JP4011209B2 - Construction method of shaft - Google Patents

Construction method of shaft Download PDF

Info

Publication number
JP4011209B2
JP4011209B2 JP28975798A JP28975798A JP4011209B2 JP 4011209 B2 JP4011209 B2 JP 4011209B2 JP 28975798 A JP28975798 A JP 28975798A JP 28975798 A JP28975798 A JP 28975798A JP 4011209 B2 JP4011209 B2 JP 4011209B2
Authority
JP
Japan
Prior art keywords
shaft
concrete
water
retaining wall
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP28975798A
Other languages
Japanese (ja)
Other versions
JP2000120366A (en
Inventor
吉輝 土橋
徳行 西田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nishimatsu Construction Co Ltd
Original Assignee
Nishimatsu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nishimatsu Construction Co Ltd filed Critical Nishimatsu Construction Co Ltd
Priority to JP28975798A priority Critical patent/JP4011209B2/en
Publication of JP2000120366A publication Critical patent/JP2000120366A/en
Application granted granted Critical
Publication of JP4011209B2 publication Critical patent/JP4011209B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明は、土留め壁構築による立坑の築造工法に関するものである。
【0002】
【従来の技術】
立坑の築造工法としては、鋼矢板工法、SMW工法、地中連続壁工法、ケーソン工法などが挙げられる。
ところで、立坑において、大深度で地盤中の地下水が高い砂質土、粘性土の互層地盤の場合は、掘削底面にヒービング、ボイリング、被圧水による盤膨れの現象が起きる。このため、根入れを必要としないケーソン工法以外は、土留め壁の根入れ長さが長くなる場合が多い。
その根入れ長を低減する方法としては、地下水位低下工法や底盤の地盤改良工法がある。
【0003】
【発明が解決しようとする課題】
しかし、地下水位低下工法は、周辺地盤の沈下を伴うため、都市部における採用が困難であり、また、底盤の地盤改良工法は、大深度における工費が極めて高いなどの問題があった。
【0004】
そこで、本発明の目的は、大深度の立坑において、土留め壁の根入れ長さを短くしながら、地盤中の地下水位の低下を小さく抑えるとともに、工期短縮と工費軽減が図れるようにした立坑の築造工法を提供することにある。
【0005】
【課題を解決するための手段】
以上の課題を解決すべく請求項1記載の発明は、土中に土留め壁を構築してから立坑を築造する工法であって、土留め壁構築工程と、土留め壁により囲まれた立坑内部に水を導入して立坑内部を水中掘削する水中掘削工程と、立坑内部の掘削底面に透水材を投入する透水材投入工程と、透水層に水中ポンプを設置する水中ポンプ設置工程と、透水材投入により形成される透水層上に水中コンクリートを打設する仮設コンクリート打設工程と、立坑内部の水を排水する排水工程と、仮設コンクリート打設により形成される仮設の底版コンクリート上及び立坑内面に本設のコンクリートを打設する本設コンクリート打設工程と、からなり、排水工程において、透水層に設置した水中ポンプを必要に応じ稼働して透水層中の水を排水すること、を特徴としている。
【0006】
ここで、土留め壁は、鋼矢板工法、SMW工法、地中連続壁工法などの一般工法により構築する。
透水材としては、砕石や砂質土などが一般的であり、これにより形成される透水層は、集水層とも呼ばれる。
立坑内部の排水は、立坑内部に設置した水中ポンプにより行う。内部水位の低下に伴い、仮設底版コンクリートに対する揚圧力がコンクリートの崩壊をもたらす危険性が発生した場合は、透水層に設置した水中ポンプにより揚圧力を低減させる。
本設コンクリートは、立坑内面に逆巻きまたは順巻きの何れかによりコンクリートを打設してから、底版コンクリートを打設するのが望ましい。
【0007】
以上のように、請求項1記載の発明によれば、立坑の築造に際して、土留め壁により囲まれた立坑内部に水を導入して立坑内部を水中掘削した後、立坑内部の掘削底面に透水材を投入して透水層を形成し、その透水層上に水中コンクリートを打設して仮設の底版コンクリートを構築するので、地盤改良工ほどの工期と工費を必要としない。
そして、地盤改良工に比べ、土留め壁と仮設底版コンクリートとの密実な連結状態が得られて、地盤中の地下水位の低下を抑えられる。
さらに、このような仮設底版コンクリート構築後、立坑内部の排水を伴って、仮設の底版コンクリート上及び立坑内面に本設のコンクリートを打設することで、土留め壁構築による立坑の築造が完了する。
【0009】
また、請求項1記載の発明によれば、透水材投入工程と並行またはその後に続いて、透水層に水中ポンプを設置しておき、続く水中コンクリート打設による仮設底版コンクリート下の透水層に設置された水中ポンプにより排水するので、次の本設コンクリート打設に際して効果的な排水が行える。
【0010】
請求項2記載の発明は、請求項1記載の立坑の築造工法であって、透水材として砕石や砂質土を用いること、を特徴としている。
【0011】
このように、請求項2記載の発明によれば、請求項1記載の透水材として砕石や砂質土を用いるので、集水層としての透水層の形成が簡易に行える。
【0012】
請求項3記載の発明は、請求項1または2記載の立坑の築造工法であって、排水工程に続いて、立坑内部及び仮設底版コンクリート面のハツリやグリーンカットなどの清掃工程を設けること、を特徴としている。
【0013】
このように、請求項3記載の発明によれば、請求項1または2記載の排水工程に続く清掃工程で、立坑内部及び仮設底版コンクリート面を清掃して、次の本設コンクリート打設に備えられる。
【0014】
請求項4記載の発明は、請求項1、2または3記載の立坑の築造工法であって、排水工程を本設コンクリート打設工程まで並行させて、本設の底版コンクリートが必要強度に達したことを確認して透水層からの排水を終了すること、を特徴としている。
【0015】
このように、請求項4記載の発明によれば、請求項1、2または3記載の排水工程を本設コンクリート打設工程まで並行させて、本設の底版コンクリートが必要強度に達したことを確認して透水層からの排水を終了するので、被圧水などの揚圧力による仮設底版コンクリート崩壊の危険性のない所定の強度を具備した本設底版コンクリートによる立坑を築造できる。
【0016】
【発明の実施の形態】
以下に、本発明に係る立坑の築造工法の実施の形態例を図1から図6に基づいて説明する。
先ず、図1は本発明を適用した一例としての土留め壁構築による立坑の築造工法を示すもので、土留め壁構築工程を示した概略縦断面図、図2は続く水中掘削工程を示した概略縦断面図、図3は続く透水材投入及び水中ポンプ設置工程を示した概略縦断面図、図4は続く仮設コンクリート打設工程を示した概略縦断面図、図5は続く排水工程及び清掃工程と本設コンクリート打設工程を示した概略縦断面図、図6は続く本設コンクリート打設完了後の立坑完成状態を示した概略縦断面図である。
【0017】
本発明に係る立坑の築造工法は、この実施の形態例では、▲1▼土留め壁構築工程、▲2▼水中掘削工程、▲3▼透水材投入及び水中ポンプ設置工程、▲4▼仮設コンクリート打設工程、▲5▼排水工程及び清掃工程、▲6▼本設コンクリート打設工程の施工手順で行うものである。
【0018】
即ち、▲1▼土留め壁構築工程では、図1に示すように、土中1において、土留め壁11を、最終根切り底まで、例えば、鋼矢板工法、SMW工法、地中連続壁工法などの一般工法で構築する。この土留め壁11が立坑12の周壁となる。
なお、図中、2は任意の地層である。
【0019】
続いて、▲2▼水中掘削工程では、図2に示すように、土留め壁11により囲まれた土中に水13を導入して、その水中にて立坑12内部の掘削を行う。このような水中掘削は、土留め壁11の安全性を確保できる根入れ長さを残す位置まで行う。
ここで、水13の導入は図示しない適宜の給水設備を用いて行う。また、水中掘削についても、図示しない適宜の掘削機械を用いて行う。
【0020】
続いて、▲3▼透水材投入及び水中ポンプ設置工程では、図3に示すように、立坑12内部の水13中の掘削底面に砕石や砂質土などの透水材料(ドレーン材)14,14,14,…と複数(図示例では3基)の水中ポンプ15,15,15を設置して、集水層(透水層)16を形成する。
なお、水中ポンプ15,15,15には、図示のように、土留め壁11内面に沿って地表に導出する排水管17,17,17が接続されるとともに、電源供給用の図示しない電気コードが接続されている。
【0021】
そして、▲4▼仮設コンクリート打設工程では、図4に示すように、立坑12内部の水13中に水中コンクリートを打設して、集水層16上に仮設の底版コンクリート18を形成する。
【0022】
その後、▲5▼排水工程及び清掃工程と続く▲6▼本設コンクリート打設工程では、図5に示すように、立坑12内部に設けた水中ポンプ31を稼働して立坑12内の水13を排水管31から排水することにより、立坑12内の水13を必要深さまで減じる。
このように、立坑12内を必要深さに応じてドライアップしてから、壁面を清掃して土留め壁11の内面に沿って逆巻きまたは順巻きにより本設の内壁コンクリート21を打設する。また、必要に応じて集水層16中に埋設した水中ポンプ15を稼働させる。
ここで、集水層16中の水中ポンプ15を稼働するのは、本設コンクリート施工時の水位低下に伴い、仮設底版コンクリートに加わる揚圧力を低減し、仮設底版コンクリート崩壊を防止するためである。
【0023】
▲6▼本設コンクリート打設工程は、図6に示すように、仮設底版コンクリート18上に本設の底版コンクリート22を打設するまでであり、その本設底版コンクリート22が必要強度に達したことを確認したら、集水層16内の水中ポンプ15を停止する。
なお、本設底版コンクリート22の強度確認は、図示しない適宜の測定器具を用いて行う。
以上によって、立坑12が完成する。
【0024】
以上の通り、本発明に係る立坑の築造工法は、以下に挙げる特徴を有するものである。
(1)土留め壁11は、鋼矢板工法、SMW工法、地中連続壁工法などの一般工法の適用が可能である。
(2)立坑12の内部掘削は、根入れ長さが短い欠点を補うため、水中掘削としている。
(3)水中掘削終了後、土留め壁11内の掘削底面に砕石や砂質土などの透水材料14,14,14,…と水中ポンプ15,15,15を設置して、集水層(透水層16を形成している。
(4)地盤改良工の代わりとして、集水層16の上に仮設の底版コンクリート18として水中コンクリートを打設している。また、土留め壁11と仮設の底版コンクリート18との連結を密実にすることで、集水量を低減している。
(5)必要深さに応じた立坑12内部のドライアップを行い、逆巻きまたは順巻きの本設内壁コンクリート21を打設している。この時、必要に応じて集水層16中の水中ポンプ15を稼働させている。
【0025】
そして、本発明に係る立坑の築造工法により得られる主な効果は、以下の通りである。
(1)土留め壁11の根入れ長さが短くできるため、工期短縮・工費軽減できる。
(2)地盤改良工の代わりに、水中コンクリートを打設するため、地盤改良工ほどの工期と工費を必要としない。
(3)地盤改良工に比べ、土留め壁11との密実な連結が可能となるので、地盤中の地下水位の低下を小さくできる。
【0026】
なお、以上の実施の形態例においては、透水材投入と水中ポンプ設置を同工程としたが、本発明はこれに限定されるものではなく、透水材投入工程の後に水中ポンプ設置工程としても良い。
また、排水や清掃の手法等も任意であり、その他、具体的な細部構造等についても適宜に変更可能であることは勿論である。
【0027】
【発明の効果】
以上のように、請求項1記載の発明に係る立坑の築造工法によれば、大深度の立坑において、土留め壁の根入れ長さを短くしながら、立坑内部の水中掘削及び水中コンクリート打設により、工期短縮と工費軽減を達成することができ、また、地盤改良工に比べ、土留め壁と仮設底版コンクリートとの密実な連結状態が得られることにより、地盤中の地下水位の低下を小さくすることができる。
【0028】
また、請求項1記載の発明に係る立坑の築造工法によれば、立坑内部に設置する水中ポンプで排水し、水中コンクリート打設による仮設底版コンクリート下の透水層に設置した水中ポンプを必要に応じ稼働して透水層中の水を排水することにより、次の本設コンクリート打設に際して効果的な排水を行うことができるといった利点が得られる。
【0029】
請求項2記載の発明に係る立坑の築造工法によれば、透水材として砕石や砂質土を用いることにより、請求項1記載の発明により得られる効果に加えて、集水層としての透水層を簡易に形成することができるといった利点が得られる。
【0030】
請求項3記載の発明に係る立坑の築造工法によれば、立坑内部及び仮設底版コンクリートを清掃することにより、請求項1または2記載の発明により得られる効果に加えて、次の本設コンクリート打設に備えることができるといった利点が得られる。
【0031】
請求項4記載の発明に係る立坑の築造工法によれば、本設の底版コンクリートが必要強度に達したことを確認して透水層からの排水を終了することにより、請求項1、2または3記載の発明により得られる効果に加えて、被圧水などの揚圧力による崩壊の危険性のない所定の強度を具備した本設底版コンクリートによる立坑を築造することができるといった利点が得られる。
【図面の簡単な説明】
【図1】本発明を適用した一例としての土留め壁構築による立坑の築造工法を示すもので、土留め壁構築工程を示した概略縦断面図である。
【図2】図1の土留め壁構築工程に続く水中掘削工程を示した概略縦断面図である。
【図3】図2の水中掘削工程に続く透水材投入及び水中ポンプ設置工程を示した概略縦断面図である。
【図4】図3の透水材投入及び水中ポンプ設置工程に続く仮設コンクリート打設工程を示した概略縦断面図である。
【図5】図4の仮設コンクリート打設工程に続く排水工程及び清掃工程と本設コンクリート打設工程を示した概略縦断面図である。
【図6】図5に続く本設コンクリート打設完了後の立坑完成状態を示した概略縦断面図である。
【符号の説明】
1 土中
2 任意の地層
11 土留め壁
12 立坑
13 水
14 透水材料
15 水中ポンプ
16 透水層
17 排水管
18 仮設底版コンクリート
21 本設内壁コンクリート
22 本設底版コンクリート
31 水中ポンプ
32 排水管
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a shaft construction method by construction of earth retaining walls.
[0002]
[Prior art]
Examples of the shaft construction method include steel sheet pile method, SMW method, underground continuous wall method, caisson method and the like.
By the way, in the case of sandy soil and cohesive soil with deep ground and high groundwater in the shaft, phenomenon of swelling of the ground due to heaving, boiling, and pressurized water occurs on the bottom of excavation. For this reason, except for the caisson method, which does not require rooting, the length of the retaining wall is often long.
As a method for reducing the penetration depth, there are a groundwater level lowering method and a ground improvement method for the bottom.
[0003]
[Problems to be solved by the invention]
However, the groundwater level lowering method involves subsidence of the surrounding ground, so it is difficult to adopt it in urban areas, and the ground improvement method for the bottom has problems such as extremely high construction costs at large depths.
[0004]
Accordingly, an object of the present invention is to reduce the construction period and reduce the construction cost while reducing the groundwater level in the ground while reducing the length of the retaining wall in a deep shaft. Is to provide a construction method.
[0005]
[Means for Solving the Problems]
In order to solve the above-mentioned problems, the invention according to claim 1 is a method for constructing a shaft after constructing a retaining wall in the soil, and comprising a retaining wall construction step and a shaft surrounded by the retaining wall An underwater excavation process for introducing water into the shaft and excavating the interior of the shaft, a permeable material injection process for supplying a permeable material to the bottom of the digging inside the shaft, a submersible pump installation process for installing a submersible pump in the permeable layer, Temporary concrete placement process for placing underwater concrete on the water permeable layer formed by material input, drainage process for draining the water inside the shaft, and temporary bottom slab concrete formed by temporary concrete placement and the inner surface of the shaft A concrete placement process in which the concrete is placed in the water, and in the drainage process, the submersible pump installed in the permeable layer is operated as necessary to drain the water in the permeable layer. It is set to.
[0006]
Here, the earth retaining wall is constructed by a general construction method such as a steel sheet pile method, an SMW method, or an underground continuous wall method.
As the water permeable material, crushed stone or sandy soil is generally used, and the water permeable layer formed thereby is also called a water collecting layer.
The drainage inside the shaft is performed by a submersible pump installed inside the shaft. If there is a risk that the lifting pressure on the temporary bottom slab concrete will cause the concrete to collapse due to the lowering of the internal water level, the lifting pressure is reduced by the submersible pump installed in the permeable layer.
It is desirable to place the bottom slab concrete after the concrete is placed on the inner surface of the shaft by reverse winding or forward winding.
[0007]
As described above, according to the first aspect of the present invention, when a shaft is constructed, water is introduced into the shaft surrounded by the retaining wall and the inside of the shaft is excavated underwater, and then the water is permeable to the bottom of the excavation inside the shaft. The material is poured to form a water permeable layer, and underwater concrete is cast on the water permeable layer to construct a temporary bottom slab concrete. Therefore, the construction period and cost as much as the ground improvement work are not required.
And compared with the ground improvement work, the solid connection state of the earth retaining wall and the temporary bottom slab concrete is obtained, and the fall of the groundwater level in the ground can be suppressed.
Furthermore, after constructing such a temporary bottom slab concrete, the construction of the shaft by construction of the retaining wall is completed by placing the concrete on the temporary bottom slab concrete and the inner surface of the shaft along with drainage inside the shaft. .
[0009]
In addition, according to the first aspect of the present invention, the submersible pump is installed in the permeable layer in parallel with or subsequent to the permeable material charging step, and is installed in the permeable layer under the temporary bottom slab concrete by the subsequent underwater concrete placement. Since the water is discharged by the submersible pump, effective drainage can be performed at the time of the next permanent concrete placement.
[0010]
Invention of Claim 2 is the construction method of the shaft of Claim 1, Comprising: It uses crushed stone and sandy soil as a water-permeable material, It is characterized by the above-mentioned.
[0011]
Thus, according to the invention described in claim 2, since crushed stone and sandy soil are used as the water-permeable material according to claim 1, formation of the water-permeable layer as the water collecting layer can be easily performed.
[0012]
The invention according to claim 3 is the construction method of the shaft according to claim 1 or 2, wherein, following the drainage process, there is provided a cleaning process such as deburring and green cutting of the interior of the shaft and the temporary bottom slab concrete surface. It is a feature.
[0013]
Thus, according to the invention described in claim 3, in the cleaning process following the draining process described in claim 1 or 2, the inside of the shaft and the temporary bottom slab concrete surface are cleaned to prepare for the next permanent concrete placement. It is done.
[0014]
Invention of Claim 4 is the construction method of the shaft of Claim 1, 2, or 3, Comprising: The drainage process was made parallel to the permanent concrete casting process, and the permanent bottom slab concrete reached the required strength After confirming this, drainage from the permeable layer is terminated.
[0015]
As described above, according to the invention described in claim 4, the drainage process described in claim 1, 2 or 3 is made parallel to the permanent concrete placing process, and the fact that the bottom slab concrete of the permanent structure has reached the required strength is confirmed. Since the drainage from the permeable layer is completed after confirmation, a shaft made of permanent bottom slab concrete having a predetermined strength without risk of collapse of the temporary bottom slab concrete due to lift pressure such as pressurized water can be constructed.
[0016]
DETAILED DESCRIPTION OF THE INVENTION
Below, the embodiment of the construction method of the shaft which concerns on this invention is described based on FIGS.
First, FIG. 1 shows the construction method of a shaft by construction of a retaining wall as an example to which the present invention is applied, a schematic longitudinal sectional view showing a retaining wall construction process, and FIG. 2 shows a subsequent underwater excavation process. FIG. 3 is a schematic longitudinal sectional view showing a subsequent permeable material charging and submersible pump installation process, FIG. 4 is a schematic longitudinal sectional view showing a subsequent temporary concrete placing process, and FIG. 5 is a subsequent draining process and cleaning. FIG. 6 is a schematic vertical cross-sectional view showing a shaft completion state after completion of the continuous concrete pouring operation.
[0017]
In this embodiment, the shaft construction method according to the present invention includes (1) a retaining wall construction process, (2) an underwater excavation process, (3) a permeable material input and an underwater pump installation process, and (4) temporary concrete. This is the construction procedure of the placing process, (5) draining process and cleaning process, and (6) permanent concrete placing process.
[0018]
That is, in the (1) earth retaining wall construction process, as shown in FIG. 1, in the soil 1, the earth retaining wall 11 is moved to the final root bottom, for example, the steel sheet pile method, the SMW method, the underground continuous wall method. It is constructed by general construction methods such as. This earth retaining wall 11 becomes the peripheral wall of the shaft 12.
In the figure, 2 is an arbitrary formation.
[0019]
Subsequently, (2) in the underwater excavation step, as shown in FIG. 2, water 13 is introduced into the soil surrounded by the retaining wall 11, and the inside of the shaft 12 is excavated in the water. Such underwater excavation is performed up to a position where a penetration length that can ensure the safety of the retaining wall 11 is left.
Here, the introduction of the water 13 is performed using an appropriate water supply facility (not shown). Also, underwater excavation is performed using an appropriate excavating machine (not shown).
[0020]
Subsequently, in the step (3) of introducing the permeable material and installing the submersible pump, as shown in FIG. 3, permeable materials (drain materials) 14 and 14 such as crushed stone and sandy soil are formed on the bottom of the excavation in the water 13 inside the shaft 12. , 14,... And a plurality (three in the illustrated example) of submersible pumps 15, 15, 15 are installed to form a water collection layer (water-permeable layer) 16.
The submersible pumps 15, 15, 15 are connected to drain pipes 17, 17, 17 that lead to the ground surface along the inner surface of the retaining wall 11, as shown in the figure. Is connected.
[0021]
Then, in (4) the temporary concrete placing step, as shown in FIG. 4, underwater concrete is placed in the water 13 inside the shaft 12 to form a temporary bottom slab concrete 18 on the water collection layer 16.
[0022]
After that, in (5) draining process and cleaning process, (6) in the concrete placing process, as shown in FIG. 5, the submersible pump 31 provided in the shaft 12 is operated to drain the water 13 in the shaft 12. By draining from the drain pipe 31, the water 13 in the shaft 12 is reduced to the required depth.
Thus, after the inside of the shaft 12 is dried up according to the required depth, the wall surface is cleaned, and the inner wall concrete 21 is placed along the inner surface of the retaining wall 11 by reverse winding or forward winding. Moreover, the submersible pump 15 embed | buried in the water collection layer 16 is operated as needed.
Here, the reason why the submersible pump 15 in the water collecting layer 16 is operated is to reduce the lifting pressure applied to the temporary bottom slab concrete and prevent the temporary bottom slab concrete from collapsing with the decrease in the water level during the construction of the concrete. .
[0023]
(6) As shown in FIG. 6, the permanent concrete placing process is until the permanent bottom slab concrete 22 is placed on the temporary bottom concrete 18 and the permanent bottom slab concrete 22 has reached the required strength. If confirmed, the submersible pump 15 in the water collection layer 16 is stopped.
In addition, the strength confirmation of the permanent bottom slab concrete 22 is performed using an appropriate measuring instrument (not shown).
Thus, the shaft 12 is completed.
[0024]
As described above, the shaft construction method according to the present invention has the following characteristics.
(1) For the retaining wall 11, a general construction method such as a steel sheet pile method, an SMW method, or an underground continuous wall method can be applied.
(2) The internal excavation of the vertical shaft 12 is underwater excavation in order to compensate for the short defect of the penetration depth.
(3) After completion of underwater excavation, water-permeable materials 14, 14, 14,... And crushed stones, sandy soil, etc. and underwater pumps 15, 15, 15 are installed on the bottom of excavation in the retaining wall 11, and a water collecting layer ( A water permeable layer 16 is formed.
(4) In place of ground improvement work, underwater concrete is placed on the water collection layer 16 as a temporary bottom slab concrete 18. Further, the amount of collected water is reduced by making the connection between the earth retaining wall 11 and the temporary bottom slab concrete 18 dense.
(5) The inside of the shaft 12 is dry-up according to the required depth, and the reversely or forwardly wound inner wall concrete 21 is placed. At this time, the submersible pump 15 in the water collection layer 16 is operated as necessary.
[0025]
The main effects obtained by the shaft construction method according to the present invention are as follows.
(1) Since the length of the retaining wall 11 can be shortened, the construction period can be shortened and the construction cost can be reduced.
(2) Since underwater concrete is placed instead of ground improvement work, the construction period and construction cost are not as high as those for ground improvement work.
(3) Since the solid connection with the retaining wall 11 is possible as compared with the ground improvement work, the decrease in the groundwater level in the ground can be reduced.
[0026]
In the above embodiment, the water-permeable material and the submersible pump are installed in the same process. However, the present invention is not limited to this, and the water-permeable material may be installed after the water-permeable material is introduced. .
In addition, drainage and cleaning methods are arbitrary, and it is needless to say that other detailed structures can be appropriately changed.
[0027]
【The invention's effect】
As described above, according to the shaft construction method according to the first aspect of the present invention, in the deep shaft, the underwater excavation and underwater concrete placement inside the shaft are performed while shortening the length of the retaining wall. Therefore, the construction period can be shortened and the construction cost can be reduced, and the groundwater level in the ground can be lowered by obtaining a more solid connection between the retaining wall and the temporary bottom slab concrete than the ground improvement work. Can be small.
[0028]
Moreover, according to the construction method of the shaft according to the invention of claim 1, the submersible pump installed in the permeable layer under the temporary bottom slab concrete by draining with the submersible pump installed in the shaft and as needed is installed. By operating and draining the water in the permeable layer, there is an advantage that the drainage can be effectively performed when the next concrete is placed.
[0029]
According to the shaft construction method according to the invention of claim 2, by using crushed stone or sandy soil as the water permeable material, in addition to the effect obtained by the invention of claim 1, the water permeable layer as the water collecting layer Can be formed easily.
[0030]
According to the shaft construction method according to the invention described in claim 3, by cleaning the inside of the shaft and the temporary bottom slab concrete, in addition to the effect obtained by the invention according to claim 1 or 2, The advantage that it can prepare for installation is acquired.
[0031]
According to the shaft construction method according to the invention of claim 4, it is confirmed that the bottom slab concrete of the main structure has reached the required strength, and drainage from the permeable layer is terminated, whereby claim 1, 2, or 3 In addition to the effects obtained by the described invention, there is an advantage that it is possible to build a shaft made of permanent bottom slab concrete having a predetermined strength without risk of collapse due to lifting pressure such as pressurized water.
[Brief description of the drawings]
FIG. 1 is a schematic longitudinal sectional view showing a retaining wall construction process, showing a shaft construction method by construction of retaining walls as an example to which the present invention is applied.
2 is a schematic longitudinal sectional view showing an underwater excavation process following the retaining wall construction process of FIG. 1; FIG.
3 is a schematic longitudinal sectional view showing a permeable material charging step and a submersible pump installation step subsequent to the submerged excavation step of FIG. 2. FIG.
4 is a schematic longitudinal sectional view showing a temporary concrete placing process following the water-permeable material charging and submersible pump installing process of FIG. 3; FIG.
5 is a schematic longitudinal sectional view showing a draining process, a cleaning process, and a permanent concrete placing process following the temporary concrete placing process of FIG. 4;
FIG. 6 is a schematic longitudinal sectional view showing a shaft completion state after completion of permanent concrete pouring following FIG. 5;
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Underground 2 Arbitrary stratum 11 Earth retaining wall 12 Vertical shaft 13 Water 14 Water permeable material 15 Submersible pump 16 Water permeable layer 17 Drain pipe 18 Temporary bottom slab concrete 21 Main wall concrete 22 Main bottom slab concrete 31 Submersible pump 32 Drain pipe

Claims (4)

土中に土留め壁を構築してから立坑を築造する工法であって、土留め壁構築工程と、土留め壁により囲まれた立坑内部に水を導入して立坑内部を水中掘削する水中掘削工程と、立坑内部の掘削底面に透水材を投入する透水材投入工程と、透水層に水中ポンプを設置する水中ポンプ設置工程と、透水材投入により形成される透水層上に水中コンクリートを打設する仮設コンクリート打設工程と、立坑内部の水を排水する排水工程と、仮設コンクリート打設により形成される仮設の底版コンクリート上及び立坑内面に本設のコンクリートを打設する本設コンクリート打設工程と、からなり、排水工程において、透水層に設置した水中ポンプを必要に応じ稼働して透水層中の水を排水すること、を特徴とする立坑の築造工法。  It is a method of building a shaft after building a retaining wall in the soil. The retaining wall building process and underwater excavation in which water is introduced into the shaft surrounded by the retaining wall to excavate the shaft. The process, the permeable material injection process for introducing the permeable material to the bottom of the excavation inside the shaft, the submersible pump installation process for installing the submersible pump in the permeable layer, and placing the underwater concrete on the permeable layer formed by the introduction of the permeable material Temporary concrete placing process, draining process for draining the water inside the shaft, and permanent concrete placing process for placing the concrete on the temporary bottom slab concrete and the inner surface of the shaft formed by the temporary concrete placement A construction method of a shaft, characterized in that, in the drainage process, a submersible pump installed in the permeable layer is operated as necessary to drain the water in the permeable layer. 透水材として砕石や砂質土を用いること、を特徴とする請求項1記載の立坑の築造工法。  The method for constructing a shaft according to claim 1, wherein crushed stone or sandy soil is used as the water permeable material. 排水工程に続いて、立坑内部及び仮設底版コンクリート面のハツリやグリーンカットなどの清掃工程を設けること、を特徴とする請求項1または2記載の立坑の築造工法。  The shaft construction method according to claim 1 or 2, characterized in that, following the drainage step, a cleaning step such as chipping or green cutting of the inside of the shaft and the temporary bottom slab concrete surface is provided. 排水工程を本設コンクリート打設工程まで並行させて、本設の底版コンクリート打設終了後、底版コンクリートが必要強度に達したことを確認して透水層からの排水を終了すること、を特徴とする請求項1、2または3記載の立坑の築造工法。  It is characterized by paralleling the drainage process to the permanent concrete casting process, and after draining the permanent bottom slab concrete, confirming that the bottom slab concrete has reached the required strength and ending drainage from the permeable layer. The shaft construction method according to claim 1, 2, or 3.
JP28975798A 1998-10-12 1998-10-12 Construction method of shaft Expired - Fee Related JP4011209B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28975798A JP4011209B2 (en) 1998-10-12 1998-10-12 Construction method of shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28975798A JP4011209B2 (en) 1998-10-12 1998-10-12 Construction method of shaft

Publications (2)

Publication Number Publication Date
JP2000120366A JP2000120366A (en) 2000-04-25
JP4011209B2 true JP4011209B2 (en) 2007-11-21

Family

ID=17747368

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28975798A Expired - Fee Related JP4011209B2 (en) 1998-10-12 1998-10-12 Construction method of shaft

Country Status (1)

Country Link
JP (1) JP4011209B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009084919A (en) * 2007-10-01 2009-04-23 Kajima Corp Ground excavating method
JP5257210B2 (en) * 2009-04-08 2013-08-07 鹿島建設株式会社 Ground excavation method
CN104164877B (en) * 2014-08-15 2016-01-20 葛洲坝集团基础工程有限公司 A kind of dyke toe underwater concrete construction method
CN113982012B (en) * 2021-11-05 2023-06-20 中铁工程装备集团有限公司 Open caisson construction method and construction device
CN114687430A (en) * 2022-04-25 2022-07-01 中国十七冶集团有限公司 Construction method of high-fall drop well outside small compartment

Also Published As

Publication number Publication date
JP2000120366A (en) 2000-04-25

Similar Documents

Publication Publication Date Title
CN101761083A (en) Underground continuous wall obstacle clearing construction method for traversing ultra-thick obstacle
CN112695803B (en) Supporting and water-stopping construction method for pipe-jacking working well and pipe ditch on beach
CN111733842A (en) Cofferdam construction method and cofferdam structure
KR20130013287A (en) Wet-type constructing method of pier foundation
JP4011209B2 (en) Construction method of shaft
JP4011212B2 (en) Construction method of shaft
CN109736337B (en) Precipitation device and method for guaranteeing integrity of cushion layer through sediment flowing treatment of foundation elevator shaft sump
CN110144871A (en) A kind of dark creek processing construction method
JP2000087361A (en) Construction method of underground structure
JP2726611B2 (en) How to set up an open caisson
JP2726621B2 (en) Caisson laying method and caisson blade structure
JP3224008B2 (en) Underwater ground improvement method
JP2000130066A (en) Construction method for vertical shaft
JP3002188B1 (en) Ground excavation method
JP2809105B2 (en) How to build an underground tank
JP2004204524A (en) Consolidation-promotion reclamation construction method and consolidation-promotion reclamation structure
CN115354704B (en) Water seepage grooving treatment method for karst foundation of fan foundation of plain wind farm
JP2784314B2 (en) How to set up an open caisson
CN219952005U (en) Backfill district foundation ditch drainage device
CN114607187B (en) Shaft type underground parking garage construction method of cast-in-situ supporting structure under slurry
CN114753231B (en) Frame beam lattice bridge structure crossing underground pipeline and construction method thereof
JP3656366B2 (en) Underground structure construction method
JPH0465932B2 (en)
CN116163309A (en) Pit-in-pit construction method in coastal silt foundation pit
JP3904294B2 (en) Underground excavation method and underground structure construction method using this method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050509

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070531

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070605

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070802

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070904

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070905

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100914

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100914

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130914

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees