JP5388786B2 - How to build a tunnel - Google Patents

How to build a tunnel Download PDF

Info

Publication number
JP5388786B2
JP5388786B2 JP2009234013A JP2009234013A JP5388786B2 JP 5388786 B2 JP5388786 B2 JP 5388786B2 JP 2009234013 A JP2009234013 A JP 2009234013A JP 2009234013 A JP2009234013 A JP 2009234013A JP 5388786 B2 JP5388786 B2 JP 5388786B2
Authority
JP
Japan
Prior art keywords
tunnel
segment
lining
general
connecting segment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2009234013A
Other languages
Japanese (ja)
Other versions
JP2011080284A (en
Inventor
憲二 三戸
郁夫 大江
充志 芥川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nishimatsu Construction Co Ltd
Original Assignee
Nishimatsu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nishimatsu Construction Co Ltd filed Critical Nishimatsu Construction Co Ltd
Priority to JP2009234013A priority Critical patent/JP5388786B2/en
Publication of JP2011080284A publication Critical patent/JP2011080284A/en
Application granted granted Critical
Publication of JP5388786B2 publication Critical patent/JP5388786B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、道路トンネル等、合流部・分岐部や非常駐車帯などのトンネル拡幅部を有するトンネルの構築方法に関する。   The present invention relates to a method for constructing a tunnel having a tunnel widening portion such as a junction, a branching portion, or an emergency parking zone such as a road tunnel.

本出願人は、本体周面から突出可能な拡幅用カッタを備えるシールド機を用いて、トンネル断面に拡幅部を構築する技術を提案した(特許文献1参照)。   The present applicant has proposed a technique for constructing a widened portion in a tunnel cross section using a shield machine provided with a widening cutter that can protrude from the peripheral surface of the main body (see Patent Document 1).

また、本出願人は、本線トンネルと支線トンネルとの合流部を構築する技術を提案した(特許文献2参照)。具体的には、合流部の区間において、本線トンネルと支線トンネルとを互いに寄り添うように掘進すると共に、それぞれ突起付きセグメントを上部及び下部に含むほぼ円形の覆工を組み立てる。次いで、突起付きセグメントの突起部を押し出して、本線トンネルと支線トンネルの上部及び下部に突起を形成する。そして、これらの突起部間に架け渡すように鋼殻を取り付け、この鋼殻と覆工の間の空間に充填材を充填して本線トンネルと支線トンネルの覆工を一体化させ、これら本線トンネルと支線トンネルと鋼殻とからなる覆工の断面の包絡線がほぼ円形になるように構築する。これによれば、地上から開削することなく、シールド機に工夫を必要とせず、それらのコストを削減することができる。また、合流される本線トンネルを供用しながら、シールドトンネルの合流部を構築することができる。   In addition, the present applicant has proposed a technology for constructing a junction between a main tunnel and a branch tunnel (see Patent Document 2). Specifically, in the section of the junction, the main tunnel and the branch tunnel are dug so as to be close to each other, and a substantially circular lining including a segment with a protrusion at the upper part and the lower part is assembled. Next, the projections of the segments with projections are extruded to form projections on the upper and lower portions of the main tunnel and the branch tunnel. Then, a steel shell is attached so as to be bridged between these protrusions, and the space between the steel shell and the lining is filled with a filler to integrate the lining of the main tunnel and the branch tunnel. And the envelope of the cross section of the lining consisting of the branch tunnel and steel shell is constructed so as to be almost circular. According to this, without cutting from the ground, it is not necessary to devise the shield machine, and it is possible to reduce their costs. In addition, the merging part of the shield tunnel can be constructed while using the merged main tunnel.

特開2005−54528号公報JP 2005-54528 A 特開2008−14076号公報JP 2008-14076 A

ところで、本線トンネルと支線トンネルとの間で、トンネル長さ方向の誤差、トンネル幅方向の誤差、鉛直方向の誤差、ローリングによる誤差が生じる。   By the way, an error in the tunnel length direction, an error in the tunnel width direction, an error in the vertical direction, and an error due to rolling occur between the main tunnel and the branch tunnel.

本発明の課題は、トンネルの拡幅部や合流部において、本線トンネルと支線トンネルとの間の誤差を容易に調整することができるトンネルの構築方法を提供することである。   The subject of this invention is providing the construction method of the tunnel which can adjust easily the difference | error between a main line tunnel and a branch tunnel in the widening part and confluence | merging part of a tunnel.

以上の課題を解決するため、請求項1に記載の発明は、トンネルの構築方法であって、ほぼ平行に掘進される本線トンネル及び支線トンネルの覆工間の地中を掘削して空洞部を形成した後、前記本線トンネル及び前記支線トンネルの上部の覆工セグメント間に連結セグメントを配置するとともに、前記本線トンネル及び前記支線トンネルの下部の覆工セグメント間に連結セグメントを配置し、前記覆工セグメント及び前記連結セグメントの対向する端面の間に、上側の端部の間隔が下側の端部の間隔よりも広くなるように隙間を設け、両セグメントの間に、前記覆工セグメント及び前記連結セグメントの端面とそれぞれ平行な端部を有する調整板を落とし込み、その後、前記覆工セグメントと前記連結セグメントとの間にコンクリートを打設することを特徴とする。   In order to solve the above-mentioned problems, the invention described in claim 1 is a tunnel construction method, in which a hollow portion is formed by excavating the underground between the main tunnel and the branch tunnel lining that are dug in parallel. After forming, a connecting segment is arranged between the main line tunnel and the upper lining segment of the branch tunnel, and a connecting segment is arranged between the main line tunnel and the lower lining segment of the branch tunnel, and the lining A gap is provided between the segments and the opposing end faces of the connecting segment so that the interval between the upper end portions is wider than the interval between the lower end portions. Drop the adjusting plate that has end portions parallel to the end faces of the segments, and then place concrete between the lining segment and the connecting segment And wherein the Rukoto.

請求項2に記載の発明は、請求項1に記載のトンネルの構築方法であって、前記両セグメントの端面に上下方向に複数の溝を設け、前記調整板の端部を前記溝と係合させることを特徴とする。   A second aspect of the present invention is the tunnel construction method according to the first aspect, wherein a plurality of grooves are provided on the end surfaces of the two segments in the vertical direction, and the end portions of the adjusting plate are engaged with the grooves. It is characterized by making it.

請求項3に記載の発明は、請求項1または2に記載のトンネルの構築方法であって、前記覆工セグメントと前記連結セグメントとを鉄筋で接続することを特徴とする。   The invention according to claim 3 is the tunnel construction method according to claim 1 or 2, characterized in that the lining segment and the connecting segment are connected by a reinforcing bar.

本発明によれば、トンネルの拡幅部や合流部において、本線トンネルと支線トンネルとの間の誤差を容易に調整することができる。   ADVANTAGE OF THE INVENTION According to this invention, the error between a main line tunnel and a branch line tunnel can be easily adjusted in the widening part and confluence | merging part of a tunnel.

本発明を適用した一実施形態の構成を示すもので、トンネル合流部の一体化覆工を示した概略正面図である。The structure of one Embodiment to which this invention is applied is shown, and it is the schematic front view which showed the integrated lining of the tunnel merge part. トンネル合流部の構築方法を示す説明図である。It is explanatory drawing which shows the construction method of a tunnel junction part. トンネル合流部の構築方法を示す説明図である。It is explanatory drawing which shows the construction method of a tunnel junction part. トンネル合流部の構築方法を示す説明図である。It is explanatory drawing which shows the construction method of a tunnel junction part. 一般セグメント6と連結セグメント9との接合部10の拡大図である。It is an enlarged view of the junction part 10 of the general segment 6 and the connection segment 9. FIG. 図5のVI矢視図である。FIG. 6 is a view on arrow VI in FIG. 5.

以下、図を参照して本発明を実施するための最良の形態を詳細に説明する。
図1は本発明を適用した一実施形態の構成としてトンネル合流部の一体化覆工を示したものである。図示のように、トンネル合流部は、本線トンネル1を構成する一側方の一般セグメント2と、本線トンネル1に接近してほぼ平行に掘進される支線トンネルであるランプトンネル5を構成する反対側の一般セグメント6と、一般セグメント2及び一般セグメント6の上下を連結する連結セグメント9とからなる。一般セグメント2及び一般セグメント6と連結セグメント9とは接合部10により接合されている。
Hereinafter, the best mode for carrying out the present invention will be described in detail with reference to the drawings.
FIG. 1 shows an integrated lining of a tunnel junction as a configuration of an embodiment to which the present invention is applied. As shown in the figure, the tunnel junction is composed of a general segment 2 on one side that constitutes the main tunnel 1 and an opposite side that constitutes a ramp tunnel 5 that is a branch tunnel that is dug in parallel to the main tunnel 1. The general segment 6 and a general segment 2 and a connecting segment 9 that connects the upper and lower sides of the general segment 6. The general segment 2, the general segment 6, and the connection segment 9 are joined by a joint 10.

トンネル合流部の構築方法について、以下説明する。まず、図2に示すように、地盤中に本線トンネル1を形成する。このとき、本線トンネルは、一般セグメント2及び切削セグメント4から形成する。一般セグメント2に対し、切削セグメント4は薄いものが用いられる。切削セグメント4は、ランプトンネル5を掘削するシールド掘削機のカッタによって掘削可能な材料からなる。
次に、上下の一般セグメント2の間に隔壁セグメント3を設置し、隔壁セグメント3と一般セグメント2との間の空間に図示しない内部支保工を設置する。なお、隔壁セグメント3は、後述するランプトンネル5を掘削するシールド掘削機のカッタによって切削されない位置に設置する。
次に、隔壁セグメント3と切削セグメント4との間の空間に裏込め材16を裏込め充填する。
The construction method of the tunnel junction will be described below. First, as shown in FIG. 2, the main tunnel 1 is formed in the ground. At this time, the main tunnel is formed from the general segment 2 and the cutting segment 4. The cutting segment 4 is thinner than the general segment 2. The cutting segment 4 is made of a material that can be excavated by a cutter of a shield excavator that excavates the ramp tunnel 5.
Next, the partition segment 3 is installed between the upper and lower general segments 2, and an internal support (not shown) is installed in the space between the partition segment 3 and the general segment 2. In addition, the partition segment 3 is installed in the position which is not cut by the cutter of the shield excavator which excavates the ramp tunnel 5 mentioned later.
Next, the backfill material 16 is backfilled into the space between the partition wall segment 3 and the cutting segment 4.

次に、図3に示すように、地盤中にランプトンネル5を形成する。このとき、ランプトンネル5は、一般セグメント6及び撤去用セグメント8から形成する。なお、ランプトンネル5を掘削するシールド掘削機のカッタによって切削セグメント4が切削される。その後、ランプトンネル5の内部にも図示しない内部支保工、作業構台を設置する。   Next, as shown in FIG. 3, the ramp tunnel 5 is formed in the ground. At this time, the ramp tunnel 5 is formed from the general segment 6 and the removal segment 8. The cutting segment 4 is cut by a cutter of a shield excavator that excavates the ramp tunnel 5. Thereafter, an internal support and a work gantry (not shown) are also installed inside the lamp tunnel 5.

次に、本線トンネル1及びランプトンネル5の覆工を囲む地中に対し、図示しないが、本線トンネル1の内部とランプトンネル5の内部から止水薬液注入工を予めそれぞれ行う。同様に、本線トンネル1及びランプトンネル5の覆工間の地中にも予め止水薬液注入工を行っておく。あるいは、凍結工法により本線トンネル1及びランプトンネル5の覆工を囲む地盤の改良を行ってもよい。   Next, although not shown in the figure surrounding the lining of the main tunnel 1 and the lamp tunnel 5, a water-stopping chemical injection is performed in advance from the inside of the main tunnel 1 and the inside of the lamp tunnel 5. Similarly, a water-stopping chemical injection is performed in advance in the ground between the main tunnel 1 and the ramp tunnel 5. Alternatively, the ground surrounding the lining of the main tunnel 1 and the ramp tunnel 5 may be improved by a freezing method.

次に、上部の撤去用セグメント8の一部を撤去する。次に、本線トンネル1及びランプトンネル5の覆工間の上部の地盤を掘削し、連結セグメント9を設置するための空洞部を形成する。   Next, a part of the upper removal segment 8 is removed. Next, the upper ground between the linings of the main tunnel 1 and the ramp tunnel 5 is excavated to form a cavity for installing the connecting segment 9.

次に、図4に示すように、掘削された上部の空洞部の天井部において、長尺鋼管フォアパイリング施工などにより図示しない支保工を形成し、支保工の下部に連結セグメント9を配置する。その後、一般セグメント2、6と連結セグメント9とを接続する。
同様に、掘削された空洞部の底部においても、一般セグメント2、6と連結セグメント9とを接続する。
Next, as shown in FIG. 4, in the ceiling of the excavated upper cavity, a support work (not shown) is formed by long steel pipe fore-piling construction, and the connecting segment 9 is arranged at the lower part of the support work. Thereafter, the general segments 2 and 6 and the connecting segment 9 are connected.
Similarly, the general segments 2 and 6 and the connecting segment 9 are connected at the bottom of the excavated cavity.

その後、内部支保工、作業構台、撤去用セグメント8及び隔壁セグメント3を完全に撤去する。以上により、図1に示すようにトンネルの拡幅部が構築される。   Thereafter, the internal support work, the work gantry, the removal segment 8 and the bulkhead segment 3 are completely removed. Thus, the widened portion of the tunnel is constructed as shown in FIG.

ここで、一般セグメント6と連結セグメント9との接続構造について説明する。
図5は一般セグメント6と連結セグメント9との接合部10の拡大図であり、図6は図5のVI矢視図である。図5に示すように、一般セグメント6及び連結セグメント9の対向面は傾斜している。一般セグメント6と連結セグメント9とは、上側の端部の間隔が下側の端部の間隔よりも広くなっている。なお、上側の連結セグメント9では、トンネル外側が上側であるが、下側の連結セグメントでは、トンネル内側が上側となる。
Here, a connection structure between the general segment 6 and the connecting segment 9 will be described.
FIG. 5 is an enlarged view of the joint portion 10 between the general segment 6 and the connecting segment 9, and FIG. As shown in FIG. 5, the opposing surfaces of the general segment 6 and the connecting segment 9 are inclined. In the general segment 6 and the connecting segment 9, the interval between the upper end portions is wider than the interval between the lower end portions. In the upper connection segment 9, the tunnel outer side is the upper side, but in the lower connection segment, the tunnel inner side is the upper side.

また、一般セグメント6及び連結セグメント9の対向面には、図6に示すように、複数の溝71、72が上下方向に設けられている。各溝71、72の幅は一定であり、トンネルの長さ方向に一定間隔で設けられている。   Further, as shown in FIG. 6, a plurality of grooves 71 and 72 are provided in the vertical direction on the opposing surfaces of the general segment 6 and the connecting segment 9. The widths of the grooves 71 and 72 are constant, and are provided at regular intervals in the length direction of the tunnel.

一般セグメント6と連結セグメント9との対向面の間には、調整板73が複数枚、配置されている。調整板73は楔形の鋼板であり、調整板73の上下2辺は平行である。調整板73の非平行な2辺は、それぞれ一般セグメント6及び連結セグメント9の端面と平行であり、それぞれ溝71、72に嵌め込まれている。   A plurality of adjustment plates 73 are arranged between the facing surfaces of the general segment 6 and the connecting segment 9. The adjustment plate 73 is a wedge-shaped steel plate, and the upper and lower sides of the adjustment plate 73 are parallel. The non-parallel two sides of the adjustment plate 73 are parallel to the end surfaces of the general segment 6 and the connecting segment 9, respectively, and are fitted in the grooves 71 and 72, respectively.

また、一般セグメント6と連結セグメント9とは、対向する端部の下側部分が鉄筋77により接続されている。
一般セグメント6と連結セグメント9との隙間には、調整板73及び鉄筋77のかぶり厚が充分となるようにコンクリート20が打設される。
The general segment 6 and the connecting segment 9 are connected by a reinforcing bar 77 at the lower part of the opposing end.
Concrete 20 is placed in the gap between the general segment 6 and the connecting segment 9 so that the cover thickness of the adjusting plate 73 and the reinforcing bar 77 is sufficient.

以下、一般セグメント6と連結セグメント9との接続方法について説明する。まず、一般セグメント6と連結セグメント9との対向部において、対向する端部のトンネル内側部分同士を鉄筋77で接続する。次に、一般セグメント6と連結セグメント9との対向部において、上方から調整板73を溝71、72に落とし込む。その後、一般セグメント6と連結セグメント9との間にコンクリート20を打設する。   Hereinafter, the connection method of the general segment 6 and the connection segment 9 is demonstrated. First, in the opposing part of the general segment 6 and the connection segment 9, the tunnel inner parts of the opposing edge part are connected by the reinforcing bar 77. Next, the adjustment plate 73 is dropped into the grooves 71 and 72 from above at the facing portion between the general segment 6 and the connecting segment 9. Thereafter, concrete 20 is placed between the general segment 6 and the connecting segment 9.

なお、一般セグメント2と連結セグメント9との接合構造は、一般セグメント6と連結セグメント9との接合構造と同様であるので説明を割愛する。   In addition, since the joining structure of the general segment 2 and the connection segment 9 is the same as the joining structure of the general segment 6 and the connection segment 9, description is omitted.

ここで、本発明により本線トンネル1とランプトンネル5との誤差を吸収する方法について説明する。本線トンネル1とランプトンネル5との間には、トンネル長さ方向の誤差、トンネル幅方向の誤差、鉛直方向の誤差、ローリングによる誤差が生ずる。   Here, a method for absorbing an error between the main tunnel 1 and the lamp tunnel 5 according to the present invention will be described. Between the main tunnel 1 and the ramp tunnel 5, an error in the tunnel length direction, an error in the tunnel width direction, an error in the vertical direction, and an error due to rolling are generated.

本発明において、トンネル長さ方向の誤差については、調整板73を嵌めこむ溝71、72の相対位置をトンネル長さ方向にずらすことにより調整することができる。また、トンネル幅方向の誤差については、一般セグメント6と連結セグメント9との位置を幅方向にずらすとともに、調整板73の位置を上下方向にずらすことにより調整することができる。同様に、鉛直方向の誤差及びローリングによる誤差についても、一般セグメント6と連結セグメント9との位置をずらすことにより調整することができる。   In the present invention, the error in the tunnel length direction can be adjusted by shifting the relative positions of the grooves 71 and 72 into which the adjustment plate 73 is fitted in the tunnel length direction. The error in the tunnel width direction can be adjusted by shifting the positions of the general segment 6 and the connecting segment 9 in the width direction and shifting the position of the adjustment plate 73 in the vertical direction. Similarly, errors in the vertical direction and errors due to rolling can be adjusted by shifting the positions of the general segment 6 and the connecting segment 9.

以上のとおり、本線トンネル1及びランプトンネル5の覆工において、その間の地中を掘削するとともに、上下の一般セグメント2、6の外周側の地中まで掘削して空洞部を形成した後、上下の一般セグメント2、6の間に連結セグメント9をそれぞれ架け渡すことで、シールド機に工夫を必要とせずに、図1に示すように、外圧に強い楕円形状のトンネル合流部を構築することができる。   As described above, in the lining of the main tunnel 1 and the ramp tunnel 5, after excavating the underground between them and excavating the underground of the upper and lower general segments 2 and 6 to form the cavity, By connecting the connecting segments 9 between the general segments 2 and 6, respectively, it is possible to construct an elliptical tunnel junction that is resistant to external pressure as shown in FIG. it can.

なお、以上の実施形態においては、1本の溝71、72に1枚の調整板73を嵌め込むこととしたが、本発明はこれに限らず、1本の溝71、72に複数枚の調整板73を嵌め込んでもよい。また、調整板73の一般セグメント6の端面及び連結セグメント9の端面と平行な面に溝71、72の間隔と等しい間隔で複数の突条を設け、1枚の調整板73の複数の突条を複数の溝71、72に嵌め込むこととしてもよい。   In the above embodiment, one adjustment plate 73 is fitted into one groove 71, 72. However, the present invention is not limited to this, and a plurality of sheets are provided in one groove 71, 72. The adjustment plate 73 may be fitted. Further, a plurality of protrusions are provided on the end face of the general segment 6 of the adjustment plate 73 and a face parallel to the end face of the connecting segment 9 at intervals equal to the intervals of the grooves 71, 72. May be fitted into the plurality of grooves 71, 72.

1 本線トンネル
2、6 一般セグメント
4 切削セグメント
5 支線トンネル
8 撤去用セグメント
9 連結セグメント
20 コンクリート
71、72 溝
73 調整板
77 鉄筋
1 Main tunnel 2, 6 General segment 4 Cutting segment 5 Branch line tunnel 8 Removal segment 9 Connection segment 20 Concrete 71, 72 Groove 73 Adjustment plate 77 Reinforcing bar

Claims (3)

ほぼ平行に掘進される本線トンネル及び支線トンネルの覆工間の地中を掘削して空洞部を形成した後、前記本線トンネル及び前記支線トンネルの上部の覆工セグメント間に連結セグメントを配置するとともに、前記本線トンネル及び前記支線トンネルの下部の覆工セグメント間に連結セグメントを配置し、
前記覆工セグメントと前記連結セグメントとの対向する端面の間に、上側の端部の間隔が下側の端部の間隔よりも広くなるように隙間を設け、
該隙間に、前記覆工セグメントの端面及び前記連結セグメントの端面とそれぞれ平行な両端部を有する調整板を落とし込み、
その後、前記覆工セグメントと前記連結セグメントとの間にコンクリートを打設することを特徴とするトンネルの構築方法。
After excavating the ground between the lining of the main line tunnel and the branch line tunnel excavated substantially in parallel, a connecting segment is arranged between the lining segments at the upper part of the main line tunnel and the branch line tunnel. , A connecting segment is arranged between the main line tunnel and the lining segment under the branch line tunnel,
Between the opposing end surfaces of the lining segment and the connecting segment, a gap is provided so that the interval between the upper end portions is wider than the interval between the lower end portions,
An adjustment plate having both end portions parallel to the end face of the lining segment and the end face of the connecting segment is dropped into the gap,
Then, concrete is cast between the lining segment and the connecting segment, and the tunnel construction method is characterized.
前記両セグメントの端面に上下方向に複数の溝を設け、
前記調整板の端部を前記溝と係合させることを特徴とする請求項1に記載のトンネルの構築方法。
A plurality of grooves are provided in the vertical direction on the end surfaces of the two segments,
The tunnel construction method according to claim 1, wherein an end portion of the adjustment plate is engaged with the groove.
前記覆工セグメントと前記連結セグメントとを鉄筋で接続することを特徴とする請求項1または2に記載のトンネルの構築方法。   The tunnel construction method according to claim 1, wherein the lining segment and the connection segment are connected by a reinforcing bar.
JP2009234013A 2009-10-08 2009-10-08 How to build a tunnel Expired - Fee Related JP5388786B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009234013A JP5388786B2 (en) 2009-10-08 2009-10-08 How to build a tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009234013A JP5388786B2 (en) 2009-10-08 2009-10-08 How to build a tunnel

Publications (2)

Publication Number Publication Date
JP2011080284A JP2011080284A (en) 2011-04-21
JP5388786B2 true JP5388786B2 (en) 2014-01-15

Family

ID=44074585

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009234013A Expired - Fee Related JP5388786B2 (en) 2009-10-08 2009-10-08 How to build a tunnel

Country Status (1)

Country Link
JP (1) JP5388786B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111520145A (en) * 2020-04-29 2020-08-11 中铁七局集团有限公司 Underground excavation tunnel primary support slope adjusting and arch changing construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3031191B2 (en) * 1995-01-26 2000-04-10 鹿島建設株式会社 Construction method of large section tunnel
JPH10212895A (en) * 1997-01-31 1998-08-11 Taisei Corp Shield machine and shield pipe jacking method
JP5106802B2 (en) * 2006-07-07 2012-12-26 西松建設株式会社 Widening part construction method of tunnel
JP4746602B2 (en) * 2007-03-29 2011-08-10 新日本製鐵株式会社 Segment connection structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111520145A (en) * 2020-04-29 2020-08-11 中铁七局集团有限公司 Underground excavation tunnel primary support slope adjusting and arch changing construction method
CN111520145B (en) * 2020-04-29 2021-10-01 中铁七局集团有限公司 Underground excavation tunnel primary support slope adjusting and arch changing construction method

Also Published As

Publication number Publication date
JP2011080284A (en) 2011-04-21

Similar Documents

Publication Publication Date Title
JP4566914B2 (en) Method of constructing rejoined segments and connected tunnels
JP6127193B1 (en) Construction method of large section underground structure
JP5550879B2 (en) How to build a tunnel
JP6147818B2 (en) Large section tunnel construction method and large section lining body
JP2012007465A (en) Retaining wall device
JP5388786B2 (en) How to build a tunnel
JP2005248478A (en) Method for constructing merging part of shield tunnel
JP4782704B2 (en) Widening structure of shield tunnel, shield tunnel segment and shield tunnel widening method
JP5106802B2 (en) Widening part construction method of tunnel
JP2011074570A (en) Method for constructing tunnel
JP5340877B2 (en) How to build a tunnel
JP6229400B2 (en) Tunnel connection structure and tunnel connection method
JP5290115B2 (en) How to build a tunnel
JP4176516B2 (en) Shield machine, tunnel construction method and tunnel
JP2018009388A (en) End structure of preceding element and construction method of underground continuous wall
JP2011080285A (en) Construction method of tunnel
JP6619710B2 (en) Tunnel widening method and tunnel reinforcement device
JP6953225B2 (en) Connection structure and connection method between shield tunnels
JP2011080242A (en) Construction method of tunnel
JP4397797B2 (en) Construction method of underground structure
JP7393256B2 (en) Hexagonal segment with invert and joint structure of hexagonal segment
JP4141321B2 (en) How to construct a confluence of shield tunnels
JP4960986B2 (en) Tunnel lining structure
JP4343078B2 (en) Underground structure and method for constructing underground structure
JP2018066138A (en) Segment wall body and tunnel lining body

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120719

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130523

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20131008

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20131008

R150 Certificate of patent or registration of utility model

Ref document number: 5388786

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees