JP3854495B2 - Construction method of tunnel junction - Google Patents
Construction method of tunnel junction Download PDFInfo
- Publication number
- JP3854495B2 JP3854495B2 JP2001347961A JP2001347961A JP3854495B2 JP 3854495 B2 JP3854495 B2 JP 3854495B2 JP 2001347961 A JP2001347961 A JP 2001347961A JP 2001347961 A JP2001347961 A JP 2001347961A JP 3854495 B2 JP3854495 B2 JP 3854495B2
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- junction
- road
- merging
- ramp
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Description
【0001】
【発明の属する技術分野】
本発明は、トンネルの分合流部の構築方法に関するものである。
【0002】
【従来の技術】
従来、道路トンネルや地下鉄等のトンネルをシールド工法で構築する場合において、これらのトンネルと出入口分合流部との接続方法は、路上から開削した開削分合流部にシールドトンネルを接続する開削工法が主流である。
近年では、2本のトンネルの通過部分の外側を、止水と山留めを目的とした連続地中壁を施工しておき、シールド通過後に2本のシールドトンネル間を掘削し、連結部のセグメントを解体し、ランプ構造物を構築する方法が提案されている。
【0003】
【発明が解決しようとする課題】
しかしながら、前記した従来の方法は、いずれも路面の専有面積が幅、長さともに広範囲になると同時に工事期間の間、路面の使用が広範囲にわたって制限されるため、交通渋滞のネックや工事公害の元となっている。
【0004】
【本発明の目的】
本発明は上記したような従来の問題点に鑑みて考えられたもので、開削部を極力縮小して路面の専有面積を最小限にしたトンネルの分合流部の構築方法を提供することを目的とする。
また本発明は、工期短縮とコストダウンを図ったトンネルの分合流部の構築方法を提供することを目的とする。
本発明は、上記目的のうち少なくとも一つを達成するようにしたものである。
【0005】
【課題を解決するための手段】
上記のような目的を達成するために、本発明のトンネルの分合流部の構築方法は、間隔を開けて掘削した複数のトンネル間を接続して構築するトンネルの分合流部の構築方法であって、掘削可能なセグメントを複数のトンネルが対向する側面に配置して前記トンネルを構築し、前記トンネルの坑内から前記分合流部を構成する鉛直方向支持部材を補強材を兼ねて構築し、路上部のランプ出入口に構築したU字擁壁部の一方から矩形シールドを前記トンネル間に向けて掘進し、前記矩形シールドによって前記トンネル間を掘削すると同時に前記トンネルの掘削可能なセグメントを掘削し、前記矩形シールドを前記トンネルと並進した後に路上部の他のU字擁壁部へ向けて掘進し、分合流部の掘削後、一方のトンネルのセグメントと補強材を取り外し、分合流部と一方のトンネルのセグメントとの一体化を行うものである。
【0006】
また、本発明のトンネルの分合流部の構築方法は、間隔を開けて掘削した複数のトンネル間を接続して構築するトンネルの分合流部の構築方法であって、路上部のランプ出入口を結ぶ途上に立坑を構築し、前記立坑に接続する分合流部トンネルを構築し、前記分合流部トンネルから矩形シールドを路上部のランプ出入口に構築したU字擁壁部の一方へ向けて掘進するとともに、シールドを水平掘進して該分合流部トンネルを前記トンネルとランプ部とに分岐し、前記ランプ部の掘削後、前記矩形シールドを前記立坑に再投入し、前記矩形シールドを路上部の他方のU字擁壁部へ向けて掘進して行うものである。
【0007】
【本発明の実施の形態1】
以下図面を参照しながら、本発明に係る一実施の形態について説明する。
【0008】
<イ>トンネル
トンネルは、道路トンネルや地下鉄等のトンネルである。
以下、本例では、間隔を開けて構築した二つの道路トンネル10A、10Bについて説明するが、道路トンネルは三つでもよい。
二つの道路トンネル10A、10Bを道路トンネル10で総称する。
図3に示すように道路トンネル10は上り線(道路トンネル10A)と下り線(道路トンネル10B)を平行して配置し、これら道路トンネル10は、例えば公知のシールドで掘削し、セグメント11A、11Bを組み立てて構築する(説明の便宜上、上り線に関する部材に符号Aを付加し、下り線に関する部材に符号Bを付加して区別する)。
道路トンネル10A、10Bの路面下には、例えば換気ダクト14A、14Bを設ける。
本発明は、二つの道路トンネル10A、10Bの間を矩形シールド23で掘削できるように、道路トンネル10Aと10Bが互いに対向する側面に掘削可能なセグメント12A、12Bを配置しておく。
【0009】
掘削可能なセグメント12A、12Bは、例えば掘削可能なコンクリートや改良土等の複合材料からなり、補強セグメント13A、13Bに改良土等を予め一体化して製作しておく。
または、現場で補強セグメント13A、13Bを設置しながら改良土等を充填するようにしてもよい。
【0010】
<ロ>分合流部
分合流部20は、分合流部トンネル21とランプ部22とからなる。
図2及び図3には、上り線(道路トンネル10A)についてランプ部22を示し、下り線のランプ部を省略している。
入口ランプ31及び出口ランプ32は、U字開削して構築したU字擁壁部30からなる。
U字擁壁部30を構築して施工するものであるから、路上部33で工事基地として占用するのは、U字開削部のみであり、従来のように幅、長さともに広範囲になることはない。
入口ランプ31からランプ部22を通って自動車(図3で矢印で示す)が進入し、分合流部トンネル21で上り線10Aに合流する。
また、上り線10Aを進行している自動車が、分合流部トンネル21でランプ部22を通ってランプ出口32から路上33へ抜ける。
本発明は、二つの道路トンネル10A、10Bの間を矩形シールド23で掘削すると同時に前記した掘削可能なセグメント12A、12Bを掘削し、補強セグメント13Aを取り外し、接続工50を行って上り線10Aのランプ部22を構築する(図1参照)。
【0011】
次に、図2、図4乃至図7を参照して道路トンネルの分合流部の構築方法について説明する。
【0012】
<イ>道路トンネルの構築(図4)
公知のシールドで道路トンネル10Aと道路トンネル10Bを、互いに所定の間隔を開けて平行に掘削し、上り線と下り線を構築する。
ここで所定の間隔とは、後述するランプ部22を構築することのできる間隔である。
二つの道路トンネル10A、10Bの間を矩形シールド23で掘削できるように道路トンネル10A、10Bが互いに対向する側面に掘削可能なセグメント12A、12Bを配置しておく。
前記したように掘削可能なセグメント12A、12Bは、掘削可能なコンクリートや改良土等の複合材料からなる。
そして道路トンネル10A、10Bの坑内に補強セグメント13A、13Bと改良土等を一体化した掘削可能なセグメント12A、12Bを構築する。
この方法として、補強セグメント13A、13Bに改良土を予め一体化してセグメント12A、12Bを製作しておいてこれを現場で配置してもよいし、あるいは現場で補強セグメント13A、13Bを構築しながら改良土を充填してセグメント12A、12Bを配置するようにしてもよい。
なお、補強セグメント13A、13Bは後述する分合流部20を構築する際の補強材の役目をもつ。
【0013】
また、路上33のランプ入口31及びランプ出口32にU字擁壁部30を構築する。
U字擁壁部30は、プレキャスト版または現場施工のどちらでもよい。プレキャスト版で施工する場合は、工期短縮につながる。
構築した一方のU字擁壁部30からランプ部22を掘削するとき、ランプ部22の掘削と並行して、または掘削前に他方のU字擁壁部30をランプ部22の掘削完了までに構築する。
U字擁壁部30の構築で開削されるのは、U字開削部のみであり、開削範囲は出入ランプ開業後と何ら変わることなく、路上部33で工事基地として占用する面積は最小限である。
【0014】
<ロ>矩形シールドによるランプ部の掘削(図2、図5)
U字擁壁部30を構築した出口ランプ32から矩形シールド23を道路トンネル10A、10Bの間に向けて掘進し、ランプ部22を掘削する。
矩形シールド23は、U字擁壁部30からの斜め低土被り発進のため、開削区間が小規模となる利点がある。
矩形シールド23が道路トンネル10A、10Bの間に到達すると、矩形シールド23は道路トンネル10A、10B間を掘削すると同時に掘削可能なセグメント12A、12Bを掘削する。
そのまま掘削し、図5の状態に至る。
その後、矩形シールド23の向きを道路トンネル10A、10Bの向きと一致するように水平状態にする。
【0015】
<ハ>矩形シールドによる分合流部トンネルの掘削(図2、図5)
水平状態となった矩形シールド23を、そのまま所定距離を水平掘進する。
ここで所定距離とは、図2及び図3に示す分合流部トンネル21の長さと一致する距離である。
このようにして矩形シールド23が道路トンネル10A、10B間を掘削すると同時に掘削可能なセグメント12A、12Bを掘削しながら水平掘進し、分合流部トンネル21を掘削する。
掘削後、分合流部20の底版201、天井部202、側壁(鉛直方向支持部材)203等の構造物を道路トンネル10A、10Bの坑内に跨って構築しておく(図6参照)。
側壁203及び補強セグメント13A、13Bが道路トンネル10の補強を兼ねており、矩形シールド23が掘削可能なセグメント12A、12Bを掘削しても問題はなく、道路トンネル10を暫定開業しながら分合流部20の施工が可能である。
後述する接続工50を施工する前に、道路トンネル10と分合流部20の接続部周辺の地盤に必要に応じて地盤改良40を行っておく。
地盤改良40は、例えば注入管41からモルタルなどの地盤改良剤を注入して行う(図5参照)。
または、置換工法や凍結工法によって地盤改良を行ってもよい。
【0016】
<ニ>矩形シールドによるランプ部の掘削(図2)
分合流部トンネル21の掘削後、矩形シールド23の向きをランプ入口31のU字擁壁部30へ向ける。
再び、矩形シールド23を路上部33のランプ入口31のU字擁壁部30へ向けて掘進する(図2参照)。
矩形シールド23によってランプ部22を掘削し、ランプ入口31のU字擁壁部30へ連絡する。
本例では、矩形シールド23がランプ出口32から発進し、入口ランプ31まで掘進したが、逆に入口ランプ31から発進し、ランプ出口32まで掘進してもよい。
【0017】
<ホ>道路トンネルと分合流部の接続工(図6、図7)
道路トンネル10Aと分合流部20の接続工50は、道路トンネル10Aのセグメント補強工51と分合流部補強工52とからなる。
セグメント補強工51は、図6に示すように先ず道路トンネル10Aのセグメント11Aを巻き込み、コンクリートなどを打設して行う。
分合流部補強工52は、図7に示すように側壁(鉛直方向支持部材)203を残して、底版201及び天版202を巻き込み、コンクリートなどを打設して行う。
これによって、セグメント補強工51と分合流部補強工52のコンクリートが一体化し、道路トンネル10Aと分合流部20を接続する接続工50が施工される。
コンクリートの養生後、補強セグメント13Aと側壁(鉛直方向支持部材)203を取り外し、道路トンネル10Aと分合流部20を連絡させて分合流部20の構築が完了する。
本発明では、矩形シールド23がランプ出入口(31、32)から掘削し、道路トンネル10A、10B間を掘削して、分合流部トンネル21を掘削し、再びランプ出入口(31、32)まで掘削するので、分合流部20を非開削工法で、1台の矩形シールドで連続して構築することができる。
なお、本発明は、これまで道路トンネル10について説明したが、地下鉄が地上の鉄道と相互乗り入れするような場合の鉄道トンネルについても適用することができる。
【0018】
【発明の実施の形態2】
以上は、矩形シールド23が一方のランプ部22から掘削し、分合流部トンネル21を掘削し、再び他方のランプ部22まで掘削して道路トンネル10の分合流部20を構築する方法について説明したが、本実施の形態で説明するように分合流部トンネル21から夫々ランプ部22を構築するようにしてもよい(図8参照)。
【0019】
路上部33のランプ入口31とランプ出口32を結ぶ途上に立坑35を構築し、この立坑35から、例えば分合流部トンネル21の幅を掘削するに十分なシールド26を水平掘進させ、分合流部トンネル21を掘削する。
分合流部トンネル21を構築したら、ランプ部22を掘削する矩形シールド25と道路トンネル10を掘削するシールド27とに分離する。
矩形シールド25を路上部33のランプ出口32に構築したU字擁壁部30へ向けて掘進するとともに、シールド27を水平掘進して分合流部トンネル21を道路トンネル10とランプ部22とに分岐する。
矩形シールド25によってランプ部22を掘削し、ランプ出口32のU字擁壁部30へ連絡する。
矩形シールド25をU字擁壁部30の開削部で解体し、立坑35へ再投入し、組立後、矩形シールド25を路上部33のランプ入口31のU字擁壁部30へ向けて掘進して行う。
なお、道路トンネル10を掘削するシールド27は、反対側から掘進してくるシールド28と地中接合する。または所定の立坑に到達する。
本例も1台の矩形シールド25を転用しながら、ランプ部22を掘削し、分合流部20を構築する。
また、本例も道路トンネル10に限らず、地下鉄が地上の鉄道と相互乗り入れするような場合の鉄道トンネルについても適用することができる。
【0020】
【本発明の効果】
本発明は、以上説明したようになるから次のような効果を得ることができる。
<イ>分合流部の掘削は、U字擁壁部からの斜め低土被り発進または到達のため、開削区間が小規模であり、分合流部構築に関し占用する路上部の工事基地は、U字開削部だけの狭い範囲を使用するだけである。
したがって、交通渋滞のネックとなることが少なく、また工事公害を大幅に減少させることができる。
<ロ>トンネル坑内に分合流部構造物と補強セグメントを構築しているため、トンネルを暫定開業しながら分合流部の構築が可能であり、工期短縮とコストダウン、及び交通渋滞の緩和につながる。
<ハ>矩形シールドの転用が可能であるため、出入分合流部を非開削工法で、しかも1台の矩形シールドで連続して分合流部を構築することができる。このため、シールドに要する費用を削減することができる。
<ニ>ランプ部施工において、開削区間が短いため、地下埋設物の移設等施工の支障となることが少ない。
【図面の簡単な説明】
【図1】道路トンネルと分合流部の関係を示す説明図。
【図2】道路トンネルと分合流部の構築概要図。
【図3】道路トンネルと分合流部の関係を示す説明図。
【図4】分合流部の施工手順を示す説明図。
【図5】分合流部の施工手順を示す説明図。
【図6】分合流部の施工手順を示す説明図。
【図7】分合流部の施工手順を示す説明図。
【図8】分合流部の他の構築方法を示す説明図。
【符号の説明】
10・・・道路トンネル
12・・・掘削可能セグメント
13・・・補強セグメント
20・・・分合流部
21・・・分合流部トンネル
22・・・ランプ部
203・・側壁(鉛直方向支持部材)
23・・・矩形シールド
30・・・U字擁壁部
31・・・入口ランプ
32・・・出口ランプ
33・・・路上[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing a junction / junction portion of a tunnel.
[0002]
[Prior art]
Conventionally, when tunnels such as road tunnels and subways are constructed by the shield method, the main method of connecting these tunnels to the entrance / exit junction is the open cut method in which the shield tunnel is connected to the open junction that has been cut from the road. It is.
In recent years, a continuous underground wall has been constructed outside the passing part of two tunnels for the purpose of water stopping and mountain retaining, and after passing through the shield, the two shield tunnels are excavated, and the connecting segment is A method of dismantling and building a lamp structure has been proposed.
[0003]
[Problems to be solved by the invention]
However, all of the above-mentioned conventional methods have a wide road area and length, and at the same time, the use of the road surface is restricted over a wide range during the construction period. It has become.
[0004]
[Object of the present invention]
The present invention was conceived in view of the conventional problems as described above, and an object of the present invention is to provide a method for constructing a merging / merging portion of a tunnel in which the excavated portion is reduced as much as possible to minimize the exclusive area of the road surface. And
It is another object of the present invention to provide a method for constructing a junction / junction portion of a tunnel that shortens the construction period and reduces costs.
The present invention is intended to achieve at least one of the above objects.
[0005]
[Means for Solving the Problems]
In order to achieve the above object, the method for constructing a junction / junction portion of a tunnel according to the present invention is a method for constructing a junction / junction portion of a tunnel constructed by connecting a plurality of tunnels excavated at intervals. And constructing the tunnel by arranging excavable segments on the side surfaces facing a plurality of tunnels, and constructing a vertical support member that constitutes the merging / merging portion from the inside of the tunnel as a reinforcing material, Excavating a rectangular shield from one of the U-shaped retaining walls constructed at the ramp entrance of the section toward the tunnel, excavating between the tunnels by the rectangular shield and simultaneously excavating the excavable segment of the tunnel, After translating the rectangular shield with the tunnel, dig toward the other U-shaped retaining wall at the top of the road, and after excavating the junction, remove the segment and reinforcement from one of the tunnels. And, it is performed the integration of the partial merging portion and one of the tunnel segment.
[0006]
Further, the method for constructing the junction / junction part of the tunnel according to the present invention is a construction method of the junction / junction part of the tunnel constructed by connecting a plurality of tunnels excavated at intervals, and connecting the ramp entrance at the upper part of the road Constructing a shaft in the middle, constructing a branch junction tunnel connected to the shaft, and excavating from the branch junction tunnel toward one of the U-shaped retaining walls built at the ramp entrance of the ramp above the road , The shield is horizontally excavated to branch the merging junction tunnel into the tunnel and the ramp portion, and after excavating the ramp portion, the rectangular shield is reintroduced into the shaft, and the rectangular shield is connected to the other of the upper part of the road. It digs towards the U-shaped retaining wall.
[0007]
[Embodiment 1 of the present invention]
Hereinafter, an embodiment according to the present invention will be described with reference to the drawings.
[0008]
<I> Tunnels are tunnels such as road tunnels and subways.
Hereinafter, in this example, two
The two
As shown in FIG. 3, the
For example,
In the present invention, the excavable segments 12A and 12B are arranged on the side surfaces where the
[0009]
The excavable segments 12A and 12B are made of, for example, a composite material such as excavable concrete and improved soil, and the improved soil and the like are integrated with the reinforcing
Or you may make it fill improvement soil etc., installing
[0010]
<B> Split / Merge Partial Junction 20 is composed of a junction /
2 and 3, the
The
Since the U-shaped
An automobile (indicated by an arrow in FIG. 3) enters from the
In addition, the automobile traveling on the up
The present invention excavates between the two
[0011]
Next, a method for constructing the junction / junction portion of the road tunnel will be described with reference to FIGS. 2 and 4 to 7.
[0012]
<I> Construction of road tunnel (Fig. 4)
The
Here, the predetermined interval is an interval at which a later-described
Segments 12A and 12B that can be excavated are arranged on the side surfaces of the
As described above, the excavable segments 12A and 12B are made of a composite material such as excavable concrete and improved soil.
Then, excavable segments 12A and 12B in which the reinforcing
As this method, the improved soil may be integrated with the
The reinforcing
[0013]
Further, the U-shaped
The U-shaped
When excavating the
The construction of the
[0014]
<B> Excavation of the ramp section with a rectangular shield (Figs. 2 and 5)
The
The
When the
Excavation is continued as it is, and the state shown in FIG. 5 is reached.
After that, the
[0015]
<C> Excavation of the junction / junction tunnel with a rectangular shield (Figs. 2 and 5)
The
Here, the predetermined distance is a distance that coincides with the length of the junction /
In this way, the
After excavation, structures such as the
The
Before constructing a connecting
The
Alternatively, the ground improvement may be performed by a replacement method or a freezing method.
[0016]
<D> Excavation of the ramp part by rectangular shield (Fig. 2)
After excavation of the junction /
Again, the
The
In this example, the
[0017]
<E> Connection work between road tunnel and junction (Figs. 6 and 7)
The connecting
As shown in FIG. 6, the
As shown in FIG. 7, the merging / merging
As a result, the concrete of the
After the curing of the concrete, the reinforcing
In the present invention, the
Although the present invention has been described with respect to the
[0018]
Second Embodiment of the Invention
The above describes the method in which the
[0019]
A
When the junction /
The
The
The
In addition, the
In this example, the diverging / merging
Further, the present example is not limited to the
[0020]
[Effect of the present invention]
Since the present invention has been described above, the following effects can be obtained.
<I> The excavation of the merging junction is a small open excavation section due to the start or arrival of the oblique low earth covering from the U-shaped retaining wall, and the construction base on the upper part of the road used for the construction of the merging junction is U It only uses a narrow area of the cut-out part.
Therefore, it is less likely to become a bottleneck for traffic congestion and construction pollution can be greatly reduced.
<B> Because the junction structure and reinforcement segment are built in the tunnel tunnel, the junction can be constructed while the tunnel is temporarily opened, leading to reduction of construction period, cost reduction, and reduction of traffic congestion. .
<C> Since the rectangular shield can be diverted, it is possible to construct the junction / merging portion continuously by the non-cutting method by the non-cutting method and by one rectangular shield. For this reason, the cost which a shield requires can be reduced.
<D> In the ramp construction, the excavation section is short, so there is little hindrance to construction such as relocation of underground objects.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram showing a relationship between a road tunnel and a junction / merging section.
FIG. 2 is a schematic diagram of the construction of a road tunnel and a junction.
FIG. 3 is an explanatory diagram showing a relationship between a road tunnel and a junction / merging section.
FIG. 4 is an explanatory view showing a construction procedure of a merging / merging portion.
FIG. 5 is an explanatory view showing a construction procedure of a junction / merging portion.
FIG. 6 is an explanatory diagram showing a construction procedure of a junction / merging portion.
FIG. 7 is an explanatory diagram showing a construction procedure of a merging / merging portion.
FIG. 8 is an explanatory diagram showing another construction method of the merging / merging portion.
[Explanation of symbols]
DESCRIPTION OF
23 ...
Claims (2)
掘削可能なセグメントを複数のトンネルが対向する側面に配置して前記トンネルを構築し、
前記トンネルの坑内から前記分合流部を構成する鉛直方向支持部材を補強材を兼ねて構築し、
路上部のランプ出入口に構築したU字擁壁部の一方から矩形シールドを前記トンネル間に向けて掘進し、
前記矩形シールドによって前記トンネル間を掘削すると同時に前記トンネルの掘削可能なセグメントを掘削し、
前記矩形シールドを前記トンネルと並進した後に路上部の他のU字擁壁部へ向けて掘進し、
分合流部の掘削後、一方のトンネルのセグメントと補強材を取り外し、
分合流部と一方のトンネルのセグメントとの一体化を行う、
トンネルの分合流部の構築方法。A method for constructing a tunnel junction where a plurality of tunnels excavated at intervals are connected and constructed.
Constructing the tunnel by arranging excavable segments on the sides facing multiple tunnels,
Constructing a vertical support member that constitutes the merging and merging portion from the inside of the tunnel also serves as a reinforcing material,
A rectangular shield is dug from one of the U-shaped retaining walls constructed at the ramp entrance at the top of the road toward the tunnel,
Excavating between the tunnels by the rectangular shield and simultaneously excavating the excavable segment of the tunnel;
After translating the rectangular shield with the tunnel, dig toward the other U-shaped retaining wall of the upper part of the road,
After excavating the junction, remove one tunnel segment and reinforcement,
Integrate the merging section with one tunnel segment,
How to construct a tunnel junction.
路上部のランプ出入口を結ぶ途上に立坑を構築し、
前記立坑に接続する分合流部トンネルを構築し、
前記分合流部トンネルから矩形シールドを路上部のランプ出入口に構築したU字擁壁部の一方へ向けて掘進するとともに、シールドを水平掘進して該分合流部トンネルを前記トンネルとランプ部とに分岐し、
前記ランプ部の掘削後、前記矩形シールドを前記立坑に再投入し、
前記矩形シールドを路上部の他方のU字擁壁部へ向けて掘進して行う、
トンネルの分合流部の構築方法。A method for constructing a tunnel junction where a plurality of tunnels excavated at intervals are connected and constructed.
Constructed a shaft on the way to the ramp entrance at the top of the road,
Establish a merging junction tunnel connecting to the shaft,
A rectangular shield is dug from the junction / junction tunnel toward one of the U-shaped retaining walls constructed at the ramp entrance at the top of the road, and the shield is dug horizontally to connect the junction / junction tunnel to the tunnel and the ramp. Branch,
After excavation of the ramp portion, the rectangular shield is reintroduced into the shaft,
The rectangular shield is dug toward the other U-shaped retaining wall at the top of the road,
How to construct a tunnel junction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001347961A JP3854495B2 (en) | 2001-11-13 | 2001-11-13 | Construction method of tunnel junction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001347961A JP3854495B2 (en) | 2001-11-13 | 2001-11-13 | Construction method of tunnel junction |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003148086A JP2003148086A (en) | 2003-05-21 |
JP3854495B2 true JP3854495B2 (en) | 2006-12-06 |
Family
ID=19160866
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001347961A Expired - Fee Related JP3854495B2 (en) | 2001-11-13 | 2001-11-13 | Construction method of tunnel junction |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3854495B2 (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006125036A (en) * | 2004-10-28 | 2006-05-18 | Taisei Corp | Ramp forming method and ramp forming apparatus |
JP4525480B2 (en) * | 2005-06-16 | 2010-08-18 | 株式会社大林組 | Ground deformation prevention method |
JP2007146432A (en) * | 2005-11-25 | 2007-06-14 | Taisei Corp | Shield machine and excavating method |
JP4754391B2 (en) * | 2006-04-06 | 2011-08-24 | 戸田建設株式会社 | Tunnel excavation method, tunnel entrance / exit branch / confluence widening section using the same, and tunnel entrance / exit branch / confluence widening section constructed thereby |
JP4730608B2 (en) * | 2006-06-05 | 2011-07-20 | 清水建設株式会社 | segment |
JP4958040B2 (en) * | 2007-01-10 | 2012-06-20 | 清水建設株式会社 | Tunnel structure and tunnel construction method |
JP7088818B2 (en) * | 2018-12-14 | 2022-06-21 | 戸田建設株式会社 | Installation method of rectangular propulsion pipe and manufacturing method of underground structure equipped with rectangular propulsion pipe |
-
2001
- 2001-11-13 JP JP2001347961A patent/JP3854495B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2003148086A (en) | 2003-05-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100752285B1 (en) | Construction method for two arches tunnel | |
US3999394A (en) | Precast ribbed arch subway structure and method | |
KR101152419B1 (en) | Ventilation of road construction include tunnel and underground way, and method for constructing thereof | |
RU2510444C2 (en) | Three-arched underground station of column type and its erection methods (yurkevich device and methods) | |
JP3854495B2 (en) | Construction method of tunnel junction | |
CN108978673A (en) | A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning | |
JP4104781B2 (en) | Construction method of underground joint structure | |
JP4083334B2 (en) | Underground structure having arch roof and method for constructing the same | |
JP3941055B2 (en) | Method of branching and joining the shield tunnel | |
JP2000179299A (en) | Large-section tunnel construction method | |
Mori et al. | Large rectangular cross-section tunneling by the multi-micro shield tunneling (MMST) method | |
JP2009091742A (en) | Tunnel construction method | |
JP4303512B2 (en) | Construction method of large section tunnel | |
US4008577A (en) | Cut and cover construction of subway with utility chamber and air conditioning with minimum street traffic disturbance | |
JP2006112137A (en) | Structure of diverging/merging section of branch tunnel, and its construction method | |
US3914946A (en) | Cut and cover construction of subway with utility chamber and air conditioning with minimum street traffic disturbance and method | |
JP3146333B2 (en) | Tunnel construction method | |
JP4593913B2 (en) | How to build a branch tunnel | |
JP4253806B2 (en) | Method of branching and joining the shield tunnel | |
Ramírez Chasco et al. | System for construction of a railway underpass | |
JP3863158B2 (en) | Tunnel of the junction and the method of constructing the junction | |
JPH0978584A (en) | Construction method for banking with tunnel-like space | |
CN112780298B (en) | Tunnel construction method using fabricated tunnel shallow buried section shed tunnel structure | |
JP4319122B2 (en) | Branch and junction structure of branching tunnel and its construction method | |
CN220748266U (en) | Underpass structure of unreserved interface existing operation station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040830 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060824 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060905 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060908 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090915 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100915 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110915 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120915 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130915 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |