JP3737351B2 - Production line construction method - Google Patents

Production line construction method Download PDF

Info

Publication number
JP3737351B2
JP3737351B2 JP2000289492A JP2000289492A JP3737351B2 JP 3737351 B2 JP3737351 B2 JP 3737351B2 JP 2000289492 A JP2000289492 A JP 2000289492A JP 2000289492 A JP2000289492 A JP 2000289492A JP 3737351 B2 JP3737351 B2 JP 3737351B2
Authority
JP
Japan
Prior art keywords
sub
model
parts
man
asynchronous
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2000289492A
Other languages
Japanese (ja)
Other versions
JP2002103186A (en
Inventor
文雄 守屋
丈洋 河野
清 井汲
大 宮下
治司 吉田
龍章 孫
浩一 細野
政和 神田
玄五 梶間
友良 竹内
雅則 吉田
淳 豊田
健次 竜田
保男 宮岡
道直 岩見
郁夫 金沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Honda Motor Co Ltd
Original Assignee
Honda Motor Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority to JP2000289492A priority Critical patent/JP3737351B2/en
Application filed by Honda Motor Co Ltd filed Critical Honda Motor Co Ltd
Priority to CN00817819.4A priority patent/CN1195604C/en
Priority to CA002393536A priority patent/CA2393536C/en
Priority to GB0214125A priority patent/GB2375741B/en
Priority to PCT/JP2000/009196 priority patent/WO2001047661A1/en
Priority to US10/130,296 priority patent/US6918168B2/en
Priority to BRPI0016748-7A priority patent/BR0016748B1/en
Publication of JP2002103186A publication Critical patent/JP2002103186A/en
Priority to US11/117,404 priority patent/US7269900B2/en
Application granted granted Critical
Publication of JP3737351B2 publication Critical patent/JP3737351B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Description

【0001】
【発明の属する技術分野】
この発明は、例えば、多機種の自動車を単一の生産ラインで生産することができる生産ラインの構築方法に関するものであり、特に、機種の違いによる生産工数の偏差を吸収して効率よく生産を行うことができる生産ラインの構築方法に係るものである。
【0002】
【従来の技術】
従来、例えば、自動車の組み立てラインのような流れ作業を行う生産ラインにあっては、特開昭61−21870号公報に示されているように、メイン部品を組み付けるメインラインと、メインラインの他にサブ部品を組み付けるサブラインを設け、これらメインライン及びサブラインによる生産ラインを構築するようにしている。
また、多数の機種を同一のラインで生産する多機種混合生産方式にあっては、特許第2920801号のように組み付け工数の異なる複数機種の車両を混合生産するために、組立ラインタクトを適切に変化させて生産効率を向上させるものが知られている。
【0003】
【発明が解決しようとする課題】
これら従来の生産ラインにおいては、機種毎に異なるアッセンブリ形態、装備、仕様、部品点数等を考慮すると最も部品点数の多い機種を基準に生産ラインの構築を行う必要があるため、メインラインが延びることにより、機種間での作業工数の変動による余剰工数と共に付帯設備等も増加し、コストアップにつながるという課題がある。
【0004】
すなわち、部品点数の異なる車両を同一のラインで組み立てるため、例えば、搬送コンベアに載置された異なる機種の車両に応じて作業工数が変化する。そのため、部品点数の少ない機種が搬送されてきた場合には、部品点数の多い機種が搬送されてきた場合に必要だった人員が必要なくなり、無駄が生じてしまう。
そこで、この発明は、機種の違いによる作業工数の偏差を吸収して効率よく生産を行うことができる生産ラインの構築方法を提供するものである。
【0005】
【課題を解決するための手段】
上記課題を解決するために、請求項1に記載した発明は、多機種の製品(例えば、実施形態における車体2)を単一のメインライン(例えば、実施形態におけるメインライン1)で生産できる生産ラインの構築方法であって、機種毎の部品データまたはメインラインに投入される機種を入力する入力手段(例えば、実施形態における入力手段101)と、前記入力手段により入力された機種毎の部品データを部品マップ化し、またメインラインに投入される機種の部品を分類処理する手順を予め記憶する制御手段(例えば、実施形態における制御回路100)と、前記手順に従って分類された結果を表示する表示手段(例えば、実施形態における表示装置102)よりなり、メインラインに投入される機種を前記入力手段により入力し、前記部品マップ化されたデータを機種の違いにかかわらず共通する部品をメイン部品(例えば、実施形態におけるメイン部品MB)として抽出し、残りの部品をサブ部品(例えば、実施形態におけるサブ部品SB)として抽出するメインサブ分類工程(例えば、実施形態におけるステップS1,S2)と、該メインサブ分類工程において抽出されたサブ部品のうちメインラインと同期してサブライン(例えば、実施形態におけるサブライン3〜12、14〜17、20〜23)で組み付け可能なサブ部品を同期サブ部品(例えば、実施形態における同期サブ部品SB1)として抽出し、残りのサブ部品を非同期サブ部品(例えば、実施形態における非同期サブ部品SB2)として抽出する同期非同期分類工程(例えば、実施形態におけるステップS3)と、該同期非同期分類工程で抽出された非同期サブ部品の全組み付け工数を、メインラインにおける機種毎に異なるメイン部品間の工数偏差(例えば、実施形態における工数偏差ER2)によって生ずる余剰作業者とサブラインにおける機種毎に異なる同期サブ部品間の工数偏差(例えば、実施形態における工数偏差ER1)によって生ずる余剰作業者との少なくともいずれか一方に割り当てる非同期サブ部品割り当て工程(例えば、実施形態におけるステップS6)よりなる前記分類処理する手順に従って処理することを特徴とする。
このように構成することで、メインラインにおける機種毎に異なるメイン部品間の工数偏差や、サブラインにおける機種毎に異なる同期部品間の工数偏差によって生じる余剰の労働力を、非同期部品の組み付け作業に割り当てることが可能となる。
請求項2に記載した発明は、前記非同期サブ部品の組み付け工数(例えば、実施形態の図8に示す非同期サブ部品SB2の長さ)を集約し、全組み付け工数を低減させて新組み付け工数(例えば、実施形態における図8における非同期サブ部品SB3の長さ)とし、該新組み付け工数を、前記メイン部品間の工数偏差によって生ずる余剰作業者と同期サブ部品間の工数偏差によって生ずる余剰作業者との少なくともいずれか一方に割り当てるようにしたことを特徴とする。
このように構成することで、非同期サブ部品の組み付け工数を集約し、全組み付け工数を低減させた新組み付け工数を前記メイン部品間の工数偏差と同期サブ部品間の工数偏差とのいずれか一方に割り当てることが可能となる。
【0006】
【発明の実施の形態】
以下、この発明の実施形態を図面と共に説明する。
先ず、自動車の車体組み立ての生産ラインを例にして、生産ラインの構成及び組み付ける部品についての説明を行う。図1は自動車の車体組み立てラインのメインラインの説明図である。図1において、1はメインラインを示し、前段塗装工程において塗装が施され順次搬送されてくる機種の異なる車体(製品)2に、各種部品を順次組み付けるものである。このメインライン1は具体的には伝達・通線ゾーンZA、インテリアゾーンZB、下廻りゾーンZC、エクステリアゾーンZD、複合保証ゾーンZEを備え、メインライン1での組み立てが終了した車体2は次段の検査工程に搬送される。ここで、各ゾーンZA,ZB,ZC,ZD,ZE間には、後述するゾーン保証ゾーンZXが設けられている。
【0007】
上記、伝達・通線ゾーンZAには、燃料/ブレーキ集中配管ASSY(アッセンブリ)の配索、エアコンコンデンサーユニットの取り付け、ABSモジュレータASSYの取り付け、ラジエターASSYの取り付けを行うために、燃料/ブレーキ集中配管ASSYサブライン3と、エアコンコンデンサユニットサブライン4と、ABSモジュレータASSYサブライン5と、ラジエターASSYサブライン6とが各々接続されている。これら各サブラインはメインライン1と同期している。
【0008】
インテリアゾーンZBには、ルーフライニングユニットの取り付け、ヒューズユニットBOXの取り付け、空調ユニットの取り付け、ヘッドライトユニットの取り付け、インパネユニットをコンベア上でASSYしたものの取り付け、バンパーをコンベア上でASSYしたものの取り付けを行うために、ルーフライニングユニットサブライン7と、ヒューズユニットBOXサブライン8と、空調ユニットサブライン9と、ヘッドライトユニットサブライン10と、インパネユニットASSYコンベアサブライン11と、バンパーASSYコンベアサブライン12とが各々接続されている。これら各サブラインはメインライン1と同期している。ここで、前記インパネユニットASSYコンベアサブライン11には、メインライン1とは非同期なコントロールBOXサブサブライン13が接続されている。尚、このコントロールBOXサブサブライン13では全機種のコントロールBOXが組み立てられる。
【0009】
また、下廻りゾーンZCには、リヤサス(リヤサスペンション)をコンベア上で小組したものの取り付け、フロントサス(フロントサスペンション)をコンベア上で小組したものの取り付け、フューエルタンクユニットの取り付け、エキパイ(エキゾーストパイプ)ASSYを小組したものの取り付けを行うために、リヤサス小組コンベアサブライン14と、フロントサスASSY小組コンベアサブライン15と、フューエルタンクユニットサブライン16と、エキパイASSY小組サブライン17とが各々接続されている。これら各サブラインもメインライン1と同期している。
【0010】
ここで、リヤサス小組コンベアサブライン14には、リヤサスASSY小組サブサブライン18が接続され、また、フロントサスASSY小組コンベアサブライン15には、ドレスUPエンジン小組サブサブライン19が接続されている。尚、ドレスUPエンジン小組とはエンジンとミッションとを組み付けることをいう。
前記リヤサスASSY小組サブサブライン18は、機種に関係なくリヤサスASSYの組み立てをメインライン1とは非同期で行い、前記リヤサス小組コンベアサブライン14に供給するラインである。また、ドレスUPエンジン小組サブサブライン19は、機種に関係なくドレスUPエンジンの組み立てをメインライン1とは非同期で行い、前記フロントサスASSY小組コンベアサブライン15に供給するラインである。
【0011】
そして、エクステリアゾーンZDには、前後のシートASSYの取り付け、前後のガラスASSYの取り付けを行うために、シートASSYサブライン20,21と、ガラスASSYサブライン22,23とが各々接続されている。これら各サブラインも、メインライン1と同期している。
最後に、複合保証ゾーンZEでは、液注入作業、バッテリの搭載、燃料の注入、エンジン始動確認等の検査を行う。
また、エクステリアゾーンZDでは、予め伝達・通線ゾーンZAで取り外され、ドア・テールゲートASSYライン24で組み立てられたフロントドアASSY、リヤドアASSY、テールゲートASSYの組み付けも行う。尚、上記メインライン1、サブライン3〜12、14〜17、20〜23、サブサブライン13,18,19以外に、図示しないサブサブラインが設けられている
【0012】
上記各ゾーンは機能別に分割されたもので、従来は係りごとで行っていた作業を機能別に分けると共に、各機能毎、つまり各ゾーン毎に設けられたゾーン保証ゾーンZXでゾーン保証を行うことで組み立て後の分解再組み立てを防止している。例えば、伝達・通線ゾーンZAでは、トランクリッド開閉用ケーブルの両端を所定の部品に取り付けた後にゾーン保証ゾーンZXで作動確認まで行うため、後段ゾーンで組み立て不良が発覚し分解して組み立て直すというようなことが生じない。
【0013】
具体的に説明すると、従来のように係り毎に組み立てを行った場合には、例えば、ケーブルの前端を取り付ける係りと、ケーブルの後端を取り付ける係りとが異なっている場合に、ケーブルの前端を取り付ける係りがケーブルに所定の遊びを与えないで取り付けてしまったときには、ケーブルの後端を取り付ける係りがこれを見つけるまで組み立て不良が発覚しない。よって、不良が判明した時点で場合によっては周囲の部品を分解して再組み立てを行わなければならないのである。ところが、このようにゾーン毎にゾーン保証を行うため、後において不良が発生することがなくなり、そのゾーン毎で作業を完結させることができる。
【0014】
ところで、各ゾーンでは異なる機種の車体2が搬送されることとなるが、例えば、あるゾーンにおける部品の機種毎の有無を図2に示すと、機種の違いにより部品点数、組み立て工数が異なることがわかる。
具体的に説明すると、機種Dでは、部品NO.1から部品NO.8まで存在するが、機種Aでは、部品NO.2、部品NO.4、部品NO.7が存在せず、機種Bでは、部品NO.1、部品NO.6、部品NO.7が存在していない。
また、機種Cでは、部品NO.1、部品NO.4、部品NO.6が存在せず、機種Eでは部品NO.2、NO.7が存在していない。機種の違いにより装備が異なる等で部品点数が一致しないからである。
【0015】
つまり、このゾーンにおいては、部品NO.3、部品NO.5、部品NO.8は、機種A、機種B、機種C、機種D、機種Eで共通部品であるが、他の部品NO.1、NO.2、NO.4、NO.6、NO.7は、機種A、機種B、機種C、機種D、機種Eで異なる部品となる。
また、これと同様に他のゾーンにおいても、異なる機種で共通する部品と、共通しない部品が存在する。
したがって、部品点数が多い機種に合わせて生産ラインを構築すると、部品点数が少ない機種の組み立て作業においては、余剰の作業人員が出てしまうのである。
【0016】
次に、生産ラインの構築方法について、図3に示すフローチャート及び図4〜図8によって説明する。
先ず、図3に示すように、任意のゾーンにおいて、機種の違いにかかわらず共通する部品をメイン部品MBとして抽出し(ステップS1)、残りの部品をサブ部品SBとして抽出する(ステップS2)。ステップS1とステップS2とでメインサブ分類工程が構成される。具体的には、図4において機種毎の工数を棒グラフ(縦軸は工数としての時間)で示すように、機種A〜機種Eの各々について共通するメイン部品MBと共通しないサブ部品SBを分類する。図2に示した例で説明すると、各機種A,B,C,D,E毎に、部品NO.3、部品NO.5、部品NO.8をメイン部品MBとして抽出し、他の部品NO.1、NO.2、NO.4、NO.6、NO.7はサブ部品SBとして抽出する。
図4に鎖線で示すのは、サブ部品SBとして抽出されたものをサブ側に記載したものである。ここで、メイン部品MBは、部品が共通するといっても機種が異なるため、機種毎の工数が一致せずバラ付きが生ずる。尚、ばらつきによって生ずる偏差を図7においてハッチングで示す。
【0017】
次に、図3のステップS3において、該メインサブ分類工程で抽出されたサブ部品SBうちメインライン1と同期してサブラインで組み付け可能なサブ部品SBを同期サブ部品SB1として抽出し、次にステップS4において残りのサブ部品SBを非同期サブ部品SB2として抽出する。ステップS3とステップS4とで同期非同期分類工程が構成される。
具体的には、図5においてサブ部品SBの工数を棒グラフ(縦軸は工数としての時間)で示すように、機種A〜機種Eの各々について、メインライン1と同期してサブラインで組み付け可能な同期サブ部品SB1と、同期できない非同期サブ部品SB2とを境界線を境にしてすみ分ける。ここで、同期サブ部品SB1も、部品が共通するといっても機種が異なるため、機種毎の工数が一致せずバラ付きが生ずる。尚、ばらつきによって生ずる工数偏差ER1をハッチングで示す。そして、図3のステップS5において、非同期サブ部品SB2を、機種毎ではなく一つの固まりである新非同期サブ部品SB3としてとりまとめる(非同期サブ部品とりまとめ工程)。具体的には、図6においてサブ部品SBの工数を棒グラフ(縦軸は工数としての時間)で示すように、境界線から下の部分を示す非同期サブ部品SB2(図5に示す)を、機種毎では全体として一つの固まりである新非同期サブ部品SB3としてとりまとめる。
【0018】
そして、図3のステップS6において、前記ステップS3、ステップS4で抽出されステップS5でとりまとめられた新非同期サブ部品SB3、つまり非同期サブ部品SB2の全(全機種の)組み付け工数を集約し、全組み付け工数を低減させた新組み付け工数としたものを、メインライン1における機種毎に異なるメイン部品MB間の工数偏差と、サブラインにおける機種毎に異なる同期サブ部品SB1間の工数偏差とに割り当てて処理を終了する。尚、全機種の非同期サブ部品SB2の組み付け工数がさほど多くなく、メインライン1における機種毎に異なるメイン部品MB間の工数偏差あるいはサブラインにおける機種毎に異なる同期サブ部品SB1間の工数偏差とのいずれか一方への割り当てで足りる場合には、双方に割り当てる必要は無い。このステップS6により非同期サブ部品割り当て工程が構成されている。
具体的には、図6における新非同期サブ部品SB3の全体の組み付け工数を、図6においてハッチングで示す各機種の同期サブ部品SB1間の工数偏差ER1と、図7のメイン部品MBの工数の棒グラフ(縦軸は工数としての時間)にハッチングで示す各機種のメイン部品MB間の工数偏差ER2との少なくともいずれか一方に割り当てるのである。
【0019】
ここで、図8に示すのは、図5に示す非同期サブ部品SB2の組み付け工数を集約し、図6に示すように組み付け工数を低減させて新組み付け工数とした非同期サブ部品SB3とし、該新組み付け工数を、前記メインライン1における機種毎に異なるメイン部品MB間の工数偏差ER2と、サブラインにおける機種毎に異なる同期サブ部品SB1間の工数偏差ER1とに割り当てる様子を示したものである。尚、図8においては、非同期サブ部品SB2は図5の機種Aから機種Eの非同期部品の工数から成る。
したがって、このように非同期サブ部品SB2の組み付け工数を集約して非同期サブ部品SB3としたことにより、より一層生産効率の高い生産ラインを構築することができる。また、非同期サブ部品SB3の工数は、前記工数偏差ER1、ER2以外に専用工数を付加してもよい。
【0020】
このようにして、構築された生産ラインでは、メインライン1における機種毎に異なるメイン部品MB間の工数偏差ER2と各サブラインにおける機種毎に異なる同期サブ部品SB1間の工数偏差ER1とによって生じる余剰の労働力を、非同期サブ部品SB2の組み付け作業に割り当てることが可能となる。
【0021】
つまり、部品点数の多い機種Dが搬送されている場合に作業に従事していた作業者は、例えば、機種Dに比較して部品点数の少ない機種Bが搬送されると、図7に示すように、メインライン1においてはメイン部品MBの組み立ての際に余剰人員が出てしまい、サブラインにおいても、図6に示すように同期サブ部品SB1の組み立ての際に余剰人員が出てしまう。ところが、これら余剰人員は、図6に示すように、機種に関係なく非同期で組み立てられる新非同期サブ部品SB3、つまり非同期サブ部品SB2を集約し全組み付け工数を低減し新工数となったもの組み立てに割り当てられるため無駄が生じないのである。
【0022】
具体的には、例えば、図1の下廻りゾーンZCにおいて、部品点数の少ない機種が搬送されている場合には組み付け工数が少ないゆえに、メインライン1においても、リヤサス小組コンベアサブライン14やフロントサスASSY小組コンベアサブライン15において作業人員が余るが、これらの余剰の作業人員を、リヤサスASSY小組サブサブライン18やドレスUPエンジン小組サブサブライン19における非同期サブ部品SB2の組立に割り当てることで、労力の無駄をなくすことができる。
したがって、部品点数の最も多い機種Dに合わせて全てのゾーンで人員を確保した場合に比較して、人員を削減できるばかりでなく、作業者にかかる負荷を均一化して、生産効率の高い生産ラインを構築することができる。尚、共通の部品を抽出する際に抽出工数が増える点以外は機種数の変化に影響されないため、汎用性が高いメリットもある。
【0023】
その結果、多機種混合生産方式を採用した場合においても、メインラインを短縮しつつ、機種の違いによる生産工数の偏差を吸収して効率よく生産でき、実質的な生産能力の拡大と付帯設備の減少を実現して、大幅なコストダウンを図ることができる。
【0024】
次に、図9に基づいて、上記生産ラインの構築方法を実施するための装置について説明する。
図9に示すように、この装置は図3に示すフローチャートを記憶させるための制御回路100に、該制御回路100に対するデータの入力を行う入力手段101が接続され、更に該制御回路100から出力されたデータを表示する表示装置102が接続されたものである。
【0025】
先ず、前記入力手段101により、各機種毎の部品のデータを入力する。この入力の際には、機種毎にその部品の工数、構成部品、組み付けるゾーンなどを入力する。この入力が終了すると、前記制御回路100により、図2に示すような部品マップが作成される。
次に、メインライン1に投入される機種が入力手段101により選択されると、制御回路100は前述した図3のフローチャートにしたがって、メイン部品の抽出(ステップS1)、サブ部品の抽出(ステップS2)、同期サブ部品の抽出(ステップS3)、非同期サブ部品の抽出(ステップS4)、非同期サブ部品の抽出(ステップS4)、非同期サブ部品のとりまとめ(ステップS5)、非同期サブ部品の割り当て(ステップS6)の順に処理を実行する。
これにより得られた結果は、表示装置102に表示され、この表示結果に沿って、非同期サブ部品の割り当て対象となる人員が選択される。
【0026】
尚、この発明は上記実施形態に限られるものではなく、例えば、自動車の生産ラインのみならず各種電気製品等、様々な製品の生産ラインに適用することができる。
【0027】
【発明の効果】
以上説明してきたように、請求項1に記載した発明によれば、メインラインにおける機種毎に異なるメイン部品間の工数偏差や、サブラインにおける機種毎に異なる同期サブ部品間の工数偏差によって生じる余剰の労働力を、非同期サブ部品の組み付け作業に割り当てることが可能となるため、機種の異なる製品を生産する場合においても、作業者にかかる負荷を均一化して、生産効率の高い生産ラインを構築することができるという効果がある。
請求項2に記載した発明によれば、非同期サブ部品の組み付け工数を集約し、全組み付け工数を低減させた新組み付け工数を前記メイン部品間の工数偏差と同期サブ部品間の工数偏差との少なくともいずれか一方に割り当てることが可能となるため、より一層生産効率の高い生産ラインを構築することができる効果がある。
【図面の簡単な説明】
【図1】 この発明の実施形態により構築された自動車の車体組み立てラインの全体図である。
【図2】 あるゾーンにおける部品と機種の関係を示す説明図である。
【図3】 この発明の実施形態の生産ラインの構築手順を示すフローチャート図である。
【図4】 あるゾーンにおける機種毎の工数を示すグラフ図である。
【図5】 あるゾーンにおける機種毎のサブ部品の工数を示すグラフ図である。
【図6】 あるゾーンにおけるサブ部品のうち非同期サブ部品をとりまとめた状態を示すグラフ図である。
【図7】 あるゾーンにおける機種毎のメイン部品の工数を示すグラフ図である。
【図8】 非同期サブ部品の組み付け工数を集約した状態を示すグラフ図である。
【図9】 この発明の実施形態の生産ラインの構築方法を実施するための装置の概略構成図である。
【符号の説明】
1 メインライン
2 車体(製品)
3〜12、14〜17、20〜23 サブライン
ER1 工数偏差
ER2 工数偏差
MB メイン部品
SB サブ部品
SB1 同期サブ部品
SB2 非同期サブ部品
SB3 新非同期サブ部品
S1,S2 メインサブ分類工程
S3 同期非同期分類工程
S6 非同期サブ部品割り当て工程
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to, for example, a production line construction method capable of producing many types of automobiles on a single production line. In particular, the present invention absorbs a deviation in production man-hours due to a difference in models and efficiently produces the production line. The present invention relates to a production line construction method that can be performed.
[0002]
[Prior art]
Conventionally, for example, in a production line that performs a flow operation such as an automobile assembly line, as disclosed in Japanese Patent Application Laid-Open No. 61-21870, a main line for assembling main parts, A sub-line for assembling sub-parts is provided, and a production line using these main lines and sub-lines is constructed.
In addition, in the multi-model mixed production system that produces a large number of models on the same line, as in Japanese Patent No. 2920801, an assembly line tact is appropriately used for mixed production of a plurality of models with different assembly man-hours. What is known to improve production efficiency is known.
[0003]
[Problems to be solved by the invention]
In these conventional production lines, it is necessary to construct the production line based on the model with the largest number of parts, considering the assembly form, equipment, specifications, number of parts, etc., which differ for each model, so the main line is extended. As a result, there is a problem that ancillary facilities and the like increase with surplus man-hours due to fluctuations in man-hours between models, leading to cost increase.
[0004]
That is, in order to assemble vehicles having different numbers of parts on the same line, for example, work man-hours change according to different types of vehicles placed on a conveyor. For this reason, when a model having a small number of parts is transported, the personnel required when a model having a large number of parts is transported are not required, resulting in waste.
Accordingly, the present invention provides a production line construction method capable of efficiently performing production by absorbing a deviation in work man-hours due to a difference in models.
[0005]
[Means for Solving the Problems]
In order to solve the above-mentioned problem, the invention described in claim 1 is a production that can produce many types of products (for example, the vehicle body 2 in the embodiment) on a single main line (for example, the main line 1 in the embodiment). A method for constructing a line, which is input means for inputting part data for each model or a model input to the main line (for example, input means 101 in the embodiment), and part data for each model input by the input means. The control means (for example, the control circuit 100 in the embodiment) for preliminarily storing the procedure for classifying parts of models to be input to the main line, and the display means for displaying the result classified according to the procedure (For example, the display device 102 in the embodiment), a model to be input to the main line is input by the input means, The main parts of the common parts regardless goods-mapped data to a difference in the model (e.g., a main component MB in the embodiment) is extracted as the remaining parts sub-component (e.g., sub-component SB in the embodiment) as The main sub-classification step to be extracted (for example, steps S1 and S2 in the embodiment) and the sub-line (for example, sub-lines 3 to 12 in the embodiment, out of the sub-parts extracted in the main sub-classification step in synchronization with the main line) 14-17, 20-23) sub-parts that can be assembled are extracted as synchronous sub-parts (eg, synchronous sub-part SB1 in the embodiment), and the remaining sub-parts are asynchronous sub-parts (eg, asynchronous sub-parts in the embodiment) Synchronous asynchronous classification process (for example, step in the embodiment) to be extracted as SB2) And 3), all assembling steps of asynchronous sub-component extracted by the synchronous asynchronous classification step, excess workers caused by man-hour difference between the different main components in each model in the main line (e.g., man-hour difference ER2 in the embodiment) Asynchronous sub-parts assignment step (for example, step S6 in the embodiment) assigned to at least one of the surplus workers caused by the man-hour deviation (for example, the man-hour deviation ER1 in the embodiment) between different synchronous sub-parts for each model in the subline ), And processing according to the classification processing procedure .
By configuring in this way, the surplus labor force caused by the man-hour deviation between main parts different for each model in the main line and the man-hour deviation between synchronous parts different for each model in the sub-line is allocated to the assembly work of the asynchronous parts. It becomes possible.
The invention described in claim 2 summarizes the assembly man-hours of the asynchronous sub-components (for example, the length of the asynchronous sub-component SB2 shown in FIG. 8 of the embodiment), reduces the total assembly man-hours (for example, The length of the asynchronous sub-part SB3 in FIG. 8 in the embodiment), and the new assembly man-hours between the surplus worker caused by the man-hour deviation between the main parts and the surplus worker caused by the man-hour deviation between the synchronous sub-parts It is characterized in that it is assigned to at least one of them.
By configuring in this way, the assembly man-hours for asynchronous sub-parts are aggregated, and the new assembly man-hours that reduce the total assembly man-hours are either one of the man-hour deviation between the main parts and the man-hour deviation between the synchronous sub-parts. It becomes possible to assign.
[0006]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described below with reference to the drawings.
First, the configuration of the production line and the parts to be assembled will be described by taking a production line for assembling a car body as an example. FIG. 1 is an explanatory diagram of a main line of an automobile body assembly line. In FIG. 1, reference numeral 1 denotes a main line, in which various parts are sequentially assembled to a vehicle body (product) 2 of a different model that is painted and conveyed sequentially in the pre-painting process. Specifically, the main line 1 includes a transmission / connection zone ZA, an interior zone ZB, a lower zone ZC, an exterior zone ZD, and a composite guarantee zone ZE. It is transported to the inspection process. Here, a zone guarantee zone ZX described later is provided between the zones ZA, ZB, ZC, ZD, and ZE.
[0007]
In the transmission / line zone ZA, fuel / brake concentration piping, assembly of an air conditioner condenser unit, installation of an ABS modulator assembly, and attachment of a radiator ASSY are performed in order to route the fuel / brake concentration assembly ASSY (assembly). The ASSY subline 3, the air conditioner capacitor unit subline 4, the ABS modulator ASSY subline 5, and the radiator ASSY subline 6 are connected to each other. Each of these sublines is synchronized with the main line 1.
[0008]
In interior zone ZB, installation of roofing unit, installation of fuse unit BOX, installation of air conditioning unit, installation of headlight unit, installation of instrument panel unit ASSY on conveyor, installation of bumper assembly ASSY on conveyor To do this, roofing unit subline 7, fuse unit BOX subline 8, air conditioning unit subline 9, headlight unit subline 10, instrument panel unit assembly conveyor subline 11, and bumper assembly conveyor subline 12 are connected to each other. Yes. Each of these sublines is synchronized with the main line 1. Here, a control BOX sub-subline 13 asynchronous with the main line 1 is connected to the instrument panel unit ASSY conveyor subline 11. In this control box sub-subline 13, all types of control boxes are assembled.
[0009]
In the lower zone ZC, a rear suspension (rear suspension) is assembled on a conveyor, a front suspension (front suspension) is assembled on a conveyor, a fuel tank unit is installed, and an exhaust pipe (exhaust pipe) ASSY is installed. In order to attach a small assembly, a rear suspension subassembly conveyor subline 14, a front suspension ASSY subassembly conveyor subline 15, a fuel tank unit subline 16, and an exhaust assembly subassembly 17 are connected to each other. Each of these sublines is also synchronized with the main line 1.
[0010]
Here, a rear suspension ASSY small assembly sub subline 18 is connected to the rear suspension small assembly conveyor subline 14, and a dress UP engine small assembly subsubline 19 is connected to the front suspension ASSY small assembly conveyor subline 15. The dress-up engine subassembly means that the engine and the mission are assembled.
The rear suspension assembly sub-subline 18 is a line for assembling the rear suspension assembly asynchronously with the main line 1 and supplying the rear suspension assembly sub-subline 14 regardless of the model. The dress UP engine sub assembly sub-subline 19 is a line that performs assembly of the dress UP engine asynchronously with the main line 1 regardless of the model, and supplies the assembly to the front suspension ASSY sub conveyor sub-line 15.
[0011]
And in the exterior zone ZD, in order to attach the front and rear sheets ASSY and the front and rear glasses ASSY, the sheet ASSY sublines 20 and 21 and the glass ASSY sublines 22 and 23 are respectively connected. Each of these sublines is also synchronized with the main line 1.
Finally, in the composite guarantee zone ZE, inspections such as liquid injection work, battery installation, fuel injection, engine start confirmation, etc. are performed.
In the exterior zone ZD, the front door ASSY, the rear door ASSY, and the tailgate ASSY that have been removed in advance in the transmission / passage zone ZA and assembled on the door / tailgate ASSY line 24 are also assembled. In addition to the main line 1, sublines 3 to 12, 14 to 17, 20 to 23, and subsublines 13, 18, and 19, sub sublines (not shown) are provided.
Each of the above zones is divided by function, and the work that has been done for each task in the past is divided by function, and zone guarantee is performed for each function, that is, the zone guarantee zone ZX provided for each zone. Prevents disassembly and reassembly after assembly. For example, in the transmission / communication zone ZA, since both ends of the trunk lid opening / closing cable are attached to predetermined parts and the operation is confirmed in the zone guarantee zone ZX, an assembly failure is detected in the rear zone, and is disassembled and reassembled. This does not happen.
[0013]
Specifically, when assembling for each engagement as in the prior art, for example, when the engagement for attaching the front end of the cable is different from the engagement for attaching the rear end of the cable, the front end of the cable is When the attachment member has been attached without giving a predetermined play to the cable, the assembly failure is not detected until the attachment member attaching the rear end of the cable finds it. Therefore, when a defect is found, in some cases, surrounding parts must be disassembled and reassembled. However, since the zone guarantee is performed for each zone in this way, a defect does not occur later, and the work can be completed for each zone.
[0014]
By the way, different types of vehicle bodies 2 are transported in each zone. For example, if the presence or absence of parts in a certain zone for each model is shown in FIG. 2, the number of parts and assembly man-hours may differ depending on the model. Recognize.
Specifically, in the model D, the part No. 1 to part no. However, in model A, part No. 2. Part No. 4. Part No. 7 does not exist and the model No. 1. Part No. 6. Parts NO. 7 does not exist.
In model C, part No. 1. Part No. 4. Part No. 6 does not exist. 2, NO. 7 does not exist. This is because the number of parts does not match because the equipment is different depending on the model.
[0015]
That is, in this zone, the part No. 3. Part No. 5. Part No. No. 8 is a common part for model A, model B, model C, model D, and model E. 1, NO. 2, NO. 4, NO. 6, NO. 7 is a different part for model A, model B, model C, model D, and model E.
Similarly, in other zones, there are parts that are common to different models and parts that are not common.
Therefore, when a production line is constructed in accordance with a model having a large number of parts, an extra work manpower is required in the assembly work of a model having a small number of parts.
[0016]
Next, a production line construction method will be described with reference to the flowchart shown in FIG. 3 and FIGS.
First, as shown in FIG. 3, in any zone, a common part is extracted as a main part MB regardless of the model (step S1), and the remaining parts are extracted as sub-parts SB (step S2). Step S1 and step S2 constitute a main sub classification process. Specifically, as shown in FIG. 4, the man-hours for each model are represented by a bar graph (the vertical axis is the time as man-hours), and the sub-components SB that are not common to the main components MB common to the models A to E are classified. . In the example shown in FIG. 2, for each model A, B, C, D, E, the part number. 3. Part No. 5. Part No. 8 is extracted as the main part MB, and other part No. 8 is extracted. 1, NO. 2, NO. 4, NO. 6, NO. 7 is extracted as a sub-part SB.
In FIG. 4, what is extracted as the sub-component SB is shown on the sub-side, which is indicated by a chain line. Here, since the main parts MB are different in model even if the parts are common, the man-hours for each model do not match, resulting in variations. A deviation caused by the variation is indicated by hatching in FIG.
[0017]
Next, in step S3 of FIG. 3, out of the sub-parts SB extracted in the main sub-classification step, sub-parts SB that can be assembled in the sub-line in synchronization with the main line 1 are extracted as synchronous sub-parts SB1, and then in step In S4, the remaining subcomponent SB is extracted as an asynchronous subcomponent SB2. Step S3 and step S4 constitute a synchronous asynchronous classification process.
Specifically, as shown in FIG. 5, the man-hours of the sub-parts SB are indicated by bar graphs (the vertical axis is the time as man-hours), and each of the models A to E can be assembled in sub-lines in synchronization with the main line 1. The synchronous subcomponent SB1 and the asynchronous subcomponent SB2 that cannot be synchronized are separated from each other on the boundary line. Here, even if the synchronous sub-component SB1 is shared, the models are different, and therefore the man-hours for each model do not match, resulting in variations. The man-hour deviation ER1 caused by the variation is indicated by hatching. Then, in step S5 of FIG. 3, the asynchronous sub-component SB2 is collected as a new asynchronous sub-component SB3 which is not a model but a single group (asynchronous sub-component collecting step). Specifically, the asynchronous sub-part SB2 (shown in FIG. 5) indicating the lower part from the boundary line is represented by a model so that the man-hour of the sub-part SB in FIG. 6 is indicated by a bar graph (the vertical axis is the time as the man-hour). Each is grouped as a new asynchronous sub-component SB3, which is a single cluster as a whole.
[0018]
Then, in step S6 of FIG. 3, all the assembly steps of all (all models) of the new asynchronous sub-part SB3 extracted in step S3 and step S4 and collected in step S5, that is, the asynchronous sub-part SB2, are aggregated. Allocating the new assembly man-hours with reduced man-hours to the man-hour deviation between main parts MB different for each model in main line 1 and man-hour deviation between synchronous sub-parts SB1 different for each model in sub-line finish. It should be noted that the assembling man-hours of the asynchronous sub-parts SB2 of all models are not so large, and either the man-hour deviation between the main parts MB different for each model in the main line 1 or the man-hour deviation between the synchronous sub-parts SB1 different for each model in the sub-line. If assignment to either one is sufficient, there is no need to assign to both. This step S6 constitutes an asynchronous sub-part assignment process.
Specifically, the total assembly man-hour of the new asynchronous sub-part SB3 in FIG. 6 is a bar graph of the man-hour deviation ER1 between the synchronous sub-parts SB1 of each model indicated by hatching in FIG. 6 and the man-hour of the main part MB in FIG. It is assigned to at least one of the manhour deviation ER2 between the main parts MB of each model indicated by hatching (the vertical axis is the time as the manhour).
[0019]
Here, FIG. 8 shows an asynchronous sub-part SB3 in which the assembly man-hours of the asynchronous sub-component SB2 shown in FIG. 5 are aggregated and the assembly man-hour is reduced as shown in FIG. This shows how the assembly man-hours are assigned to the man-hour deviation ER2 between main parts MB different for each model in the main line 1 and the man-hour deviation ER1 between synchronous sub-parts SB1 different for each model in the sub-line. In FIG. 8, the asynchronous subcomponent SB2 includes the number of man-hours for the asynchronous components of model A to model E in FIG.
Therefore, by integrating the assembly man-hours of the asynchronous sub-component SB2 into the asynchronous sub-component SB3, a production line with higher production efficiency can be constructed. In addition, the man-hours of the asynchronous sub-component SB3 may include dedicated man-hours in addition to the man-hour deviations ER1 and ER2.
[0020]
In the production line thus constructed, surplus produced by the man-hour deviation ER2 between the main parts MB different for each model in the main line 1 and the man-hour deviation ER1 between the synchronous sub-components SB1 different for each model in each sub-line. The labor force can be assigned to the assembly work of the asynchronous sub-part SB2.
[0021]
That is, when the model D having a large number of parts is transported, an operator who is engaged in the work, for example, when the model B having a small number of parts compared to the model D is transported, as shown in FIG. Moreover, in the main line 1, surplus personnel appear when assembling the main part MB, and also in the sub line, surplus personnel appear when assembling the synchronous sub part SB1 as shown in FIG. However, as shown in FIG. 6, these surplus personnel are assembled in a new asynchronous sub-part SB3 that is assembled asynchronously regardless of the model, that is, the asynchronous sub-part SB2 is aggregated to reduce the total assembly man-hours. There is no waste because it is assigned.
[0022]
Specifically, for example, in the lower zone ZC of FIG. 1, when a model with a small number of parts is being transported, the assembly man-hours are small. Therefore, the rear suspension subassembly conveyor subline 14 and the front suspension ASSY subassembly are also provided in the main line 1. Although there are surplus workers in the conveyor subline 15, these surplus workers are allocated to the assembly of the asynchronous subpart SB2 in the rear suspension ASSY subassembly subsubline 18 and the dress up engine subassembly subsubline 19, thereby eliminating waste of labor. Can do.
Therefore, compared to the case where personnel are secured in all zones according to the model D with the largest number of parts, not only can the number of personnel be reduced, but also the load on the workers can be made uniform and the production line can be produced with high efficiency. Can be built. It should be noted that there is a merit of high versatility because it is not affected by changes in the number of models except that the number of extraction steps increases when extracting common parts.
[0023]
As a result, even when the multi-model mixed production method is adopted, the main line can be shortened and the production man-hours due to the difference in the models can be absorbed efficiently. The reduction can be realized and the cost can be greatly reduced.
[0024]
Next, an apparatus for implementing the production line construction method will be described with reference to FIG.
As shown in FIG. 9, in this apparatus, an input means 101 for inputting data to the control circuit 100 is connected to the control circuit 100 for storing the flowchart shown in FIG. The display device 102 for displaying the received data is connected.
[0025]
First, the input means 101 is used to input component data for each model. At the time of this input, the man-hour of the part, the component parts, the zone to be assembled, etc. are input for each model. When this input is completed, the control circuit 100 creates a component map as shown in FIG.
Next, when a model to be input to the main line 1 is selected by the input unit 101, the control circuit 100 extracts a main part (step S1) and a sub part (step S2) according to the flowchart of FIG. ), Extraction of synchronous subparts (step S3), extraction of asynchronous subparts (step S4), extraction of asynchronous subparts (step S4), collection of asynchronous subparts (step S5), allocation of asynchronous subparts (step S6) ) In the order.
The result thus obtained is displayed on the display device 102, and a person who is to be assigned an asynchronous sub-part is selected along the display result.
[0026]
In addition, this invention is not restricted to the said embodiment, For example, it can apply not only to the production line of a motor vehicle but to the production line of various products, such as various electric products.
[0027]
【The invention's effect】
As described above, according to the first aspect of the present invention, the surplus caused by the man-hour deviation between main parts different for each model in the main line or the man-hour deviation between synchronous sub-parts different for each model in the sub-line. Since it is possible to allocate the work force to the assembly work of asynchronous sub-parts, even when producing products of different models, the load on workers should be equalized and a production line with high production efficiency should be built There is an effect that can be.
According to the invention described in claim 2, the assembly man-hours of the asynchronous sub-parts are aggregated, and the new assembly man-hours obtained by reducing the total assembly man-hours are at least the man-hour deviation between the main parts and the man-hour deviation between the synchronous sub-parts. Since it can be assigned to either one, there is an effect that a production line with higher production efficiency can be constructed.
[Brief description of the drawings]
FIG. 1 is an overall view of an automobile body assembly line constructed according to an embodiment of the present invention.
FIG. 2 is an explanatory diagram showing the relationship between parts and models in a certain zone.
FIG. 3 is a flowchart showing a production line construction procedure according to the embodiment of the present invention.
FIG. 4 is a graph showing man-hours for each model in a certain zone.
FIG. 5 is a graph showing the number of sub-parts for each model in a certain zone.
FIG. 6 is a graph showing a state in which asynchronous sub-parts are gathered among sub-parts in a certain zone.
FIG. 7 is a graph showing man-hours for main parts for each model in a certain zone.
FIG. 8 is a graph showing a state in which assembly man-hours for asynchronous sub-parts are aggregated.
FIG. 9 is a schematic configuration diagram of an apparatus for carrying out a production line construction method according to an embodiment of the present invention.
[Explanation of symbols]
1 Main line 2 Body (product)
3-12, 14-17, 20-23 Subline ER1 Effort deviation ER2 Effort deviation MB Main part SB Subpart SB1 Synchronous subpart SB2 Asynchronous subpart SB3 New asynchronous subpart S1, S2 Main subclassification process S3 Synchronous asynchronous classification process S6 Asynchronous sub-part assignment process

Claims (2)

多機種の製品を単一のメインラインで生産できる生産ラインの構築方法であって、
機種毎の部品データまたはメインラインに投入される機種を入力する入力手段と、
前記入力手段により入力された機種毎の部品データを部品マップ化し、またメインラインに投入される機種の部品を分類処理する手順を予め記憶する制御手段と、
前記手順に従って分類された結果を表示する表示手段よりなり、
メインラインに投入される機種を前記入力手段により入力し、前記部品マップ化されたデータを機種の違いにかかわらず共通する部品をメイン部品として抽出し、残りの部品をサブ部品として抽出するメインサブ分類工程と、
該メインサブ分類工程において抽出されたサブ部品のうちメインラインと同期してサブラインで組み付け可能なサブ部品を同期サブ部品として抽出し、残りのサブ部品を非同期サブ部品として抽出する同期非同期分類工程と、
該同期非同期分類工程で抽出された非同期サブ部品の全組み付け工数を、メインラインにおける機種毎に異なるメイン部品間の工数偏差によって生ずる余剰作業者とサブラインにおける機種毎に異なる同期サブ部品間の工数偏差によって生ずる余剰作業者との少なくともいずれか一方に割り当てる非同期サブ部品割り当て工程よりなる前記分類処理する手順に従って処理することを特徴とする生産ラインの構築方法。
A production line construction method that can produce many types of products on a single main line,
An input means for inputting part data for each model or a model to be input to the main line,
Control means for preliminarily storing a procedure for classifying parts data of models to be input to the main line, and parts data for each model input by the input means is converted into a parts map;
Comprising display means for displaying the results classified according to the procedure,
The model input to the main line is input by the input means, the component mapped data is extracted as a main component regardless of the model, and the remaining components are extracted as sub components. A classification process;
A synchronous asynchronous classification step of extracting sub-components that can be assembled in the sub-line in synchronization with the main line among the sub-components extracted in the main sub-classification step as synchronous sub-components, and extracting the remaining sub-components as asynchronous sub-components; ,
The total assembly man-hours of asynchronous sub-parts extracted in the synchronous asynchronous classification process are the surplus workers caused by the man-hour deviation between main parts that differ for each model in the main line , and the man-hour deviation between synchronous sub-parts that differs for each model in the sub-line A method for constructing a production line, characterized in that processing is performed in accordance with the classification processing procedure comprising an asynchronous sub-part assignment step that is assigned to at least one of surplus workers generated by
前記非同期サブ部品の組み付け工数を集約し、全組み付け工数を低減させて新組み付け工数とし、該新組み付け工数を、前記メイン部品間の工数偏差によって生ずる余剰作業者と同期サブ部品間の工数偏差によって生ずる余剰作業者との少なくともいずれか一方に割り当てるようにしたことを特徴とする請求項1に記載の生産ラインの構築方法。Aggregate assembly man-hours of the asynchronous sub-component, reduces the total assembling steps and new assembling man-hour, the該新assembling steps, the steps deviation between the excess workers and synchronization sub-component caused by man-hour difference between the main part 2. The production line construction method according to claim 1, wherein the production line is assigned to at least one of the surplus workers generated .
JP2000289492A 1999-12-28 2000-09-22 Production line construction method Expired - Lifetime JP3737351B2 (en)

Priority Applications (8)

Application Number Priority Date Filing Date Title
JP2000289492A JP3737351B2 (en) 2000-09-22 2000-09-22 Production line construction method
CA002393536A CA2393536C (en) 1999-12-28 2000-12-25 Production line construction method, body assembly method, and body assembly line
GB0214125A GB2375741B (en) 1999-12-28 2000-12-25 Method for organizing a production line and method and apparatus for assembling a vehicle body
PCT/JP2000/009196 WO2001047661A1 (en) 1999-12-28 2000-12-25 Production line construction method, body assembly method, and body assembly line
CN00817819.4A CN1195604C (en) 1999-12-28 2000-12-25 Production line construction method, body assembly method and body assembly line
US10/130,296 US6918168B2 (en) 1999-12-28 2000-12-25 Assembly line organizing method
BRPI0016748-7A BR0016748B1 (en) 1999-12-28 2000-12-25 Assembly line organization method and Assembly method and line of a plurality of vehicle chassis types.
US11/117,404 US7269900B2 (en) 1999-12-28 2005-04-29 Method for assembling a plurality of vehicle body types

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000289492A JP3737351B2 (en) 2000-09-22 2000-09-22 Production line construction method

Publications (2)

Publication Number Publication Date
JP2002103186A JP2002103186A (en) 2002-04-09
JP3737351B2 true JP3737351B2 (en) 2006-01-18

Family

ID=18772881

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000289492A Expired - Lifetime JP3737351B2 (en) 1999-12-28 2000-09-22 Production line construction method

Country Status (1)

Country Link
JP (1) JP3737351B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040039120A (en) * 2002-11-04 2004-05-10 현대자동차주식회사 Method for generating production data of vehicles
JP7115290B2 (en) * 2018-12-20 2022-08-09 トヨタ自動車株式会社 automobile production system

Also Published As

Publication number Publication date
JP2002103186A (en) 2002-04-09

Similar Documents

Publication Publication Date Title
WO2001047661A1 (en) Production line construction method, body assembly method, and body assembly line
JP2000085649A (en) Vehicle assembly line
Weber Automotive development processes: Processes for successful customer oriented vehicle development
KR101476806B1 (en) Apparatus for maintenance of a vehicle
JP3737351B2 (en) Production line construction method
CN101081597A (en) Vehicle cockpit with self supporting submodules
JP3898428B2 (en) Tact setting method for vehicle assembly line
US20060143921A1 (en) Modular construction coach body for large vehicles, in particular rail vehicles for passenger transport and method for production of such a coach body
Axelsson et al. A Comparative Case Study of Distributed Network Architectures for Different Automotive Applications.
CN201368984Y (en) Multiple-protocol data convertor for diagnosing automobile fault
CA2280414C (en) Zone inspection manufacturing line
CN102943709A (en) Multifunctional engine control unit
Gutiérrez et al. Ambient intelligence in intermodal transport services: a practical implementation in road logistics
Axelsson et al. Correlating business needs and network architectures in automotive applications-a comparative case study
JP3989427B2 (en) Vehicle assembly line
Al-Zaher et al. Cost-effective design of automotive framing systems using flexibility and reconfigurability principles
Gritsuk et al. Features of the subject area of the information model of the system of remote monitoring of the technical condition and modes of operation of the truck
Schockenhoff et al. Customer-Oriented Concept Assessment
Ahrens Automotive Engineering
DE102009019957A1 (en) Vehicle has computer unit, where computer unit is central computer unit, in which two controllers are integrated, and computer unit is arranged in interior of vehicle and controls or regulates multiple vehicle functions
Lograsso et al. Low-Power Flexible Controls Architecture for General Motors Partnership for a New Generation (Pngv) Precept Vehicle
Bowler et al. A math-data environment to improve vehicle creation
Wedeniwski et al. Enterprise Architectures: Surrounded by Historical Structures
Chang et al. System development concept in car body electronics
DE102021104809A1 (en) Roof module, vehicle body and method of manufacturing a vehicle body

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050726

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050824

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051018

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051026

R150 Certificate of patent or registration of utility model

Ref document number: 3737351

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081104

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091104

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091104

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101104

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101104

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111104

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111104

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121104

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131104

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term