it to the output interface 22. As shown in FIG. 3, the work process to be changed is discolored and displayed. Alternatively, blinking or a framed display as indicated by reference numeral α1 in FIG. 3 may be performed.

また、前記入力手段31からの能率変更工程の指定に応答して、能率指定部44は、変更倍率の入力画面データを作成し、前記出力インタフェイス22に与えることで、図3において参照符号α2で示すような入力画面表示が行われる。これに応答して作業者が入力手段31から前記変更倍率を入力すると(図3の例では1.5倍)、前記能率指定部44は、その変更倍率を指定するデータを作成し、能率変更データ記憶部45に与えるとともに、出力インタフェイス22に与える。   Further, in response to the specification of the efficiency changing process from the input means 31, the efficiency specifying unit 44 creates input screen data of the change magnification and gives it to the output interface 22, so that the reference symbol α2 in FIG. The input screen display as shown in FIG. In response to this, when the operator inputs the change magnification from the input means 31 (1.5 in the example of FIG. 3), the efficiency designating unit 44 creates data for designating the change magnification, and changes the efficiency. The data is given to the data storage unit 45 and also given to the output interface 22.

その後、前記入力手段31からのシミュレーションの開始操作などに応答して、シミュレーション部46は、前記工程データ記憶部41および能率変更データ記憶部45を参照し、能率変更後の作業工程表を再作成し、前記工程データ記憶部41を介してガントチャート表示データ作成部5に与え、表示手段21でのガントチャートの表示データを作成する。このとき、前記ガントチャート表示データ作成部5のチャート高さ補正部51は、前記能率変更データ記憶部45を参照し、変更前の能率値に対する変更後の能率値の比を、変更前の矩形領域の高さに乗じて新たな矩形領域の表示データを作成する。   Thereafter, in response to a simulation start operation or the like from the input means 31, the simulation unit 46 refers to the process data storage unit 41 and the efficiency change data storage unit 45 and re-creates the work process table after the efficiency change. Then, the data is given to the Gantt chart display data creation unit 5 via the process data storage unit 41, and the display data of the Gantt chart on the display means 21 is created. At this time, the chart height correction unit 51 of the Gantt chart display data creation unit 5 refers to the efficiency change data storage unit 45 and calculates the ratio of the efficiency value after the change to the efficiency value before the change to the rectangle before the change. Multiply the height of the area to create display data for a new rectangular area.

これによって、図2の初期状態から、たとえば図3で示すように、工程3のワークB,C,Dについて、能率値を1.5倍とすることで、シミュレーション結果は図4で示すように、処理時間は1/1.5に短縮される。すなわち、ワークB,C,Dの工程3における本来の処理時間は、それぞれ150分、160分、60分であるので、100分、107分、40分に短縮することができる。   Thus, from the initial state of FIG. 2, for example, as shown in FIG. 3, by increasing the efficiency value by 1.5 times for the workpieces B, C, and D in step 3, the simulation result is as shown in FIG. The processing time is reduced to 1 / 1.5. That is, since the original processing time in the process 3 of the workpieces B, C, and D is 150 minutes, 160 minutes, and 60 minutes, respectively, it can be shortened to 100 minutes, 107 minutes, and 40 minutes.

こうして、前記ワークB以降の以降の工程4,5での作業開始時間が早まり、前記ワークB,C,Dの納期遅れを解消することができる作業工程表を再作成することができる。なお、図3および図4の例では、3つのワークB,C,Dに一括に同じ能率値を設定しているけれども、個別に設定してもよい。   Thus, the work start time in the subsequent processes 4 and 5 after the work B is advanced, and the work process chart capable of eliminating the delay in delivery of the work B, C, and D can be recreated. In the example of FIGS. 3 and 4, the same efficiency value is set for the three works B, C, and D at once, but may be set individually.

前記シミュレーションの結果、納期を満足する等で、再作成された作業工程表で決定の場合には、作業者は入力手段31から決定操作などを行うことで、その再作成された作業工程表は工程データ記憶部41に記憶され、その作業工程表によるガントチャートを表示手段21に表示し、以後の工程管理が行われる。これに対して、決定でない場合は、作業者は再度能率変更工程の指定や倍率の指定を繰返す。   As a result of the simulation, if the decision is made with the re-created work process table due to satisfying the delivery date, etc., the operator performs a determination operation or the like from the input means 31, and the re-created work process table is A Gantt chart stored in the process data storage unit 41 and based on the work process table is displayed on the display means 21, and subsequent process management is performed. On the other hand, if it is not a decision, the worker repeats the specification of the efficiency changing process and the specification of the magnification again.

図5は、上述のようなガントチャートの表示の変更方法を説明するためのフローチャートである。ステップS1では、初期工程作成部42によって初期の作業工程データが作成されて工程データ記憶部41に記憶され、ステップS2では、その作業工程データから、ガントチャート表示データ作成部5がガントチャート表示データを作成し、表示部2に与えて表示を行わせる。ステップS3では、入力手段31から終了の指示があったか否かが判断され、終了の指示が行われると処理を終了してそのガントチャートのままで工程が管理され、終了でない、すなわち作業工程を変更(修正)する場合にはステップS4に移る。   FIG. 5 is a flowchart for explaining a method for changing the display of the Gantt chart as described above. In step S1, initial work process data is created by the initial process creation unit 42 and stored in the process data storage unit 41. In step S2, the Gantt chart display data creation unit 5 uses the Gantt chart display data from the work process data. Is generated and given to the display unit 2 for display. In step S3, it is determined whether or not there is an end instruction from the input means 31, and when the end instruction is given, the process is terminated and the process is managed as it is in the Gantt chart. In the case of (correction), the process proceeds to step S4.

ステップS4では、前記能率値を変更すべき1または複数の作業工程が入力手段31から指定されるとともに、その作業工程の表示が行われ、ステップS5では、各作業工程に対する能率変更値の入力画面が表示され、それに伴い入力操作が行われる。ステップS6では、それらの変更値の入力結果に応答して、シミュレーション部46がシミュレーションを行い、その結果から、ステップS7で、ガントチャート表示データ作成部5がガントチャートの表示データを作成して表示手段21に表示させるにあたって、チャート高さ補正部51が、変更前の能率値に対する変更後の能率値の比を、変更前の矩形領域の高さに乗じて新たな矩形領域の表示データを作成する。   In step S4, one or more work processes whose efficiency values are to be changed are designated from the input means 31, and the work processes are displayed. In step S5, an efficiency change value input screen for each work process is displayed. Is displayed, and an input operation is performed accordingly. In step S6, the simulation unit 46 performs a simulation in response to the input results of the changed values. From the result, the Gantt chart display data creation unit 5 creates and displays the Gantt chart display data in step S7. When displaying on the means 21, the chart height correction unit 51 multiplies the ratio of the efficiency value after the change to the efficiency value before the change to the height of the rectangle area before the change, and creates display data for a new rectangular area. To do.

このようにガントチャート表示データ作成部5がガントチャートの表示データを作成して表示手段21に表示させるにあたって、チャート高さ補正部51が、矩形領域の高さを、現在の各作業工程における能率値に対応した高さとする表示データを作成することで、作業者は各作業工程での現在の能率を、視覚的に容易に認識することができる。これによって、予め作成された作業工程に、納期の変更や他の作業の割込みが生じるなどして、作業工程を修正(調整)する必要が生じた場合に、どの工程の作業能率を向上して、作業時間をどれだけ詰められるか等、前記作業工程の修正(調整)に、容易かつ短時間で対応することができる。前記の作業工程の修正(調整)結果は、適宜ラインに伝達される。また、各作業工程での能率を視覚的に認識できることから、作業能率の向上を図るべき対策の必要な作業工程を容易に判断することもできる。   In this way, when the Gantt chart display data creation unit 5 creates Gantt chart display data and displays it on the display means 21, the chart height correction unit 51 determines the height of the rectangular area in each current work process. By creating display data having a height corresponding to the value, the worker can easily visually recognize the current efficiency in each work process. This improves the work efficiency of any process when it becomes necessary to modify (adjust) the work process due to a change in delivery time or interruption of other work in a work process created in advance. It is possible to easily and quickly cope with correction (adjustment) of the work process, such as how much work time can be reduced. The result of correction (adjustment) of the work process is appropriately transmitted to the line. Further, since the efficiency in each work process can be visually recognized, it is possible to easily determine a work process that requires a countermeasure to improve the work efficiency.

また、前記チャート高さ補正部51は、作業能率の変更後の矩形領域の高さを、変更前の能率値に対する変更後の能率値の比を変更前の高さに乗じた値とするので、能率値の変更の大きい作業工程と、小さい作業工程との違いを明確にすることができる。これによって、前記能率の向上を人員の増加で対応するような場合に、いつ頃、どの程度必要かを視覚的に容易に認識することができる。なお、前記比は、前記能率値の比を正確に反映したものでなくてもよく、分り易く、たとえば10%までは10%、それを超えて20%までは20%というように、段階的に増加するものであってもよい。   Further, the chart height correcting unit 51 sets the height of the rectangular area after the change of the work efficiency to a value obtained by multiplying the ratio before the change by the ratio of the efficiency value after the change to the efficiency value before the change. The difference between a work process with a large change in efficiency value and a small work process can be clarified. This makes it possible to easily visually recognize when and how much it is necessary when the improvement in efficiency is handled by an increase in personnel. The ratio may not accurately reflect the ratio of the efficiency values, and is easy to understand, for example, 10% up to 10% and 20% up to 20%. May be increased.

さらにまた、経験の浅い作業者からベテランに変更したり、作業者を増加するなどして、前記能率を変更する場合に、入力手段31から1または複数の任意の作業工程の能率を変更してみて、その結果を、工程調整部4のシミュレーション部46は、前記矩形領域の面積が一定、すなわち一定の作業量を確保しつつ、前記矩形領域の期間を伸縮させ、かつ予め定められた工程間隔を維持するように、前記能率変更後の作業工程をシフトさせる(作業開始および終了時刻をずらす)シミュレーションを行うので、前記変更の適否を容易に判定することができる。これによって、最も効果的な作業工程となるように、作業工程表の修正(調整)を行うことができる。   Furthermore, when changing the efficiency by changing from an inexperienced worker to an experienced worker or increasing the number of workers, the efficiency of one or more arbitrary work processes is changed from the input means 31. As a result, the simulation unit 46 of the process adjustment unit 4 expands and contracts the period of the rectangular region while ensuring a constant work amount, that is, a constant work amount, and a predetermined process interval. Therefore, it is possible to easily determine the suitability of the change because the simulation is performed to shift the work process after the efficiency change (shift the work start and end times). As a result, the work process chart can be corrected (adjusted) so as to be the most effective work process.

(実施の形態2)
図6は、本発明の実施の他の形態に係る工程管理装置1aの電気的構成を示すブロック図である。この工程管理装置1aは、前述の工程管理装置1に類似し、対応する部分には同一の参照符号を付して示し、その説明を省略する。前述の工程管理装置1では、予め定められた作業工程を守りながら、単に指定された作業工程の能率をアップした工程をシミュレーションしていたのに対して、注目すべきは、この工程管理装置1aでは、前記作業工程の追加や時間帯の変更等に対して、能率をアップする作業工程と、そのアップ率とを定め、結果をシミュレーションすることである。
(Embodiment 2)
FIG. 6 is a block diagram showing an electrical configuration of a process management apparatus 1a according to another embodiment of the present invention. This process management apparatus 1a is similar to the above-described process management apparatus 1, and corresponding portions are denoted by the same reference numerals, and description thereof is omitted. In the process management apparatus 1 described above, a process in which the efficiency of a designated work process is simply improved while observing a predetermined work process is to be noted. Then, with respect to the addition of the work process, the change of the time zone, etc., the work process for increasing the efficiency and the up rate are determined, and the result is simulated.

すなわち、入力手段31から前記作業工程の追加や時間帯の変更等を受付けると、作業割り付け変更部6が、前記初期工程作成部42で予め作成された作業工程表に対して、変更が受付けられた作業工程の作業時間帯を変更する一方、能率変更工程指定部7が、経験の浅い作業者からベテランに変更したり、作業者を増加するなどして、前記能率を変更できそうな作業工程の候補を、変更が受付けられた作業工程の前または後の少なくとも一方側の所定範囲の作業工程について受付ける。   That is, when an addition of the work process, a change in time zone, or the like is received from the input unit 31, the work allocation change unit 6 receives a change from the work process table created in advance by the initial process creation unit 42. While changing the working time zone of the working process, the efficiency changing process designating unit 7 may change the efficiency by changing from an inexperienced worker to an experienced worker or increasing the number of workers. Are accepted for a predetermined range of work processes on at least one side before or after the work process in which the change is accepted.

このため、工程調整部4aには、前記工程データ記憶部41と、初期工程作成部42と、能率変更データ記憶部45aと、シミュレーション部46aとが設けられるとともに、能率変更工程データ記憶部47と、割り付け変更データ記憶部48と、能率変更値計算部49とが設けられる。   Therefore, the process adjustment unit 4a includes the process data storage unit 41, the initial process creation unit 42, the efficiency change data storage unit 45a, and the simulation unit 46a, and the efficiency change process data storage unit 47. An allocation change data storage unit 48 and an efficiency change value calculation unit 49 are provided.

前記能率変更工程データ記憶部47は、前記能率変更工程指定部7で指定された作業工程を記憶する。前記割り付け変更データ記憶部48は、前記作業割り付け変更部6で変更された作業割り付けを記憶する。前記能率変更値計算部49は、前記能率変更工程データ記憶部47および割り付け変更データ記憶部48を参照し、割り付け変更データで指定された作業工程の順で作業を行った場合に、各作業工程の矩形領域の面積がその作業工程に必要な一定の作業量となるように、かつ予め定められた工程間隔を維持するように、能率変更工程データで指定される作業工程における前記能率を変更する。この能率変更値計算部49で求められた能率変更データは、能率変更データ記憶部45aに記憶される。 The efficiency change process data storage unit 47 stores the work process designated by the efficiency change process designation unit 7. The assignment change data storage unit 48 stores the work assignment changed by the work assignment change unit 6. When the efficiency change value calculation unit 49 refers to the efficiency change process data storage unit 47 and the allocation change data storage unit 48 and performs work in the order of the work processes specified by the allocation change data, The efficiency in the work process specified by the efficiency change process data is changed so that the area of the rectangular area becomes a constant work amount necessary for the work process and a predetermined process interval is maintained. . The efficiency change data obtained by the efficiency change value calculation unit 49 is stored in the efficiency change data storage unit 45a.

一方、シミュレーション部46aは、前記工程データ記憶部41および能率変更データ記憶部45aを参照し、各作業工程をシフトさせた変更後の作業工程表を再作成し、前記工程データ記憶部41から前記ガントチャート表示データ作成部5を介して表示手段21に表示させるとともに、再作成された作業工程表が決定の場合に、前記工程データ記憶部41に記憶させる。前記ガントチャート表示データ作成部5のチャート高さ補正部51は、前記能率変更データ記憶部45aを参照し、能率変更後の作業工程の能率に対応して、前記ガントチャートにおける矩形領域の高さを変更したガントチャート表示データ作成を作成する。   On the other hand, the simulation unit 46a refers to the process data storage unit 41 and the efficiency change data storage unit 45a, re-creates the changed work process table in which each work process is shifted, and stores the process data storage unit 41 from the process data storage unit 41. The data is displayed on the display means 21 via the Gantt chart display data creation unit 5 and is stored in the process data storage unit 41 when the re-created work process table is determined. The chart height correction unit 51 of the Gantt chart display data creation unit 5 refers to the efficiency change data storage unit 45a and corresponds to the height of the rectangular area in the Gantt chart corresponding to the efficiency of the work process after the efficiency change. Create the Gantt chart display data creation with changed.

図7〜図10は、上述のような作業工程の変更方法を説明するための図である。本実施の形態では、作業工程(リソース)は縦軸で示すように5工程、作業時間は横軸で示し、作業すべきワークは参照符号A,B,C,D,E,Fの6つとする。また、図2と同様に、各作業工程の標準時間は40分から220分、ワーク間および隣接作業工程間の時間間隔は、それぞれ10分および30分である。さらにまた、ワークの納期は、ワークA,B,C,D,Eはスケール一杯の1100分、ワークFだけが、三角の指標で示すように、750分となっている。また、ワークFだけが、工程3までで、作業が終了(完成)するものとする。   7-10 is a figure for demonstrating the change method of the above work processes. In the present embodiment, the work process (resource) is represented by 5 processes as shown by the vertical axis, the work time is represented by the horizontal axis, and the works to be worked are six reference symbols A, B, C, D, E, and F. To do. Similarly to FIG. 2, the standard time for each work process is 40 to 220 minutes, and the time intervals between workpieces and adjacent work processes are 10 minutes and 30 minutes, respectively. Furthermore, the workpiece delivery time is 1100 minutes for the workpieces A, B, C, D, and E, and the workpiece F is only 750 minutes as indicated by the triangular index. Further, it is assumed that only the work F is completed (completed) by the process 3.

先ず、図7は、前記初期工程作成部42で作成されたままの作業工程を示すガントチャートである。当初から予定されていたワークA,B,C,D,E毎に、それぞれ異なる作業時間に、ワークの交換時間およびワークの引き渡し時間が積み上げられて、完了時間となっている。この状態で作業者が、作業割り付け変更部6から、工程3に、ワークFを追加するものとする。しかしながら、この図7で示すように、単純に、予定されていた総てのワークA,B,C,D,Eの処理が終了した後に作業が行われてのでは、納期に間に合わなくなっている。   First, FIG. 7 is a Gantt chart showing the work process as created by the initial process creation unit 42. For each work A, B, C, D, E scheduled from the beginning, the work exchange time and the work delivery time are accumulated at different work times, and the completion time is reached. In this state, it is assumed that the worker adds the work F to the process 3 from the work assignment changing unit 6. However, as shown in FIG. 7, if the work is simply performed after all the scheduled processing of the workpieces A, B, C, D, and E is completed, it is not in time for the delivery date. .

このため、作業者は、図8で示すように、その割込みが生じる工程3において、納期以前で、納期に最も近いワークの工程間隔C,D間に、前記ワークFの割込みを、前記作業割り付け変更部6から指定し、割り付け変更データ記憶部48に記憶させるとともに、図9で示すように、その割込みに伴い、能率を変更すべき作業工程を指定し、能率変更工程記憶部47に記憶させる(図9の例では、割り込まれるワークC,Dと、それ以前のワークA,Bとが、枠で指定されている)。   For this reason, as shown in FIG. 8, the worker assigns the work F interrupt to the work allocation between the process intervals C and D of the work closest to the delivery date before the delivery date in the process 3 where the interruption occurs. Designated from the change unit 6 and stored in the allocation change data storage unit 48, and as shown in FIG. 9, in accordance with the interruption, the work process whose efficiency should be changed is designated and stored in the efficiency change process storage unit 47. (In the example of FIG. 9, the work C and D to be interrupted and the previous work A and B are designated by a frame).

これに応答して、能率変更値計算部49は、割り付け変更データ記憶部48に記憶されているように、工程3において、ワークFを、ワークの工程間隔C,D間に嵌め込めるように、能率変更工程記憶部47に記憶されているワークA,B,C,D,Fに必要な能率変更値を計算する。その際、能率変更値計算部49は、前記能率変更工程記憶部47の能率変更工程データで指定された全作業工程(ワークA〜D間)における所要時間が一定のままで、前記割り付け変更データ記憶部48の割り付け変更データで指定された作業工程の増加分を吸収するように、前記能率を変更する。   In response to this, the efficiency change value calculation unit 49, as stored in the allocation change data storage unit 48, in step 3, the work F can be fitted between the work process intervals C and D. An efficiency change value necessary for the workpieces A, B, C, D, and F stored in the efficiency change process storage unit 47 is calculated. At that time, the efficiency change value calculation unit 49 keeps the required time in all the work processes (between workpieces A to D) specified by the efficiency change process data in the efficiency change process storage unit 47, and the allocation change data The efficiency is changed so as to absorb the increase in the work process specified by the allocation change data in the storage unit 48.

具体的には、各ワークA,B,C,F,Dの標準処理時間をTA,TB,TC,TF,TDとし、それぞれ130分、150分、160分、60分、80分であり、それらのワークA,B,C,F,Dの工程間隔をJとし、10分であり、工程3で能率を変更すべき最初のワークAの作業開始時刻をSAとし、270分であり、能率を変更すべき最後のワークDの作業開始時刻をEDとし、800分であり、Kを必要な能率アップの比とするとき、
(TA+TB+TC+TF+TD)×1/K+J×4=ED−SA ・・・(1)
したがって、
(130+150+160+60+80)×1/K+10×4=800−270
から、
K=58/49≒1.184
となる。
Specifically, the standard processing time of each work A, B, C, F, D is TA, TB, TC, TF, TD, respectively 130 minutes, 150 minutes, 160 minutes, 60 minutes, 80 minutes, The process interval of the workpieces A, B, C, F, and D is J, 10 minutes, the work start time of the first work A whose efficiency should be changed in the process 3 is SA, and 270 minutes. When the work start time of the last workpiece D to be changed is ED, it is 800 minutes, and K is the ratio of the required efficiency increase,
(TA + TB + TC + TF + TD) × 1 / K + J × 4 = ED−SA (1)
Therefore,
(130 + 150 + 160 + 60 + 80) × 1 / K + 10 × 4 = 800-270
From
K = 58/49 ≒ 1.184
It becomes.

これによって、各ワークA,B,C,D,E,Fの処理時間は、それぞれ109分、126分、135分、50分、67分となり、図10で示すように、割込み処理したワークFも、納期に間に合うようになったことが理解される。   As a result, the processing times of the workpieces A, B, C, D, E, and F are 109 minutes, 126 minutes, 135 minutes, 50 minutes, and 67 minutes, respectively. As shown in FIG. However, it is understood that it is now in time for delivery.

こうして求められた能率アップの比Kおよび各ワークA,B,C,D,E,Fの処理時間は、能率変更データ記憶部45aに記憶され、前記入力手段31からのシミュレーションの開始操作などに応答して、シミュレーション部46aは、前記比Kと、前記能率変更工程データおよび割り付け変更データに基づいて、工程および能率の変更後の作業工程表を再作成し、前記工程データ記憶部41を介してガントチャート表示データ作成部5に与え、表示手段21でのガントチャートの表示データを作成する。このとき、前記ガントチャート表示データ作成部5のチャート高さ補正部51は、前記能率変更データ記憶部45aを参照し、変更前の能率値に対する変更後の能率値の比Kを、変更前の矩形領域の高さに乗じて、図10で示すような、新たな矩形領域の表示データを作成する。   The efficiency increase ratio K and the processing times of the workpieces A, B, C, D, E, and F obtained in this way are stored in the efficiency change data storage unit 45a and used for the start operation of the simulation from the input means 31. In response, the simulation unit 46a re-creates the work process table after the process and the efficiency change based on the ratio K, the efficiency change process data, and the allocation change data, and passes the process data storage unit 41 through the process data storage unit 41. To the Gantt chart display data creation unit 5 to create display data of the Gantt chart on the display means 21. At this time, the chart height correction unit 51 of the Gantt chart display data creation unit 5 refers to the efficiency change data storage unit 45a and calculates the ratio K of the efficiency value after the change to the efficiency value before the change. By multiplying the height of the rectangular area, new rectangular area display data as shown in FIG. 10 is created.

このようなシミュレーションの結果、納期を満足する等で、再作成された作業工程表で決定の場合には、作業者は入力手段31から決定操作などを行うことで、その再作成された作業工程表は工程データ記憶部41に記憶され、その作業工程表によるガントチャートを表示手段21に表示し、以後の工程管理が行われる。これに対して、決定でない場合は、作業者は再度作業割り付けの指定や、能率変更工程の指定を繰返す。   As a result of such a simulation, when the delivery date is determined by satisfying the delivery date or the like, the worker performs a determination operation or the like from the input means 31 to perform the re-created work process. The table is stored in the process data storage unit 41, a Gantt chart based on the work process table is displayed on the display means 21, and subsequent process management is performed. On the other hand, if it is not a decision, the worker repeats the assignment of work and the designation of the efficiency changing process again.

なお、たとえばワークDの処理時間が短いなどして、納期以前で、納期に最も近いワークの工程間隔C,D間に、追加のワークFの割込みを行えない場合には、さらに以前のワークの工程間隔B,C間に嵌め込むようにしてもよく、さらに追加のワークFの工程3だけに限らず、それ以前の工程2,1について、能率をアップするようにしてもよい。また、割込みが生じた工程3以降の工程4,5において、前記工程3の能率アップによって、当初の予定よりも早くに処理の終了したワークA,Bについては、図10で示すように、当初の予定通りに処理するだけでなく、予定を繰り上げて処理するようにしてもよい。さらにまた、図10の例では、5つのワークA,B,C,F,Dに一括に同じ能率値を設定しているけれども、個別に設定してもよい。   For example, if the processing time of the workpiece D is short, and an additional workpiece F cannot be interrupted between the process intervals C and D of the workpiece closest to the delivery date before the delivery date, the previous workpiece You may make it engage | insert between process space | intervals B and C, Furthermore, you may make it improve not only the process 3 of the additional workpiece | work F but the processes 2 and 1 before that. Further, in steps 4 and 5 after the step 3 where the interruption occurs, the works A and B that have been processed earlier than originally planned due to the efficiency improvement of the step 3, as shown in FIG. In addition to processing according to the schedule, the schedule may be advanced and processed. Furthermore, in the example of FIG. 10, although the same efficiency value is set for the five workpieces A, B, C, F, and D at once, they may be set individually.

図11は、上述のような作業工程の変更方法を説明するためのフローチャートである。図5の処理に類似し、対応する部分には同一のステップ番号を付して示す。ステップS1では、初期工程作成部42によって初期の作業工程データが作成されて工程データ記憶部41に記憶され、ステップS2では、その作業工程データから、ガントチャート表示データ作成部5がガントチャート表示データを作成し、表示部2に与えて表示を行わせる。ステップS3では、入力手段31から終了の指示があったか否かが判断され、終了の指示が行われると処理を終了してそのガントチャートのままで工程が管理され、終了でない、すなわち作業工程を変更(修正)する場合にはステップS11に移る。   FIG. 11 is a flowchart for explaining a method for changing a work process as described above. Similar to the processing of FIG. 5, the corresponding steps are denoted by the same step numbers. In step S1, initial work process data is created by the initial process creation unit 42 and stored in the process data storage unit 41. In step S2, the Gantt chart display data creation unit 5 uses the Gantt chart display data from the work process data. Is generated and given to the display unit 2 for display. In step S3, it is determined whether or not there is an end instruction from the input means 31, and when the end instruction is given, the process is terminated and the process is managed as it is in the Gantt chart. In the case of (correction), the process proceeds to step S11.

ステップS11では、前記追加や時間帯の変更等を行うべき1または複数の作業工程が入力手段31から指定されるとともに、その作業工程の表示が行われ、ステップS12では、前記追加や時間帯の変更等に伴い、能率を変更すべき作業工程が入力手段31から指定されるとともに、その作業工程の表示が行われる。ステップS13では、その能率を変更すべき作業工程について、上述のようにして能率アップの比Kが求められる。ステップS6では、それらの変更値の入力結果に応答して、シミュレーション部46aがシミュレーションを行い、その結果から、ステップS7で、ガントチャート表示データ作成部5がガントチャートの表示データを作成して表示手段21に表示させるにあたって、チャート高さ補正部51が、変更前の能率値に対する変更後の能率値の比を、変更前の矩形領域の高さに乗じて新たな矩形領域の表示データを作成する。   In step S11, one or a plurality of work processes to be added or changed in time zone are designated from the input means 31, and the work process is displayed. In step S12, the addition or time zone is displayed. Along with the change or the like, a work process whose efficiency is to be changed is designated from the input means 31 and the work process is displayed. In step S13, the efficiency increase ratio K is determined for the work process whose efficiency should be changed as described above. In step S6, in response to the input results of these changed values, the simulation unit 46a performs a simulation. From the result, the Gantt chart display data creation unit 5 creates and displays display data for the Gantt chart in step S7. When displaying on the means 21, the chart height correction unit 51 multiplies the ratio of the efficiency value after the change to the efficiency value before the change to the height of the rectangle area before the change, and creates display data for a new rectangular area. To do.

このように構成することで、入力手段31から、作業割り付け変更部6に前記作業工程の追加や時間帯の変更を指定し、それに伴い、能率変更工程指定部7に能率を変更できそうな作業工程の候補を指定すると、工程調整部4aにおける能率変更値計算部49が、作業割り付け変更部6によって割り付けられた作業工程の順で作業を行った場合に、前記各作業工程間に予め定められた工程間隔を維持するように、前記能率変更工程指定部7によって指定された作業工程に対して、ガントチャートの矩形領域の面積がその作業工程に必要な一定の作業量となるように、前記矩形領域の能率を変更する一方、シミュレーション部46aが、求められた能率および作業時間に基づき、作業工程をシフトさせ(作業開始および終了時刻をずらす)、該変更後の作業工程表を再作成するので、前記作業工程の追加や時間帯の変更等が生じても、その変更された作業工程付近の工程の能率を変更することで、該変更に容易に対応することができる。すなわち、割り込ませる作業工程以外にも、前後の作業工程の能率を向上し、割り込ませる時間を捻出するようなケースで、従来では、その時間を捻出するのに、どの作業工程にはどれだけの能率の向上が必要であるのか等を、即座に見積もることが困難であり、机上での計算の後に、各作業工程の標準作業時間を記憶したマスターテーブルを変更するという非常に手間の掛る作業を行う必要があるのに対して、本実施の形態では、そのような煩雑な作業を不要にすることができる。   By configuring in this way, from the input means 31, the work allocation changing unit 6 is designated to add the work process or the time zone is changed, and accordingly, the work whose efficiency is likely to be changed to the efficiency changing process designating part 7. When a process candidate is designated, when the efficiency change value calculation unit 49 in the process adjustment unit 4a performs work in the order of the work processes assigned by the work assignment change unit 6, it is predetermined between the work processes. So that the area of the rectangular area of the Gantt chart is a certain amount of work necessary for the work process with respect to the work process designated by the efficiency change process designating unit 7 so as to maintain the process interval. While changing the efficiency of the rectangular area, the simulation unit 46a shifts the work process (shifts the work start and end times) based on the obtained efficiency and work time, Since the work schedule after the change is re-created, even if the work process is added or the time zone is changed, the change of the efficiency of the process near the changed work process can be easily changed. Can respond. In other words, in addition to the work process to be interrupted, it is a case where the efficiency of the previous and subsequent work processes is improved and the time to interrupt is devised. It is difficult to estimate immediately whether it is necessary to improve efficiency, etc., and after the calculation on the desk, the master table that stores the standard work time of each work process is changed. In contrast to this, in this embodiment, such a complicated operation can be eliminated.

また、前記能率変更値計算部49は、候補の全作業工程における所要時間が一定のままで、前記追加や時間帯の変更等を吸収するように、前記能率を変更するので、作業工程の移動や割込みによる変更(修正)を行うにあたって、その影響が、前記能率の変更対象の作業工程以外に及ばないようにすることができる。   In addition, the efficiency change value calculation unit 49 changes the efficiency so as to absorb the addition, the change of the time zone, and the like while the required time in all candidate work processes remains constant. When the change (correction) is performed due to or interruption, it is possible to prevent the influence from affecting the work process other than the efficiency change target.

(実施の形態3)
図12は、本発明の実施のさらに他の形態に係る工程管理装置1bの電気的構成を示すブロック図である。この工程管理装置1bは、前述の工程管理装置1aに類似し、対応する部分には同一の参照符号を付して示し、その説明を省略する。前述の工程管理装置1,1aでは、能率変更値計算部49による計算は、単に、許容される作業時間に、必要な作業量から能率のアップ率(前記比K)を定めているのに対して、注目すべきは、この工程管理装置1bの工程調整部4bでは、能率変更値計算部49bに関連して能率変更上限データ記憶部50がさらに設けられており、前記能率変更値計算部49bは、計算したアップ率(前記比K)が前記能率変更上限データ記憶部における上限値を超えている場合には、その上限値を適用(制限)することである。
(Embodiment 3)
FIG. 12 is a block diagram showing an electrical configuration of a process management apparatus 1b according to still another embodiment of the present invention. This process management device 1b is similar to the above-described process management device 1a, and the corresponding parts are denoted by the same reference numerals, and the description thereof is omitted. In the above-described process management apparatuses 1 and 1a, the calculation by the efficiency change value calculation unit 49 merely determines the efficiency increase rate (the ratio K) from the required work amount in the allowable work time. It should be noted that the process adjustment unit 4b of the process management apparatus 1b is further provided with an efficiency change upper limit data storage unit 50 in association with the efficiency change value calculation unit 49b, and the efficiency change value calculation unit 49b. Is to apply (limit) the upper limit value when the calculated up rate (the ratio K) exceeds the upper limit value in the efficiency change upper limit data storage unit.

図13〜図17は、上述のような能率のアップ率の上限付きでの作業工程の変更方法を説明するための図である。図13は、前記初期工程作成部42で作成されたままの作業工程を示すガントチャートであり、図7と同様に、工程1〜5を処理すべきワークA,B,C,D,Eに、工程3までのワークFを割込ませるものとする。また、ワークDは工程4での作業は無いものとする。各工程1〜5での作業時間の標準値は40分〜160分、さらに前述のように、工程間の引き渡しには30分、同一工程での連続する作業間には準備時間として最低10分の時間余裕が必要であるとする。   FIG. 13 to FIG. 17 are diagrams for explaining a method of changing a work process with the upper limit of the efficiency increase rate as described above. FIG. 13 is a Gantt chart showing the work process that has been created by the initial process creation unit 42, and in the same manner as in FIG. 7, the work A, B, C, D, and E to be processed in steps 1 to 5 are shown. Suppose that the workpiece F up to step 3 is interrupted. Further, it is assumed that the work D has no work in the step 4. The standard value of the working time in each process 1 to 5 is 40 minutes to 160 minutes. Further, as described above, 30 minutes for delivery between processes, and 10 minutes as minimum preparation time between successive work in the same process. It is assumed that there is a need for a time margin.

そして、本実施の形態では、前記能率変更上限データ記憶部50に、各作業工程における能率のアップ率(前記比K)の上限値が予め設定されている(以降、本実施の形態では、その上限値は、1〜5の全作業工程において、一律15%増加までとする)。また、各ワークA,B,C,D,E,Fの納期は、工程の開始時刻からの相対時刻として計算され、追加のワークFには750分、さらに本実施の形態では、ワークD,Eにも納期が与えられており、それぞれ980分および1090分であり、割込み前は、それらのワークD,Eは納期内に作業が終了(完成)しているものとする。   In the present embodiment, an upper limit value of the efficiency increase rate (the ratio K) in each work process is preset in the efficiency change upper limit data storage unit 50 (hereinafter, in the present embodiment, The upper limit value is a uniform 15% increase in all work steps 1 to 5). In addition, the delivery date of each work A, B, C, D, E, F is calculated as a relative time from the start time of the process, 750 minutes for the additional work F, and in the present embodiment, the work D, E is also given a delivery date, which is 980 minutes and 1090 minutes, respectively, and before interruption, these works D and E are assumed to have been completed (completed) within the delivery date.

図13で示すように、単純に、予定されていた総てのワークA,B,C,D,Eの処理が終了した後に、ワークFの作業工程を追加したのでは、該追加のワークFが納期に間に合わなくなっている。そこで、前述の図8と同様に、作業者は、図14で示すように、その割込みが生じる工程3において、納期以前で、納期に最も近いワークの工程間隔C,D間に、前記ワークFの割込みを、前記作業割り付け変更部6から指定し、割り付け変更データ記憶部48に記憶させるとともに、図15で示すように、その割込みに伴い、能率を変更すべき作業工程を指定し、能率変更工程記憶部47に記憶させる(図15の例では、割り込まれるワークDよりも以前のワークA,B,Cが、枠で指定されている)。   As shown in FIG. 13, simply by adding the work process of the workpiece F after the processing of all the workpieces A, B, C, D, and E that have been scheduled is completed, the additional workpiece F is added. Is not in time for delivery. Therefore, as in FIG. 8 described above, as shown in FIG. 14, the worker, in the process 3 where the interruption occurs, before the delivery date, between the process intervals C and D of the workpieces closest to the delivery date, Is specified from the work allocation change unit 6 and is stored in the allocation change data storage unit 48. Also, as shown in FIG. The process is stored in the process storage unit 47 (in the example of FIG. 15, the works A, B, and C before the work D to be interrupted are designated by a frame).

これに応答して、前記能率変更値計算部49bは、割り付け変更データ記憶部48に記憶されているように、工程3において、ワークFを、ワークC,Dの工程間に嵌め込めるように、能率変更工程記憶部47に記憶されているワークA,B,Cに必要な能率変更値を計算する。その際、後述するように、能率変更値計算部49bは、前記能率変更上限データ記憶部50を参照し、計算した変更値(アップ率(比K))が上限値の前記15%を超えているか否かを判断し、超えている場合には、その上限値に設定して、以降のワークD,Eの処理を、これらのワークA,B,C,Fの処理後に順次繰り下げる。   In response to this, the efficiency change value calculation unit 49b, as stored in the allocation change data storage unit 48, in step 3, the work F can be fitted between the work C and D processes. An efficiency change value necessary for the workpieces A, B, and C stored in the efficiency change process storage unit 47 is calculated. At that time, as described later, the efficiency change value calculation unit 49b refers to the efficiency change upper limit data storage unit 50, and the calculated change value (up rate (ratio K)) exceeds the 15% of the upper limit value. If it exceeds, the upper limit value is set, and the subsequent processing of the workpieces D and E is sequentially lowered after the processing of these workpieces A, B, C, and F.

具体的には、先ず前記図10と同様に、能率変更値計算部49bは、能率変更工程記憶部47に記憶されているワークA,B,Cに必要な能率変更値を計算する。すなわち、工程3において、元々のワークAの処理開始時刻からワークCの処理完了時刻までの所要時間を基準として固定した上で、さらにワークFの作業時間およびその準備時間を追加しても、元々の所要時間内で作業を終了できるようにするための能率変更(向上)値を、ワークA,B,Cについて算出する。その方法として、たとえば前記式1と同様に、下式をKについて解くことで得られるKの値を能率変更の倍率とすることで可能となる。   Specifically, first, as in FIG. 10, the efficiency change value calculation unit 49 b calculates the efficiency change values necessary for the workpieces A, B, and C stored in the efficiency change process storage unit 47. That is, even if the work time and the preparation time of the work F are further added after fixing the required time from the processing start time of the original work A to the processing completion time of the work C in the step 3, the work time and the preparation time thereof are added. An efficiency change (improvement) value for enabling the work to be completed within the required time is calculated for the workpieces A, B, and C. As a method thereof, for example, as in the case of Equation 1, it is possible to set the value of K obtained by solving the following equation for K as the efficiency change magnification.

(TA+TB+TC)×1/K+TF+J×3=EC−SA ・・・(2)
したがって、各ワークA,B,Cの標準処理時間をTA,TB,TCとし、それぞれ150分、100分、150分、100分であり、Jを連続する作業間に必要な準備時間(前記10分)とし、ECをワークCの工程3での元の処理完了時刻(620分)とし、SAをワークAの工程3での処理開始時刻(200分)とすると、上式は、
(150+100+150+100)×1/K+10×3=620−200
から、
K=50/39≒1.39
となる。
(TA + TB + TC) × 1 / K + TF + J × 3 = EC−SA (2)
Accordingly, the standard processing times of the workpieces A, B, and C are TA, TB, and TC, which are 150 minutes, 100 minutes, 150 minutes, and 100 minutes, respectively. Min), EC is the original process completion time (620 minutes) in process 3 of work C, and SA is the process start time (200 minutes) in process 3 of work A.
(150 + 100 + 150 + 100) × 1 / K + 10 × 3 = 620−200
From
K = 50/39 ≒ 1.39
It becomes.

しかしながら、このアップ率(比K)は、前述の上限値(+15%)を上回っており、実行不可能=制約違反となる。この状況を作業者に伝達する方法として、図16で示すように、表示手段21に表示するガントチャートの高さを、1.39倍に変更した上で、1倍を超える高さ部分について、赤色などの目立つ色で表示して、制約違反となることを示すことも可能である。能率変更値計算部49bは、制約違反となることを示した上で、次に、制約に従うように、すなわち前記上限値の15%にアップ率(比K)を制限し、前記能率変更データ記憶部45aに格納した後、シミュレーション部46aが、この新たなアップ率(比K)を用いて、アップ対象のワークA,B,Cと、それに続くワークF,D,Eとの作業工程をシフトする。すなわち、割り付け変更情報(ワークFの工程3の作業順序を4番目に変更)と、能率変更データ(上記のワークA,B,Cの工程3での変更後の処理時間)とに基づいて、前詰めで全体工程のシミュレーションを実行する。シミュレーション結果(各作業工程の開始および終了時刻)は、工程データ記憶部41に格納される。   However, this up rate (ratio K) exceeds the above-mentioned upper limit (+ 15%), and execution is impossible = constraint violation. As a method of transmitting this situation to the worker, as shown in FIG. 16, the height of the Gantt chart displayed on the display means 21 is changed to 1.39 times, and the height portion exceeding 1 time is It is also possible to display a conspicuous color such as red to indicate a violation of the constraint. The efficiency change value calculation unit 49b indicates that the restriction is violated, and then restricts the up rate (ratio K) to 15% of the upper limit value in accordance with the restriction, and stores the efficiency change data storage. After storing in the unit 45a, the simulation unit 46a uses the new up rate (ratio K) to shift the work processes of the workpieces A, B, and C to be increased and the subsequent workpieces F, D, and E. To do. That is, based on the allocation change information (change the work order of the process 3 of the work F to the fourth) and the efficiency change data (the processing time after the change in the process 3 of the work A, B, C described above), Execute the simulation of the whole process with justification. The simulation result (start time and end time of each work process) is stored in the process data storage unit 41.

図17は、そのシミュレーション結果を示すもので、工程3におけるワークA,B,Cでの能率のアップ率(比K)が上限値(+15%)で制限されているので、ワークCの元々の処理完了時刻(完了基準)に対して、追加分のワークFの処理完了時刻が60分遅れている。その影響は、工程3の後続作業(ワークD,Eの作業)遅れとなって伝播されているが、各ワークF,D,Eは、いずれも納期に間に合っており、工程追加作業は終了となる。終了となって、最終的に前記チャート高さ補正部51によって高さ補正されたガントチャートが、表示手段21で再表示され、この図17で示すようになる。   FIG. 17 shows the simulation result. Since the efficiency increase rate (ratio K) in the workpieces A, B, and C in step 3 is limited by the upper limit (+ 15%), the original value of the workpiece C is shown. The processing completion time of the additional work F is delayed by 60 minutes with respect to the processing completion time (completion reference). The influence is propagated with a delay in the subsequent work (work D, E work) of process 3, but each work F, D, E is in time for delivery, and the process addition work is finished. Become. At the end, the Gantt chart whose height has been finally corrected by the chart height correcting unit 51 is redisplayed on the display means 21 and becomes as shown in FIG.

これに対して、工程3で作業終了となるワークFについて、納期遅れが生じている場合には、作業者は、さらに前のワークB,C間に嵌め込んだり、前の工程1,2の能率アップを指定したりすることで対応することができる。また、後続の工程4,5まで作業の行われるワークD,Eについて、納期遅れが生じている場合には、作業者は、その後の工程4,5の能率アップを指定することで対応することもできる。   On the other hand, when the delivery date is delayed for the work F which is completed in the process 3, the operator can further fit the work between the previous works B and C, It can be dealt with by specifying efficiency improvement. In addition, if there is a delay in the delivery date for the workpieces D and E on which the operations up to the subsequent steps 4 and 5 are performed, the worker should respond by designating an increase in the efficiency of the subsequent steps 4 and 5. You can also.

図18は、上述のような作業工程の変更方法を説明するためのフローチャートである。図11の処理に類似し、対応する部分には同一のステップ番号を付して示す。ステップS1では、初期工程作成部42によって初期の作業工程データが作成されて工程データ記憶部41に記憶され、ステップS2では、その作業工程データから、ガントチャート表示データ作成部5がガントチャート表示データを作成し、表示部2に与えて表示を行わせる。ステップS3では、入力手段31から終了の指示があったか否かが判断され、終了の指示が行われると処理を終了してそのガントチャートのままで工程が管理され、終了でない、すなわち作業工程を変更(修正)する場合にはステップS11に移る。   FIG. 18 is a flowchart for explaining a method for changing a work process as described above. Similar to the processing of FIG. 11, the corresponding steps are denoted by the same step numbers. In step S1, initial work process data is created by the initial process creation unit 42 and stored in the process data storage unit 41. In step S2, the Gantt chart display data creation unit 5 uses the Gantt chart display data from the work process data. Is generated and given to the display unit 2 for display. In step S3, it is determined whether or not there is an end instruction from the input means 31, and when the end instruction is given, the process is terminated and the process is managed as it is in the Gantt chart. In the case of (correction), the process proceeds to step S11.

ステップS11では、前記追加や時間帯の変更等を行うべき1または複数の作業工程が入力手段31から指定されるとともに、その作業工程の表示が行われ、ステップS12では、前記追加や時間帯の変更等に伴い、能率を変更すべき作業工程が入力手段31から指定されるとともに、その作業工程の表示が行われる。続いてステップS21では、その能率を変更すべき作業工程について、能率変更上限データ記憶部50から、能率のアップ率(比K)の上限値が読出される。ステップS13aでは、その能率を変更すべき作業工程について、上述のようにして能率アップの比Kが、前記上限値の範囲内で求められる。ステップS6では、それらの変更値の入力結果に応答して、シミュレーション部46aがシミュレーションを行い、その結果から、ステップS7で、ガントチャート表示データ作成部5がガントチャートの表示データを作成して表示手段21に表示させるにあたって、チャート高さ補正部51が、変更前の能率値に対する変更後の能率値の比を、変更前の矩形領域の高さに乗じて新たな矩形領域の表示データを作成する。   In step S11, one or a plurality of work processes to be added or changed in time zone are designated from the input means 31, and the work process is displayed. In step S12, the addition or time zone is displayed. Along with the change or the like, a work process whose efficiency is to be changed is designated from the input means 31 and the work process is displayed. Subsequently, in step S21, the upper limit value of the efficiency increase rate (ratio K) is read from the efficiency change upper limit data storage unit 50 for the work process whose efficiency is to be changed. In step S13a, for the work process whose efficiency is to be changed, the efficiency increase ratio K is determined within the range of the upper limit as described above. In step S6, in response to the input results of these changed values, the simulation unit 46a performs a simulation. From the result, the Gantt chart display data creation unit 5 creates and displays display data for the Gantt chart in step S7. When displaying on the means 21, the chart height correction unit 51 multiplies the ratio of the efficiency value after the change to the efficiency value before the change to the height of the rectangle area before the change, and creates display data for a new rectangular area. To do.

このように能率変更値計算部49bが、変更後の能率のアップ率(比K)を計算してみて、その計算結果が能率変更上限データ記憶部50に記憶される上限を超えており、したがって作業能率の向上に限界がある場合には、変更後の能率をその限界値とすることで、実行可能な範囲で、工程の修正が可能になるとともに、能率の変更幅が上限の範囲内かどうかを容易に判断できるようになる。   Thus, the efficiency change value calculation unit 49b calculates the efficiency increase rate (ratio K) after the change, and the calculation result exceeds the upper limit stored in the efficiency change upper limit data storage unit 50. If there is a limit to the improvement of work efficiency, it is possible to modify the process within the feasible range by setting the efficiency after the change as the limit value, and whether the change width of the efficiency is within the upper limit range. It will be possible to judge easily.

加えて、特定ワークの作業時間帯を移動させる際に、移動先に特定ワークを処理可能な空き時間が無い場合で、かつ、ワーク毎の処理能力向上に上限がある場合でも、移動先の隣接作業の能力を上限まで一時的に向上させた上で、後続の作業を最低限遅らせることによって、納期遅れを解消するような複雑な工程の修正を短時間かつ容易に実行できる。   In addition, when moving the work time zone of a specific workpiece, even if there is no free time available for processing the specific workpiece at the destination, and there is an upper limit to the processing capacity improvement for each workpiece, By temporarily improving the work capacity up to the upper limit and delaying the subsequent work as much as possible, it is possible to easily execute a complicated process correction for eliminating the delay in delivery time in a short time.

(実施の形態4)
図19は、本発明の実施の他の形態に係る工程管理装置1cの電気的構成を示すブロック図である。この工程管理装置1cは、前述の工程管理装置1bに類似している。注目すべきは、この工程管理装置1cの工程調整部4cでは、前記能率変更値計算部49bで計算された能率が、前記能率変更上限データ記憶部50に記憶されている上限値を超えているか否かから、能率変更工程指定部7cによる前記能率変更工程の割付けの可否を判断し、割付けが不可能な場合は、前記能率変更工程指定部7cに、前記能率変更工程を追加させる割付け変更可否判断部40が設けられていることである。
(Embodiment 4)
FIG. 19 is a block diagram showing an electrical configuration of a process management apparatus 1c according to another embodiment of the present invention. This process management apparatus 1c is similar to the above-described process management apparatus 1b. It should be noted that, in the process adjustment unit 4c of the process management device 1c, does the efficiency calculated by the efficiency change value calculation unit 49b exceed the upper limit value stored in the efficiency change upper limit data storage unit 50? Whether or not the efficiency change process designation unit 7c determines whether the efficiency change process can be allocated. If the allocation is impossible, the efficiency change process designation unit 7c adds the efficiency change process. The determination unit 40 is provided.

すなわち、前記割付け変更可否判断部40は、前記能率変更工程指定部7によって指定された能率変更の対象となる処理開始時刻が最も早い工程の開始時刻から、処理完了時刻が最も遅い工程の完了時刻までの時間幅内で、追加の工程を割込ませるにあたって、前記能率変更値計算部49bで計算された各工程の能率の拡大幅が、能率変更上限データ記憶部に記憶されているそれぞれの工程における能率の上限を超えているかどうかから、能率変更の対象となる作業工程の割付けの妥当性を判断する。その結果、必要な能率の拡大幅が上限を超えている場合、すなわち割付け不可能な場合は、前記能率変更工程指定部7cに前記能率変更工程を追加させ、同様の判定を行う。   That is, the allocation change possibility determination unit 40 determines the completion time of the process with the latest process completion time from the start time of the process with the earliest process start time specified by the efficiency change process specification unit 7. In order to interrupt an additional process within the time width up to, each process stored in the efficiency change upper limit data storage unit is an expansion of the efficiency of each process calculated by the efficiency change value calculation unit 49b. The validity of the allocation of the work process that is the target of the efficiency change is judged based on whether or not the upper limit of the efficiency is exceeded. As a result, if the necessary efficiency expansion width exceeds the upper limit, that is, if allocation is impossible, the efficiency changing process is added to the efficiency changing process designating unit 7c, and the same determination is performed.

図20〜図26は、上述のような能率変更工程の自動指定の様子を示すフローチャートである。図20は、前記初期工程作成部42で作成されたままの作業工程を示すガントチャートであり、工程1〜5に、処理すべきワークはA,B,C,D,Eであり、納期の関係で、工程2と工程3との間で、ワークC,D,E間で作業順の入替えが行われ、E→D→Cの順となっている。このため、工程3のワークDとワークCとの作業間で、段取り替えが40分発生しているものとする。各工程1〜5での作業時間の標準値は50分〜130分、さらに前述のように、工程間の引き渡しには30分、同一工程での連続する作業間には準備時間として最低10分の時間余裕が必要であるとする。   FIG. 20 to FIG. 26 are flowcharts showing a state of automatic designation of the efficiency changing process as described above. FIG. 20 is a Gantt chart showing the work process that has been created by the initial process creation unit 42. In steps 1 to 5, the workpieces to be processed are A, B, C, D, and E. In relation, the work order is switched between the works C, D, and E between the process 2 and the process 3, and the order is E → D → C. For this reason, it is assumed that a setup change has occurred for 40 minutes between work D and work C in step 3. The standard value of the working time in each process 1 to 5 is 50 minutes to 130 minutes, and as described above, 30 minutes for delivery between processes, and 10 minutes as minimum preparation time between consecutive work in the same process. It is assumed that there is a need for a time margin.

そして、本実施の形態では、前記能率変更上限データ記憶部50に、各作業工程における能率のアップ率(前記比K)の上限値が予め設定されている。ここでは、以降、能率を変更する工程3について具体的に示し、各ワークA,B,C,Eの標準作業時間は、それぞれ130分、150分、50分、70分、前記能率アップによる作業時間の上限値(最も短縮した作業時間)は、それぞれ100分、110分、40分、50分とする。また、各ワークA,B,C,D,Eの納期は、工程の開始時刻からの相対時刻として計算され、それぞれ620分、820分、1050分、930分、890分とする。   In the present embodiment, the efficiency change upper limit data storage unit 50 is preset with an upper limit value of the efficiency increase rate (the ratio K) in each work process. Here, the step 3 for changing the efficiency is specifically shown below, and the standard work times of the workpieces A, B, C, and E are 130 minutes, 150 minutes, 50 minutes, and 70 minutes, respectively. The upper time limit (the most shortened work time) is 100 minutes, 110 minutes, 40 minutes, and 50 minutes, respectively. Moreover, the delivery date of each workpiece | work A, B, C, D, E is calculated as a relative time from the start time of a process, and shall be 620 minutes, 820 minutes, 1050 minutes, 930 minutes, and 890 minutes, respectively.

図20で示すような、単純に納期を優先してシミュレーション部46aがシミュレーションした結果を見て、作業者が入力操作部3から作業割り付け変更部6を介して、作業割り付けの変更情報(変更した作業と変更後の順序)を入力すると、割り付け変更データ記憶部48に格納されるとともに、前記シミュレーション部46aから工程データ記憶部41およびガントチャート表示データ作成部5を介して、表示手段21には、図21に示すような作業割り付けの変更画面が表示される。ここでは、前述のような工程3で段取り替え作業が発生しているワークD→Cの作業順序を変更するために、ワークCの作業順序をワークBとEとの間(前から3番目)に移動させるよう指示されている。   As shown in FIG. 20, when the simulation unit 46 a simply gives priority to the delivery date and sees the simulation result, the operator changes the work allocation change information (changed) from the input operation unit 3 through the work allocation change unit 6. When the operation and the order after the change are input, they are stored in the assignment change data storage unit 48, and from the simulation unit 46a to the display means 21 via the process data storage unit 41 and the Gantt chart display data creation unit 5. A work assignment change screen as shown in FIG. 21 is displayed. Here, in order to change the work order of the work D → C in which the setup change work is generated in the process 3 as described above, the work order of the work C is set between the work B and E (third from the front). Instructed to move to.

本実施の形態では、工程3において、上記のようにワークB→C→Eの順序で作業する場合は、段取り替えは発生しないものとする。そのため、この順序変更によって、工程3での段取り替え作業の発生は回避できるが、この図21から理解されるように、通常の工程2から3への引き渡し間に、ワークBとEの間にはCの作業を割り込ませる余裕時間はない。一方、工程3において、ワークE以降の作業開始時刻を繰り下げることによって、ワークBとEとの間にCの作業を割り付ける場合、図22に示すように、繰り下げたワークEとDとが納期遅れになる。   In the present embodiment, in the step 3, when the work is performed in the order of the workpieces B → C → E as described above, it is assumed that no setup change occurs. For this reason, the change in the order can avoid the occurrence of a setup change operation in the step 3. However, as can be understood from FIG. 21, during the transfer from the normal step 2 to the step 3, between the workpieces B and E, Has no time to interrupt C's work. On the other hand, in the process 3, when the work C is assigned between the work B and E by lowering the work start time after the work E, as shown in FIG. 22, the lowered work E and D are delayed in delivery date. become.

そこで本実施の形態では、前記能率変更工程指定部7cは、割り付け変更データ記憶部48に記憶されている割り付け変更データを基に、変更先で関係する作業の中で能率変更対象となる作業を追加する。ここでは、初回のため、初期変更作業として移動元であるワークCの工程3を追加(指定)する。このワークCを能率変更の対象ワークとして最初に選択する理由は、「変更先での近い作業から順に能率変更対象として追加する」という考えに基づいている。選択されたワークCの工程3の作業は、能率変更の対象作業として能率変更工程記憶部47に格納される。なお、ここで選択する作業は、本実施の形態のように1つに限らず、複数であってもよい。   Therefore, in the present embodiment, the efficiency change process designating unit 7c performs an operation to be an efficiency change target among the tasks related to the change destination based on the assignment change data stored in the assignment change data storage unit 48. to add. Here, since it is the first time, process 3 of work C, which is the movement source, is added (designated) as the initial change work. The reason why the work C is first selected as the efficiency change target work is based on the idea that “the work is added as an efficiency change target in order from the closest work at the change destination”. The work of process 3 of the selected workpiece C is stored in the efficiency change process storage unit 47 as an efficiency change target work. Note that the number of operations selected here is not limited to one as in the present embodiment, but may be a plurality.

次に、このワークCを能率変更の対象ワークとして、能率変更値計算部49bは、前述の図8や図14と同様にして、ワークBとEとの間に割り込めるように、工程3でのCの能率変更値を計算する。ここでは、前述のように、工程2から3への受け渡しによる間合い等、その工程3において、ワークBとEとの間に余裕時間は無いので、現実には不可能であるが、図23で示すように、ワークCの処理に許容できる時間が0(能率が無限大)となる必要がある。したがって、その計算結果を受けて、割付け変更可否判断部40は、能率変更上限データ記憶部50から、その工程3におけるワークCの上限作業時間を読出し、割付けが不可能であることを判定すると、結果は割付け不可となる。図23では、ワークCの処理に許容できる時間が0分であるのに対して、能率を上限(40分)まで高めても、該ワークCの処理を吸収できない状態を示している。   Next, with this work C as the efficiency change target work, the efficiency change value calculation unit 49b, in the same manner as in FIG. 8 and FIG. The efficiency change value of C is calculated. Here, as described above, since there is no allowance time between the workpieces B and E in the step 3, such as the time between delivery from the step 2 to the step 3, it is impossible in practice. As shown, the time allowed for processing the workpiece C needs to be 0 (efficiency is infinite). Therefore, upon receiving the calculation result, the allocation change permission determination unit 40 reads the upper limit work time of the workpiece C in the process 3 from the efficiency change upper limit data storage unit 50, and determines that the allocation is impossible. The result cannot be assigned. FIG. 23 shows a state where the time allowed for the processing of the workpiece C is 0 minute, but the processing of the workpiece C cannot be absorbed even if the efficiency is increased to the upper limit (40 minutes).

その判定結果を受けて、前記能率変更工程指定部7cは、再度割り付け変更データ記憶部48に記憶されている割り付け変更データを基に、変更先で関係する作業の中で能力変更対象となる作業を追加する。図24では、前のワークBの処理も能率を上限まで高めることで、或る程度、ワークCの処理を行うための時間を確保できているものの、このワークBの元々の処理時間内だけでは、ワークCの処理を吸収できない状態を示している。   In response to the determination result, the efficiency change process designating unit 7c re-assigns the work to be changed in the work related to the change destination based on the assignment change data stored in the assignment change data storage unit 48 again. Add In FIG. 24, the processing of the previous work B can also be secured to some extent by increasing the efficiency up to the upper limit. However, the processing time of the work C can be secured to some extent, but only within the original processing time of the work B. The state which cannot absorb the process of the workpiece | work C is shown.

この図24の状態では、能率変更値計算部49bが、能率アップすべきワークB,Cのアップ率Kを前述の式1,2と同様に計算すると、以下の通りになる。   In the state shown in FIG. 24, when the efficiency change value calculation unit 49b calculates the up rate K of the workpieces B and C to be increased in efficiency in the same manner as in the expressions 1 and 2, the following results.

(TB+TC)×1/K+J×1=EB−SB ・・・(3)
したがって、各ワークB,Cの標準処理時間をTB,TCとし、それぞれ150分、50分であり、Jを連続する作業間に必要な準備時間(前記10分)とし、EBをワークBの工程3での元の処理完了時刻(540分)とし、SBをワークBの工程3での処理開始時刻(410分)とすると、上式は、
(150+50)×1/K+10×1=540−410
から、
K=20/12≒1.67
となる。
(TB + TC) × 1 / K + J × 1 = EB−SB (3)
Therefore, the standard processing times of the workpieces B and C are TB and TC, respectively, and are 150 minutes and 50 minutes, respectively, J is a necessary preparation time (10 minutes) between successive operations, and EB is a process of the workpiece B 3 is the original processing completion time (540 minutes) in step 3, and SB is the processing start time (410 minutes) in step 3 of work B.
(150 + 50) × 1 / K + 10 × 1 = 540-410
From
K = 20/12 ≒ 1.67
It becomes.

したがって、処理時間に変換すると、
ワークBの工程3:150/1.67=90分
ワークCの工程3:50/1.67=30分
となり、上限値の100分および40分にはそれぞれ収まっていない。
Therefore, when converted to processing time,
Work B process 3: 150 / 1.67 = 90 minutes Work C process 3: 50 / 1.67 = 30 minutes, which are not within the upper limit of 100 minutes and 40 minutes, respectively.

このため、割付け変更可否判断部40が再度割付けを不可と判定すると、前記能率変更工程指定部7cは、図25で示すように、ワークCに近いワークEを、再度能率アップすべき処理に追加する。この図25の状態では、能率変更値計算部49bが、能率アップすべきワークB,C,Eのアップ率Kを前述の式1〜3と同様に計算すると、以下の通りになる。   For this reason, when the allocation change possibility determination unit 40 determines that the allocation is impossible again, the efficiency change process specifying unit 7c adds the workpiece E close to the workpiece C to the process to be increased again, as shown in FIG. To do. In the state of FIG. 25, when the efficiency change value calculation unit 49b calculates the up rate K of the workpieces B, C, and E to be increased in efficiency in the same manner as the above-described equations 1 to 3, the following is obtained.

(TB+TC+TE)×1/K+J×2=EE−SB ・・・(4)
したがって、追加のワークEの標準処理時間をTE=70分とし、EEをワークEの工程3での元の処理完了時刻(610分)とすると、上式は、
(150+50+70)×1/K+20×1=620−410
から、
K=27/19≒1.42
となる。
(TB + TC + TE) × 1 / K + J × 2 = EE−SB (4)
Therefore, assuming that the standard processing time of the additional workpiece E is TE = 70 minutes and EE is the original processing completion time (610 minutes) in the step 3 of the workpiece E, the above formula is
(150 + 50 + 70) × 1 / K + 20 × 1 = 620-410
From
K = 27/19 ≒ 1.42
It becomes.

したがって、処理時間に変換すると、
ワークBの工程3:150/1.42=106分
ワークCの工程3:50/1.42=36分
ワークEの工程3:70/1.42=50分
となり、これによってワークEについては上限値の50分に収まっているものの、ワークB,Cについては、100分および40分の上限値にそれぞれ収まっていない。
Therefore, when converted to processing time,
Work B process 3: 150 / 1.42 = 106 minutes Work C process 3: 50 / 1.42 = 36 minutes Work E process 3: 70 / 1.42 = 50 minutes. Although the upper limit value is within 50 minutes, the workpieces B and C are not within the upper limit value of 100 minutes and 40 minutes, respectively.

このため、割付け変更可否判断部40が再度割付けを不可と判定すると、前記能率変更工程指定部7cは、図26で示すように、ワークAを、再度能率アップすべき処理に追加する。この図26の状態では、能率変更値計算部49bが、能率アップすべきワークA,B,C,Eのアップ率Kを前述の式1〜4と同様に計算すると、以下の通りになる。   For this reason, when the allocation change possibility determination unit 40 determines that the allocation is impossible again, the efficiency changing process designating unit 7c adds the work A to the process to be increased again, as shown in FIG. In the state of FIG. 26, when the efficiency change value calculation unit 49b calculates the up rate K of the workpieces A, B, C, and E to be increased in efficiency in the same manner as the above-described equations 1 to 4, the following is obtained.

(TA+TB+TC+TE)×1/K+J×3=EE−SA ・・・(5)
したがって、追加のワークAの標準処理時間をTA=130分とし、SAをワークAの工程3での元の処理開始時刻(270分)とすると、上式は、
(130+150+50+70)×1/K+10×3=620−270
から、
K=40/32=1.25
となる。
(TA + TB + TC + TE) × 1 / K + J × 3 = EE−SA (5)
Therefore, if the standard processing time of the additional workpiece A is TA = 130 minutes and SA is the original processing start time (270 minutes) in the step 3 of the workpiece A, the above formula is
(130 + 150 + 50 + 70) × 1 / K + 10 × 3 = 620-270
From
K = 40/32 = 1.25
It becomes.

したがって、処理時間に変換すると、
ワークAの工程3:130/1.25=104分
ワークBの工程3:150/1.25=120分
ワークCの工程3:50/1.25=40分
ワークEの工程3:70/1.25=56分
となり、総てのワークA,B,C,Eについて、上限値の100分、110分、40分、50分に収まっている。
Therefore, when converted to processing time,
Work A process 3: 130 / 1.25 = 104 minutes Work B process 3: 150 / 1.25 = 120 minutes Work C process 3: 50 / 1.25 = 40 minutes Work E process 3: 70 / 1.25 = 56 minutes, and all workpieces A, B, C, and E are within the upper limit of 100 minutes, 110 minutes, 40 minutes, and 50 minutes.

これによって、割付け変更可否判断部40が割付けを妥当と判定すると、シミュレーション部46aがシミュレーションを行い、チャート高さ補正部51が高さを補正した図26で示すようなガントチャート表示が行われる。図26では、工程3でのワークA,B,C,Eの作業時間が、前記能率アップ率K(1.25倍)に相当する比率で短縮され、ワークAの処理開始時刻とワークEの処理完了時刻とを変更することなく、ワークB,E間にワークCの処理が嵌め込まれている。その結果、図21と比較して、納期遅れを発生させることなく、ワークD,C間の段取り替えが解消されていることが理解される。また、前述の各実施の形態と同様に、能率変更した工程3のワークA,B,C,Eの作業に対応する長方形の高さが、他の作業(標準の高さ)より高くなっており、標準を超える部分を濃く表示する効果もあり、能率アップを設定したことが視覚的に判断し易くなっている。   Accordingly, when the allocation change possibility determination unit 40 determines that the allocation is appropriate, the simulation unit 46a performs a simulation, and a Gantt chart display as shown in FIG. 26 in which the height is corrected by the chart height correction unit 51 is performed. In FIG. 26, the work times of the workpieces A, B, C and E in the step 3 are shortened by a ratio corresponding to the efficiency increase rate K (1.25 times), and the processing start time of the workpiece A and the workpiece E The processing of the workpiece C is inserted between the workpieces B and E without changing the processing completion time. As a result, as compared with FIG. 21, it is understood that the setup change between the workpieces D and C is eliminated without causing a delivery delay. Similarly to the above-described embodiments, the height of the rectangle corresponding to the work A, B, C, E of the process 3 in which the efficiency has been changed is higher than the other work (standard height). In addition, there is an effect that the portion exceeding the standard is displayed darkly, and it is easy to visually determine that the efficiency improvement is set.

図27は、上述のような作業工程の変更方法を説明するためのフローチャートである。図18の処理に類似し、対応する部分には同一のステップ番号を付して示す。図18の処理と異なる点は、前述のステップS12に代わるステップS12aでは、能率を変更すべき作業工程が、割付け変更データ記憶部48のデータを受けて、能率変更工程指定部7cが自動で指定(追加)してゆくことである。また、ステップS13aで能率変更値が計算された結果、ステップS31で、その変更値で作業工程の割付けが可能、すなわち前記能率変更値が能率変更データ記憶部50に記憶されている上限値以下であるか否かが、割付け変更可否判断部40で判定され、割付けができない場合は前記ステップS12aの能率変更工程の自動指定(追加)に戻り、割付け可能な場合はステップS6のシミュレーションに移る。   FIG. 27 is a flowchart for explaining a method for changing a work process as described above. Similar to the processing of FIG. 18, the corresponding steps are denoted by the same step numbers. 18 differs from the process of FIG. 18 in that, in step S12a instead of step S12 described above, the work process whose efficiency is to be changed receives the data in the allocation change data storage unit 48, and is automatically designated by the efficiency change process designation unit 7c. (Add) to do. In addition, as a result of the efficiency change value calculated in step S13a, the work process can be assigned with the change value in step S31, that is, the efficiency change value is equal to or less than the upper limit value stored in the efficiency change data storage unit 50. Whether or not there is allocation is determined by the allocation change permission determination unit 40. If the allocation cannot be performed, the process returns to the automatic designation (addition) of the efficiency changing process in step S12a.

このように構成することで、特定ワークの作業時間帯を移動させる際に、移動先に特定ワークを処理可能な空き時間が無い場合で、かつ、ワーク毎に能率アップの上限がある場合でも、移動先での隣接作業を段階的に選択し、能率を上限内で一時的に向上させることによって、段取り替え作業や納期遅れを解消するような複雑なスケジュール修正を短時間で、かつ容易に実行できるようになる。   By configuring in this way, when moving the work time zone of a specific work, even if there is no free time that can process the specific work at the destination, and there is an upper limit of efficiency improvement for each work, By selecting adjacent work at the destination step by step and temporarily improving efficiency within the upper limit, complex schedule correction that eliminates setup change work and delivery delays can be performed quickly and easily. become able to.

1,1a,1b,1c 工程管理装置
2 表示部
21 表示手段
22 出力インタフェイス
3 入力操作部
31 入力手段
32 入力インタフェイス
4,4a,4b,4c 工程調整部
40 割付け変更可否判断部
41 工程データ記憶部
42 初期工程作成部
43 能率変更工程指定部
44 能率指定部
45,45a 能率変更データ記憶部
46,46a シミュレーション部
47 能率変更工程データ記憶部
48 割り付け変更データ記憶部
49,49b 能率変更値計算部
50 能率変更上限データ記憶部
5 ガントチャート表示データ作成部
51 チャート高さ補正部
6 作業割り付け変更部
7,7c 能率変更工程指定部
1, 1a, 1b, 1c Process management device 2 Display unit 21 Display unit 22 Output interface 3 Input operation unit 31 Input unit 32 Input interface 4, 4a, 4b, 4c Process adjustment unit 40 Allocation change possibility determination unit 41 Process data Storage unit 42 Initial process creation unit 43 Efficiency change process specification unit 44 Efficiency specification unit 45, 45a Efficiency change data storage unit 46, 46a Simulation unit 47 Efficiency change process data storage unit 48 Allocation change data storage unit 49, 49b Efficiency change value calculation Section 50 Efficiency change upper limit data storage section 5 Gantt chart display data creation section 51 Chart height correction section 6 Work allocation change section 7, 7c Efficiency change process designation section

Claims (7)

複数の各作業工程を、作業開始時期を前縁とし、作業終了時期を後縁とした矩形領域で表すガントチャートによって表示手段に表示し、前記作業工程を管理する装置において、
前記各作業工程における能率を前記矩形領域の高さで表し、前記表示手段に与えるガントチャート表示データ作成部と、
前記作業工程の変更を受付ける入力操作部と、
予め作成された作業工程表に対して、前記入力操作部によって変更が受付けられた作業工程の作業時間帯を変更する作業割り付け変更部と、
予め作成された作業工程表に対して、前記入力操作部によって変更が受付けられた作業工程の前または後の少なくとも一方側の所定範囲の作業工程について、前記能率の変更対象の作業工程として指定する能率変更工程指定部と、
前記作業割り付け変更部によって割り付けられた作業工程の順で作業を行った場合に、前記各作業工程間に予め定められた工程間隔を維持するように、前記能率変更工程指定部によって指定された作業工程に対して、前記矩形領域の面積がその作業工程に必要な一定の作業量となるように、前記矩形領域の作業時間を伸縮させるとともに前記能率を変更し、かつその作業工程をシフトさせ、該変更後の作業工程表を再作成して前記ガントチャート表示データ作成部に与える工程調整部と備えることを特徴とする工程管理装置。
In the device for managing the work process, each work process is displayed on the display means by a Gantt chart represented by a rectangular area with the work start time as the leading edge and the work end time as the trailing edge.
The efficiency in each work process is represented by the height of the rectangular area, and the Gantt chart display data creation unit that gives the display means ,
An input operation unit for accepting a change in the work process;
A work assignment changing unit that changes a work time zone of a work process whose change is accepted by the input operation unit with respect to a work process table created in advance,
With respect to a work process table created in advance, a work process in a predetermined range on at least one side before or after the work process accepted by the input operation unit is designated as a work process to be changed in efficiency. An efficiency change process designation section;
Work designated by the efficiency changing process designating part so as to maintain a predetermined process interval between the work processes when work is performed in the order of work processes assigned by the work assignment changing part. For the process, the working time of the rectangular area is expanded and contracted so that the area of the rectangular area becomes a certain amount of work necessary for the work process, and the efficiency is changed, and the work process is shifted, process management apparatus, characterized in that it comprises a step adjustment unit recreate the work process table after the change given to the Gantt chart display data producing unit.
前記工程調整部は、
現在の作業工程データを記憶する工程データ記憶部と、
前記能率変更工程指定部で指定された作業工程を記憶する能率変更工程データ記憶部と、
前記作業割り付け変更部で変更された作業割り付けを記憶する割り付け変更データ記憶部と、
前記能率変更工程データ記憶部および割り付け変更データ記憶部を参照し、割り付け変更データで指定された作業工程の順で作業を行った場合に、各作業工程の矩形領域の面積がその作業工程に必要な一定の作業量となるように、かつ予め定められた工程間隔を維持するように、能率変更工程データで指定される作業工程における前記能率を変更する能率変更値計算部と、
前記能率変更値計算部で求められた能率変更データを記憶する能率変更データ記憶部と、
前記工程データ記憶部および能率変更データ記憶部を参照し、各作業工程をシフトさせた変更後の作業工程表を再作成し、決定の場合に前記工程データ記憶部に記憶させるシミュレーション部とを備え、
前記ガントチャート表示データ作成部は、前記能率変更データ記憶部を参照し、能率変更後の作業工程の能率に対応して、前記矩形領域の高さを変更して、前記表示手段に与えるチャート高さ補正部を備えることを特徴とする請求項記載の工程管理装置。
The process adjustment unit is
A process data storage unit for storing current work process data;
An efficiency change process data storage unit for storing the work process designated by the efficiency change process designation unit;
An assignment change data storage unit for storing the work assignment changed by the work assignment change unit;
When the efficiency change process data storage unit and the allocation change data storage unit are referred to and work is performed in the order of the work processes specified by the allocation change data, the area of the rectangular area of each work process is necessary for the work process. An efficiency change value calculation unit that changes the efficiency in the work process specified by the efficiency change process data so as to be a constant work amount and maintain a predetermined process interval;
An efficiency change data storage unit for storing efficiency change data obtained by the efficiency change value calculation unit;
A simulation unit that refers to the process data storage unit and the efficiency change data storage unit, re-creates the changed work process table that has shifted each work process, and stores it in the process data storage unit in the case of determination; ,
The Gantt chart display data creation unit refers to the efficiency change data storage unit, changes the height of the rectangular area according to the efficiency of the work process after the efficiency change, and gives the chart height to the display means process management apparatus according to claim 1, wherein the is provided with a correction unit.
前記チャート高さ補正部は、変更後の矩形領域の高さを、変更前の能率値に対する変更後の能率値の比を、変更前の矩形領域の高さに乗ずることで決定することを特徴とする請求項記載の工程管理装置。 The chart height correction unit determines the height of the rectangular area after the change by multiplying the ratio of the efficiency value after the change to the efficiency value before the change by the height of the rectangular area before the change. The process management apparatus according to claim 2 . 前記能率変更値計算部は、前記能率変更工程データで指定された全作業工程における所要時間が一定のままで、前記割り付け変更データで指定された作業工程の増加分を吸収するように、前記能率を変更することを特徴とする請求項記載の工程管理装置。 The efficiency change value calculation unit is configured to absorb the increase in the work process specified by the allocation change data while maintaining the time required for all work processes specified by the efficiency change process data to be constant. The process management apparatus according to claim 2, wherein: 前記各作業工程における能率の変更量の上限を記憶する能率変更上限データ記憶部をさらに備え、
前記能率変更値計算部は、変更後の能率を計算し、その計算結果が前記能率変更上限データ記憶部における上限値を超えている場合には、上限値を適用することを特徴とする請求項記載の工程管理装置。
Further comprising an efficiency change upper limit data storage unit for storing an upper limit of an efficiency change amount in each work process;
The efficiency change value calculation unit calculates the efficiency after the change, and when the calculation result exceeds an upper limit value in the efficiency change upper limit data storage unit, the upper limit value is applied. 2. The process management apparatus according to 2 .
前記シミュレーション部は、前記能率変更値計算部で前記変更後の能率に上限値が適用された場合には、当該作業工程以降の工程の開始および終了時刻を遅らせることで、変更後の作業工程表を再作成することを特徴とする請求項記載の工程管理装置。 The simulation unit, when an upper limit value is applied to the efficiency after the change by the efficiency change value calculation unit, by delaying the start and end time of the process after the work process, work table after the change The process management apparatus according to claim 5 , wherein the process management device is recreated. 前記各作業工程における能率の変更量の上限を記憶する能率変更上限データ記憶部と、
前記能率変更値計算部で計算された能率が前記上限値を超えているか否かから、前記能率変更工程指定部による前記能率変更工程の割付けの可否を判断し、割付けが不可能な場合は、前記能率変更工程指定部に、前記能率変更工程を追加させる割付け変更可否判断部とをさらに備えることを特徴とする請求項記載の工程管理装置。
An efficiency change upper limit data storage unit for storing an upper limit of an efficiency change amount in each of the work steps;
If the efficiency calculated by the efficiency change value calculation unit exceeds the upper limit value, determine whether the efficiency change process can be assigned by the efficiency change process designation unit, and if the assignment is impossible, The process management apparatus according to claim 2 , further comprising an allocation change permission determination unit that causes the efficiency change process designating unit to add the efficiency change process.
JP2010108075A 2010-02-02 2010-05-10 Process control device Expired - Fee Related JP5529620B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010108075A JP5529620B2 (en) 2010-02-02 2010-05-10 Process control device

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2010021326 2010-02-02
JP2010021326 2010-02-02
JP2010108075A JP5529620B2 (en) 2010-02-02 2010-05-10 Process control device

Publications (2)

Publication Number Publication Date
JP2011181058A JP2011181058A (en) 2011-09-15
JP5529620B2 true JP5529620B2 (en) 2014-06-25

Family

ID=44692459

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010108075A Expired - Fee Related JP5529620B2 (en) 2010-02-02 2010-05-10 Process control device

Country Status (1)

Country Link
JP (1) JP5529620B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015173873A1 (en) * 2014-05-12 2015-11-19 富士通株式会社 Display method for work schedule pertaining to crop cultivation, work schedule display program, and work schedule display device
JP6510949B2 (en) * 2015-10-06 2019-05-08 株式会社神戸製鋼所 Schedule correction support apparatus and method
WO2019013224A1 (en) * 2017-07-12 2019-01-17 パナソニックIpマネジメント株式会社 Manufacturing status visualization method, manufacturing status visualization device, and manufacturing system
JP7075906B2 (en) * 2019-03-19 2022-05-26 株式会社日立製作所 Work instruction support system and work instruction support method
JP7296753B2 (en) * 2019-03-27 2023-06-23 株式会社富士通エフサス Working time display method, working time display program and working time display device
CN113554244B (en) * 2020-04-23 2024-06-25 中国石油化工股份有限公司 Production change early warning method and device for refining enterprises based on efficiency change short plates

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08137949A (en) * 1991-10-24 1996-05-31 Nec Corp Method for changing plan of gantt chart
JPH05120296A (en) * 1991-10-25 1993-05-18 Nec Corp Gantt chart editor
JPH0830686A (en) * 1994-07-14 1996-02-02 Yokogawa Electric Corp Scheduling system
JP2002055710A (en) * 2000-08-11 2002-02-20 Fujitsu Ltd Process chart editing system
JP2004094770A (en) * 2002-09-03 2004-03-25 Hitachi Ltd Method and device for displaying work in process
JP4444575B2 (en) * 2003-03-31 2010-03-31 株式会社リコー Resource management program, recording medium, image processing apparatus design system, and image processing apparatus
JP5657189B2 (en) * 2005-11-09 2015-01-21 株式会社神戸製鋼所 Schedule correction apparatus, schedule correction program, and schedule correction method
JP5166908B2 (en) * 2007-07-06 2013-03-21 株式会社神戸製鋼所 Schedule management apparatus, method, and program

Also Published As

Publication number Publication date
JP2011181058A (en) 2011-09-15

Similar Documents

Publication Publication Date Title
JP5529620B2 (en) Process control device
JP7057199B2 (en) Diamond analysis support device and method
US9841755B2 (en) Job plan creation system
JP5657189B2 (en) Schedule correction apparatus, schedule correction program, and schedule correction method
US20160231733A1 (en) Program creation device, program creation method, and program
EP1505462A2 (en) Programmable controller
WO2012114444A1 (en) Engineering device
JP2013156800A (en) Process control system and process management program
JP5221458B2 (en) Spray movement path generation method and spray movement path generation apparatus in spray robot
CN106560850B (en) Plan generation device and plan generation method
JP2014123227A (en) Production schedule creation method and device
JP2020106958A (en) Production planning support device and method
JP5622483B2 (en) Processing scheduling system
CN108687417A (en) Control device, wire electric discharge machine, program editing device and control method
JP2009282897A (en) Operation assignment method and operation assignment apparatus
JP6611227B2 (en) NC machine control system
CN104616197A (en) Separable query transaction data scheduling method and apparatus
JP3981670B2 (en) Machining shape drawing device
JP2005182282A (en) Schedule planning method and device
JP6107712B2 (en) Work plan display system
JP7013968B2 (en) Information processing equipment, process plan display method and process plan display program
WO2024084555A1 (en) Machining simulation assistance device and computer-readable storage medium
JP6603541B2 (en) Vehicle operation support system
WO2024042766A1 (en) Progress management system, production execution system, and progress management method
JP5401222B2 (en) Scheduling method and schedule display method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20121001

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130919

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20131008

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20131204

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140408

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140417

R150 Certificate of patent or registration of utility model

Ref document number: 5529620

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees