JP3684115B2 - Floor slab construction method - Google Patents
Floor slab construction method Download PDFInfo
- Publication number
- JP3684115B2 JP3684115B2 JP22119399A JP22119399A JP3684115B2 JP 3684115 B2 JP3684115 B2 JP 3684115B2 JP 22119399 A JP22119399 A JP 22119399A JP 22119399 A JP22119399 A JP 22119399A JP 3684115 B2 JP3684115 B2 JP 3684115B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- steel plate
- bottom steel
- floor slab
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、建築や土木の分野で用いられる床版であって、特に橋梁用として好適な床版の施工方法に関するものである。
【0002】
【従来の技術】
一般に、橋梁等における床版は、鋼床版と、合成床版を含む広義のコンクリート類床版とに大別される。このうち、鋼床版は軽量であるが高価であり、よって支間が短い場合にはコンクリート類床版が主として用いられている。特に、鋼材からなる底板の上にコンクリート類を打設してなる合成床版は、完成時に十分な強度と耐久性を有し、また現場作業が少なく工期が短いため、その開発が活発に進められている。
【0003】
従来、このような合成床版としては、次のようなものが知られている。
【0004】
A)平坦もしくは略平坦な底鋼板の上に、補強用及びずれ止め用のCT鋼材や主鉄筋を格子状に溶接し、その上にコンクリート類を打設したもの(例えば特開昭62−21910号公報参照)。
【0005】
B)図17に示すように、底鋼板3の支点間部分(主桁2同士の間の部分)を上に凸のアーチ状とし、その上にコンクリート類4を打設することにより、架設時及び完成時の強度向上を図るようにしたもの(特開昭59−185209号公報参照)。
【0006】
【発明が解決しようとする課題】
上記床版では、コンクリート打設時及び完成後の使用時において、型枠である底鋼板に十分な強度(特に曲げ強度)を確保し、かつ、架設中に不安定な挙動が起こるのを防ぐ必要がある。このため、例えば上記A)の床版では、補強用のCT鋼材等をかなり密な状態で底鋼板上に配置しなければならない。従って、多くの加工工数が必要であり、また、床版全体の軽量化が困難であるという不都合がある。
【0007】
一方、B)の床版では、底鋼板が上に凸のアーチ状をなしているため、次のような不都合が存在する。
【0008】
a)底鋼板の上にコンクリート打設時の荷重や完成後の輪荷重が加えられると、この底鋼板には多大な膜圧縮力が作用する。従って、この膜圧縮力による底鋼板の座屈を防止するために、底鋼板の板厚を大きくしたり、リブを設置したりする必要があり、重量及びコストの増大は免れ得ない。
【0009】
b)アーチ構造は、周知のように偏載荷重(支間の半分の分布荷重や支間1/4点の集中荷重)に弱く、当該偏載荷重を受けると大きく変形するおそれがある。従って、底鋼板の上にはコンクリートを均一に打設する必要があり、施工が難しい。
【0010】
c)コンクリート部分も含めた構造全体についてみても、最大曲げモーメントが発生し易い支間中央部で最も床版厚が小さくなっており、支点部付近の強度設計が過剰になる可能性がある。
【0011】
本発明は、このような事情に鑑み、簡単な構造で、不都合なくコンクリートの打設ができ、また完成後の輪荷重等にも十分に耐えることができる床版の施工方法を提供することを目的とする。
【0012】
【課題を解決するための手段】
上記課題を解決するための手段として、本発明は、型枠を下から支持し、この型枠の上にコンクリート類を打設することにより床版を形成する施工方法であって、上記型枠としてその支点間部分の少なくとも一つが下向きに凸の形状を有するものを用いる方法である。
【0013】
なお、ここでいう「コンクリート類」には、コンクリートの他、これに類するものが含まれ、例えば建築用床版ではモルタル等の使用も可能である。
【0014】
この床版の施工方法によれば、型枠としてその支点間部分が下向きに凸の形状を有するものを用いることにより、その上から荷重が加えられた場合に、型枠の底板に膜引張力を生じさせることができる。そして、この底板の支点間部分と支点部分との落差と、水平方向の膜引張力とによって生じるモーメント分だけ、実際に底板に発生する曲げモーメントを軽減させることができる。従って、底板を薄くし、また補強用リブの使用量を減らしながら、施工時におけるコンクリートの打設による荷重、及び、完成後に加えられる輪荷重等に耐え得る床版を施工することが可能となる。
【0015】
また、床版全体に作用する曲げモーメントに着目すると、当該曲げモーメントは支点間部分の中央部もしくはその近傍で最大となり、この部分で床版表面の曲げ応力も最も厳しくなるが、上記床版の施工方法では、床版下面の型枠として下向きに凸の形状を有するものを用いるため、上記曲げモーメントが最大となる部分において床版自体の厚みひいては断面係数を増大させることになり、その分、曲げに起因する床版下面の引張応力を軽減することができる。従って、この発明にかかる床版の施工方法は、曲げモーメントの分布からみても非常に合理的であるといえる。
【0016】
なお、この施工方法が適用される床版は、コンクリート類を打設した後、上記型枠を撤去してコンクリート床版としてもよいし、そのままコンクリート類と型枠とを一体化して合成床版としてもよい。型枠としては、引張強度に優れた鋼板等が好適である。
【0017】
また、この方法では、コンクリート打設時に型枠に大きな膜引張力が作用し、型枠の支点部分同士が相互接近する方向に変位しようとするため、この変位を規制しながらコンクリート類の打設を行うようにする。
【0018】
具体的には、型枠の上にその支点同士を結ぶ方向に延びる圧縮材を固定し、その上からコンクリート類を打設して上記圧縮材を埋め込むようにする。
【0019】
この方法において、上記圧縮材には例えば鋼材を使用することも可能であるが、その場合には、圧縮材とコンクリート類との異質性が高いため、両者の肌離れに起因して上記圧縮材を起点とするひび割れが圧縮材に沿って発生し、このひび割れによって床版コンクリート類が複数の梁に分割化(はり状化)されるおそれがある。かかるはり状化は、耐久性の低下をもたらし、輪荷重に対して床版が抵抗できなくなる事態も生じ得る。
【0020】
従ってこの方法では、上記圧縮材として、その少なくとも表面がコンクリート類で形成されたものを用いる。このようにすれば、当該圧縮材を埋め込んでも上記肌離れが生じにくく、これに起因するひび割れが防止される。
【0021】
この場合、上記圧縮材としてプレキャスト鉄筋コンクリートを用いれば、施工が簡単であり、しかも十分な強度を確保することができる。
【0022】
【発明の実施の形態】
本発明の第1の実施の形態を図1〜図5に基づいて説明する。
【0023】
図1は、本実施形態の床版の施工方法が適用される床版、及びこれを備えた橋梁の上部構造を示している。図において、左右の主桁(橋桁)10が相互平行な状態で配されている。各主桁10は、図例ではI型断面を有し、その上端部に図2にも示すような略T字状のフランジ部12が形成されている。
【0024】
両フランジ部12上には、型枠を兼ねる薄肉の底鋼板14が支持されている。詳しくは、図2に示すボルト15等を用いて底鋼板14の両端部が両フランジ部12の内側端に剛結されている。
【0025】
この構造の特徴として、底鋼板14は、その支点間部分(図例では中間部分)の断面形状が下向きに凸の曲線状となるように予め成形されている。さらに、両フランジ部12の内側端には、橋軸直角方向(幅方向)に延びる複数本の圧縮材(図例ではH形鋼)20の両端がボルト等で固定されている。この圧縮材20は、後述のコンクリート打設時の荷重等によって両フランジ部12同士が相互接近する方向(すなわち内側方向)に水平変位するのを規制するためのものである。
【0026】
上記両フランジ12の外側端には、平坦な底鋼板16が固定され、その上に補強材(図例ではT形鋼)18が固定されている。各補強材18は上記圧縮材20と一直線状に並んでおり、これら補強材18と圧縮材20の上端部同士が添接板21を介して連結されている。
【0027】
床版の補強及びコンクリートのひび割れ防止のため、補強材18及び圧縮材20の上面には、橋軸方向と平行な方向(長手方向)に延びる鉄筋22が固定されている。また、ずれ止め手段として、底鋼板14,16上には多数のスタッドジベル26が立設されている。そして、その上からコンクリート24が打設され、両底鋼板14,16と一体化されることにより、両主桁10上に合成床版が形成されており、各補強材18、圧縮材20、及び鉄筋22はコンクリート24内に埋め込まれた状態となっている。
【0028】
なお、上記底鋼板14として、図6(a)(b)に示すような縞鋼板、すなわち上面に多数の突起14aが一体に形成された鋼板を用いるようにすれば、簡単な構成で当該底鋼板14とコンクリート24との付着力を高めることができる。その結果、上記スタッドジベル26や補強リブなどのずれ止め線材を設けることなく、もしくはこれらの数を大幅に減らしながら、底鋼板14とコンクリート24とのずれ止めを有効に行うことができ、また高い合成効果を維持することが可能である。また、床版下縁のコンクリート中に配置されるべき引張鉄筋を省略することも可能であり、施工の簡略化にもつながる。この効果は、底板が鋼板以外の材料からなるものであっても、その上面に凹凸を一体的に形成することにより、得ることが可能である。
【0029】
底鋼板16や補強材18、鉄筋22、スタッドジベル26等は、本発明の構成要素となるものではなく、適宜省略が可能である。
【0030】
上記構造は、主桁10上に底鋼板14,16及び圧縮材20等を設置した後、その上にコンクリート24を打設することにより施工することができるが、その打設時、あるいは施工完了後の使用時において、強度的及び経済的に非常に有利なものとなっている。以下、その理由を詳細に説明する。
【0031】
1)底鋼板14に発生する曲げモーメントの低減
コンクリート24の打設時、底鋼板14には図3に示すような分布荷重w(y)が作用する。この荷重により、底鋼板14の両端には、鉛直上向きの支持反力が生ずるとともに、底鋼板14の膜引張力と釣り合う水平力Hが発生する。同様に、底鋼板14の幅方向中央部にも膜引張力と釣り合う水平力Hが作用している。ここで、底鋼板14の両端部分(支点部分)から中央部分までの突出量をfとすると、上記両水平力Hの着力点には鉛直方向にfの落差があるため、これらの水平力Hに起因するモーメントH・fが発生する。このモーメントH・fと、底鋼板14の曲げモーメントMsとの和が、上記分布荷重及び鉛直反力により生じる曲げモーメントMoと釣り合うのであるから、次の式を得ることができる。
【0032】
【数1】
【0033】
つまり、上記の構造によれば、中央部の下向き最大突出量fに起因して底鋼板14の曲げモーメントMsが削減され、しかも、この削減度合いは水平力Hが大きいほど(すなわち荷重が大きいほど)著しくなる。従って、底鋼板14に発生する力としては膜引張力が支配的となり、底鋼板14はその全断面についてほぼ均等に引張られることになる。すなわち、鋼板表面にのみ高い曲げ応力が発生するのを避け、底鋼板14の全断面を有効に使うことができる。従って、薄肉の底鋼板14を用いながら、また、補強材の使用を抑えながらも、コンクリート打設時の荷重さらには完成後の輪荷重にも十分対抗できるのである。
【0034】
さらに、上記図1に示した圧縮材20等を用いて両主桁10のフランジ部12同士が相互接近する方向に変位するのを規制しながらコンクリート24を打設するようにすれば、支持端の水平力Hが主桁10に有害な変形を与えることを確実に防ぐことができる。
【0035】
2)床版全体に作用する曲げモーメントとの関係
完成後の床版に対し、支点間に荷重(例えば輪荷重)が作用したとき、これに起因して床版各部に作用する最大曲げモーメント分布は幅方向中央部で最大となる。一方、上記図1に示した床版は、その下面が下に凸の形状をなしているため、幅方向中央部で床版厚が最大となっている。すなわち、この幅方向中央部で断面係数が最大となっており、その分、床版表面に発生する曲げ応力が抑えられる構造となっている。このように、曲げモーメントが最大となる部分と断面係数が最大となる部分とがほぼ合致しているため、床版に生じる応力を幅方向にわたって均一化することができる。
【0036】
3)従来のアーチ型構造との比較
a)弾性座屈について:上記図17に示したように、支点間部分を上向きに凸の形状としたアーチ型構造の場合、コンクリート打設等による荷重が作用すると、底鋼板には膜圧縮力が働く。従って、この膜圧縮力に起因する底鋼板の弾性座屈を防止するための設計が必要となる。具体的には、底鋼板を厚肉にしたり、リブを増加したりしなければならず、重量及びコストの低減の妨げとなる。特に、構造が長大化して支間が大きくなると、その分底鋼板は座屈しやすくなるため、構造はますます大がかりなものとなってしまう。
【0037】
これに対して上記図1に示す構造では、アーチ型構造とは逆に底鋼板14が下向きに凸の形状をなしており、底鋼板14には膜引張力が作用するため、弾性座屈のおそれがなく、基本的には底鋼板14の引張強度のみを考慮すれば足りる。従って、底鋼板14を厚肉にしたりリブを増強したりする必要がなく、構造の軽量化及び低コスト化が果たせる。
【0038】
b)偏載荷重について:アーチ型構造の場合、図5(a)に示すような偏載荷重(支間中央から外れた位置に作用する荷重)を受けると、その荷重作用点から底鋼板の凸部が離れる方向に移りやすく、最悪の場合には下に凸の状態に飛び移るおそれがある。このような変形は極めて大きなものであり、構造の安定性を著しく阻害するものである。これに対し、同図(b)に示すように下に凸の底鋼板14に偏載荷重が作用した場合、上記とは逆に凸部が当該荷重の作用点に近づく方向に移る傾向があり、大きな変形は生じない。従って、偏載荷重に対しても非常に安定した構造となっている。しかも、その荷重によって両端部(支点部分)との落差が大きくなるほど、底鋼板14の曲げモーメントMsを相殺するモーメント要素(=H・f)が大きくなるのであるから、非常に合理的である。
【0039】
なお、上記凸部分の最大突出量fは適宜設定が可能であるが、この突出量fが大きくなると、底鋼板14の曲げモーメント低減度合いが高まる反面、その膨らみ分だけ打設コンクリート量が増えて床版重量が増加するため、そのバランスを考慮して突出量fを決めることが望ましい。以下、この点について検討を行う。
【0040】
いま、支点間距離をLとし、橋軸直角方向(幅方向)にy軸をとるとともに、当該方向の中央位置のy座標を0に設定する。そして、底鋼板14の形状を下に凸な二次曲線であると仮定すると、コンクリート打設による分布荷重w(y)と支持端鉛直反力とに起因して発生する曲げモーメントM(y)は、次式で表される。
【0041】
【数2】
【0042】
ここで、鉛直下向きにz軸座標をとると、上記分布荷重w(y)は次式で表される。
【0043】
【数3】
【0044】
この(数3)を上記(数2)に代入して積分演算を行うことにより、次式を得ることができる。
【0045】
【数4】
【0046】
この(数4)に基づき、単位荷重法等を用いて水平力Hを求めると、次式が得られる。
【0047】
【数5】
【0048】
ここで、底鋼板14の板厚をtsとすると、I=ts3/12、A=tsであるから、μの値は次式で与えられる。
【0049】
【数6】
【0050】
ここで板厚tsが突出量fに比べて十分小さい場合、μ≒0と置くことができる。これを(数5)に代入して変形すると、次式を得ることができる。
【0051】
【数7】
【0052】
一方、単位長さ当たりの鉄筋コンクリート重量をWは次式によって表される。
【0053】
【数8】
【0054】
この(数8)及び上記(数7)において、通常形態の橋梁用床版ではβ=0.02〜0.05と想定できる。この範囲内でβに適当な値を代入すると、H/ρL2及びW/ρL2はαの関数となる。これを同一のグラフに表したものが図4である。
【0055】
底鋼板の設計は、水平膜引張力Hにより生ずる応力と床版完成後に輪荷重により生ずる応力等との和が許容応力度を超えないようになされるため、水平膜引張力Hが小さいほど、薄い板を使用することができて経済的となる。
【0056】
そこで、図4において水平膜引張力Hに着目すると、当該引張力Hはαが0.02(=1/50)より小さくなると急激に上昇する。従って、αは1/50以上とする(すなわち突出量fを支点間距離Lの1/50以上とする)ことが好ましい。さらに、突出量fを支点間距離Lの1/30以上とすることにより、水平膜引張力Hをほぼ最小限に抑えることが可能になる。
【0057】
一方、コンクリート重量Wに着目すると、当該重量Wはαの上昇に伴ってほぼ線形的に増加するが、水平膜引張力Hの減少する割合が小さくなるα>1/10以上の領域では、底鋼板の板厚を減少させる効果がほとんど上昇しない。従って、床版軽量化の観点からは、αを1/10(=0.1)以下とする(すなわち突出量fを支点間距離Lの1/10以下とする)ことが好ましい。さらに、突出量fを支点間距離Lの1/20以下とすることが、より好ましい。
【0058】
第2の実施の形態を図7及び図8に基づいて説明する。
【0059】
上記第1の実施の形態に示すように、埋め込み用の圧縮材20として鋼材を用いた場合、この鋼材と打設されるコンクリート24との異質性が高いため、両者が比較的肌離れしやすく、これに起因してひび割れが発生するおそれがある。
【0060】
そこで、この実施の形態では、上記圧縮材20としてプレキャスト(予め成形した)鉄筋コンクリートからなるものを用い、上記肌離れに起因するひび割れを防ぐようにしている。
【0061】
この場合の主桁10に対する圧縮材20の位置決め手段としては、例えば、図8に示すように主桁10の上側フランジ部12の上面に突起13を設け、この突起13が嵌入可能な孔28を圧縮材20側に設けるようにすればよい。
【0062】
上記肌離れを防ぐには、圧縮材20の少なくとも表面がコンクリートもしくはこれに類するものであればよく、例えば圧縮材20全体がコンクリートで一体化されたものであってもよい。ただし、上記のようなプレキャスト鉄筋コンクリートを用いれば、施工時の取扱いが容易で、しかも高い強度を確保できる。
【0063】
第3の実施の形態を図9に示す。この実施の形態では、上記図1に示したような直線状の圧縮材20に代え、床版幅方向に延びる圧縮材部分34の両端から下方に脚部32を垂設した変位規制部材30を用いる。そして、その両脚部32の下端を両フランジ部12に固定することにより、両フランジ部12の水平変位を規制する。この状態で圧縮材部分34よりも下方のレベルまでコンクリートを打設し、これを硬化させた後、両脚部32を途中部分で切り離して圧縮材部分34を撤去する。
【0064】
なお、上記変位規制部材30以外の各部構造の詳細は、上記図1に示したものと同等である。
【0065】
この施工方法によれば、圧縮材部分34の撤去により、それまでの水平変位規制力が解除され、打設されたコンクリートには圧縮力が導入され、完成後の輪荷重等に起因する床版下部の引張応力を低減することができる。また、撤去した圧縮材部分34は次の施工に繰り返し使用できるので、圧縮材20を埋め込む方法よりも経済的である。
【0066】
なお、上記脚部32の切離し作業を容易にするには、予め切離し部分で脚部32を分割しておき、この部分をボルト等によって着脱可能に連結しておくようにすればよい。
【0067】
第4の実施の形態を図10に示す。ここでは、コンクリートを打設する前に、引張ワイヤ40の一端を両フランジ部12に連結し、他端をアンカー42を介して橋外部の適所に連結しておく。
【0068】
この方法においても、両フランジ部12が内側に水平変位するのを引張ワイヤ40の張力で規制しながら、底鋼板14上にコンクリートを打設することができる。コンクリートの打設及び硬化後は、フランジ部12から引張ワイヤ40を切り離すことにより、上記変位規制力を解除させ、第3の実施の形態と同様にコンクリートにプレストレスを与えることができる。
【0069】
第5の実施の形態を図12(a)(b)に示す。
【0070】
上記底鋼板14とコンクリート24とのずれ止めを行う手段として、図12(a)(b)に示すように、例えばフラットバーからなる補強リブ40を底鋼板14上に立直状態で固定する方法がよく知られている。この方法を本発明のように底鋼板14が下に凸の曲面状のものに適用するには、当該底鋼板14の断面が直線となる方向(図12(a)では奥行き方向)に沿って上記補強リブ40を平行に配すれば、底鋼板14のもつ膜作用を阻害することなく、これに補強リブ40を固定することができる。
【0071】
ところが、この補強リブ40のみを設けた構造では、その上からコンクリートを打設して補強リブ40を埋め込むと、当該コンクリートに対して各補強リブ40が上向きに鋭く食い込んだ状態となるため、その食い込み部分からひび割れが発生し、かつ、このひび割れが上向きに進行しやすい。このようにしてひび割れが最終的にコンクリート上面にまで到達すると、当該コンクリートはリブ配設位置で分断され、いわゆるはり状化された状態となってしまう。
【0072】
そこで、この実施の形態では、各補強リブ40に図12(b)に示すような貫通孔41を設け、この貫通孔41に例えば鋼製線材からなる細い鉄筋42を通し、下に凸の曲面に沿って配するようにしている。
【0073】
このような構成によれば、底鋼板14の近傍で打設コンクリートが補強リブ40と直交する方向に変位することが上記鉄筋42によって規制されるため、かかる変位に伴う上記ひび割れの進行が最小限に食い止められる。また、鉄筋42は底鋼板14とコンクリートとの肌離れを抑制する手段としても期待できる。
【0074】
しかも、当該鉄筋42に細いものを用いて底鋼板14とともに撓み変形できるようにしておけば、底鋼板14の膜作用を阻害することがなく、本発明の十分な作用効果を得ることが可能である。
【0075】
また、当該鉄筋42は、補強リブ40に設けた貫通孔41に挿通するだけでよいので、施工も容易である。
【0076】
第6の実施の形態を図13(a)(b)に示す。
【0077】
底鋼板14とコンクリート24とのずれ止め手段として、上述のスタッドジベルや補強リブも有効であるが、これらは打設されたコンクリートに対して鋭く食い込んだ状態となるため、ひび割れの集中度が高く、耐久性に大きな影響を及ぼすおそれがある。
【0078】
そこで、この実施の形態では、例えば鉄鋼材料からなる線材を螺旋状にして容易に撓み変形できるようにしたずれ止め線材46を底鋼板14上に配し、その底鋼板14に対して上記ずれ止め線材46の各下端部44のみを局所的に固定(例えば点溶接)するようにしている。これら下端部44は全て固定する必要はなく、特定の下端部44のみを間欠的に固定するようにしてもよい。
【0079】
この構成によれば、次のような効果が得られる。
【0080】
a)上記スタッドジベルや補強リブに比べてひび割れの集中度合いが下げられ(すなわちひび割れが分散化され)、その結果、十分な耐久性が維持される。
【0081】
b)スタッドジベルや補強リブに比べてコンクリートとの接触面積が大きいため、ずれ止め効果や肌離れ抑止効果が高く、また、十分な合成効果を得ることができる。
【0082】
c)ずれ止め線材46が容易に撓み変形するので、鋼板14の膜作用を阻害することがない。
【0083】
d)スタッドジベルや補強リブに比べて溶接面積が少ないので、施工が容易である。
【0084】
なお、上記ずれ止め線材46は必ずしも螺旋状に限られず、撓み変形可能な曲線状をなし、その一部が局所的に底鋼板14に固定されるものであればよい。例えば、図14(a)に示すような波形あるいはジグザグ形のずれ止め線材46の谷部分のみを局所的に底鋼板14上に固定するようにしてもよいし、同図(b)に示すような半円もしくはこれに近似した有端のずれ止め線材46の両端を底鋼板14に固定するようにして、このずれ止め線材46を多数並設するようにしてもよい。
【0085】
ただし、ずれ止め部材46を前記図13に示すような螺旋状とすれば、撓み変形をより容易にできるとともに、コンクリートとの接触面積を効果的に増やしてずれ止め作用をより顕著なものにすることが可能となる。
【0086】
その他、本発明は例として次のような実施形態をとることも可能である。
【0087】
(1) 本発明は、橋梁用床版及びその施工に限らず、その他の土木用床版、あるいは建築用床版及びその施工にも適用が可能である。また、橋桁による支持個所も2か所に限らず、3か所以上に設定してもよい。例えば、第7の実施の形態として図15に示すように、縦横両方向について3か所以上の支点をもつ(すなわち3本以上の橋桁で支持される)床版の場合、各支点間部分17の少なくとも一つを下に凸の形状とすることにより、その部分において上述の作用・効果を得ることができる。
【0088】
この場合、どの支点間部分17を下に凸の形状とするかについては、仕様に応じて適宜設定すればよい。また、このように複数の支点間部分17が存在する場合、支点間部分17ごとに別の底鋼板14を用いる(すなわち支点間部分17に対応して底鋼板14を分割する)ようにしてもよいし、全支点間部分17について共通の底鋼板14を使用する(すなわち単一の底鋼板14を橋桁上に載せる)ようにしてもよい。
【0089】
(2) 上記各実施形態で示した底鋼板14の具体的な形状は特に問わず、支点間部分が下向きに凸である範囲で適宜設定が可能である。例えば、全体を曲面とする他、図16(a)(b)に示すように複数の平面を組み合わせたものであってもよいし、同図(c)(d)に示すように平面と曲面とを組み合わせたものであってもよい。曲面の具体的な断面形状も種々設定が可能であり、二次あるいはそれよりも高次の曲線、円弧、楕円曲線、双曲線、正弦曲線、懸垂線(双曲線正弦関数曲線)、サイクロイド曲線等、その種類を問わない。
【0090】
(3) 上記実施形態では、底鋼板14上に直接コンクリートを打設するようにしているが、床版下部で発生する引張力に対しては、コンクリートはほとんど寄与できないので、予め、当該床版下部に空隙を確保するための箱状部材や管状部材を導入したり、底鋼板14上に軽量の硬質ウレタン等を敷設したりしておき、その上からコンクリートを打設するようにしてもよい。また、床版の用途によっては、コンクリートに代えてモルタル等を使用できることは前述の通りである。
【0091】
(4) 上記実施形態では、底鋼板14と打設コンクリート24とを一体化して合成床版としたものを示したが、コンクリート打設及び硬化後、底鋼板14を撤去してコンクリート床版とするようにしてもよい。すなわち、底鋼板14を型枠としてのみ用いるようにしてもよい。この場合も、底鋼板14を下に凸の形状とすることにより、簡単な構造で、強度的に不都合なくコンクリートの打設ができることはいうまでもない。また、このように型枠を撤去させるか、型枠を残存させて合成床版とするかにかかわらず、当該型枠の材質は鋼板に限られるものではなく、引張力に対抗する膜部材として使用できるものであれば広く適用が可能である。例えば、FRPや木板、高強度繊維で織られた布材等も型枠として用いることができる。
【0092】
【実施例】
上記図1に示した構造において、主桁間隔を8.4m、底鋼板14の板厚tsを8mm、最大突出量fを390mm、圧縮材20の高さ寸法及び幅寸法を200mm、圧縮材20の間隔を1m、支点部分の床版厚tcoを270mmとして施工を行った。この時の主桁フランジ部12の内向き水平方向変位を数値解析で求めた結果が図11である。この図に示されるように、上記方向のフランジ部変位は最大でも約1.4mmであり、コンクリートが打設されても主桁10に有害な影響を与えていないことを確認できた。
【0093】
なお、この影響の回避を特に厳しく求められる場合には、少なくとも一方の主桁10が橋軸直角方向に移動するのを許容するように橋梁を構築する等の手段をとればよい。
【0094】
【発明の効果】
以上のように本発明は、型枠を下から支持し、この型枠の上にコンクリート類を打設することにより床版を形成する施工方法において、上記型枠としてその支点間部分の少なくとも一つが下向きに凸の形状を有するものを用いるものであるので、簡単な構造で、不都合なくコンクリートの打設ができ、また完成後の輪荷重等にも十分に耐えるようにすることができる効果がある。
【図面の簡単な説明】
【図1】 本発明の第1の実施の形態にかかる橋梁の上部構造を示す斜視図である。
【図2】 図1のA部の拡大図である。
【図3】 図1に示される底鋼板上にコンクリートが打設される際に発生する各力を示す説明図である。
【図4】 支点間距離に対する最大突出量の比率αと発生膜水平力H及び必要コンクリート重量Wとの関係を示すグラフである。
【図5】 (a)は上に凸の底鋼板上に荷重が作用する際に生じ得る変形を示す説明図、(b)は下に取付の底鋼板上に荷重が作用する際に生じ得る変形を示す説明図である。
【図6】 (a)は上記底鋼板の一例としての縞鋼板を示す平面図、(b)は(a)のA−A線断面図である。
【図7】 本発明の第2の実施の形態にかかる施工方法を示す斜視図である。
【図8】 図7に示す圧縮材の位置決め構造例を示す斜視図である。
【図9】 本発明の第3の実施の形態にかかる施工方法を示す斜視図である。
【図10】 本発明の第4の実施の形態にかかる施工方法を示す説明図である。
【図11】 本発明の実施例における橋軸直角方向のフランジ部変位の解析結果を示すグラフである。
【図12】 (a)は本発明の第5の実施の形態にかかる施工方法を示す説明図、(b)はその要部を示す斜視図である。
【図13】 (a)は本発明の第6の実施の形態にかかる施工方法を示す説明図、(b)はその施工方法で用いられるずれ止め部材と底鋼板との溶接状態を示す斜視図である。
【図14】 (a)(b)は前記ずれ止め部材の変形例を示す斜視図である。
【図15】 本発明の第7の実施の形態における床版の支持状態を示す模式図である。
【図16】 (a)(b)(c)(d)は型枠形状の変形例を示す説明図である。
【図17】 橋梁用床版の従来例を示す断面斜視図である。
【符号の説明】
10 主桁(橋桁)
14 底鋼板
14a 縞鋼板の突起
17 支点間部分
20 圧縮材
24 コンクリート
30 変位規制部材
34 圧縮材部分
46 ずれ止め部材[0001]
BACKGROUND OF THE INVENTION
The present invention is a floor slab used in the field of architecture and civil engineering, and is particularly suitable for a bridge.EditionIt relates to the construction method.
[0002]
[Prior art]
In general, floor slabs in bridges and the like are roughly classified into steel slabs and broad concrete slabs including synthetic slabs. Of these, steel slabs are lightweight but expensive, and therefore concrete slabs are mainly used when the span is short. In particular, synthetic floor slabs made by placing concrete on the bottom plate made of steel have sufficient strength and durability when completed, and there are few on-site work and a short construction period. It has been.
[0003]
Conventionally, the following are known as such synthetic slabs.
[0004]
A) On a flat or substantially flat bottom steel plate, CT steel materials and main reinforcing bars for reinforcement and slip prevention are welded in a lattice shape, and concrete is placed thereon (for example, JP-A-62-21910) No. publication).
[0005]
B) As shown in FIG. 17, the portion between the fulcrums of the bottom steel plate 3 (the portion between the main girders 2) is formed in an upwardly arched shape, and concrete 4 is placed on the arch, thereby installing And an improvement in strength at the time of completion (see JP-A-59-185209).
[0006]
[Problems to be solved by the invention]
The above-mentioned floor slab ensures sufficient strength (particularly bending strength) for the bottom steel plate, which is the formwork, during concrete placement and use after completion, and prevents unstable behavior from occurring during construction. There is a need. For this reason, for example, in the floor slab of A), it is necessary to arrange the CT steel material for reinforcement on the bottom steel plate in a fairly dense state. Therefore, there are inconveniences that many processing steps are required and it is difficult to reduce the weight of the entire floor slab.
[0007]
On the other hand, the floor slab of B) has the following inconvenience because the bottom steel plate has an upwardly convex arch shape.
[0008]
a)When a load at the time of placing concrete or a ring load after completion is applied on the bottom steel plate, a large film compressive force acts on the bottom steel plate. Therefore, in order to prevent buckling of the bottom steel plate due to this film compressive force, it is necessary to increase the thickness of the bottom steel plate or install ribs, and an increase in weight and cost is inevitable.
[0009]
b)As is well known, the arch structure is vulnerable to an offset load (a distributed load half of the span and a concentrated load of a quarter of the span), and may be greatly deformed when the offset load is received. Therefore, it is necessary to uniformly cast the concrete on the bottom steel plate, and the construction is difficult.
[0010]
c)In the entire structure including the concrete part, the floor slab thickness is the smallest at the center part of the span where the maximum bending moment is likely to occur, and the strength design near the fulcrum part may be excessive.
[0011]
In view of such circumstances, the present invention has a simple structure, a floor on which concrete can be placed without inconvenience, and can sufficiently withstand wheel loads after completion.EditionThe purpose is to provide a construction method.
[0012]
[Means for Solving the Problems]
As means for solving the above problems, the present invention provides:A construction method for forming a floor slab by supporting a formwork from below and placing concrete on the formwork, wherein at least one of the portions between the fulcrums is downwardly convex as the formwork. It is a method using what has.
[0013]
The “concrete” referred to here includes concrete and other similar materials. For example, mortar can be used for building floor slabs.
[0014]
This floor slabAccording to the construction method of theThe part between the fulcrums is belowIn the directionConvex shapeBy using what hasA load is applied from aboveOn the bottom plate of the formworkMembrane tensionCan be generated.Then, the bending moment that is actually generated in the bottom plate by the moment generated by the drop between the fulcrum portion and the fulcrum portion of the bottom plate and the film tension in the horizontal direction.Can be reduced.Therefore, the bottom plate is made thinner and the amount of reinforcing ribs used is reduced, but it can withstand the load caused by concrete placement during construction and the wheel load applied after completion.It is possible to construct an obtainable floor slab.
[0015]
Further, when focusing on the bending moment acting on the entire slab, the bending moment is maximized at or near the center of the portion between the fulcrums, and the bending stress on the floor slab surface is the most severe at this portion.In construction method,Under the floor slabIn order to use what has a convex shape downward as a mold,The part where the bending moment is maximumInThe thickness of the floor slab itself and the section modulusWill increaseAccordingly, the tensile stress on the bottom of the slab caused by bendingCan be reduced.Therefore, the floor slab according to the present inventionThe construction method isIt can be said that the distribution of the bending moment is very reasonable.
[0016]
The floor slab to which this construction method is applied isAfter placing concrete, the above-mentioned formwork may be removed to form a concrete floor slab, or the concrete and formwork may be integrated as they are to form a composite floor slab. As the formwork, steel plates with excellent tensile strength are suitable.The
[0017]
In this method,A large film tensile force acts on the formwork when placing the concrete, and the fulcrum parts of the formwork try to displace in a direction in which they approach each other.To make a placement.
[0018]
Specifically, a compression material extending in the direction connecting the fulcrums is fixed on the mold, and concrete is placed from above to embed the compression material.Like that.
[0019]
In this method, for example, a steel material can be used as the compression material. In this case, the compression material and the concrete are highly heterogeneous. Cracks starting from the cracks occur along the compressed material, and the floor slab concrete may be divided into a plurality of beams due to the cracks. Such beaming causes a decrease in durability and may cause a situation where the floor slab cannot resist the wheel load.
[0020]
Therefore, in this method,Use at least the surface of the compression material made of concrete.The In this way, the compressed materialEven if embedded, the above-mentioned skin separation is unlikely to occur, and cracks due to this are prevented.
[0021]
In this case, if precast reinforced concrete is used as the compression material, construction is simple and sufficient strength can be ensured.
[0022]
DETAILED DESCRIPTION OF THE INVENTION
A first embodiment of the present invention will be described with reference to FIGS.
[0023]
FIG.Floor slab to which the construction method of the floor slab of this embodiment is applied, and thisThe superstructure of the provided bridge is shown. In the figure, left and right main girders (bridge girders) 10 are arranged in parallel to each other. Each
[0024]
A thin
[0025]
As a feature of this structure, the
[0026]
A flat
[0027]
In order to reinforce the floor slab and prevent cracks in the concrete, reinforcing
[0028]
If the
[0029]
The
[0030]
The above structure can be constructed by placing the
[0031]
1) Reduction of bending moment generated in the
When the concrete 24 is placed, a distributed load w (y) as shown in FIG. With this load, a vertically upward support reaction force is generated at both ends of the
[0032]
[Expression 1]
[0033]
That is, according to the above-described structure, the bending moment Ms of the
[0034]
Further, if the concrete 24 is placed while restricting displacement of the
[0035]
2) Relationship with bending moment acting on the whole slab
When a load (for example, a wheel load) is applied between fulcrums on the completed floor slab, the maximum bending moment distribution acting on each part of the floor slab due to this is maximized at the center in the width direction. On the other hand, the floor slab shown in FIG. 1 has a maximum floor slab thickness at the center in the width direction because the bottom surface has a downwardly convex shape. That is, the section modulus is maximized at the central portion in the width direction, and the bending stress generated on the floor slab surface is reduced accordingly. As described above, since the portion where the bending moment is maximized and the portion where the section modulus is maximized are substantially matched, the stress generated in the floor slab can be made uniform in the width direction.
[0036]
3) Comparison with conventional arched structure
a)Regarding elastic buckling: As shown in FIG. 17 above, in the case of an arch type structure in which the portion between the fulcrums is convex upward, when a load due to concrete placement or the like acts, a film compressive force acts on the bottom steel plate. . Therefore, a design for preventing elastic buckling of the bottom steel plate due to the film compressive force is required. Specifically, the bottom steel plate must be thickened or the ribs increased, which hinders weight and cost reduction. In particular, when the structure becomes longer and the span becomes larger, the bottom steel sheet becomes more likely to buckle, so that the structure becomes increasingly large.
[0037]
On the other hand, in the structure shown in FIG. 1, the
[0038]
b)About the uneven load: In the case of the arch type structure, when receiving an uneven load (load acting at a position deviating from the center of the span) as shown in FIG. It is easy to move away, and in the worst case, it may jump down. Such deformation is extremely large and significantly impedes structural stability. On the other hand, when an uneven load is applied to the bottom
[0039]
The maximum protruding amount f of the convex portion can be set as appropriate. However, when the protruding amount f increases, the bending moment reduction degree of the
[0040]
Now, the distance between the fulcrums is set to L, the y axis is taken in the direction perpendicular to the bridge axis (width direction), and the y coordinate of the center position in the direction is set to 0. Assuming that the shape of the
[0041]
[Expression 2]
[0042]
If the z-axis coordinate is taken vertically downward, the distributed load w (y) is expressed by the following equation.
[0043]
[Equation 3]
[0044]
By substituting this (Equation 3) into the above (Equation 2) and performing an integral operation, the following equation can be obtained.
[0045]
[Expression 4]
[0046]
When the horizontal force H is obtained using the unit load method or the like based on (Equation 4), the following equation is obtained.
[0047]
[Equation 5]
[0048]
Here, the thickness of the
[0049]
[Formula 6]
[0050]
Where plate thickness tsIs sufficiently smaller than the protrusion amount f, μ≈0 can be set. Substituting this into (Equation 5) and transforming it gives the following equation.
[0051]
[Expression 7]
[0052]
On the other hand, the reinforced concrete weight per unit length is expressed by the following equation.
[0053]
[Equation 8]
[0054]
In this (Equation 8) and the above (Equation 7), it can be assumed that β = 0.02 to 0.05 in the bridge slab of the normal form. By substituting an appropriate value for β within this range, H / ρL2 and W / ρL2 become functions of α. This is shown in the same graph in FIG.
[0055]
The design of the bottom steel plate is such that the sum of the stress caused by the horizontal membrane tensile force H and the stress caused by the wheel load after completion of the floor slab does not exceed the allowable stress level. A thin plate can be used, which is economical.
[0056]
Therefore, focusing on the horizontal membrane tensile force H in FIG. 4, the tensile force H increases rapidly when α is smaller than 0.02 (= 1/50). Therefore, α is preferably 1/50 or more (that is, the protrusion amount f is 1/50 or more of the fulcrum distance L). Furthermore, by setting the protrusion amount f to 1/30 or more of the fulcrum distance L, the horizontal membrane tensile force H can be suppressed to a minimum.
[0057]
On the other hand, when paying attention to the concrete weight W, the weight W increases almost linearly as α increases, but in the region where α> 1/10 or more where the decreasing rate of the horizontal membrane tensile force H decreases, The effect of reducing the thickness of the steel sheet hardly increases. Therefore, from the viewpoint of weight reduction of the floor slab, α is preferably 1/10 (= 0.1) or less (that is, the protrusion amount f is 1/10 or less of the distance L between the fulcrums). Furthermore, it is more preferable that the protruding amount f is 1/20 or less of the fulcrum distance L.
[0058]
A second embodiment will be described with reference to FIGS.
[0059]
As shown in the first embodiment, when a steel material is used as the
[0060]
Therefore, in this embodiment, a material made of precast (pre-formed) reinforced concrete is used as the
[0061]
As a means for positioning the
[0062]
In order to prevent the separation of the skin, it is sufficient that at least the surface of the
[0063]
A third embodiment is shown in FIG. In this embodiment, instead of the
[0064]
The details of the structure of each part other than the
[0065]
According to this construction method, by removing the
[0066]
In order to facilitate the work of separating the
[0067]
A fourth embodiment is shown in FIG. Here, before placing the concrete, one end of the
[0068]
Also in this method, it is possible to place concrete on the
[0069]
A fifth embodiment is shown in FIGS. 12 (a) and 12 (b).
[0070]
As a means for preventing the
[0071]
However, in the structure where only the reinforcing
[0072]
Therefore, in this embodiment, each reinforcing
[0073]
According to such a configuration, displacement of the cast concrete in the direction perpendicular to the reinforcing
[0074]
In addition, if the
[0075]
Further, since the reinforcing
[0076]
A sixth embodiment is shown in FIGS. 13 (a) and 13 (b).
[0077]
As the means for preventing the
[0078]
Therefore, in this embodiment, for example, a
[0079]
According to this configuration, the following effects can be obtained.
[0080]
a)Compared with the stud gibber and the reinforcing rib, the concentration of cracks is lowered (that is, cracks are dispersed), and as a result, sufficient durability is maintained.
[0081]
b)Since the contact area with the concrete is larger than that of the stud gibber and the reinforcing rib, the effect of preventing slippage and the effect of preventing skin separation are high, and a sufficient composite effect can be obtained.
[0082]
c)Since the
[0083]
d)Construction is easy because the welding area is small compared to stud gibbles and reinforcing ribs.
[0084]
Note that the above-described
[0085]
However, if the
[0086]
In addition, this invention can also take the following embodiment as an example.
[0087]
(1) The present invention is not limited to a bridge slab and its construction, but can also be applied to other civil engineering slabs or a building floor slab and its construction. Also, the number of support points by the bridge girder is not limited to two, and may be set to three or more. For example, as shown in FIG. 15 as the seventh embodiment, in the case of a floor slab having three or more fulcrums in both vertical and horizontal directions (that is, supported by three or more bridge girders), By making at least one convex downward, the above-mentioned actions and effects can be obtained at that portion.
[0088]
In this case, which
[0089]
(2) The specific shape of the
[0090]
(3) In the above embodiment, concrete is directly placed on the
[0091]
(4) In the above embodiment, the
[0092]
【Example】
In the structure shown in FIG. 1, the main girder interval is 8.4 m, and the thickness t of the bottom steel plate 14.s8mm, maximum protrusion f is 390mm, the height and width of the
[0093]
If it is particularly strictly necessary to avoid this influence, a measure such as building a bridge so as to allow at least one
[0094]
【The invention's effect】
As described above, the present inventionIs the typeIn a construction method for forming a floor slab by supporting a frame from below and placing concrete on the mold, at least one of the fulcrum portions has a downwardly convex shape as the mold Therefore, there is an effect that the concrete can be placed without any inconvenience with a simple structure and that it can sufficiently withstand the wheel load after completion.
[Brief description of the drawings]
FIG. 1 is a perspective view showing an upper structure of a bridge according to a first embodiment of the present invention.
FIG. 2 is an enlarged view of part A in FIG.
FIG. 3 is an explanatory diagram showing each force generated when concrete is placed on the bottom steel plate shown in FIG. 1;
FIG. 4 is a graph showing the relationship between the ratio α of the maximum protrusion amount with respect to the distance between fulcrums, the generated membrane horizontal force H, and the necessary concrete weight W.
5A is an explanatory diagram showing deformation that can occur when a load acts on an upwardly convex bottom steel plate, and FIG. 5B can occur when a load acts on a bottom steel plate that is mounted downward. It is explanatory drawing which shows a deformation | transformation.
6A is a plan view showing a striped steel plate as an example of the bottom steel plate, and FIG. 6B is a cross-sectional view taken along line AA in FIG.
FIG. 7 is a perspective view showing a construction method according to a second embodiment of the present invention.
FIG. 8 is a perspective view showing an example of a positioning structure of the compressed material shown in FIG.
FIG. 9 is a perspective view showing a construction method according to a third embodiment of the present invention.
FIG. 10 is an explanatory diagram showing a construction method according to a fourth embodiment of the present invention.
FIG. 11 is a graph showing an analysis result of flange portion displacement in a direction perpendicular to the bridge axis in the example of the present invention.
12A is an explanatory view showing a construction method according to a fifth embodiment of the present invention, and FIG. 12B is a perspective view showing an essential part thereof.
FIG. 13A is an explanatory view showing a construction method according to a sixth embodiment of the present invention, and FIG. 13B is a perspective view showing a welded state between a detent member used in the construction method and a bottom steel plate. It is.
14 (a) and 14 (b) are perspective views showing a modification of the slip prevention member.
FIG. 15 is a schematic diagram showing a support state of a floor slab in a seventh embodiment of the present invention.
FIGS. 16A, 16B, 16C, and 16D are explanatory views showing a modified form of the formwork.
FIG. 17 is a cross-sectional perspective view showing a conventional example of a bridge slab.
[Explanation of symbols]
10 Main girder (bridge girder)
14 Bottom steel plate
14a Protrusion of striped steel plate
17 Between fulcrums
20 Compressed material
24 concrete
30 Displacement restricting member
34 Compressed material
46 Anti-slip member
Claims (2)
上記型枠としてその支点間部分の少なくとも一つが下向きに凸の形状を有するものを用いるとともに、While using at least one of the parts between the fulcrum as the mold has a downwardly convex shape,
上記型枠の支点部分同士を結ぶ方向に延びる圧縮材であって少なくともその表面がコンクリート類で形成された圧縮材を上記型枠の上に固定し、その上からコンクリート類を打設して上記圧縮材を埋め込むことにより、上記型枠の支点部分同士が相互接近する方向に変位するのを規制しながらコンクリート類を打設することを特徴とする床版の施工方法。A compression material that extends in a direction connecting the fulcrum portions of the mold, and at least the surface of the compression material is formed of concrete, and is fixed on the mold, and concrete is placed on the compression material. A method for constructing a floor slab, wherein concrete is placed while embedding a compression material while restricting displacement of fulcrum portions of the above-mentioned formwork toward each other.
上記圧縮材としてプレキャスト鉄筋コンクリートを用いることを特徴とする床版の施工方法。A floor slab construction method characterized by using precast reinforced concrete as the compression material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22119399A JP3684115B2 (en) | 1998-08-06 | 1999-08-04 | Floor slab construction method |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22291798 | 1998-08-06 | ||
JP10-222917 | 1998-08-06 | ||
JP22119399A JP3684115B2 (en) | 1998-08-06 | 1999-08-04 | Floor slab construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2000110117A JP2000110117A (en) | 2000-04-18 |
JP3684115B2 true JP3684115B2 (en) | 2005-08-17 |
Family
ID=26524146
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP22119399A Expired - Fee Related JP3684115B2 (en) | 1998-08-06 | 1999-08-04 | Floor slab construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3684115B2 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107201726B (en) * | 2017-06-08 | 2018-12-04 | 宁波市交通规划设计研究院有限公司 | The all welded steel structured bridge of section assembling eliminates the construction method of residual stress |
CN111197283A (en) * | 2020-02-19 | 2020-05-26 | 中交路桥建设有限公司 | Steel-concrete hollow bridge deck, prefabricated structure and construction method thereof |
CN114427194A (en) * | 2022-03-21 | 2022-05-03 | 菏泽市公路规划设计院 | Toughness steel mixes bridge floor |
-
1999
- 1999-08-04 JP JP22119399A patent/JP3684115B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2000110117A (en) | 2000-04-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0823954B1 (en) | Improvements in or relating to reinforced concrete structural elements | |
JP5020163B2 (en) | Support for overhanging slab | |
KR100693872B1 (en) | Connection structure and construction method for steel and concrete composite deck with a blocked out | |
US20030093961A1 (en) | Composite structural member with longitudinal structural haunch | |
JP5184836B2 (en) | Construction method of synthetic steel slab girder bridge | |
US20050210793A1 (en) | Load supporting structure | |
KR100635137B1 (en) | Bridge slab construction method and lattice bar deck-shaped precast concrete plate applied therein | |
JP3684115B2 (en) | Floor slab construction method | |
KR100984249B1 (en) | Bridge construction method using strength connector detail and composite curing pannel | |
WO1998038386A1 (en) | Pre-cast concrete decking for load supporting structures | |
JP3877995B2 (en) | How to build a string string bridge | |
JP2967874B1 (en) | How to build an overhead suspension bridge | |
KR100592196B1 (en) | large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket and its installation method | |
KR102104291B1 (en) | Repair and strengthening system of bridge superstructure | |
KR101105404B1 (en) | Deck plate system using cap plate | |
KR102487850B1 (en) | Cantilever precast half-deck including integral support and cantilever structure construction method using same | |
KR100989153B1 (en) | Psc girder connection structure with strength connector detail for substitution of rebar placement in deck and bridge construction method using the same | |
EP1416101A1 (en) | Composite beam | |
KR20100002502A (en) | Prestessed composite beam having profiled steel web | |
JP4293696B2 (en) | Construction method of composite floor slab bridge | |
KR20150033221A (en) | Prestressed Concrete Girder | |
KR101819326B1 (en) | Steel-concrete composite girder and construction method | |
KR102452624B1 (en) | Prestressed concrete girder with prestress introduced by h-beam and steel plate | |
JP3839648B2 (en) | Composite floor slab and steel bridge | |
CN220433380U (en) | Post-tensioned prestressing T-shaped beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20041115 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050111 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050314 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050524 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050527 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080603 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090603 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100603 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100603 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110603 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120603 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130603 Year of fee payment: 8 |
|
LAPS | Cancellation because of no payment of annual fees |