JP3981587B2 - Method for burying sewage tank and sewage tank unit used in the method - Google Patents
Method for burying sewage tank and sewage tank unit used in the method Download PDFInfo
- Publication number
- JP3981587B2 JP3981587B2 JP2002126238A JP2002126238A JP3981587B2 JP 3981587 B2 JP3981587 B2 JP 3981587B2 JP 2002126238 A JP2002126238 A JP 2002126238A JP 2002126238 A JP2002126238 A JP 2002126238A JP 3981587 B2 JP3981587 B2 JP 3981587B2
- Authority
- JP
- Japan
- Prior art keywords
- sewage tank
- concrete plate
- foundation concrete
- factory
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Description
【0001】
【発明の属する技術分野】
本発明は、地中に埋設されて汚水を一時的に貯留する汚水槽の埋設方法、及びその方法に用いられる汚水槽ユニットに関し、特に、一般家庭等からの排水を受ける小型の樹脂製汚水槽の技術分野に属する。
【0002】
【従来の技術】
従来より、下水道の普及が困難な地域では、地中に埋設した浄化槽により汚水を一時的に貯留して浄化した後に、河川に放流するようにしている。また、下水処理場までの距離が長く、地形的な要因からも自然流下方式の下水道が敷設し難い地域において、近年、下水道の途中に汚水を一時貯留してから電動ポンプ等により圧送するポンプピットを設けて、強制的に下流側に流すようにした圧力式の下水道を採用することが提案されている。
【0003】
前記のポンプピットは、下水管の間に配置される汚水槽の内部に水中ポンプや槽内配管、水位制御装置等を一体化したもので、地上から大きな荷重の加わるところに埋設されるものや、比較的大型のものでは一般的にコンクリート製の汚水槽が用いられ、また、比較的小型であまり大きな荷重を受けないものでは樹脂製のものが用いられている。
【0004】
そして、前記の浄化槽や小型のポンプピットのような樹脂製の汚水槽を地中に埋設するときの手順としては、一般的に、まず埋設坑の底部に基礎コンクリートスラブを打設し、その上に汚水槽を設置して周囲を埋め戻した後に、汚水槽上面のマンホール(開口)を囲むように上部コンクリートスラブを打設するものである。
【0005】
また、例えば特開平9−221822号公報には、基礎コンクリートスラブを現場で打設するのではなく、予め工場にて製作しておいて埋設坑に設置するという技術が開示されている。こうすれば、コンクリートの養生のための期間が不要になって工事期間が短縮できるとともに、現場での管理不良に起因するコンクリートの強度不足や信頼性の低下を防止できる。
【0006】
さらに、例えば特開2001−342678号公報に記載のものでは、埋設坑を掘削する際に予め埋設坑の大きさに合わせて準備した枠体を用いることで、埋設坑の法面の崩れを防止して掘削作業を容易に行うことができるとともに、その枠体の上縁と下縁とを水平にしておけば、水平出しの作業が容易に行えるとしている。
【0007】
【発明が解決しようとする課題】
ところが、前記従来例に係る汚水槽の埋設方法によれば、たとえ前者の従来例(特開平9−221822号公報)のように基礎コンクリートスラブを予め工場で製作しておいても、汚水槽を埋めた後に上部コンクリートスラブを打設しなくてはならないから、その分のコンクリートの養生期間が必要になるし、その上部コンクリートスラブについて強度不足や信頼性の問題が残る。
【0008】
また、そのように現場にてコンクリートを打設する作業は、元来、繁雑で手間の掛かるものであるし、前記後者の従来例(特開2001−342678号公報)のように枠体を用いることで水平出しの作業を容易化できたとしても、この水平出しの作業を基礎と汚水槽自体とで少なくとも2回は行わなくてはならないから、このことによっても現場での作業はかなり繁雑なものとなる。
【0009】
さらに、一般家庭等に設置される小型の汚水槽であっても、これを例えば駐車場の下に設置する場合には、ある程度以上の耐荷重性が要求されるので、この場合には基礎コンクリートスラブと上部コンクリートスラブとの間に別途、支柱等を配設して、樹脂製の汚水槽に大きな荷重が加わらないようにする必要がある。
【0010】
つまり、従来までの汚水槽の埋設方法では、埋設現場での施工工事が煩雑で手間と時間の掛かるものであり、さらなる簡素化と工期の短縮とが求められているのが実状である。
【0011】
本発明は斯かる諸点に鑑みてなされたものであり、その目的とするところは、地中に埋設する汚水槽等の構成に工夫を凝らして、その耐久信頼性を向上しつつ、埋設現場での工事を簡素化しかつ工期の短縮を図ることにある。
【0012】
【課題を解決するための手段】
前記目的を達成するために、本発明の解決手段では、汚水槽や基礎コンクリートスラブだけでなく上部コンクリートスラブも予め工場で製作し、それらを組み立てて一体のユニットとした上で、埋設坑内に設置する。
【0013】
具体的に、請求項1の発明は、基礎コンクリート板上に樹脂製の汚水槽を載置するとともに、該汚水槽の上部にその上面の開口部を囲むようにして上部コンクリート板を配設し、それら基礎コンクリート板、汚水槽及び上部コンクリート板が一体となった汚水槽ユニットを組み立てるユニット組立工程と、埋設現場の地面を掘削して、前記汚水槽ユニット全体を収容可能な埋設坑を形成する掘削工程と、この掘削工程で形成した埋設坑の底部に前記基礎コンクリート板を設置して、当該埋設坑の内部に前記汚水槽ユニットを収容する設置工程とを備え、
前記汚水槽が、上側ケーシングと下側ケーシングとに分割されており、
前記組立工程では、前記上側ケーシングと基礎コンクリート板とを連結部材により連結して、それらの中間に下側ケーシングを挟持させるようにし、さらに、その組立工程を全て工場で行って、一体化した汚水槽ユニットを埋設現場に搬送する汚水槽の埋設方法である。
【0014】
前記の方法により、まず、ユニット組立工程にて基礎コンクリート板、汚水槽及び上部コンクリート板を一体化して汚水槽ユニットを組み立てる。こうすれば、後は埋設現場にて掘削した埋設坑に前記汚水槽ユニットを収容して水平に設置するだけでよい。つまり、現場でのコンクリート打設工事が不要になり、また、水平出しの作業も汚水槽ユニット全体として1回だけで済む。
【0015】
従って、この方法によれば、現場での工事が従来までに比べて格段に簡素なものとなり、コンクリートの養生のための時間も不要になるので、工期が大幅に短縮でき、コストの低減も可能となる。しかも、基礎や上部コンクリートスラブを工場にて製作することで、その品質が安定して耐久信頼性が向上する。
【0016】
しかも、組立工程は全て工場で行うことで、その組立精度を向上しかつ安定させることができるので、汚水槽ユニットの耐久信頼性をさらに向上できる。
【0017】
また、前記汚水槽を上側ケーシングと下側ケーシングとに分割可能としているので、その成形性を損なうことなく、汚水槽の形状の設計自由度を向上できる。しかも、汚水槽の上側ケーシング及び下側ケーシングと基礎コンクリート板とは同時に組み立てることで、汚水槽を複数の部材からなるものとしても、組立工数の増大を招くことはない。
【0018】
次に、請求項2の発明は、予め工場で製作されて埋設坑の底部に設置される基礎コンクリート板と、この基礎コンクリート板の上面に載置されて上側及び下側ケーシングに分割可能な樹脂製の汚水槽と、予め工場で製作されて前記汚水槽の上部にその上面の開口部を囲むようにして配設された上部コンクリート板とを備え、前記汚水槽の上側ケーシング及び基礎コンクリート板が、その中間に下側ケーシングを挟持した状態で連結部材により連結されているとともに、
前記汚水槽の上側及び下側ケーシングの接合部には、それぞれ、外方に向かって略水平 に延出するフランジが形成され、上側ケーシングのフランジの上面には金属製の環状部材が載置され、前記連結部材は、その上端部が前記環状部材に固定される一方、下端部が基礎コンクリート板に固定されていることを特徴とする汚水槽ユニットである。
【0019】
前記の構成を有する汚水槽ユニットは、これを現場にて埋設坑の内部に設置するようにするだけでよいので、請求項1の発明と同様に現場での作業が格段に簡素化され、工事期間が大幅に短縮でき、コストの低減が可能となる上に、品質が安定して耐久信頼性が向上する。また、樹脂製汚水槽を上下に2分割可能な構造としたことで、その成形性を損なうことなく形状の設計自由度を向上することができる。しかも、そのように汚水槽を複数の部材からなるものとしても、それらを基礎コンクリート板と同時に組み立てることができるから、組立工数の増大を招くことはない。
【0020】
しかも、樹脂製の上側及び下側ケーシングが互いにフランジにおいて密着し、それらの接合状態が安定するとともに、上側ケーシングのフランジに金属製環状部材を載置するだけで、樹脂製のフランジを別段、補強することもなく、上側ケーシングと基礎コンクリート板とを連結部材により十分な強度でもって連結することができる。
【0021】
また、前記上側ケーシングのフランジの上面には周囲の土砂の重量が効果的に作用することになるので、このことによっても上側及び下側ケーシング同士の接合状態が安定し、さらに汚水槽全体の浮上防止効果も得られる。尚、前記上側ケーシングのフランジの上面にさらに浮上防止用の環状コンクリート部材を載置するようにしてもよく、この場合は、環状コンクリート部材も予め工場で製作して汚水槽ユニットとして一体化するのが好ましい。
【0022】
また、請求項3の発明は、予め工場で製作されて埋設坑の底部に設置される基礎コンクリート板と、この基礎コンクリート板の上面に載置された樹脂製の汚水槽と、予め工場で製作されて前記汚水槽の上部にその上面の開口部を囲むようにして配設された上部コンクリート板とを備え、前記上部コンクリート板と基礎コンクリート板とを連結支持柱により連結して、それらの間に汚水槽を挟持させたものであり、該汚水槽の下端部を基礎コンクリート板の上面に対して、少なくともその面に沿う移動を規制するように保持する保持部材が設けられていることを特徴とする汚水槽ユニットである。
【0023】
前記構成の汚水槽ユニットは、請求項2の発明と同様に現場での作業を格段に簡素化し、工事期間を大幅に短縮可能とし、コストの低減を可能とする上に、品質が安定して耐久信頼性も向上する。また、上部コンクリート板と基礎コンクリート板との間に連結支持柱を配設したことで、上方からの荷重に対する耐性が向上するとともに、上部コンクリート板と基礎コンクリート板との間に汚水槽を挟持して、それらを同時に組み立てることができるので、組立工数の増大を防止できる。
【0024】
さらに、汚水槽の下端部を基礎コンクリート板の上面に対して少なくともその面に沿う移動を規制するように保持する保持部材を設けているので、上部コンクリート板と基礎コンクリート板との間での汚水槽の保持がより確実なものとなる。
【0025】
請求項4の発明は、予め工場で製作されて埋設坑の底部に設置される基礎コンクリート板と、この基礎コンクリート板の上面に載置された樹脂製の汚水槽と、予め工場で製作されて前記汚水槽の上部にその上面の開口部を囲むようにして取り付けられた上部コンクリート板とを備え、前記汚水槽の上端部及び下端部に設た取付部をそれぞれ締結部材により上部コンクリート板及び基礎コンクリート板に固定したことを特徴とする汚水槽ユニットである。
【0026】
前記構成の汚水槽ユニットは、請求項2や請求項3の発明と同じく、現場での作業を格段に簡素化し、工事期間を大幅に短縮可能とし、コストの低減を可能とする上に、品質が安定して耐久信頼性も向上する。
【0027】
【発明の実施の形態】
以下、本発明の実施形態を図面に基いて説明する。
【0028】
(実施形態1)
図1、2は、本願発明に係る汚水槽ユニットとして、一般家庭からの排水を一時、貯留した上で下水管まで圧送する宅内排水用ポンプユニットAを示し、図示の汚水槽1は、例えば家庭の裏庭のようにあまり大きな荷重が加わらない場所に埋設する比較的小型のものである。この汚水槽1は、略同じコップ形状の2つのケーシング2,3を組み合わせて全体として樽形状としたものであって、詳しくは、前記2つのケーシング2,3はいずれも例えばガラス繊維で強化したポリエステル樹脂からなり、そのうちの下側のもの(下側ケーシング2)は、矩形板状の基礎コンクリート板4の上面に載置されていて、上方に向かって徐々に大径となる有底のコップ形状をなし、また、上側のもの(上側ケーシング3)は、前記下側ケーシング2を上下に逆転させて上端部(底部)に円形のマンホール穴3a(開口部)を空けたものである。また、前記上側及び下側ケーシング3,2の接合部には、それぞれ外方に向かって略水平に延出する円環状フランジ3b,2aが形成されている。
【0029】
前記上側ケーシング3のフランジ3bの上面には、円環状の押さえ金具5(環状部材)が載置されていて、この押さえ金具5と前記基礎コンクリート板4とが複数の連結部材6,6,…により強固に連結されており、このことで、前記上側ケーシング3と基礎コンクリート板4との間に下側ケーシング2が挟持されて、それらが一体化されている。すなわち、前記押さえ金具5は、鋼板を断面が略L字状をなす円環状に成形したものであり、上側ケーシング3のフランジ3bに当接する鍔部には周方向に略等間隔を空けて複数個の貫通孔が形成されている。この各貫通孔に対応するようにして、上側及び下側ケーシング3,2の各フランジ3b,2aにもそれぞれ貫通孔が形成されており、それら各貫通孔を重ね合わせて貫通するよう、押さえ金具5の上方からボルト7,7,…が挿入されている。
【0030】
そして、前記各ボルト7の頭部(上端部)が押さえ金具5の鍔部上面において各貫通孔の周縁部に溶接されており、一方、ボルト7の先端部(下端部)は下側ケーシング2のフランジ2aの下面よりも下方に突出して、ターンバックル8,8,…の上端部に連結されている。この各ターンバックル8は上下方向に延びていて、その下端部が、基礎コンクリート板4の上面から突出するように埋設されたアンカーボルト9,9,…に連結されている。つまり、前記各ボルト7、ターンバックル8及びアンカーボルト9によって連結部材6が構成されている。
【0031】
一方、上側ケーシング3の上端部外周には縮径部3cが形成され、この縮径部3cとの境界となる段差部に、上部コンクリート板10とマンホール蓋11とを受ける円環状の受け金具12が載置されている。この受け金具12も前記押さえ金具5と同じく、鋼板を断面が略L字状をなす円環状に成形したもので、そのうちの円筒部分が上側ケーシング3の縮径部3cに外嵌合する一方、鍔部には周方向に略等間隔を空けて複数のボルト孔が貫通形成されている。また、その受け金具12の上部に載置される上部コンクリート板10にも前記各ボルト孔に対応するようにしてボルト孔が形成されており、それら各ボルト孔を重ね合わせて貫通するよう、受け金具12の上方からボルト13,13,…が挿通されていて、その下端側にナット14,14,…が螺合されている。
【0032】
前記基礎コンクリート板4及び上部コンクリート板10は、いずれも、予め工場にて適切な温度管理の下に製作されたものであり、内部の鉄筋の配置や結束の状態も安定していて、これらに錆を生じることもなく、コンクリート板としての強度及び耐久信頼性が極めて高い。また、この実施形態では、前記したケーシング2、3及び基礎コンクリート板4の連結や、上部ケーシング3への上部コンクリート板10等の固定も全て工場にて行うようにしており、これらの組立精度が高くかつ安定することで、ポンプユニットA全体としても耐久信頼性が極めて高い。
【0033】
尚、図1に符号15として示すのは、ポンプユニットA全体が地下水等により浮上することを防止するための重しとなるコンクリート環状体であり、このコンクリート環状体15も前記基礎コンクリート板4や上部コンクリート板10と同様に予め工場で製作して、汚水槽1の押さえ金具4の上面に載置したものである。また、同図に符号16,16として示すのは、ポンプユニットAを吊り上げるときに使用するアンカーボルトである。
【0034】
次に、主に図2を参照しながら、ポンプユニットAの内部の概略構成及びその機能について説明すると、図示の如く、汚水槽1の一側(図の左側)の側壁には、上流側の下水管に接続する流入管18が設けられ、この流入管18内の通路の下流端が汚水槽1の内部に臨んで開口するとともに、この開口部を覆うようにしてバッフルプレート19が設けられている。そして、例えば家庭からの排水は前記流入管18の開口から汚水槽1内に噴出してバッフルプレート19の裏面に衝突し、その後、汚水槽1の内部に貯留される。この汚水槽1の内部には、汚水を汲み上げて吐出する電動式の水中ポンプ20が配設され、この水中ポンプ20から吐出された汚水が接続管21を介して上下方向に延びる配管22に至り、さらに流出管23を介して汚水槽1の外に排出されて、下流側の下水管に送り出される。尚、前記上下方向の配管22の途中には逆流防止弁24が配設されている。
【0035】
さらに、前記汚水槽1の内部には、溜まっている汚水の水位を検出するための気泡式水位検出装置25と、汚水の異常水位を検出するためのフロートスイッチ26とが配設されていて、それらの水位検出装置25及びフロートスイッチ26から出力される信号が図外の制御盤に入力する一方、この信号に基づいて制御盤から出力される制御信号が前記水中ポンプ20に入力されて、該水中ポンプ20が汚水槽1内の汚水の水位に応じて自動的に起動、停止されるようになっている。すなわち、例えば、水中ポンプ20は、汚水槽1内の水位が図示の如く予め設定した高水位HLを超えたときに運転を開始する一方、汚水の排出によって水位が低下して、予め設定した低水位LL以下になると、自動で停止する。
【0036】
尚、前記水中ポンプ20は図示の如くチェーン27によりマンホール蓋11に連結されているとともに、汚水槽1内を上下に延びるガイドパイプ28に沿って上下に移動可能とされており、これを点検等する際にはマンホール蓋11を開けてチェーン26をたぐり上げることで、水中ポンプ20を汚水の中から容易に取り出すことができる。また、そのようにして点検した後に、水中ポンプ20をガイドパイプ27に沿って一番下まで降ろせば、水中ポンプ20の自重によって、その吐出口が接続管21の上流端部に自動的に接続されるようになっている。
【0037】
(汚水槽の埋設方法)
次に、前記汚水槽1を地中に埋設する手順を説明する。まず、工場にて、上述したように、予め製作しておいた基礎コンクリート板4の上に汚水槽1を載置して、押さえ金具5及び連結部材6,6,…によって一体的に連結する。また、汚水槽1の上側ケーシング3の上端部に受け金具12と上部コンクリート板10とを取り付けて固定する。こうして、基礎コンクリート板4、汚水槽1及び上部コンクリート板10が一体となってポンプユニットAが組み立てられる(ユニット組立工程)。その際、浮上防止用のコンクリート環状体15もポンプユニットAに組み付けるようにしてもよい。
【0038】
一方、前記汚水槽1の埋設現場では、地面の所定箇所を掘削して、ポンプユニットAの全体を収容可能な埋設坑Hを形成する(掘削工程)。そして、工場から埋設現場に搬送した前記ポンプユニットAを、図3に示すようにトラックUのクレーンC等により吊りつり下げて、埋設坑Hに収容する。この際、埋設坑Hの底部にポンプユニットAの基礎コンクリート板4を略水平になるように水平出しをして設置する(設置工程)。
【0039】
そうして、図1に示すように、上部コンクリート板10がちょうど地面と同じくらいの高さになるようにして、ポンプユニットAを埋設坑H内に略水平に設置することができたら、その後、該ポンプユニットAの周りに土砂を埋め戻して、埋設工事を終了する。
【0040】
したがって、この実施形態に係る汚水槽の埋設方法によれば、まず、工場にて適切な管理の下に基礎コンクリート板4及び上部コンクリート板10を製作し、さらに、汚水槽1と一体化してポンプユニットAを完成させるようにしているので、コンクリートスラブの品質が安定するとともに、それらを汚水槽1に組み立てる作業の精度も高くなりかつ安定したものとなって、ポンプユニットA全体としての耐久信頼性が向上する。
【0041】
そして、そのようにして組み立てたポンプユニットAを埋設現場に搬送して、埋設坑Hに水平に設置するだけでよいので、埋設現場でのコンクリート打設工事が不要になり、また、水平出しの作業も最小限度で済むようになって、現場での作業が格段に簡素なものとなる。しかも、コンクリートの養生のための時間がなくなるので工期を大幅に短縮でき、さらに、コストの低減も図られる。
【0042】
加えて、この実施形態では、前記汚水槽1を下側ケーシング2と上側ケーシング3とに分割可能としているので、それらの成形性を損なうことなく、汚水槽1の形状についての設計の自由度を向上できる。特に、2つのケーシング2,3を略同じ形状としたことで、成形型の共用によってさらなるコストの低減も可能となる。一方、そのように汚水槽1を複数のケーシング2,3に分割した場合、それらを組み合わせる作業が必要になるが、上述したように、上側ケーシング3と基礎コンクリート板4との間に下側ケーシング2を挟持して、それらを同時に組み立てるようにしているので、組立工数は増大しない。
【0043】
(実施形態2)
図4は、本発明の実施形態2に係るポンプユニットAの一例を示す。尚、このポンプユニットAの全体的な構成は上述した実施形態1のものと同じなので、同一部材には同一の符号を付してその説明は省略する。この実施形態2のものでは、汚水槽29が繊維強化樹脂により一体成形されていて、これが基礎コンクリート板4と上部コンクリート板30との間に挟持されているとともに、該基礎コンクリート板4及び上部コンクリート板30が4本の連結支持柱31,31,…により連結されている。
【0044】
前記ポンプユニットAの上部コンクリート板30は、前記実施形態1のものと同様に予め工場で製作したものであるが、基礎コンクリート板4と略同じ大きさの矩形状とされていて、これが上下方向に見て基礎コンクリート板4に略合致するように配置されている。そして、該上部コンクリート板30及び基礎コンクリート板4の四隅に対応するように、それぞれ鋼製パイプからなる連結支持柱31,31…が配設されている。この各連結支持柱31の上端部には矩形板状の鋼板が溶接されていて、これが図示しないアンカーボルト等により上部コンクリート板30に締結されており、同様に、各連結支持柱31の下端部の鋼板がアンカーボルト等により基礎コンクリート板4に締結されている。
【0045】
また、前記汚水槽29の下端部には周方向に等間隔を空けて4つの樹脂製ブラケット32,32,…(保持部材)が配設され、この各ブラケット32にはそれぞれ断面略L字状の鋼板製取付アングル33,33,…が接着され、この各取付アングル33が図示しないボルト等により基礎コンクリート板4に固定されている。すなわち、この実施形態では、4本の連結支持柱31,31,…により互いに連結された2枚のコンクリート板4,30の間に汚水槽29を挟持させるとともに、この汚水槽29の下両端部をブラケット32,32,…及び取付アングル33,33,…により基礎コンクリート板4に固定して、一体のポンプユニットAを構成したものである。
【0046】
したがって、この実施形態2に係るポンプユニットAによれば、前記実施形態1のものと同様に、予め工場にて製作した基礎コンクリート板4及び上部コンクリート板30を汚水槽29と一体化してポンプユニットAを組み立て、このユニットを埋設現場に搬送して、埋設坑Hに収容して設置すればよいから、現場での作業が格段に簡素化し、工期が大幅に短縮でき、コストの低減も可能になるとともに、品質が安定して耐久信頼性が向上する。
【0047】
しかも、上下2枚のコンクリート板4,30の間に汚水槽29を挟持して一体化するようにしているので、それらを同時に組み立てることができ、組立工数を低減できるとともに、特に汚水槽29の下端部についてはブラケット32,32,…及び取付アングル33,33,…によって基礎コンクリート板4に固定するようにしているので、汚水槽29の保持はより確実なものとなる。
【0048】
また、上部コンクリート板30と基礎コンクリート板4との間にはその四隅をそれぞれ支持するように連結支持柱31,31,…が配設されているので、ポンプユニットA全体として上方からの荷重に対する耐力が向上しており、従って、この実施形態2のポンプユニットAは、例えば一般家庭の駐車場の下に設置する場合のように、ある程度以上の耐荷重性が要求される場合に、特に好適なものである。
【0049】
尚、前記汚水槽29の下端部においてブラケット32,32,…と取付アングル33,33,…とは必ずしも接着しなくてもよく、各ブラケット32及び取付アングル33を係合させて、汚水槽29の下端部を基礎コンクリート板4の上面に対し、その面に沿う移動を規制するように保持するようにしてもよい。
【0050】
(実施形態3)
図5は、本発明の実施形態3に係るポンプユニットAの一例を示す。これは、実施形態2と同じ一体型の汚水槽29を用いて、その上端部及び下端部をそれぞれ上部コンクリート板33及び基礎コンクリート板4に固定して一体化するようにしたものである。尚、この実施形態3のポンプユニットAについても、前記実施形態1、2のものと同じ部材には同一の符号を付して、その説明は省略する。
【0051】
そして、この実施形態3のポンプユニットAでは、汚水槽29の上端部及び下端部においてそれぞれ周方向に等間隔を空けて4つのブラケット32,32,…を配設し、この各ブラケット32を取付アングル33,33,…及びボルト34,34,…によって上部コンクリート板33又は基礎コンクリート板4に固定している。
【0052】
したがって、この実施形態3に係るポンプユニットAによれば、前記実施形態1、2のものと同様に埋設現場での作業が格段に簡素化し、工期が大幅に短縮でき、コスト低減が可能になるとともに、耐久耐久信頼性が向上するものである。
【0053】
尚、本発明の構成は、前記実施形態1〜3のものに限定されることはなく、その他の種々の構成をも包含するものである。すなわち、例えば、前記各実施形態では本発明の汚水槽ユニットを、宅内排水用ポンプユニットAに適用しているがこれに限らず、例えば浄化槽等に適用してもよい。
【0054】
【発明の効果】
以上、説明したように、請求項1の発明に係る汚水槽の埋設方法によると、汚水槽と基礎コンクリート板と上部コンクリート板とを全て予め工場にて製作し、それらを組み立てて一体のユニットとした上で埋設坑内に設置するようにしたことで、現場での工事を格段に簡素化することができ、工期も大幅に短縮できるとともに、コスト低減も可能となる。その上さらに、基礎や上部コンクリートスラブの品質が安定して、耐久信頼性が向上する。
【0055】
また、汚水槽やコンクリート板の組み立てを工場で行うようにすることで、汚水槽ユニットの耐久信頼性をさらに向上できる。
【0056】
さらに、樹脂製の汚水槽を上下に分割可能とすることで、その成形性を損なうことなく、汚水槽の形状の設計自由度を向上できる。しかも、2つのケーシングと基礎コンクリート板とを同時に組み立てることができるので、組立工数の増大を招くことがない。
【0057】
請求項2の発明に係る汚水槽ユニットは、前記請求項1の発明に係る埋設方法に好適なもので、埋設現場での作業を格段に簡素化でき、工期を大幅に短縮でき、コストを低減できる上に、耐久信頼性を向上でき、しかも、汚水槽の設計の自由度を向上できる。
【0058】
また、汚水槽の上側及び下側ケーシングの接合部にフランジを設け、その上に金属製環状部材を載置してこれを連結部材により基礎コンクリート板に固定したことで、2つのケーシングの接合状態が安定するとともに、樹脂製の上側ケーシングを特に補強することなく、十分な強度でもって基礎コンクリート板に連結することができる。しかも、フランジの上面に作用する土砂の重量によってケーシング同士の接合状態が安定し、さらに汚水槽全体の浮上防止効果も得られる。
【0059】
請求項3の発明に係る汚水槽ユニットによると、請求項2の発明と同様に、一体化した汚水槽ユニットを埋設坑の内部に略水平に設置するだけでよいから、埋設現場での作業を格段に簡素化でき、工期を大幅に短縮でき、コストを低減できる上に、耐久信頼性を向上できる。さらに、連結支持柱を配設したことで、上方からの荷重に対する耐力を向上できるとともに、コンクリート板と汚水槽とを同時に組み立てることができて、組立工数の増大を防止できる。
【0060】
しかも、保持部材によって汚水槽の下端部を保持することで、汚水槽の保持状態をより確実なものとすることができる。
【0061】
請求項4の発明に係る汚水槽ユニットによると、請求項2、3の発明と同様に一体化した汚水槽ユニットを埋設坑の内部に略水平に設置するだけでよいから、埋設現場での作業を格段に簡素化でき、工期を大幅に短縮でき、コストを低減できる上に、耐久信頼性を向上できる。
【図面の簡単な説明】
【図1】 本発明の実施形態1に係るポンプユニットを埋設坑の内部に収容して、これを埋め戻す前の状態を示す説明図である。
【図2】 ポンプユニットの内部の概略構成を示す図である。
【図3】 ポンプユニットを埋設坑に収容する作業の説明図である。
【図4】 実施形態2に係る図1相当図である。
【図5】 実施形態3に係る図1相当図である。
【符号の説明】
A 宅内排水用ポンプユニット(汚水槽ユニット)
1、29 汚水槽
2 下側ケーシング
2a フランジ
3 上側ケーシング
3b フランジ
4 基礎コンクリート板
5 押さえ金具(環状部材)
6 連結部材
7 ボルト
8 ターンバックル
9 アンカーボルト
10,30,33 上部コンクリート板
31 連結支持柱
32 ブラケット(保持部材、取付部)
33 取付アングル(保持部材、取付部)[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method of burying a sewage tank that is buried in the ground and temporarily stores sewage, and a sewage tank unit used in the method, and in particular, a small resin sewage tank that receives wastewater from a general household or the like. Belongs to the technical field.
[0002]
[Prior art]
Conventionally, in areas where it is difficult to spread sewerage, sewage is temporarily stored and purified by septic tanks buried in the ground before being discharged into rivers. Also, in areas where the distance to the sewage treatment plant is long and it is difficult to lay sewerage due to topographical factors, in recent years, a pump pit that temporarily stores sewage in the middle of the sewer and then pumps it with an electric pump, etc. It has been proposed to employ a pressure-type sewer system that is forced to flow downstream.
[0003]
The pump pit is an integrated submersible pump, tank piping, water level control device, etc. in a sewage tank arranged between sewage pipes, embedded in a place where a large load is applied from the ground, In general, a concrete sewage tank is used for a relatively large one, and a resin one is used for a relatively small one that does not receive a large load.
[0004]
As a procedure for burying a resin sewage tank such as the septic tank or small pump pit in the ground, generally, a foundation concrete slab is first placed at the bottom of the buried pit, After the sewage tank is installed and the surroundings are backfilled, the upper concrete slab is placed so as to surround the manhole (opening) on the upper surface of the sewage tank.
[0005]
Further, for example, Japanese Patent Application Laid-Open No. 9-221822 discloses a technique in which a foundation concrete slab is not placed on site but manufactured in advance in a factory and installed in a buried mine. In this way, a period for curing the concrete is no longer necessary and the construction period can be shortened, and it is possible to prevent insufficient strength of concrete and deterioration of reliability due to poor management at the site.
[0006]
Further, for example, in the one described in Japanese Patent Application Laid-Open No. 2001-342678, the excavation of the buried mine prevents the collapse of the slope of the buried mine by using a frame prepared in advance according to the size of the buried mine. In addition, excavation work can be easily performed, and leveling work can be easily performed if the upper and lower edges of the frame body are leveled.
[0007]
[Problems to be solved by the invention]
However, according to the sewage tank embedding method according to the conventional example, even if the foundation concrete slab is manufactured in the factory in advance as in the former conventional example (Japanese Patent Laid-Open No. 9-221822), Since the upper concrete slab must be cast after filling, the concrete curing period is required, and the upper concrete slab has problems of insufficient strength and reliability.
[0008]
In addition, the work of placing concrete in the field is originally complicated and time-consuming, and a frame is used as in the latter conventional example (Japanese Patent Laid-Open No. 2001-342678). Even if the leveling work can be facilitated by this, the leveling work must be performed at least twice for the foundation and the sewage tank itself. It will be a thing.
[0009]
Furthermore, even if it is a small sewage tank installed in a general household, when it is installed under a parking lot, for example, a load resistance of a certain level or more is required. It is necessary to separately provide a column or the like between the slab and the upper concrete slab so that a large load is not applied to the resin sewage tank.
[0010]
That is, in the conventional method for burying a sewage tank, the construction work at the burial site is complicated and time-consuming and time-consuming, and further simplification and shortening of the construction period are required.
[0011]
The present invention has been made in view of such various points. The purpose of the present invention is to improve the durability and reliability of the sewage tank embedded in the ground, while improving the durability and reliability. Is to simplify the construction and shorten the construction period.
[0012]
[Means for Solving the Problems]
In order to achieve the above object, according to the solution means of the present invention, not only the sewage tank and the basic concrete slab but also the upper concrete slab are manufactured in the factory in advance and assembled into an integrated unit and installed in the buried mine. To do.
[0013]
Specifically, according to the first aspect of the present invention, a resin sewage tank is placed on a foundation concrete board, and an upper concrete board is disposed on the upper part of the sewage tank so as to surround an opening on the upper surface thereof. A unit assembly process for assembling a sewage tank unit in which a basic concrete board, a sewage tank and an upper concrete board are integrated, and an excavation process for excavating the ground at the burial site to form a buried mine that can accommodate the entire sewage tank unit. And installing the foundation concrete plate at the bottom of the buried mine formed in this excavation process, and housing the sewage tank unit inside the buried mineProcessAnd
The sewage tank is divided into an upper casing and a lower casing,
In the assembly step, the upper casing and the foundation concrete plate are connected by a connecting member so that the lower casing is sandwiched between them,This is a sewage tank embedding method in which all assembly processes are performed in a factory and an integrated sewage tank unit is transported to an embedding site.
[0014]
By the above method, first, the basic concrete plate, the sewage tank and the upper concrete plate are integrated in the unit assembling process to assemble the sewage tank unit. If it carries out like this, after that, the said sewage tank unit should just be accommodated in the burial excavation excavated in the burial site, and should be installed horizontally. In other words, the concrete placement work on site is not required, and the leveling work is only required once for the entire sewage tank unit.
[0015]
Therefore, according to this method, construction on site is much simpler than before, and the time for curing the concrete is not required, so the construction period can be greatly shortened and the cost can be reduced. It becomes. Moreover, by manufacturing the foundation and upper concrete slab at the factory, the quality is stabilized and the durability reliability is improved.
[0016]
In addition, since the assembly process can be performed entirely at the factory, the assembly accuracy can be improved and stabilized, so that the durability reliability of the sewage tank unit can be further improved.
[0017]
Further, the sewage tank can be divided into an upper casing and a lower casing.BecauseThe design freedom of the shape of the sewage tank can be improved without impairing its formability. In addition, the upper and lower casings of the sewage tank and the foundation concrete board can be assembled at the same time.AndEven if the sewage tank is composed of a plurality of members, the number of assembling steps is not increased.
[0018]
Next, the claim2The invention is a foundation concrete plate manufactured in advance in the factory and installed at the bottom of the buried mine, a resin sewage tank placed on the upper surface of the foundation concrete plate and divided into an upper and lower casing, An upper concrete plate manufactured in advance in the factory and disposed at the upper part of the sewage tank so as to surround the opening on the upper surface thereof, and the upper casing and the basic concrete board of the sewage tank have a lower casing in the middle. It is connected by a connecting member in a sandwiched stateWith
The joints of the upper and lower casings of the sewage tank are respectively substantially horizontal toward the outside. And a metal annular member is placed on the upper surface of the flange of the upper casing, and the upper end portion of the connecting member is fixed to the annular member, while the lower end portion is foundation concrete. Fixed to the boardThis is a sewage tank unit.
[0019]
Since the sewage tank unit having the above-described configuration only needs to be installed inside the buried mine at the site, the work at the site is greatly simplified as in the first aspect of the invention. The period can be greatly shortened, the cost can be reduced, and the quality is stabilized and the durability reliability is improved. In addition, since the resin sewage tank has a structure that can be divided into two vertically, the shape design freedom can be improved without impairing the moldability. Moreover, even if the sewage tank is composed of a plurality of members as described above, they can be assembled at the same time as the foundation concrete plate, so that the number of assembling steps is not increased.
[0020]
Moreover,The upper and lower casings made of resin are closely attached to each other at the flange, and their joined state is stabilized, and the resin flange is reinforced by simply placing a metal annular member on the flange of the upper casing. In addition, the upper casing and the foundation concrete plate can be connected with sufficient strength by the connecting member.
[0021]
In addition, since the weight of the surrounding earth and sand effectively acts on the upper surface of the flange of the upper casing, this also stabilizes the joined state between the upper and lower casings, and the floating of the entire sewage tank A prevention effect is also obtained. An annular concrete member for preventing levitation may be further placed on the upper surface of the flange of the upper casing. In this case, the annular concrete member is also manufactured in advance in the factory and integrated as a sewage tank unit. Is preferred.
[0022]
Claims3The present invention includes a foundation concrete plate manufactured in advance in a factory and installed at the bottom of a buried mine, a resin sewage tank placed on the upper surface of the foundation concrete board, and a sewage tank manufactured in advance in the factory. And an upper concrete plate disposed so as to surround the opening on the upper surface of the upper concrete plate, the upper concrete plate and the foundation concrete plate are connected by a connecting support column, and a sewage tank is sandwiched between them. The sewage tank unit is characterized in that a holding member is provided to hold the lower end of the sewage tank with respect to the upper surface of the foundation concrete plate so as to restrict at least movement along the surface. .
[0023]
The sewage tank unit configured as described above is claimed in claim2As in the case of the present invention, the work at the site is greatly simplified, the construction period can be greatly shortened, the cost can be reduced, the quality is stabilized, and the durability reliability is improved. In addition, by arranging the connection support column between the upper concrete plate and the foundation concrete plate, the resistance against the load from above is improved, and a sewage tank is sandwiched between the upper concrete plate and the foundation concrete plate. Since these can be assembled at the same time, an increase in the number of assembly steps can be prevented.
[0024]
Furthermore, since the holding member which hold | maintains the lower end part of a sewage tank with respect to the upper surface of a foundation concrete board at least along the surface is provided, the sewage between an upper concrete board and a foundation concrete board is provided. The tank is more reliably held.
[0025]
Claim4The present invention includes a foundation concrete plate manufactured in advance in a factory and installed at the bottom of a buried mine, a resin sewage tank placed on the upper surface of the foundation concrete board, and a sewage tank manufactured in advance in the factory. And an upper concrete plate attached so as to surround the opening on the upper surface thereof, and the attachment portions provided at the upper end portion and the lower end portion of the sewage tank are respectively fixed to the upper concrete plate and the foundation concrete plate by fastening members. This is a sewage tank unit.
[0026]
The sewage tank unit configured as described above is claimed in claim2And claims3Similar to the invention of the present invention, the work at the site is greatly simplified, the construction period can be greatly shortened, the cost can be reduced, the quality is stabilized, and the durability reliability is improved.
[0027]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0028]
(Embodiment 1)
1 and 2 show a home drainage pump unit A that temporarily stores wastewater from a general household and then pumps it to a sewer pipe as a sewage tank unit according to the present invention. It is a relatively small one that is buried in a place where a large load is not applied, such as a backyard. The
[0029]
On the upper surface of the
[0030]
The head (upper end) of each
[0031]
On the other hand, a diameter-reduced
[0032]
The foundation
[0033]
In addition, what is shown as the code |
[0034]
Next, the schematic configuration inside the pump unit A and its function will be described mainly with reference to FIG. 2. As shown in the drawing, the side wall on one side (left side in the figure) of the
[0035]
Furthermore, a bubble-type water
[0036]
The
[0037]
(Method of burying sewage tank)
Next, the procedure for burying the
[0038]
On the other hand, in the burial site of the
[0039]
Then, as shown in FIG. 1, when the upper
[0040]
Therefore, according to the embedding method of the sewage tank according to this embodiment, first, the foundation
[0041]
And since the pump unit A assembled in this way is only transported to the burial site and installed horizontally in the burial pit H, the concrete placement work at the burial site becomes unnecessary, and the leveling The work will be minimal, and the work on site will be much simpler. Moreover, since the time for curing the concrete is eliminated, the construction period can be greatly shortened, and the cost can be reduced.
[0042]
In addition, in this embodiment, since the
[0043]
(Embodiment 2)
FIG. 4 shows an example of a pump unit A according to
[0044]
The upper
[0045]
Further, four
[0046]
Therefore, according to the pump unit A according to the second embodiment, similarly to the first embodiment, the basic
[0047]
Moreover, since the
[0048]
Moreover, since the
[0049]
The
[0050]
(Embodiment 3)
FIG. 5 shows an example of a pump unit A according to
[0051]
And in the pump unit A of this
[0052]
Therefore, according to the pump unit A according to the third embodiment, the work on the burial site is greatly simplified, the construction period can be greatly shortened, and the cost can be reduced, as in the first and second embodiments. At the same time, durability, durability and reliability are improved.
[0053]
In addition, the structure of this invention is not limited to the thing of the said Embodiment 1-3, It includes other various structures. That is, for example, in each of the above embodiments, the sewage tank unit of the present invention is applied to the residential drainage pump unit A, but is not limited thereto, and may be applied to, for example, a septic tank.
[0054]
【The invention's effect】
As described above, according to the method for burying a sewage tank according to the invention of
[0055]
Moreover, the durability reliability of a sewage tank unit can be further improved by assembling a sewage tank and a concrete board in a factory.
[0056]
furtherSince the resin sewage tank can be divided vertically, the design freedom of the shape of the sewage tank can be improved without impairing its moldability. And since two casings and a foundation concrete board can be assembled simultaneously, an increase in an assembly man-hour is not caused.
[0057]
Claim2The sewage tank unit according to the invention is suitable for the burying method according to the invention of the first aspect, can greatly simplify the work at the burial site, can greatly shorten the construction period, and can reduce the cost. Can improve durability and reliability,In addition, the degree of freedom in designing the sewage tank can be improved.
[0058]
AlsoA flange is provided at the joint between the upper and lower casings of the sewage tank, and a metal annular member is placed on the flange and fixed to the foundation concrete plate by a connecting member. In addition to being stable, the resin upper casing can be connected to the foundation concrete plate with sufficient strength without any particular reinforcement. In addition, the joining state of the casings is stabilized by the weight of the earth and sand acting on the upper surface of the flange, and the effect of preventing the entire sewage tank from rising is also obtained.
[0059]
Claim3According to the sewage tank unit according to the invention of claim2As in the case of, the integrated sewage tank unit only needs to be installed almost horizontally inside the buried mine, so the work at the buried site can be greatly simplified, the construction period can be greatly shortened, and the cost can be reduced. In addition, durability and reliability can be improved. Furthermore, by providing the connection support column, it is possible to improve the yield strength against the load from above, and it is possible to assemble the concrete plate and the sewage tank at the same time, thereby preventing an increase in the number of assembly steps.
[0060]
Moreover, the holding state of the sewage tank can be made more reliable by holding the lower end portion of the sewage tank by the holding member.
[0061]
Claim4According to the sewage tank unit according to the invention of claim2,3As in the case of this invention, it is only necessary to install an integrated sewage tank unit approximately horizontally inside the buried mine, so the work at the buried site can be greatly simplified, the construction period can be greatly shortened, and the cost can be reduced. Moreover, durability reliability can be improved.
[Brief description of the drawings]
FIG. 1 is an explanatory view showing a state before a pump unit according to
FIG. 2 is a diagram showing a schematic configuration inside a pump unit.
FIG. 3 is an explanatory diagram of an operation for housing a pump unit in a buried mine.
FIG. 4 is a view corresponding to FIG. 1 according to the second embodiment.
FIG. 5 is a view corresponding to FIG. 1 according to the third embodiment.
[Explanation of symbols]
A House drainage pump unit (sewage tank unit)
1,29 Sewage tank
2 Lower casing
2a Flange
3 Upper casing
3b flange
4 foundation concrete board
5 Presser bracket (annular member)
6 Connecting members
7 volts
8 Turnbuckle
9 Anchor bolt
10, 30, 33 Upper concrete board
31 Connecting support pillar
32 Bracket (holding member, mounting part)
33 Mounting angle (holding member, mounting part)
Claims (4)
埋設現場の地面を掘削して、前記汚水槽ユニット全体を収容可能な埋設坑を形成する掘削工程と、
前記掘削工程で形成した埋設坑の底部に前記基礎コンクリート板を設置して、当該埋設坑の内部に前記汚水槽ユニットを収容する設置工程とを備え、
前記汚水槽が、上側ケーシングと下側ケーシングとに分割されており、
前記組立工程では、前記上側ケーシングと基礎コンクリート板とを連結部材により連結して、それらの中間に下側ケーシングを挟持させるようにし、
前記組立工程を全て工場で行って、一体化した汚水槽ユニットを埋設現場に搬送することを特徴とする汚水槽の埋設方法。The resin sewage tank is placed on the foundation concrete board, and the upper concrete board is disposed on the upper part of the sewage tank so as to surround the opening on the upper surface, and the foundation concrete board, the sewage tank and the upper concrete board are disposed. A unit assembly process for assembling an integrated wastewater tank unit;
Excavation process of excavating the ground of the burial site to form a buried mine that can accommodate the entire sewage tank unit;
The established the foundation concrete plate to the bottom of the buried pit formed in the excavation process, and a setting step for accommodating the sewage tank units inside of the buried pit,
The sewage tank is divided into an upper casing and a lower casing,
In the assembly process, the upper casing and the foundation concrete plate are connected by a connecting member, and the lower casing is sandwiched between them,
A method for embedding a sewage tank, wherein all the assembly steps are performed in a factory, and the integrated sewage tank unit is conveyed to a burial site.
前記基礎コンクリート板の上面に載置され、上側及び下側ケーシングに分割可能な樹脂製の汚水槽と、A resin sewage tank placed on the upper surface of the foundation concrete plate and separable into upper and lower casings;
予め工場で製作され、前記汚水槽の上部にその上面の開口部を囲むようにして配設された上部コンクリート板とを備え、It is manufactured in advance in a factory, and is provided with an upper concrete plate disposed so as to surround the opening on the upper surface of the sewage tank,
前記汚水槽の上側ケーシングと基礎コンクリート板とが、その中間に下側ケーシングを挟持した状態で連結部材により連結されており、The upper casing and the foundation concrete plate of the sewage tank are connected by a connecting member with the lower casing sandwiched between them,
前記汚水槽の上側及び下側ケーシングの接合部には、それぞれ、外方に向かって略水平に延出するフランジが形成され、Each of the joints of the upper and lower casings of the sewage tank is formed with a flange extending substantially horizontally toward the outside,
前記上側ケーシングのフランジの上面に金属製の環状部材が載置され、A metal annular member is placed on the upper surface of the flange of the upper casing,
前記連結部材は、その上端部が前記環状部材に固定される一方、下端部が基礎コンクリート板に固定されていることを特徴とする汚水槽ユニット。The connecting member has a top end fixed to the annular member and a bottom end fixed to a foundation concrete plate.
前記基礎コンクリート板の上面に載置された樹脂製の汚水槽と、
予め工場で製作され、前記汚水槽の上部にその上面の開口部を囲むようにして配設された上部コンクリート板とを備え、
前記上部コンクリート板と基礎コンクリート板とが連結支持柱により連結されていて、該上部コンクリート板と基礎コンクリート板との間に汚水槽が挟持されているとともに、
上記汚水槽の下端部を基礎コンクリート板の上面に対して、少なくともその面に沿う移動を規制するように保持する保持部材が設けられている
ことを特徴とする汚水槽ユニット。 A foundation concrete plate that is manufactured in advance at the factory and installed at the bottom of the underground mine,
A resin sewage tank placed on the upper surface of the foundation concrete plate;
It is manufactured in advance in a factory, and is provided with an upper concrete plate disposed so as to surround the opening on the upper surface of the sewage tank,
The upper concrete plate and the foundation concrete plate are connected by a connection support column, and a sewage tank is sandwiched between the upper concrete plate and the foundation concrete plate,
A sewage tank unit, comprising: a holding member that holds the lower end of the sewage tank with respect to the upper surface of the foundation concrete plate so as to restrict at least movement along the surface .
前記基礎コンクリート板の上面に載置された樹脂製の汚水槽と、
予め工場で製作され、前記汚水槽の上部にその上面の開口部を囲むようにして取り付けられた上部コンクリート板とを備え、
前記汚水槽の上端部及び下端部に設けられた取付部がそれぞれ締結部材により上部コンクリート板及び基礎コンクリート板に固定されていることを特徴とする汚水槽ユニット。 A foundation concrete plate that is manufactured in advance at the factory and installed at the bottom of the underground mine,
A resin sewage tank placed on the upper surface of the foundation concrete plate;
An upper concrete plate manufactured in advance in the factory and attached to the upper part of the sewage tank so as to surround the opening on the upper surface thereof,
The sewage tank unit, wherein attachment parts provided at an upper end part and a lower end part of the sewage tank are respectively fixed to an upper concrete plate and a foundation concrete plate by fastening members .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002126238A JP3981587B2 (en) | 2002-04-26 | 2002-04-26 | Method for burying sewage tank and sewage tank unit used in the method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002126238A JP3981587B2 (en) | 2002-04-26 | 2002-04-26 | Method for burying sewage tank and sewage tank unit used in the method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003313937A JP2003313937A (en) | 2003-11-06 |
JP3981587B2 true JP3981587B2 (en) | 2007-09-26 |
Family
ID=29540712
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002126238A Expired - Fee Related JP3981587B2 (en) | 2002-04-26 | 2002-04-26 | Method for burying sewage tank and sewage tank unit used in the method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3981587B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5000771B2 (en) * | 2011-01-31 | 2012-08-15 | 株式会社カンケン | Septic tank installation structure |
-
2002
- 2002-04-26 JP JP2002126238A patent/JP3981587B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2003313937A (en) | 2003-11-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3981587B2 (en) | Method for burying sewage tank and sewage tank unit used in the method | |
GB2369400A (en) | Underground water storage system | |
KR102169152B1 (en) | concrete form of sewage disposal tank using wave steel pipe | |
KR101761779B1 (en) | Method for constructing base-inserting steel sump | |
KR20150073562A (en) | Sump supported by a concrete foundation | |
JP3888174B2 (en) | Temporary deadline construction method | |
WO1994020341A1 (en) | Fuel station and method for assembling of the same | |
JP5038975B2 (en) | Anti-levitation manhole structure | |
KR102338259B1 (en) | Septic system and the construction method thereof | |
JP4679402B2 (en) | Outdoor drainage equipment for unequal settlement and its installation method | |
RU2728224C1 (en) | Assembly method of modular pumping station of waste water pumping | |
US6247490B1 (en) | Booster station | |
KR100408926B1 (en) | The contructing method of FRP box culvert and structure | |
KR20020033686A (en) | Drainage System using Hexa-Tube Connector | |
KR200341018Y1 (en) | A mold for drainage | |
JP2005113501A (en) | Foundation pile-cum-storage tank, method of constructing the same, and method of using stored water | |
JP6313533B2 (en) | Buried tank and its construction method | |
KR20070047925A (en) | Construction work method of rain water chamber and that structure | |
KR100195787B1 (en) | Construction method of pit for vacuum valve | |
JP7240279B2 (en) | Underground reservoir | |
JP2001279696A (en) | Structure of small-sized manhole | |
JP2919467B1 (en) | Underground water storage tank and pit component used for its construction | |
KR200342267Y1 (en) | Hume concrete pipe establishment structure | |
WO2001009465A1 (en) | Vehicle washing hall | |
JP5960529B2 (en) | Concrete filtration tank |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20041104 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20041104 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060922 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20061003 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20061127 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070213 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070403 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070619 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070702 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100706 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100706 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110706 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120706 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120706 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130706 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130706 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130706 Year of fee payment: 6 |
|
LAPS | Cancellation because of no payment of annual fees |