JP5485067B2 - Electricity supply and demand adjustment system - Google Patents

Electricity supply and demand adjustment system Download PDF

Info

Publication number
JP5485067B2
JP5485067B2 JP2010173827A JP2010173827A JP5485067B2 JP 5485067 B2 JP5485067 B2 JP 5485067B2 JP 2010173827 A JP2010173827 A JP 2010173827A JP 2010173827 A JP2010173827 A JP 2010173827A JP 5485067 B2 JP5485067 B2 JP 5485067B2
Authority
JP
Japan
Prior art keywords
power
timer
opening
switchgear
closing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2010173827A
Other languages
Japanese (ja)
Other versions
JP2012034541A (en
Inventor
聡 高田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chugoku Electric Power Co Inc
Original Assignee
Chugoku Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chugoku Electric Power Co Inc filed Critical Chugoku Electric Power Co Inc
Priority to JP2010173827A priority Critical patent/JP5485067B2/en
Publication of JP2012034541A publication Critical patent/JP2012034541A/en
Application granted granted Critical
Publication of JP5485067B2 publication Critical patent/JP5485067B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/12Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/12Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation
    • Y04S10/123Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation the energy generation units being or involving renewable energy sources

Landscapes

  • Charge And Discharge Circuits For Batteries Or The Like (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Description

本発明は、タイマー式開閉器を用いて、分散型電源による電力の需給調整を行うシステムに関する。   The present invention relates to a system for adjusting supply and demand of electric power by a distributed power source using a timer type switch.

近年、太陽光発電設備等の分散型電源が電力系統に連系されるようになり、そういった分散型電源の台数が増加している。それに伴って、ゴールデンウィーク等、電力の需要の少ない期間には、分散型電源により発電された電力が電力系統に対して過剰に流入することにより、電力の需給調整が困難になることが予想される。   In recent years, distributed power sources such as photovoltaic power generation facilities have been linked to the power system, and the number of such distributed power sources has increased. Along with this, during periods of low demand for power, such as Golden Week, it is expected that power generated by distributed power sources will flow excessively into the power system, making it difficult to adjust power supply and demand. .

特開平6−141469号公報JP-A-6-141469

分散型電源の増加に伴い、電力の需給調整が困難になることに対して、今後、電力系統側に大容量の蓄電設備を設置する等の対策を、大規模に実施する必要があると考えられる。その場合には、蓄電設備等の設置費用が高額であるため、電力系統の運用者に多額の費用負担がかかるという問題が発生する。   With the increase in distributed power sources, it will be difficult to adjust the supply and demand of electric power. In the future, it will be necessary to implement measures on a large scale, such as installing large-capacity power storage facilities on the power system side. It is done. In that case, since the installation cost of the power storage equipment or the like is high, there is a problem that a large amount of cost is imposed on the operator of the power system.

なお、特許文献1には、制御回路と、電力会社の配電線端子との間に一定時間のみスイッチがオンとなるタイマーを有する配電盤が開示されているが、タイマーを使って夜間に電気料金が安価な商用電源から電気製品等に電力を供給するものであり、電力需要の少ない時期に太陽光発電や風力発電による電力を調整するものではない。   Patent Document 1 discloses a switchboard having a timer that is switched on only for a certain period of time between a control circuit and a power distribution line terminal of an electric power company. Electric power is supplied from an inexpensive commercial power source to electrical products and the like, and electric power from solar power generation or wind power generation is not adjusted at a time when power demand is low.

本発明は、上記課題を鑑みてなされたものであり、その主たる目的は、分散型電源による電力の需給調整を低コストに行うことにある。   The present invention has been made in view of the above problems, and a main object thereof is to perform power supply and demand adjustment by a distributed power source at low cost.

上記課題を解決するために、本発明は、電力需給調整システムであって、電力を発生させる分散型電源と、前記分散型電源から電力線を通じて電力の供給を受ける電力系統と、前記電力線を開路又は閉路にする開閉装置と、前記電力系統に連系し、前記電力線の開路時期を管理する管理装置と、を備え、前記管理装置が、前記開閉装置の識別データと、前記電力系統における電力の需要が通常より少なくなる時期を示す時期データとを対応付けて記憶する手段と、前記電力系統及び前記電力線を通じて前記開閉装置に対して、当該開閉装置の識別データに対応付けられた前記時期データを送信する手段と、を備え、前記開閉装置が、前記時期データを記憶する手段と、前記管理装置から前記時期データを受信したときに、記憶した前記時期データを、受信した前記時期データに変更する手段と、前記時期データに基づいて、前記時期には前記電力線を開路にし、前記時期以外には前記電力線を閉路にする手段と、を備え、前記管理装置が、1又は所定数の前記開閉装置を1のグループとし、当該グループごとに異なる時期を示す前記時期データを記憶することを特徴とする。 In order to solve the above problems, the present invention is a power supply and demand adjustment system, which is a distributed power source that generates power, a power system that receives power supply from the distributed power source through a power line, and opens or opens the power line. A switchgear for closing the circuit, and a management device linked to the power system and managing a circuit opening time of the power line , wherein the management device includes identification data of the switchgear and demand for power in the power system. Means for storing time data indicating a time when the time becomes less than normal, and transmitting the time data associated with the identification data of the switchgear to the switchgear through the power system and the power line. and means for, the said closing device, means for storing the previous SL time period data, when receiving the timing data from the management device, the stored the time de The data, and means for changing the timing data received, based on said timing data, said the timing to the power line to open, and means for the closing of the power line in addition to the timing, the management A device is characterized in that one or a predetermined number of the switchgears are grouped into one group, and the time data indicating a different time for each group is stored .

電力系統に連系する負荷は、変電所の系統電力や分散型電源の余剰電力を消費するが、
この構成によれば、その負荷による消費電力量が少なくなる時期において、開閉装置が電力線を開路にすることにより、通常はつながっている分散型電源を電力系統から切り離す。これによれば、開閉装置を用いて、電力の需要が減少する時期に、分散型電源による電力が電力系統に過剰に供給されるのを回避するので、低コストに電力の需給調整を行うことができる。
次に、この構成によれば、管理装置は、開閉装置ごとの時期データを記憶し、その開閉装置ごとに時期データを送信し、一方、開閉装置は、管理装置から時期データを受信し、更新する。これによれば、電力会社は、管理装置を用いて、配下にある開閉装置ごとの時期データを一括管理できるので、電力系統全体における電力の需給調整を行うことができる。
そして、この構成によれば、管理装置は、1台の開閉装置又は所定台数の装置グループごとに、異なる時期に開路するように管理する。これによれば、電力需要が通常の状態から少し減少することが想定されるときに、その減少分の電力が1台又は所定台数の分散型電源から供給されるのを停止することにより、電力系統における電力の需給バランスを図ることができる。また、1台又は所定台数の分散型電源を切り離す時期を別にするので、各分散型電源から供給される電力を均等に抑制し、売電の対価を均等にすることができる。
The load connected to the power grid consumes the grid power of the substation and the surplus power of the distributed power source.
According to this configuration, when the power consumption due to the load decreases, the switchgear opens the power line, thereby disconnecting the normally connected distributed power source from the power system. According to this, since the power supply by the distributed power source is avoided from being excessively supplied to the power system using the switchgear when the power demand decreases, the power supply and demand can be adjusted at low cost. Can do.
Next, according to this configuration, the management device stores the timing data for each switching device and transmits the timing data for each switching device, while the switching device receives and updates the timing data from the management device. To do. According to this, since the electric power company can collectively manage the timing data for each switching device under its control using the management device, it is possible to adjust the power supply and demand in the entire power system.
And according to this structure, a management apparatus manages so that it may open at different time for every switch apparatus or predetermined number of apparatus groups. According to this, when it is assumed that the power demand is slightly decreased from the normal state, the power for the decrease is stopped by stopping the supply of power from one or a predetermined number of distributed power sources. The power supply / demand balance in the grid can be achieved. In addition, since the time for disconnecting one or a predetermined number of distributed power sources is set separately, the power supplied from each distributed power source can be suppressed evenly, and the price of power sales can be made equal.

その他、本願が開示する課題及びその解決方法は、発明を実施するための形態の欄、及び図面により明らかにされる。   In addition, the problems disclosed by the present application and the solutions thereof will be clarified by the description of the mode for carrying out the invention and the drawings.

本発明によれば、分散型電源による電力の需給調整を低コストに行うことができる。   ADVANTAGE OF THE INVENTION According to this invention, the supply-and-demand adjustment of the electric power by a distributed power supply can be performed at low cost.

第1の実施の形態に係る電力需給調整システム1aの構成を示す図である。It is a figure which shows the structure of the electric power supply-and-demand adjustment system 1a which concerns on 1st Embodiment. タイマー式開閉装置5aのハードウェア構成を示す図である。It is a figure which shows the hardware constitutions of the timer-type opening / closing apparatus 5a. 第2の実施の形態に係る電力需給調整システム1bの構成を示す図である。It is a figure which shows the structure of the electric power supply-and-demand adjustment system 1b which concerns on 2nd Embodiment. タイマー式開閉装置5bのハードウェア構成を示す図である。It is a figure which shows the hardware constitutions of the timer type opening / closing apparatus 5b. 電力系統管理装置7aのハードウェア構成を示す図である。It is a figure which shows the hardware constitutions of the electric power grid | system management apparatus 7a. 電力系統管理装置7aの記憶部75に記憶されるタイマー設定値データ75Aの構成を示す図である。It is a figure which shows the structure of the timer setting value data 75A memorize | stored in the memory | storage part 75 of the electric power grid | system management apparatus 7a. その他の実施の形態に係る電力需給調整システム1cの構成を示す図である。It is a figure which shows the structure of the electric power supply-and-demand adjustment system 1c which concerns on other embodiment. 開閉装置5cの構成を示す図である。It is a figure which shows the structure of the opening / closing apparatus 5c. 電力系統管理装置7bの記憶部75に記憶される信号送信スケジュールデータ75Bの構成を示す図である。It is a figure which shows the structure of the signal transmission schedule data 75B memorize | stored in the memory | storage part 75 of the electric power grid | system management apparatus 7b.

以下、図面を参照しながら、本発明を実施するための形態を説明する。本発明の実施の形態に係る電力需給調整システムは、1年間のうち、任意の期間又は時間帯(時期)が設定可能なタイマーにより、その期間又は時間帯に分散型電源を電力系統から切り離す機能を持った開閉装置を、分散型電源を電力系統に接続する電気回路に設置するものである。そして、ゴールデンウィーク等、電力の需要が少なく、分散型電源により発電された電力が電力系統に過剰に流入して、電力の需給調整が困難となることが予想される期間について、分散型電源を切り離すことにより、過剰な電力が電力系統に流入することを回避する。   Hereinafter, embodiments for carrying out the present invention will be described with reference to the drawings. The power supply and demand adjustment system according to the embodiment of the present invention has a function of separating a distributed power source from a power system during a period or time period by a timer that can set an arbitrary period or time period (time) in one year. A switchgear having a power supply is installed in an electric circuit that connects a distributed power source to a power system. Then, disconnect the distributed power supply during periods such as Golden Week where power demand is low and the power generated by the distributed power supply is expected to flow excessively into the power system, making it difficult to adjust the power supply and demand. This prevents excessive power from flowing into the power system.

≪第1の実施の形態≫
<システムの構成>
図1は、第1の実施の形態に係る電力需給調整システム1aの構成を示す図である。電力需給調整システム1aは、電力系統2、電力線3、分電盤4、タイマー式開閉装置5a及び分散型電源6を含む。電力系統2は、変電所(図示せず)から受けた系統電力を送電し、連系する分散型電源6からの電力を受電するともに、連系する負荷(図示せず)に電力を供給する配電線等である。電力線3は、電力系統2、分電盤4、タイマー式開閉装置5a及び分散型電源6を順次接続する引込線や屋内配線等である。
<< First Embodiment >>
<System configuration>
FIG. 1 is a diagram showing a configuration of an electric power supply and demand adjustment system 1a according to the first embodiment. The power supply and demand adjustment system 1 a includes a power system 2, a power line 3, a distribution board 4, a timer type switchgear 5 a and a distributed power source 6. The power system 2 transmits system power received from a substation (not shown), receives power from the distributed power source 6 and supplies power to a connected load (not shown). Distribution line etc. The power line 3 is a service line, an indoor wiring, or the like that sequentially connects the power system 2, distribution board 4, timer type switchgear 5 a, and distributed power source 6.

分電盤4は、電力を安全に使用するために必要な漏電遮断器や配線用遮断器を1つにまとめた箱であり、引込線により電力系統2に接続され、一方、屋内配線により負荷(図示せず)や分散型電源6に接続される。タイマー式開閉装置5aは、分電盤4と、分散型電源6との間に設置され、その間の開路及び閉路のタイミング(時期データ)を記憶し、そのタイミングに応じて開路又は閉路の操作を行う。分散型電源6は、分電盤4を経由して電力系統2に連系し、発電した電力を電力系統2に供給するものであるが、分電盤4との間にタイマー式開閉装置5aが設置されることで、開路及び閉路のタイミングに応じて電力供給が制限される。   The distribution board 4 is a box in which the earth leakage circuit breaker and wiring circuit breaker necessary for the safe use of electric power are combined into one, connected to the electric power system 2 by a lead-in wire, while the load ( (Not shown) or a distributed power source 6. The timer-type opening / closing device 5a is installed between the distribution board 4 and the distributed power source 6, stores opening and closing timings (timing data) between them, and performs an opening or closing operation according to the timing. Do. The distributed power source 6 is connected to the power system 2 via the distribution board 4 and supplies the generated power to the power system 2. Is installed, the power supply is limited according to the timing of opening and closing.

図2は、タイマー式開閉装置5aのハードウェア構成を示す図である。タイマー式開閉装置5aは、開閉部51、タイマー52、入力部53、処理部54及び記憶部55を備え、各部がバス56を介してデータを送受信可能なように接続されている。開閉部51は、処理部54からの指示により分電盤4と、分散型電源6との間を開路又は閉路にする部分であり、例えば、開閉器によって実現される。タイマー52は、処理部54の指示により開路及び閉路のタイミングを設定し、そのタイミングに従って開路及び閉路のトリガとなる信号を処理部54に発信する部分であり、例えば、時計や割り込みコントローラ等によって実現される。入力部53は、オペレータが操作によりデータ(例えば、タイマー52の設定値)を入力する部分であり、例えば、操作ボタンやタッチパネル等によって実現される。   FIG. 2 is a diagram showing a hardware configuration of the timer type opening / closing device 5a. The timer-type opening / closing device 5 a includes an opening / closing unit 51, a timer 52, an input unit 53, a processing unit 54, and a storage unit 55, and each unit is connected so that data can be transmitted / received via a bus 56. The opening / closing part 51 is a part that opens or closes the space between the distribution board 4 and the distributed power source 6 according to an instruction from the processing part 54, and is realized by, for example, a switch. The timer 52 is a part that sets the timing of opening and closing according to an instruction of the processing unit 54 and transmits a signal that triggers the opening and closing according to the timing to the processing unit 54, and is realized by, for example, a clock or an interrupt controller Is done. The input unit 53 is a part where an operator inputs data (for example, a set value of the timer 52) by an operation, and is realized by, for example, an operation button or a touch panel.

処理部54は、所定のメモリを介して各部間のデータの受け渡しを行うととともに、タイマー式開閉装置5a全体の制御を行うものであり、CPU(Central Processing Unit)が所定のメモリに格納されたプログラムを実行することによって実現される。特に、入力部53からタイマー設定値(開路及び閉路のタイミング)を取得したときに、そのタイマー設定値を設定する指示をタイマー52に発し、タイマー52から開路又は閉路のトリガを受けたときに、開路又は閉路の指示を開閉部51に発する。記憶部55は、処理部54からデータを記憶したり、記憶したデータを読み出したりするものであり、例えば、HDD(Hard Disk Drive)やSSD(Solid State Drive)等の不揮発性記憶装置によって実現される。   The processing unit 54 transfers data between the respective units via a predetermined memory and controls the entire timer type opening / closing device 5a. A CPU (Central Processing Unit) is stored in the predetermined memory. This is realized by executing the program. In particular, when a timer setting value (opening and closing timing) is acquired from the input unit 53, an instruction to set the timer setting value is issued to the timer 52, and when an opening or closing trigger is received from the timer 52, An instruction for opening or closing is issued to the opening / closing unit 51. The storage unit 55 stores data from the processing unit 54 and reads the stored data, and is realized by a non-volatile storage device such as an HDD (Hard Disk Drive) or an SSD (Solid State Drive), for example. The

<システムの動作>
電力需給調整システム1aにおいて、タイマー式開閉器5aが設置され、そのタイマー式開閉器5aのタイマー52には開路及び閉路のタイミングが設定されており、そのタイミングに従って、分電盤4と、分散型電源6との間を開路又は閉路に操作する。その間が開路になると、分散型電源6による発電電力が遮断され、電力系統2には供給されない。その間が閉路になると、分散型電源6による発電電力が分電盤4を経由して電力系統2に供給される。
<System operation>
In the power supply and demand adjustment system 1a, a timer-type switch 5a is installed, and the timer 52 of the timer-type switch 5a is set to open and close timings. According to the timing, the distribution board 4 and the distributed type Operate between power supply 6 and open circuit. If the circuit is opened during this period, the power generated by the distributed power source 6 is cut off and is not supplied to the power system 2. When the circuit is closed during this period, the power generated by the distributed power source 6 is supplied to the power system 2 via the distribution board 4.

タイマー式開閉器5aのタイマー52には、過去の実績等から電力需要が低下する時期を想定したタイマー設定値が予め設定されている。予め設定されたタイマー設定値を変更する必要がなければ、タイマー式開閉器5aは設定変更機能を備えなくてもよい。一方、予め設定されたタイマー設定値を変更する必要があれば、タイマー式開閉器5aは手動による設定変更機能(具体的には、入力部53)を備えることになる。例えば、年によってコールデンウィークの期間が変わり、それにより休日の日付も変わるので、それに応じてタイマー設定値を変更する。この場合、タイマー設定値の変更は、電力系統2を運用する電力会社等から、ゴールデンウィークの期間等、給電停止対象の時期に間に合うように委託を受けた作業員が実施するが、電力会社の顧客が実施することも考えられる。   In the timer 52 of the timer type switch 5a, a timer set value is set in advance, assuming a time when the power demand is reduced based on past results. If it is not necessary to change the preset timer setting value, the timer-type switch 5a may not have a setting change function. On the other hand, if it is necessary to change a preset timer setting value, the timer type switch 5a is provided with a manual setting change function (specifically, the input unit 53). For example, the duration of the Colden week changes depending on the year, and the holiday date changes accordingly, so the timer setting value is changed accordingly. In this case, the timer setting value is changed by an operator commissioned by the power company operating the power grid 2 in time for the power supply suspension target, such as the Golden Week period. May be implemented.

≪第2の実施の形態≫
<システムの構成>
図3は、第2の実施の形態に係る電力需給調整システム1bの構成を示す図である。電力需給調整システム1bは、電力系統2、電力線3、分電盤4、タイマー式開閉装置5b、分散型電源6及び電力系統管理装置7aを含む。図1の電力需給調整システム1aの構成と比較すると、タイマー式開閉装置5aが5bに代わり、電力系統管理装置7aが追加されている。タイマー式開閉装置5bは、タイマー式開閉装置5aと同様に、分電盤4と、分散型電源6との間に設置され、記憶したタイマー設定値に応じて開路又は閉路の操作を行うが、さらにPLC(Power Line Communication)通信機能を備え、電力系統管理装置7aからタイマー設定値を受信し、記憶したタイマー設定値を変更する。電力系統管理装置7aは、電力系統2に連系し、同じく電力系統2に連系するタイマー式開閉装置5bとPLC通信機能によりデータの送受信が可能であり、配下にある各タイマー式開閉装置5bにタイマー設定値を送信する。
<< Second Embodiment >>
<System configuration>
FIG. 3 is a diagram illustrating a configuration of a power supply and demand adjustment system 1b according to the second embodiment. The power supply and demand adjustment system 1b includes a power system 2, a power line 3, a distribution board 4, a timer type switchgear 5b, a distributed power source 6, and a power system management device 7a. Compared with the configuration of the power supply and demand adjustment system 1a in FIG. 1, the timer type opening / closing device 5a is replaced with 5b, and a power system management device 7a is added. As with the timer type switchgear 5a, the timer type switchgear 5b is installed between the distribution board 4 and the distributed power source 6, and operates to open or close according to the stored timer setting value. Furthermore, it has a PLC (Power Line Communication) communication function, receives a timer set value from the power system management device 7a, and changes the stored timer set value. The power system management device 7a is linked to the power system 2, and can transmit and receive data by the PLC type communication function with the timer type switching device 5b that is also linked to the power system 2, and each subordinate timer type switching device 5b. Send the timer set value to.

図4は、タイマー式開閉装置5bのハードウェア構成を示す図である。タイマー式開閉装置5bは、開閉部51、タイマー52、通信部57、処理部54及び記憶部55を備え、各部がバス56を介してデータを送受信可能なように接続されている。図2のタイマー式開閉装置5aの構成と比較すると、入力部53の代わりに通信部57が備わっている。通信部57は、電力系統管理装置7aとの間でPLC通信を行う部分であり、電力系統管理装置7aからタイマー設定値を受信し、処理部54に受け渡す機能を持ち、例えば、PLC通信モデム等により実現される。処理部54は、通信部57からタイマー設定値(開路及び閉路のタイミング)を取得したときに、そのタイマー設定値を設定する指示をタイマー52に発し、タイマー52から開路又は閉路のトリガを受けたときに、開路又は閉路の指示を開閉部51に発する。   FIG. 4 is a diagram showing a hardware configuration of the timer type opening / closing device 5b. The timer-type opening / closing device 5 b includes an opening / closing unit 51, a timer 52, a communication unit 57, a processing unit 54, and a storage unit 55, and each unit is connected so that data can be transmitted / received via a bus 56. Compared to the configuration of the timer type opening / closing device 5 a of FIG. 2, a communication unit 57 is provided instead of the input unit 53. The communication unit 57 is a part that performs PLC communication with the power system management device 7a, and has a function of receiving a timer setting value from the power system management device 7a and passing it to the processing unit 54. For example, a PLC communication modem Etc. When the processing unit 54 obtains a timer set value (opening and closing timing) from the communication unit 57, the processing unit 54 issues an instruction to set the timer setting value to the timer 52, and receives an opening or closing trigger from the timer 52. Sometimes, an opening or closing instruction is issued to the opening / closing unit 51.

図5は、電力系統管理装置7aのハードウェア構成を示す図である。電力系統管理装置7aは、通信部71、表示部72、入力部73、処理部74及び記憶部75を備え、各部がバス76を介してデータを送受信可能なように接続されている。通信部71は、タイマー式開閉装置5bとの間でPLC通信を行う部分であり、タイマー設定値をタイマー式開閉装置5bに送信する機能を持ち、例えば、PLC通信モデム等によって実現される。表示部72は、処理部74からの指示によりデータを表示する部分であり、例えば、液晶ディスプレイ(LCD:Liquid Crystal Display)等によって実現される。入力部73は、オペレータがデータ(例えば、タイマー式開閉装置5bごとのタイマー設定値)を入力する部分であり、例えば、キーボードやマウス等によって実現される。   FIG. 5 is a diagram illustrating a hardware configuration of the power system management apparatus 7a. The power system management device 7 a includes a communication unit 71, a display unit 72, an input unit 73, a processing unit 74, and a storage unit 75, and each unit is connected so that data can be transmitted and received via a bus 76. The communication unit 71 is a part that performs PLC communication with the timer-type opening / closing device 5b, and has a function of transmitting a timer set value to the timer-type opening / closing device 5b, and is realized by, for example, a PLC communication modem. The display unit 72 is a part that displays data according to an instruction from the processing unit 74, and is realized by, for example, a liquid crystal display (LCD). The input unit 73 is a part where an operator inputs data (for example, a timer set value for each timer-type opening / closing device 5b), and is realized by, for example, a keyboard or a mouse.

処理部74は、所定のメモリを介して各部間のデータの受け渡しを行うととともに、電力系統管理装置7a全体の制御を行うものであり、CPUが所定のメモリに格納されたプログラムを実行することによって実現される。記憶部75は、処理部74からデータを記憶したり、記憶したデータを読み出したりするものであり、例えば、HDDやSSD等の不揮発性記憶装置によって実現される。なお、電力系統管理装置7aは、汎用的なPC(Personal Computer)やサーバであってもよいし、専用の装置であってもよい。   The processing unit 74 transfers data between the units via a predetermined memory and controls the entire power system management device 7a. The CPU executes a program stored in the predetermined memory. It is realized by. The storage unit 75 stores data from the processing unit 74 and reads the stored data, and is realized by, for example, a nonvolatile storage device such as an HDD or an SSD. The power system management device 7a may be a general-purpose PC (Personal Computer) or server, or may be a dedicated device.

<データの構成>
図6は、電力系統管理装置7aの記憶部75に記憶されるタイマー設定値データ75Aの構成を示す図である。タイマー設定値データ75Aは、タイマー式開閉装置5bごとのタイマー設定値を示すデータであり、開閉装置ID75A1及びタイマー設定値75A2を含む、電力系統管理装置7aが管轄するタイマー式開閉装置5bの台数分のレコードからなる。開閉装置ID75A1は、電力系統管理装置7aがタイマー設定値を送信する対象となるタイマー式開閉装置5bに固有のID(識別データ)であり、例えば、当該開閉装置のMAC(Media Access Control)アドレスが設定される。タイマー設定値75A2は、タイマー式開閉装置5bに送信すべきタイマー設定値を示すデータであり、具体的には、電力需要が少なくなる期間に対応して開閉部51(開閉器)を開路すべきタイミング及び閉路すべきタイミングが設定される。
<Data structure>
FIG. 6 is a diagram showing a configuration of timer set value data 75A stored in the storage unit 75 of the power system management device 7a. The timer set value data 75A is data indicating a timer set value for each timer type switchgear 5b, and includes the number of timer type switchgears 5b managed by the power system management device 7a, including the switchgear ID 75A1 and the timer set value 75A2. It consists of records. The switchgear ID 75A1 is an ID (identification data) unique to the timer-type switchgear 5b to which the power system management device 7a transmits a timer set value. For example, the MAC (Media Access Control) address of the switchgear is Is set. The timer set value 75A2 is data indicating a timer set value to be transmitted to the timer type switching device 5b. Specifically, the switch unit 51 (switch) should be opened corresponding to a period when the power demand decreases. The timing and the timing to be closed are set.

タイマー設定値データ75Aの設定パターンについては、配下にあるタイマー式開閉装置5bに対して、すべてを同じタイマー設定値にする方法や、開閉装置ごとにタイマー設定値を変える方法がある。これによれば、分散型電源6から電力系統2に流入する電力を調整することができる。例えば、電力需要が大きく減少することが想定される期間に、電力系統2への電力を大きく抑制する際には、多くの開閉装置に対するタイマー設定値を同じにして、該当する期間に多くの分散型電源6を電力系統2から切り離すようにする。一方、電力需要が少し減少することが想定される期間に、電力系統2への電力を少し抑制する際には、所定の期間や時間帯に一部の分散型電源6を切り離すために、1又は所定数の開閉装置を1のグループにし、各グループに対するタイマー設定値が互いに異なるように設定する。   Regarding the setting pattern of the timer set value data 75A, there are a method of setting all the same timer set values for the subordinate timer type switchgear 5b and a method of changing the timer set value for each switchgear. According to this, the electric power flowing into the electric power system 2 from the distributed power source 6 can be adjusted. For example, when the power to the power system 2 is largely suppressed during a period when the power demand is expected to greatly decrease, the timer setting values for many switchgears are set to be the same, and a large amount of dispersion is applied during the corresponding period. The mold power source 6 is disconnected from the power system 2. On the other hand, when the power to the power system 2 is slightly suppressed during a period in which the power demand is expected to decrease slightly, in order to disconnect some of the distributed power sources 6 during a predetermined period or time zone, 1 Alternatively, a predetermined number of switchgears are grouped into one group, and the timer setting values for each group are set to be different from each other.

<システムの動作>
電力需給調整システム1bにおいて、電力系統管理装置7aは、記憶部75からタイマー設定値データ75Aを読み出し、各開閉装置ID75A1に対応するタイマー式開閉装置5bにタイマー設定値75A2を送信する。このとき、通常はタイマー式開閉装置5bが開閉部51を閉路にしているので、開路にするタイミングに遅れないようにタイマー設定値を送信するものとする。タイマー式開閉装置5bは、電力系統管理装置7aからタイマー設定値を受信し、そのタイマー設定値をタイマー52に設定するとともに、タイマー52に設定した結果(実際にタイマー52に設定されているタイマー値)を電力系統管理装置7aに送信する。電力系統管理装置7aは、各タイマー式開閉装置5bからタイマー設定結果を受信する。
<System operation>
In the power supply and demand adjustment system 1b, the power system management device 7a reads the timer setting value data 75A from the storage unit 75, and transmits the timer setting value 75A2 to the timer type switching device 5b corresponding to each switching device ID 75A1. At this time, since the timer-type opening / closing device 5b normally closes the opening / closing part 51, it is assumed that the timer set value is transmitted so as not to be late for the opening timing. The timer type switching device 5b receives the timer set value from the power system management device 7a, sets the timer set value in the timer 52, and sets the timer 52 as a result (the timer value actually set in the timer 52). ) To the power system management device 7a. The power system management device 7a receives the timer setting result from each timer-type opening / closing device 5b.

これによれば、電力系統2を運用する電力会社は、顧客の分散型電源6の前に設置されたタイマー式開閉装置5bに正しくタイマー設定値が設定されたか否かを確認することができ、正しいタイマー値が未設定であれば、タイマー設定値を再送することも可能である。なお、タイマー設定値の変更は、ゴールデンウィークの期間等、給電停止対象の時期に間に合うように、電力会社が実施する。   According to this, the electric power company that operates the electric power system 2 can confirm whether or not the timer set value is correctly set in the timer type switching device 5b installed in front of the customer's distributed power source 6, If the correct timer value is not set, the timer set value can be retransmitted. The timer setting value is changed by the electric power company in time for the power supply suspension target time such as the Golden Week period.

そして、タイマー式開閉装置5bのタイマー52に設定されたタイマー設定値に応じて、分電盤4と、分散型電源6との間が開路又は閉路になる。   And according to the timer set value set to the timer 52 of the timer type switching device 5b, the space between the distribution board 4 and the distributed power source 6 is opened or closed.

なお、上記実施の形態では、図1に示すタイマー式開閉装置5a、図3に示すタイマー式開閉装置5b及び電力系統管理装置7a内の各部を機能させるために、処理部(CPU)で実行されるプログラムをコンピュータにより読み取り可能な記録媒体に記録し、その記録したプログラムをコンピュータに読み込ませ、実行させることにより、本発明の実施の形態に係る電力需給調整システム1a及び1bが実現されるものとする。この場合、プログラムをインターネット等のネットワーク経由でコンピュータに提供してもよいし、プログラムが書き込まれた半導体チップ等をコンピュータに組み込んでもよい。   In the above-described embodiment, the processing is executed by the processing unit (CPU) in order to cause the respective units in the timer-type opening / closing device 5a shown in FIG. 1, the timer-type opening / closing device 5b shown in FIG. 3, and the power system management device 7a to function. The power supply and demand adjustment systems 1a and 1b according to the embodiment of the present invention are realized by recording a program on a computer-readable recording medium, causing the computer to read and execute the recorded program. To do. In this case, the program may be provided to the computer via a network such as the Internet, or a semiconductor chip or the like in which the program is written may be incorporated in the computer.

以上説明した本発明の実施の形態によれば、タイマー式開閉装置5a及び5b(開閉装置)を、分散型電源6を設けた家屋(数万軒又はそれ以上の軒数)に設置することにより、数万kW又はそれ以上の電力が電力系統2に流入するのを回避することができる。これによれば、開閉装置を設置しない場合(例えば、開閉装置の代わりに蓄電池を設置する場合)に比べ、廉価な調整設備により、電力系統6における電力の需給バランスの確保が可能になる。そして、電力系統6を運用する電力会社において、電力の需給調整用に確保すべき蓄電設備等の設備容量を低減し、必要な対策費用を軽減することが可能になる。   According to the embodiment of the present invention described above, by installing the timer type switchgear 5a and 5b (switchgear) in a house (tens of thousands or more) provided with the distributed power source 6, It can be avoided that tens of thousands of kW or more of power flows into the power system 2. According to this, as compared with the case where no switchgear is installed (for example, when a storage battery is installed instead of the switchgear), it is possible to ensure the supply and demand balance of power in the power system 6 with inexpensive adjustment equipment. And in the electric power company which operates the electric power grid | system 6, it becomes possible to reduce the installation capacity of the electrical storage equipment etc. which should be ensured for supply and demand adjustment of electric power, and to reduce a required countermeasure cost.

詳細には、開閉装置の設置により対策を行う費用は、開閉装置1台の設置費用を10万円とし、1万軒に設置すると、10億円になる。この場合の調整可能な電力は、電力容量3kWの分散型電源が1万軒として、3万kW程度と想定する。一方、3万kWの電力を調整するのに必要な蓄電池のコストは、蓄電池の設置費用を10万円/kWとすると、30億円になる。開閉装置の10億円と、蓄電池の30億円とを比較すれば、開閉装置の方が低コストになり、有利である。   Specifically, the cost of taking measures by installing a switchgear is set at 100,000 yen for one switchgear and the cost for installing one switchgear is 1 billion yen. The adjustable power in this case is assumed to be about 30,000 kW with 10,000 distributed power sources having a power capacity of 3 kW. On the other hand, the cost of the storage battery required to adjust the power of 30,000 kW is 3 billion yen when the installation cost of the storage battery is 100,000 yen / kW. Comparing 1 billion yen for the switchgear with 3 billion yen for the storage battery, the switchgear is advantageous because it is less expensive.

なお、開閉装置を設置する場合、分散型電源6の運用者に対して、発電した電力を売電することができない不利益が生じるため、契約面での補償等も想定されるが、その補償等の金額を考慮してもコスト面での効果があると考えられる。   In the case of installing a switchgear, there is a disadvantage that the generated power cannot be sold to the operator of the distributed power source 6, so contractual compensation etc. is also assumed, but the compensation Considering the amount of money, etc., it is considered that there is a cost effect.

≪その他の実施の形態≫
以上、本発明を実施するための形態について説明したが、上記実施の形態は本発明の理解を容易にするためのものであり、本発明を限定して解釈するためのものではない。本発明はその趣旨を逸脱することなく変更、改良され得るとともに、本発明にはその等価物も含まれる。例えば、図3に示す電力需給調整システム1bにおいては、タイマー式開閉装置5bを用いたが、タイマー機能を持たない開閉装置を用いてもよい。
<< Other embodiments >>
As mentioned above, although the form for implementing this invention was demonstrated, the said embodiment is for making an understanding of this invention easy, and is not for limiting and interpreting this invention. The present invention can be changed and improved without departing from the gist thereof, and equivalents thereof are also included in the present invention. For example, in the power supply and demand adjustment system 1b shown in FIG. 3, the timer type opening / closing device 5b is used, but an opening / closing device having no timer function may be used.

図7は、その他の実施の形態に係る電力需給調整システム1cの構成を示す図である。電力需給調整システム1cは、電力系統2、電力線3、分電盤4、開閉装置5c、分散型電源6及び電力系統管理装置7bを含む。図3の電力需給調整システム1bの構成と比較すると、タイマー式開閉装置5bが開閉装置5cに代わり、電力系統管理装置7aが7bに代わっている。開閉装置5cは、タイマー式開閉装置5bと同様に、分電盤4と、分散型電源6との間に設置され、PLC通信機能を備えるが、電力系統管理装置7bから送信された入切の信号に応じて、分電盤4と、分散型電源6とを接続する電力線3を閉路又は開路にする。電力系統管理装置7bは、電力系統2に連系し、同じく電力系統2に連系する開閉装置5cとPLC通信機能によりデータの送受信が可能であり、各開閉装置5cに入切の信号を送信する。   FIG. 7 is a diagram showing a configuration of an electric power supply and demand adjustment system 1c according to another embodiment. The power supply and demand adjustment system 1c includes a power system 2, a power line 3, a distribution board 4, a switching device 5c, a distributed power source 6, and a power system management device 7b. Compared with the configuration of the power supply and demand adjustment system 1b of FIG. 3, the timer type switching device 5b is replaced with the switching device 5c, and the power system management device 7a is replaced with 7b. The switchgear 5c is installed between the distribution board 4 and the distributed power source 6 and has a PLC communication function, similar to the timer-type switchgear 5b. Depending on the signal, the power line 3 connecting the distribution board 4 and the distributed power supply 6 is closed or opened. The power system management device 7b is connected to the power system 2, and can transmit and receive data by the PLC communication function with the switchgear 5c that is also linked to the power system 2, and transmits an on / off signal to each switchgear 5c. To do.

図8は、開閉装置5cの構成を示す図である。開閉装置5cは、開閉部51、通信部57、処理部54及び記憶部55を備え、各部がバス56を介してデータを送受信可能なように接続されている。図4のタイマー式開閉装置5bの構成と比較すると、タイマー52がなくなっている。通信部57は、電力系統管理装置7bとの間でPLC通信を行う部分であり、電力系統管理装置7bから入切信号を受信し、処理部54に受け渡す機能を持ち、例えば、PLC通信モデム等により実現される。処理部54は、通信部57から入切信号(閉路及び開路のタイミング)を取得したときに、その入切信号に応じて閉路又は開路の指示を開閉部51に発する。   FIG. 8 is a diagram illustrating a configuration of the opening / closing device 5c. The opening / closing device 5 c includes an opening / closing unit 51, a communication unit 57, a processing unit 54, and a storage unit 55, and each unit is connected so that data can be transmitted / received via the bus 56. Compared to the configuration of the timer type opening and closing device 5b of FIG. 4, the timer 52 is eliminated. The communication unit 57 is a part that performs PLC communication with the power system management device 7b. The communication unit 57 has a function of receiving an on / off signal from the power system management device 7b and passing it to the processing unit 54. For example, a PLC communication modem Etc. When the processing unit 54 obtains an on / off signal (timing of closing and opening) from the communication unit 57, the processing unit 54 issues an instruction to close or open the opening / closing unit 51 according to the on / off signal.

なお、電力系統管理装置7bは、図5に示す電力系統管理装置7aと同じハードウェア構成を有するが、記憶部75のデータ及び処理部74の処理内容が異なる。   The power system management device 7b has the same hardware configuration as that of the power system management device 7a shown in FIG. 5, but the data in the storage unit 75 and the processing content of the processing unit 74 are different.

図9は、電力系統管理装置7bの記憶部75に記憶される信号送信スケジュールデータ75Bの構成を示す図である。信号送信スケジュールデータ75Bは、開閉装置5cごとの入切信号の送信スケジュールを示すデータであり、開閉装置ID75B1及びスケジュール75B2を含む、電力系統管理装置7bが管轄する開閉装置5cの台数分のレコードからなる。開閉装置ID75B1は、電力系統管理装置7bが入切信号を送信する対象となる開閉装置5cに固有のIDであり、例えば、当該開閉装置のMACアドレスが設定される。スケジュール75B2は、開閉装置5cに入切信号を送信すべきタイミングを示すデータであり、具体的には、電力系統2における電力需要が少なくなる期間に対応して開閉部51を開路すべきタイミング(切信号の送信タイミング)及び閉路すべきタイミング(入信号の送信タイミング)が設定される。   FIG. 9 is a diagram showing a configuration of signal transmission schedule data 75B stored in the storage unit 75 of the power system management apparatus 7b. The signal transmission schedule data 75B is data indicating an on / off signal transmission schedule for each switching device 5c, and includes records for the number of switching devices 5c managed by the power system management device 7b, including the switching device ID 75B1 and the schedule 75B2. Become. The switchgear ID 75B1 is an ID unique to the switchgear 5c to which the power system management device 7b transmits an on / off signal. For example, the MAC address of the switchgear is set. The schedule 75B2 is data indicating the timing at which an on / off signal should be transmitted to the switchgear 5c. Specifically, the schedule 75B2 is a timing at which the switchgear 51 should be opened corresponding to a period when the power demand in the power system 2 is reduced ( (Sending signal transmission timing) and closing timing (input signal transmission timing) are set.

電力需給調整システム1cにおいて、電力系統管理装置7bは、記憶部75から信号送信スケジュールデータ75Bを読み出し、スケジュール75B2に従って各開閉装置ID75B1に対応する開閉装置5bに入切信号を送信する。このとき、通常はタイマー式開閉装置5bが開閉部51を閉路にしているので、開路にするタイミングに遅れないように切信号を送信するものとする。開閉装置5cは、電力系統管理装置7bから入切信号を受信し、その入切信号に応じて、開閉部51を閉路又は開路にする。なお、電力系統管理装置7bは、電力系統2の送電状態により、電力需要が減少しつつあると判断したときには、リアルタイムにスケジュール75B2を変更してもよいし、スケジュール75B2に関係なく切信号を開閉装置5cに送信してもよい。   In the power supply and demand adjustment system 1c, the power system management device 7b reads the signal transmission schedule data 75B from the storage unit 75, and transmits an on / off signal to the switching device 5b corresponding to each switching device ID 75B1 according to the schedule 75B2. At this time, since the timer-type opening / closing device 5b normally closes the opening / closing part 51, it is assumed that a disconnection signal is transmitted so as not to be delayed from the opening timing. The switchgear 5c receives an on / off signal from the power system management device 7b, and closes or opens the switchgear 51 in accordance with the on / off signal. When the power system management device 7b determines that the power demand is decreasing due to the power transmission state of the power system 2, the power system management device 7b may change the schedule 75B2 in real time or open and close the cut signal regardless of the schedule 75B2. You may transmit to the apparatus 5c.

これによれば、開閉装置5cの開閉タイミングは、電力系統管理装置7bにおいて一括管理され、開閉装置5c等に渡されることもなく、スケジュールデータの一元化を図ることができる。また、開閉装置5cには、タイマー52の機能を付加する必要がないので、さらに低コストに電力の需給調整を行うことができる。   According to this, the opening / closing timing of the opening / closing device 5c is collectively managed by the power system management device 7b, and it is possible to unify the schedule data without being transferred to the opening / closing device 5c or the like. Moreover, since it is not necessary to add the function of the timer 52 to the opening / closing device 5c, it is possible to adjust the supply and demand of electric power at a lower cost.

1a、1b 電力需給調整システム
2 電力系統
3 電力線
5a、5b タイマー式開閉装置(開閉装置)
51 開閉部
52 タイマー
53 入力部
54 処理部
57 通信部
6 分散型電源
7a、7b 電力系統管理装置(管理装置)
DESCRIPTION OF SYMBOLS 1a, 1b Electric power supply-and-demand adjustment system 2 Electric power system 3 Electric power line 5a, 5b Timer type switchgear (switching device)
51 Opening / closing unit 52 Timer 53 Input unit 54 Processing unit 57 Communication unit 6 Distributed power supply 7a, 7b Power system management device (management device)

Claims (1)

電力を発生させる分散型電源と、
前記分散型電源から電力線を通じて電力の供給を受ける電力系統と、
前記電力線を開路又は閉路にする開閉装置と、
前記電力系統に連系し、前記電力線の開路時期を管理する管理装置と、
を備え、
前記管理装置は、
前記開閉装置の識別データと、前記電力系統における電力の需要が通常より少なくなる時期を示す時期データとを対応付けて記憶する手段と、
前記電力系統及び前記電力線を通じて前記開閉装置に対して、当該開閉装置の識別データに対応付けられた前記時期データを送信する手段と、
を備え、
前記開閉装置は、
記時期データを記憶する手段と、
前記管理装置から前記時期データを受信したときに、記憶した前記時期データを、受信した前記時期データに変更する手段と、
前記時期データに基づいて、前記時期には前記電力線を開路にし、前記時期以外には前記電力線を閉路にする手段と、
を備え
前記管理装置は、
1又は所定数の前記開閉装置を1のグループとし、当該グループごとに異なる時期を示す前記時期データを記憶する
ことを特徴とする電力需給調整システム。
A distributed power source that generates power,
A power system that receives power supply from the distributed power source through a power line;
An opening and closing device for opening or closing the power line;
A management device that is linked to the power system and manages the opening time of the power line;
With
The management device
Means for associating and storing identification data of the switchgear and time data indicating a time when power demand in the power system is less than normal;
Means for transmitting the time data associated with the identification data of the switchgear to the switchgear through the power system and the power line;
With
The switchgear is
And means for storing the previous Symbol time period data,
Means for changing the stored time data to the received time data when the time data is received from the management device;
Based on the time data, means for opening the power line at the time and closing the power line at other times;
Equipped with a,
The management device
An electric power supply and demand adjustment system , wherein one or a predetermined number of the switchgears are grouped into one group, and the time data indicating a different time for each group is stored .
JP2010173827A 2010-08-02 2010-08-02 Electricity supply and demand adjustment system Expired - Fee Related JP5485067B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010173827A JP5485067B2 (en) 2010-08-02 2010-08-02 Electricity supply and demand adjustment system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010173827A JP5485067B2 (en) 2010-08-02 2010-08-02 Electricity supply and demand adjustment system

Publications (2)

Publication Number Publication Date
JP2012034541A JP2012034541A (en) 2012-02-16
JP5485067B2 true JP5485067B2 (en) 2014-05-07

Family

ID=45847288

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010173827A Expired - Fee Related JP5485067B2 (en) 2010-08-02 2010-08-02 Electricity supply and demand adjustment system

Country Status (1)

Country Link
JP (1) JP5485067B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101289784B1 (en) * 2012-06-14 2013-08-07 주식회사 케이디파워 Decentralized power grid-connected distribution system using sunrise-sunset time and grid-connetion method for decentralized power supply system using the same
JP6424038B2 (en) * 2014-07-25 2018-11-14 株式会社ダイヘン Welding apparatus and processing system

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1023670A (en) * 1996-06-28 1998-01-23 Shinko Electric Co Ltd Method for controlling output of non-utility feeding device and output controlling device
JP4667554B2 (en) * 2000-01-17 2011-04-13 大阪瓦斯株式会社 Power supply device having an inverter
JP3925350B2 (en) * 2002-08-23 2007-06-06 株式会社日立製作所 Coordinating controller for electric power equipment
JP4123006B2 (en) * 2003-02-25 2008-07-23 松下電工株式会社 Solar power system
JP5350011B2 (en) * 2009-02-26 2013-11-27 三洋電機株式会社 Grid interconnection device and power distribution system
JP4743351B2 (en) * 2009-12-02 2011-08-10 コニカミノルタホールディングス株式会社 Power sale management system

Also Published As

Publication number Publication date
JP2012034541A (en) 2012-02-16

Similar Documents

Publication Publication Date Title
WO2019130540A1 (en) System, control device, method for controlling mining units, and program
US10552925B2 (en) Electricity distribution arrangement, system and method
CN103854232A (en) Systems and methods for configuring, optimizing and managing micro-grids
KR101231707B1 (en) Intelligent outlet for plc communication capable of meter-reading and remote control
US20140277800A1 (en) Power Management System For A Structure
Ratnam et al. Receding horizon optimization-based approaches to managing supply voltages and power flows in a distribution grid with battery storage co-located with solar PV
WO2012106029A1 (en) Smart node
BR112013032908B1 (en) APPARATUS AND METHOD FOR CONTROLLING POWER SERVICE EQUIPMENT CONNECTED TO AN ELECTRICAL POWER NETWORK AND READABLE STORAGE MEDIA
WO2009020752A2 (en) Method and system for measurement and control of individual circuits
KR20180008799A (en) Intelligent control system for power generation equipment
CN102812608B (en) Method and apparatus for recording electrical consumption and production
US20200020050A1 (en) Elimination of the protected loads panel through hardware-enabled dynamic load management
JP5485067B2 (en) Electricity supply and demand adjustment system
EP2525462B1 (en) Demand response management system and method with VAR support
JP2012155713A (en) Methods and apparatus for controlling loads coupled to electrical grid
CN107394624A (en) Smart home distribution box and power distribution control method
US12034303B2 (en) Systems and methods for managing electricity supply from demand
WO2014058969A2 (en) Use of a demand response to enable improved power supply restoration planning
US20230394602A1 (en) Systems and methods for managing electricity supply from demand
JP2012198889A (en) Systems and methods for generating bill
Obushevs et al. Demand side management platform for HAN flexibility estimation with agent control
JP6143420B2 (en) System and method for generating billing
US20130128392A1 (en) System and Method for Securely Connecting Energy Devices to a Power Bus
Paunescu et al. Hardware home energy management system for monitoring the quality of energy service at small consumers
Jeddi et al. Network impact of multiple HEMUs with PVs and BESS in a low voltage distribution feeder

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20121203

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20121225

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130205

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130806

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140218

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140219

R150 Certificate of patent or registration of utility model

Ref document number: 5485067

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees