JP4478615B2 - Steel pipe sheet pile wall construction method - Google Patents

Steel pipe sheet pile wall construction method Download PDF

Info

Publication number
JP4478615B2
JP4478615B2 JP2005172161A JP2005172161A JP4478615B2 JP 4478615 B2 JP4478615 B2 JP 4478615B2 JP 2005172161 A JP2005172161 A JP 2005172161A JP 2005172161 A JP2005172161 A JP 2005172161A JP 4478615 B2 JP4478615 B2 JP 4478615B2
Authority
JP
Japan
Prior art keywords
steel pipe
pipe sheet
sheet pile
excavation
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2005172161A
Other languages
Japanese (ja)
Other versions
JP2006348471A (en
Inventor
直仁 筒井
忠信 安西
直 岩本
正仁 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP2005172161A priority Critical patent/JP4478615B2/en
Publication of JP2006348471A publication Critical patent/JP2006348471A/en
Application granted granted Critical
Publication of JP4478615B2 publication Critical patent/JP4478615B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

本発明は、鋼管矢板を用いて土留壁や基礎を施工するための鋼管矢板壁構築工法に関する。   The present invention relates to a steel pipe sheet pile wall construction method for constructing a retaining wall and a foundation using a steel pipe sheet pile.

従来、鋼管矢板壁を構築する方法として、予め地盤内に孔を掘削し、この孔内に鋼管矢板を先行して建て込まれた鋼管矢板に連結部を介して連結しながら建て込んで、建て込んだ鋼管矢板の周囲に硬化材を注入するという作業を順次繰り返して行うものがある(例えば、特許文献1、2または3参照。)。
特許第2935632号公報 特許第2935633号公報 特許第2935634号公報
Conventionally, as a method of constructing a steel pipe sheet pile wall, a hole is excavated in advance in the ground, and the steel pipe sheet pile is built in the hole while being connected via a connecting portion. There is one that sequentially repeats the operation of injecting a hardening material around the steel pipe sheet pile inserted (see, for example, Patent Documents 1, 2, or 3).
Japanese Patent No. 2935632 Japanese Patent No. 2935633 Japanese Patent No. 2935634

しかし、従来の方法では、孔の掘削、鋼管矢板の建て込み、硬化材の注入という作業を鋼管矢板1本ずつに行っているため、鋼管矢板1本当たりの施工に要する時間が長くなっていた。また、鋼管矢板を連結しながら建て込むために、先行して建て込まれた鋼管矢板の周囲の硬化材を掘削して、その掘削部分に再度硬化材を注入しなければならず、発生する残土量、硬化材の使用量が多いという問題もあった。   However, in the conventional method, since the operations of drilling holes, installing steel pipe sheet piles, and injecting hardened material are performed on each steel pipe sheet pile, the time required for construction per steel pipe sheet pile has been increased. . In addition, in order to build steel pipe sheet piles while connecting them, the hardened material around the previously built steel pipe sheet piles must be excavated, and the hardened material must be reinjected into the excavated portion, resulting in the generated residual soil There was also a problem that the amount of the curing material used was large.

本発明の課題は、上記のような鋼管矢板壁構築工法において、鋼管矢板1本当たりの施工時間を短縮することである。また、掘削によって発生する残土量、鋼管矢板の周囲に注入する硬化材の使用量を削減することである。   The subject of this invention is shortening the construction time per steel pipe sheet pile in the above steel pipe sheet pile wall construction methods. Moreover, it is to reduce the amount of residual soil generated by excavation and the amount of hardened material used around the steel pipe sheet pile.

以上の課題を解決するため、請求項1に記載の発明は、鋼管矢板どうしを連結して連続壁を構築する鋼管矢板壁構築工法であって、例えば図1から6に示すように、先行して地盤内に埋設された鋼管矢板1aから構築方向に複数の鋼管矢板1b、1cをそれぞれ建て込むための複数の孔5b、5cを地盤内に掘削する掘削工程と、隣接する鋼管矢板1a、1b、1cの継手(雄継手2、雌継手3)どうしを嵌め込みながら前記複数の鋼管矢板1b、1cを前記複数の孔5b、5c内にそれぞれ建て込む建込工程と、前記複数の孔5b、5c内に建て込まれた前記複数の鋼管矢板1b、1cの周囲に充填材7を充填する充填工程と、を備えることを特徴とする。   In order to solve the above-mentioned problems, the invention described in claim 1 is a steel pipe sheet pile wall construction method for constructing a continuous wall by connecting steel pipe sheet piles, and for example, as shown in FIGS. An excavation process for excavating a plurality of holes 5b, 5c in the ground from the steel pipe sheet pile 1a embedded in the ground in the construction direction, and the adjacent steel pipe sheet piles 1a, 1b 1c, a plurality of steel pipe sheet piles 1b and 1c are built in the plurality of holes 5b and 5c, respectively, and the plurality of holes 5b and 5c are inserted into the joints (male joint 2 and female joint 3). And a filling step of filling a filler 7 around the plurality of steel pipe sheet piles 1b and 1c built therein.

地盤内に孔5を掘削する作業、掘削された孔5に鋼管矢板1を建て込む作業、孔5内に建て込まれた鋼管矢板1の周囲に充填材7を充填する作業を、従来のように鋼管矢板1本ずつ行うのではなく複数本ずつ行うことにより、鋼管矢板1の1本当たりの施工時間を短縮することができる。また、地盤内に複数の孔5b、5cを掘削する際に、掘削される複数の孔5b、5cの間では、地盤を重複して掘削したり、重複して充填材7を充填したりすることがないため、掘削によって発生する残土量、鋼管矢板1b、1cの周囲に充填する充填材7の使用量を削減することができる。   The work of excavating the hole 5 in the ground, the work of installing the steel pipe sheet pile 1 in the excavated hole 5, and the work of filling the filler 7 around the steel pipe sheet pile 1 built in the hole 5 are as conventional. In addition, it is possible to reduce the construction time per one steel pipe sheet pile 1 by performing a plurality of pipe sheet piles instead of one by one. Further, when excavating the plurality of holes 5b and 5c in the ground, the ground is dug between the plurality of excavated holes 5b and 5c, or the filler 7 is filled with duplication. Therefore, it is possible to reduce the amount of remaining soil generated by excavation and the amount of filler 7 that is filled around the steel pipe sheet piles 1b and 1c.

請求項2に記載の発明は、請求項1に記載の鋼管矢板壁構築工法において、例えば図1から6に示すように、前記掘削工程の後に、先行して地盤内に埋設された鋼管矢板1aの継手(雄継手2、雌継手3)をガイドとして、この継手の側部の地盤を掘削して、この鋼管矢板1aに隣接して掘削された孔5aを修正する修正掘削工程を備えることを特徴とする。   The invention according to claim 2 is the steel pipe sheet pile wall construction method according to claim 1, for example, as shown in FIGS. 1 to 6, the steel pipe sheet pile 1a embedded in the ground in advance after the excavation step. The above-mentioned joints (male joint 2 and female joint 3) are used as a guide to excavate the ground on the side of the joint and to provide a modified excavation process for correcting the hole 5a excavated adjacent to the steel pipe sheet pile 1a. Features.

このように、先行して地盤内に埋設された鋼管矢板1aの継手をガイドとして、この継手の側部の地盤を掘削して、この鋼管矢板1aに隣接して掘削された孔5aを修正することにより、この継手の破損を防止しつつ隣接する鋼管矢板1aの建て込みを容易にすることができる。そして、この修正掘削の作業は、地盤内に掘削される複数の孔5b、5cのうち、先行して地盤内に埋設された鋼管矢板1aに隣接して掘削された孔5bのみで済むため、鋼管矢板1の1本当たりの施工時間を短縮することができる。   In this way, using the joint of the steel pipe sheet pile 1a previously embedded in the ground as a guide, the ground on the side of the joint is excavated, and the hole 5a excavated adjacent to the steel pipe sheet pile 1a is corrected. Thus, it is possible to facilitate the erection of the adjacent steel pipe sheet pile 1a while preventing breakage of the joint. And since the work of this correction excavation is only the hole 5b excavated adjacent to the steel pipe sheet pile 1a previously embedded in the ground among the plurality of holes 5b, 5c excavated in the ground, The construction time per one steel pipe sheet pile 1 can be shortened.

請求項3に記載の発明は、請求項1または2に記載の鋼管矢板壁構築工法において、例えば図1から6に示すように、前記掘削工程において前記複数の孔5b、5cのうち、先行して地盤内に埋設された鋼管矢板1a側から数えて偶数番目の孔5cから掘削することを特徴とする。   The invention according to claim 3 is the steel pipe sheet pile wall construction method according to claim 1 or 2, wherein, for example, as shown in FIGS. 1 to 6, the excavation step is preceded by the plurality of holes 5b and 5c. Then, excavation is performed from the even-numbered holes 5c counted from the side of the steel pipe sheet pile 1a embedded in the ground.

このように、先行して地盤内に埋設された鋼管矢板1a側から偶数番目の孔5cから掘削することにより、偶数番目の孔5cを掘削する位置の両側には先行して地盤内に埋設された鋼管矢板1aの周囲の充填材7や掘削された孔がない。このため、それらに影響を受けることなく孔5cの掘削作業を行うことができるため、その施工精度を向上させることができる。   Thus, by excavating from the even-numbered holes 5c from the steel pipe sheet pile 1a side previously embedded in the ground, both sides of the position where the even-numbered holes 5c are excavated are previously embedded in the ground. There is no filler 7 or excavated hole around the steel pipe sheet pile 1a. For this reason, since the excavation work of the hole 5c can be performed without being affected by them, the construction accuracy can be improved.

請求項4に記載の発明は、請求項1から3のいずれか一項に記載の鋼管矢板壁構築工法において、例えば図1から6に示すように、前記建込工程において前記複数の鋼管矢板1b、1cのうち、先行して地盤内に埋設された鋼管矢板1a側から数えて偶数番目の鋼管矢板1cから建て込むことを特徴とする。   The invention according to claim 4 is the steel pipe sheet pile wall construction method according to any one of claims 1 to 3, for example, as shown in FIGS. 1 to 6, the plurality of steel pipe sheet piles 1b in the erection step. 1c, it is built from the even-numbered steel pipe sheet pile 1c counting from the steel pipe sheet pile 1a side previously embedded in the ground.

このように、先行して地盤内に埋設された鋼管矢板1a側から偶数番目の鋼管矢板1cから建て込むことにより、偶数番目の鋼管矢板1cを建て込む位置の両側には建て込まれた鋼管矢板がない。このため、その継手に影響を受けることなく鋼管矢板1cの建込作業を行うことができるため、その施工精度を向上させることができる。   Thus, the steel pipe sheet pile built in the both sides of the position which builds in the even-numbered steel pipe sheet pile 1c by building in from the even-numbered steel pipe sheet pile 1c from the steel pipe sheet pile 1a side previously embedded in the ground. There is no. For this reason, since the construction work of the steel pipe sheet pile 1c can be performed without being influenced by the joint, the construction accuracy can be improved.

本発明によれば、鋼管矢板どうしを連結して連続壁を構築する鋼管矢板壁構築工法において、地盤内への孔の掘削作業、この孔への鋼管矢板の建込作業、この鋼管矢板の周囲への充填材の充填作業を鋼管矢板複数本ずつ行うことにより、従来に比べ鋼管矢板1本当たりの施工に要する時間を短くすることができる。また、複数の孔の掘削を同じ掘削工程のなかで行うので、従来に比べ掘削によって発生する残土量、鋼管矢板の周囲に充填する充填材の使用量を少なくすることができる。   According to the present invention, in a steel pipe sheet pile wall construction method for connecting steel pipe sheet piles to construct a continuous wall, a hole excavation work into the ground, a steel pipe sheet pile installation work in this hole, and the circumference of this steel pipe sheet pile By performing a plurality of steel pipe sheet piles filling work, the time required for construction per steel pipe sheet pile can be shortened as compared with the prior art. In addition, since excavation of a plurality of holes is performed in the same excavation process, the amount of residual soil generated by excavation and the amount of filler used to fill the periphery of the steel pipe sheet pile can be reduced as compared with the prior art.

さらに、先行して地盤内に埋設された鋼管矢板の継手をガイドとして、この継手の側部の地盤を掘削して、この鋼管矢板に隣接して掘削された孔を修正する修正掘削を行うことが望ましい。この場合でも、修正掘削の作業は、地盤内に掘削される複数の孔のうち、先行して地盤内に埋設された鋼管矢板に隣接して掘削された孔のみで済むため、鋼管矢板1本当たりの施工に要する時間を短くすることができる。   Furthermore, using the joint of the steel pipe sheet pile previously embedded in the ground as a guide, excavating the ground on the side of this joint and performing a modified excavation to correct the hole drilled adjacent to this steel pipe sheet pile Is desirable. Even in this case, the correction excavation work is only a hole excavated adjacent to the steel pipe sheet pile previously embedded in the ground out of a plurality of holes excavated in the ground, so one steel pipe sheet pile The time required for the construction can be shortened.

また、掘削作業において先行して地盤内に埋設された鋼管矢板側から偶数番目の孔から掘削すれば、先行して地盤内に埋設された鋼管矢板の周囲の充填材や、既に掘削された孔に影響を受けることなく、孔の掘削の施工精度を高めることができる。   In addition, if excavating from the even-numbered holes from the side of the steel pipe sheet pile previously embedded in the ground in excavation work, the filler around the steel pipe sheet pile previously embedded in the ground or the holes already drilled It is possible to improve the construction accuracy of the hole excavation without being affected by the above.

また、鋼管矢板の建込作業において先行して地盤内に埋設された鋼管矢板側から偶数番目の鋼管矢板から建て込めば、既に建て込まれた鋼管矢板の継手に影響を受けることなく、鋼管矢板の建て込みの施工精度を高めることができる。   In addition, if the steel pipe sheet pile is installed from the even numbered steel pipe sheet pile from the side of the steel pipe sheet pile previously embedded in the ground in the construction work of the steel pipe sheet pile, the steel pipe sheet pile is not affected by the joint of the already built steel pipe sheet pile. The construction accuracy of erection can be improved.

以下、図を参照して本発明を実施するための最良の形態を詳細に説明する。
図1に示すように、本実施の形態においては、本発明の鋼管矢板壁構築工法を、地盤内に鋼管矢板1どうしを連結し埋設して土留壁(連続壁)の構築に適用している。
Hereinafter, the best mode for carrying out the present invention will be described in detail with reference to the drawings.
As shown in FIG. 1, in the present embodiment, the steel pipe sheet pile wall construction method of the present invention is applied to the construction of a retaining wall (continuous wall) by connecting and embedding steel pipe sheet piles 1 in the ground. .

まず、本実施の形態に用いる鋼管矢板1について説明する。
図1に示すように、鋼管矢板1は、鋼管本体に雄継手2および雌継手3を設けたものである。これら雄継手2、雌継手3は、それぞれ鋼管本体の長手軸線に沿った長尺部材である。そして、鋼管矢板1(例えば、鋼管矢板1c)の雄継手2をこれに隣接する鋼管矢板1(鋼管矢板1b)の雌継手3に係止することにより、隣接する鋼管矢板1(鋼管矢板1cと鋼管矢板1b)どうしを相互に連結できるようになっている。
First, the steel pipe sheet pile 1 used for this Embodiment is demonstrated.
As shown in FIG. 1, a steel pipe sheet pile 1 is a steel pipe main body provided with a male joint 2 and a female joint 3. The male joint 2 and the female joint 3 are long members along the longitudinal axis of the steel pipe body. Then, by engaging the male joint 2 of the steel pipe sheet pile 1 (for example, the steel pipe sheet pile 1c) with the female joint 3 of the steel pipe sheet pile 1 (steel pipe sheet pile 1b) adjacent thereto, the adjacent steel pipe sheet pile 1 (steel pipe sheet pile 1c and Steel pipe sheet piles 1b) can be connected to each other.

雄継手2は一対のアングルをその先端を外方に向けて並設したもので、雌継手3は一対のアングルをその先端を向かい合わせにして並設したものである。なお、継手の構成、形状等は、これに限定されるものではなく任意に設定することができる。例えば、雄継手2をT型鋼によって構成してもよい。また、継手は互いに係合できれば良く、必ずしも雄雌一対のものである必要はなく、円管状で同形状の継手のものであってもよい。   The male joint 2 has a pair of angles arranged in parallel with the tips facing outward, and the female joint 3 has a pair of angles arranged with the tips facing each other. In addition, the structure of a joint, a shape, etc. are not limited to this, It can set arbitrarily. For example, the male joint 2 may be made of T-shaped steel. The joints only need to be able to engage with each other, and are not necessarily a pair of males and females.

ここで、建て込まれる鋼管矢板1のうち、先行鋼管矢板側から離れた位置の鋼管矢板1cにおいては、その雌継手3を取り囲むようにして継手防護材4が取り付けられる。同様に、図6(a)に示すように、先行鋼管矢板1aの雌継手3にも、埋設された状態で継手防護材4が取り付けられている。   Here, in the steel pipe sheet pile 1 to be built, in the steel pipe sheet pile 1c at a position away from the preceding steel pipe sheet pile side, the joint protective material 4 is attached so as to surround the female joint 3. Similarly, as shown to Fig.6 (a), the joint protective material 4 is attached to the female joint 3 of the preceding steel pipe sheet pile 1a in the embedded state.

継手防護材4は、その雌継手3のスリットを閉塞し、鋼管矢板1周辺に充填する充填材7が雌継手3内に入り込まないようにするものである。例えば、ゴムシート4aが雌継手3を取り囲むようにして設置され、ゴムシート4aの内側に長手方向の中空空間が形成され、スラグサンド4bが詰められたものである。   The joint protective material 4 closes the slit of the female joint 3 so that the filler 7 filling the periphery of the steel pipe sheet pile 1 does not enter the female joint 3. For example, the rubber sheet 4a is installed so as to surround the female joint 3, a longitudinal hollow space is formed inside the rubber sheet 4a, and slag sand 4b is packed therein.

次に、本実施の形態における鋼管矢板壁構築工法の手順を説明する。
図1から6に示すように、本実施の形態における鋼管矢板壁構築工法は、後述する掘削工程、修正掘削工程、建込工程および充填工程を備えて概略構成されている。そして、これらの工程を1サイクルとして順次繰り返して土留壁を構築するものである。
Next, the procedure of the steel pipe sheet pile wall construction method in the present embodiment will be described.
As shown in FIGS. 1-6, the steel pipe sheet pile wall construction method in this Embodiment is roughly comprised including the excavation process mentioned later, a correction excavation process, the erection process, and the filling process. Then, these steps are sequentially repeated as one cycle to construct a retaining wall.

まず、掘削工程において、図1に示すように、先行して地盤内に埋設された鋼管矢板1a(以下、先行鋼管矢板1aとする。)の側方で土留壁の構築方向に、2本の鋼管矢板1b、1cをそれぞれ建て込むための2つの孔5b、5cを地盤内に掘削する。これらの孔5b、5cは、鋼管矢板1の雌継手3及び雄継手2を包含する所定の径を有するものである。   First, in the excavation process, as shown in FIG. 1, two steel pipe sheet piles 1a (hereinafter referred to as a preceding steel pipe sheet pile 1a) embedded in the ground in advance are arranged in the direction of construction of the retaining wall. Two holes 5b and 5c for embedding the steel pipe sheet piles 1b and 1c, respectively, are excavated in the ground. These holes 5 b and 5 c have a predetermined diameter including the female joint 3 and the male joint 2 of the steel pipe sheet pile 1.

ここで、図2、3に示すように、2つの孔5b、5cのうち、まず先行鋼管矢板1a側から数えて2番目の孔5cから掘削し、次に先行鋼管矢板1a側から数えて1番目、すなわち先行鋼管矢板1aにおいて掘削された孔5aに隣接する孔5bを掘削する。   Here, as shown in FIGS. 2 and 3, the two holes 5b and 5c are first excavated from the second hole 5c counted from the preceding steel pipe sheet pile 1a side, and then counted from the preceding steel pipe sheet pile 1a side. That is, the hole 5b adjacent to the hole 5a excavated in the preceding steel pipe sheet pile 1a is excavated.

また、図6(a)に示すように、前記1番目の孔5bを掘削する際には、先行鋼管矢板1aの雌継手3を誤って破損しないように、雌継手3から若干離れた位置で、先行鋼管矢板1aにおける孔5aと前記2番目の孔5cとにオーバーラップさせて掘削する。このとき、孔5bの掘削ラインが充填材7に及んでいることからわかるように、地盤を掘削すると同時に先行鋼管矢板1aの周囲に充填された充填材7の一部も掘削する。   Further, as shown in FIG. 6 (a), when excavating the first hole 5b, at a position slightly away from the female joint 3 so as not to accidentally break the female joint 3 of the preceding steel pipe sheet pile 1a. Then, excavation is performed by overlapping the hole 5a in the preceding steel pipe sheet pile 1a and the second hole 5c. At this time, as can be seen from the fact that the excavation line of the hole 5b extends to the filler 7, at the same time as excavating the ground, a part of the filler 7 filled around the preceding steel pipe sheet pile 1a is also excavated.

孔5の掘削は、例えば、図2(a)、図3(a)に示すように、オールケーシング工法を用いて行っている。具体的には、全旋回式ケーシング施工機8を掘削位置に設置し、ケーシングチューブ9圧入しながら回転し、これにより孔壁の崩壊を防止しながら、内部をハンマーグラブ11などの掘削機で排土しつつ、ケーシングチューブ9を順次継ぎ足して所定の深さまで埋設する。   Excavation of the hole 5 is performed using an all casing method, for example, as shown in FIGS. 2 (a) and 3 (a). Specifically, the all-swivel casing construction machine 8 is installed at the excavation position and rotated while the casing tube 9 is press-fitted, thereby preventing the collapse of the hole wall and exhausting the inside with an excavator such as a hammer grab 11. While soiling, the casing tubes 9 are successively added and buried to a predetermined depth.

なお、掘削中のケーシングチューブ9の先端は、孔壁保護のために常に掘削深度より先行させる。また、掘削中の孔内水位は、ボイリングやヒービングを防止するため孔5内に注水して常に地下水位以下にならないように調整する。また、掘削には、アースドリル12を併用しても良い。   Note that the tip of the casing tube 9 during excavation always precedes the excavation depth in order to protect the hole wall. In addition, the water level in the hole during excavation is adjusted so that it does not always fall below the groundwater level by pouring water into the hole 5 in order to prevent boiling and heaving. Moreover, you may use together the earth drill 12 for excavation.

所定の深さまで掘削した後、図2(b)、図3(b)に示すように、非硬化型の安定液としてベントナイト安定液、ポリマー安定液等をケーシングチューブ9内に充填しながらケーシングチューブ9を引き抜き、孔5の掘削が終了する。   After excavating to a predetermined depth, as shown in FIGS. 2 (b) and 3 (b), the casing tube 9 is filled with a bentonite stabilizing solution, a polymer stabilizing solution, etc. as a non-curing type stabilizing solution. 9 is pulled out and the excavation of the hole 5 is completed.

次に、掘削工程の後に、修正掘削工程において、先行鋼管矢板1aの雌継手3をガイドとして、この雌継手3の側部の地盤を掘削して、この鋼管矢板1aの孔5aに隣接して掘削された孔5bを修正する。   Next, after the excavation process, in the modified excavation process, the ground on the side of the female joint 3 is excavated using the female joint 3 of the preceding steel pipe sheet pile 1a as a guide, and adjacent to the hole 5a of the steel pipe sheet pile 1a. The drilled hole 5b is corrected.

修正掘削の孔6の位置は、図6(b)に示すように、先行鋼管矢板1aにおける孔5aに隣接して掘削された孔5bの掘削ラインよりも継手側に若干寄せてある。さらに、その掘削径は、余分な掘削を避けるために若干小さくしてある(同図の点線で修正掘削の掘削ラインを示す。)。これにより、前記1番目の孔5bは、真円ではなくやや横に膨らんだ形状となっている。   As shown in FIG. 6B, the position of the hole 6 for correction excavation is slightly closer to the joint side than the excavation line of the hole 5b excavated adjacent to the hole 5a in the preceding steel pipe sheet pile 1a. Further, the diameter of the excavation is slightly reduced in order to avoid excessive excavation (the excavation line for the correction excavation is indicated by a dotted line in the figure). As a result, the first hole 5b is not a perfect circle but has a shape bulging slightly.

また、修正掘削の孔6の掘削ラインが、鋼管矢板1aの継手防護材4に及んでいることからわかるように、本修正掘削工程では、地盤を掘削すると同時に継手防護材4の一部も掘削する。   In addition, as can be seen from the fact that the drilling line of the hole 6 for the modified excavation extends to the joint protective material 4 of the steel pipe sheet pile 1a, in this modified excavation process, a part of the joint protective material 4 is excavated simultaneously with excavating the ground. To do.

修正掘削は、例えば、図3(c)に示すように、鋼管矢板1aの雌継手3の内部あるいは外部と摺動して昇降自在なガイド機構を有するアースドリル13を用いて行っている。具体的には、ケリーバー13aの先端にロータリーサポート13bを装着して地盤を切削し、その後ロータリーサポート13bに替えてドリリングバケット(図示せず)を装着して切削した土砂を排出して行っている。   For example, as shown in FIG. 3C, the correction excavation is performed using an earth drill 13 having a guide mechanism that can slide up and down by sliding inside or outside the female joint 3 of the steel pipe sheet pile 1a. Specifically, a rotary support 13b is attached to the tip of the kelly bar 13a to cut the ground, and then a drilling bucket (not shown) is attached instead of the rotary support 13b to discharge the cut earth and sand. .

なお、掘削にあたっては、掘削工程において孔5内にベントナイト安定液、ポリマー安定液等が充填されているため、孔5壁の崩壊が防止されている。また、同時に雌継手3の内部の清掃も行う。   In excavation, since the hole 5 is filled with a bentonite stabilizing solution, a polymer stabilizing solution, or the like in the excavation process, the wall of the hole 5 is prevented from collapsing. At the same time, the inside of the female joint 3 is also cleaned.

次に、修正掘削工程の後に、建込工程において、図1に示すように、隣接する鋼管矢板1a、1b、1cの継手どうしを嵌め込みながら2本の鋼管矢板1b、1cを2つの孔5b、5c内にそれぞれ建て込む。   Next, after the correction excavation process, in the erection process, as shown in FIG. Each is built in 5c.

図6(c)、(d)に示すように、2本の鋼管矢板1b、1cのうち、まず先行鋼管矢板1a側から数えて2番目の鋼管矢板1cを建て込み、次に先行鋼管矢板1a側から数えて1番目、すなわち先行鋼管矢板1aに隣接する鋼管矢板1bを建て込む。すなわち、前記2番目の鋼管矢板1cは、その雌継手3、雄継手2が所定の位置になるように建て込まれる。そして、前記1番目の鋼管矢板1bは、その雄継手2を先行鋼管矢板1aの雌継手3の位置に、その雌継手3を2番目の鋼管矢板1cの雄継手2の位置に合わせて建て込まれる。   As shown in FIGS. 6C and 6D, of the two steel pipe sheet piles 1b and 1c, first, the second steel pipe sheet pile 1c counting from the preceding steel pipe sheet pile 1a side is built, and then the preceding steel pipe sheet pile 1a. The steel pipe sheet pile 1b adjacent to the first, ie, the preceding steel pipe sheet pile 1a, is built in from the side. That is, the second steel pipe sheet pile 1c is built so that the female joint 3 and the male joint 2 are in a predetermined position. The first steel pipe sheet pile 1b is built with its male joint 2 in the position of the female joint 3 of the preceding steel pipe sheet pile 1a and its female joint 3 in the position of the male joint 2 of the second steel pipe sheet pile 1c. It is.

鋼管矢板1の建て込みは、例えば図4に示すように、鋼管矢板1をクレーンで孔5の上方に位置させて吊り下げ、鋼管矢板1を順次溶接して継ぎ足して徐々に下降させて所定の深さまで建て込むことで行っている。前記1番目の鋼管矢板1bを建て込む際には、先行鋼管矢板1aの雌継手3および2番目の鋼管矢板1cの雄継手2とをガイドとして下降させている。これにより、鋼管矢板1aと鋼管矢板1bおよび鋼管矢板1bと鋼管矢板1cが互いにその継手が嵌め合わされて連結される。   For example, as shown in FIG. 4, the steel pipe sheet pile 1 is hung by placing the steel pipe sheet pile 1 above the hole 5 with a crane, sequentially welding the steel pipe sheet pile 1, and gradually lowering it. It is done by building to the depth. When the first steel pipe sheet pile 1b is installed, the female joint 3 of the preceding steel pipe sheet pile 1a and the male joint 2 of the second steel pipe sheet pile 1c are lowered as a guide. Thereby, the steel pipe sheet pile 1a, the steel pipe sheet pile 1b, the steel pipe sheet pile 1b, and the steel pipe sheet pile 1c are connected to each other by fitting their joints.

なお、前記2番目の鋼管矢板1cの雌継手3には継手防護材4が取り付けられる。例えば、この継手防護材4は、鋼管矢板1cを建て込む前に予めゴムシート4aを取り付けておき、鋼管矢板1cを建て込んだ後にゴムシート4aと雌継手3の内部にスラグサンド4bを詰め込むことで形成される。   A joint protective material 4 is attached to the female joint 3 of the second steel pipe sheet pile 1c. For example, the joint protective material 4 is prepared by attaching a rubber sheet 4a in advance before the steel pipe sheet pile 1c is built, and stuffing the slag sand 4b into the rubber sheet 4a and the female joint 3 after the steel pipe sheet pile 1c is built. Formed with.

次に、建込工程の後に、充填工程において、図6(e)に示すように、2つの孔5b、5c内に建て込まれた2本の鋼管矢板1b、1cの周囲に充填材7を充填する。また、鋼管矢板1a、1b、1cにおいて嵌め合わされた継手3、4の間にも充填材7を充填する。   Next, after the erection process, in the filling process, as shown in FIG. 6 (e), the filler 7 is placed around the two steel pipe sheet piles 1b and 1c built in the two holes 5b and 5c. Fill. The filler 7 is also filled between the joints 3 and 4 fitted in the steel pipe sheet piles 1a, 1b and 1c.

また、充填に先立って、図5(a)に示すように、鋼管矢板1b、1c内にはバックホウ15により土砂14を所定の深さ埋め戻しておいて、鋼管矢板1b、1c内への充填材7のまわり込みを防止する。   Prior to filling, as shown in FIG. 5 (a), the steel pipe sheet piles 1b and 1c are filled with earth and sand 14 by a backhoe 15 to a predetermined depth, and filled into the steel pipe sheet piles 1b and 1c. Prevents the material 7 from getting around.

充填材7の充填は、例えば図5(b)に示すように、注入配管14を、鋼管矢板1b、1cの周囲、鋼管矢板1aと鋼管矢板1b及び鋼管矢板1bと鋼管矢板1cとにおいて連結された雄継手2と雌継手3の間にそれぞれ配置して、圧送ポンプで注入配管14を通じて注入打設することにより行う。充填材7の注入打設中はその打設高さを測定しながら、落差が大きくならないように管理する。   For example, as shown in FIG. 5B, the filling material 7 is filled by connecting the injection pipe 14 around the steel pipe sheet piles 1b and 1c, the steel pipe sheet pile 1a and the steel pipe sheet pile 1b, and the steel pipe sheet pile 1b and the steel pipe sheet pile 1c. It arrange | positions between the male joint 2 and the female joint 3, and it inject | pours through the injection | pipe piping 14 with a pressure pump, and it carries out. While the filling material 7 is being poured, the height of the casting is measured and managed so that the drop does not become large.

充填材7は、例えば流動化処理土を用いている。なお、充填材7としては、流動化処理土に限らず所定の強度と止水性をもつ材料、例えば、ベントナイトモルタル、通常のモルタルあるいはコンクリートでもよい。   As the filler 7, for example, fluidized soil is used. The filler 7 is not limited to fluidized soil, and may be a material having a predetermined strength and water-stopping property, such as bentonite mortar, normal mortar, or concrete.

そして、鋼管矢板1b、1cの周囲にその上端部まで充填材7を充填し、鋼管矢板1b、1c内にその上端部まで土砂14を埋戻すことにより、充填作業が終了する。   And the filling work is complete | finished by filling the filler 7 to the upper end part around the steel pipe sheet piles 1b and 1c, and backfilling the earth and sand 14 to the upper end part in the steel pipe sheet piles 1b and 1c.

以下、図1に示すように、地盤内に孔5d,5eを掘削し、鋼管矢板1d、1eを建て込み、充填材7を充填する作業を上述したと同様の工程で繰り返して、さらに必要なだけ順次繰り返すことにより、所望の長さの土留壁が構築される。   Hereinafter, as shown in FIG. 1, holes 5d and 5e are excavated in the ground, steel pipe sheet piles 1d and 1e are built, and the work of filling the filler 7 is repeated in the same process as described above, and further necessary. The retaining wall having a desired length is constructed by repeating the process only in order.

本実施の形態によれば、地盤内に孔5を掘削する作業、掘削された孔5に鋼管矢板1を建て込む作業、孔5内に建て込まれた鋼管矢板1の周囲に充填材7を充填する作業を、従来のように鋼管矢板1の1本ずつ行うのではなく2本ずつ行っているため、鋼管矢板1の1本当たりの施工時間を短縮することができる。また、地盤内に2つの孔5b、5cを掘削する際に、掘削される2つの孔5b、5cの間では、地盤を重複して掘削したり、重複して充填材7を充填したりすることがないため、掘削によって発生する残土量、鋼管矢板1b、1cの周囲に充填する充填材7の使用量を削減することができる。   According to the present embodiment, the work of excavating the hole 5 in the ground, the work of installing the steel pipe sheet pile 1 in the excavated hole 5, the filler 7 around the steel pipe sheet pile 1 built in the hole 5. Since the work of filling is not performed one by one for the steel pipe sheet pile 1 as in the prior art, but is performed two by two, the construction time per one steel pipe sheet pile 1 can be shortened. Moreover, when excavating the two holes 5b and 5c in the ground, the ground is dug between the two excavated holes 5b and 5c, or the filler 7 is filled with duplication. Therefore, it is possible to reduce the amount of remaining soil generated by excavation and the amount of filler 7 that is filled around the steel pipe sheet piles 1b and 1c.

また、修正掘削の作業も、地盤内に掘削される複数の孔5b、5cのうち、先行鋼管矢板における孔5aに隣接して掘削された孔5bのみで済むため、鋼管矢板1b、1cの1本当たりの施工時間を短縮することができる。   Further, since the correction excavation work is only the hole 5b excavated adjacent to the hole 5a in the preceding steel pipe sheet pile among the plurality of holes 5b and 5c excavated in the ground, one of the steel pipe sheet piles 1b and 1c is required. The construction time per book can be shortened.

さらに、先行鋼管矢板1a側から2番目の孔5cから掘削することにより、先行鋼管矢板1aの周囲の充填材7に影響を受けることなく孔5cの掘削作業を行うことができるため、その施工精度を向上させることができる。   Further, by excavating from the second hole 5c from the preceding steel pipe sheet pile 1a side, the excavation work of the hole 5c can be performed without being affected by the filler 7 around the preceding steel pipe sheet pile 1a. Can be improved.

また、先行鋼管矢板側から2番目の鋼管矢板1cから建て込むことにより、既に建て込まれた鋼管矢板1の継手に影響を受けることなく鋼管矢板1cの建込作業を行うことができるため、その施工精度を向上させることができる。また、先行鋼管矢板1aに隣接して建て込まれる1番目の鋼管矢板1bは、両サイドの継手で案内されるため、ぐらつかない安定して建て込むことができる。   Moreover, since the construction work of the steel pipe sheet pile 1c can be performed without being influenced by the joint of the steel pipe sheet pile 1 already built by building from the second steel pipe sheet pile 1c from the preceding steel pipe sheet pile side, Construction accuracy can be improved. Moreover, since the 1st steel pipe sheet pile 1b built adjacent to the preceding steel pipe sheet pile 1a is guided by the joint of both sides, it can be built stably without wobbling.

そして、前記1番目の鋼管矢板1bの雌継手3は、修正掘削するためのガイドとしての役割が必要ないため、遮水性能を要求される部分だけに鋼管矢板1bの長手軸線に沿って設けられていればよい。同様に、前記2番目の鋼管矢板1cの雄継手2も、前記1番目の鋼管矢板1bの雌継手3に対応する部分だけに設けられていればよい。   And since the female joint 3 of the said 1st steel pipe sheet pile 1b does not need the role as a guide for correction | amendment excavation, it is provided along the longitudinal axis of the steel pipe sheet pile 1b only in the part by which water-blocking performance is requested | required. It only has to be. Similarly, the male joint 2 of the 2nd steel pipe sheet pile 1c should just be provided only in the part corresponding to the female joint 3 of the said 1st steel pipe sheet pile 1b.

以上のとおり、土留壁全体としての施工精度を向上させるとともに、土留壁を能率的に構築して施工コストの削減を図ることができる。   As described above, it is possible to improve the construction accuracy of the entire retaining wall and efficiently construct the retaining wall to reduce the construction cost.

なお、以上の実施の形態においては、1つの掘削工程で掘削する孔5の数を2つとしたが、本発明はこれに限定されるものではなく、施工条件などに応じて、3つ以上としてもよい。同様に、1つの建込工程で建て込む鋼管矢板1の数を2本としたが、3本以上としてもよい。ここで、これらの施工数は、土質、孔5の掘削の径、深さなどの施工条件により設定され、掘削、修正掘削、建込、充填作業の各1工程が、それぞれ1日で終了することが可能な数が望ましい。また、孔の掘削順序、鋼管矢板の建込み順序を、先行鋼管矢板側から2番目、1番目の順としたが、逆に1番目、2番目の順としてもよい。なお、孔、鋼管矢板の数が3以上である場合には、先行鋼管矢板側から偶数番目、奇数番目の順で施工してもよいし、その逆に奇数番目、偶数番目の順に施工してもよいし、さらにこれらの他の順で施工できることは勿論である。その他、具体的な細部構造等についても適宜に変更可能であることは勿論である。   In the above embodiment, the number of holes 5 to be excavated in one excavation process is two, but the present invention is not limited to this, and according to construction conditions, etc., the number of holes 5 is three or more. Also good. Similarly, although the number of the steel pipe sheet piles 1 built in one erection process was two, it is good also as three or more. Here, the number of constructions is set according to the construction conditions such as the soil quality, the diameter and depth of excavation of the hole 5, and each process of excavation, correction excavation, erection and filling work is completed in one day. A number that is possible is desirable. Moreover, although the drilling order of the holes and the order of installing the steel pipe sheet piles are the second and first orders from the preceding steel pipe sheet pile side, the first and second orders may be reversed. In addition, when the number of holes and steel pipe sheet piles is 3 or more, construction may be performed in the order of even number and odd number from the preceding steel pipe sheet pile side, and vice versa. Of course, it can be constructed in these other orders. In addition, it is needless to say that specific detailed structures and the like can be appropriately changed.

本発明を適用した一実施の形態の鋼管矢板壁の施工状態を示す平面図である。It is a top view which shows the construction state of the steel pipe sheet pile wall of one Embodiment to which this invention is applied. 同施工手順を説明するための断面図であり、掘削工程の一部を示すものである。It is sectional drawing for demonstrating the construction procedure, and shows a part of excavation process. 同施工手順を説明するための断面図であり、掘削工程の一部及び修正掘削工程を示すものである。It is sectional drawing for demonstrating the construction procedure, and shows a part of excavation process and a correction excavation process. 同施工手順を説明するための断面図であり、鋼管矢板の建込工程を示すものである。It is sectional drawing for demonstrating the construction procedure, and shows the construction process of a steel pipe sheet pile. 同施工手順を説明するための断面図であり、充填工程を示すものである。It is sectional drawing for demonstrating the construction procedure, and shows a filling process. 鋼管矢板の建て込み手順を説明するための平面図である。It is a top view for demonstrating the construction procedure of a steel pipe sheet pile.

符号の説明Explanation of symbols

1、1a、1b、1c、1d、1e 鋼管矢板
2 雄継手
3 雌継手
4 継手防護材
5、5a、5b、5c、5d、5e 孔
6 孔(修正掘削)
7 充填材
1, 1a, 1b, 1c, 1d, 1e Steel pipe sheet pile 2 Male joint 3 Female joint 4 Joint protective material 5, 5a, 5b, 5c, 5d, 5e Hole 6 (Modified excavation)
7 Filler

Claims (4)

鋼管矢板どうしを連結して連続壁を構築する鋼管矢板壁構築工法であって、
先行して地盤内に埋設された鋼管矢板から構築方向に複数の鋼管矢板をそれぞれ建て込むための複数の孔を地盤内に掘削する掘削工程と、
隣接する鋼管矢板の継手どうしを嵌め込みながら前記複数の鋼管矢板を前記複数の孔内にそれぞれ建て込む建込工程と、
前記複数の孔内に建て込まれた前記複数の鋼管矢板の周囲に充填材を充填する充填工程と、を備えることを特徴とする鋼管矢板壁構築工法。
A steel pipe sheet pile wall construction method that connects steel pipe sheet piles to build a continuous wall,
A drilling process for excavating a plurality of holes in the ground to embed a plurality of steel pipe sheet piles in the construction direction from a steel pipe sheet pile previously embedded in the ground;
An erection process of building the plurality of steel pipe sheet piles in the plurality of holes while fitting the joints of adjacent steel pipe sheet piles,
A steel pipe sheet pile wall construction method, comprising: a filling step of filling a filler around the plurality of steel pipe sheet piles built in the plurality of holes.
前記掘削工程の後に、先行して地盤内に埋設された鋼管矢板の継手をガイドとして、この継手の側部の地盤を掘削して、この鋼管矢板に隣接して掘削された孔を修正する修正掘削工程を備えることを特徴とする請求項1に記載の鋼管矢板壁構築工法。   After the excavation step, the steel pipe sheet pile joint previously embedded in the ground is used as a guide, the ground on the side of the joint is excavated, and the hole excavated adjacent to the steel pipe sheet pile is corrected. The steel pipe sheet pile wall construction method according to claim 1, further comprising an excavation process. 前記掘削工程において前記複数の孔のうち、先行して地盤内に埋設された鋼管矢板側から数えて偶数番目の孔から掘削することを特徴とする請求項1または2に記載の鋼管矢板壁構築工法。   3. The steel pipe sheet pile wall construction according to claim 1, wherein, in the excavation step, excavation is performed from an even-numbered hole counted from the steel pipe sheet pile side embedded in the ground in advance. Construction method. 前記建込工程において前記複数の鋼管矢板のうち、先行して地盤内に埋設された鋼管矢板側から数えて偶数番目の鋼管矢板から建て込むことを特徴とする請求項1から3のいずれか一項に記載の鋼管矢板壁構築工法。   It builds from an even-numbered steel pipe sheet pile counted from the steel pipe sheet pile side previously embedded in the ground among the plurality of steel pipe sheet piles in the erection step. Steel pipe sheet pile wall construction method according to item.
JP2005172161A 2005-06-13 2005-06-13 Steel pipe sheet pile wall construction method Active JP4478615B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005172161A JP4478615B2 (en) 2005-06-13 2005-06-13 Steel pipe sheet pile wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005172161A JP4478615B2 (en) 2005-06-13 2005-06-13 Steel pipe sheet pile wall construction method

Publications (2)

Publication Number Publication Date
JP2006348471A JP2006348471A (en) 2006-12-28
JP4478615B2 true JP4478615B2 (en) 2010-06-09

Family

ID=37644600

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005172161A Active JP4478615B2 (en) 2005-06-13 2005-06-13 Steel pipe sheet pile wall construction method

Country Status (1)

Country Link
JP (1) JP4478615B2 (en)

Also Published As

Publication number Publication date
JP2006348471A (en) 2006-12-28

Similar Documents

Publication Publication Date Title
KR100847352B1 (en) Supporting tube assembly for tunnel supporting method with grouted steel pipe in the borehole and supporting method of using thereof
KR100939535B1 (en) Guide for execution of underground diaphragm wall
JP5274145B2 (en) Cast-in-place pile and its construction method
KR100927186B1 (en) Method of constructing cantilevered continuous wallsfor retaining earth and cutting off water
JP2015187373A (en) Method for reinforcing hole wall for construction of cast-in-place concrete pile
KR101676814B1 (en) CFT pile Construction Method and the Shoring Method using the same file
JP5677728B2 (en) Tunnel reinforcement method, tunnel reinforcement structure
KR100914158B1 (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR20090120092A (en) Precast concrete wall and construction method using the same
JP4712456B2 (en) Foundation reinforcement method
KR20080027481A (en) Ground boring method using multi-point rock boring
KR101045625B1 (en) Construction method of retaining wall using cast-in-place pile
KR20100124028A (en) Construction method of lower end expanded type cast-in-place piles
KR101078080B1 (en) Earth retaining wall and it's construction method using the precast pile and ground reinforcement
JP4373824B2 (en) Joining method of cast-in-place pile and steel pipe column
JP4478615B2 (en) Steel pipe sheet pile wall construction method
CN109706919A (en) Rock-entering secant pile construction method
JP6735138B2 (en) Construction method of retaining wall structure and retaining wall structure
JP6729902B1 (en) Construction method of soil cement continuous wall
JP2005220573A (en) Pile driving method
JP2008013999A (en) Construction method of cast-in-place concrete pile
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
CN113309119A (en) Construction method for constructing inclined pile by mud retaining wall
JP4993131B2 (en) Foundation reinforcement method for existing structures
KR100654973B1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080411

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100226

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100302

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100315

R150 Certificate of patent or registration of utility model

Ref document number: 4478615

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130319

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140319

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313532

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250