JP3706377B2 - Roof repair method - Google Patents
Roof repair method Download PDFInfo
- Publication number
- JP3706377B2 JP3706377B2 JP2003321062A JP2003321062A JP3706377B2 JP 3706377 B2 JP3706377 B2 JP 3706377B2 JP 2003321062 A JP2003321062 A JP 2003321062A JP 2003321062 A JP2003321062 A JP 2003321062A JP 3706377 B2 JP3706377 B2 JP 3706377B2
- Authority
- JP
- Japan
- Prior art keywords
- hook bolt
- new
- roof
- existing
- roof material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Roof Covering Using Slabs Or Stiff Sheets (AREA)
Description
本発明は、老朽化した波形スレート板の既設屋根材の上に新規屋根材を設置する屋根補修工法に関するものである。 The present invention relates to a roof repair method for installing a new roof material on an existing roof material of an aging corrugated slate plate.
大型工場、倉庫、体育館等の波形スレート板屋根材が古くなったとき、これを撤去して新規屋根材を設置すると、工事期間中、工場での操業や、倉庫等の使用が不可能となる。そこで波形スレート板の既設屋根材を撤去することなく、その上に金属板の新規屋根材を設置することが行われている。 When the corrugated slate plate roofing material of a large factory, warehouse, gymnasium, etc. becomes old, if this is removed and a new roofing material is installed, operation in the factory or use of the warehouse, etc. becomes impossible during the construction period. . Therefore, a new roof material made of a metal plate is installed on the corrugated slate plate without removing the existing roof material.
この場合、新規屋根材の上から新規屋根材および既設屋根材に長いドリルタッピングネジを貫通させ、その先端を既設屋根材を支持する母屋にねじ込み新規屋根材を固定する従来方法では、建築物内に既設屋根材や母屋の孔あけによる施工くず、ごみ、ちり等が落下する。 In this case, in the conventional method in which a long drill tapping screw is passed through the new roof material and the existing roof material from above the new roof material, and the tip is screwed into the main building supporting the existing roof material, the new roof material is fixed. Construction waste, garbage, dust, etc. due to drilling of existing roofing materials and purlins fall.
このため、操業中の工場や使用中の倉庫、体育館等に落下物の防止のためのテントを張るなど、大がかりな養生が必要である。しかも孔あけやドリルタッピングの締付けによって老朽化した既設屋根のスレート板に割れ、ひび、欠け等が生じるおそれがある。 For this reason, large-scale curing is required, such as setting up tents to prevent falling objects in factories in operation, warehouses in use, and gymnasiums. Moreover, there is a risk that cracks, cracks, chips, etc. may occur in the slate plate of the existing roof that has deteriorated due to drilling or drill tapping tightening.
そこで、既設屋根材に、これを加工することなく固定できるクランプ金具を介して新規屋根材を設置する補修工法が提案され、実施されている。 In view of this, a repair method for installing a new roof material via a clamp fitting that can be fixed to the existing roof material without processing it has been proposed and implemented.
例えば下記特許文献1の工法では、クランプ金具として、金属板からなるほぼ箱形で、上部を新規屋根材の山部に沿う断面形状とし、底面部を既設屋根材の山部に沿う断面形状とし、底面部にはその端縁に開口する切欠きを形成したクランプ金具を用い、上記切欠きを、既設屋根材の山部から突出するフックボルトに設けたナットの座金と既設屋根材の山部との間の隙間からフックボルト軸まわりに嵌込んでクランプ金具をその中にフックボルトの上端を収納した状態で既設屋根材の山部に固定し、このようにして固定された多数のクランプ金具の上に新規屋根材の山部を重ね合わせてドリルタッピングネジ等によりクランプ金具にねじ締め固定する。
For example, in the method of
また例えば下記特許文献2の工法では、クランプ金具として中央部が既設屋根材の山部を跨ぐ断面山形で、頂端に孔を設け、中央部の左右の脚端から支持部が翼状に上方へ延出するクランプ金具を用い、既設屋根材の山部から突出する既設のフックボルトの上端をクランプ金具の頂端の孔に貫通させてクランプ金具の両脚端を既設屋根材の谷部に支持せしめ、フックボルトを利用してクランプ金具をナット締めすることでクランプ金具を既設屋根材に固定し、このように固定されて直線状に配列する複数クランプ金具の上記支持部上に屋根下地材を架設してドリルタッピングネジ等によりねじ締め固定し、この下地材の上に新規屋根材をねじ締め固定するものである。
これらの公報の工法によればいずれも既設のスレート屋根材に孔あけすることなく新規屋根材を設置することができる。 According to the methods described in these publications, a new roof material can be installed without drilling holes in an existing slate roof material.
ところで更に、上記クランプ金具や屋根下地材等の屋根補修用の部品をできるだけ少なくし、ないしは廃止し、かつ新規屋根材の板厚を薄くするなどして補修コストを低減し、同時に補修屋根構造を軽量化することで耐震上でも有利にしたいという要望が出てきている。 By the way, the number of roof repair parts such as clamp fittings and roof base materials is reduced or eliminated as much as possible, and the thickness of the new roof material is reduced to reduce the repair cost. There is a demand to make it more advantageous in terms of earthquake resistance by reducing the weight.
この要望に応える工法として、新規屋根材に、既設屋根材から突出するフックボルト対応位置で孔を形成しておき、この孔にフックボルトを挿通させて既設屋根材の上に新規屋根材を直接重ね合せ、新規屋根材に、フックボルト挿通孔およびこれから突出するフックボルトの上端を被覆するカバー部材を適宜の手段で固定する工法が考えられ得る。 As a method of responding to this demand, a hole is formed in the new roof material at a position corresponding to the hook bolt protruding from the existing roof material, and the hook bolt is inserted into this hole so that the new roof material is directly placed on the existing roof material. A method of fixing the cover member covering the hook bolt insertion hole and the upper end of the hook bolt protruding therefrom to the new roof material by appropriate means can be considered.
この工法によれば、クランプ金具や屋根下地材も不要であるし、また新規屋根材は既設屋根材の上に直接に重ね合せて支持させることができるから従来のような強度を必要とせず、板厚を薄くすることができ、またアルミニウムやプラスチックの屋根材の使用も可能となる。 According to this method, there is no need for clamp fittings and roof base materials, and new roof materials can be directly superposed on and supported on existing roof materials, so conventional strength is not required, The plate thickness can be reduced, and aluminum or plastic roofing materials can be used.
しかしながら、この工法には次のような問題がある。即ち、既設のスレート板屋根、特に大型工場や体育館などの屋根では建物によって既設のフックボルトの設置位置が山部2つおきであったり3つおきであったりして一定でなく、また同一建物の屋根でも2つおきの部分や3つおきの部分などがある。また屋根施工後に補強のために既設のフックボルト間に更に新しいフックボルトを設ける場合もある。このため新規屋根材に孔あけを行うに際しては、既設屋根の各部についてフックボルトの配置を点検し、配置に合わせて新規屋根材に孔あけをしなければならず、作業が極めて面倒で、この工法の実施が阻害されている。 However, this method has the following problems. In other words, on existing slate plate roofs, especially large factory and gymnasium roofs, the installation position of existing hook bolts is not constant because every two or three mountain parts are installed depending on the building. Even every roof has every second and every third part. Further, a new hook bolt may be provided between the existing hook bolts for reinforcement after the roof construction. For this reason, when drilling a new roof material, it is necessary to inspect the arrangement of hook bolts for each part of the existing roof, and to drill a hole in the new roof material according to the arrangement, which is very troublesome. Implementation of the construction method is hindered.
そこで本発明は、既設の波形スレート板屋根の屋根上で、フックボルト位置に対応して作業性よく新規屋根材に孔あけを行うことができ、この屋根材を既設屋根材に設置することで補修コストの低減および補修屋根の軽量化を実現する屋根補修工法を提供することを課題としてなされたものである。 Therefore, the present invention is capable of drilling a new roof material with good workability corresponding to the position of the hook bolt on the roof of the existing corrugated slate plate roof, and installing this roof material on the existing roof material. An object of the present invention is to provide a roof repair method for reducing repair costs and reducing the weight of repair roofs.
本発明は、屋根材を母屋に固定するフックボルトの上端が山部から突出する波形スレート板の既設屋根材に、これを覆う波形金属板または波形プラスチック板の新規屋根材を設置する屋根補修工法であって、新規屋根材の山部に、既設屋根材の山部の上記フックボルト対応位置で、フックボルト挿通孔を形成する孔あけ工程と、上記フックボルト挿通孔に上記フックボルトの上端を挿通させて新規屋根材を既設屋根材の上に重ね合せ載置する新規屋根材載置工程と、新規屋根材の上記フックボルト挿通孔の上に、パッキン材を介在せしめてカバー部材を、その上端に形成したフックボルト挿通孔に上記フックボルトの上端を挿通せしめて新規屋根材の山部を跨ぐように設置するカバー部材設置工程と、上記カバー部材のフックボルト挿通孔から突出する上記フックボルトの上端からナット部材で上記カバー部材を上から締込んで、上記カバー部材を介して新規屋根材を既設屋根材に押付け固定する新規屋根材固定工程と、上記カバー部材に、そのフックボルト挿通孔および外挿通孔から突出するフックボルトの上端を覆うキャップを取付けるキャップ取付け工程とからなり、上記孔あけ工程では、母屋の上方位置で既設屋根材の山部から突出して直線状に配列する上記各フックボルトの上端に、先端を錐状とした孔あけ工具を支持せしめ、既設屋根材を覆うようにして位置決めした新規屋根材を上記孔あけ工具の先端に支持せしめ、新規屋根材の支持点まわりに打込み工具を打込んで上記孔あけ工具を新規屋根材に貫通させて孔あけを行ない、孔あけされた新規屋根材の既設屋根材上への落下により上記新規屋根材載置工程を完了せしめる(請求項1)。 The present invention relates to a roof repair method for installing a new roof material of a corrugated metal plate or a corrugated plastic plate on an existing roof material of a corrugated slate plate in which an upper end of a hook bolt for fixing the roof material to a main building protrudes from a mountain portion. A step of forming a hook bolt insertion hole at a position corresponding to the hook bolt of the peak portion of the existing roof material on the peak portion of the new roof material, and an upper end of the hook bolt at the hook bolt insertion hole. A new roofing material placing step for inserting and placing the new roofing material on the existing roofing material, and a cover member by interposing a packing material on the hook bolt insertion hole of the new roofing material, A cover member installation step in which the upper end of the hook bolt is inserted into the hook bolt insertion hole formed at the upper end so as to straddle the mountain portion of the new roof material, and the hook bolt insertion hole of the cover member A new roofing material fixing step in which the cover member is tightened from above with a nut member from the upper end of the protruding hook bolt, and the new roofing material is pressed and fixed to the existing roofing material through the cover member, and the cover member, A cap mounting step for attaching a cap that covers the upper end of the hook bolt projecting from the hook bolt insertion hole and the outer insertion hole. In the above drilling step, it projects linearly from the peak portion of the existing roofing material at a position above the main building. A drilling tool with a conical tip is supported on the upper end of each of the hook bolts arranged in the above, and a new roofing material positioned so as to cover the existing roofing material is supported on the tip of the drilling tool, and a new roof is formed. The existing roofing material of the new roofing material that has been drilled by driving a driving tool around the support point of the material and penetrating the above drilling tool through the new roofing material. Allowed to complete the new roofing placing step by dropping to (claim 1).
この工法では新規屋根材を既設屋根材上の設置位置に位置決めして孔あけ工具に支持させ、新規屋根材の支持点まわりを打込み工具で打ち込むと孔あけ工具の先端が新規屋根材をつき破って孔があけられ、同時に新規屋根材は既設屋根材の上に載置された状態となる。後は、上記カバー部材を取付け、更にこれにキャップを取付けることで新規屋根材の設置は完了する。 In this method, the new roofing material is positioned at the installation position on the existing roofing material and supported by the drilling tool, and when the driving tool is driven around the support point of the new roofing material, the tip of the drilling tool breaks through the new roofing material. The new roofing material is placed on the existing roofing material at the same time. After that, the installation of the new roofing material is completed by attaching the cover member and attaching a cap to the cover member.
この工法によれば、既設屋根材を支える母屋に沿って直線状に配列するフックボルトの相互間隔が不規則であっても、作業性よくフックボルト対応位置で新規屋根材に孔あけを行うことができる。また新規屋根材を固定するためのクランプ金具も、下地材も不要である。また新規屋根材は全体が既設屋根材に直接に支持されているから、従来のような大きな強度は必要なく、板厚を薄くすることができ、アルミニウム板やプラスチック板の使用も可能であり、屋根補修のコストを低減でき、補修屋根を軽量にすることができる。 According to this method, even if the distance between hook bolts arranged in a straight line along the main building supporting the existing roofing material is irregular, drilling is performed in the new roofing material at a position corresponding to the hook bolt with good workability. Can do. In addition, there is no need for clamp fittings or base materials for fixing the new roofing material. In addition, the new roofing material is directly supported by the existing roofing material, so there is no need for large strength as in the past, and the plate thickness can be reduced, and aluminum plates and plastic plates can be used. The cost of repairing the roof can be reduced, and the repaired roof can be made lighter.
上記孔あけ工具としては、先端が錐状で、軸心に基端面に開口する縦孔を有する工具が好適に用いられ、縦孔に既設のフックボルトの上端を挿入してフックボルトに支持させる。(請求項2)。 As the drilling tool, a tool having a conical tip and having a vertical hole opening in the base end surface at the axial center is preferably used, and the upper end of an existing hook bolt is inserted into the vertical hole and supported by the hook bolt. . (Claim 2).
上記打込み工具としては、打込み端を筒状に形成した工具が好適に用いられ、新規屋根材の孔あけ工具による支持点まわりに打込むことで、容易に孔あけがなされる(請求項3)。 As the driving tool, a tool having a driving end formed in a cylindrical shape is preferably used, and punching can be easily performed by driving around a support point by a drilling tool for a new roofing material. .
上記新規屋根材固定工程において、上記ナット部材として、リング状で、その内周から複数の板ばねの爪が中心方向に突出する板ばねナットを用い、上記カバー部材のフックボルト挿通孔から突出する上記フックボルトの上端を上記板ばねナットの中心に貫通させ、板ばねナットにより上記カバー部材の上端に締込むことで作業性よく新規屋根材を固定することができる(請求項4)。 In the new roofing material fixing step, as the nut member, a leaf spring nut having a ring shape and a plurality of leaf spring claws projecting in the center direction from the inner periphery thereof is projected from the hook bolt insertion hole of the cover member. A new roofing material can be fixed with good workability by passing the upper end of the hook bolt through the center of the leaf spring nut and tightening the upper end of the cover member with the leaf spring nut.
図1は本発明の屋根補修工法により新規屋根材が設置された屋根の要部断面を示すものであるが、図1により既設の波形スレート板屋根について説明すると、既設屋根材1は野地板10を介して母屋2に支持され、山部を貫通するフックボルト3の下端を母屋2のエッジに係止せしめ、山部から突出するフックボルト3の上端に取付けたナット301を、座金302およびパッキン材303を介して上記山部に対して締付けて既設屋根材1を固定せしめてある。
FIG. 1 shows a cross section of the main part of a roof on which a new roof material is installed by the roof repair method of the present invention. The existing corrugated slate plate roof will be described with reference to FIG. The
本発明の実施形態について説明する。金属板の新規屋根材4は図1および図2に示すように既設屋根材1に合致する波形で、幅は600〜700mm、長さは屋根の流れ方向長さに対応する長さ(例えば約5000mm)のものが多用される。
An embodiment of the present invention will be described. As shown in FIGS. 1 and 2, the
新規屋根材4には先ず既設屋根材1上で孔あけがなされる。図2および図3はこの孔あけ工程を示すもので、既設のフックボルト3は各母屋2(図1,図4)上の位置で既設屋根材1の山部の2つないし3つおきの間隔で直線状に配列している。孔あけ加工では図2(A)に示すように先ず各フックボルト3の上端に孔あけ工具51を支持せしめる。孔あけ工具51は鋼材からなり円柱状の基端部511と円錐形の加工部512とからなるコマ形で加工部512の先端は鋭角状に尖っている。工具51の軸心には基底面に開口する縦孔513が形成してある。縦孔513の開口側は既設のフックボルト3のナット301に嵌合する形状としてあり、加工部512内まで延びる部分はフックボルト3の上端を挿通し得る形状としてある。加工部512の外周には尖端から基端側へ縦方向に複数のV字形の溝が形成してあって、各溝間は断面三角形の尖条514を形成している。
The
孔あけ工具51は、その縦孔513に既設屋根材1から突出するフックボルト3の上端を挿入せしめることでフックボルト3に支持させる。このようにして、1枚の新規屋根材4によって補修される既設屋根材1の範囲にある各フックボルト3に孔あけ工具51を支持させる。
The
次に、新規屋根材4の1枚を、既設屋根材1への設置位置に位置決めして、図3(A)に示すように上から孔あけ工具51の先端に既設屋根材1を覆うように支持させる。そして、孔あけ工具51の先端で支持されている新規屋根材4の山部の支持点まわりに上から打込み工具52で打込む。
Next, one piece of the
打込み工具52は下半部を筒状とした柱状で、下半部の内径は孔あけ工具51の外径よりも若干大きく、下端(打込み端)522の開口周縁は新規屋根材4の山部にほぼ沿う波形状としてある。また柱部外周には軸対象位置に凹部521が形成してある。
The driving
打込み工具52は、孔あけ工具51により支持された新規屋根材4の支持点まわりに打込み端522を置いて新規屋根材4の山部上に立てられる。この場合、上記凹部521は、新規屋根材4の山部に対する打込み端522の方向性を決める役割を果たす。新規屋根材4の各支持点は母屋の上方で直線状に配列しており、かつ屋根材4は薄く(0.4〜0.5mm程度)、尖った孔あけ工具51の先端で支持されているから作業者が手指で屋根材4を軽く押すことでどの山部に支持点があるかは容易に確認することができる。
The driving
打込み工具52による打込みは、工具52の頭を小型のハンマーで叩くことによりなされる。新規屋根材4は支持点まわりが打込まれることにより、孔あけ工具51により打抜かれて孔あけがなされる。このように各支持点まわりで孔あけされると、図3(B)に示すように新規屋根材4は既設屋根材1の上に落ちて屋根材1に重なり、孔あけと同時に新規屋根材載置工程が完了する。孔あけ工具51は、新規屋根材4に打抜き形成された孔40から突出する既設のフックボルト3の上端から抜取ることで除去される。
Driving with the driving
打抜き形成されたフックボルト挿通用の孔40まわりには、めくれ状にバリ41が発生する。しかしながら、このバリ41は、その後の新規屋根材固定作業に支障をきたすものではない。孔あけ工具51として図2で示したように加工部512の外周に尖条514を形成したものを用いたのは、バリ41を孔40の周方向に細かく分離した状態で発生させるためである。バリ41を分離させることで、形成される孔40の形状が不規則になるのを防ぎ、かつ孔形成に必要な打込み力を小さくすることができる。勿論、本発明の実施に用いる孔かけ工具51は尖条514を形成したものに限定されるものではない。
Around the
図4は、既設屋根材1の上に重ね合された新規屋根材4を固定する工程を示すもので先ず、孔40から突出する既設のフックボルト3の上端まわりにパッキン材6を取付ける。パッキン材6は中心孔を有するドーナツ形で、孔40をカバーする大きさで、厚く柔軟な材料からなり、中心孔にフックボルト3を挿通させ打抜かれた孔40を覆うようにする。
FIG. 4 shows a process of fixing the
次にパッキン材6を覆うように新規屋根材4の山部にカバー部材7を取付ける。カバー部材7は全体がほぼ鞍形で新規屋根材4の山部に合致する断面形状としてあり、頂部中央は突出部71が形成され、突出部71の頂面には本体の山沿い方向にフックボルト挿通用の長孔72が形成してある。このカバー部材7は、長孔72に既設のフックボルト3の上端を挿通させ、パッキン材6を覆うようにしてセットされる。
Next, the
次にカバー部材7の長孔72から突出する既設のフックボルト3の上端を利用してナット部材8によりカバー部材7を上から締付けることにより、カバー部材7を介して新規屋根材4を既設屋根材1に押付け固定する。
Next, by using the upper end of the existing
ナット部材8としては、図5に示すように、多角形、例えば六角形のリング状で、その内周から複数の板ばねの爪81が中心に向け斜め上方に突出する板ばねニットが好適に用いられ得る。板ばねナット8はその中心にフックボルト3の上端を挿入して押込み、爪81がフックボルト3のネジ溝に係合した板ばねナット8をその外周に六角レンチを係合させて締め込む。これによりパッキン材6を圧縮変形させ、パッキン材6を介してカバー部材7が新規屋根材4に押付けられ、新規屋根材4は既設屋根材1に押付けられ固定される。
As the
最後にカバー部材7には、孔72およびそれから突出するフックボルト3り上端を覆うようにキャップ9が被冠せしめられる(図6)。キャップ9は、その周壁から内方へ突出する凸部91をカバー部材7の外周に形成した凹部に嵌合させることでカバー部材7に固定される。
Finally, a
このようにして、新規屋根材4は既設屋根材1の上に順次設置される。新規屋根材4の孔あけは作業現場の既設屋根材1の上で作業性容易になされ、孔40が打抜かれると同時に新規屋根材4は自動的に既設屋根材4の上に置かれるから作業能率が極めて良好である。設置された新規屋根材4は既設屋根材1の上に直接に重ねられ支持されているから、局部的にクランプ金具を介して支持されている従来の補修屋根のような強度を必要とせず板厚を薄くすることができ、また鋼板以外にアルミニウム板や繊維強化プラスチック板を用いることができる。補修屋根は軽量化されるから耐震の面でも有利である。
In this way, the
1 既設屋根材
2 母屋
3 フックボルト
4 新規屋根材
40 フックボルト挿通孔
51 孔あけ工具
513 縦孔
52 打込み工具
522 打込み端
6 パッキン材
7 カバー部材
8 板ばねナット
9 キャップ
DESCRIPTION OF
Claims (4)
新規屋根材の山部に、既設屋根材の山部の上記フックボルト対応位置で、フックボルト挿通孔を形成する孔あけ工程と、
上記フックボルト挿通孔に上記フックボルトの上端を挿通させて新規屋根材を既設屋根材の上に重ね合せ載置する新規屋根材載置工程と、
新規屋根材の上記フックボルト挿通孔の上に、パッキン材を介在せしめてカバー部材を、その上端に形成したフックボルト挿通孔に上記フックボルトの上端を挿通せしめて新規屋根材の山部を跨ぐように設置するカバー部材設置工程と、
上記カバー部材のフックボルト挿通孔から突出する上記フックボルトの上端からナット部材で上記カバー部材を上から締込んで、上記カバー部材を介して新規屋根材を既設屋根材に押付け固定する新規屋根材固定工程と、
上記カバー部材に、そのフックボルト挿通孔および該挿通孔から突出するフックボルトの上端を覆うキャップを取付けるキャップ取付け工程とからなり、
上記孔あけ工程では、母屋の上方位置で既設屋根材の山部から突出して直線状に配列する上記各フックボルトの上端に、先端を錐状とした孔あけ工具を支持せしめ、既設屋根材を覆うようにして位置決めした新規屋根材を上記孔あけ工具の先端に支持せしめ、新規屋根材の支持点まわりに打込み工具を打込んで上記孔あけ工具を新規屋根材に貫通させて孔あけを行ない、孔あけされた新規屋根材の既設屋根材上への落下により上記新規屋根材載置工程を完了せしめる屋根補修工法。 The roof repair method of installing a new roofing material of a corrugated metal plate or corrugated plastic plate covering the existing roofing material of a corrugated slate plate in which the upper end of the hook bolt that fixes the roofing material to the main building protrudes from the mountain part,
A drilling step of forming a hook bolt insertion hole at the position corresponding to the hook bolt of the peak portion of the existing roof material on the peak portion of the new roof material,
A new roof material placing step of placing the new roof material on top of the existing roof material by inserting the upper end of the hook bolt into the hook bolt insertion hole;
Cover the cover member with a packing material above the hook bolt insertion hole of the new roof material, and insert the upper end of the hook bolt into the hook bolt insertion hole formed at the upper end of the cover material to straddle the peak of the new roof material Cover member installation process to install,
A new roof material for fixing the new roof material to the existing roof material through the cover member by tightening the cover member from above with a nut member from the upper end of the hook bolt protruding from the hook bolt insertion hole of the cover member Fixing process;
The cover member comprises a cap mounting step of attaching a cap that covers the hook bolt insertion hole and the upper end of the hook bolt protruding from the insertion hole,
In the drilling step, the upper end of each hook bolt that protrudes from the peak portion of the existing roofing material at a position above the main building and supports the drilling tool whose tip is conical, supports the existing roofing material. The new roofing material positioned so as to be covered is supported on the tip of the drilling tool, the driving tool is driven around the support point of the new roofing material, and the drilling tool is passed through the new roofing material to make a hole. A roof repair method in which the new roof material placement process is completed by dropping the drilled new roof material onto the existing roof material.
In the new roofing material fixing step, as the nut member, a leaf spring nut having a ring shape and a plurality of leaf spring claws projecting in the center direction from an inner periphery thereof is projected from the hook bolt insertion hole of the cover member. 4. The roof repair method according to claim 1, wherein an upper end of the hook halt is passed through a center of the leaf spring nut and is tightened to an upper end of the cover member by the leaf spring nut.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003321062A JP3706377B2 (en) | 2003-09-12 | 2003-09-12 | Roof repair method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003321062A JP3706377B2 (en) | 2003-09-12 | 2003-09-12 | Roof repair method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2005089985A JP2005089985A (en) | 2005-04-07 |
JP3706377B2 true JP3706377B2 (en) | 2005-10-12 |
Family
ID=34452844
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003321062A Expired - Fee Related JP3706377B2 (en) | 2003-09-12 | 2003-09-12 | Roof repair method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3706377B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007046392A (en) * | 2005-08-11 | 2007-02-22 | Nippon Light Metal Co Ltd | Corrugated roof member and method for repairing slate roof |
JP6059955B2 (en) * | 2012-10-31 | 2017-01-11 | 旭化成ホームズ株式会社 | Installation method of solar cell module |
-
2003
- 2003-09-12 JP JP2003321062A patent/JP3706377B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2005089985A (en) | 2005-04-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH09112519A (en) | Assembly of screw and washer | |
US5908278A (en) | Stress plate with depending sleeve | |
JP3706377B2 (en) | Roof repair method | |
JP7123644B2 (en) | Refurbished Enclosure | |
JP3655270B2 (en) | Roof repair method | |
JP6272289B2 (en) | Connection structure between support member and lower folded plate roof, support member used for the same, and holding member for the support member | |
JP3124051U (en) | Saddle for wave slate repair | |
JP2907422B2 (en) | Roof repair method | |
EP0922147B1 (en) | Fastener for corrugated sheeting | |
JP3448256B2 (en) | Roof repair method, roof repair structure and roof repair clamp | |
JP4686020B2 (en) | Roof repair method | |
JP2010047911A (en) | Method for repairing roof | |
JP3708937B2 (en) | New roof mounting tool and new roof mounting method | |
JP5309327B2 (en) | Fixing the outdoor fixture | |
JP2001279876A (en) | Method and structure for repairing roof and clamp for repairing roof used in the same | |
AU694544B2 (en) | Fastener for corrugated sheeting | |
JP2016130441A (en) | Repair method for corrugated slate roof | |
JP2005256374A (en) | Roof repairing construction method | |
KR20100040762A (en) | Anchor bolt | |
JP5309326B2 (en) | Fixing method of outdoor fixed object and fixing tool used for the method | |
JP5859779B2 (en) | Double folded plate roof structure and construction method of double folded plate roof | |
JP3147417U (en) | Roof replacement fitting | |
JP3377373B2 (en) | Renovated roof and its renovation method | |
CN1601124A (en) | Expansion bolt | |
CN116331445A (en) | Ship grid installation method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050707 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050726 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050728 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
LAPS | Cancellation because of no payment of annual fees |