JP3916911B2 - Shielding machine starting mechanism and starting method and temporary assembly segment with stopper used therefor - Google Patents
Shielding machine starting mechanism and starting method and temporary assembly segment with stopper used therefor Download PDFInfo
- Publication number
- JP3916911B2 JP3916911B2 JP2001308160A JP2001308160A JP3916911B2 JP 3916911 B2 JP3916911 B2 JP 3916911B2 JP 2001308160 A JP2001308160 A JP 2001308160A JP 2001308160 A JP2001308160 A JP 2001308160A JP 3916911 B2 JP3916911 B2 JP 3916911B2
- Authority
- JP
- Japan
- Prior art keywords
- temporary assembly
- shield machine
- stopper
- assembly segment
- segment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、シールド機発進機構と発進方法に関し、特に坑口ケーシングを用い、これに設置したシールド機をケーシングの後方に配備した仮組セグメントからの反力で発進させる際に、組立仮組セグメントの水平方向を保持して安全で精度の良い発進を図るシールド機発進機構および発進方法とそれに用いるストッパー付仮組セグメントに関する。
【0002】
【従来の技術】
シールド機を竪坑やシールドトンネルから発進させるためには、坑口からの漏水漏砂を完全に防止することが必要になることから、従来のシールド機発進は、一般的に坑口形成部にエントランスを設置して止水機構を形成すると共に、坑口形成部を囲繞している周辺の地盤に薬液注入による地盤改良部を形成している。
【0003】
この場合の地盤改良厚は、シールド機の軸長から竪坑壁の厚さを差し引いた値を最小値にする必要があり、誤差等を勘案することでその施工域を長大化させていた。
【0004】
又、従来からのシールド機発進としては、坑口に両端が解放した筒状のカプセル本体を設置しながら、この中部にシールド機を設置してカプセル本体の内面と仮組セグメントとの間に止水材を設けている例(特公平4−37916号公報参照)もあり、漏水漏砂を防止し、コスト、作業性及び安全性を良好にするとしているが、これらの特長は坑壁外径の大きさによって確保されていることから、コスト高の問題点を提起している。
【0005】
しかして、本発明者等は、以上の問題点を解決するために、図6の平断面図に示しているシールド機発進機構及び発進方法を既に提案してきた。(特願2001−208021号参照)
本シールド機発進機構では、シールド機1の軸長より短い軸長のケーシング2を竪坑壁4の内面に形成した坑口予定部15に対峙させており、ケーシング2にはシールド機1が設置されているが、坑口は、シールド機の直接切削で形成されることからシールド機の発進前には存在していない。
【0006】
ケーシング2の前端部5には、高水圧止水材であるエントランスパッキン6が装備された坑口ケーシング7が接合されており、エントランスパッキン6は高圧止水材としてシールド機が発進した過程においてシールド機1との間に遮水機構を形成するように構成している。
【0007】
同様に、ケーシング2の後端部8にはパッキン9が装備されており、シールド機1もしくはシールド機1の後部に設けられる仮組セグメント10との間に遮水機構を形成することを可能にしている。
【0008】
坑口ケーシング7を接合したケーシング2の軸長(L5)は、シールド機1の軸長より短いが、遮水機構を確保するための軸長値は、シールド機1の軸長(L1)から壁厚(L3)を差し引いた値以上の、L5>(L 1 −L 3 )から決定されるものであり、壁厚(L3)の設定に従ってケーシング2の軸長(L5)特定することによって遮水機構を有効に機能させるように構成している。
【0009】
又、シールド機1は、その後部に装備した元押しジャッキ11をその後方に配置されている反力壁3と鋼製反力12に配備している仮組セグメント10に当接させることで、ケーシング2から前方の坑口予定部15に向かって前進可能に構成されている。
【0010】
尚、シールド機1と仮組セグメント10との間にはテールシールパッキン13が配置されていることで通常通りに遮水されていると共に、地盤改良部14を坑口予定部15が形成される竪坑壁4の外面に配置することによってシールド機の発進時における止水処置を完全にしている。
【0011】
以上のようなシールド機1とケーシング2との関連構成は、ケーシング2の後端部8に装備されているパッキン9によって、シールド機1との間に遮水機構を形成することを可能にしており、これによってケーシング2の内部と竪坑壁4の内部とを遮断状態に形成している。
【0012】
従って、本シールド機発進機構では、パッキン9で形成する遮水機構を段階的に適宜に対応させることで坑口からの漏水漏砂を完全に防止すると共に、作業空間を確保しながら坑壁の外径を小さくしている。
【0013】
上述のように、坑口は、竪坑壁3の壁面におけるシールド機1の直接切削によって形成する形態に構成されていることから、竪坑壁4の坑口予定部15は、切削可能な低強度コンクリートを形成する貧配合コンクリートから成るNOMST壁等で構成されており、シールド機1の発進時までは坑口の形成は行われていない。
【0014】
このために、本シールド機発進機構は、竪坑壁に坑口を形成する鏡開きのための作業空間を不要にし、坑口を事前に設けることで発生する竪坑内への漏水漏砂を防止するための困難な設備を必要としていない。
【0015】
又、地盤改良部14は、本来的に竪坑内への漏水漏砂を防止することを目的にして坑外壁面に隣接する地盤に施工されるものであるが、本シールド機発進機構における地盤改良部14の場合は、上述のように竪坑壁に坑口を形成していないことから、地盤改良部14の形成は、竪坑壁の坑口予定部に相当する狭い範囲において薄い施工厚さで簡素に対処することが可能であり、予め坑口を形成する従来の方式と比較して、地盤改良部における大幅なコスト削減を図れるものであり、上記で提示した従来の問題点を全て解決していることになる。
【0016】
しかしながら、本提案のシールド機発進機構に限らず通常のシールド機においても同様であるが、その発進時には、反力を得るために設置する仮組セグメントがシールド機から出た際に、シールド機受け台と仮組セグメントとの間に隙間が生じることになるので、通常はこの間にキャンバー等を入れて仮組セグメントの落ち込みを防止するのが一般的である。
【0017】
しかして、ケーシングを用いてシールド機を発進させる場合には、仮組セグメントの殆どがケーシング2の内部に在ることから、キャンバー等を入れることが出来ずに、仮組セグメント10が宙に浮いた状態になっていた。
【0018】
このために、仮組セグメント10は、図7の側断面図で示すように下方に落ち込むことになる。このような現象は、結果的に仮組セグメントに座屈等を生じさせて適切な反力を得ることができない状態を形成させたり、エントランスパッキン6やパッキン9との間に形成される止水機構が、仮組セグメントの落ち込みによるシールド機の傾斜によって、密接な接触状態を維持できなくなって止水機構として確実に機能しない状態に陥るという問題点を生じていた。
【0019】
【発明が解決しようとする課題】
本発明は、以上の従来例が提起している各問題点に鑑みて改善するために提案するものであり、坑口ケーシングを用いても組立仮組セグメントの水平方向を保持して安全で精度の良い発進を図ると共に坑口からの漏水漏砂を完全に防止しながら、坑壁の外径を小さくし、地盤改良域の厚さを減少させて統合的な施工コストの低減を促進するシールド機発進機構および発進方法とそれに用いるストッパー付仮組セグメントを提供している。
【0020】
【課題を解決するための手段】
請求項1に記載の発明であるシールド機発進機構は、坑壁内面に配置したケーシングにシールド機を設置し、シールド機の後端に配備する仮組セグメントから反力を取ることでシールド機を発進するシールド機発進機構であって、配備される仮組セグメント中にストッパー付仮組セグメントが所定の間隔で配置され、ストッパー付仮組セグメントは、ケーシングに押し当てられて仮組セグメントの水平方向を維持するストッパーを、当該仮組セグメントにその外周面から突出可能に収納して構成されることを特徴としており、組立仮組セグメントの方向を保持することで坑口ケーシングを用いても組立仮組セグメントの座屈等を回避させて安全で精度の良い発進を図ると共に止水機構を確実に機能させて坑口からの漏水漏砂を完全に防止しながら、坑壁の外径を小さくし、地盤改良域の厚さを減少させて統合的な施工コストの低減を促進している。
【0021】
請求項2に記載の発明であるシールド機発進方法は、ケーシングに押し当てられて仮組セグメントの水平方向を維持するストッパーを、当該仮組セグメントにその外周面から突出可能に収納して構成したストッパー付仮組セグメントを用い、坑壁内面に配置したケーシングに設置したシールド機を坑口予定部に当接させる段階でストッパー付仮組セグメントを配置して、坑壁の切削を完了した段階でストッパー付仮組セグメントのストッパーを突出させることで仮組セグメントの水平方向を維持し、次いでシールド機が地盤改良部を掘削し始める段階でストッパー付仮組セグメントを配置して、地盤改良部の掘削を完了した段階でストッパー付仮組セグメントからストッパーを突出させると共に本セグメントを配置して本セグメントの水平方向を確保することを特徴としており、組立仮組セグメントの方向を保持して、組立仮組セグメントの座屈等を回避させると共に止水機構を確実に機能させることで坑口からの漏水漏砂を防止し安全で精度の高い発進を図っている。
【0022】
本発明によるストッパー付仮組セグメントは、請求項1又は2に記載されたシールド機発進機構もしくはシールド機発進方法に用いるストッパー付仮組セグメントであって、突出可能なストッパーを仮組セグメントに放射状に装備させて成り、組立仮組セグメントの水平方向を保持して安全で精度の良い発進を図っている。
【0023】
【発明の実施の形態】
本発明によるシールド機発進機構は、坑壁内面に配置したケーシングにシールド機を設置し、該シールド機の後端に配備する仮組セグメントから反力を取ることでシールド機を発進するシールド機発進機構であって、配備される仮組セグメント中にストッパー付仮組セグメントが所定の間隔で配置され、ストッパー付仮組セグメントは、ケーシングに押し当てられて仮組セグメントの水平方向を維持するストッパーを、当該仮組セグメントにその外周面から突出可能に収納して構成されることを特徴としている。
【0024】
以下に、本発明によるシールド機発進機構の一実施の形態を図面に基づいて詳細に説明するが、本実施の形態におけるシールド機発進機構は、配置したケーシングが、軸長を坑壁の厚さで特定され、設置するシールド機の軸長を該ケーシングより長くして、ケーシング後端とシールド機との間に遮水機構を装備すると共にケーシング前端に遮水部材を配置して成るシールド機発進機構に適用した例であり、理解を容易にするために従来と同様の部位については同一の符号を用いている。
【0025】
図1は、本発明によるシールド機発進機構の一実施の形態を示す概要図であり、 図1(a)は、仮組セグメントの背面図、図1(b)は、図1(a)を(b)−(b)矢視にした部分側断面図である。
【0026】
本実施の形態でのシールド機1は、図1(a)に示すようにケーシング2の支持架台23上に設置されており、ケーシング2は、図1(b)のように従来例と同様に先端部5に配置されている坑口ケーシング7を竪坑壁4の坑口予定部15に対峙させて配置している。
【0027】
仮組セグメント10は、表示を省略しているが、従来例と同様にその後方に配置されている反力コンクリートと鋼製反力に配備されており、ケーシング2の内面に設置されたシールド機1は、その後部に装備した元押しジャッキを仮組セグメント10に当接させることで、ケーシング2から前方の坑口予定部15に向かって前進可能に構成されている。
【0028】
図1(b)で示している工程の状態は、発明の理解を容易にするために、シールド機1が、ケーシング2から前方に前進して、竪坑壁4の坑口予定部15に到達している状態を示している。
【0029】
本工程までのシールド機1の前進については、ケーシングを設置してシールド機を発進させる通常の工法と同様であることから、その経過を省略しているが、ケーシング2の内面に設置されたシールド機1を、その後方に配置した空押用ジャッキによってシールド機のカッター盤が回転可能になる位置まで空押ししており、しかる後に、空押用ジャッキを撤去して反力コンクリートと鋼製反力とを配備している。
【0030】
仮組セグメント10は、シールド機1を竪坑壁4の坑口予定部15に到達するまで空押しした後に、鋼製反力に配備されるものであり、当初に1R、2Rを組み立てることでシールド機の元押しジャッキに当接させているが、本発明による発進機構には、仮組セグメントの方向保持装置が装備されているものであって、本実施の形態では、方向保持装置であるストッパー付仮組セグメント16が仮組セグメント2Rとして配置されている。
【0031】
次いで、シールド機1は、仮組セグメント10を元押しジャッキで押すことで、順次に3R、4Rと組み立てしながら竪坑壁4を切削して行くが、竪坑壁4の切削を終えた状態では、仮組セグメント10の間に組み込まれたストッパー付仮組セグメント16が、シールド機1の後端から出るような位置関係になるように配慮されている。
【0032】
ストッパー付仮組セグメント16は、組み立てた仮組セグメント10がシールド機1の発進に連れて、その後端から外れることで段差が発生しても、仮組セグメント10が下方に落ち込まないように対処するものであり、内面に装備してあるストッパー17を外周面から適宜の長さに突出させて、ケーシング2に設けられたセグメント支持架台18に押し当てるように構成されている。
【0033】
そして、ストッパー付仮組セグメントに設けるストッパーは、図2の部分拡大図に示す実施形態のように構成されている。
【0034】
ストッパー17は、仮組セグメント20の内面に装備されており、その心棒21を仮組セグメント20の外周面に穿孔した面板穴22から突出できるように構成されている。心棒21は、先端23を丸棒に形成すると共に基礎部分24にはオネジ25と把握部26とを形成しており、基礎部分24は、仮組セグメント20の内面に溶接付けによって固着されてコンクリート中に埋め込まれている支持部27のメネジと螺合して進退可能に構成されている。
【0035】
ストッパー17は、常時は仮組セグメント20の内部に収納されているが、把握部26をスパナー等で回転させることで心棒21を仮組セグメント20の外周面から突出させることが出来るものであり、組み立てた仮組セグメント10がシールド機1の後端から外れた際に仮組セグメント10が下方に落ち込まない適宜な長さに突出させることができる。
【0036】
以上のように、本発明によるシールド機発進機構は、上記一実施の形態のように構成することによって、坑口ケーシングを用いても組立仮組セグメントの座屈等を回避させて安全で精度の良い発進を図ると共に止水機構を確実に機能させて坑口からの漏水漏砂を完全に防止しながら、坑壁の外径を小さくし、地盤改良域の厚さを減少させて施工コストを統合的に低減している。
【0037】
次に、本発明によるシールド機の発進方法について説明する。本発明によるシールド機の発進方法は、上記一実施の形態で説明したシールド機発進機構において、シールド機を坑口予定部に当接させる段階でストッパー付仮組セグメントを配置して、坑壁の切削を完了した段階でストッパー付仮組セグメントのストッパーを突出させることで仮組セグメントの水平方向を維持し、次いでシールド機が地盤改良部を掘削し始める段階でストッパー付仮組セグメントを配置して、地盤改良部の掘削を完了した段階でストッパー付仮組セグメントからストッパーを突出させると共に本セグメントを配置して本セグメントの水平方向を確保することを特徴としている。
【0038】
以下に、本発明によるシールド機の発進方法についてその一実施の形態を図面に基づいて詳細に説明する。
【0039】
図3は、本発明によるシールド機の発進方法において、シールド機が竪坑壁の坑口予定部に対する切削を完了した工程での側断面図である。
【0040】
シールド機1は、仮組セグメント10を3R、4Rと組み立てながら発進状態に移行しており、この段階では、シールド機1の発進に連れて2Rとして配置されていたストッパー付仮組セグメント16が、シールド機1の後端から外れることで段差が発生する。
【0041】
しかして、本発明では、ストッパー付仮組セグメント16の内面に装備してあるストッパー17の心棒21を、仮組セグメントの外周面から適宜の長さに突出させて、ケーシング2のセグメント支持架台18に押し当てるように調整することができるので、仮組セグメント10が下方に落ち込むことがない。
【0042】
同様に、図4は、竪坑壁の切削を完了したシールド機が、地盤改良部の掘削を完了して地盤の掘進に至る工程での断面図である。
【0043】
本工程におけるシールド機1は、段差の発生によって発生する可能性が危惧される位置に相当する仮組セグメント5Rとして、ストッパー付仮組セグメント16を配置しながら仮組セグメント6Rを組み立てることで前進を続けて地盤改良部の掘削から地盤の掘進に至っており、本セグメント19の1Rを設置する段階にある。
【0044】
この段階では、シールド機1の発進に連れて第2に5Rとして配置したストッパー付仮組セグメント16がシールド機1の後端から外れるので、ストッパー付仮組セグメント16の内面に装備してあるストッパー17の心棒21をセグメント支持架台18に押し当てるように調整しており、仮組セグメント10が下方に落ち込むのを防止している。
【0045】
従って、本発明による発進方法では、仮組セグメント10がその水平方向を確実に維持しており、これによって、シールド機が竪坑から地盤中に発進する時にも組み立てた仮組セグメント10の座屈等を回避させて、安全で精度の良い発進を図ると共に、ケーシング2とその前端部5に接合されている坑口ケーシング7に装備されたエントランスパッキン6との間及び仮組セグメント10とケーシング2の後端部8に装備されているパッキン9の間に形成されている各止水機構を確実に機能させており、坑口からの漏水漏砂を完全に防止している。
【0046】
尚、本発明による発進機構と発進方法は、上記した一実施の形態に限定されるものでなく、シールド機の発進にケーシングを用いる方式の発進機構であれば当然に適用可能である。
【0047】
上記の各実施形態に用いている本発明によるストッパー付仮組セグメントは、突出可能なストッパーを仮組セグメントの外周面に放射状に装備させている。
【0048】
図5は、本発明によるストッパー付仮組セグメントの実施の形態を示す斜視図であり、上記実施の形態と同様の部位については同一の符号で説明する。
【0049】
ストッパー付仮組セグメント16は、仮組セグメント20の内面に一つもしくは複数のストッパー17を装備して構成されており、図2の実施の形態で説明したように、仮組セグメント20の外周面に穿孔した面板穴22からその心棒21を突出できるように構成されている。
【0050】
心棒21は、基礎部分にはオネジと把握部とを形成して、把握部を回転させることで進退可能に構成されており、外周面から適宜の長さに突出させて、ケーシングに設けられたセグメント支持架台に押し当てることで、組み立てた仮組セグメントがシールド機の後端から外れて段差が発生しても、仮組セグメントが下方に落ち込まないように機能している。
【0051】
従って、ストッパー17の配置は、仮組セグメント20の直下に単独に設けても良いが、ストッパー付仮組セグメント16の安定性を考慮すると、図示のように2個以上の複数のストッパー17を放射状に所定の間隔で装備することが望ましいものである。
【0052】
しかして、本発明によるシールド機発進機構と発進方法は、上記各実施の形態で説明したシールド機発進機構と発進方法において、シールド機の後端に配備する仮組セグメント中に、所定の間隔でストッパー付仮組セグメントを仮組配置することによっても構成できるものである。
【0053】
以上、本発明によるシールド機発進機構および発進方法とそれに用いるストッパー付仮組セグメントを各実施の形態に基づいて詳細に説明してきたが、本発明は上記実施の形態に何ら限定されるものでなく、竪坑、隧道、トンネル等の適用分野、ケーシング、仮組セグメント等の具体的な形状や材質に関する変更においても発明の趣旨に反しない範囲において種々の変更が包含されることは当然のことである。
【0054】
【発明の効果】
請求項1に記載のシールド機発進機構は、坑壁内面に配置したケーシングにシールド機を設置し、シールド機の後端に配備する仮組セグメントから反力を取ることでシールド機を発進するシールド機発進機構であって、配備される仮組セグメント中にストッパー付仮組セグメントが所定の間隔で配置され、ストッパー付仮組セグメントは、ケーシングに押し当てられて仮組セグメントの水平方向を維持するストッパーを、当該仮組セグメントにその外周面から突出可能に収納して構成されることを特徴としており、組立仮組セグメントの方向を保持することで坑口ケーシングを用いても組立仮組セグメントの座屈等を回避させて安全で精度の良い発進を図ると共に止水機構を確実に機能させて坑口からの漏水漏砂を完全に防止しながら、坑壁の外径を小さくし、地盤改良域の厚さを減少させて統合的な施工コストの低減を促進している。
【0055】
請求項2に記載の発明であるシールド機発進方法は、ケーシングに押し当てられて仮組セグメントの水平方向を維持するストッパーを、当該仮組セグメントにその外周面から突出可能に収納して構成したストッパー付仮組セグメントを用い、坑壁内面に配置したケーシングに設置したシールド機を坑口予定部に当接させる段階でストッパー付仮組セグメントを配置して、坑壁の切削を完了した段階でストッパー付仮組セグメントのストッパーを突出させることで仮組セグメントの水平方向を維持し、次いでシールド機が地盤改良部を掘削し始める段階でストッパー付仮組セグメントを配置して、地盤改良部の掘削を完了した段階でストッパー付仮組セグメントからストッパーを突出させると共に本セグメントを配置して本セグメントの水平方向を確保することを特徴としており、組立仮組セグメントの方向を保持して、組立仮組セグメントの座屈等を回避させると共に止水機構を確実に機能させることで坑口からの漏水漏砂を防止し安全で精度の高い発進を図れる効果を奏している。
【0056】
本発明によるストッパー付仮組セグメントは、請求項1又は2に記載されたシールド機発進機構もしくはシールド機発進方法に用いるストッパー付仮組セグメントであって、突出可能なストッパーを仮組セグメントに放射状に装備させて成り、組立仮組セグメントの水平方向を保持して安全で精度の良い発進させる効果を奏している。
【図面の簡単な説明】
【図1】本発明によるシールド機発進機構の概要図
【図2】本発明によるシールド機発進機構に用いるストッパーの断面図
【図3】本発明によるシールド機発進機構でシールド機による竪坑壁の切削完了状態図
【図4】本発明によるシールド機発進機構でシールド機による地盤改良部の掘削状態図
【図5】本発明によるストッパー付仮組セグメントの斜視図
【図6】従来におけるシールド機発進機構の概要図
【図7】従来における仮組セグメントの落ち込み状態を示す側断面図
【符号の説明】
1 シールド機、2 ケーシング、3 反力壁、4 竪坑壁、5 前端部、6 エントランスパッキン、7 坑口ケーシング、8 後端部、9 パッキン、10 仮組セグメント、11 元押しジャッキ、12 鋼製反力、13 テールシールパッキン、14 地盤改良部、15 坑口予定部、16 ストッパー付仮組セグメント、17 ストッパー、18 セグメント支持架台、19 本セグメント、20 仮組セグメント、21 心棒、22 面板穴、23 先端、24 基礎部分、25 オネジ、26 把握部、27 支持部 [0001]
BACKGROUND OF THE INVENTION
The present invention relates to a shield machine starting mechanism and a starting method, and more particularly, when a shield machine installed in a wellhead casing is started by a reaction force from a temporary assembly segment disposed behind the casing, The present invention relates to a shield machine starting mechanism and a starting method for maintaining a horizontal direction and starting safely and accurately, and a temporary assembly segment with a stopper used therefor .
[0002]
[Prior art]
In order to start the shield machine from the shaft or shield tunnel, it is necessary to completely prevent water leakage from the wellhead, so the conventional shield machine start is generally installed at the entrance Thus, a water stopping mechanism is formed, and a ground improvement portion by chemical injection is formed on the surrounding ground surrounding the well opening forming portion.
[0003]
In this case, the ground improvement thickness needs to be a minimum value obtained by subtracting the thickness of the shaft wall from the shaft length of the shield machine, and the construction area has been lengthened by taking into account errors and the like.
[0004]
In addition, as a conventional shield machine start-up, a cylindrical capsule body with both ends open is installed at the wellhead, and a shield machine is installed in the middle to stop water between the inner surface of the capsule body and the temporary assembly segment. There is also an example (see Japanese Patent Publication No. 4-37916) that has been provided with materials, which prevents water leakage and sand and improves cost, workability and safety. Because it is secured by size, it raises the problem of high costs.
[0005]
Thus, the present inventors in order to solve the above problems, a shield machine start mechanism and start methods are shown in cross-sectional plan view of FIG. 6 has been already proposed. (See Japanese Patent Application No. 2001-208021)
In this shield machine starting mechanism, a
[0006]
A
[0007]
Similarly, a packing 9 is provided at the rear end 8 of the
[0008]
The axial length (L 5 ) of the
[0009]
Moreover, the
[0010]
In addition, the
[0011]
The related configuration of the
[0012]
Accordingly, in this shield machine starting mechanism, the water-blocking mechanism formed by the packing 9 is appropriately handled in a stepwise manner to completely prevent water leakage from the wellhead and to secure the work space. The diameter is reduced.
[0013]
As described above, since the wellhead is formed in a form formed by direct cutting of the
[0014]
For this reason, this shield machine start mechanism eliminates the need for a work space for mirror opening to form a wellhead in the shaft wall, and it is difficult to prevent water leakage and sand from entering the shaft by providing the wellhead in advance. Does not require any special equipment.
[0015]
In addition, the
[0016]
However, this applies not only to the proposed shield machine start mechanism, but also to ordinary shield machines. At the time of start, when the temporary assembly segment installed to obtain reaction force comes out of the shield machine, Since a gap is generated between the table and the temporary assembly segment, it is common to prevent the temporary assembly segment from dropping by inserting a camber or the like between them.
[0017]
Thus, when starting the shield machine using the casing, most of the temporary assembly segments are inside the
[0018]
Therefore,
[0019]
[Problems to be solved by the invention]
The present invention is proposed in order to improve in view of the respective problems raised by the above conventional example, and even if a wellhead casing is used, the horizontal direction of the assembly temporary assembly segment is maintained and the safety and accuracy are maintained. Shield machine launch that promotes reduction of integrated construction cost by reducing the outer diameter of the pit wall and reducing the thickness of the ground improvement area while ensuring good start and completely preventing water leakage from the pit A mechanism and a starting method and a temporary assembly segment with a stopper used therefor are provided.
[0020]
[Means for Solving the Problems]
The shield machine starting mechanism according to the first aspect of the present invention includes a shield machine installed in a casing disposed on the inner surface of a well wall, and the shield machine is obtained by taking a reaction force from a temporary assembly segment disposed at the rear end of the shield machine. A shield machine starting mechanism for starting, wherein temporary provisional segments with stoppers are arranged at predetermined intervals in the provisional temporary assembly segments, and the temporary assembly segments with stoppers are pressed against the casing in the horizontal direction of the temporary assembly segments. The stopper is maintained so that it can be protruded from the outer peripheral surface of the temporary assembly segment so that the assembly temporary assembly can be used even if the wellhead casing is used by maintaining the direction of the assembly temporary assembly segment. Avoiding buckling of the segment, etc. to ensure safe and accurate start-up and ensure that the water stop mechanism functions reliably to prevent water leakage from the wellhead. Et al., The outer diameter of pit wall is reduced, and promotes the reduction of integrated construction cost by reducing the thickness of the ground improvement region.
[0021]
The shield machine starting method according to
[0022]
The temporary assembly segment with a stopper according to the present invention is a temporary assembly segment with a stopper used in the shield machine starting mechanism or the shield machine starting method according to
[0023]
DETAILED DESCRIPTION OF THE INVENTION
The shield machine start mechanism according to the present invention is a shield machine start mechanism in which a shield machine is installed in a casing disposed on the inner surface of a mine wall, and the shield machine is started by taking a reaction force from a temporary assembly segment provided at the rear end of the shield machine. a mechanism, temporary assembly segments with stopper are arranged at predetermined intervals in the temporary assembly segment is deployed, temporary assembly segments with stopper is a stopper to keep the horizontal temporarily assembled segments is pressed against the casing The temporary assembly segment is configured to be housed so as to protrude from the outer peripheral surface thereof .
[0024]
Hereinafter, an embodiment of a shield machine starting mechanism according to the present invention will be described in detail with reference to the drawings. The shield machine starting mechanism according to the present embodiment has a casing whose axial length is the thickness of a well wall. The shield machine start is made by making the shaft length of the shield machine to be specified longer than that of the casing and providing a water shielding mechanism between the rear end of the casing and the shield machine and arranging a water shielding member at the casing front end. This is an example applied to a mechanism, and the same reference numerals are used for the same parts as in the prior art in order to facilitate understanding.
[0025]
FIG. 1 is a schematic view showing an embodiment of a shield machine starting mechanism according to the present invention, FIG. 1 (a) is a rear view of a temporary assembly segment, and FIG. 1 (b) is a view of FIG. 1 (a). (B)-(b) It is the partial sectional side view made into the arrow view.
[0026]
The
[0027]
The
[0028]
In order to facilitate the understanding of the invention, the state of the process shown in FIG. 1 (b) is that the
[0029]
The forward movement of the
[0030]
The
[0031]
Next, the
[0032]
The
[0033]
And the stopper provided in the temporary assembly segment with a stopper is comprised like embodiment shown in the elements on larger scale of FIG.
[0034]
The
[0035]
The
[0036]
As described above, the shield machine starting mechanism according to the present invention is configured as in the above-described embodiment, so that even if a wellhead casing is used, buckling of the assembled temporary assembly segment is avoided, and the safety is high. The construction cost is integrated by reducing the outer diameter of the pit wall and reducing the thickness of the ground improvement area, while starting and at the same time functioning the water stop mechanism to completely prevent leakage of sand from the pit. Has been reduced.
[0037]
Next, the starting method of the shield machine according to the present invention will be described. The shield machine start method according to the present invention is the shield machine start mechanism described in the above embodiment, wherein the temporary assembly segment with a stopper is disposed at the stage where the shield machine is brought into contact with the planned wellhead portion, and the well wall is cut. The horizontal direction of the temporary assembly segment is maintained by projecting the stopper of the temporary assembly segment with stopper at the stage of completing, and then the temporary assembly segment with stopper is arranged at the stage where the shield machine begins to excavate the ground improvement part, When the excavation of the ground improvement part is completed, the stopper is protruded from the temporary assembly segment with a stopper and the segment is arranged to ensure the horizontal direction of the segment.
[0038]
In the following, an embodiment of a method for starting a shield machine according to the present invention will be described in detail with reference to the drawings.
[0039]
FIG. 3 is a cross-sectional side view of the shield machine start method according to the present invention in a process in which the shield machine has finished cutting the planned wellhead portion of the shaft wall.
[0040]
The
[0041]
Thus, in the present invention, the
[0042]
Similarly, FIG. 4 is a cross-sectional view in a process in which the shield machine that has completed the cutting of the shaft wall completes excavation of the ground improvement portion and proceeds to the ground excavation.
[0043]
The
[0044]
At this stage, as the
[0045]
Therefore, in the starting method according to the present invention, the
[0046]
The starting mechanism and the starting method according to the present invention are not limited to the above-described embodiment, and can naturally be applied to any starting mechanism using a casing for starting the shield machine.
[0047]
The temporary assembly segment with stopper according to the present invention used in each of the above embodiments is provided with radially projecting stoppers that can protrude.
[0048]
FIG. 5 is a perspective view showing an embodiment of a temporary assembly segment with a stopper according to the present invention. The same parts as those in the above embodiment will be described with the same reference numerals.
[0049]
The
[0050]
The
[0051]
Therefore, the
[0052]
Thus, the shield machine start mechanism and start method according to the present invention are the shield machine start mechanism and start method described in each of the above embodiments, at a predetermined interval in the temporary assembly segment provided at the rear end of the shield machine. It can also be configured by temporarily assembling the temporary assembly segments with stoppers.
[0053]
As described above, the shield machine starting mechanism and the starting method according to the present invention and the temporary assembly segment with a stopper used therefor have been described in detail based on the respective embodiments, but the present invention is not limited to the above-described embodiments. It should be understood that various modifications may be included within the scope of the invention even in a change in specific shapes and materials such as application fields such as shafts, tunnels, tunnels, casings, temporary assembly segments, and the like. .
[0054]
【The invention's effect】
The shield machine starting mechanism according to
[0055]
The shield machine starting method according to
[0056]
The temporary assembly segment with a stopper according to the present invention is a temporary assembly segment with a stopper used in the shield machine starting mechanism or the shield machine starting method according to
[Brief description of the drawings]
FIG. 1 is a schematic view of a shield machine starting mechanism according to the present invention. FIG. 2 is a sectional view of a stopper used in the shield machine starting mechanism according to the present invention. Completion state diagram [FIG. 4] Excavation state diagram of ground improvement part by shield machine with shield machine start mechanism according to the present invention [FIG. 5] Perspective view of temporary assembly segment with stopper according to the present invention
FIG. 6 is a schematic diagram of a conventional shield machine starting mechanism.
FIG. 7 is a side sectional view showing a conventional temporary assembly segment drop state.
1 shielding machine, 2 casing, 3 reaction wall, 4 shaft wall, 5 front end, 6 entrance packing, 7 well casing, 8 rear end, 9 packing, 10 temporary assembly segment, 11 former jack, 12 steel reaction Force, 13 Tail seal packing, 14 Ground improvement part, 15 Wellhead planned part, 16 Temporary assembly segment with stopper, 17 Stopper, 18 segment support base, 19 segments, 20 Temporary assembly segment, 21 Mandrel, 22 Face plate hole, 23 Tip , 24 foundation part, 25 male screw, 26 grasping part, 27 support part
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001308160A JP3916911B2 (en) | 2001-10-04 | 2001-10-04 | Shielding machine starting mechanism and starting method and temporary assembly segment with stopper used therefor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001308160A JP3916911B2 (en) | 2001-10-04 | 2001-10-04 | Shielding machine starting mechanism and starting method and temporary assembly segment with stopper used therefor |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2006299096A Division JP4279307B2 (en) | 2006-11-02 | 2006-11-02 | Shield machine start mechanism and start method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003113697A JP2003113697A (en) | 2003-04-18 |
JP3916911B2 true JP3916911B2 (en) | 2007-05-23 |
Family
ID=19127508
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001308160A Expired - Fee Related JP3916911B2 (en) | 2001-10-04 | 2001-10-04 | Shielding machine starting mechanism and starting method and temporary assembly segment with stopper used therefor |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3916911B2 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7134079B2 (en) * | 2018-12-05 | 2022-09-09 | 大成建設株式会社 | reaction force receiving structure |
CN109488319B (en) * | 2018-12-17 | 2024-03-08 | 中国铁建重工集团股份有限公司 | Tunneling machine |
CN113418647B (en) * | 2021-06-22 | 2022-07-12 | 腾达建设集团股份有限公司 | Floating force testing device and method for shield segment in surrounding rock |
-
2001
- 2001-10-04 JP JP2001308160A patent/JP3916911B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2003113697A (en) | 2003-04-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4279307B2 (en) | Shield machine start mechanism and start method | |
JP3916911B2 (en) | Shielding machine starting mechanism and starting method and temporary assembly segment with stopper used therefor | |
JP2007077677A (en) | Construction method for underground structure | |
US20040267209A1 (en) | Injection needle retractable injector | |
JP3916909B2 (en) | Shield machine start mechanism and start method | |
JP2000199225A (en) | Steel pipe pile for supporting building | |
DK163682B (en) | PLAYING DEVIL WITH PLAYING MUFF AND ROCKY PLAYING ELEMENT | |
JP3284026B2 (en) | Lock bolt fall prevention bracket | |
KR20180009638A (en) | Cutting Method and Apparatus using Wire Saw | |
JPH07189598A (en) | Lock bolt setting method | |
JP4549585B2 (en) | Shield machine start mechanism and start method | |
JP3637112B2 (en) | Segment joint structure | |
JPH07217368A (en) | Execution method of tunnel | |
JP3022282B2 (en) | Assembly structure of tunnel lining members | |
JP4059732B2 (en) | Entrance packing device and water stopping method in start shaft | |
JP4536564B2 (en) | Widening part structure and widening part construction method of shield tunnel | |
JP4045473B2 (en) | Segment assembly method and segment | |
JP2545294B2 (en) | Construction method of removable anchor | |
JPH10231692A (en) | Structure of segment joint | |
JP2544042B2 (en) | Hexagonal concrete segment assembly structure | |
JP2673187B2 (en) | Shield tunnel joining method | |
JPH03281898A (en) | Method for connecting shield tunnel to structure or shield tunnels each other, and device therefor | |
JPH10220185A (en) | Joint structure of segment | |
JP2011032790A (en) | Backing prevention device at start of shield machine | |
JP2000282459A (en) | Pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040607 |
|
RD03 | Notification of appointment of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7423 Effective date: 20040601 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060726 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060905 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20061102 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070116 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070207 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3916911 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130216 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20160216 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |