JP4412826B2 - Scaffolding jig for scaffolding - Google Patents

Scaffolding jig for scaffolding Download PDF

Info

Publication number
JP4412826B2
JP4412826B2 JP2000228081A JP2000228081A JP4412826B2 JP 4412826 B2 JP4412826 B2 JP 4412826B2 JP 2000228081 A JP2000228081 A JP 2000228081A JP 2000228081 A JP2000228081 A JP 2000228081A JP 4412826 B2 JP4412826 B2 JP 4412826B2
Authority
JP
Japan
Prior art keywords
shaped base
base plate
scaffold
plate
jig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2000228081A
Other languages
Japanese (ja)
Other versions
JP2002038710A (en
Inventor
俊介 中島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Kasei Homes Corp
Original Assignee
Asahi Kasei Homes Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Kasei Homes Corp filed Critical Asahi Kasei Homes Corp
Priority to JP2000228081A priority Critical patent/JP4412826B2/en
Publication of JP2002038710A publication Critical patent/JP2002038710A/en
Application granted granted Critical
Publication of JP4412826B2 publication Critical patent/JP4412826B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は建築現場等に仮設される足場の控を支持する控え受け治具に係り、特に建物基礎の一部を利用することによって建物基礎に簡単かつ強固に取付固定し得る足場用控え受け治具に関するものである。
【0002】
【従来の技術】
従来の建築現場、工事現場等に仮設される足場は一般的に図7(a)、(b)に示す如く、足場51の控52の下部を地盤53に固定するに当っては、図に示すような打込み杭54を使用し、この打込み杭54を地盤53に打込むと共に、この打込み杭54を控52の下部に結合させ、該打込み杭54をアンカーとして利用することによって、控52を地盤53に安定した状態で固定していた。また、この控52は建築物の外側に設けていた。
【0003】
【発明が解決しようとする課題】
然るに、前述の建築現場等に仮設される足場51に於ては、足場51の控52を地盤53に固定するために、打込み杭54を地盤53に打込まなければならないので、現場での作業が極めて煩雑であり、かつ基礎内部へ控を設置しようとする場合には、基礎内部の地盤面に敷設されている防湿シート(図示せず)を打込み杭54によって破損させてしまい、基礎内部の地盤面の防水性を阻害してしまう等の問題があった。
【0004】
また、前述の従来の足場51に於ては、控52の単管が1階の床部分を斜めに横切って配置されるために、建て方作業中には、その控52が配置された部分の床面は、足場51を完全に撤去するまでは床板の敷設工事が出来ない問題があった。
【0005】
従って、建て方作業中には、控52の配置された場所の床は開口部として放置せざるを得ず、そのためにこの場所は転落災害が発生する危険性が残る等の問題があった。
【0006】
本発明に係る足場用控え受け治具は、前述の従来の多くの問題点に鑑み開発された全く新しい技術であって、特に既に設置されている建物基礎の一部、特に開口部を利用することによって建物基礎に簡単にまた強固に取付固定することが出来、しかも必要に応じては控が起立されている床面にも床板の敷設工事を施すことが容易に出来る全く新しい発明を提供するものである。
【0007】
【課題を解決するための手段】
本発明に係る足場用控え受け治具は、前述の従来の問題点を根本的に改善した発明であって、その第1発明の要旨は、建築現場等に設置される足場の控を支持し得る治具に於て、建物基礎の凹状に形成された開口部に跨って載置されかつ該建物基礎に固定し得るコ字形ベースプレートと、該コ字形ベースプレートの背面に一体的に起立突設され床板目地部に位置する部分が扁平板によって形成された控接続具とで構成したことを特徴とした足場用控え受け治具である。
【0008】
第1発明に於ては、前述のように建物基礎の一部に跨って載置し得るコ字形ベースプレートを形成したので、このコ字形ベースプレートを建物基礎に跨って挟持させることによって、控え受け治具を建物基礎に簡単かつ確実に固定することが出来る。
【0009】
また、前記コ字形ベースプレートの背面には控接続具が一体的に起立突設されているので、前述のようにコ字形ベースプレートを建物基礎に取付固定することによって、該控接続具を建設現場の床面より自動的に起立突設せしめることが出来る。また、該控接続具を支柱、特に管状に形成した場合には、方向が自在となり、複数の控を受けることが出来る。
【0010】
また、コ字形ベースプレートの背面に起立突設した控接続具の床板目地部に位置する部分を扁平板によって形成したので、この控接続具の扁平板の周りには、そのままの状態で床板を敷設することが出来る。
【0011】
従って、本発明の足場用控え受け治具を利用した場合には、建て方作業中にも支柱が配置された場所の床を開口部として放置する必要がなく、そのためにこの場所で転落災害が発生することを防止出来る。
【0012】
本発明に係る足場用控え受け治具の第2発明の要旨は、前記コ字形ベースプレートの内側に配置された挟持板がボルトの回動によって移動して前記建物基礎の側面を挟持するように構成したことを特徴とした第1発明の足場用控え受け治具である。
【0013】
第2発明に於ては、コ字形ベースプレートの内側に配置された挟持板がボルトの回動によって移動するように構成されているので、ボルトを回動することによって建物基礎の側面を挟持板で締め付けて、建物基礎にコ字形ベースプレートを強固に取付固定することが出来る。
【0014】
前述のように、コ字形ベースプレートを建物基礎に固定するに当って、このコ字形ベースプレートの内側に設けた挟持板を建物基礎の側面に幅広く面接触させるようにした場合には、建物基礎の外側面を損傷することがなく、しかもコ字形ベースプレートを建物基礎に安定した状態で強固に固定することが出来る。
【0015】
前述のコ字形ベースプレートの内側に配置された挟持板を移動し得るボルトをコ字形ベースプレートの側壁にネジ孔を穿設するか或はナットを溶着し、これ等のネジ孔或はナットに挿通して取付けるように構成した場合には、該ボルトを回動することによってその先端部でコ字形ベースプレートの内側に設けられた挟持板を移動せしめ、挟持板で建物基礎を挟持してコ字形ベースプレートを簡単かつ確実に建物基礎に取付固定することが出来る。
【0016】
【発明の実施の形態】
図により本発明に係る足場用控え受け治具の一実施例を具体的に説明すると、図1は本発明に係る第1実施例の足場用控え受け治具の使用状態を示す斜視説明図、図2(a)、(b)は夫々図1の足場用控え受け治具の構成を示す縦断面図、図3は図1の足場用控え受け治具の要部の構成を示す斜視説明図、図4は図1の足場用控え受け治具を使用して足場を構築する状態の要部の斜視説明図である。
【0017】
図5(a)、(b)は夫々本発明に係る第2実施例の足場用控え受け治具の要部を示す説明図、図6(a)、(b)、(c)は夫々図5の足場用控え受け治具の側面図、底面図及び正面図である。
【0018】
図1乃至図4に於て本発明の第1実施例を説明する。1は本発明に係る足場用控え受け治具であって、断面が下向のコ字形ベースプレート2が基板となっている。このコ字形ベースプレート2は、特に図3によって明らかな如く、背板2aの両側下部に側板2b、2cを設けることによって形成されている。
【0019】
前記コ字形ベースプレート2の各側板2b、2cの内側には夫々挟持板3が所定の間隔を保って平行に配置され、これ等の挟持板3は夫々板厚が小さく簡単に変形し得る連結片4を介して各側板2b、2cの下縁に一体的に連結されている。
【0020】
前記コ字形ベースプレート2の背板2aのほぼ中央には控接続具5が一体的に起立突設されている。この控接続具5の下部は、図に示す如く、扁平板5aで形成されており、かつこの扁平板5aにはこれと直交する方向に高さの小さい補強ブラケット6が一体的に固着されている。建物基礎9の開口部10にコ字形ベースプレート2を跨がせた場合には、この補強ブラケット6の高さが開口部10の高さより低くなるので、建て方前にこの補強ブラケット6の上方に床板11を全面的に敷きつめることが出来る。
【0021】
前記コ字形ベースプレート2の側板2b、2cの中央部の貫通孔内には、特に図3に示す如く、ナット7が溶着されており、かつこのナット7にはボルト8が挿通し得る如く螺合されている。従って、ボルト8をナット7に螺合して、ボルト8の先端部をコ字形ベースプレート2の中心部に移動させた場合には、ボルト8の先端部で挟持板3を押してコ字形ベースプレート2の中心部に徐々に移動させることが出来るように構成されている。
【0022】
前述のような構成を有する本発明の足場用控え受け治具1の使用に当っては、先ず図1に示す如く、建物基礎9の開口部10上にコ字形ベースプレート2を跨がせ、この状態でコ字形ベースプレート2の両側の側板2b、2cに取付けられたナット7にボルト8を挿通し、ボルト8の先端部で両側の挟持板3を移動させながら、開口部10の建物基礎9の両側面を締付けることによって、足場用控え受け治具1を建物基礎9に安定した状態で取付ける。
【0023】
次に、図2(a)、(b)及び図4に示す如く、足場用控え受け治具1の控接続具5の周りの1階の床梁には床板11を順に敷設し、控接続具5の下部の扁平板5aは並列された床板11で形成される目地部12に配置することが出来る。
【0024】
この際扁平板5aに固着された補強ブラケット6は、特に図2(b)に示す如く、床板11の下方に配置される。
【0025】
前述のように1階の床に敷設された床板11の目地部12に起立された控接続具5には、特に図4に示す如く、連結治具13を介して複数の足場用パイプ14を連結固定することによって、建築現場に足場を簡単に構築することが出来る。
【0026】
前記コ字形ベースプレート2の側板2b、2cの内側に配置された2枚の挟持板3の相互の間隔は、両者間に挿入される建物基礎9の左右幅よりも少し大きければ良い。また、両側の挟持板3と側板2b、2cとの間隔は約2〜6mmあれば良い。
【0027】
前記実施例に於ては、コ字形ベースプレート2の両内側に夫々挟持板3を設けて構成したが、その内の片方は省略することも可能である。また、前記実施例に於ては、側板2b、2cに夫々ナット7を溶着したが、これ等のナット7の代りに側板2b、2cにボルト8が螺合し得るネジ孔を直接穿設して構成することも可能である。
【0028】
次に、図5(a)、(b)及び図6(a)、(b)、(c)に於て、本発明の第2実施例を説明する。この第2実施例に示す足場用控え受け治具15は、前記第1実施例の足場用控え受け治具1を改良し、その構造をより簡略化したものである。
【0029】
即ち、第2実施例の足場用控え受け治具15は、基本的には前記足場用控え受け治具1と同一構造により構成されている。従って、足場用控え受け治具15は、背板2a、側板2b、2cよりなるコ字形ベースプレート2と、このコ字形ベースプレート2の背板2aに起立突設された控接続具5とより構成されている。
【0030】
そして、前記足場用控え受け治具1に於ては、コ字形ベースプレート2内に配置した挟持板3を連結片4を介してコ字形ベースプレート2の側板2b、2cに一体的に連結したのに対し、第2実施例の足場用控え受け治具15に於ては、特に図6(b)に示す如く、比較的面積の小さい挟持板16をボルト8の先端に固定して構成し、ボルト8の回動によって該挟持板16を建物基礎9の側面に当接し得るように構成している。
【0031】
また、足場用控え受け治具15に於ては、コ字形ベースプレート2内に複数の補強リブ17a、17bが設けられており、これ等の補強リブ17a、17bによってコ字形ベースプレート2を補強している。
【0032】
【発明の効果】
本発明に於ては、コ字形ベースプレートを用いたので、このプレートを建物基礎に跨がせることによって安定せしめることが出来る。また、建物基礎の一部を挟持し得るコ字形ベースプレートの内側に挟持板を配置し、かつこの挟持板を移動し得る手段を該コ字形ベースプレートの外側に設けたので、この手段を用いて挟持板を移動させることによって建物基礎の一部を挟持し、コ字形ベースプレートを建物基礎に簡単かつ確実に固定することが出来る効果を有している。さらに、建物基礎の開口部にコ字形ベースプレートを跨がせることによって、足場用控え受け治具の高さを低くして、その後の床板の敷設を容易にすることが出来る。
【0033】
かつ、コ字形ベースプレートを建物基礎に固定するに当っては、前述のような挟持板を建物基礎の側面に幅広く面接触させるので、建物基礎の外側面を損傷することがなく、しかもコ字形ベースプレートを建物基礎に安定した状態で強固に固定することが出来る。また、前記コ字形ベースプレートの背面には控接続具が一体的に起立突設されているので、前述のようにコ字形ベースプレートを建物基礎に取付固定することによって、該控接続具を建設現場の床面より自動的に起立突設せしめることが出来る効果も有している。従って、従来の如く、打込み杭を地盤に打込む必要もなく、そのために地盤面に敷設されている防湿シートを破損させて防水性を阻害させることがない。
【0034】
前述の本発明の控え受け治具に於て、コ字形ベースプレートの側壁にネジ孔を穿設するか或はナットを溶着し、これ等のネジ孔或はナットにボルトを挿通して構成した場合には、該ボルトを回動することによって、その先端部でコ字形ベースプレートの内側に配置された挟持板を移動せしめ、挟持板で建物基礎を挟持してコ字形ベースプレートを簡単かつ確実に建物基礎に取付固定することが出来る。
【0035】
さらに、本発明の控え受け治具に於て、コ字形ベースプレートの背面に起立突設した控接続具の下部を扁平板によって構成した場合には、この控接続具の下部の周りにはそのままの状態で床板を敷設することが出来る。また、この控接続具の下部の扁平板は、床面に敷設された床板間の目地部に位置せしめることが出来る効果がある。従って、本発明の足場用控え受け治具を利用した場合には、建て方作業中にも控接続具が配置された場所の床を開口部として放置する必要がなく、そのためにこの場所で転落災害が発生することを防止出来る等の多大な効果を有している。
【0036】
本発明に係る足場用控え受け治具は、前述の構造と作用とを有するので、建物基礎さえ出来ていれば、この足場用控え受け治具を利用して建物本体の建て方より先に足場を建てることが可能であり、これによって建築現場の安全性をより確実にすることが出来る効果を有している。
【図面の簡単な説明】
【図1】 図1は本発明に係る第1実施例の足場用控え受け治具の使用状態を示す斜視説明図である。
【図2】 図2(a)、(b)は夫々図1の足場用控え受け治具の構成を示す縦断面図である。
【図3】 図3は図1の足場用控え受け治具の要部の構成を示す斜視説明図である。
【図4】 図4は図1の足場用控え受け治具を使用して足場を構築する状態の要部の斜視説明図である。
【図5】 図5(a)、(b)は夫々本発明に係る第2実施例の足場用控え受け治具の要部を示す説明図である。
【図6】 図6(a)、(b)、(c)は夫々図5の足場用控え受け治具の側面図、底面図及び正面図である。
【図7】 図7(a)、(b)は建築現場に構築される足場の従来例を示す斜視説明図である。
【符号の説明】
1 …足場用控え受け治具
2 …コ字形ベースプレート
2a …背板
2b …側板
2c …側板
3 …挟持板
4 …連結片
5 …控接続具
5a …扁平板
6 …補強ブラケット
7 …ナット
8 …ボルト
9 …建物基礎
10 …開口部
11 …床板
12 …目地部
13 …連結治具
14 …足場用パイプ
15 …足場用控え受け治具
16 …挟持板
17a…補強リブ
17b…補強リブ
51 …足場
52 …控
53 …地盤
54 …打込み杭
[0001]
BACKGROUND OF THE INVENTION
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a holding jig for supporting a lock of a scaffold temporarily installed at a construction site or the like, and in particular, a holding holder for a scaffold that can be easily and firmly attached and fixed to a building foundation by using a part of the building foundation. It relates to ingredients.
[0002]
[Prior art]
As shown in FIGS. 7 (a) and 7 (b), conventional temporary scaffolds for construction sites, construction sites, etc. are generally shown in the figure when fixing the lower part of the lock 52 of the scaffold 51 to the ground 53. By using a driven pile 54 as shown, this driven pile 54 is driven into the ground 53, and this driven pile 54 is coupled to the lower part of the hook 52, and the driven pile 54 is used as an anchor, whereby the hook 52 is It was fixed to the ground 53 in a stable state. The lock 52 was provided outside the building.
[0003]
[Problems to be solved by the invention]
However, in the scaffold 51 temporarily set up at the construction site or the like, in order to fix the lock 52 of the scaffold 51 to the ground 53, the driven pile 54 must be driven into the ground 53. Is extremely complicated, and when it is intended to install a lock inside the foundation, a moisture-proof sheet (not shown) laid on the ground surface inside the foundation will be damaged by the driving pile 54, and the inside of the foundation will be damaged. There were problems such as hindering the waterproofing of the ground surface.
[0004]
Moreover, in the above-mentioned conventional scaffold 51, since the single pipe of the handle 52 is disposed diagonally across the floor portion of the first floor, the portion where the handle 52 is disposed during the building work. There was a problem that the floor laying work could not be done until the scaffold 51 was completely removed.
[0005]
Therefore, during the building work, the floor where the tab 52 is placed must be left as an opening, and there is a problem that this place has a risk of falling accidents.
[0006]
The scaffold holding jig according to the present invention is a completely new technology developed in view of the above-described conventional problems, and particularly uses a part of a building foundation already installed, particularly an opening. The invention provides a completely new invention that can be easily and firmly attached and fixed to the building foundation, and that, if necessary, the floor plate can be easily laid on the floor on which the tab is raised. Is.
[0007]
[Means for Solving the Problems]
The scaffold receiving jig for a scaffold according to the present invention is an invention that has fundamentally improved the above-mentioned conventional problems, and the gist of the first invention is to support a handle of a scaffold installed at a construction site or the like. A jig-shaped base plate that is placed over an opening formed in a concave shape on a building foundation and can be fixed to the building foundation, and a rear-standing projection integrally formed on the back surface of the U-shaped base plate. A scaffolding receiving jig for a scaffold, characterized in that a portion located at a floor plate joint portion is constituted by a locking connection formed by a flat plate .
[0008]
In the first invention, since the U-shaped base plate that can be placed across a part of the building foundation is formed as described above, the U-shaped base plate is sandwiched across the building foundation, so Tools can be easily and securely fixed to the building foundation.
[0009]
In addition, since the latch connection is integrally raised on the back surface of the U-shaped base plate, the latch connection is fixed to the building foundation by attaching and fixing the U-shaped base plate to the building foundation as described above. It can be set up automatically from the floor. Further, when the tap connection tool is formed in a column, particularly in a tubular shape, the direction can be freely set and a plurality of taps can be received.
[0010]
In addition, since the portion located in the floor plate joint portion of the connection fitting standing upright on the back of the U-shaped base plate is formed by a flat plate, the floor plate is laid as it is around the flat plate of this connection fitting I can do it.
[0011]
Therefore, when the holding jig for scaffolding of the present invention is used, it is not necessary to leave the floor of the place where the column is arranged as an opening portion even during the construction work, and for this reason there is a fall disaster at this place. It can be prevented from occurring.
[0012]
The gist of the second invention of the scaffold receiving jig for a scaffold according to the present invention is such that a clamping plate arranged inside the U-shaped base plate moves by the rotation of a bolt to clamp the side surface of the building foundation. A scaffold receiving jig for a scaffold according to the first aspect of the present invention.
[0013]
In the second invention, the sandwiching plate disposed inside the U-shaped base plate is configured to move by the rotation of the bolt. Therefore, the side surface of the building foundation is moved by the sandwiching plate by rotating the bolt. By tightening, the U-shaped base plate can be firmly attached and fixed to the building foundation.
[0014]
As mentioned above, when fixing the U-shaped base plate to the building foundation, if the clamping plate provided inside the U-shaped base plate is in wide contact with the side of the building foundation, The side face is not damaged, and the U-shaped base plate can be firmly fixed to the building foundation in a stable state.
[0015]
Bolts that can move the clamping plate arranged inside the above-mentioned U-shaped base plate are threaded with holes on the side walls of the U-shaped base plate or welded with nuts, and inserted into these screw holes or nuts. If the bolt is turned, the clamping plate provided inside the U-shaped base plate is moved at the tip of the bolt, and the building foundation is clamped by the clamping plate to move the U-shaped base plate. It can be easily and securely attached to the building foundation.
[0016]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 is a perspective explanatory view showing a usage state of the scaffold receiving jig of the first embodiment according to the present invention. 2A and 2B are longitudinal sectional views showing the structure of the scaffolding receiving jig for scaffolding in FIG. 1, respectively. FIG. 3 is a perspective explanatory view showing the structure of the main part of the scaffolding receiving jig for scaffolding in FIG. 4 is a perspective explanatory view of a main part in a state in which the scaffold is constructed using the scaffold holding jig of FIG.
[0017]
FIGS. 5 (a) and 5 (b) are explanatory views showing the main part of the scaffolding receiving jig for the scaffold according to the second embodiment of the present invention, and FIGS. 6 (a), 6 (b) and 6 (c) are diagrams. FIG. 5 is a side view, a bottom view, and a front view of a scaffold receiving jig for 5 scaffolds.
[0018]
A first embodiment of the present invention will be described with reference to FIGS. Reference numeral 1 denotes a scaffold holding jig according to the present invention, and a U-shaped base plate 2 having a downward cross section serves as a substrate. The U-shaped base plate 2 is formed by providing side plates 2b and 2c at the lower portions on both sides of the back plate 2a, as clearly shown in FIG.
[0019]
Inside the respective side plates 2b, 2c of the U-shaped base plate 2, sandwiching plates 3 are arranged in parallel at a predetermined interval, and these sandwiching plates 3 have small thicknesses and can be easily deformed. 4 is integrally connected to the lower edge of each side plate 2b, 2c.
[0020]
At the center of the back plate 2 a of the U-shaped base plate 2, a latch connection 5 is erected in an upright manner. As shown in the figure, the lower part of the locking connector 5 is formed by a flat plate 5a, and a reinforcing bracket 6 having a small height in a direction perpendicular to the flat plate 5a is integrally fixed thereto. Yes. When the U-shaped base plate 2 is straddled over the opening 10 of the building foundation 9, the height of the reinforcing bracket 6 is lower than the height of the opening 10. The floor board 11 can be spread all over.
[0021]
A nut 7 is welded in the through hole at the center of the side plates 2b and 2c of the U-shaped base plate 2 as shown in FIG. 3, and the nut 8 is screwed so that a bolt 8 can be inserted therethrough. Has been. Therefore, when the bolt 8 is screwed into the nut 7 and the tip of the bolt 8 is moved to the center of the U-shaped base plate 2, the clamping plate 3 is pushed by the tip of the bolt 8 to It is configured so that it can be gradually moved to the center.
[0022]
In using the scaffold holding jig 1 of the present invention having the above-described configuration, first, as shown in FIG. 1, the U-shaped base plate 2 is straddled on the opening 10 of the building foundation 9. The bolt 8 is inserted into the nuts 7 attached to the side plates 2b and 2c on both sides of the U-shaped base plate 2 in the state, and the holding plate 3 on both sides is moved at the tip of the bolt 8, while the building foundation 9 of the opening 10 is moved. By tightening both side surfaces, the scaffold receiving jig 1 is attached to the building foundation 9 in a stable state.
[0023]
Next, as shown in FIGS. 2 (a), 2 (b) and 4, a floor plate 11 is laid in order on the floor beam on the first floor around the locking connection 5 of the holding jig 1 for scaffolding, and the locking connection is made. The flat plate 5a at the lower part of the tool 5 can be arranged on a joint portion 12 formed by parallel floor plates 11.
[0024]
At this time, the reinforcing bracket 6 fixed to the flat plate 5a is disposed below the floor plate 11, particularly as shown in FIG.
[0025]
As described above, a plurality of scaffolding pipes 14 are connected to the tap connection tool 5 erected on the joint portion 12 of the floor board 11 laid on the floor of the first floor via a connecting jig 13 as shown in FIG. By connecting and fixing, a scaffold can be easily constructed at the construction site.
[0026]
The distance between the two sandwiching plates 3 arranged inside the side plates 2b and 2c of the U-shaped base plate 2 only needs to be slightly larger than the lateral width of the building foundation 9 inserted between them. Moreover, the space | interval of the clamping plate 3 and the side plates 2b and 2c on both sides should just be about 2-6 mm.
[0027]
In the above embodiment, the sandwiching plates 3 are provided on both inner sides of the U-shaped base plate 2, but one of them can be omitted. In the above embodiment, the nuts 7 are welded to the side plates 2b and 2c, respectively. Instead of these nuts 7, screw holes into which the bolts 8 can be screwed are directly drilled into the side plates 2b and 2c. It is also possible to configure.
[0028]
Next, a second embodiment of the present invention will be described with reference to FIGS. 5 (a) and 5 (b) and FIGS. 6 (a), 6 (b) and 6 (c). The scaffold receiving jig 15 shown in the second embodiment is a modification of the scaffold receiving jig 1 of the first embodiment, and the structure thereof is further simplified.
[0029]
That is, the scaffold retainer jig 15 of the second embodiment basically has the same structure as the scaffold retainer jig 1. Therefore, the scaffold holding jig 15 is composed of a U-shaped base plate 2 composed of the back plate 2a, the side plates 2b and 2c, and a locking connector 5 which stands upright on the back plate 2a of the U-shaped base plate 2. ing.
[0030]
In the scaffold holding jig 1, the clamping plate 3 arranged in the U-shaped base plate 2 is integrally connected to the side plates 2 b and 2 c of the U-shaped base plate 2 through the connecting piece 4. On the other hand, in the scaffold holding jig 15 of the second embodiment, a clamping plate 16 having a relatively small area is fixed to the tip of the bolt 8 as shown in FIG. The sandwiching plate 16 can be brought into contact with the side surface of the building foundation 9 by turning 8.
[0031]
In addition, the scaffold receiving jig 15 is provided with a plurality of reinforcing ribs 17a and 17b in the U-shaped base plate 2, and the U-shaped base plate 2 is reinforced by these reinforcing ribs 17a and 17b. Yes.
[0032]
【The invention's effect】
In the present invention, since the U-shaped base plate is used, the plate can be stabilized by straddling the building foundation. In addition, a clamping plate is arranged inside the U-shaped base plate that can clamp a part of the building foundation, and means for moving the clamping plate is provided outside the U-shaped base plate. By moving the plate, a part of the building foundation is sandwiched and the U-shaped base plate can be easily and reliably fixed to the building foundation. Further, by placing the U-shaped base plate over the opening of the building foundation, the height of the scaffold receiving jig can be lowered, and the subsequent laying of the floor board can be facilitated.
[0033]
Moreover, when fixing the U-shaped base plate to the building foundation, the clamping plate as described above is brought into wide surface contact with the side surface of the building foundation, so that the outer surface of the building foundation is not damaged, and the U-shaped base plate is used. Can be firmly fixed to the building foundation in a stable state. In addition, since the latch connection is integrally raised on the back surface of the U-shaped base plate, the latch connection is fixed to the building foundation by attaching and fixing the U-shaped base plate to the building foundation as described above. It also has the effect of being able to automatically stand upright from the floor. Therefore, unlike the prior art, it is not necessary to drive the driving pile into the ground, and therefore, the moisture-proof sheet laid on the ground surface is not damaged and the waterproof property is not inhibited.
[0034]
In the above-described holding jig of the present invention, when a screw hole is drilled in the side wall of the U-shaped base plate or a nut is welded, and a bolt is inserted into these screw hole or nut. In this case, by rotating the bolt, the clamping plate arranged inside the U-shaped base plate is moved at the tip of the bolt, and the building foundation is clamped by the clamping plate so that the U-shaped base plate can be easily and reliably built. It can be attached and fixed to.
[0035]
Furthermore, in the retainer jig of the present invention, when the lower part of the hook connecting device standingly protruded on the back surface of the U-shaped base plate is constituted by a flat plate, the lower part of the hook connecting tool is left as it is. A floorboard can be laid in the state. In addition, the flat plate at the lower part of the connection member has an effect that it can be positioned at the joint between the floor plates laid on the floor surface. Therefore, when the holding jig for scaffolding of the present invention is used, it is not necessary to leave the floor of the place where the lug connector is placed during the construction work as an opening, and for this reason, it falls down at this place. It has great effects such as being able to prevent disasters from occurring.
[0036]
Since the scaffold receiving jig for a scaffold according to the present invention has the above-described structure and operation, if the building foundation is made, the scaffold receiving jig for the scaffold is used before the building body is built using this scaffold receiving jig. Can be built, and this has the effect of making the safety of the construction site more reliable.
[Brief description of the drawings]
FIG. 1 is an explanatory perspective view showing a usage state of a scaffold holding jig of a first embodiment according to the present invention.
2 (a) and 2 (b) are longitudinal sectional views showing the structure of the scaffold holding jig of FIG. 1, respectively.
FIG. 3 is a perspective explanatory view showing a configuration of a main part of the scaffold holding jig of FIG.
4 is a perspective explanatory view of a main part in a state in which a scaffold is constructed using the scaffold holding jig of FIG. 1. FIG.
FIGS. 5 (a) and 5 (b) are explanatory views showing a main part of a scaffold receiving jig for a scaffold according to a second embodiment of the present invention.
6 (a), 6 (b), and 6 (c) are a side view, a bottom view, and a front view, respectively, of the scaffold holding jig of FIG.
7 (a) and 7 (b) are perspective explanatory views showing a conventional example of a scaffold constructed on a construction site.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Scaffolding receiving jig 2 ... U-shaped base plate 2a ... Back plate 2b ... Side plate 2c ... Side plate 3 ... Holding plate 4 ... Connection piece 5 ... Locking connector 5a ... Flat plate 6 ... Reinforcement bracket 7 ... Nut 8 ... Bolt DESCRIPTION OF SYMBOLS 9 ... Building foundation 10 ... Opening part 11 ... Floor board 12 ... Joint part 13 ... Connection jig 14 ... Scaffolding pipe 15 ... Scaffolding holding jig 16 ... Holding plate 17a ... Reinforcement rib 17b ... Reinforcement rib 51 ... Scaffold 52 ... 53 ... Ground 54 ... Stake pile

Claims (2)

建築現場等に設置される足場の控を支持し得る治具に於て、建物基礎の凹状に形成された開口部に跨って載置されかつ該建物基礎に固定し得るコ字形ベースプレートと、該コ字形ベースプレートの背面に一体的に起立突設され床板目地部に位置する部分が扁平板によって形成された控接続具とで構成したことを特徴とした足場用控え受け治具。In a jig that can support a handle of a scaffold installed at a building site or the like, a U-shaped base plate that is placed across an opening formed in a concave shape of a building foundation and can be fixed to the building foundation; A scaffolding receiving jig for a scaffold, characterized in that the scaffolding jig is constructed by a protruding connection integrally formed on the back surface of the U-shaped base plate, and a portion located at a floor plate joint portion formed by a flat plate . 前記コ字形ベースプレートの内側に配置された挟持板がボルトの回動によって移動して前記建物基礎の側面を挟持するように構成したことを特徴とした請求項1の足場用控え受け治具。  The holding jig for scaffolding according to claim 1, wherein a holding plate disposed inside the U-shaped base plate is configured to move by rotation of a bolt to hold the side surface of the building foundation.
JP2000228081A 2000-07-28 2000-07-28 Scaffolding jig for scaffolding Expired - Lifetime JP4412826B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000228081A JP4412826B2 (en) 2000-07-28 2000-07-28 Scaffolding jig for scaffolding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000228081A JP4412826B2 (en) 2000-07-28 2000-07-28 Scaffolding jig for scaffolding

Publications (2)

Publication Number Publication Date
JP2002038710A JP2002038710A (en) 2002-02-06
JP4412826B2 true JP4412826B2 (en) 2010-02-10

Family

ID=18721442

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000228081A Expired - Lifetime JP4412826B2 (en) 2000-07-28 2000-07-28 Scaffolding jig for scaffolding

Country Status (1)

Country Link
JP (1) JP4412826B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7309272B2 (en) * 2019-07-17 2023-07-18 クリナップ株式会社 pedestal

Also Published As

Publication number Publication date
JP2002038710A (en) 2002-02-06

Similar Documents

Publication Publication Date Title
US7159262B2 (en) Bridge overhang bracket
US4763878A (en) Apparatus for jacking basement walls
US4893784A (en) Method and apparatus for jacking basement walls
CA2534944C (en) Bridge overhang bracket
US7117648B1 (en) Cross tie connection bracket
JP4412826B2 (en) Scaffolding jig for scaffolding
US4669704A (en) Method and apparatus for jacking basement walls
JP3477074B2 (en) Connection structure of horizontal members and vertical members on upper and lower floors
JPH0536042Y2 (en)
JP2007092352A (en) Temporary scaffold baseboard
JP3734571B2 (en) Wall panel mounting structure
JPH0849406A (en) Temporary member support fitting for construction
JP3033549U (en) Prefabricated scaffolding
CN218932850U (en) Jacking and pile body for trestle
JPH0671749U (en) Work scaffolding
JPH0119718Y2 (en)
JP2581699Y2 (en) Large support equipment
JPH0438030Y2 (en)
JPH0327166Y2 (en)
JP3350816B2 (en) How to build a wooden structure
JPH11293919A (en) Retaining structure of form and method thereof
JP3018921U (en) Scaffolding board support member, frame scaffolding assembly and scaffolding structure
JPH0539155Y2 (en)
JPS6011233Y2 (en) Joist support fittings
JPH0728320Y2 (en) Bracket to prevent slope drop

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070622

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20080131

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090821

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090901

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20091022

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20091117

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20091117

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121127

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4412826

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121127

Year of fee payment: 3

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121127

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121127

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131127

Year of fee payment: 4

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term