JP4017844B2 - Roofing construction structure - Google Patents

Roofing construction structure Download PDF

Info

Publication number
JP4017844B2
JP4017844B2 JP2001211108A JP2001211108A JP4017844B2 JP 4017844 B2 JP4017844 B2 JP 4017844B2 JP 2001211108 A JP2001211108 A JP 2001211108A JP 2001211108 A JP2001211108 A JP 2001211108A JP 4017844 B2 JP4017844 B2 JP 4017844B2
Authority
JP
Japan
Prior art keywords
roof material
starter
roof
mark
stage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001211108A
Other languages
Japanese (ja)
Other versions
JP2003027664A (en
Inventor
大介 江浜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nichiha Corp
Original Assignee
Nichiha Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nichiha Corp filed Critical Nichiha Corp
Priority to JP2001211108A priority Critical patent/JP4017844B2/en
Publication of JP2003027664A publication Critical patent/JP2003027664A/en
Application granted granted Critical
Publication of JP4017844B2 publication Critical patent/JP4017844B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Description

【0001】
【技術分野】
本発明は,屋根構造体に対して,スタータを最下段に配置すると共に,その後順次屋根材を重ね合わせて配置する屋根材の施工構造に関する。
【0002】
【従来技術】
図7に示すごとく,建築物の屋根構造体4に対して屋根材9を施工する場合には,まず軒先41にスタータ92と呼ばれる部材を配置すると共にその表面を覆って第1段目の屋根材9を配置する。次いで,図8〜図10に示すごとく,この屋根材9の上側表面に,第2段目の屋根材9を重ねて配置し,その後,順次同様にして,第3段目以降の屋根材9を配置して,屋根材9の施工を行っている。
【0003】
上記屋根材9の施工構造においては,上記第2段目の屋根材9は,第1段目の屋根材9の上側部分95を覆っていると共に,その下側部分96がスタータ92の上側部分925と第1段目の屋根材9を介して重なり合った重なり部931(図9参照)を有している。また,第3段目以降の屋根材9も,前段の屋根材9の上側部分95を覆っていると共に,その下側部分96が前々段の屋根材9の上側部分95と前段の屋根材9を介して重なり合った重なり部931(図10参照)を有している。そして,上記重なり部931により,雨,雪等が降ったときに,屋根材9の隙間から水分が建築物に浸入することを容易に防止している。
【0004】
また,上記スタータ92の上側部分925の形状は,上記屋根材9の上側部分95の形状と略同一の形状を有して製造されている。これは,上記重なり部931の上下方向の幅が,上記スタータ92と屋根材9とにより形成された幅W8と,上記屋根材9同士により形成された幅W9との間で,略同一になるように考慮しているからである。
【0005】
【解決しようとする課題】
しかしながら,上記従来の屋根材9の施工構造においては,上記スタータ92は,上側部分925の形状を屋根材9の上側部分95の形状に合わせておく必要がある。そのため,スタータ92は,屋根材9の種類に合わせて複数種類準備しておく必要があり,このスタータ92を製造する工程の合理化を行うことが困難になっている。
【0006】
本発明は,かかる従来の問題点に鑑みてなされたもので,各種の屋根材に対して共通に使用することができるスタータを用いて,上下,左右のどちらの方向に対しても容易に位置合わせを行うことができる屋根材の施工構造を提供しようとするものである。
【0007】
【課題の解決手段】
本発明は,屋根構造体に対して,横長矩形状のスタータを最下段に配置すると共に,該スタータの表面を覆うように第1段目の屋根材を配置し,次いで,該第1段目の屋根材の上側表面を覆うように第2段目の屋根材を配置し,以降順次先に配置した屋根材の上側表面を覆うように第3段目以降の屋根材を配置し,上記スタータ及び上記各屋根材を上記屋根構造体に固定してなる屋根材の施工構造であって,上記スタータは,上辺における左右方向の中央位置に,上記第1段目の屋根材との間の位置合わせを行うためのセンターマークを有し,上記各段の屋根材は,左右の側辺には,上記スタータに設けた上記センターマークとの間の位置合わせを行う第1マークと,隣り合う上記屋根材との間の位置合わせを行う第2マークとを有し,また,上辺における左右方向の中央位置には,1つ上段の屋根材の上記第2マークとの間の位置合わせを行う第3マークを有しており,上記第2段目の屋根材の下側部分と上記スタータの上側部分とは,上記第1段目の屋根材を介して互いに重なり合う状態に配置して第1重なり部を形成しており,上記第3段目以降の屋根材の下側部分と当該屋根材の前々段の屋根材の上側部分とは,前段の屋根材を介して互いに重なり合う状態に配置して第2重なり部を形成していることを特徴とする屋根材の施工構造にある(請求項1)。
【0008】
本発明においては,上記スタータは,従来のように上記屋根材の形状に合わせて製作しておくのではなく,上記屋根材がどのような形状をしている場合にも,上記横長矩形状を有するスタータを使用する。そのため,上記スタータは,各種の形状を有する屋根材に対して共通に使用することができる。
【0009】
上記のごとく,第1段目の屋根材は,スタータに対して,該スタータに設けた上記センターマークと第1段目の屋根材に設けた上記第1マークとを合わせて配置する。そして,第1段目の屋根材の上側表面に第2段目の屋根材を配置したとき,スタータと第2段目の屋根材との間で,上記第1重なり部を形成する。
そのため,この第1重なり部が重なり合う幅は,センターマーク又は第1マークの位置を変更することにより,容易に変更することができる。そのため,第1重なり部は,上記各段の屋根材が重なり合って形成する第2重なり部とは別に設定することができ,任意の幅に設定することができる。
【0010】
また,上記のごとく,上記スタータは上辺の上記中央位置に上記センターマークを有しており,上記各段の屋根材は左右の側辺に上記第1マークを有している。そのため,センターマークと第1マークとを合わせることにより,上記スタータと第1段目の屋根材との間の位置合わせを容易に行うことができる。
また,上記各段の屋根材は左右の側辺に上記第2マークを有している。そのため,左右に隣接する各段の屋根材は,それぞれ第2マーク同士を合わせることにより,隣り合う屋根材との間の位置合わせを容易に行うことができる。
【0011】
また,上記各段の屋根材は上辺の上記中央位置に上記第3マークを有している。そのため,上記第2マークと第3マークとを合わせることにより,各段の屋根材と該屋根材の1つ上段の屋根材との間の位置合わせを容易に行うことができる。
それ故,本発明における屋根材の施工構造においては,上記左右方向及び上下方向のどちらの方向に対しても容易に位置合わせを行うことができる。
【0012】
【発明の実施の形態】
本発明における屋根材としては,例えば,窯業系建築板を用いることができる。また,上記スタータ又は屋根材はすべて同じ形状のものを使用することができ,それらを屋根構造体における左右の端部に配置する際には,上記中央位置における上記センターマーク又は上記第3マークを目印にして,左右半分に分割して切断し,使用することができる。
また,上記スタータのセンターマーク又は上記屋根材の第3マークは,V字状に形成することができる。この場合には,V字状の部分に応力集中を働かせて,容易にそれらを左右半分に分割,切断することができる。
【0013】
また,上記スタータのセンターマーク及び上記屋根材の第1マーク,第2マーク,第3マークのそれぞれは,半円状又はU字状の円弧状,あるいはV字状等の形状を有する切欠きにより構成することができる。
また,上記スタータのセンターマークと上記屋根材の第1マークとを同じ形状の切欠きに,また,上記屋根材における第2マークと第3マークとを同じ形状の切欠きに形成することができる。この場合,同じ形状の切欠きを合わせて上記屋根材を配置することができる。そのため,屋根材の施工が一層容易になる。
【0014】
また,上記スタータは,左右の側辺に,軒先との位置合わせを行う軒先マークを有していることが好ましい(請求項2)。
これにより,上記スタータは,軒先に対して容易に位置合わせができると共に,上記軒先マークよりも先端の部分を軒先よりも突出させて施工することができる。
【0015】
また,上記スタータは,上記センターマークを上辺及び下辺に有していると共に,上記軒先マークを上下方向の中央位置から上下対称の位置に有していることが好ましい(請求項3)。
この場合,上記スタータは,横長矩形状の長辺におけるどちらの辺を上側に向けて施工してもよく,屋根構造体に配置することが一層容易になる。
【0016】
また,上記第1重なり部は,50mm以上の幅に形成されていることが好ましい(請求項4)。
この場合,雨,雪等が降ったときに,上記スタータと屋根材との隙間から水分が建築物に浸入することを容易に防止することができる。
また,上記第1重なり部の幅は,あまり大きくする必要はなく,実際には80mm未満とすることが好ましい。
【0017】
【実施例】
以下に,図面を用いて本発明の実施例につき説明する。
図6(a)に示すごとく,本例における屋根材1の施工構造は,屋根構造体4に対して,横長矩形状のスタータ2を配置した後,各段の屋根材1を重ね合わせて配置して固定する。
図1に示すごとく,屋根材1の施工を行うに際しては,まず,スタータ2を最下段に配置すると共に,該スタータ2の表面201を覆うように第1段目の屋根材1を配置する。次いで,図2〜図4に示すごとく,第1段目の屋根材1の上側表面101を覆うように第2段目の屋根材1を配置し,以降順次先に配置した各段の屋根材1の上側表面101を覆うように第3段目以降の屋根材1を配置する。
【0018】
図5(c)に示すごとく,上記スタータ2は,上辺21における左右方向の中央位置に,上記第1段目の屋根材1との間の位置合わせを行うためのセンターマーク211を有している。
図5(a)に示すごとく,上記屋根材1は,左右の側辺12には,上記スタータ2に設けた上記センターマーク211との間の位置合わせを行う第1マーク121と,隣り合う上記屋根材1との間の位置合わせを行う第2マーク122とを有している。また,屋根材1は,上辺11における左右方向の中央位置には,1つ上段の屋根材1の上記第2マーク122との間の位置合わせを行う第3マーク111を有している。
【0019】
図3に示すごとく,上記第2段目の屋根材1の下側部分16と上記スタータ2の上側部分25とは,第1段目の屋根材1を介して互いに重なり合う状態に配置して第1重なり部31を形成している。
図4に示すごとく,以下同様にして,上記第3段目以降の屋根材1の下側部分16と当該屋根材1の前々段の屋根材1の上側部分15とは,前段の屋根材1を介して互いに重なり合う状態に配置して第2重なり部32を形成している。
【0020】
以下に,これを詳説する。
図5(c)に示すごとく,上記スタータ2は,左右の側辺22に,軒先41との位置合わせを行う軒先マーク221を有している。また,スタータ2は,上記センターマーク211を上辺21及び下辺23に有していると共に,上記軒先マーク221を上下方向の中央位置から上下対称の位置に有している。
【0021】
本例においては,上記スタータ2はすべて同じサイズに形成されており,上記各段に用いる屋根材1もまたすべて同じサイズに形成されている。
また,上記スタータ2のセンターマーク211及び上記屋根材1の第1マーク121は,半円状又はU字状に形成された円弧状の切欠きにより構成されている。また,スタータ2の軒先マーク221,及び屋根材1の第2マーク122及び第3マーク111は,V字状の切欠きによって構成されている。
【0022】
本例においては,図5(a)に示すごとく,上記屋根材1の上辺11と側辺12とは,曲線で結ばれている。これに対し,図5(b)に示すごとく,上記屋根材1の上辺11と側辺12とは,直線で結ばれていてもよい。このように,上記屋根材1は,上側部分25の左右両側を切断して,5角形に近い形状を有しており,これにより軽量化を図っている。
【0023】
また,本例においては,図6(a)に示すごとく,最下段にスタータ2を配置し,1段目に屋根材1を配置した。これに対し,図6(b)に示すごとく,上記屋根材1の厚みが大きくなったとき等には,上記スタータ2の更に下段にこのスタータ2よりも上下方向の幅の小さい小スタータ25を配置してもよい。
【0024】
以下に,上記屋根材1を上記屋根構造体4に施工する方法につき説明する。
屋根材1の施工を行うに際しては,まず,図1に示すごとく,スタータ2を,横長矩形状の長辺である上辺21及び下辺23が屋根構造体4の横方向に位置するようにし,当該スタータ2の側辺22に隣接するスタータ2の側辺22を繋いで,配置する。また,スタータ2の上記軒先マーク221を軒先41に合わせて施工する。こうして,施工構造の最下段として,スタータ2を配置する。
【0025】
次いで,図2に示すごとく,上記スタータ2の表面201を覆うように,上下方向に対しては,スタータ2の下辺23と第1段目の屋根材1の下辺13とを合わせて位置合わせを行い,第1段目の屋根材1を配置する。また,このとき,左右方向に対しては,第1段目の屋根材1は,その円弧状の切欠きである第1マーク121と,スタータ2における円弧状の切欠きであるセンターマーク211とを合わせて位置合わせを行い,配置する。つまり,この屋根材1は,屋根構造体4に配置したスタータ2に対して,長辺の半分の長さを横方向にずらして配置する。
【0026】
次いで,図3に示すごとく,第1段目の屋根材1の上側表面101を覆うように第2段目の屋根材1を配置する。このとき,第1段目の屋根材1におけるV字状の切欠きである第3マーク111に,第2段目の屋根材1におけるV字状の切欠きである第2マーク122を合わせて配置する。
そして,この配置により,上記第2段目の屋根材1の下側部分16と上記スタータ2の上側部分25との間には,第1段目の屋根材1を介してそれらが互いに重なり合った第1重なり部31(図3中斜線部)が形成される。
【0027】
次いで,図4に示すごとく,第2段目の屋根材1の上側表面101を覆うように第3段目の屋根材1を配置する。このとき,第2段目の屋根材1におけるV字状の切欠きである上記第3マーク111に,第3段目の屋根材1におけるV字状の切欠きである第2マーク122を合わせて配置する。そして,この配置により,上記第3段目の屋根材1の下側部分16と上記第1段目の屋根材1の上側部分15との間には,第2段目の屋根材1を介してそれらが互いに重なり合った第2重なり部32(図4中斜線部)が形成される。
【0028】
以下同様にして,第4段目以降の屋根材1を,前段の屋根材1の上側表面15を覆うように配置する。そして,第4段目以降の屋根材1の下側部分16と,当該屋根材1の前々段の屋根材1の上側部分15との間にも,前段の屋根材1を介してそれらが互いに重なり合った第2重なり部32が形成される。
なお,上記各段の屋根材1の施工を行う際に,各段の配列の終端100に位置する屋根材1は,上記V字状の第3マーク111に沿って半分に切断し,施工を行うことができる。
【0029】
本例においては,上記スタータ2は,従来のように上記屋根材1の形状に合わせて製作しておくのではなく,上記屋根材1がどのような形状をしている場合にも,上記横長矩形状を有するスタータ2を使用する。そのため,上記スタータ2は,各種の形状を有する屋根材1に対して共通に使用することができる。
【0030】
また,上記のごとく,上記第1段目の屋根材1をスタータ2に対して配置するときは,それぞれ円弧状の切欠きを有する上記センターマーク211と第1マーク121とを合わせて配置する。また,第2段目以降の屋根材1を前段の屋根材1に配置するときは,それぞれV字状の切欠きを有する第2マーク122と第3マーク111とを合わせて配置する。つまり,同じ種類の切欠きを合わせて屋根材1の配置を行うため,配置が容易であり,配置ミス等を少なくすることができる。
【0031】
また,上記第1重なり部31において,第2段目の屋根材1とスタータ2とが重なり合う重なり幅W1(図3参照)は,センターマーク211又は第1マーク121の位置を変更することにより,容易に変更することができる。そのため,第1重なり部31の重なり幅W1は,上記各段の屋根材1同士が重なり合って形成する第2重なり部32の重なり幅W2(図4参照)とは別に設定することができ,任意の幅に設定することができる。
【0032】
また,上記各重なり幅W1,W2は,50mm以上の幅を有して形成されている。そのため,雨,雪等が降ったときに,上記スタータ2と屋根材1との隙間又は屋根材1同士の隙間から水分が建築物に浸入することを容易に防止することができる。
また,上記スタータ2及び屋根材1は,釘等によって上記屋根構造体4に固定することができる。
【0033】
また,上記スタータ2のセンターマーク211,上記各段の屋根材1の第1マーク121,第2マーク122,第3マーク111により,上記スタータ2及び各段の屋根材1は,上記左右方向及び上下方向のどちらの方向に対しても容易に位置合わせを行うことができる。そのため,この正確な位置合わせにより,上記屋根材1の施工構造は,優れた外観を呈することができる。
【図面の簡単な説明】
【図1】実施例における,屋根材の施工方法を示す図で,スタータを配置した状態を示す説明図。
【図2】実施例における,屋根材の施工方法を示す図で,第1段目の屋根材を配置した状態を示す説明図。
【図3】実施例における,屋根材の施工方法を示す図で,第2段目の屋根材を配置した状態を示す説明図。
【図4】実施例における,屋根材の施工方法を示す図で,第3段目の屋根材を配置した状態を示す説明図。
【図5】実施例における,(a)屋根材,(b)他の屋根材,(c)スタータを示す平面図。
【図6】実施例における,屋根材の施工構造を示す側面図。
【図7】従来例における,屋根材の施工方法を示す図で,スタータを配置した状態を示す説明図。
【図8】従来例における,屋根材の施工方法を示す図で,第1段目の屋根材を配置した状態を示す説明図。
【図9】従来例における,屋根材の施工方法を示す図で,第2段目の屋根材を配置した状態を示す説明図。
【図10】従来例における,屋根材の施工方法を示す図で,第3段目の屋根材を配置した状態を示す説明図。
【符号の説明】
1...屋根材,
11...上辺,
111...第3マーク,
12...側辺,
121...第1マーク,
122...第2マーク,
15...上側部分,
16...下側部分,
2...スタータ,
21...上辺,
211...センターマーク,
22...側辺,
221...軒先マーク,
23...下辺,
25...上側部分,
31...第1重なり部,
32...第2重なり部,
4...屋根構造体,
[0001]
【Technical field】
The present invention relates to a construction structure for a roof material in which a starter is disposed at the lowest stage with respect to the roof structure, and then the roof materials are sequentially stacked one after another.
[0002]
[Prior art]
As shown in FIG. 7, when the roof material 9 is constructed on the roof structure 4 of the building, first, a member called a starter 92 is arranged on the eaves 41 and the surface is covered to cover the first stage roof. The material 9 is arranged. Next, as shown in FIG. 8 to FIG. 10, the second-stage roof material 9 is arranged on the upper surface of the roof material 9, and thereafter, in the same manner, the third-stage roof material 9 and subsequent roof materials 9. The roof material 9 is being constructed.
[0003]
In the construction structure of the roof material 9, the second-stage roof material 9 covers the upper part 95 of the first-stage roof material 9, and the lower part 96 is the upper part of the starter 92. 925 and the overlapping part 931 (refer FIG. 9) which overlapped through the roof material 9 of the 1st step | paragraph. Further, the roof material 9 after the third stage also covers the upper part 95 of the roof material 9 in the previous stage, and the lower part 96 thereof covers the upper part 95 of the roof material 9 in the previous stage and the roof material in the previous stage. 9 and an overlapping portion 931 (see FIG. 10) that overlap each other. The overlapping portion 931 easily prevents moisture from entering the building through the gaps in the roofing material 9 when rain, snow, or the like falls.
[0004]
The shape of the upper portion 925 of the starter 92 is manufactured to have substantially the same shape as the shape of the upper portion 95 of the roof material 9. This is because the vertical width of the overlapping portion 931 is substantially the same between a width W8 formed by the starter 92 and the roofing material 9 and a width W9 formed by the roofing materials 9 together. It is because it considers.
[0005]
[Problems to be solved]
However, in the construction structure of the conventional roof material 9, the starter 92 needs to match the shape of the upper portion 925 with the shape of the upper portion 95 of the roof material 9. Therefore, it is necessary to prepare a plurality of types of starters 92 according to the types of the roofing material 9, and it is difficult to rationalize the process for manufacturing the starters 92.
[0006]
The present invention has been made in view of such conventional problems, and can be easily positioned in both the vertical and horizontal directions using a starter that can be commonly used for various roofing materials. It is intended to provide a construction structure for roof materials that can be combined.
[0007]
[Means for solving problems]
In the present invention, a horizontally long rectangular starter is arranged at the bottom of the roof structure, and a first-stage roof material is arranged so as to cover the surface of the starter, and then the first-stage roof The second stage roofing material is arranged so as to cover the upper surface of the roofing material, and the third and subsequent roofing materials are arranged sequentially so as to cover the upper surface of the previously arranged roofing material. And a roof material construction structure in which each roof material is fixed to the roof structure, wherein the starter is positioned between the upper roof material and the first-stage roof material at a central position in the left-right direction. A center mark for alignment is provided, and the roof material of each step is adjacent to the first mark for alignment with the center mark provided on the starter on the left and right sides. A second mark for alignment with the roofing material, and At the center in the left-right direction on the upper side, there is a third mark for alignment with the second mark of the upper roof material, and the lower part of the second roof material And the upper part of the starter are arranged so as to overlap each other via the first stage roofing material to form a first overlapping part, and the lower part of the roofing material after the third stage And the upper part of the roof material of the previous stage of the roof material are arranged so as to overlap each other via the roof material of the previous stage, and a construction structure of the roof material is formed (Claim 1).
[0008]
In the present invention, the starter is not manufactured according to the shape of the roof material as in the prior art, but the horizontally long rectangular shape is used regardless of the shape of the roof material. Use the starter you have. Therefore, the starter can be commonly used for roof materials having various shapes.
[0009]
As described above, the first-stage roof material is arranged with respect to the starter by combining the center mark provided on the starter and the first mark provided on the first-stage roof material. When the second-stage roof material is disposed on the upper surface of the first-stage roof material, the first overlapping portion is formed between the starter and the second-stage roof material.
Therefore, the width at which the first overlapping portion overlaps can be easily changed by changing the position of the center mark or the first mark. Therefore, the first overlapping portion can be set separately from the second overlapping portion formed by overlapping the roof materials at the respective steps, and can be set to an arbitrary width.
[0010]
Further, as described above, the starter has the center mark at the center position on the upper side, and the roof material of each step has the first mark on the left and right sides. Therefore, by aligning the center mark and the first mark, the alignment between the starter and the first-stage roof material can be easily performed.
The roof material of each step has the second mark on the left and right sides. Therefore, the roof material of each step | line adjacent to right and left can align easily between adjacent roof materials by aligning 2nd marks, respectively.
[0011]
Further, the roof material of each step has the third mark at the center position on the upper side. Therefore, by aligning the second mark and the third mark, it is possible to easily perform alignment between the roof material at each level and the roof material one level above the roof material.
Therefore, in the construction structure of the roof material according to the present invention, the alignment can be easily performed in both the left-right direction and the up-down direction.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
As the roofing material in the present invention, for example, a ceramic building board can be used. The starter or the roofing material can be of the same shape, and when they are arranged at the left and right end portions of the roof structure, the center mark or the third mark at the center position is used. It can be used as a mark, cut into left and right halves and cut.
Also, the center mark of the starter or the third mark of the roof material can be formed in a V shape. In this case, stress concentration is applied to the V-shaped portion, and they can be easily divided and cut into left and right halves.
[0013]
Further, the center mark of the starter and the first mark, the second mark, and the third mark of the roof material are each formed by a notch having a semicircular or U-shaped arc shape or a V-shaped shape. Can be configured.
In addition, the center mark of the starter and the first mark of the roof material can be formed in a notch having the same shape, and the second mark and the third mark in the roof material can be formed in a notch having the same shape. . In this case, it is possible to arrange the roof material with notches having the same shape. Therefore, the construction of roofing material becomes easier.
[0014]
Moreover, it is preferable that the starter has an eaves edge mark for alignment with the eaves edge on the left and right sides.
As a result, the starter can be easily aligned with the eaves edge, and can be constructed with the tip portion protruding beyond the eaves edge mark.
[0015]
The starter preferably has the center mark on the upper side and the lower side, and the eaves mark at a vertically symmetrical position from the center position in the vertical direction.
In this case, the starter may be constructed so that either side of the long side of the horizontally long rectangular shape faces upward, and it is easier to arrange the starter on the roof structure.
[0016]
Moreover, it is preferable that the said 1st overlap part is formed in the width | variety of 50 mm or more.
In this case, when rain, snow or the like falls, it is possible to easily prevent moisture from entering the building through the gap between the starter and the roofing material.
Further, the width of the first overlapping portion does not need to be so large, and is actually preferably less than 80 mm.
[0017]
【Example】
Embodiments of the present invention will be described below with reference to the drawings.
As shown in FIG. 6 (a), the construction structure of the roofing material 1 in this example is arranged by arranging the roofing material 1 on each stage after arranging the horizontally long rectangular starter 2 on the roofing structure 4. And fix.
As shown in FIG. 1, when the roof material 1 is constructed, first, the starter 2 is arranged at the lowest level, and the first-stage roof material 1 is arranged so as to cover the surface 201 of the starter 2. Next, as shown in FIG. 2 to FIG. 4, the second-stage roof material 1 is arranged so as to cover the upper surface 101 of the first-stage roof material 1, and the roof material of each stage arranged sequentially thereafter thereafter. The roof material 1 after the third stage is disposed so as to cover the upper surface 101 of the first stage.
[0018]
As shown in FIG. 5 (c), the starter 2 has a center mark 211 for aligning with the first-stage roofing material 1 at the center position in the left-right direction on the upper side 21. Yes.
As shown in FIG. 5 (a), the roof material 1 is adjacent to the left and right side edges 12 adjacent to the first mark 121 for alignment with the center mark 211 provided on the starter 2. And a second mark 122 for positioning with the roofing material 1. Further, the roof material 1 has a third mark 111 at the center position in the left-right direction on the upper side 11 for performing alignment with the second mark 122 of the roof material 1 one level above.
[0019]
As shown in FIG. 3, the lower portion 16 of the second-stage roofing material 1 and the upper portion 25 of the starter 2 are arranged so as to overlap each other via the first-stage roofing material 1. One overlapping portion 31 is formed.
As shown in FIG. 4, in the same manner, the lower portion 16 of the roof material 1 after the third stage and the upper portion 15 of the roof material 1 before the roof material 1 are the roof material of the previous stage. The second overlapping portions 32 are formed so as to overlap each other via 1.
[0020]
This is described in detail below.
As shown in FIG. 5C, the starter 2 has eaves edge marks 221 that align with the eaves edge 41 on the left and right sides 22. In addition, the starter 2 has the center mark 211 on the upper side 21 and the lower side 23 and the eaves mark 221 at a vertically symmetrical position from the vertical center position.
[0021]
In this example, the starters 2 are all formed in the same size, and the roofing materials 1 used for the steps are also formed in the same size.
Further, the center mark 211 of the starter 2 and the first mark 121 of the roof material 1 are constituted by arc-shaped notches formed in a semicircular shape or a U-shape. Further, the eaves mark 221 of the starter 2 and the second mark 122 and the third mark 111 of the roofing material 1 are configured by V-shaped notches.
[0022]
In this example, as shown to Fig.5 (a), the upper side 11 and the side 12 of the said roofing material 1 are connected with the curve. On the other hand, as shown in FIG.5 (b), the upper side 11 and the side 12 of the said roofing material 1 may be connected with the straight line. Thus, the roof material 1 has a shape close to a pentagon by cutting the left and right sides of the upper portion 25, thereby reducing the weight.
[0023]
Moreover, in this example, as shown to Fig.6 (a), the starter 2 is arrange | positioned at the lowest step and the roofing material 1 is arrange | positioned at the 1st step. On the other hand, as shown in FIG. 6B, when the thickness of the roofing material 1 is increased, a small starter 25 having a smaller vertical width than that of the starter 2 is provided further below the starter 2. You may arrange.
[0024]
Hereinafter, a method for constructing the roof material 1 on the roof structure 4 will be described.
When constructing the roofing material 1, first, as shown in FIG. 1, the starter 2 is arranged so that the upper side 21 and the lower side 23, which are the long sides of the horizontally long rectangular shape, are positioned in the lateral direction of the roof structure 4. The side 22 of the starter 2 adjacent to the side 22 of the starter 2 is connected and arranged. Further, the eaves mark 221 of the starter 2 is installed in accordance with the eaves 41. Thus, the starter 2 is arranged as the lowest stage of the construction structure.
[0025]
Next, as shown in FIG. 2, in order to cover the surface 201 of the starter 2, the lower side 23 of the starter 2 and the lower side 13 of the first roofing material 1 are aligned in the vertical direction. The first stage roofing material 1 is arranged. At this time, in the left-right direction, the first-stage roofing material 1 includes a first mark 121 that is an arc-shaped notch and a center mark 211 that is an arc-shaped notch in the starter 2. Align and align the positions. That is, the roofing material 1 is arranged by shifting the length of half of the long side in the lateral direction with respect to the starter 2 arranged on the roof structure 4.
[0026]
Next, as shown in FIG. 3, the second-stage roof material 1 is arranged so as to cover the upper surface 101 of the first-stage roof material 1. At this time, the second mark 122 that is a V-shaped notch in the second-stage roof material 1 is aligned with the third mark 111 that is a V-shaped notch in the first-stage roof material 1. Deploy.
And by this arrangement, they overlap each other via the first-stage roof material 1 between the lower part 16 of the second-stage roof material 1 and the upper part 25 of the starter 2. A first overlapping portion 31 (shaded portion in FIG. 3) is formed.
[0027]
Next, as shown in FIG. 4, the third-stage roof material 1 is disposed so as to cover the upper surface 101 of the second-stage roof material 1. At this time, the second mark 122 that is a V-shaped notch in the third-stage roof material 1 is aligned with the third mark 111 that is a V-shaped notch in the second-stage roof material 1. Arrange. With this arrangement, the second-stage roof material 1 is interposed between the lower portion 16 of the third-stage roof material 1 and the upper portion 15 of the first-stage roof material 1. Thus, a second overlapping portion 32 (shaded portion in FIG. 4) in which they overlap each other is formed.
[0028]
Similarly, the fourth and subsequent roof materials 1 are arranged so as to cover the upper surface 15 of the previous roof material 1. And between the lower part 16 of the roofing material 1 after the fourth stage and the upper part 15 of the roofing material 1 of the preceding stage of the roofing material 1, they are interposed via the roofing material 1 of the previous stage. A second overlapping portion 32 that overlaps each other is formed.
In addition, when performing the roof material 1 of each step, the roof material 1 located at the terminal end 100 of each step array is cut in half along the V-shaped third mark 111, and the work is performed. It can be carried out.
[0029]
In this example, the starter 2 is not manufactured according to the shape of the roof material 1 as in the prior art, but the horizontally long shape is used regardless of the shape of the roof material 1. A starter 2 having a rectangular shape is used. Therefore, the starter 2 can be commonly used for the roofing material 1 having various shapes.
[0030]
Further, as described above, when the first-stage roofing material 1 is arranged with respect to the starter 2, the center mark 211 and the first mark 121 each having an arcuate cutout are arranged together. When the roof material 1 after the second stage is arranged on the roof material 1 of the previous stage, the second mark 122 and the third mark 111 each having a V-shaped notch are arranged together. That is, since the roof material 1 is arranged by combining the same type of notches, the arrangement is easy and arrangement errors and the like can be reduced.
[0031]
Moreover, in the said 1st overlap part 31, the overlap width W1 (refer FIG. 3) with which the roof material 1 and the starter 2 of a 2nd step overlap is changed by changing the position of the center mark 211 or the 1st mark 121. It can be easily changed. Therefore, the overlapping width W1 of the first overlapping portion 31 can be set separately from the overlapping width W2 (see FIG. 4) of the second overlapping portion 32 formed by overlapping the roof materials 1 of the respective steps. Can be set to a width of
[0032]
Each of the overlapping widths W1 and W2 is formed to have a width of 50 mm or more. Therefore, when rain, snow or the like falls, it is possible to easily prevent moisture from entering the building through the gap between the starter 2 and the roofing material 1 or the gap between the roofing materials 1.
The starter 2 and the roofing material 1 can be fixed to the roof structure 4 with nails or the like.
[0033]
Further, the starter 2 and the roof material 1 of each step are arranged in the left and right direction by the center mark 211 of the starter 2, the first mark 121, the second mark 122, and the third mark 111 of the roof material 1 of each step. Positioning can be easily performed in either of the vertical directions. Therefore, the construction structure of the roof material 1 can exhibit an excellent appearance by this accurate alignment.
[Brief description of the drawings]
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is a diagram illustrating a roof material construction method in an embodiment and is an explanatory diagram illustrating a state in which a starter is arranged.
FIG. 2 is a diagram showing a roof material construction method in the embodiment, and is an explanatory diagram showing a state in which the first-stage roof material is arranged.
FIG. 3 is a diagram showing a roof material construction method in the embodiment, and is an explanatory diagram showing a state in which a second-stage roof material is arranged.
FIG. 4 is a diagram showing a roof material construction method in the embodiment, and is an explanatory diagram showing a state in which a third-stage roof material is arranged.
FIG. 5 is a plan view showing (a) a roof material, (b) another roof material, and (c) a starter in the embodiment.
FIG. 6 is a side view showing the construction structure of the roof material in the embodiment.
FIG. 7 is a diagram showing a roof material construction method in a conventional example, and is an explanatory diagram showing a state in which a starter is arranged.
FIG. 8 is a diagram showing a roof material construction method in a conventional example, and is an explanatory diagram showing a state in which a first-stage roof material is arranged.
FIG. 9 is a diagram showing a roof material construction method in a conventional example, and is an explanatory diagram showing a state in which a second-stage roof material is arranged.
FIG. 10 is a diagram illustrating a roof material construction method in a conventional example, and is an explanatory diagram illustrating a state in which a third-stage roof material is disposed.
[Explanation of symbols]
1. . . Roofing material,
11. . . Upper side,
111. . . 3rd mark,
12 . . Side,
121. . . First mark,
122. . . Second mark,
15. . . Upper part,
16. . . Lower part,
2. . . Starter,
21. . . Upper side,
211. . . Center mark,
22. . . Side,
221. . . Eaves mark,
23. . . Bottom,
25. . . Upper part,
31. . . The first overlap,
32. . . Second overlap,
4). . . Roof structure,

Claims (4)

屋根構造体に対して,横長矩形状のスタータを最下段に配置すると共に,該スタータの表面を覆うように第1段目の屋根材を配置し,次いで,該第1段目の屋根材の上側表面を覆うように第2段目の屋根材を配置し,以降順次先に配置した屋根材の上側表面を覆うように第3段目以降の屋根材を配置し,上記スタータ及び上記各屋根材を上記屋根構造体に固定してなる屋根材の施工構造であって,上記スタータは,上辺における左右方向の中央位置に,上記第1段目の屋根材との間の位置合わせを行うためのセンターマークを有し,上記各段の屋根材は,左右の側辺には,上記スタータに設けた上記センターマークとの間の位置合わせを行う第1マークと,隣り合う上記屋根材との間の位置合わせを行う第2マークとを有し,また,上辺における左右方向の中央位置には,1つ上段の屋根材の上記第2マークとの間の位置合わせを行う第3マークを有しており,上記第2段目の屋根材の下側部分と上記スタータの上側部分とは,上記第1段目の屋根材を介して互いに重なり合う状態に配置して第1重なり部を形成しており,上記第3段目以降の屋根材の下側部分と当該屋根材の前々段の屋根材の上側部分とは,前段の屋根材を介して互いに重なり合う状態に配置して第2重なり部を形成していることを特徴とする屋根材の施工構造。    With respect to the roof structure, a horizontally long starter is arranged at the lowest level, and the first level roofing material is arranged so as to cover the surface of the starter. The second-stage roof material is arranged so as to cover the upper surface, and the third and subsequent roof materials are arranged so as to cover the upper surface of the previously arranged roof material, and the starter and each roof. A construction structure of a roof material in which a material is fixed to the roof structure, and the starter is positioned at the center position in the left-right direction on the upper side to align with the first-stage roof material. The roof material of each step has a first mark for alignment with the center mark provided on the starter on the left and right sides, and the adjacent roof material. With a second mark for alignment between the And a third mark for alignment with the second mark of the upper roof material, and a lower portion of the second roof material, The upper part of the starter is arranged so as to overlap each other via the first stage roofing material to form a first overlapping part, and the lower part of the roofing material after the third stage and The roof material construction structure characterized in that the upper part of the roof material of the preceding stage of the roof material is arranged so as to overlap with each other via the roof material of the previous stage to form a second overlapping portion. 請求項1において,上記スタータは,左右の側辺に,軒先との位置合わせを行う軒先マークを有していることを特徴とする屋根材の施工構造。2. The construction structure of a roof material according to claim 1, wherein the starter has eaves edge marks for alignment with eaves edges on the left and right sides. 請求項1又は2において,上記スタータは,上記センターマークを上辺及び下辺に有していると共に,上記軒先マークを上下方向の中央位置から上下対称の位置に有していることを特徴とする屋根材の施工構造。The roof according to claim 1 or 2, wherein the starter has the center mark on the upper side and the lower side, and has the eaves mark in a vertically symmetrical position from a center position in the vertical direction. Construction structure of the material. 請求項1〜4のいずれか一項において,上記第1重なり部は,50mm以上の幅に形成されていることを特徴とする屋根材の施工構造。The construction structure of a roof material according to any one of claims 1 to 4, wherein the first overlapping portion is formed to have a width of 50 mm or more.
JP2001211108A 2001-07-11 2001-07-11 Roofing construction structure Expired - Fee Related JP4017844B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001211108A JP4017844B2 (en) 2001-07-11 2001-07-11 Roofing construction structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001211108A JP4017844B2 (en) 2001-07-11 2001-07-11 Roofing construction structure

Publications (2)

Publication Number Publication Date
JP2003027664A JP2003027664A (en) 2003-01-29
JP4017844B2 true JP4017844B2 (en) 2007-12-05

Family

ID=19046478

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001211108A Expired - Fee Related JP4017844B2 (en) 2001-07-11 2001-07-11 Roofing construction structure

Country Status (1)

Country Link
JP (1) JP4017844B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6479923B1 (en) * 2017-10-03 2019-03-06 日新製鋼株式会社 Eaves starter and roof structure using it

Also Published As

Publication number Publication date
JP2003027664A (en) 2003-01-29

Similar Documents

Publication Publication Date Title
US20060265989A1 (en) Self-Aligning Roofing Shingles
JP4017844B2 (en) Roofing construction structure
JPH0886050A (en) Roof covering structure
JP3432183B2 (en) Renovation roofing material and its mounting structure
JP2011226231A (en) Roofing structure and roofing material
JP3164991B2 (en) Construction method of building roof
JP3924116B2 (en) Roof tile and roof tile construction structure
JP3378566B2 (en) Metal roofing material of conical roof and its construction method
JPH10131405A (en) Flat seam roofing tile
JP3496570B2 (en) Roofing structure
JP3283488B2 (en) Roof panel and manufacturing method thereof
JPH0726662A (en) Roofing board
JPH0633513A (en) Joining method for column and beam
JP3318159B2 (en) Flat roofing material and its construction method.
JP3184056B2 (en) Roofing material for industrialized building and roofing method
JP3432952B2 (en) Roof mounting method and prefinished roof panel
JP3784957B2 (en) Foundation formation method to build buildings such as houses
JP5421616B2 (en) Roofing construction structure
JPH09195447A (en) Roof tile for roof panel
JPH06146300A (en) Reinforcement frame member for building rc construction foundation, and the like
JPH06185171A (en) Flat roof tile
JP3280817B2 (en) Roof panel and roof of building using this roof panel
JP3845588B2 (en) Eave sky construction method and corner parts
JPH01105820A (en) Laying method for block mat
JPH05321409A (en) Roofing tile

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050330

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060906

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070515

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20070601

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20070601

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070703

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070911

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070919

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100928

Year of fee payment: 3

LAPS Cancellation because of no payment of annual fees