JP4807036B2 JP2005313059A JP2005313059A JP4807036B2 JP 4807036 B2 JP4807036 B2 JP 4807036B2 JP 2005313059 A JP2005313059 A JP 2005313059A JP 2005313059 A JP2005313059 A JP 2005313059A JP 4807036 B2 JP4807036 B2 JP 4807036B2
Authority
JP
Japan
Prior art keywords
humidity
bathroom
air
drying operation
ventilation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2005313059A
Other languages
Japanese (ja)
Other versions
JP2007120855A (en
Inventor
祐史 山口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Max Co Ltd
Original Assignee
Max Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Max Co Ltd filed Critical Max Co Ltd
Priority to JP2005313059A priority Critical patent/JP4807036B2/en
Publication of JP2007120855A publication Critical patent/JP2007120855A/en
Application granted granted Critical
Publication of JP4807036B2 publication Critical patent/JP4807036B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Accessory Of Washing/Drying Machine, Commercial Washing/Drying Machine, Other Washing/Drying Machine (AREA)
  • Drying Of Solid Materials (AREA)
  • Air Conditioning Control Device (AREA)

Description

この発明は、浴室空調装置に関する。詳しくは、浴室内で衣類などの洗濯物や乾かし物(以下洗濯物等という)を乾燥したのち、乾燥後の洗濯物等を浴室内に放置したり、乾燥時間が不十分であったような場合でも、追加乾燥処理(再乾燥処理)を自動的に行うことで、洗濯物等を確実に乾燥させることができるようにしたものである。   The present invention relates to a bathroom air conditioner. Specifically, after drying laundry and dried items such as clothes (hereinafter referred to as laundry) in the bathroom, the laundry after drying is left in the bathroom or the drying time is insufficient. Even in this case, the laundry can be reliably dried by automatically performing the additional drying process (re-drying process).

乾燥機能付きの空調装置として、浴室空調装置が知られている(特許文献1)。このような浴室空調装置を利用して、浴室内で洗濯物等の乾燥を行う場合には、浴室内に設置されたランドリーパイプ等の物干し部材に洗濯物等を掛け、そして操作部に設けられた乾燥モードスイッチを選択する共に、タイマによって乾燥時間を選択して乾燥運転を行う。   A bathroom air conditioner is known as an air conditioner with a drying function (Patent Document 1). When drying such laundry in the bathroom using such a bathroom air conditioner, the laundry is hung on a laundry member such as a laundry pipe installed in the bathroom, and is provided in the operation unit. The drying mode switch is selected, and the drying operation is performed by selecting the drying time with a timer.

乾燥運転は通常タイマ運転であり、予め選択されたタイマ時間後(例えば4時間後)に乾燥運転が終了し、終了した段階で洗濯物等を浴室から取り出して、タンスなどに収納する。   The drying operation is a normal timer operation, and the drying operation ends after a timer time selected in advance (for example, after 4 hours). When the drying operation is completed, the laundry is taken out of the bathroom and stored in a chest.

特開2004−211959号公報Japanese Patent Application Laid-Open No. 2004-21959

ところで、上述したように乾燥運転は通常タイマ運転であり、設定されたタイマ時間になると乾燥運転が自動的に停止する。タイマ時間の設定が充分でないと、例えば節電を考慮してタイマ時間の設定が短すぎたような場合には、乾燥運転が終了しても洗濯物等が完全には乾燥されていない場合がある。つまり、生乾きの状態となっている。そのような場合には、再度乾燥運転モードを選択し、改めてタイマ時間を設定して乾燥運転を実行しなければならない。   By the way, as described above, the drying operation is a normal timer operation, and the drying operation automatically stops when the set timer time is reached. If the timer time is not set sufficiently, for example, if the timer time is set too short in consideration of power saving, the laundry may not be completely dried even after the drying operation is completed. . In other words, it is in a dry state. In such a case, it is necessary to select the drying operation mode again, set the timer time again, and execute the drying operation.

また、タイマ設定時間が適切で洗濯物等が充分乾燥していても、乾燥運転終了後浴室内に洗濯物等を放置してしまう場合がある。例えば、深夜などに乾燥運転を行うようなときである。洗濯物等を浴室内にそのまま放置すると乾燥した洗濯物等に浴室内の水分が再度付着することになるから、洗濯物等の乾燥が充分でないという問題が生じるおそれもある。   Moreover, even if the timer setting time is appropriate and the laundry is sufficiently dried, the laundry may be left in the bathroom after the drying operation is completed. For example, when drying operation is performed at midnight or the like. If the laundry or the like is left in the bathroom as it is, moisture in the bathroom will adhere to the dried laundry or the like again, which may cause a problem that the laundry or the like is not sufficiently dried.

そこで、この発明はこのような従来の課題を解決したものであって、洗濯物等の乾燥が不十分であるときは、自動的に再度乾燥運転モードを実行するようにしたものである。   Therefore, the present invention solves such a conventional problem, and automatically dries the operation mode again when the laundry or the like is insufficiently dried.

上述した課題を解決するため、この発明に係る浴室空調装置は、浴室内の空調運転を行う空調手段と、浴室内の湿度を検出する湿度検出手段とを備えた浴室空調装置であって、湿度検出手段により乾燥運転開始前の24時間換気運転時に検出した第1の湿度と、乾燥運転終了後に24時間換気運転を再開して所定時間経過後に検出した第2の湿度とを比較する湿度比較手段と、湿度比較手段に基づき、第2の湿度が第1の湿度よりも大きいときは追加乾燥運転を実行し、第2の湿度が第1の湿度以下のときは24時間換気運転を実行するよう制御する制御手段とを備えたことを特徴とする。 To solve the problems described above, the bathroom air conditioning system according to the present invention, there is provided a full air conditioning system comprising a conditioning means for performing air conditioning operation in the bathroom, and a humidity detecting means for detecting the humidity in the bathroom, wet A humidity comparison comparing the first humidity detected during the 24-hour ventilation operation before the start of the drying operation and the second humidity detected after a predetermined time has elapsed after the completion of the drying operation by the degree detection means and means, based on the humidity comparing means, when the second humidity is greater than the first humidity perform additional drying operation, when the second humidity is less than the first humidity perform a 24-hour ventilation operation And a control means for controlling to do so.

この発明では、空調運転モードの1つに乾燥運転モードを用意する。また、浴室内の湿度を検出するため湿度検出手段としての湿度センサを備える。湿度センサは空調装置本体内であって、浴室内の空気を吸い込む吸込口付近に設けることができる。湿度センサのセンサ出力は空調運転を制御する制御・演算部に供給される。   In the present invention, a drying operation mode is prepared as one of the air conditioning operation modes. Moreover, in order to detect the humidity in a bathroom, the humidity sensor as a humidity detection means is provided. The humidity sensor can be provided in the air conditioner main body and in the vicinity of the inlet for sucking air in the bathroom. The sensor output of the humidity sensor is supplied to a control / arithmetic unit that controls the air conditioning operation.

制御・演算部には各種の運転モードを選択するための操作部が関連されている。
したがってこの制御・演算部の機能としては、その一部として検出された湿度を比較し、その結果で空調運転モードを制御する機能が含まれる。
The control / arithmetic unit is associated with an operation unit for selecting various operation modes.
Therefore, the function of this control / calculation unit includes a function of comparing the humidity detected as a part thereof and controlling the air conditioning operation mode based on the result.

浴室空調装置には24時間換気運転モードが用意され、この24時間換気運転モードが選択されているときは、浴室内の湿度が定期的に検出される。洗濯物等を乾燥する乾燥運転モードが選択されたときは、この乾燥運転モードが選択された直前に検出された湿度若しくは乾燥運転モードが選択された直後に検出された湿度を第1の湿度として保存する。第1の湿度については、通常運転されている24時間換気運転モード時に、定期的(例えば30分毎)に湿度をサンプリングして、その平均値を第1の湿度として用いることもできる。その場合には、乾燥運転モードが選択されたタイミングの直前までにサンプリングされた湿度の平均値を使用することができる。24時間換気運転モードでは、第1の湿度(平均値)は50%程度となる。 The bathroom air conditioner is provided with a 24-hour ventilation operation mode. When the 24-hour ventilation operation mode is selected, the humidity in the bathroom is periodically detected. When drying operation mode for drying the laundry or the like is selected, the drying operation mode is detected just before a selected humidity or drying operation mode is detected immediately after the selected humidity first humidity Save as. As for the first humidity, it is possible to sample the humidity periodically (for example, every 30 minutes) and use the average value as the first humidity in the normal operation of the 24-hour ventilation operation mode. In that case, the average value of the humidity sampled immediately before the timing when the drying operation mode is selected can be used. In the 24-hour ventilation operation mode, the first humidity (average value) is about 50%.

次に、乾燥運転モードが終了してから所定時間経過後に、浴室内の湿度を検出する。所定時間とは、30分〜1時間程度である。所定時間が短すぎると、乾燥運転モード時の室内湿度(15〜30%)を検出してしまうおそれがあるからである。検出されたこの湿度を第2の湿度として、第1の湿度と比較する。
Next, the humidity in the bathroom is detected after a lapse of a predetermined time from the end of the drying operation mode. The predetermined time is about 30 minutes to 1 hour. This is because if the predetermined time is too short, indoor humidity (15 to 30%) in the dry operation mode may be detected. This detected humidity is set as the second humidity and compared with the first humidity.

乾燥運転前(直後を含む。)と比較して湿度が上昇しているときは、浴室内の湿度が高くなっていることになるので、この場合には洗濯物等が充分乾燥していないと判断して、追加乾燥運転を行う。追加乾燥運転の運転時間は湿度差によって異ならせる。追加乾燥運転の運転時間と湿度差との関係を、予めマップ化しておけば、湿度差から、その湿度差に適した追加乾燥運転時間や稼働対象を簡単に選択できる。   When the humidity is higher than before (including immediately after) the drying operation, the humidity in the bathroom is higher. In this case, the laundry is not sufficiently dry. Judgment is made and additional drying operation is performed. The operation time for the additional drying operation varies depending on the humidity difference. If the relationship between the operation time of the additional drying operation and the humidity difference is mapped in advance, the additional drying operation time and the operation target suitable for the humidity difference can be easily selected from the humidity difference.

追加乾燥運転は、風量を一定にしてヒータ温度(ヒータ発熱量)と運転時間を、湿度差に応じて可変する場合でもよければ、ヒータ温度を一定にして風量と運転時間を、湿度差に応じて可変してもよいし、あるいはその双方(風量とヒータ温度運転時間)を湿度差に応じて可変にしてもよい。さらに、ヒータに通電せずに循環換気運転を行うようにしてもよい。第1回目の追加乾燥後も継続して湿度を監視して、第2回目以降の追加乾燥を行ってもよい。洗濯物等を確実に乾燥させるためである。   In the additional drying operation, if the air temperature is constant and the heater temperature (heater calorific value) and operation time can be varied according to the humidity difference, the heater temperature is constant and the air flow and operation time according to the humidity difference. Alternatively, both of them (air volume and heater temperature operation time) may be made variable according to the humidity difference. Furthermore, the circulation ventilation operation may be performed without energizing the heater. The humidity may be continuously monitored after the first additional drying, and the second and subsequent additional drying may be performed. This is for reliably drying the laundry.

この発明では、乾燥運転直前の湿度に対して、乾燥運転終了後の湿度が高いときは追加乾燥運転を自動的に行うようにしたものである。これによって、洗濯物等が浴室内に放置されている場合でも、あるいは乾燥運転時間が短く設定させてしまったようなときでも、洗濯物等を確実に乾燥させることができる。   In the present invention, when the humidity after the completion of the drying operation is higher than the humidity immediately before the drying operation, the additional drying operation is automatically performed. Thereby, even when the laundry or the like is left in the bathroom or when the drying operation time is set to be short, the laundry or the like can be reliably dried.

続いて、この発明に係る浴室空調装置の好ましい実施例を図面を参照して詳細に説明する。   Next, a preferred embodiment of a bathroom air conditioner according to the present invention will be described in detail with reference to the drawings.

図1はこの発明に係る浴室空調装置1の適用例であって、洗面所17に隣接した浴室18に設置された状態を示している。   FIG. 1 is an application example of a bathroom air conditioner 1 according to the present invention, and shows a state where the bathroom air conditioner 1 is installed in a bathroom 18 adjacent to a washroom 17.

浴室空調装置1は浴室18の天井に設置される。浴室18の天井パネルには、浴室空調装置1の本体ケース63が入る開口部が形成され、浴室空調装置1は、フロントパネル6が露出するようにして、天井裏から吊り下げる形態、あるいは天井パネルに固定する形態等で取り付けられる。   The bathroom air conditioner 1 is installed on the ceiling of the bathroom 18. The ceiling panel of the bathroom 18 is formed with an opening for receiving the main body case 63 of the bathroom air conditioner 1. The bathroom air conditioner 1 is suspended from the back of the ceiling so that the front panel 6 is exposed, or the ceiling panel. It is attached in the form fixed to

浴室18の天井に取り付けられた浴室空調装置1では、排気ダクト接続部19に排気ダクト20が接続される。排気ダクト20は、建物の外壁に取り付けた排気グリル21に接続される。これにより、浴室空調装置1で吸い込んだ浴室18内の空気を、排気ダクト20を介して外に排気できる構成となっている。   In the bathroom air conditioner 1 attached to the ceiling of the bathroom 18, an exhaust duct 20 is connected to the exhaust duct connection portion 19. The exhaust duct 20 is connected to an exhaust grill 21 attached to the outer wall of the building. Thereby, the air in the bathroom 18 sucked by the bathroom air conditioner 1 can be exhausted to the outside through the exhaust duct 20.

浴室空調装置1は、後述するように洗濯物等を乾燥させる機能を備えているので、浴室18には洗濯物などの洗濯物等27等を掛けるランドリーパイプ(吊り下げ部材)22を備える。吹出口6aから吹き出す空気が、浴槽18a外の洗い場18bなどに居る入浴者に直接当たると、寒さを感じることがあるので、吹き出方向はランドリーパイプ22側に向くように設定される。   Since the bathroom air conditioner 1 has a function of drying laundry etc. as will be described later, the bathroom 18 is provided with a laundry pipe (hanging member) 22 for hanging the laundry 27 such as laundry. When the air blown out from the outlet 6a directly hits a bather in the washing place 18b etc. outside the bathtub 18a, it may feel cold, so the blowing direction is set to face the laundry pipe 22 side.

吹き出方向が調整できる構成では、浴室空調装置1の設置位置に応じて自在に吹き出し方向が調整可能であるので、この場合においてもランドリーパイプ22側に向くように吹き出し方向が設定される。   In the configuration in which the blowing direction can be adjusted, the blowing direction can be freely adjusted according to the installation position of the bathroom air conditioner 1, and in this case as well, the blowing direction is set so as to face the laundry pipe 22 side.

浴室18の入口には浴室ドア23を備える。浴室ドア23は空気取入口(ガラリ)23aを備え、洗面所17等の空気を浴室18内に取り込めるようになっている。   A bathroom door 23 is provided at the entrance of the bathroom 18. The bathroom door 23 is provided with an air inlet 23a, so that air from the washroom 17 and the like can be taken into the bathroom 18.

洗面所17等の他室の空気を吸い込むための吸気ダクト接続部65aを本体ケース63に設け、吸気ダクト接続部65と接続した吸気ダクト65を設けることで、浴室18内の空気に加え、吸気口65bから他室の空気を吸い込み、吸い込んだ空気を屋外へ排気することができる。また、吸気ダクト接続部65を設けたが、これを設けず、他室の換気を行わない構造でもよい。   An intake duct connection portion 65a for sucking in air from other rooms such as the washroom 17 is provided in the main body case 63, and an intake duct 65 connected to the intake duct connection portion 65 is provided. The air in the other room can be sucked from the mouth 65b, and the sucked air can be discharged to the outside. Moreover, although the intake duct connection part 65 was provided, this may not be provided and the structure which does not ventilate another room may be sufficient.

図2〜図5は浴室空調装置1の内部構成例を示すもので、図2は浴室空調装置1の分解斜視図、図3はその平面図、図4は図3のA−A断面図、図5は図3のB−B断面図である。これら断面図は、説明の都合上浴室空調装置1の内部構成を概略的に示した。   2-5 shows the example of an internal structure of the bathroom air conditioner 1, FIG. 2 is an exploded perspective view of the bathroom air conditioner 1, FIG. 3 is the top view, FIG. 4 is AA sectional drawing of FIG. 5 is a cross-sectional view taken along line BB in FIG. These sectional views schematically show the internal configuration of the bathroom air conditioner 1 for convenience of explanation.

図2以下に示す浴室空調装置1は複数の運転モードを実現できるように構成されている。運転モードとは、換気運転モード、暖房運転モード、涼風運転モード、乾燥運転モードなどである。そのため、この浴室空調装置1には、涼風(送風)及び温風を吹き出す循環空調ユニット51(図2以下参照)と、換気ユニット52(図4参照)を備える。   The bathroom air conditioner 1 shown in FIG. 2 and subsequent figures is configured so as to realize a plurality of operation modes. The operation mode includes a ventilation operation mode, a heating operation mode, a cool air operation mode, a dry operation mode, and the like. For this reason, the bathroom air conditioner 1 includes a circulation air conditioning unit 51 (see FIG. 2 and subsequent figures) that blows cool air (air blowing) and warm air, and a ventilation unit 52 (see FIG. 4).

図4に示すように循環空調ユニット51は、循環ファン部53とヒータ部54を備える。循環ファン部53はシロッコファンで循環手段を構成し、循環ファンモータ53aに回転駆動される多翼の羽根車(ファン)55と、風路を形成する循環ファンケース56を備える。   As shown in FIG. 4, the circulation air conditioning unit 51 includes a circulation fan unit 53 and a heater unit 54. The circulation fan unit 53 is a sirocco fan that constitutes circulation means, and includes a multi-blade impeller (fan) 55 that is rotationally driven by a circulation fan motor 53a, and a circulation fan case 56 that forms an air passage.

循環ファンケース56は、羽根車55の軸方向に沿った面を開口して形成される吸込口57aと、羽根車55の接線方向に沿って形成される風路56aと連通した吹出口57bとを備える。   The circulation fan case 56 includes a suction port 57a formed by opening a surface along the axial direction of the impeller 55, and a blowout port 57b communicating with an air passage 56a formed along the tangential direction of the impeller 55. Is provided.

図3に示すヒータ部54は加熱手段を構成し、図5に示すように循環ファンケース56の吹出口57b近傍の風路56aにPTCヒータ58を備える。   The heater part 54 shown in FIG. 3 constitutes a heating means, and as shown in FIG.

換気ユニット52は、図4に示すように換気ファン部59を備える。換気ファン部59はシロッコファンで換気手段を構成し、換気ファンモータ59aに回転駆動される多翼の羽根車(ファン)60と、風路を形成する換気ファンケース61を備える。   The ventilation unit 52 includes a ventilation fan unit 59 as shown in FIG. The ventilation fan unit 59 is a sirocco fan that forms ventilation means, and includes a multi-blade impeller (fan) 60 that is rotationally driven by a ventilation fan motor 59a, and a ventilation fan case 61 that forms an air passage.

換気ファンケース61は、図4に示すように羽根車60の軸方向に沿った面を開口して形成される吸込口62aと、羽根車60の接線方向に沿って形成される風路61aと連通した吹出口62bとを備える。   As shown in FIG. 4, the ventilation fan case 61 includes a suction port 62 a formed by opening a surface along the axial direction of the impeller 60, and an air passage 61 a formed along the tangential direction of the impeller 60. And an air outlet 62b in communication.

循環空調ユニット51と換気ユニット52は本体ケース63に取り付けられる。本体ケース63は、換気ユニット52の吹出口62bと連通する排気ダクト接続部64を一の側面に備える。また、本体ケース63は、排気ダクト接続部64を備えた側面と異なる側面に吸気ダクト接続部65を備える。排気ダクト接続部64に排気ダクト(図示はしない)が接続され、吸気ダクト接続部65に吸気ダクト65aが接続され、例えば、洗面所等の他室に連通し、他室の空気を吸い込むようになっている。吸気ダクト接続部65を複数設けて、洗面所17に加えて図示しないトイレ等の空気を吸い込むようにしてもよい。   The circulation air conditioning unit 51 and the ventilation unit 52 are attached to the main body case 63. The main body case 63 includes an exhaust duct connection portion 64 that communicates with the air outlet 62b of the ventilation unit 52 on one side surface. Further, the main body case 63 includes an intake duct connection portion 65 on a side surface different from the side surface including the exhaust duct connection portion 64. An exhaust duct (not shown) is connected to the exhaust duct connection portion 64, and an intake duct 65a is connected to the intake duct connection portion 65. For example, the exhaust duct connection portion 64 communicates with another room such as a washroom and sucks air in the other room. It has become. A plurality of intake duct connection portions 65 may be provided so as to suck air from a toilet (not shown) in addition to the washroom 17.

換気ユニット52は、図4に示すように本体ケース63の吸気ダクト接続部65と換気ファン部59の吸込口62aが連通して第1の換気風路66aが形成される。   In the ventilation unit 52, as shown in FIG. 4, the intake duct connecting part 65 of the main body case 63 and the suction port 62a of the ventilation fan part 59 communicate with each other to form a first ventilation air passage 66a.

本体ケース63内には、図4に示すように換気ファン部59の吸込口62aの下側に換気風路形成部67が取り付けられ、第2の吸気風路66bを介して吸込口62aと連通する吸気口68が形成される。   In the main body case 63, as shown in FIG. 4, a ventilation air passage forming portion 67 is attached to the lower side of the intake port 62a of the ventilation fan portion 59, and communicates with the intake port 62a via the second intake air passage 66b. An intake port 68 is formed.

本体ケース63の一部であって、浴室18内の空気が循環する風路内には、浴室28内の湿度検出手段が設置される。例えば図5に鎖線で示す風路内、この例では循環ファンケース56内であって、循環ファンモータ53aとPTCヒータ58との間の底面側に湿度検出手段として機能する湿度センサ26が取り付け固定される。   Humidity detection means in the bathroom 28 is installed in a part of the main body case 63 and in an air passage through which the air in the bathroom 18 circulates. For example, the humidity sensor 26 functioning as humidity detecting means is attached and fixed in the air passage shown by a chain line in FIG. Is done.

図6は浴室空調装置1の制御機能部の一例を示すブロック図である。浴室空調装置1の制御機能部においては、CPU(Central Processing Unit)やメモリ等で構成される制御・演算部24に、操作部(リモコン操作部)25及び湿度検出用の湿度センサ26が接続される。制御・演算部24には、さらに循環ファンファン53a、換気ファンモータ59a及びヒータ58等が接続される。操作部25は、例えば浴室空調装置1本体と独立したリモートコントロール装置であって、図1に示すように、洗面所17の壁面等に取り付けられる。   FIG. 6 is a block diagram illustrating an example of a control function unit of the bathroom air conditioner 1. In the control function unit of the bathroom air conditioner 1, an operation unit (remote control operation unit) 25 and a humidity sensor 26 for humidity detection are connected to a control / calculation unit 24 including a CPU (Central Processing Unit) and a memory. The The control / arithmetic unit 24 is further connected to a circulation fan fan 53a, a ventilation fan motor 59a, a heater 58, and the like. The operation unit 25 is, for example, a remote control device independent of the bathroom air conditioner 1 main body, and is attached to the wall surface of the washroom 17 as shown in FIG.

図7は操作部25の一例を示す構成図である。操作部25はLCDなどの表示部39と、各種操作ボタン等を備える。操作ボタンとしては、例えば、浴室空調装置1の電源ON・OFFを行う電源ボタン38、暖房運転モードを選択する暖房モードボタン28と、涼風運転モードを選択する涼風モードボタン29と、換気運転モードを選択する換気モードボタン30と、乾燥運転モードを選択する乾燥モードボタン31を備える。   FIG. 7 is a configuration diagram illustrating an example of the operation unit 25. The operation unit 25 includes a display unit 39 such as an LCD and various operation buttons. As operation buttons, for example, a power button 38 for turning on / off the bathroom air conditioner 1, a heating mode button 28 for selecting a heating operation mode, a cool air mode button 29 for selecting a cool air operation mode, and a ventilation operation mode are provided. A ventilation mode button 30 to be selected and a drying mode button 31 to select a drying operation mode are provided.

乾燥運転モードは、浴室内で洗濯物等を乾燥させるときに使用される運転モードであって、この発明ではこの乾燥運転モードに関連して、浴室18内の湿度を考慮した追加運転モードが設定されている。   The drying operation mode is an operation mode used when drying laundry in the bathroom, and in the present invention, an additional operation mode in consideration of the humidity in the bathroom 18 is set in relation to the drying operation mode. Has been.

選択した運転モードを利用者が確認できるように、例えば各ボタンに対応してランプ32を備え、選択された運転モードのボタンに対応するランプ32が点灯する。タイマボタン33によって設定した時間(タイマ時間)だけ、運転モードが実行される。   In order to allow the user to check the selected operation mode, for example, a lamp 32 is provided corresponding to each button, and the lamp 32 corresponding to the button of the selected operation mode is turned on. The operation mode is executed only for the time set by the timer button 33 (timer time).

さらに、乾燥運転モードの終了ボタン34を備える。この終了ボタン34によって設定された運転時間内であっても強制的に乾燥運転モードを終了させることができる。   Further, a drying operation mode end button 34 is provided. Even within the operation time set by the end button 34, the drying operation mode can be forcibly ended.

このように浴室空調装置1は、複数の運転モードが用意され、その何れかを選択できるようになっている。暖房運転モードから説明する。   As described above, the bathroom air conditioner 1 is provided with a plurality of operation modes, and any one of them can be selected. The heating operation mode will be described.

(1)暖房運転モード
暖房運転モードボタン28が押されると、制御・演算部24からの制御信号に基づいて循環ファンモータ53aとPTCヒータ58が駆動される。循環ファンモータ53aが駆動されると、フロントパネル6の吸込口6bを通して、循環ファン部53の吸込口57aから室内の空気が吸い込まれ、循環ファンケース56によって吹出口57bへと空気が流れる。
(1) Heating Operation Mode When the heating operation mode button 28 is pressed, the circulation fan motor 53a and the PTC heater 58 are driven based on a control signal from the control / calculation unit 24. When the circulation fan motor 53a is driven, indoor air is sucked from the suction port 57a of the circulation fan part 53 through the suction port 6b of the front panel 6, and the air flows to the outlet 57b by the circulation fan case 56.

このとき同時にPTCヒータ58が通電される。PTCヒータ58が加熱されることで風路56aを通る空気が加温され、フロントパネル69の吹出口7から温風が吹き出される。これにより、暖房モードでは冬場等に浴室102を暖めることができる。   At the same time, the PTC heater 58 is energized. As the PTC heater 58 is heated, the air passing through the air passage 56 a is heated, and hot air is blown out from the air outlet 7 of the front panel 69. Thereby, in the heating mode, the bathroom 102 can be warmed in winter or the like.

暖房モードでは、換気ファンモータ59aは駆動されないので、換気は行われない。そのため、暖房モードで暖められた浴室18内の空気が屋外に排出されることはない。   In the heating mode, the ventilation fan motor 59a is not driven, so that ventilation is not performed. Therefore, the air in the bathroom 18 heated in the heating mode is not discharged to the outside.

(2)涼風運転モード
涼風モードボタン29が押されると、制御・演算部24からの制御信号によって循環ファンモータ53aが駆動される。循環ファンモータ53aが駆動されるとフロントパネル6の吸込口6bを通して、循環ファン部53の吸込口57aから室内の空気が吸い込まれ、循環ファンケース56によって吹出口57bへと空気が流れる。
(2) Cool Wind Operation Mode When the cool wind mode button 29 is pressed, the circulation fan motor 53a is driven by a control signal from the control / calculation unit 24. When the circulation fan motor 53a is driven, indoor air is sucked from the suction port 57a of the circulation fan unit 53 through the suction port 6b of the front panel 6, and air flows to the outlet 57b by the circulation fan case 56.

涼風モードでは、PTCヒータ58に対する通電は行われない。したがって風路56aを通る空気は加温されず、室内の温度に応じた送風が吹出口6aから風が吹き出される。これにより、涼風運転モードでは夏場等に浴室空調装置1を扇風機として使用できる。涼風モードでは、換気ファンモータ59aは駆動され、換気が行われ、循環換気運転が行われる。   In the cool breeze mode, the PTC heater 58 is not energized. Therefore, the air passing through the air passage 56a is not heated, and the air corresponding to the room temperature is blown out from the air outlet 6a. Thereby, in the cool breeze operation mode, the bathroom air conditioner 1 can be used as a fan in summer or the like. In the cool air mode, the ventilation fan motor 59a is driven, ventilation is performed, and a circulation ventilation operation is performed.

(3a)換気運転モード
換気モードボタン30が押されると、制御・演算部24からの制御信号によって換気ファンモータ59aが駆動される。換気ファンモータ59aが駆動されると、吸込口6bから浴室18内の空気が吸い込まれ、第2の換気風路66b及び換気ファン部59の吸込口62aを通って浴室18内の空気が屋外に排気される(図4鎖線図示)。
(3a) Ventilation operation mode When the ventilation mode button 30 is pressed, the ventilation fan motor 59a is driven by a control signal from the control / calculation unit 24. When the ventilation fan motor 59a is driven, the air in the bathroom 18 is sucked from the suction port 6b, and the air in the bathroom 18 passes outside through the second ventilation air passage 66b and the suction port 62a of the ventilation fan unit 59. The air is exhausted (shown by the chain line in FIG. 4).

また、図11に示す羽根車60が回転することで、第1の換気風路66a及び換気ファン部59の吸込口62aを通り、図1に示す浴室18外からの空気が吸い込まれ、そして排気される(図4鎖線図示)。   Further, when the impeller 60 shown in FIG. 11 rotates, the air from the outside of the bathroom 18 shown in FIG. 1 is sucked through the first ventilation air passage 66a and the suction port 62a of the ventilation fan unit 59, and then exhausted. (FIG. 4 shows a chain line).

(3b)24時間換気モード
24時間換気モードボタン30aが押されると、制御・演算部24からの制御信号によって換気ファンモータ59aが起動される。換気ファンモータ59aが駆動されると吸気口6bから浴室18内の空気が吸い込まれ、第2の換気風路66b及び換気ファン部59の吸込口62aを通って浴室18内の空気が屋外に排気される(図4鎖線図示)。
(3b) 24-hour ventilation mode When the 24-hour ventilation mode button 30a is pressed, the ventilation fan motor 59a is activated by a control signal from the control / calculation unit 24. When the ventilation fan motor 59a is driven, the air in the bathroom 18 is sucked from the intake port 6b, and the air in the bathroom 18 is exhausted to the outside through the second ventilation air passage 66b and the suction port 62a of the ventilation fan unit 59. (FIG. 4 shows a chain line).

また、図11に示す羽根車60が回転することで、第1の換気風路66a及び換気ファン部59の吸込口62aを通り、図1に示す浴室18外からの空気が吸い込まれ、そして排気される(図4鎖線図示)。   Further, when the impeller 60 shown in FIG. 11 rotates, the air from the outside of the bathroom 18 shown in FIG. 1 is sucked through the first ventilation air passage 66a and the suction port 62a of the ventilation fan unit 59, and then exhausted. (FIG. 4 shows a chain line).

なお、24時間換気モードは、通常選択されており、住宅全体等の所定エリアの換気を所定の換気回数(例えば0.5回/時)を満たすように、連続的にまたは断続的にファンモータ59aが駆動され、浴室18の浴室ドア23aの空気取込口(ガラリ)23aを通して、居室等の他室の空気が吸い込まれて、常時換気を行うようになっている。   The 24-hour ventilation mode is normally selected, and the fan motor is continuously or intermittently set so that the ventilation of a predetermined area such as the entire house satisfies a predetermined ventilation frequency (for example, 0.5 times / hour). 59a is driven, and air in other rooms such as a living room is sucked in through the air inlet 23a of the bathroom door 23a of the bathroom 18 so that ventilation is always performed.

(4a)乾燥運転モード
乾燥モードボタン31が押されると、制御・演算部24からの制御信号によって、循環ファンモータ53a、換気ファンモータ59a及びPTCヒータ58が駆動される。
(4a) Drying Operation Mode When the drying mode button 31 is pressed, the circulation fan motor 53a, the ventilation fan motor 59a, and the PTC heater 58 are driven by a control signal from the control / calculation unit 24.

循環ファンモータ53aが駆動されると、吸込口6bを通して、循環ファン部53の吸込口57aから室内の空気が吸い込まれ、循環ファンケース56によって吹出口57bへと空気が流れる。PTCヒータ58が駆動され通電されると、風路56aを通る空気が加温され、フロントパネル6の吹出口6aから温風が吹き出される。   When the circulation fan motor 53a is driven, indoor air is sucked from the suction port 57a of the circulation fan unit 53 through the suction port 6b, and the air flows to the outlet 57b by the circulation fan case 56. When the PTC heater 58 is driven and energized, the air passing through the air passage 56a is heated and hot air is blown out from the air outlet 6a of the front panel 6.

換気ファンモータ59aが駆動されると、羽根車60が回転することで、浴室18内の空気が吸込口6bから吸い込まれ、吸い込まれた空気は第2の換気風路66b及び換気ファン部59の吸込口62aを通って屋外に排気される。   When the ventilation fan motor 59a is driven, the impeller 60 rotates, so that the air in the bathroom 18 is sucked from the suction port 6b, and the sucked air passes through the second ventilation air passage 66b and the ventilation fan unit 59. The air is exhausted outdoors through the suction port 62a.

これにより、乾燥モードでは、浴室18内に温風を吹き出すことで、ランドリーパイプ22に吊された洗濯物等の洗濯物を乾燥させることができる。   Thus, in the drying mode, by blowing warm air into the bathroom 18, the laundry such as the laundry suspended on the laundry pipe 22 can be dried.

(4b)追加乾燥運転モード
乾燥運転モードが選択されたときには、上述した制御・演算部24では、湿度センサ26からのセンサ出力が監視され、第1の所定条件下での湿度(第1の湿度)と、第2の所定条件下での湿度(第2の湿度)とが比較され、その湿度差の有無が検知され、湿度差があるときはこの湿度差に応じて追加乾燥運転が行われる。
(4b) Additional Drying Operation Mode When the drying operation mode is selected, the control / calculation unit 24 described above monitors the sensor output from the humidity sensor 26 and determines the humidity (first humidity) under the first predetermined condition. ) And the humidity under the second predetermined condition (second humidity), the presence or absence of the humidity difference is detected, and if there is a humidity difference, additional drying operation is performed according to the humidity difference .

ここに、第1の所定条件下とは、乾燥運転モードの直前または直後のことであり、第2の所定条件下とは、乾燥運転モードが終了してから所定時間経過したときを指す。   Here, the first predetermined condition is immediately before or immediately after the drying operation mode, and the second predetermined condition is when a predetermined time has elapsed after the drying operation mode is finished.

この例では、洗濯物等を乾燥する乾燥運転モードが選択されたときは、この乾燥運転モードが選択された直前に検出された湿度若しくは乾燥運転モードが選択された直後に検出された湿度を第1の湿度として保存する。第1の湿度については、通常運転されている24時間換気運転モード時に、定期的(例えば30分毎)に湿度をサンプリングして、その平均値を第1の湿度として用いることができる。その場合には、乾燥運転モードが選択されたタイミングの直前までにサンプリングされた湿度の平均値が第1の湿度として使用される。24時間換気運転モードでは、第1の湿度(平均値)は50%程度となる。   In this example, when the drying operation mode for drying laundry is selected, the humidity detected immediately before the drying operation mode is selected or the humidity detected immediately after the drying operation mode is selected Store as 1 humidity. As for the first humidity, it is possible to sample the humidity periodically (for example, every 30 minutes) and use the average value as the first humidity during the 24-hour ventilation operation mode that is normally operated. In that case, the average value of the humidity sampled immediately before the timing when the drying operation mode is selected is used as the first humidity. In the 24-hour ventilation operation mode, the first humidity (average value) is about 50%.

次に、乾燥運転モードが終了してから所定時間経過後に(第2の所定条件下に相当する)、浴室内の湿度を検出する。所定時間とは、30分〜1時間程度である。所定時間が短すぎると、乾燥運転モード時の室内湿度(15〜30%)を検出してしまうおそれがあるからである。検出されたこの湿度を第2の湿度として、第1の湿度と比較する。   Next, the humidity in the bathroom is detected after a predetermined time has elapsed since the drying operation mode ended (corresponding to a second predetermined condition). The predetermined time is about 30 minutes to 1 hour. This is because if the predetermined time is too short, indoor humidity (15 to 30%) in the dry operation mode may be detected. This detected humidity is set as the second humidity and compared with the first humidity.

乾燥運転前(直後を含む。)と比較して湿度が上昇しているときは、浴室内の湿度が高くなっていることになるので、この場合には洗濯物等が充分乾燥していないと判断して、追加乾燥運転を行う。追加乾燥運転の運転時間は湿度差によって異ならせる。   When the humidity is higher than before (including immediately after) the drying operation, the humidity in the bathroom is higher. In this case, the laundry is not sufficiently dry. Judgment is made and additional drying operation is performed. The operation time for the additional drying operation varies depending on the humidity difference.

追加乾燥運転は、風量を一定にしてヒータ温度(ヒータ発熱量)と運転時間を、湿度差に応じて可変する場合でもよければ、ヒータ温度を一定にして風量と運転時間を、湿度差に応じて可変してもよいし、あるいはその双方(風量とヒータ温度運転時間)を湿度差に応じて可変してもよい。さらに、ヒータ58に通電涼風運転モードと同様な循環ファンモータ53aと換気ファンモータ59aとを駆動した循環換気運転でもよい。   In the additional drying operation, if the air temperature is constant and the heater temperature (heater calorific value) and operation time can be varied according to the humidity difference, the heater temperature is constant and the air flow and operation time according to the humidity difference. Alternatively, both of them (air volume and heater temperature operation time) may be varied according to the humidity difference. Further, the circulation ventilation operation in which the heater 58 is driven by the circulation fan motor 53a and the ventilation fan motor 59a similar to the energized cool wind operation mode may be used.

追加乾燥運転の運転時間と湿度差との関係を、予めテーブル化しておけば、検知された湿度差から、その湿度差に適した追加乾燥運転時間や稼働対象を簡単に選択できる。   If the relationship between the operation time of the additional drying operation and the humidity difference is tabulated in advance, the additional drying operation time and the operation target suitable for the humidity difference can be easily selected from the detected humidity difference.

その一例を以下の(表1)に示す。(表1)に示す湿度比較データテーブルの追加乾燥運転モードは、風量とヒータ発熱量の双方を可変した場合である。この湿度比較データテーブルは、図6に示す湿度比較データテーブル記憶部39に記憶されている。   One example is shown in the following (Table 1). The additional drying operation mode of the humidity comparison data table shown in (Table 1) is a case where both the air volume and the heater heat generation amount are varied. This humidity comparison data table is stored in the humidity comparison data table storage unit 39 shown in FIG.

Figure 0004807036
湿度差が少ないときは、追加乾燥時間は短く設定され、湿度差が大きくなるにつれて追加乾燥時間が長くなるように設定されている。湿度差が大きいときはそれだけ湿気が洗濯物等に付着していると考えられるからである。ただし、(表1)に示した追加乾燥時間の例は、あくまでも一例にすぎない。
Figure 0004807036
When the humidity difference is small, the additional drying time is set short, and the additional drying time is set longer as the humidity difference becomes larger. This is because when the humidity difference is large, it is considered that moisture adheres to the laundry. However, the example of the additional drying time shown in (Table 1) is only an example.

第1回目の追加乾燥後も継続して湿度を監視して、第2回目以降の追加乾燥を行ってもよい。洗濯物等を確実に乾燥させるためである。その場合の追加乾燥運転の終了は、以下の何れかを選択できる。   The humidity may be continuously monitored after the first additional drying, and the second and subsequent additional drying may be performed. This is for reliably drying the laundry. In that case, the end of the additional drying operation can be selected from the following.

(1)リモコン操作部25に設けられた乾燥運転終了ボタン34が選択されたときには、追加乾燥時間が経過する前であっても強制終了する。これは、使用者の意思を尊重するためである。 (1) When the drying operation end button 34 provided on the remote control operation unit 25 is selected, the operation is forcibly ended even before the additional drying time has elapsed. This is to respect the intention of the user.

(2)追加乾燥運転を所定回数行ってから強制終了させる。例えば3回繰り返したなら、強制終了させる。 (2) The additional drying operation is forcibly terminated after a predetermined number of times. For example, if it is repeated three times, it is forcibly terminated.

(3)湿度差が大きいとき、追加乾燥運転を繰り返し行うが、タイマによる設定時間で強制終了させる。例えば8時間後に強制終了させる。この場合には、予め追加乾燥運転の上限時間がタイマによって初期設定されることになる。 (3) When the humidity difference is large, the additional drying operation is repeated, but forcibly terminated at the set time by the timer. For example, it is forcibly terminated after 8 hours. In this case, the upper limit time of the additional drying operation is preset by the timer in advance.

なお、乾燥運転モードは、24時間換気運転モードと併用することも可能である。この場合には、所定の部屋に備えた空気の取り入れ口から、新鮮な外気が取り込まれる。そして、必要換気風量が得られるように換気ファン部59の風量を設定することで、所定換気回数を満たすことができる。風量は、所定換気回数を満たす換気ファン部59の風量を標準と設定することができる。   The dry operation mode can be used in combination with the 24-hour ventilation operation mode. In this case, fresh outside air is taken in from an air intake provided in a predetermined room. And the predetermined ventilation frequency | count can be satisfy | filled by setting the air volume of the ventilation fan part 59 so that required ventilation air volume may be obtained. The air volume can be set to the standard air volume of the ventilation fan unit 59 that satisfies the predetermined ventilation frequency.

続いて、上述した追加乾燥運転機能付きの乾燥運転モードの処理例を図8のフローチャートを参照して説明する。この例は24時間換気運転モードが動作しているときに乾燥運転モードが選択された場合の処理例である。   Next, an example of processing in the drying operation mode with the additional drying operation function described above will be described with reference to the flowchart of FIG. This example is a processing example when the dry operation mode is selected when the 24-hour ventilation operation mode is operating.

図8に示す処理プログラムは乾燥運転モードが選択されたとき起動されるが、24時間換気運転モードが選択されているときには、その前提として湿度センサ26からのセンサ出力(湿度情報)が、定期的にサンプリングされ、サンプリングされた湿度情報の平均値が、制御・演算部24内のメモリ(外部メモリでも可)に第1の湿度情報として保存されているものとする。24時間換気運転モードがオフで、乾燥運転モードのみが選択されるようなケースでは、乾燥運転モードが選択された直後のセンサ出力が読み込まれて、その湿度情報が第1の湿度情報として保存されるものとする。したがって図8は前者の例である。   The processing program shown in FIG. 8 is activated when the drying operation mode is selected. However, when the 24-hour ventilation operation mode is selected, the sensor output (humidity information) from the humidity sensor 26 is periodically assumed as a precondition. It is assumed that the average value of the sampled humidity information is stored as the first humidity information in a memory (or an external memory) in the control / calculation unit 24. In the case where the 24-hour ventilation operation mode is off and only the drying operation mode is selected, the sensor output immediately after the drying operation mode is selected is read and the humidity information is stored as the first humidity information. Shall be. Therefore, FIG. 8 is an example of the former.

24時間換気運転モードが稼働している状態では、吸い込み空気湿度が定期的にサンプリングされる(ステップ81)。この状態のときに乾燥モードボタン31が操作されて乾燥運転モードが選択され、そしてタイマボタン33によって乾燥運転時間が選択されて、乾燥運転時間が設定される(ステップ82)。   In the state where the 24-hour ventilation operation mode is operating, the intake air humidity is periodically sampled (step 81). In this state, the drying mode button 31 is operated to select the drying operation mode, and the drying operation time is selected by the timer button 33 to set the drying operation time (step 82).

これによって乾燥運転が開始されると共に、予めサンプリングされ、平均化された吸い込む空気湿度が第1の湿度として保存される(ステップ83)。追加乾燥運転を行うことによって、浴室18内の湿度は次第に低くなる(下がる)。この湿度低下によって、洗濯物等は次第に乾燥する。   As a result, the drying operation is started, and the intake air humidity sampled and averaged in advance is stored as the first humidity (step 83). By performing the additional drying operation, the humidity in the bathroom 18 gradually decreases (decreases). Due to this decrease in humidity, the laundry and the like are gradually dried.

追加乾燥運転中は設定された乾燥運転時間が監視され、乾燥運転時間が到来することで、乾燥運転が終了する(ステップ84)。乾燥運転が終了すると、24時間換気運転モードに移行すると共に、乾燥運転終了後の所定時間(第1の所定時間であって、大凡30分〜1時間)が経過したとき、吸い込み空気湿度を検知し、検知した空気湿度が第2の湿度として上述したメモリに保存される(ステップ85)。   During the additional drying operation, the set drying operation time is monitored, and when the drying operation time arrives, the drying operation ends (step 84). When the drying operation is completed, the mode shifts to the 24-hour ventilation operation mode, and the intake air humidity is detected when a predetermined time (first predetermined time, approximately 30 minutes to 1 hour) after the drying operation has elapsed. Then, the detected air humidity is stored in the memory described above as the second humidity (step 85).

続いて、第1の湿度と第2の湿度の湿度差が比較され(ステップ86)、第2の湿度が第1の湿度を下回っているときは、乾燥運転モード終了をそのまま維持し、24時間換気運転モードを継続する(ステップ87)。現在の浴室18内の湿度が乾燥運転開始時の湿度よりも下回っているときは、浴室18内の湿度が洗濯物等の洗濯物に付着しにくいので、このまま乾燥運転モードを終了させても洗濯物等の乾燥状態は、そのまま維持すると考えられる。   Subsequently, the humidity difference between the first humidity and the second humidity is compared (step 86). When the second humidity is lower than the first humidity, the end of the drying operation mode is maintained as it is for 24 hours. The ventilation operation mode is continued (step 87). When the current humidity in the bathroom 18 is lower than the humidity at the start of the drying operation, the humidity in the bathroom 18 is less likely to adhere to laundry such as laundry, so washing even if the drying operation mode is terminated as it is. It is thought that the dry state of things etc. is maintained as it is.

これに対して、第2の湿度が第1の湿度よりも大きい(高い)ときには、浴室18の内部湿度が上昇しているものと判断し、洗濯物は生乾きの状態となっていると考えられる。その場合には、(表1)に示した湿度比較データテーブルを参照して追加乾燥運転時間及び稼働対象を指定して追加乾燥運転モードに遷移する(ステップ88)。   On the other hand, when the second humidity is higher (higher) than the first humidity, it is determined that the internal humidity of the bathroom 18 has increased, and the laundry is considered to be in a dry state. . In that case, with reference to the humidity comparison data table shown in (Table 1), the additional drying operation time and the operation target are designated, and a transition is made to the additional drying operation mode (step 88).

そして、1回目の乾燥運転後であって、この追加乾燥運転時間を含めた第2の所定時間が経過したとき、あるいは乾燥終了ボタン34が押されたときは、追加乾燥運転モードを終了させる(ステップ89)。   Then, after the first drying operation, when the second predetermined time including the additional drying operation time has elapsed or when the drying end button 34 is pressed, the additional drying operation mode is terminated ( Step 89).

ここで、ステップ89における第2の所定時間とは、次のケースをそれぞれ含むものとする。   Here, the second predetermined time in step 89 includes the following cases.

(1)追加乾燥処理回数が1回に設定されているときは、テーブルを参照したときの追加乾燥運転時間を指す。この場合にはステップ90には遷移しない。 (1) When the number of additional drying processes is set to 1, it indicates the additional drying operation time when referring to the table. In this case, the process does not transition to step 90.

(2)追加乾燥処理回数が複数回に設定されているときは、最後の追加乾燥運転時間を指す。この場合、次の追加乾燥運転モードに遷移すると、ステップ90において追加乾燥終了後における第1の所定時間を待って第2の湿度を検知する。そして、新たに検知されたこの第2の湿度を基準にして湿度差の比較が行われる(ステップ86)。つまり追加乾燥処理回数ごとに第2の湿度が更新されると共に、湿度比較データテーブルを参照して追加乾燥時間が新たに設定されることになる。 (2) When the number of additional drying processes is set to a plurality of times, it indicates the last additional drying operation time. In this case, when transitioning to the next additional drying operation mode, the second humidity is detected in step 90 after waiting for a first predetermined time after completion of the additional drying. Then, the humidity difference is compared based on the newly detected second humidity (step 86). That is, the second humidity is updated every additional drying process, and the additional drying time is newly set with reference to the humidity comparison data table.

(3)追加乾燥処理回数が設定されず、タイマによる追加乾燥運転の上限時間(例えば8時間)が設定されているときは、この上限時間を指す。したがってこの場合でもステップ90に遷移して第2の湿度の更新が行われ、追加乾燥時間の再設定処理がなされる。 (3) When the number of additional drying processes is not set and an upper limit time (for example, 8 hours) of additional drying operation by a timer is set, this upper limit time is indicated. Accordingly, even in this case, the process proceeds to step 90, where the second humidity is updated, and the additional drying time is reset.

以上のような処理を行うことで、浴室18内に洗濯物が放置されているような場合でも、洗濯物等の乾燥状態を維持できる。   By performing the above processing, the laundry can be kept dry even when the laundry is left in the bathroom 18.

上述した浴室空調装置1は、循環用ファンと換気ファンとを独立して設けたが、循環ファンと換気ファンとを単一のファンで構成し、風路切換手段であるダンパにより、循環風路を換気風路を切り換え、または双方の風路に空気を送風できるような構造であってよく、実施例に記載された浴室空調装置に限られるものではない。   In the bathroom air conditioner 1 described above, the circulation fan and the ventilation fan are provided independently. However, the circulation fan and the ventilation fan are configured as a single fan, and the circulation air path is provided by a damper that is an air path switching unit. The ventilation air passage may be switched, or air may be blown to both air passages, and is not limited to the bathroom air conditioner described in the embodiments.

また、本発明の浴室とは、浴槽を持たないシャワー室も含み、洗面所とは脱衣所を含むものである。   Moreover, the bathroom of this invention also includes the shower room which does not have a bathtub, and a washroom includes a dressing room.

この発明では、浴室内に設置される浴室乾燥機に適用できる。   The present invention can be applied to a bathroom dryer installed in a bathroom.

この発明に係る浴室空調装置の設置例を示す要部断面図である。It is principal part sectional drawing which shows the example of installation of the bathroom air conditioner which concerns on this invention. 浴室空調装置の分解斜視図である。It is a disassembled perspective view of a bathroom air conditioner. 図2の平面図である。FIG. 3 is a plan view of FIG. 2. 図3のA−A断面図である。It is AA sectional drawing of FIG. 図3のB−B断面図である。It is BB sectional drawing of FIG. 浴室空調装置の運転モード制御系を示す要部の系統図である。It is a systematic diagram of the principal part which shows the operation mode control system of a bathroom air conditioner. リモコン操作部の配置例を示す図である。It is a figure which shows the example of arrangement | positioning of a remote control operation part. 追加乾燥処理例を示すフローチャートである。It is a flowchart which shows the example of an additional drying process.

符号の説明Explanation of symbols

1・・・浴室空調装置
6b・・・吸込口
18・・・浴室
24・・・制御・演算部
25・・・操作部
26・・・湿度センサ
27・・・洗濯物
30・・・換気モードボタン
31・・・乾燥モードボタン
34・・・乾燥終了ボタン

DESCRIPTION OF SYMBOLS 1 ... Bathroom air conditioner 6b ... Suction port 18 ... Bathroom 24 ... Control and calculation part 25 ... Operation part 26 ... Humidity sensor 27 ... Laundry 30 ... Ventilation mode Button 31 ... Drying mode button 34 ... Drying end button

Claims (3)

浴室内の空調運転を行う空調手段と、
浴室内の湿度を検出する湿度検出手段とを備えた浴室空調装置であって、
前記湿度検出手段により乾燥運転開始前の24時間換気運転時に検出した第1の湿度と、乾燥運転終了後に24時間換気運転を再開して所定時間経過後に検出した第2の湿度とを比較する湿度比較手段と、
前記湿度比較手段に基づき、前記第2の湿度が前記第1の湿度よりも大きいときは追加乾燥運転を実行し、前記第2の湿度が前記第1の湿度以下のときは24時間換気運転を実行するよう制御する制御手段とを備えた
ことを特徴とする浴室空調装置。
Air-conditioning means for air-conditioning operation in the bathroom;
A bathroom air conditioner comprising humidity detecting means for detecting humidity in the bathroom,
Humidity for comparing the first humidity detected by the humidity detection means during the 24-hour ventilation operation before the start of the drying operation with the second humidity detected after the drying operation is resumed for a predetermined time after the completion of the drying operation. A comparison means;
Based on the humidity comparison means, an additional drying operation is performed when the second humidity is greater than the first humidity, and a 24-hour ventilation operation is performed when the second humidity is less than or equal to the first humidity. A bathroom air conditioner comprising control means for controlling execution.
前記制御手段は、前記湿度比較手段と、予め設定されたデータテーブルに基づいて、湿度差に適した追加乾燥運転時間を決定する
ことを特徴とする請求項1記載の浴室空調装置。
The bathroom air conditioner according to claim 1 , wherein the control means determines an additional drying operation time suitable for a humidity difference based on the humidity comparison means and a preset data table .
前記制御手段は、前記追加乾燥運転の実行時間が予め設定された上限値に達した場合に、前記追加乾燥運転を強制終了する
ことを特徴とする請求項1または請求項2記載の浴室空調装置。
The bathroom air conditioner according to claim 1 or 2 , wherein the control means forcibly terminates the additional drying operation when an execution time of the additional drying operation reaches a preset upper limit value. .
JP2005313059A 2005-10-27 2005-10-27 Bathroom air conditioner Active JP4807036B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005313059A JP4807036B2 (en) 2005-10-27 2005-10-27 Bathroom air conditioner

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005313059A JP4807036B2 (en) 2005-10-27 2005-10-27 Bathroom air conditioner

Publications (2)

Publication Number Publication Date
JP2007120855A JP2007120855A (en) 2007-05-17
JP4807036B2 true JP4807036B2 (en) 2011-11-02

Family

ID=38144895

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005313059A Active JP4807036B2 (en) 2005-10-27 2005-10-27 Bathroom air conditioner

Country Status (1)

Country Link
JP (1) JP4807036B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5577692B2 (en) * 2009-12-22 2014-08-27 ダイキン工業株式会社 AIR CONDITIONER AND METHOD FOR JUDGING FAILURE OF HUMIDITY SENSOR IN THE AIR CONDITIONER
JP5647797B2 (en) * 2010-02-24 2015-01-07 大阪瓦斯株式会社 Drying operation control method for bathroom heating dryer
CN104420147B (en) * 2013-08-30 2018-03-16 博西华电器(江苏)有限公司 dryer and its control method
JP7489579B2 (en) 2021-02-26 2024-05-24 パナソニックIpマネジメント株式会社 Dehumidifier

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001141362A (en) * 1999-09-01 2001-05-25 Matsushita Electric Works Ltd Bathroom clothing dryer
JP4794766B2 (en) * 2001-07-31 2011-10-19 パナソニックエコシステムズ株式会社 Dehumidifier

Also Published As

Publication number Publication date
JP2007120855A (en) 2007-05-17

Similar Documents

Publication Publication Date Title
JP4604588B2 (en) Bathroom air conditioner
JP4321682B2 (en) Bathroom ventilation dryer
JP4330335B2 (en) Bathroom air conditioner
JP4807036B2 (en) Bathroom air conditioner
JP5071491B2 (en) Bathroom air conditioner
JP4994021B2 (en) Bathroom ventilation system and bathroom ventilation system
JP4548027B2 (en) Bathroom air conditioner
JP7270568B2 (en) Bathroom dryer and its control method
JP4572716B2 (en) Bathroom air conditioner
JP4715393B2 (en) Air conditioner
JP4706378B2 (en) Bathroom air conditioner
JP2005164114A (en) Bathroom air conditioning system
JP3567863B2 (en) Bathroom drying equipment
JP3859026B2 (en) Clothes dryer
JP4788242B2 (en) Bathroom air conditioner
JP6413251B2 (en) Blower
JP2004257605A (en) Bathroom ventilation, heating, and drying apparatus
JP2007032874A (en) Air conditioner
JP2013061106A (en) Bathroom heating dryer
JP4042553B2 (en) Bathroom ventilator
JP3521175B2 (en) Operation control method for bathroom heating / drying system, bathroom heating / drying apparatus, and controller therefor
JP6748902B2 (en) Heating system
JP4706386B2 (en) Bathroom air conditioner
JPH10244100A (en) Ventilating drier
JP3862407B2 (en) Bathroom heating dryer

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080917

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110117

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110222

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110422

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20110422

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110719

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110801

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140826

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4807036

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150