JP3990589B2 - Reinforcing structure for shaft opening - Google Patents
Reinforcing structure for shaft opening Download PDFInfo
- Publication number
- JP3990589B2 JP3990589B2 JP2002115224A JP2002115224A JP3990589B2 JP 3990589 B2 JP3990589 B2 JP 3990589B2 JP 2002115224 A JP2002115224 A JP 2002115224A JP 2002115224 A JP2002115224 A JP 2002115224A JP 3990589 B2 JP3990589 B2 JP 3990589B2
- Authority
- JP
- Japan
- Prior art keywords
- segment
- opening
- gate
- shaft
- reinforcing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、複数のセグメントを地上で連結して組み立て、組み立てたセグメントを地下に圧入して立坑を沈設し、該立坑から掘削機を発進させてトンネルを形成するときに、掘削機の発進口や到達口を構成する、開閉可能なゲート(シャッタともいう)を備える開口部の補強構造に関するものである。
【0002】
【従来の技術】
シールド掘削機等の掘削機によってトンネルや地下空間を構築する場合、まず、トンネルを掘削しようとするルートの両端部あるいは中間部に、掘削機を発進、到達させるための立坑(発進立坑及び到達立坑)を構築し、掘削機を発進立坑の内部へ降ろし、降ろした掘削機を発進立坑から発進させて所定のルートを掘削した後に到達立坑へ到達させる。
【0003】
立坑の構築には種々の工法があり、例えば、アーバンリング工法(商品名)等が知られている。構築する立坑の大深度化に伴ない、立坑を構成する土留め壁の外部には非常に大きな土圧や水圧が作用し、掘削機を発進させるために土留め壁を開口する際に、その部分の土砂が崩壊して立坑内に流入し、掘削機を発進させることができない問題がある。
【0004】
そこで、従来は、開口時に周囲の地山が崩壊するのを防止するためあるいは地下水の立坑内への流入を防止するために、発進口の前方に地盤改良部あるいは凍結部を形成する方法が行なわれている(以下、「先行技術1」という)。
【0005】
しかし、先行技術1は、地盤改良部や凍結部の形成に多くの費用と工期を必要とするといった問題がある。
【0006】
このため、発進口周囲の地盤改良工事をせずに掘削機を発進することができる工法が求められ、特開平10−205280号公報には下記に示すゲート(シャッタ)を用いるトンネル施工方法が開示されている。該工法において、発進立坑を構成する土留め壁(構築壁等ともいう)に設けた発進口は、掘削機により掘削可能な封止材により封鎖されている。更に、発進口には開閉可能なゲートが設けられている。ゲートは、発進立坑の周囲の土圧及び水圧を支持できる強度を備える。更に、掘削機の発進の際に発進立坑内に形成される圧力室の充填材が、ゲートの開放時にゲートと構築壁との間から漏れるのを防止するための漏出防止部材がゲートに設けられている。ゲートと掘削機との間に構築壁外部の圧力に対抗する圧力室を形成し、その後、ゲートを移動して発進口を開放し、掘削機により発進口を封鎖している封止材を掘削して掘削機を発進立坑の外に向けて発進させる(以下、「先行技術2」という)。
【0007】
【発明が解決しようとする課題】
しかしながら、先行技術2には下記の問題があった。
【0008】
円筒状の立坑には鉛直方向及び円周方向の力が加わる。まず、そのうちの鉛直方向の力については、地上で組み立てられたセグメント(土留め壁)には水中掘削されながらジャッキにより地中に圧入されるため鉛直方向のジャッキ圧が加わる。従って、セグメントに組み込まれた開口部にも、鉛直方向のジャッキ圧が加わる。ただし、前記ジャッキ圧は、立坑沈設時のみ加わる荷重であり、沈設完了後はこのような荷重は加わらない。
【0009】
次に、円周方向については、地中深く圧入された沈設後のセグメント(土留め壁)は、土留め外周の土圧及び水圧を受けることになり、円筒状立坑ではそれは土留め部材の圧縮力となって部材、開口部に加わる。
【0010】
更に、立坑の開口部は開閉ゲートを備え、掘削機を発進する際には開口部を開放するためにゲートを引き上げる。このときゲートの直上方部のセグメントは引き上げたゲートが接触しないようにしなければならない。そのため、位置や大きさを調整して配置しなければならず、例えば、通常のセグメントよりも桁高さ(厚さ)を低く(薄く)しなければならない。
【0011】
しかしながら、セグメントの桁高さを低くすれば剛性が不足し、立坑を沈設するときに立坑に加わるジャッキ圧に対して開口部及び周囲の剛性が不足するという問題があった。
【0012】
従って、本発明の目的は、上述の課題を解決し、立坑沈設時の圧力及び土留め外周の土圧及び水圧に対抗し、開口部及びその周辺の剛性を十分に確保することができ、且つ、ゲート引き上げの邪魔とならず、良好な作業性を確保することができる立坑開口部の補強構造を提供することにある。
【0013】
【課題を解決するための手段】
請求項1記載の発明は、ゲートを備える開口部を配置して複数のセグメントを組み立て、組み立てたセグメントを地中に圧入して沈設する立坑における開口部の補強構造において、前記開口部の直上方部のセグメントが、引き上げ時の前記ゲートと接触しないように配置された第1セグメントと、前記第1セグメントと重ねて配置された補強用の第2セグメントとからなる二重構造となっており、前記第2セグメントは、前記第1セグメントから撤去可能に取り付けられていることに特徴を有するものである。
【0014】
請求項2記載の発明は、前記開口部の左右両側及び下部に補強部材が配置されたことに特徴を有するものである。
請求項3記載の発明は、前記開口部の左右両側及び下部に補強部材が配置され、更に、前記開口部の上部には、前記第2セグメントを撤去した後の前記開口部の上部を補強するための補強梁が、前記開口部の左右両側の前記補強部材の上部間を連結して、前記ゲートと接触しないように取り付けられたことに特徴を有するものである。
【0015】
請求項4記載の発明は、立坑沈設時にセグメントに加わる荷重を前記開口部を閉塞している前記ゲートに伝達するための伝達手段を備え、前記伝達手段は、前記二重構造のセグメントと前記開口部を閉塞している前記ゲートとの間に介在して配置されることに特徴を有するものである。
【0016】
本発明においては、立坑開口部の直上方部のセグメントを、第1セグメント及び第2セグメントからなる二重構造とする。通常のセグメントを開口部の直上方部に配置したのでは開口部のゲート引き上げ時にゲートと接触してしまうので、第1セグメントは、通常のセグメントよりも薄い桁高さ(厚さ)とし、且つ、ゲート引き上げ時にゲートと接触しないように配置する。第2セグメントは、第1セグメントの内側に重ねて配置して第1セグメントを補強する。第1と第2セグメントとを重ねた二重構造のセグメントの厚さは、他のセグメントと同等あるいはそれ以上の桁高さ(厚さ)を有するので、二重構造のセグメントは、立坑沈設時に加わる鉛直のジャッキ圧に対抗し剛性を確保することができるとともに、立坑に加わる土圧、水圧による円周方向の力にも対抗することができる。第2セグメントは、沈設終了後、ゲートを引き上げる前に第1セグメントから取り外すので引き上げるゲートと接触しない。
【0017】
また、二重構造のセグメントと開口部閉塞時のゲートとの間に、荷重伝達手段としての部材を配置し、該部材を介してジャッキ圧を開口部閉塞時のゲートによって受け止める。
【0018】
更に、開口部の左右両側及び上下に補強部材を配置する。開口部上部は、ゲート引上げ前までは二重構造のセグメントが補強部材の役割を担うが、ゲート引上げ以降は取り外された第2セグメントに変わる補強部材としてゲートと接触しない立坑の内部側の位置に、左右両側の補強部材の上部間にわたり補強梁を連結して取り付ける。このように、開口部の左右及び上下に補強部材を配置することにより、立坑の沈設後、第2セグメント撤去後の立坑に加わる水圧、土圧による円周方向の力に対抗することができる。
【0019】
【発明の実施の形態】
次に、本発明の実施の形態を図面を参照しながら説明する。
【0020】
図1〜14は、本発明の実施の形態に係る図面であり、図1は、立坑及び開口部を示す正面図、図2は、図1のA−A線断面図、図3は、図1のB−B線断面図、図4は、図1のC−C線断面図、図5は、開口部をゲートによって閉塞時の立坑及び開口部を示す断面図、図6は、補強梁を設置後且つゲート閉塞時の立坑開口部の断面図、図7は、補強梁を設置後且つゲート引き上げ時(開口部開放時)の立坑開口部の断面図、図8は、補強梁設置後且つゲート引上時の図1のD−D線断面図、図9は、図6の部分拡大図、図10は、図7の部分拡大図、図11は、二重構造のセグメントを構成する第1セグメントを示す断面図、図12は、正面図、図13は、二重構造のセグメントを構成する第2セグメントを示す断面図、図14は正面図である。
【0021】
円筒状の立坑1の構築は、複数の鋼製セグメント2を地上で円筒状に組み立て、組み立てたセグメント(リング)2を地下に圧入して沈設するアーバンリング工法等により行われる。セグメント2を組み立てるときに同時に開閉ゲート6を備える開口部3も組み立てられる。ゲート6は開口部3を閉塞した状態で組み立てられる。以下、説明のため、個々のセグメント(セグメントピース)をセグメント2、組み立てたセグメントリング(土留め壁)をリング20とする。セグメント2は鋼製のほか、コンクリート製等が用いられる。セグメント2は、立坑1が円筒形のためやや彎曲している。
【0022】
複数のセグメント2により組み立てられたリング20に配置される開口部3は、図1、及び図5、図7〜10に示すように、四角形の枠材4と、枠材4に設けられた四角形の開口5とを備えている。開口5は、シールド掘削機30が通過するのに十分な大きさに開けられている。枠材4の上部には開閉ゲート6が挿通可能なスリット11が設けられ、ゲート6はスリット11を通過して上方に引き上げられるようになっている。
【0023】
開口部3の直上方部のセグメントは、図1、図2、図6、図9、図11〜14に示すように、第1セグメント21と第2セグメント22とからなる二重構造となっている。図11、図12に示すように、第1セグメント21は、上下の主桁13、13、左右の側板14、14、側板14、14間の複数の縦リブ15、立坑の外周面を構成するスキンプレート16からなっており、縦リブ15の立坑内部側はL字状に折れ曲げられアングル部15aを形成している。図13、図14に示すように、第2セグメント22は、上下の主桁23、23、左右の側板24、24、側板24、24間の複数の縦リブ25からなっており、縦リブ25の立坑外部側はL字状に折れ曲げられアングル部25aを形成している。17、27は、ボルト孔である。第1、第2セグメントの側板14、24及び縦リブ15、25は、ゲートの引上げ位置に対応して桁高さが形成されている。すなわち、第1セグメント21は、ゲートの引上げ時に支障しない桁高に制約され、そして、第2セグメント22は、第1セグメント21の内側に重ねて取り付け可能なように大きさ及び形状が形成され、また、第1セグメント21と第2セグメント22の合計した桁高は、枠材4の厚さ以下に制約される。
【0024】
第2セグメント22を第1セグメント21の内側に配置し、縦リブ15、25のアングル部15a、25aに設けられたボルト孔を介してボルト結合により第2セグメント22を第1セグメント21に取り付ける。第1及び第2セグメント21、22からなる二重構造のセグメントは、通常のセグメント2と同等或いはそれ以上の高さ、すなわち、厚さとなっており、このような二重構造となっているため、立坑1の沈設時においては、通常のセグメント2と同等に沈設時のジャッキ圧に耐えることができる補強構造となっている。
【0025】
図1中にゲート6を引き上げる範囲を符号Hにより示す。第1セグメント21をリング20に組み立てるときには、ゲート6の引き上げ時にゲート6と接触しないように、配置位置及び桁高さを調整して組み立てられる。第1セグメント21から第2セグメント22を取り外せば、引き上げたゲート6は第1セグメント21と接触しない。このような二重構造の第1、第2セグメント21、22は、開口部3の直上方部において、ゲート6を引き上げる範囲Hより広い範囲、すなわち、ゲート6の高さ及び幅を超える範囲に配置しないと、ゲート6の引き上げ時の障害となるので、図1の実施例では複数枚、具体的には高さ方向に4枚づつ、幅方向に2枚づつの合計8枚配置されている。第2セグメント22を第1セグメント21から取り外すことにより、第2セグメント取り外し後の第1セグメントと接触せずにゲート6を引き上げることができる。
【0026】
次に、開口部の周囲の補強について説明する。
【0027】
図1に示すように、開口部3を構成する枠材4の左右両側には、枠材4の外側に補強部材7、8が鉛直に配設されている。更に、図1、図4〜5に示すように、枠材4の下側には、枠材4の外側に補強部材9が水平に設けられている。下側の補強部材9はリング20とほぼ同じ曲率で彎曲している。一方、開口部3の直上方部には、上述の二重構造の第1、第2セグメント21、22が配されているが、開口部3の上部には、左右両側の補強部材9の上部間を連結して、図6〜8に示すように、直線状の補強梁10が、ゲート6と接触しない立坑1(リング20)の内部側の位置に連結して取り付けられている。補強梁10は、第2セグメント22を撤去する際及び撤去後のリング20に加わる円周方向の力に対抗し、開口部3を補強する。
【0028】
次に、ゲートにジャッキ圧を伝達する手段について説明する。
【0029】
開口部3は、セグメント2をリング20に組み立てるときに、ゲート6を閉塞した状態で組み立てられる。図5、図6、図9に示すように、閉塞したゲート6に、セグメント2(リング20)に伝わったジャッキ圧を伝達する手段として、伝達部材12が取り付けられている。伝達部材12は、その上部が二重構造のセグメント21及び22に取り付けられ、その下端は閉塞した状態のゲート6の上端と当接して取り付けられ、ゲート6を固定している。このようにしてゲート6を固定した伝達部材12は、立坑1の施工時(アーバンリング工法)に、ジャッキ圧により推力及び垂直方向の軸力をゲート6に伝達する部材として作用し開口部3を補強する作用を有する。伝達部材12は撤去可能となっており、ゲート6の引き上げ時には、図7、図10に示すように撤去する。
【0030】
[作用]
次に、本発明の開口部の補強構造を備える発進立坑によるシールド掘削機の発進工程を説明する。
【0031】
▲1▼ 地上において、開口部3の直上方部に第1セグメント21及び第2セグメント22からなる二重構造のセグメントを備えるリング20を組み立てる。開口部3が備えるゲート6は、組み立て時には閉塞されている。
【0032】
▲2▼ 第1セグメント21及び第2セグメント22からなる二重構造のセグメントの下部に伝達部材12を取り付ける。伝達部材12の下端は開口部3を閉塞しているゲート6の上端と当接させてゲート6を固定する。
【0033】
▲3▼ アーバンリング工法によりリング20を沈設する。第1セグメント21及び第2セグメント22からなる二重構造のセグメント及び伝達部材12の補強作用により、開口部3は沈設時のジャッキ圧による荷重及び水圧、土圧に対して強固に対抗する
▲4▼ 沈設後、開口部3の内側に、エントランスパッキン28を備えるエントランス金枠29を取り付ける。次いで、開口部3の上部に、補強梁10を補強部材7と8との間に連結して取り付ける。
【0034】
▲5▼ 次いで、伝達部材12及び第1セグメント21にボルト止めされている第2セグメント22を、ボルトを外して第1セグメント21から撤去する。第2セグメント22を撤去した後も補強梁10の作用により、開口部3の上部は、撤去後のリング20に加わる水圧、土圧による円周方向の力に対抗し、開口部3を補強する。
【0035】
▲6▼ エントランス金枠29にシールド掘削機30を装着する。次いで、ゲート6をチェーンブロック(図示せず)等により引き上げ、そして、シールド掘削機30を発進させる。
【0036】
【発明の効果】
以上説明したように、本発明によれば、以下に示す有用な効果がもたらされる。
【0037】
▲1▼ 開口部の直上方部に二重構造のセグメントを配置し、アーバンリング工法による沈設時のジャッキ圧による一時的な荷重に対しては二重構造のセグメントにより開口部を補強し、沈設後のシールド掘削機発進時には第2セグメントを撤去してゲート引き上げ可能となるので、作業効率を損なうことなく有効に開口部を補強することができる。
【0038】
▲2▼ 開口部の左右及び上下を補強部材、補強梁によって補強するため、ゲート部の荷重はその部分だけに加わる荷重を考えればよいことになるのでゲートへの荷重負担が減りゲートの板厚を薄くすることができる。
【0039】
▲3▼ 二重構造のセグメントに加わる荷重をゲートに伝達する伝達手段を設けたので、沈設時のジャッキ推力及び垂直方向の軸力をゲートによって受けることができる。
【図面の簡単な説明】
【図1】本発明の実施の形態に係るゲートによって開口部が閉塞されている状態の立坑及び開口部を示す正面図である。
【図2】本発明の実施の形態に係るゲートによって開口部が閉塞され且つ補強梁が設置される前の図1のA−A線断面図である。
【図3】本発明の実施の形態に係る図1のB−B線断面図である。
【図4】本発明の実施の形態に係る図1のC−C線断面図である。
【図5】本発明の実施の形態に係るゲートによって開口部が閉塞されている状態の立坑及び開口部を示す断面図である。
【図6】本発明の実施の形態に係るゲートによって開口部が閉塞され且つ補強梁が設置された後の立坑及び開口部を示す断面図である。
【図7】本発明の実施の形態に係る補強梁が設置された後且つゲートを引き上げたときの立坑及び開口部を示す断面図である。
【図8】本発明の実施の形態に係る補強梁が設置された後且つゲートを引き上げたときの図1のD−D線断面図である。
【図9】本発明の実施の形態に係る図6の部分拡大図である。
【図10】本発明の実施の形態に係る図7の部分拡大図である。
【図11】本発明の実施の形態に係る二重構造のセグメントを構成する第1セグメントを示す断面図である。
【図12】本発明の実施の形態に係る図11の正面図である。
【図13】本発明の実施の形態に係る二重構造のセグメントを構成する第2セグメントを示す断面図である。
【図14】本発明の実施の形態に係る図13の正面図である。
【符号の説明】
1 立坑
2 セグメント
3 開口部
4 枠材
5 開口
6 ゲート
7、8、9 開口部補強部材
10 補強梁
11 スリット
12 伝達部材
13 主桁
14 側板
15 縦リブ
16 スキンプレート
17 ボルト孔
20 リング
21 第1セグメント
22 第2セグメント
23 主桁
24 側板
25 縦リブ
27 ボルト孔
28 エントランスパッキン
29 エントランス金枠
30 シールド掘削機[0001]
BACKGROUND OF THE INVENTION
The present invention assembles a plurality of segments connected on the ground, presses the assembled segments into the basement, sinks a shaft, starts an excavator from the shaft, and forms a tunnel to form a start port of the excavator The present invention relates to a reinforcing structure of an opening provided with an openable / closable gate (also referred to as a shutter) that constitutes an arrival port.
[0002]
[Prior art]
When constructing a tunnel or underground space with an excavator such as a shield excavator, first, a shaft (starting shaft and reaching shaft) for starting and reaching the excavator at both ends or an intermediate portion of the route to be excavated through the tunnel. ), The excavator is lowered into the start shaft, the lowered excavator is started from the start shaft, and a predetermined route is excavated to reach the destination shaft.
[0003]
There are various methods for constructing a shaft, for example, an urban ring method (trade name) and the like are known. Along with the deepening of the shaft to be built, very large earth pressure and water pressure act on the outside of the retaining wall that constitutes the shaft, and when the retaining wall is opened to start the excavator, There is a problem that part of the earth and sand collapses and flows into the shaft, and the excavator cannot be started.
[0004]
Therefore, conventionally, a method of forming a ground improvement part or a frozen part in front of the starting port has been performed in order to prevent the surrounding natural ground from collapsing at the time of opening or to prevent inflow of groundwater into the shaft. (Hereinafter referred to as “
[0005]
However, the
[0006]
For this reason, there is a need for a construction method that can start an excavator without performing ground improvement work around the start opening. JP-A-10-205280 discloses a tunnel construction method using a gate (shutter) described below. Has been. In the construction method, a start port provided in a retaining wall (also referred to as a construction wall) constituting a start shaft is sealed with a sealing material that can be excavated by an excavator. Furthermore, a gate that can be opened and closed is provided at the start opening. The gate has a strength capable of supporting earth pressure and water pressure around the start shaft. In addition, the gate is provided with a leakage prevention member for preventing the pressure chamber filling material formed in the start shaft when the excavator starts from leaking between the gate and the building wall when the gate is opened. ing. A pressure chamber that opposes the pressure outside the building wall is formed between the gate and the excavator, and then the gate is moved to open the start opening, and the excavator seals the start opening. The excavator is then started out of the starting shaft (hereinafter referred to as “
[0007]
[Problems to be solved by the invention]
However, Prior
[0008]
Cylindrical shafts are subjected to vertical and circumferential forces. First, regarding the vertical force, vertical jacking pressure is applied to the segment assembled on the ground (earth retaining wall) because it is pressed into the ground by the jack while being excavated underwater. Therefore, the jack pressure in the vertical direction is also applied to the opening incorporated in the segment. However, the jack pressure is a load applied only when the shaft is set, and such load is not applied after the setting is completed.
[0009]
Next, with respect to the circumferential direction, the segment after installation (the retaining wall) that has been deeply pressed into the ground is subjected to earth pressure and water pressure on the outer periphery of the retaining wall, and in the cylindrical shaft, it is the compression of the retaining member. Force is applied to the member and the opening.
[0010]
Further, the opening of the shaft is provided with an open / close gate, and when starting the excavator, the gate is pulled up to open the opening. At this time, the segment just above the gate must be prevented from coming into contact with the raised gate. Therefore, the position and size must be adjusted and arranged, for example, the digit height (thickness) must be lower (thinner) than that of a normal segment.
[0011]
However, there is a problem that if the girder height of the segment is lowered, the rigidity is insufficient, and the rigidity of the opening and surroundings is insufficient with respect to the jack pressure applied to the shaft when the shaft is set.
[0012]
Accordingly, the object of the present invention is to solve the above-mentioned problems, to counteract the pressure at the time of shaft construction and the earth pressure and water pressure around the earth retaining wall, to sufficiently secure the rigidity of the opening and its surroundings, and Another object of the present invention is to provide a reinforcing structure for a shaft opening that can ensure good workability without interfering with the raising of the gate.
[0013]
[Means for Solving the Problems]
According to the first aspect of the present invention, in the reinforcing structure of the opening in the shaft in which the opening provided with the gate is arranged to assemble a plurality of segments, and the assembled segment is press-fitted into the ground and set down, immediately above the opening The segment of the part has a double structure consisting of a first segment arranged so as not to contact the gate at the time of pulling up, and a second segment for reinforcement arranged overlapping the first segment, The second segment is characterized in that it is removably attached to the first segment.
[0014]
The invention according to
According to a third aspect of the present invention, reinforcing members are disposed on both the left and right sides and the lower portion of the opening, and the upper portion of the opening after the second segment is removed is reinforced at the upper portion of the opening. reinforcing beams for concatenates between an upper portion of the reinforcing member of the right and left sides of the opening and has a particular feature which is mounted so as not to contact with the gate.
[0015]
According to a fourth aspect of the present invention, there is provided transmission means for transmitting a load applied to the segment when the shaft is set to the gate closing the opening, and the transmission means includes the double-structured segment and the opening. It is characterized in that it is arranged so as to be interposed between the gate blocking the part.
[0016]
In the present invention, the segment immediately above the shaft opening has a double structure including a first segment and a second segment. If the normal segment is arranged immediately above the opening, it will come into contact with the gate when the gate of the opening is lifted, so the first segment has a thinner digit height (thickness) than the normal segment, and , Arrange so as not to contact the gate when the gate is lifted. The second segment is disposed so as to overlap the inside of the first segment and reinforces the first segment. The thickness of the double-structured segment that overlaps the first and second segments has the same or higher girder height (thickness) as the other segments. It can resist the vertical jack pressure applied and ensure rigidity, and can also counter the circumferential force caused by earth pressure and water pressure applied to the shaft. Since the second segment is removed from the first segment after the sinking is completed and before the gate is lifted, it does not come into contact with the gate to be lifted.
[0017]
Further, a member as a load transmitting means is disposed between the double-structured segment and the gate when the opening is closed, and the jack pressure is received by the gate when the opening is closed through the member.
[0018]
Further, reinforcing members are arranged on both the left and right sides and the top and bottom of the opening. In the upper part of the opening, the double-structured segment plays the role of a reinforcing member until the gate is lifted, but after the gate is lifted, it is at a position inside the shaft that does not contact the gate as a reinforcing member that changes to the removed second segment. The reinforcement beams are connected and connected between the upper portions of the left and right reinforcement members. In this way, by arranging the reinforcing members on the left and right and top and bottom of the opening, it is possible to counter the circumferential force caused by the water pressure and earth pressure applied to the shaft after the shaft is removed after the shaft is set.
[0019]
DETAILED DESCRIPTION OF THE INVENTION
Next, embodiments of the present invention will be described with reference to the drawings.
[0020]
1 to 14 are drawings according to an embodiment of the present invention, FIG. 1 is a front view showing a shaft and an opening, FIG. 2 is a cross-sectional view taken along line AA in FIG. 1, and FIG. 4 is a cross-sectional view taken along the line C-C of FIG. 1, FIG. 5 is a cross-sectional view showing the shaft and the opening when the opening is closed by a gate, and FIG. 6 is a reinforcing beam. 7 is a cross-sectional view of the shaft opening when the gate is closed and when the gate is closed, FIG. 7 is a cross-sectional view of the shaft opening after the reinforcement beam is installed and when the gate is lifted (when the opening is opened), and FIG. 1 is a cross-sectional view taken along the line DD of FIG. 1 when the gate is pulled up, FIG. 9 is a partially enlarged view of FIG. 6, FIG. 10 is a partially enlarged view of FIG. FIG. 12 is a front view, FIG. 13 is a sectional view showing a second segment constituting a double-structured segment, and FIG. 14 is a front view. That.
[0021]
Construction of the
[0022]
As shown in FIGS. 1, 5, and 7 to 10, the
[0023]
As shown in FIGS. 1, 2, 6, 9, and 11 to 14, the segment immediately above the
[0024]
The
[0025]
In FIG. 1, the range in which the
[0026]
Next, reinforcement around the opening will be described.
[0027]
As shown in FIG. 1, reinforcing
[0028]
Next, means for transmitting the jack pressure to the gate will be described.
[0029]
The
[0030]
[Action]
Next, the starting process of the shield excavator by the starting shaft having the opening reinforcing structure of the present invention will be described.
[0031]
(1) On the ground, a
[0032]
{Circle around (2)} The
[0033]
(3) The
[0034]
(5) Next, the
[0035]
(6) Mount the
[0036]
【The invention's effect】
As described above, according to the present invention, the following useful effects are brought about.
[0037]
(1) A double-structured segment is placed immediately above the opening, and the opening is reinforced by the double-structured segment for temporary loads caused by jacking pressure during installation by the urban ring method. Since the second segment can be removed and the gate can be lifted when the shield excavator starts later, the opening can be effectively reinforced without impairing the work efficiency.
[0038]
(2) Since the left and right and upper and lower sides of the opening are reinforced by reinforcing members and beams, the load on the gate only needs to be taken into consideration, so the load on the gate is reduced and the gate thickness is reduced. Can be made thinner.
[0039]
(3) Since the transmission means for transmitting the load applied to the segment of the double structure to the gate is provided, jack thrust and vertical axial force at the time of setting can be received by the gate.
[Brief description of the drawings]
FIG. 1 is a front view showing a shaft and an opening in a state where the opening is closed by a gate according to an embodiment of the present invention.
2 is a cross-sectional view taken along line AA of FIG. 1 before an opening is closed by a gate according to an embodiment of the present invention and a reinforcing beam is installed.
3 is a cross-sectional view taken along line BB in FIG. 1 according to the embodiment of the present invention.
4 is a cross-sectional view taken along line CC of FIG. 1 according to the embodiment of the present invention.
FIG. 5 is a sectional view showing a shaft and an opening in a state where the opening is closed by a gate according to an embodiment of the present invention.
FIG. 6 is a cross-sectional view showing the shaft and the opening after the opening is closed and the reinforcing beam is installed by the gate according to the embodiment of the present invention.
FIG. 7 is a cross-sectional view showing the shaft and the opening when the reinforcing beam according to the embodiment of the present invention is installed and when the gate is lifted.
8 is a cross-sectional view taken along the line DD of FIG. 1 after the reinforcing beam according to the embodiment of the present invention is installed and when the gate is lifted.
9 is a partially enlarged view of FIG. 6 according to the embodiment of the present invention.
10 is a partially enlarged view of FIG. 7 according to the embodiment of the present invention.
FIG. 11 is a cross-sectional view showing a first segment constituting a double-structured segment according to an embodiment of the present invention.
12 is a front view of FIG. 11 according to the embodiment of the present invention.
FIG. 13 is a cross-sectional view showing a second segment constituting a double-structured segment according to the embodiment of the present invention.
14 is a front view of FIG. 13 according to the embodiment of the present invention.
[Explanation of symbols]
DESCRIPTION OF
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002115224A JP3990589B2 (en) | 2002-04-17 | 2002-04-17 | Reinforcing structure for shaft opening |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002115224A JP3990589B2 (en) | 2002-04-17 | 2002-04-17 | Reinforcing structure for shaft opening |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003307092A JP2003307092A (en) | 2003-10-31 |
JP3990589B2 true JP3990589B2 (en) | 2007-10-17 |
Family
ID=29396667
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002115224A Expired - Fee Related JP3990589B2 (en) | 2002-04-17 | 2002-04-17 | Reinforcing structure for shaft opening |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3990589B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101501834B1 (en) * | 2013-07-30 | 2015-03-12 | 조광래 | Underground excavation opening and closing devices |
-
2002
- 2002-04-17 JP JP2002115224A patent/JP3990589B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2003307092A (en) | 2003-10-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH0377887B2 (en) | ||
KR19990078524A (en) | Composite Underground Structure Construction Method | |
JP2001032673A (en) | Tunnel work execution method | |
JP2007162266A (en) | Two-step earth retaining wall and its construction method | |
JP3888174B2 (en) | Temporary deadline construction method | |
JP3990589B2 (en) | Reinforcing structure for shaft opening | |
JP3453664B2 (en) | Shaft construction method | |
JP2000265474A (en) | Temporary cofferdam constructing method for construction | |
CN112302052B (en) | Vertical shaft construction system and construction method thereof | |
JP4805002B2 (en) | Earth retaining structure using steel pipe, construction method thereof and shield machine start-up construction method | |
JP3165548B2 (en) | Casing tube | |
JP2973815B2 (en) | Construction method of pressure-resistant wall under the building | |
JP4094990B2 (en) | Slide gate device installed at the opening of a shaft and its construction method | |
CN217204259U (en) | Horse riding well | |
JP4323075B2 (en) | Shaft opening structure | |
JPH11117686A (en) | Segment corresponding to opening covered with resin on inner surface | |
CN215948100U (en) | Underdrain reinforcing combination system | |
CN219547766U (en) | Underground diaphragm wall pile combination structure for preventing hole collapse | |
JPH04309692A (en) | Underground space construction method | |
JP4302274B2 (en) | Pipe roof structure and pipe roof construction method | |
JPH10168867A (en) | Landslide prevention pile and construction method for the prevention pile | |
JP3903371B2 (en) | Opening structure of shaft and start and arrival method from shaft | |
JP2005264500A5 (en) | ||
KR20230108567A (en) | Longitudinal and lateral integration structure of pile and structure manufactured using the same | |
CN118065397A (en) | Construction method of deep foundation pit supporting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050318 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070223 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070306 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070425 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070703 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070720 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100727 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3990589 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100727 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110727 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110727 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120727 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120727 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130727 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |