JP4494500B2 - Drain material placing device and method - Google Patents

Drain material placing device and method Download PDF

Info

Publication number
JP4494500B2
JP4494500B2 JP2008222428A JP2008222428A JP4494500B2 JP 4494500 B2 JP4494500 B2 JP 4494500B2 JP 2008222428 A JP2008222428 A JP 2008222428A JP 2008222428 A JP2008222428 A JP 2008222428A JP 4494500 B2 JP4494500 B2 JP 4494500B2
Authority
JP
Japan
Prior art keywords
casing
drain material
ground
casings
parallel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2008222428A
Other languages
Japanese (ja)
Other versions
JP2010053659A (en
Inventor
伸二 井上
清久 武山
好英 宮本
Original Assignee
信幸建設株式会社
ドレーン基礎工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=42069853&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=JP4494500(B2) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by 信幸建設株式会社, ドレーン基礎工業株式会社 filed Critical 信幸建設株式会社
Priority to JP2008222428A priority Critical patent/JP4494500B2/en
Publication of JP2010053659A publication Critical patent/JP2010053659A/en
Application granted granted Critical
Publication of JP4494500B2 publication Critical patent/JP4494500B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

本発明は、ドレーン材の打設装置および方法に関し、高さ方向にスペースの制約がある打設現場であっても、ドレーン材を所定の深さまで効率よく打設することができるドレーン材の打設装置および方法に関するものである。   The present invention relates to an apparatus and method for placing a drain material, and is capable of efficiently placing a drain material to a predetermined depth even at a placement site where space is restricted in the height direction. The present invention relates to an installation apparatus and method.

軟弱な粘土地盤の圧密促進やゆるい砂質地盤等の液状化防止対策として、地盤にドレーン材を打設する方法が、知られている。ドレーン材は一般に、その地盤上に高く立設した長いケーシングに内装して打設される。そのため、高さ方向に使用できるスペースの制約がある打設現場の場合には、深い位置までドレーン材を打設することが困難になる。   As a measure for promoting consolidation of soft clay ground and preventing liquefaction of loose sandy ground, a method of placing a drain material on the ground is known. In general, the drain material is placed in a long casing standing high on the ground. Therefore, in the case of a placement site where there is a restriction on the space that can be used in the height direction, it becomes difficult to drive the drain material to a deep position.

そこで、ケーシングおよびドレーン材を、順次継ぎ足して打設する方法が提案されている(例えば、特許文献1参照)。しかしながら、この提案の方法ではケーシングおよびドレーン材を継ぎ足す作業が煩雑になり、作業効率を向上させるには限界があるという問題があり、打設作業の効率性を向上させることができる方法や装置が求められていた。
特開平10−292361号公報
In view of this, there has been proposed a method in which the casing and the drain material are successively added and placed (for example, see Patent Document 1). However, in this proposed method, the work of adding the casing and the drain material becomes complicated, and there is a problem that there is a limit in improving the work efficiency, and the method and apparatus that can improve the efficiency of the placing work Was demanded.
JP-A-10-292361

本発明の目的は、高さ方向にスペースの制約がある打設現場であっても、ドレーン材を所定の深さまで効率的に打設することができるドレーン材の打設装置および方法を提供することにある。   An object of the present invention is to provide a drain material placing apparatus and method that can efficiently place a drain material to a predetermined depth even in a placement site where space is restricted in the height direction. There is.

上記目的を達成するため本発明のドレーン材の打設装置は、長手方向に互いに連結可能な複数本のケーシングと、これらケーシングを順次継ぎ足して先端にアンカーを取付けたドレーン材を内挿した状態で、地盤に打ち込む打ち込み手段と、地盤に打込んだケーシングを地盤上に引抜く引抜き手段とを備えたドレーン材の打設装置において、前記複数本のケーシングを並列させるとともに供給源から繰り出した前記ドレーン材を、これら並列させたケーシングに連続するよう内挿した状態で保持するステーションと、ステーション内でケーシングを1本ずつ移動させる移動手段とを設け、ケーシングの打ち込み工程では、ステーション内で並列させたケーシングを、前記移動手段により順次打ち込み位置に移動させ、ケーシングの引抜き工程では、1本ずつ順次地盤上に露出されて、ドレーン材をケーシングに連続するように内挿させた状態のまま、地盤に打ち込まれている下方のケーシングとの連結を解除されるケーシングを、前記移動手段によりステーション内で並列するように移動させる構成にしたことを特徴とするものである。   In order to achieve the above object, the drain material placing device of the present invention includes a plurality of casings that can be connected to each other in the longitudinal direction, and a state in which the drain material having the anchors attached to the tips by sequentially adding these casings is inserted. In the drain material placing device provided with a driving means for driving into the ground and a pulling means for pulling out the casing driven into the ground onto the ground, the drain which is fed from the supply source while arranging the plurality of casings in parallel A station for holding the material in a state of being continuously inserted in the paralleled casings and a moving means for moving the casings one by one in the stations are provided, and in the casing driving process, they are arranged in parallel in the stations. The casing is sequentially moved to the driving position by the moving means, and the casing is pulled out. Is a casing that is exposed on the ground one by one, and in which the drain material is inserted so as to be continuous with the casing, and the casing is released from the lower casing driven into the ground. The moving device is configured to move in parallel in the station.

ここで、前記ステーション内で並列させたケーシングの下端部近傍および上端部近傍になるようにローラをステーションに設け、これらローラに前記ドレーン材を架け回して、並列させたケーシングに連続するように内挿する構成にすることもできる。或いは、前記ステーション内で並列させたケーシングの下端部近傍および上端部近傍に着脱可能なローラを設け、これらローラに前記ドレーン材を架け回して、並列させたケーシングに連続するように内挿する構成にすることもできる。前記複数本のケーシングの長さは、例えば、5m以上7m以下にする。   Here, rollers are provided in the station so as to be near the lower end portion and near the upper end portion of the casings arranged in parallel in the station, and the drain material is wound around these rollers so as to continue to the casings arranged in parallel. It can also be configured to be inserted. Alternatively, a configuration is provided in which removable rollers are provided in the vicinity of the lower end portion and the upper end portion of the casings arranged in parallel in the station, and the drain material is wound around these rollers and is inserted so as to be continuous with the paralleled casings. It can also be. The length of the plurality of casings is, for example, 5 m or more and 7 m or less.

また、本発明のドレーン材の打設方法は、長手方向に互いに連結可能な複数本のケーシングを順次継ぎ足して、これらケーシングとともに内挿したドレーン材を地盤の所定深さまで打込んだ後、ドレーン材の先端に取付けたアンカーによって、ドレーン材を地盤中に固定した状態にして、ケーシングを地盤上に引抜くドレーン材の打設方法において、前記複数本のケーシングを並列し、供給源から繰り出したドレーン材を、これら並列したケーシングに連続するように内挿しておき、打ち込み位置に配置したケーシングとともに内挿しているドレーン材を地盤に打ち込み、順次、次のケーシングを打ち込み位置に移動させるとともに、この移動させたケーシングと、地盤に打ち込まれている下方のケーシングとを連結し、この移動させたケーシングとともに内挿しているドレーン材を地盤に打ち込む工程を、必要な本数のケーシングに対して繰り返し行なうことによりドレーン材を地盤の所定深さまで打ち込み、その後、打込んだケーシングを、1本ずつ順次地盤上に露出するように引抜いて、ドレーン材をケーシングに連続するように内挿させた状態のまま、地盤上に露出したケーシングと、地盤に打ち込まれている下方のケーシングとの連結を解除して、連結を解除した地盤上のケーシングを並列させるようにしたことを特徴とするものである。   The drain material placing method of the present invention includes a plurality of casings that can be connected to each other in the longitudinal direction in sequence, and the drain material inserted together with the casings is driven to a predetermined depth in the ground, and then the drain material. In the drain material placing method in which the drain material is fixed in the ground by the anchor attached to the tip of the drain, and the casing is pulled out on the ground, the plurality of casings are juxtaposed and the drain fed from the supply source The material is inserted so as to continue to these parallel casings, the drain material inserted together with the casing arranged at the driving position is driven into the ground, and the next casing is sequentially moved to the driving position. And the lower casing that is driven into the ground Repeat the process of driving the drain material inserted together with the ground into the ground by repeating the required number of casings to drive the drain material to the predetermined depth of the ground, and then place the driven casings one by one in order. With the drain material exposed to the top, the drain material is inserted so as to be continuous with the casing, and the connection between the casing exposed on the ground and the lower casing driven into the ground is released. The casings on the ground whose connection has been released are arranged in parallel.

ここで、前記並列したケーシングの下端部近傍および上端部近傍になるようにローラをステーションに取付け、これらローラに前記ドレーン材を架け回して、並列したケーシングに連続するように内挿させ、ケーシングを打込み位置に移動させる際および地盤上に引抜いたケーシングを並列させる際には、必要な箇所のローラに対してドレーン材の架け替えを行なうようにすることもできる。或いは、前記並列したケーシングの下端部近傍および上端部近傍にローラを取付け、これらローラに前記ドレーン材を架け回して、並列したケーシングに連続するように内挿させ、ケーシングを地盤に打ち込む際には、そのケーシングに取付けたローラを取外し、打込んだケーシングを地盤上に引抜いた際には、そのケーシングにローラを取付けるようにすることもできる。   Here, a roller is attached to the station so as to be near the lower end and the upper end of the parallel casings, and the drain material is laid around these rollers, and is inserted so as to be continuous with the parallel casings. When moving to the driving position and when the casings pulled out on the ground are arranged in parallel, it is possible to replace the drain material with respect to the roller at a necessary location. Alternatively, when rollers are attached to the vicinity of the lower end and the upper end of the parallel casings, and the drain material is laid around these rollers to be inserted into the parallel casings, and the casings are driven into the ground. When the roller attached to the casing is removed and the driven casing is pulled out on the ground, the roller can be attached to the casing.

本発明によれば、複数本のケーシングを並列させるとともに供給源から繰り出したドレーン材を、これら並列させたそれぞれのケーシングに連続するよう内挿した状態で保持するステーション内で、並列させたケーシングを移動手段によって、1本ずつ順次打設位置に移動させ、打設位置に配置したケーシングとともに内挿しているドレーン材を打ち込み手段により地盤に打ち込み、順次、次のケーシングを打設位置に移動させるとともに、この移動させたケーシングを、地盤に打ち込んでいる下方のケーシングに連結し、このケーシングとともに内挿しているドレーン材を打ち込み手段により地盤に打ち込む工程を、必要な本数のケーシングに対して繰り返し行なうことにより、高さ方向にスペースの制約がある打設現場であっても、ドレーン材を所定の深さまで打ち込むことができる。   According to the present invention, a plurality of casings are arranged in parallel and the drain material fed from the supply source is held in a state where the drain material is held in a state of being continuously inserted in each of the paralleled casings. The moving means sequentially moves one by one to the placement position, and the drain material inserted together with the casing arranged at the placement position is driven into the ground by the driving means, and the next casing is sequentially moved to the placement position. The step of connecting the moved casing to the lower casing driven into the ground and driving the drain material inserted together with the casing into the ground by the driving means is repeated for the required number of casings. Because of this, even if the installation site has space restrictions in the height direction, It can drive the emissions material to a predetermined depth.

その後、ドレーン材の先端に取付けたアンカーによって、ドレーン材を地盤中に固定した状態にして、打込んだケーシングのみを引抜き手段により、1本ずつ順次地盤上に露出するように引抜いて、ドレーン材をケーシングに連続するように内挿させた状態のまま、地盤上に露出させたケーシングと、地盤に打ち込まれている下方のケーシングとの連結を解除して、連結を解除した地盤上のケーシングを、1本ずつ順次移動手段によって、ステーション内に並列させるようにすることで、高さ方向にスペースの制約がある打設現場であっても、すべてのケーシングを引抜くことができる。   After that, with the anchor attached to the tip of the drain material, the drain material is fixed in the ground, and only the driven casing is pulled out by the pulling means one by one so as to be exposed on the ground one by one. The casing on the ground is released by releasing the connection between the casing exposed on the ground and the lower casing that is driven into the ground, while being inserted in the casing continuously to the casing. By sequentially moving them one by one in the station one by one, it is possible to pull out all the casings even at a placement site where there is a space restriction in the height direction.

そして、ドレーン材を常時、複数本のケーシングに連続するように内挿した状態にして、ケーシングを地盤に打ち込む際には、並列させたケーシングを順次、移動手段により移動させて長手方向に連結させ、ケーシングを引抜く際には、地盤上に引抜いて順次連結を解除したケーシングを、移動手段により移動させて並列させるので、迅速に打設作業を行なうことができ、作業効率を向上させることができる。   And, when the drain material is always inserted into a plurality of casings continuously and driven into the ground, the parallel casings are sequentially moved by the moving means and connected in the longitudinal direction. When pulling out the casing, the casings, which are pulled out on the ground and sequentially released from the connection, are moved by the moving means and arranged in parallel, so that the placing work can be performed quickly and work efficiency can be improved. it can.

以下、本発明のドレーン材の打設装置および方法を実施形態に基づいて説明する。   Hereinafter, the drain material placing device and method of the present invention will be described based on embodiments.

図1に例示するように、この実施形態のドレーン材の打設装置1(以下、打設装置1という)は、バックホウをベースにした車体に取付けられている。この車体にはアウトリガーが設けられており、打設装置1を取付けた際の安定性が確保できるようになっている。打設装置1は、枠体3を基本構造としたステーション2と、ステーション2の下端部に設置された打ち込み引抜き手段8とを備えている。ステーション2には、上側作業足場3aおよび下側作業足場3bが設けられ、上端部には移動手段であるチェーンブロック7が設けられている。   As illustrated in FIG. 1, a drain material placing device 1 (hereinafter, referred to as a placing device 1) of this embodiment is attached to a vehicle body based on a backhoe. This vehicle body is provided with an outrigger so that stability when the driving device 1 is attached can be secured. The driving device 1 includes a station 2 having a frame body 3 as a basic structure, and driving and extracting means 8 installed at a lower end portion of the station 2. The station 2 is provided with an upper work scaffold 3a and a lower work scaffold 3b, and a chain block 7 as a moving means is provided at the upper end.

ステーション2には、長手方向に互いに連結可能な複数本のケーシング4(第1ケーシング4a、第2ケーシング4b、第3ケーシング4c、第4ケーシング4d、第5ケーシング4e)が立った状態で並列して保持されている。ステーション2で保持されるケーシング4の本数は5本に限定されるものではなく、必要な本数のケーシング4が保持される。ケーシング4は、それぞれスタンド上に並立され、外れ止めにより保持されている。   In the station 2, a plurality of casings 4 (first casing 4a, second casing 4b, third casing 4c, fourth casing 4d, and fifth casing 4e) that can be connected to each other in the longitudinal direction are arranged in parallel. Is held. The number of casings 4 held at the station 2 is not limited to five, and a necessary number of casings 4 are held. The casings 4 are juxtaposed on the stand, and are held by a stopper.

また、第2ケーシング4b、第3ケーシング4c、第4ケーシング4dおよび第5ケーシング4eの上端部近傍、下端部近傍になるように、ステーション2にはローラ5a〜5gが固設されている。さらに、ステーション2には、その後端上部に導入ローラ6a、第1ケーシング4aの上方位置(後述する打ち込み位置)に、もう一つの導入ローラ6bが固設されている。   Further, rollers 5a to 5g are fixed to the station 2 so as to be near the upper end and the lower end of the second casing 4b, the third casing 4c, the fourth casing 4d, and the fifth casing 4e. Further, in the station 2, an introduction roller 6a is fixed at the upper end of the rear end, and another introduction roller 6b is fixed above the first casing 4a (a driving position described later).

車体の後側には、ドレーン材Dを巻き取った供給ロール11が軸支されている。この供給ロール11から繰り出したドレーン材Dは、導入ローラ6aを介してステーション2に導入され、それぞれのローラ5a〜5g、導入ローラ6bに架け回されて、ステーション2に保持されたそれぞれのケーシング4に連続するように内挿されている。これらローラ5a〜5gおよび導入ローラ6bは、ドレーン材Dの架け替え作業(ドレーン材Dの架け回しや架け回しているドレーン材Dの取外し等)を容易に行なえるように片持ち構造にすることが好ましい。   A supply roll 11 around which the drain material D is wound is supported on the rear side of the vehicle body. The drain material D fed out from the supply roll 11 is introduced into the station 2 through the introduction roller 6 a, and is laid around the respective rollers 5 a to 5 g and the introduction roller 6 b, and the respective casings 4 held in the station 2. Are interpolated to be continuous. These rollers 5a to 5g and the introduction roller 6b have a cantilever structure so that the drain material D can be easily replaced (for example, the drain material D can be routed or the drain material D that is being routed is removed). Is preferred.

ドレーン材Dの先端は、第1ケーシング4aの下端部から突出し、打ち込み引抜き手段8を通過して地盤の表面近傍まで達し、その先端にはアンカー10が取付けられている。ドレーン材Dは、ステーション2に固設されたそれぞれのローラ5a〜5g、6a、6bに架け回されてケーシング4に内挿されているので、ドレーン材Dとケーシング4とは相対的な移動が円滑に行なえるようになっている。   The leading end of the drain material D protrudes from the lower end of the first casing 4a, passes through the driving and pulling means 8, reaches the vicinity of the surface of the ground, and the anchor 10 is attached to the leading end. Since the drain material D is wound around the rollers 5a to 5g, 6a and 6b fixed to the station 2 and inserted into the casing 4, the drain material D and the casing 4 are relatively moved. It can be done smoothly.

打ち込み引抜き手段8が設置されているステーション2の前方部(図1では、左端部)は、ケーシング4の打ち込み位置になっている。それぞれのケーシング4は、チェーンブロック7により吊設されてステーション2内を水平移動および上下移動できるようになっている。そのため、チェーンブロック7を用いて、ケーシング4を打ち込み位置に移動させ、或いは打ち込み位置にあるケーシング4を他の位置に移動させることができる。   The front portion (left end portion in FIG. 1) of the station 2 where the driving and drawing means 8 is installed is the driving position of the casing 4. Each casing 4 is suspended by a chain block 7 and can move horizontally and vertically in the station 2. Therefore, using the chain block 7, the casing 4 can be moved to the driving position, or the casing 4 at the driving position can be moved to another position.

打ち込み引抜き手段8は、ケーシング4を地盤へ打ち込む打ち込み機能と、地盤に打込まれているケーシング4を地盤上に引抜く引抜き機能を有し、この実施形態では、上下動する保持チャック9を有している。保持チャック9がケーシング4を保持した状態で下方移動すると、ケーシング4が地盤に打込まれ、ケーシング4を保持した状態で上方移動すると、地盤に打ち込まれているケーシング4が引抜かれることになる。   The driving and extracting means 8 has a driving function for driving the casing 4 into the ground and a pulling function for pulling the casing 4 driven into the ground onto the ground. In this embodiment, the driving and pulling means 8 has a holding chuck 9 that moves up and down. is doing. When the holding chuck 9 moves downward with the casing 4 held, the casing 4 is driven into the ground. When the holding chuck 9 moves upward with the casing 4 held, the casing 4 driven into the ground is pulled out.

次に、図2〜図12に基づいて、この打設装置1を用いたドレーン材Dの打設方法を説明する。尚、図2〜図12では、打設装置1の構造を分かり易くするために、上側作業足場3a、下側作業足場3bなど、一部の構成を省略して示している。   Next, a method for placing the drain material D using the placement apparatus 1 will be described with reference to FIGS. 2 to 12, in order to make the structure of the placing device 1 easier to understand, some components such as the upper work scaffold 3a and the lower work scaffold 3b are omitted.

まず、図2〜図8に基づいて、ケーシング4とともにケーシング4に内挿されているドレーン材Dを所定の深さまで打ち込む工程について説明する。チェーンブロック7を用いて、第1ケーシング4aをステーション2の打ち込み位置に移動させ、図2に例示するように、打ち込み引抜き手段8の保持チャック9に保持させる。ドレーン材Dの先端のアンカー10は、第1ケーシング4aの下端部にセットされている。そして、打ち込み引抜き手段8を作動させて第1ケーシング4aとともに、第1ケーシング4aに内挿されているドレーン材Dを地盤に打ち込む。   First, based on FIGS. 2-8, the process of driving in the drain material D inserted in the casing 4 with the casing 4 to the predetermined depth is demonstrated. The first casing 4a is moved to the driving position of the station 2 by using the chain block 7 and is held by the holding chuck 9 of the driving and extracting means 8 as illustrated in FIG. The anchor 10 at the tip of the drain material D is set at the lower end of the first casing 4a. And the driving | pulling extraction means 8 is operated and the drain material D inserted in the 1st casing 4a is driven into the ground with the 1st casing 4a.

第1ケーシング4aをある程度の深さまで打込んだ後は、図3に例示するように架け回されているドレーン材Dを導入ローラ6bおよびローラ5aから取外してフリーな状態にする。そして、第2ケーシング4bをチェーンブロック7に吊設して、打ち込み位置まで移動させる。ドレーン材Dはローラ5b〜5g、導入ローラ6aに架け回されているので、円滑に第2ケーシング4bを移動させることができる。   After driving the first casing 4a to a certain depth, the drain material D laid around as illustrated in FIG. 3 is removed from the introduction roller 6b and the roller 5a to make it free. Then, the second casing 4b is suspended from the chain block 7 and moved to the driving position. Since the drain material D is stretched around the rollers 5b to 5g and the introduction roller 6a, the second casing 4b can be moved smoothly.

第2ケーシング4bを打ち込み位置まで移動させた後は、図4に例示するように第2ケーシング4bの下端部を、地盤に打ち込んでいる第1ケーシング4aの上端部に連結する。その際に、ドレーン材Dを架け回しているローラ5bから取外すとともに、導入ローラ6bに架け回し、弛んでいるドレーン材Dの余長は、供給ロール11側へ巻き戻す。   After the second casing 4b is moved to the driving position, the lower end portion of the second casing 4b is connected to the upper end portion of the first casing 4a driven into the ground as illustrated in FIG. At that time, the drain material D is removed from the roller 5b that is wound around, and the slack of the drain material D that is slackened around the introduction roller 6b is rewound to the supply roll 11 side.

第1ケーシング4aの上端部と第2ケーシング4bの下端部とは嵌合構造になっていて、嵌め込んだ上端部と下端部とにピン等を貫通するように取付けることにより、強固に連結できるようになっている。第2ケーシング4bは、第1ケーシング4aに連結した後でチェーンブロック7から取外す。   The upper end portion of the first casing 4a and the lower end portion of the second casing 4b have a fitting structure, and can be firmly connected by attaching a pin or the like to the inserted upper end portion and lower end portion. It is like that. The second casing 4b is detached from the chain block 7 after being connected to the first casing 4a.

ケーシング4をチェーンブロック7に吊設する作業、吊設しているケーシング4をチェーンブロック7から取外す作業および導入ローラ6bに対するドレーン材Dの架け替え作業、ローラ5bに対するドレーン材Dの取外し作業は、図1に例示した上側作業足場3aに作業者が載って行なうことができる。また、第1ケーシング4aの上端部と第2ケーシング4bの下端部の連結作業、ローラ5aに対するドレーン材Dの取外し作業は、図1に例示した下側作業足場3bに作業者が載って行なうことができる。   The operation of suspending the casing 4 on the chain block 7, the operation of removing the suspended casing 4 from the chain block 7, the replacement operation of the drain material D with respect to the introduction roller 6b, and the operation of removing the drain material D from the roller 5b are as follows: An operator can be carried on the upper work scaffold 3a illustrated in FIG. In addition, the connection work between the upper end of the first casing 4a and the lower end of the second casing 4b and the work of removing the drain material D from the roller 5a are performed by an operator on the lower work scaffold 3b illustrated in FIG. Can do.

次いで、図5に例示するように、第2ケーシング4bを打ち込み引抜き手段8の保持チャック9に保持させて、第2ケーシング4bを地盤に打ち込む。ドレーン材Dは、第1ケーシング4aおよび第2ケーシング4bを連続するように内挿されているので、第2ケーシング4bとともに、第2ケーシング4bに内挿されているドレーン材Dが地盤に打ち込まれることになる。   Next, as illustrated in FIG. 5, the second casing 4 b is driven onto the ground by holding the second casing 4 b on the holding chuck 9 of the driving and extracting means 8. Since the drain material D is inserted so that the first casing 4a and the second casing 4b are continuous, the drain material D inserted in the second casing 4b is driven into the ground together with the second casing 4b. It will be.

第2ケーシング4bをある程度の深さまで打込んだ後は、第3ケーシング4cについても第2ケーシング4bと同様の手順によって、第3ケーシング4cをある程度の深さまで打ち込む。そして、図6に例示するように架け回されているドレーン材Dを導入ローラ6bおよびローラ5eから取外してフリーな状態にする。   After driving the second casing 4b to a certain depth, the third casing 4c is driven to a certain depth for the third casing 4c by the same procedure as the second casing 4b. Then, the drain material D laid around as illustrated in FIG. 6 is removed from the introduction roller 6b and the roller 5e to be in a free state.

次いで、第4ケーシング4dをチェーンブロック7に吊設して、打ち込み位置まで移動させる。ドレーン材Dはローラ5f、5g、導入ローラ6aに架け回されているので、円滑に第4ケーシング4dを移動させることができる。   Next, the fourth casing 4d is suspended from the chain block 7 and moved to the driving position. Since the drain material D is wound around the rollers 5f and 5g and the introduction roller 6a, the fourth casing 4d can be moved smoothly.

第4ケーシング4dを打ち込み位置まで移動させた後は、図7に例示するように第4ケーシング4dの下端部を、地盤に打ち込んでいる第3ケーシング4cの上端部に連結する。その際に、ドレーン材Dをローラ5eに架け回すとともに、導入ローラ6bに架け回し、弛んでいるドレーン材Dの余長は、供給ロール11側へ巻き戻す。   After moving the fourth casing 4d to the driving position, the lower end portion of the fourth casing 4d is connected to the upper end portion of the third casing 4c driven into the ground as illustrated in FIG. At that time, the drain material D is wound around the roller 5e and is also wound around the introduction roller 6b, and the extra length of the slack drain material D is rewound to the supply roll 11 side.

次いで、既述した第2ケーシング4b、第3ケーシング4cと同様に、第4ケーシング4dを打ち込み引抜き手段8の保持チャック9に保持させて地盤に打ち込む。このようにして、第4ケーシング4dとともに、第4ケーシング4dに内挿されているドレーン材Dが地盤に打ち込まれることになる。   Next, similarly to the second casing 4b and the third casing 4c described above, the fourth casing 4d is held by the holding chuck 9 of the driving and extracting means 8 and driven into the ground. In this way, together with the fourth casing 4d, the drain material D inserted in the fourth casing 4d is driven into the ground.

次いで、この実施形態では、架け回されているドレーン材Dを導入ローラ6bおよびローラ5e〜5gから取外してフリーな状態にする。そして、チェーンブロック7を用いて第5ケーシング4eを打ち込み位置まで移動させ、図8に例示するように第5ケーシング4eの下端部を、地盤に打ち込んでいる第4ケーシング4dの上端部に連結する。その際に、ドレーン材Dを導入ローラ6bに架け回し、弛んでいるドレーン材Dの余長は、供給ロール11側へ巻き戻す。   Next, in this embodiment, the drain material D that is being laid is removed from the introduction roller 6b and the rollers 5e to 5g to be in a free state. Then, the fifth casing 4e is moved to the driving position using the chain block 7, and the lower end portion of the fifth casing 4e is connected to the upper end portion of the fourth casing 4d driven into the ground as illustrated in FIG. . At that time, the drain material D is wound around the introduction roller 6b, and the slack drain material D is rewound to the supply roll 11 side.

次いで、第5ケーシング4eとともに内挿しているドレーン材Dを地盤に打ち込むことにより、打ち込む工程が完了する。   Next, the driving step is completed by driving the drain material D inserted together with the fifth casing 4e into the ground.

このように、ケーシング4とともに内挿しているドレーン材Dを地盤に打ち込み、順次、次のケーシング4を打ち込み位置に移動させるとともに、この移動させたケーシング4を地盤に打ち込んでいる下方のケーシング4に連結し、この移動させたケーシング4とともに内挿しているドレーン材Dを地盤に打ち込む工程を、必要な本数のケーシング4に対して繰り返し行なう。   In this way, the drain material D inserted together with the casing 4 is driven into the ground, the next casing 4 is sequentially moved to the driving position, and the moved casing 4 is moved to the lower casing 4 driven into the ground. The step of connecting and driving the drain material D inserted together with the moved casing 4 into the ground is repeated for the required number of casings 4.

ケーシング4を打込み位置に移動させる際には、移動させるケーシング4を円滑に移動できるように必要な箇所のローラ5a〜5g、導入ローラ6bに対してドレーン材Dの架け替え作業を行なうようにすればよく、上記実施形態に例示した架け替え作業に限定されるものではない。   When the casing 4 is moved to the driving position, the replacement work of the drain material D is performed on the rollers 5a to 5g and the introduction roller 6b at necessary positions so that the casing 4 to be moved can be smoothly moved. What is necessary is just and it is not limited to the replacement work illustrated in the said embodiment.

地盤上では、複数本のケーシング4をステーション2に並列させて保持しているので、高さ方向に大きなスペースが不要になる。したがって、高さ方向にスペースの制約がある打設現場であっても、複数本のケーシング4を順次継ぎ足して打ち込むことにより、ドレーン材Dを所定の深さまで打ち込むことができる。ケーシング4の長さは、例えば、5m〜7m程度であり、ドレーン材Dを20m程度の深さまで打ち込む場合には、長さ5mのケーシング4を4本継ぎ足せばよい。従来のように、長さ20mの1本のケーシングを用いる場合と比べて、高さ方向の制約を受けにくくなる。   Since a plurality of casings 4 are held in parallel with the station 2 on the ground, a large space in the height direction becomes unnecessary. Therefore, even in a placement site where space is restricted in the height direction, the drain material D can be driven to a predetermined depth by sequentially adding and driving a plurality of casings 4. The length of the casing 4 is, for example, about 5 m to 7 m, and when the drain material D is driven to a depth of about 20 m, four casings 4 having a length of 5 m may be added. Compared to the case of using a single casing having a length of 20 m as in the prior art, it is less likely to be restricted in the height direction.

しかも、ステーション2で並列している状態のケーシング4を、チェーンブロック7を用いて打ち込み位置に移動させて、ドレーン材Dをケーシング4に連続するように内挿した状態のまま、ケーシング4どうしを長手方向に連結すればよいので、迅速に作業を行なうことができ、作業の煩雑さが軽減される。   Moreover, the casings 4 in parallel at the station 2 are moved to the driving position using the chain block 7, and the casings 4 are kept in a state where the drain material D is inserted so as to be continuous with the casing 4. Since it only has to be connected in the longitudinal direction, the work can be performed quickly, and the complexity of the work is reduced.

次に、図9〜図12に基づいて、地盤に打ち込んだケーシング4を地盤上に引抜くようにする引抜き工程について説明する。この引抜き工程は、上記したケーシング4を打ち込む工程の逆の手順となる。   Next, with reference to FIGS. 9 to 12, a drawing process for drawing the casing 4 driven into the ground onto the ground will be described. This drawing process is the reverse procedure of the process of driving the casing 4 described above.

ドレーン材Dを所定の深さまで打ち込んだ後は、図9に例示するように、打ち込んだケーシング4を打ち込み引抜き手段8の保持チャック9に保持させ、打ち込み引抜き手段8を作動させて地盤上に引抜く。この際に、連結しているケーシング4に、ドレーン材Dを連続するように内挿させた状態のままにしておき、まず、第5ケーシング4eの全長が地盤上に露出するまで引抜く。この状態で、第5ケーシング4eの下端部と第4ケーシング4dの上端部との連結を解除する。連結を解除した後は、導入ローラ6bから架け回されているドレーン材Dを取外してフリーな状態にする。   After the drain material D is driven to a predetermined depth, as shown in FIG. 9, the driven casing 4 is held by the holding chuck 9 of the driving and extracting means 8, and the driving and extracting means 8 is operated and pulled onto the ground. Unplug. At this time, the drain material D is continuously inserted in the connected casing 4 and is first drawn out until the entire length of the fifth casing 4e is exposed on the ground. In this state, the connection between the lower end portion of the fifth casing 4e and the upper end portion of the fourth casing 4d is released. After releasing the connection, the drain material D stretched around the introduction roller 6b is removed to make it free.

次いで、図10に例示するように、第4ケーシング4dとの連結が解除されてフリーになった第5ケーシング4eを、チェーンブロック7に吊設してステーション2の後方位置に移動させる。そして、導入ローラ6b、ローラ5e〜5gにドレーン材Dを架け回す。吊設している第5ケーシング4eは、移動させた位置でチェーンブロック7から取外して、ステーション2内で保持する。   Next, as illustrated in FIG. 10, the fifth casing 4 e released from the connection with the fourth casing 4 d is suspended from the chain block 7 and moved to the rear position of the station 2. Then, the drain material D is wound around the introduction roller 6b and the rollers 5e to 5g. The suspended fifth casing 4 e is removed from the chain block 7 at the moved position and held in the station 2.

上記の引抜き工程を、第4ケーシング4d、第3ケーシング4c、第2ケーシング4b、第1ケーシング4aに対しても順次行なって、フリーになったケーシング4をチェーンブロック7を用いて、ステーション2内で並列するように移動させて保持する。この実施形態では、図11に例示するように、第1ケーシング4aを地盤上に引抜いて、ドレーン材Dをすべてのケーシング4に連続するように内挿させた状態のままにして、ステーション2内にすべてのケーシング4を並列させることにより、引抜き工程が完了する。   The above-described drawing step is sequentially performed on the fourth casing 4d, the third casing 4c, the second casing 4b, and the first casing 4a, and the free casing 4 is used in the station 2 by using the chain block 7. Move and hold in parallel. In this embodiment, as illustrated in FIG. 11, the first casing 4 a is pulled out on the ground, and the drain material D is inserted so as to be continuous with all the casings 4. By pulling all the casings 4 in parallel, the drawing process is completed.

このように、ケーシング4を1本ずつ順次地盤上に露出するように引抜いて、ドレーン材Dをケーシング4に連続するように内挿させた状態のまま、地盤上に露出させたケーシング4と、地盤に打ち込まれている下方のケーシング4との連結を解除し、フリーになった地盤上のケーシング4を、1本ずつ順次、ステーション2内に並列させるようにするので、高さ方向にスペースの制約がある打設現場であっても、すべてのケーシング4を引抜くことができる。   In this way, the casing 4 is pulled out so as to be sequentially exposed on the ground one by one, and the casing 4 exposed on the ground with the drain material D being inserted so as to be continuous with the casing 4, The connection with the lower casing 4 that has been driven into the ground is released, and the casings 4 on the ground that have become free are arranged in parallel in the station 2 one by one. All casings 4 can be pulled out even at a placement site with restrictions.

しかも、連結を解除してフリーになったケーシング4を、チェーンブロック7を用いてドレーン材Dをケーシング4に連続するように内挿した状態のまま、並列するように移動させればよいので、迅速に作業を行なうことができ、作業の煩雑さが軽減される。   Moreover, since the casing 4 that has been released after being released from the connection may be moved in parallel with the drain material D inserted into the casing 4 continuously using the chain block 7, The work can be performed quickly, and the complexity of the work is reduced.

引抜いて打ち込み位置にあるケーシング4を移動させて並列させる際には、移動させるケーシング4を円滑に移動できるように必要な箇所のローラ5a〜5g、導入ローラ6bに対してドレーン材Dの架け替え作業を行なう。   When the casing 4 at the driving position is pulled out and moved in parallel, the drain material D is replaced with the rollers 5a to 5g and the introduction roller 6b at necessary portions so that the casing 4 to be moved can be moved smoothly. Do the work.

次いで、図12に例示するように、第1ケーシング4aの下端部から突出しているドレーン材Dを切断する。地盤に打ち込まれたドレーン材Dは、先端に取付けたアンカー10によって、地盤中に固定された状態になるので、上記の引抜き工程によってケーシング4のみを地盤上に引抜くことにより、地盤の所定深さまで打設されることになる。このようにドレーン材Dを切断することにより、その位置でのドレーン材Dの打設作業が完了するので、ドレーン材Dを所定の深さまで効率よく打設することができる。   Next, as illustrated in FIG. 12, the drain material D protruding from the lower end of the first casing 4a is cut. Since the drain material D driven into the ground is fixed in the ground by the anchor 10 attached to the tip, by pulling only the casing 4 on the ground by the above-described drawing process, a predetermined depth of the ground is obtained. It will be set up. By cutting the drain material D in this manner, the operation of placing the drain material D at that position is completed, so that the drain material D can be efficiently driven to a predetermined depth.

次の位置にドレーン材Dを打設するには、ステーション2の打ち込み位置を次の打設位置にあわせるように車体を移動させる。そして、第1ケーシング4aの下端部から突出しているドレーン材Dの先端にアンカー10を取付けて、図2〜図12に例示した工程を行なえばよい。   In order to drive the drain material D to the next position, the vehicle body is moved so that the driving position of the station 2 matches the next driving position. And the anchor 10 may be attached to the front-end | tip of the drain material D which protrudes from the lower end part of the 1st casing 4a, and the process illustrated in FIGS.

このように、本発明によれば、ドレーン材Dをある位置に打設した後は、ステーション2内に複数本のケーシング4が並列され、供給ロール11から繰り出したドレーン材Dが、これら並列されたケーシング4に連続するよう内挿した状態で保持されているので、ドレーン材Dの先端にアンカー10を取付けるだけで、すぐに次の位置でドレーン材Dの打設作業行なうことができる。   Thus, according to the present invention, after the drain material D is placed at a certain position, the plurality of casings 4 are arranged in parallel in the station 2, and the drain material D fed from the supply roll 11 is arranged in parallel. Since it is held in a state of being continuously inserted into the casing 4, simply by attaching the anchor 10 to the tip of the drain material D, it is possible to immediately perform the operation of placing the drain material D at the next position.

従来の長尺のケーシングでは、損傷等した場合はそのケーシングがまったく使用できなくなり、別のケーシングを使用する必要があったが、本発明によれば、損傷等したケーシング4だけを別のケーシング4に取り替えるだけでよいので、メンテナンス性に優れている。また、ケーシング4を短尺化できるので、ケーシング4の運搬が容易になり、ケーシング4を保管するスペースを小さくできるというメリットもある。さらには、継ぎ足すケーシング4の本数を変えるだけで、ドレーン材Dを要求される深さまで打設できるので、打設深さの異なる様々な打設現場に対応することが容易になる。   In the case of a conventional long casing, if the casing is damaged, the casing cannot be used at all, and another casing needs to be used. However, according to the present invention, only the damaged casing 4 is replaced with another casing 4. Because it is only necessary to replace it with, it is easy to maintain. Moreover, since the casing 4 can be shortened, there is an advantage that the casing 4 can be easily transported and the space for storing the casing 4 can be reduced. Furthermore, since the drain material D can be driven to the required depth only by changing the number of casings 4 to be added, it becomes easy to cope with various driving sites with different driving depths.

次いで、別の実施形態を説明する。この実施形態は、上記した実施形態の導入ローラ6bおよびローラ5a〜5gに替えて、第1ケーシング4aの上端部近傍にはローラ5が設け、第2ケーシング4b、第3ケーシング4c、第4ケーシング4dおよび第5ケーシング4eの上端部近傍と下端部近傍にローラ5を設けたものであり、これらローラ5は、ボルト等によって着脱可能になっている。その他の構成は上記した実施形態と同様である。   Next, another embodiment will be described. In this embodiment, instead of the introduction roller 6b and the rollers 5a to 5g of the above-described embodiment, the roller 5 is provided in the vicinity of the upper end portion of the first casing 4a, and the second casing 4b, the third casing 4c, and the fourth casing are provided. The rollers 5 are provided in the vicinity of the upper end and the lower end of the 4d and the fifth casing 4e, and these rollers 5 are detachable by bolts or the like. Other configurations are the same as those of the above-described embodiment.

供給ロール11から繰り出したドレーン材Dは、ステーション2に固設された導入ガイドローラ6を介してステーション2に導入され、それぞれのローラ5に架け回されてステーション2に保持された複数本のケーシング4に連続するように内挿されている。ドレーン材Dは、それぞれのケーシング4に設けられたローラ5に架け回されてケーシング4に内挿されているので、ドレーン材Dとケーシング4とは相対的な移動が円滑に行なえるようになっている。   The drain material D fed out from the supply roll 11 is introduced into the station 2 through the introduction guide roller 6 fixed to the station 2, and is wound around each roller 5 to be held in the station 2. 4 is inserted continuously. Since the drain material D is looped around the rollers 5 provided in the respective casings 4 and inserted into the casings 4, the drain material D and the casing 4 can smoothly move relative to each other. ing.

図13〜図20に基づいて、この実施形態の打設装置1を用いたドレーン材Dの打設方法を説明する。尚、図13〜図20では、打設装置1の構造を分かり易くするために、上側作業足場3a、下側作業足場3bなど、一部の構成を省略して示している。   Based on FIGS. 13-20, the placement method of the drain material D using the placement apparatus 1 of this embodiment is demonstrated. In FIG. 13 to FIG. 20, in order to make the structure of the placing device 1 easier to understand, some configurations such as the upper work scaffold 3 a and the lower work scaffold 3 b are omitted.

まず、図13〜図17に基づいて、ドレーン材Dを所定の深さまで打ち込む工程について説明する。チェーンブロック7を用いて、第1ケーシング4aをステーション2の打ち込み位置に移動させ、図13に例示するように、打ち込み引抜き手段8の保持チャック9に保持させる。ドレーン材Dの先端のアンカー10は、第1ケーシング4aの下端部にセットされている。そして、打ち込み引抜き手段8を作動させて第1ケーシング4aとともに、第1ケーシング4aに内挿されているドレーン材Dを地盤に打ち込む。   First, a process of driving the drain material D to a predetermined depth will be described with reference to FIGS. Using the chain block 7, the first casing 4 a is moved to the driving position of the station 2 and held by the holding chuck 9 of the driving and extracting means 8 as illustrated in FIG. 13. The anchor 10 at the tip of the drain material D is set at the lower end of the first casing 4a. Then, the driving / pulling means 8 is operated to drive the drain material D inserted in the first casing 4a into the ground together with the first casing 4a.

第1ケーシング4aをある程度の深さまで打込んだ後は、図14に例示するように、第2ケーシング4bをチェーンブロック7に吊設して、打ち込み位置まで移動させる。ドレーン材Dがローラ5に架け回されているので、円滑に第2ケーシング4bを移動させることができる。   After the first casing 4a is driven to a certain depth, the second casing 4b is suspended from the chain block 7 and moved to the driving position as illustrated in FIG. Since the drain material D is wound around the roller 5, the second casing 4b can be moved smoothly.

ここで、第1ケーシング4aの上端部近傍のローラ5と第2ケーシング4bの下端部近傍のローラ5を取外す。そして、第2ケーシング4bの下端部を、地盤に打ち込んでいる第1ケーシング4aの上端部に連結する。第2ケーシング4bは、第1ケーシング4aに連結した後でチェーンブロック7から取外す。   Here, the roller 5 near the upper end of the first casing 4a and the roller 5 near the lower end of the second casing 4b are removed. And the lower end part of the 2nd casing 4b is connected with the upper end part of the 1st casing 4a driven into the ground. The second casing 4b is detached from the chain block 7 after being connected to the first casing 4a.

ケーシング4をチェーンブロック7に吊設する作業および吊設しているケーシング4をチェーンブロック7から取外す作業は、図1に例示した上側作業足場3aに作業者が載って行なうことができる。また、ケーシング4に対するローラ5の取外し作業、後述するケーシング4に対するローラ5の取付け作業は、図1に例示した下側作業足場3bに作業者が載って行なうことができる。   The operation of suspending the casing 4 on the chain block 7 and the operation of removing the suspended casing 4 from the chain block 7 can be performed by an operator on the upper work scaffold 3a illustrated in FIG. Moreover, the removal work of the roller 5 with respect to the casing 4 and the attachment work of the roller 5 with respect to the casing 4 which will be described later can be performed by an operator on the lower work scaffold 3b illustrated in FIG.

次いで、図15に例示するように、第2ケーシング4bを打ち込み引抜き手段8の保持チャック9に保持させて、第2ケーシング4bを地盤に打ち込む。ドレーン材Dは、第1ケーシング4aおよび第2ケーシング4bを連続するように内挿されているので、第2ケーシング4bとともに、第2ケーシング4bに内挿されているドレーン材Dが地盤に打ち込まれることになる。   Next, as illustrated in FIG. 15, the second casing 4 b is driven onto the ground by holding the second casing 4 b on the holding chuck 9 of the driving and extracting means 8. Since the drain material D is inserted so that the first casing 4a and the second casing 4b are continuous, the drain material D inserted in the second casing 4b is driven into the ground together with the second casing 4b. It will be.

第2ケーシング4bをある程度の深さまで打込んだ後は、第3ケーシング4c、第4ケーシング4dに対しても、既述した第2ケーシング4bと同様に、打ち込み作業を行なって、ドレーン材Dを地盤に打ち込む。このように、ケーシング4とともに内挿しているドレーン材Dを地盤に打ち込み、順次、次のケーシング4を打ち込み位置に移動させるとともに、この移動させたケーシング4を地盤に打ち込んでいる下方のケーシング4に連結し、この移動させたケーシング4とともに内挿しているドレーン材Dを地盤に打ち込む工程を、必要な本数のケーシング4に対して繰り返し行なう。   After driving the second casing 4b to a certain depth, the driving operation is performed on the third casing 4c and the fourth casing 4d in the same manner as the second casing 4b described above, so that the drain material D is obtained. Drive into the ground. Thus, the drain material D inserted together with the casing 4 is driven into the ground, and the next casing 4 is sequentially moved to the driving position, and the moved casing 4 is moved to the lower casing 4 driven into the ground. The step of connecting and driving the drain material D inserted together with the moved casing 4 into the ground is repeated for the required number of casings 4.

この実施形態では、図16に例示するように、チェーンブロック7を用いて第5ケーシング4eを打ち込み位置まで移動させ、第4ケーシング4dの上端部近傍のローラ5と第5ケーシング4cの下端部近傍のローラ5を取外し、第5ケーシング4eの下端部を、地盤に打ち込んでいる第4ケーシング4dの上端部に連結する。次いで、図17に例示するように、第5ケーシング4eとともに内挿しているドレーン材Dを地盤に打ち込むことにより、打ち込む工程が完了する。   In this embodiment, as illustrated in FIG. 16, the fifth casing 4e is moved to the driving position using the chain block 7, and the roller 5 in the vicinity of the upper end portion of the fourth casing 4d and the vicinity of the lower end portion of the fifth casing 4c. The lower roller 5 is removed, and the lower end of the fifth casing 4e is connected to the upper end of the fourth casing 4d driven into the ground. Next, as illustrated in FIG. 17, the driving step is completed by driving the drain material D inserted together with the fifth casing 4e into the ground.

この実施形態においても、先の実施形態と同様に、高さ方向にスペースの制約がある打設現場であっても、複数本のケーシング4を順次継ぎ足して打ち込むことにより、ドレーン材Dを所定の深さまで打ち込むことができ、また、迅速に作業を行なうことができ、作業の煩雑さが軽減される。   Also in this embodiment, as in the previous embodiment, even in a placement site where there is a space restriction in the height direction, a plurality of casings 4 are sequentially added and driven, whereby the drain material D is given a predetermined amount. It can be driven to the depth, and the work can be performed quickly, reducing the complexity of the work.

次に、図18〜図20に基づいて、地盤に打ち込んだケーシング4を地盤上に引抜くようにする引抜き工程について説明する。この引抜き工程は、上記したケーシング4を打ち込む工程の逆の手順となる。   Next, with reference to FIGS. 18 to 20, a drawing process for drawing the casing 4 driven into the ground onto the ground will be described. This drawing process is the reverse procedure of the process of driving the casing 4 described above.

ドレーン材Dを所定の深さまで打ち込んだ後は、図18に例示するように、打ち込んだケーシング4を打ち込み引抜き手段8の保持チャック9に保持させ、打ち込み引抜き手段8を作動させて地盤上に引抜く。この際に、連結しているケーシング4に、ドレーン材Dを連続するように内挿させた状態のままにしておき、まず、第5ケーシング4eの全長が地盤上に露出するまで引抜く。この状態で、第5ケーシング4eの下端部と第4ケーシング4dの上端部との連結を解除する。連結を解除した第5ケーシング4eの下端部と、第4ケーシング4dの上端部とには、それぞれローラ5を取付け、取付けたローラ5にはドレーン材Dを架け回す。   After the drain material D is driven to a predetermined depth, as shown in FIG. 18, the driven casing 4 is held by the holding chuck 9 of the driving and extracting means 8, and the driving and extracting means 8 is operated and pulled on the ground. Unplug. At this time, the drain material D is continuously inserted in the connected casing 4 and is first drawn out until the entire length of the fifth casing 4e is exposed on the ground. In this state, the connection between the lower end portion of the fifth casing 4e and the upper end portion of the fourth casing 4d is released. The roller 5 is attached to the lower end portion of the fifth casing 4e and the upper end portion of the fourth casing 4d, respectively, and the drain material D is wound around the attached roller 5.

次いで、図19に例示するように、第4ケーシング4dとの連結が解除されてフリーになった第5ケーシング4eを、チェーンブロック7に吊設してステーション2の後方位置に移動させる。ドレーン材Dがローラ5に架け回されているので、円滑に第5ケーシング4eを移動させることができる。吊設している第5ケーシング4eは、移動させた位置でチェーンブロック7から取外して、ステーション2内で保持する。   Next, as illustrated in FIG. 19, the fifth casing 4 e released from the connection with the fourth casing 4 d is hung on the chain block 7 and moved to the rear position of the station 2. Since the drain material D is wound around the roller 5, the fifth casing 4e can be smoothly moved. The suspended fifth casing 4 e is removed from the chain block 7 at the moved position and held in the station 2.

上記の引抜き工程を、第4ケーシング4d、第3ケーシング4c、第2ケーシング4b、第1ケーシング4aに対しても順次行なって、フリーになったケーシング4をチェーンブロック7を用いて、ステーション2内で並列するように移動させて保持する。この実施形態では、図20に例示するように、第1ケーシング4aを地盤上に引抜いて、ドレーン材Dをすべてのケーシング4に連続するように内挿させた状態のままにして、ステーション2内にすべてのケーシング4を並列させることにより、引抜き工程が完了する。   The above-described drawing step is sequentially performed on the fourth casing 4d, the third casing 4c, the second casing 4b, and the first casing 4a, and the free casing 4 is used in the station 2 by using the chain block 7. Move and hold in parallel. In this embodiment, as illustrated in FIG. 20, the first casing 4 a is pulled out on the ground, and the drain material D is inserted so as to be continuous with all the casings 4. By pulling all the casings 4 in parallel, the drawing process is completed.

このように、ケーシング4を1本ずつ順次地盤上に露出するように引抜いて、ドレーン材Dをケーシング4に連続するように内挿させた状態のまま、地盤上に露出させたケーシング4と、地盤に打ち込まれている下方のケーシング4との連結を解除し、フリーになった地盤上のケーシング4を、1本ずつ順次、ステーション2内に並列させるようにするので、高さ方向にスペースの制約がある打設現場であっても、すべてのケーシング4を引抜くことができる。   In this way, the casing 4 is pulled out so as to be sequentially exposed on the ground one by one, and the casing 4 exposed on the ground with the drain material D being inserted so as to be continuous with the casing 4, The connection with the lower casing 4 that has been driven into the ground is released, and the casings 4 on the ground that have become free are arranged in parallel in the station 2 one by one. All casings 4 can be pulled out even at a placement site with restrictions.

しかも、連結を解除してフリーになったケーシング4を、チェーンブロック7を用いてドレーン材Dをケーシング4に連続するように内挿した状態のまま、並列するように移動させればよいので、迅速に作業を行なうことができ、作業の煩雑さが軽減される。   Moreover, since the casing 4 that has been released after being released from the connection may be moved in parallel with the drain material D inserted into the casing 4 continuously using the chain block 7, The work can be performed quickly, and the complexity of the work is reduced.

次いで、図20に例示するように、第1ケーシング4aの下端部から突出しているドレーン材Dを切断する。このようにドレーン材Dを切断することにより、その位置でのドレーン材Dの打設作業が完了するので、ドレーン材Dを所定の深さまで効率よく打設することができる。   Next, as illustrated in FIG. 20, the drain material D protruding from the lower end of the first casing 4a is cut. By cutting the drain material D in this manner, the operation of placing the drain material D at that position is completed, so that the drain material D can be efficiently driven to a predetermined depth.

次の位置にドレーン材Dを打設するには、ステーション2の打ち込み位置を次の打設位置にあわせるように車体を移動させる。そして、第1ケーシング4aの下端部から突出しているドレーン材Dの先端にアンカー10を取付けて、図13〜図20に例示した工程を行なえばよい。   In order to drive the drain material D to the next position, the vehicle body is moved so that the driving position of the station 2 matches the next driving position. And what is necessary is just to perform the process illustrated in FIGS. 13-20 by attaching the anchor 10 to the front-end | tip of the drain material D which protrudes from the lower end part of the 1st casing 4a.

本発明のドレーン材の打設装置を例示する側面図である。It is a side view which illustrates the placement apparatus of the drain material of this invention. 図1のドレーン材の打設装置により、第1ケーシングとともにドレーン材を打ち込む工程を例示する説明図である。It is explanatory drawing which illustrates the process which drives a drain material with a 1st casing by the placement apparatus of the drain material of FIG. 必要なローラに対して架け回していたドレーン材を取外す工程を例示する説明図である。It is explanatory drawing which illustrates the process of removing the drain material currently hung around the required roller. 第1ケーシングの上端部と第2ケーシングの下端部とを連結する工程を例示する説明図である。It is explanatory drawing which illustrates the process of connecting the upper end part of a 1st casing, and the lower end part of a 2nd casing. 第2ケーシングとともにドレーン材を打ち込む工程を例示する説明図である。It is explanatory drawing which illustrates the process of driving in a drain material with a 2nd casing. 必要なローラに対して架け回していたドレーン材を取外す工程を例示する説明図である。It is explanatory drawing which illustrates the process of removing the drain material currently hung around the required roller. 第4ケーシングとともにドレーン材を打ち込む工程を例示する説明図である。It is explanatory drawing which illustrates the process of driving in a drain material with a 4th casing. 第5ケーシングとともにドレーン材を打ち込む工程を例示する説明図である。It is explanatory drawing which illustrates the process of driving in a drain material with a 5th casing. 第5ケーシングを地盤上に引抜く工程を例示する説明図である。It is explanatory drawing which illustrates the process of extracting a 5th casing on the ground. 第5ケーシングをステーション内で並列するように移動させる工程を例示する説明図である。It is explanatory drawing which illustrates the process of moving a 5th casing so that it may parallel in a station. 第1ケーシングを地盤上に引抜く工程を例示する説明図である。It is explanatory drawing which illustrates the process of extracting a 1st casing on the ground. 地盤に打ち込んだドレーン材を地盤表面近傍で切断する工程を例示する説明図である。It is explanatory drawing which illustrates the process of cut | disconnecting the drain material driven into the ground in the ground surface vicinity. 別の実施形態によって、第1ケーシングとともにドレーン材を打ち込む工程を例示する説明図である。It is explanatory drawing which illustrates the process of driving in drain material with a 1st casing by another embodiment. 第1ケーシングの上端部と第2ケーシングの下端部とを連結する工程を例示する説明図である。It is explanatory drawing which illustrates the process of connecting the upper end part of a 1st casing, and the lower end part of a 2nd casing. 第2ケーシングとともにドレーン材を打ち込む工程を例示する説明図である。It is explanatory drawing which illustrates the process of driving in a drain material with a 2nd casing. 第4ケーシングの上端部と第5ケーシングの下端部とを連結する工程を例示する説明図である。It is explanatory drawing which illustrates the process of connecting the upper end part of a 4th casing, and the lower end part of a 5th casing. 第5ケーシングとともにドレーン材を打ち込む工程を例示する説明図である。It is explanatory drawing which illustrates the process of driving in a drain material with a 5th casing. 第5ケーシングを地盤上に引抜いて、第4ケーシングとの連結を解除する工程を例示する説明図である。It is explanatory drawing which illustrates the process of pulling out the 5th casing on the ground and releasing the connection with the 4th casing. 第5ケーシングをステーション内で並列するように移動させる工程を例示する説明図である。It is explanatory drawing which illustrates the process of moving a 5th casing so that it may parallel in a station. 第1ケーシングを地盤上に引抜いた後、地盤に打ち込んだドレーン材を地盤表面近傍で切断する工程を例示する説明図である。It is explanatory drawing which illustrates the process of cut | disconnecting the drain material driven into the ground near the ground surface, after drawing a 1st casing on the ground.

符号の説明Explanation of symbols

1 打設装置
2 ステーション
3 枠体
3a 上側作業足場
3b 下側作業足場
4、4a、4b、4c、4d、4e ケーシング
5、5a、5b、5c、5d、5e、5f、5g ローラ
6a、6b 導入ローラ
7 チェーンブロック(移動手段)
8 打ち込み引抜き手段
9 保持チャック
10 アンカー
11 供給ロール
D ドレーン材
DESCRIPTION OF SYMBOLS 1 Placing device 2 Station 3 Frame 3a Upper work scaffold 3b Lower work scaffold 4, 4a, 4b, 4c, 4d, 4e Casing 5, 5a, 5b, 5c, 5d, 5e, 5f, 5g Roller 6a, 6b Introduction Roller 7 Chain block (moving means)
8 Punching and drawing means 9 Holding chuck 10 Anchor 11 Supply roll D Drain material

Claims (7)

長手方向に互いに連結可能な複数本のケーシングと、これらケーシングを順次継ぎ足して先端にアンカーを取付けたドレーン材を内挿した状態で、地盤に打ち込む打ち込み手段と、地盤に打込んだケーシングを地盤上に引抜く引抜き手段とを備えたドレーン材の打設装置において、前記複数本のケーシングを並列させるとともに供給源から繰り出した前記ドレーン材を、これら並列させたケーシングに連続するよう内挿した状態で保持するステーションと、ステーション内でケーシングを1本ずつ移動させる移動手段とを設け、ケーシングの打ち込み工程では、ステーション内で並列させたケーシングを、前記移動手段により順次打ち込み位置に移動させ、ケーシングの引抜き工程では、1本ずつ順次地盤上に露出されて、ドレーン材をケーシングに連続するように内挿させた状態のまま、地盤に打ち込まれている下方のケーシングとの連結を解除されるケーシングを、前記移動手段によりステーション内で並列するように移動させる構成にしたドレーン材の打設装置。   A plurality of casings that can be connected to each other in the longitudinal direction, and a means for driving into the ground in a state in which drains having the anchors attached to the tips by sequentially adding these casings are inserted, and the casing driven into the ground is placed on the ground. In the drain material placing device provided with a pulling means for pulling out, the plurality of casings are arranged in parallel and the drain material fed out from a supply source is inserted in a state continuous with these juxtaposed casings. A holding station and a moving means for moving the casing one by one in the station are provided. In the casing driving step, the casings arranged in parallel in the station are sequentially moved to the driving position by the moving means, and the casing is pulled out. In the process, the drain material is exposed on the ground one by one and the drain material is A drain which is configured to move the casing, which is released from the connection with the lower casing driven into the ground, in a state of being inserted continuously to the ring, so as to be parallel in the station by the moving means. Material placement device. 前記ステーション内で並列させたケーシングの下端部近傍および上端部近傍になるようにローラをステーションに設け、これらローラに前記ドレーン材を架け回して、並列させたケーシングに連続するように内挿する構成にした請求項1に記載のドレーン材の打設装置。   A structure in which rollers are provided in the station so as to be near the lower end and upper end of the casings arranged in parallel in the station, and the drain material is wound around these rollers and is inserted so as to be continuous with the arranged casings. The drain material placing device according to claim 1. 前記ステーション内で並列させたケーシングの下端部近傍および上端部近傍に着脱可能なローラを設け、これらローラに前記ドレーン材を架け回して、並列させたケーシングに連続するように内挿する構成にした請求項1に記載のドレーン材の打設装置。   Removable rollers are provided in the vicinity of the lower end and the upper end of the casings arranged in parallel in the station, and the drain material is wound around these rollers, and is inserted so as to be continuous with the arranged casings. The drain material placing device according to claim 1. 前記複数本のケーシングの長さが5m以上7m以下である請求項1〜3のいずれかに記載のドレーン材の打設装置。   The drain material placing device according to any one of claims 1 to 3, wherein a length of the plurality of casings is 5 m or more and 7 m or less. 長手方向に互いに連結可能な複数本のケーシングを順次継ぎ足して、これらケーシングとともに内挿したドレーン材を地盤の所定深さまで打込んだ後、ドレーン材の先端に取付けたアンカーによって、ドレーン材を地盤中に固定した状態にして、ケーシングを地盤上に引抜くドレーン材の打設方法において、前記複数本のケーシングを並列し、供給源から繰り出したドレーン材を、これら並列したケーシングに連続するように内挿しておき、打ち込み位置に配置したケーシングとともに内挿しているドレーン材を地盤に打ち込み、順次、次のケーシングを打ち込み位置に移動させるとともに、この移動させたケーシングと、地盤に打ち込まれている下方のケーシングとを連結し、この移動させたケーシングとともに内挿しているドレーン材を地盤に打ち込む工程を、必要な本数のケーシングに対して繰り返し行なうことによりドレーン材を地盤の所定深さまで打ち込み、その後、打込んだケーシングを、1本ずつ順次地盤上に露出するように引抜いて、ドレーン材をケーシングに連続するように内挿させた状態のまま、地盤上に露出したケーシングと、地盤に打ち込まれている下方のケーシングとの連結を解除して、連結を解除した地盤上のケーシングを並列させるようにしたドレーン材の打設方法。   A plurality of casings that can be connected to each other in the longitudinal direction are sequentially added, and after the drain material inserted together with these casings is driven to a predetermined depth of the ground, the drain material is placed in the ground by an anchor attached to the tip of the drain material. In the drain material placing method in which the casing is pulled out on the ground in a fixed state, the plurality of casings are arranged in parallel, and the drain material fed from the supply source is continuously connected to the parallel casing. Insert the drain material inserted together with the casing arranged in the driving position into the ground, and sequentially move the next casing to the driving position, and the moved casing and the lower part driven into the ground Connect the casing and drain material inserted with the moved casing. The process of driving into the board is repeatedly performed on the required number of casings to drive the drain material to a predetermined depth of the ground, and then the driven casings are pulled out one by one so as to be sequentially exposed on the ground, With the drain material inserted in the casing so as to be continuous with the casing, the casing exposed on the ground is released from the lower casing driven into the ground, and the casing on the ground is released. A method of placing drain material that is arranged in parallel. 前記並列したケーシングの下端部近傍および上端部近傍になるようにローラをステーションに取付け、これらローラに前記ドレーン材を架け回して、並列したケーシングに連続するように内挿させ、ケーシングを打込み位置に移動させる際および地盤上に引抜いたケーシングを並列させる際には、必要な箇所のローラに対してドレーン材の架け替えを行なうようにした請求項5に記載のドレーン材の打設方法。   Rollers are attached to the station so that they are in the vicinity of the lower end and the upper end of the parallel casings, and the drain material is laid around these rollers, and is inserted continuously to the parallel casings. 6. The method for placing a drain material according to claim 5, wherein the drain material is replaced with a roller at a necessary portion when the casing is pulled out on the ground when moving. 前記並列したケーシングの下端部近傍および上端部近傍にローラを取付け、これらローラに前記ドレーン材を架け回して、並列したケーシングに連続するように内挿させ、ケーシングを地盤に打ち込む際には、そのケーシングに取付けたローラを取外し、打込んだケーシングを地盤上に引抜いた際には、そのケーシングにローラを取付けるようにした請求項5に記載のドレーン材の打設方法。   When the rollers are attached to the vicinity of the lower end portion and the upper end portion of the parallel casings, the drain material is laid around these rollers, and inserted into the casings in parallel, and when the casings are driven into the ground, 6. The method for placing a drain material according to claim 5, wherein when the roller attached to the casing is removed and the driven casing is pulled out on the ground, the roller is attached to the casing.
JP2008222428A 2008-08-29 2008-08-29 Drain material placing device and method Active JP4494500B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008222428A JP4494500B2 (en) 2008-08-29 2008-08-29 Drain material placing device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008222428A JP4494500B2 (en) 2008-08-29 2008-08-29 Drain material placing device and method

Publications (2)

Publication Number Publication Date
JP2010053659A JP2010053659A (en) 2010-03-11
JP4494500B2 true JP4494500B2 (en) 2010-06-30

Family

ID=42069853

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008222428A Active JP4494500B2 (en) 2008-08-29 2008-08-29 Drain material placing device and method

Country Status (1)

Country Link
JP (1) JP4494500B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5225302B2 (en) * 2010-02-24 2013-07-03 ドレーン基礎工業株式会社 Draining device for drain material

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1076989A (en) * 1996-09-04 1998-03-24 I H I Amutetsuku:Kk Work barge for drain construction
JPH1161797A (en) * 1997-08-22 1999-03-05 I H I Amutetsuku:Kk Air valve of casing pipe in drain material driving device
JP2006307552A (en) * 2005-04-28 2006-11-09 Maeda Corp Device and method for placing and cutting drain material for ground improvement, and ground improvement method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1076989A (en) * 1996-09-04 1998-03-24 I H I Amutetsuku:Kk Work barge for drain construction
JPH1161797A (en) * 1997-08-22 1999-03-05 I H I Amutetsuku:Kk Air valve of casing pipe in drain material driving device
JP2006307552A (en) * 2005-04-28 2006-11-09 Maeda Corp Device and method for placing and cutting drain material for ground improvement, and ground improvement method

Also Published As

Publication number Publication date
JP2010053659A (en) 2010-03-11

Similar Documents

Publication Publication Date Title
CN104075028B (en) Piping lane poling method of construction
JP2009287312A (en) Bridge construction apparatus
JP4494500B2 (en) Drain material placing device and method
JP6309400B2 (en) Pile removal method
JP2012251353A (en) Curved start method of shield machine
JP2007037314A (en) Electric wire relaying method and protective net used for it
JP2014074291A (en) Cast-in-place pile construction apparatus and cast-in-place pile construction method
US9009976B2 (en) Method and apparatus for energy chain installation
JP6489728B1 (en) Column rebuilding method
JP2011162990A (en) Device for pulling out h-shaped steel for earth retaining
JP5512300B2 (en) Pig iron cutting device and pig iron cutting method in a blast furnace
JP2009174244A (en) Excavation method for tunnel
KR101068170B1 (en) A sheet pile pulling apparatus
JP2018003318A (en) Cutter of concrete member and dismantling method of concrete member
JP4812666B2 (en) Tunnel lining concrete placement method
JP4728819B2 (en) Pile extraction device and pile extraction method
JP6523867B2 (en) Pile press-in method, reaction frame and pile press-in and pull-out machine
JP2008231862A (en) Movable scaffold device in cutting edge, and earth retaining method for cutting face, using it
JP2010047995A (en) Leader changing method of pile driver
KR101249481B1 (en) Concrete diamond wire saw apparatus and method thereof
JP3692120B2 (en) Pile removal device
CN104718328A (en) Multi-stage telescopic arm device and deep-digging excavator comprising multi-stage telescopic arm device
JPS583094B2 (en) Sheet pile press-in equipment and sheet pile press-in method
KR101844286B1 (en) Heat exchanger bundle exchanging device and method
JP2017044004A (en) Press-in device and sub-chuck frame with sub-chuck

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100226

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20100226

A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20100318

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100330

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100407

R150 Certificate of patent or registration of utility model

Ref document number: 4494500

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130416

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130416

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130416

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130416

Year of fee payment: 3

R157 Certificate of patent or utility model (correction)

Free format text: JAPANESE INTERMEDIATE CODE: R157

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130416

Year of fee payment: 3

R157 Certificate of patent or utility model (correction)

Free format text: JAPANESE INTERMEDIATE CODE: R157

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130416

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140416

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250