JP3653483B2 - Structure of basement and construction method - Google Patents
Structure of basement and construction method Download PDFInfo
- Publication number
- JP3653483B2 JP3653483B2 JP2001209432A JP2001209432A JP3653483B2 JP 3653483 B2 JP3653483 B2 JP 3653483B2 JP 2001209432 A JP2001209432 A JP 2001209432A JP 2001209432 A JP2001209432 A JP 2001209432A JP 3653483 B2 JP3653483 B2 JP 3653483B2
- Authority
- JP
- Japan
- Prior art keywords
- basement
- floor
- underground wall
- wall
- slab
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【0001】
【発明の属する技術分野】
本発明はプレハブ住宅の地下部位に構築される地下室或いは地下車庫等の構造地下室の構造と施工方法に関し、特に、耐圧スラブに連続した地下壁の上部に連続して1階スラブ,梁及び1階基礎立上り部を設けた構造と、施工方法に関するものである。
【0002】
【従来の技術】
プレハブ住宅は工業化された生産システムによって製造された多数の部材を利用して建築される低層建築物であり、居住性や耐久性の向上、長寿命化に伴う間取りの自由度の向上、これらを実現するための合理的な建築構造の追求、コストの低減等を主眼として開発されている。
【0003】
最近では、地下部位を活用するために鉄筋コンクリート構造(RC)の地下室や地下車庫等の構造地下室を設けたプレハブ住宅の需要も増加している。プレハブ住宅の地下部位に構造地下室を構築する場合、地盤を掘削する際の費用や構造地下室を構築した後の埋め戻しに要する費用が大きいという問題がある。
【0004】
このため、プレハブ住宅の地下部位に地下室を構築する場合、土砂の掘削量を少なくして掘削費用や埋め戻し費用を軽減するために、地下室の地盤面からの深さが小さくなるように設定するのが一般的である。この場合、地下室の天井スラブとプレハブ住宅の1階の床までの距離を小さくすることが可能であり、該天井スラブに1階基礎立上り部を形成してプレハブ住宅の基礎とすることが出来る。
【0005】
またプレハブ住宅の地下部位に地下車庫を構築する場合、該地下車庫の基準レベルとしては道路面が設定される。このため、必ずしも地下車庫とプレハブ住宅との接続関係が前述した地下室とプレハブ住宅との関係と一致するものではない。しかし、道路面を基準として地下車庫を設置すると共に、該地下車庫の天井スラブを1階スラブとしてプレハブ住宅を構築することもあり、この場合、前述した地下室とプレハブ住宅との関係と同様となる。
【0006】
本件出願人は、地下室と該地下室の上部構造物の基礎を一体化させる施工方法を開発して既に特許出願している(特開平8-113951号公報)。この技術は、予め地上で地下室に対応する型枠や配筋をした地下室ユニットを構成しておき、この地下室ユニットを所定の位置に設置した後、地下室の天井スラブに対応する部位に対して配筋し、更に、天井スラブに於ける基礎に対応する部位に配筋すると共に受け金具を配置して該受け金具に型枠を設置し、その後、地下室ユニットの型枠及び基礎の型枠内にコンクリートを打設することで、地下室と基礎を一体化して構成し得るようにしたものである。この地下室と一体基礎の施工方法では、基礎が天井スラブの上部で且つ内側平面(地下室の壁部から離隔した位置)に形成されている場合を対象としている。
【0007】
【発明が解決しようとする課題】
地下室或いは地下車庫等の構造地下室の上部にプレハブ住宅を建築する場合、1階基礎立上り部は必ずしも天井スラブの上部で且つ内側片面に形成されるものではなく、地下壁の上部に形成される場合もある。このように、地下壁の上部に1階基礎立上り部が形成される場合には、上記公報に開示された技術では対応し得ないという問題がある。
【0008】
本発明の目的は、プレハブ住宅の地下部位に構造地下室を構築するに際し、構造地下室の地下壁の上部に1階基礎立上り部を形成した構造地下室の構造と、施工方法を提供することにある。
【0009】
【課題を解決するための手段】
上記課題を解決するために本発明に係る構造地下室の構造は、プレハブ住宅の地下部位に構築される構造地下室の構造であって、プレハブ住宅の荷重を耐圧スラブに伝達する地下壁と、プレハブ住宅の荷重を地下壁に伝達する梁と、を有し、鉄筋が地下壁の上部から該地下壁の上部に形成された1階基礎立上り部に跨がって配筋され及び鉄筋が梁の上部から該梁の上部に形成された1階基礎立上り部に跨がって配筋され、または鉄筋が地下壁の上部から該地下壁の上部に形成された1階基礎立上り部に跨がって配筋され及び1階スラブ上面に突出した梁が1階基礎立上り部を兼ねて構成され、前記各1階基礎立上り部にアンカーボルトが配置され、且つ地下壁から1階スラブ,梁及び1階基礎立上り部までが連続して打設されたコンクリートによって構成されたものである。
【0010】
上記構造地下室の構造では、プレハブ住宅の荷重を耐圧スラブに伝達する地下壁と、プレハブ住宅の荷重を地下壁に伝達する梁を有しており、地下壁から該地下壁の上部に形成された1階基礎立上り部及び梁の上部から該梁の上部に形成される1階基礎立上り部に跨がる鉄筋が配筋され、または鉄筋が地下壁から該地下壁の上部に形成された1階基礎立上り部に配筋され及び1階スラブ上面に突出した梁が1階基礎立上りを兼ねて構成され、各1階立上り部にアンカーボルトが配置され、且つ地下壁,1階スラブ(構造地下室の天井スラブ),梁,1階基礎立上り部が連続して打設されたコンクリートによって一体化されるため、信頼性の高い基礎立上り部を構成することが出来、且つ住宅の荷重を梁,地下壁を介して耐圧スラブに伝達することが出来る。
【0011】
特に、地下壁,梁の上部に、該地下壁,梁に連続させた1階基礎立上り部を構成することによって、これらの1階基礎立上り部に埋設されたアンカーボルトは地下壁,梁及び1階基礎立上り部のコンクリートが一体化しているのに伴って、高い引抜き強度を確保することが出来る。
【0012】
また構造地下室の施工方法は、プレハブ住宅の地下部位に構築される構造地下室の施工方法であって、プレハブ住宅の荷重が梁及び地下壁を介して伝達される耐圧スラブを構築した後、構造地下室の地下壁と1階スラブ及び梁に対応する部位の配筋と型枠を施工し、且つ地下壁の上部から該地下壁の上部に形成される1階基礎立上り部に跨がって該1階基礎立上り部の配筋を行うと共に梁の上部から該梁の上部に形成される1階基礎立上り部に跨がって該1階基礎立上り部の配筋し、または地下壁の上部から該地下壁の上部に形成される1階基礎立上り部に跨がって該1階基礎立上り部の配筋を行うと共に1階スラブ上面に突出した梁が1階基礎立上り部を兼ねて構成し、前記各1階基礎立上り部にアンカーボルトを配置し、1階基礎立上り部に沿って該1階基礎立上り部の型枠を配置すると共に該型枠の下端が1階スラブの上面に対応する高さになるように保持し、その後、地下壁から1階スラブ,梁及び1階基礎立上り部まで連続してコンクリートを打設することを特徴とするものである。
【0013】
上記構造地下室の施工方法では、プレハブ住宅の荷重が梁,地下壁を介して伝達される耐圧スラブを構築した後、地下室を構成する地下壁と該地下壁の上部に構成される1階スラブ及び梁に配筋すると共に型枠を施工し、且つ地下壁の上部から該地下壁の上部に形成される1階基礎立上り部までに跨がって且つ梁の上部から該梁の上部に形成される1階基礎立上り部までに跨がって配筋し、または1階スラブの上面に突出した梁が1階基礎立上り部を兼ねて構成される場合は該梁の配筋し、且つ各1階立上り部にアンカーボルトを配置した後、型枠を施工してコンクリートを打設することで、一度のコンクリート打設によって、連続した地下壁と1階スラブ,梁及び1階基礎立上り部を構築することが出来る。
【0014】
【発明の実施の形態】
以下、上記構造地下室の構造の好ましい実施形態について図を用いて説明し、合わせて施工方法について説明する。図1はドライエリアを設けた地下室の構成を説明する断面図である。図2は地下車庫の構成を説明する断面図である。図3は図1の地下室を構築する際の型枠を説明する図である。図4は地下壁の上部に構成される立上り部の型枠を受ける受け金具を説明する図である。図5は地下壁と立上り部の外周面が同一面となる例を説明する図である。
【0015】
本発明に係る構造地下室の構造は、地下室や地下車庫等の構造地下室を構成する地下壁と、該地下壁の上部に配置された1階基礎立上り部(以下単に「立上り部」という)とが、両者に跨がって配筋された鉄筋である立上り鉄筋により接続されると共に連続したコンクリートによって一体的に構成されたものである。このため、立上り部に埋設されたアンカーボルトの高い引抜強度を確保することが可能であり、該アンカーボルトに上部構造物の躯体を構成する柱を接続する場合であっても、鉛直方向の力及び水平方向の力に対し安定した強度を発揮することが可能である。
【0016】
以下、図により具体的に説明する。図1は、構造地下室としての地下室Aを示しており、図2は地下車庫Bを示している。前記地下室A,地下車庫Bには、居室や倉庫となり或いは自動車の収容部となる内部空間Cが設けられており、該空間Cの一方側に面して地上に開放されたドライエリア或いは道路等の外部空間Dが配置されている。そして内部空間Cと外部空間Dとの間は、窓やシャッター等からなる開口部Eが構成されている。
【0017】
図1に於いて、地下室Aは、地面に接地してフーチングとしての機能を有し上部に構築した図示しないプレハブ住宅の荷重や地下室Aの荷重が均等に作用する耐圧スラブ1と、天井に対応して形成され上面に立上り部5〜7が設けられた1階スラブ2と、地下室Aの壁面を構成しプレハブ住宅の荷重を耐圧スラブ1に伝達すると共に土圧に対抗する地下壁3と、プレハブ住宅の荷重を支持すると共に地下壁3に伝達する梁4とを有して構成されている。
【0018】
耐圧スラブ1から地下壁3にかけて鉄筋8が配筋されており、厚さの異なる部位はレベルの異なる部位に形成される傾斜部には該傾斜に沿って鉄筋8が延長されている。この耐圧スラブ1に対応する鉄筋8は、地下室Aの他の部位に先立って配筋されると共にコンクリート10が打設される。即ち、地下室Aを構築するに際し、耐圧スラブ1は最初に構築される。そして、耐圧スラブ1が荷重を負担し得る強度に達したとき、1階スラブ2,梁4,地下壁3及び立上り部5〜7が構築される。
【0019】
地下壁3から1階スラブ2にかけて鉄筋8が配筋されており、地下壁3の上部で且つ1階スラブ2との接続部位では、地下壁3,1階スラブ2に配筋された鉄筋8の端部がL字型に折り曲げられて夫々他方側に延長されて配筋されている。耐圧スラブ1に配筋された鉄筋8と、1階スラブ2,地下壁3に配筋された鉄筋8は、夫々の配置部位に於けるコンクリート10と共に、該部位に設定された許容曲げモーメント及び剪断応力を満足し得る太さを有する。従って、各部位に配筋された鉄筋8が異なる太さを有するか、同一の太さを有するかを限定するものではない。
【0020】
1階スラブ2の上面に設けられる立上り部5は、プレハブ住宅に於ける1階の床のみを受けることを目的とする基礎であり、大きな荷重が作用するものではない。このため、立上り部5には、一端が1階スラブ2に差し込まれた鉄筋11が配筋されている。
【0021】
立上り部6はプレハブ住宅の躯体を構成する図示しない梁や柱を取り付ける機能を有するものであり、1階スラブ2に設けた梁4の上部に形成されている。本実施例では、梁4は1階スラブ2を含んで該1階スラブ2の下面側に形成されており、立上り部6は1階スラブ2の上面側に形成されている。前述したように、梁4はプレハブ住宅に作用する鉛直方向の荷重や水平方向の荷重を支持すると共に地下室Aの地下壁3に伝達する機能を有する。また梁4には枠状の鉄筋12が配置されており、この鉄筋12によって鉄筋8の強度を補強している。また立上り部6の鉄筋13は該立上り部6から梁4にまたがって配筋されており、該鉄筋13に沿って予め設定された部位にはアンカーボルト14が配置されている。
【0022】
立上り部7は地下壁3の上部で且つ1階スラブ2の上面側に設けられている。この立上り部7の機能は特に限定するものではなく、立上り部5と同様にプレハブ住宅に於ける1階の床のみを受ける機能を有するものであって良く、また立上り部6と同様にプレハブ住宅の躯体を構成する梁や柱を取り付けて荷重を支持する機能を有するものであっても良い。しかし、地下壁3が鉛直方向の荷重や水平方向の荷重を支持する機能を有し、立上り部7が地下壁3の上部に設けられることから、該立上り部7をプレハブ住宅の躯体を支持し得るように構成することが好ましい。
【0023】
本実施例では、立上り部7はプレハブ住宅の躯体を取り付けて該躯体から伝えられる鉛直荷重及び水平荷重を支持し得るように構成されている。
【0024】
立上り部7と地下壁3にまたがって鉄筋15が配筋されている。この鉄筋15は、下端側が地下壁3の上端側に設けた鉄筋8及び1階スラブ2から地下壁3の上端部分にかけて配筋された鉄筋8の折曲部の地下壁3側の部分に並行に配置され、上端側が立上り部7の上端側に到達するように配筋され、鉄筋8に所定の手段で固定されている。従って、鉄筋15は地下壁3の上端部分から立上り部7にかけて配筋されている。
【0025】
また立上り部7の予め設定された位置には、プレハブ住宅の躯体を地下室Aに取り付けるためのアンカーボルト14が配置されている。アンカーボルト14は、立上り部7に配筋された鉄筋15の高さ方向と並行して、下端側が地下壁3の上端側に到達し且つ上端側が立上り部7から所定長さ突出するように配置されて所定の手段で固定されている。
【0026】
立上り部7の厚さは地下壁3の厚さよりも小さい。本発明に於いて、地下壁3の厚さ方向の中心(以下単に「中心」という)と、地下壁3の上部に設けた立上り部7の中心が一致することを限定するものではない。本実施例では、図1に示すように、立上り部7は、内周側の面7aが地下壁3の内周側の面3aと同一平面になるように配置されており、従って、両者の中心は一致することなく内周側に偏心している。しかし、立上り部7の中心と地下壁3の中心とが一致していても良いことは当然である。
【0027】
例えば、立上り部7の中心と地下壁3の中心とが一致している場合、地下壁3の上端部分に配置された水平方向の鉄筋8の数によっては、該鉄筋8とアンカーボルト14が互いに干渉して配筋位置や配筋方法を特別に考慮する必要が生じるが、立上り部7が地下壁3に対し内周側或いは外周側の何れかに偏心した場合、前記鉄筋8の数の如何に関わらず干渉することがない。このため、鉄筋15及びアンカーボルト14を配筋する際に作業性が向上し、且つコンクリートを打設したときに該コンクリートの充填度(まわりこみ)を向上させることが可能である。
【0028】
上記地下壁3,1階スラブ2,梁4,立上り部5〜7は連続して打設されたコンクリート16によって実質的に一体化されている。即ち、地下室Aでは、第1段階で耐圧スラブ1が形成され、その後、第2段階で地下壁3,1階スラブ2,梁4,立上り部5〜7が形成される。従って、地下壁3と1階スラブ2との間、1階スラブ2と立上り部5〜7の間のコンクリート16に不連続な境界が形成されることがない。
【0029】
上記の如く、地下壁3と1階スラブ2,立上り部7が連続的に一体化したコンクリート16によって構成されるため、地下壁3から立上り7にまたがって配筋した鉄筋15及びアンカーボルト14に対するコンクリート16の付着長さは、これらのコンクリート16に対する埋設長と等しくなり、高い引抜き強度を確保すると共に高い信頼性を発揮することが可能となる。このため、鉄筋15,アンカーボルト14の信頼性を向上させることが可能であり、これらの鉄筋15,アンカーボルト14の長さを従来の工法で施工した場合と比較して短くすることが可能となる。
【0030】
図2(a),(b)は構造地下室としての地下車庫Bの構成を説明する断面図である。尚、図に於いて前述の地下室Aと同一部分及び同一の機能を有する部分には同一の符号を付して説明を省略してある。
【0031】
同図(a)の地下車庫Bの構造は、前述した地下室Aと実質的に同一である。即ち、本実施例では、1階スラブ2の上面に2つの立上り部5と、梁4の上部に対応した立上り部6とが形成されており、地下壁3の上部には、該地下壁3から立上り部7にまがって配筋された鉄筋15ヲ有する立上り部7が形成されている。このように、夫々の立上り部5〜7の構造は前述した地下室Aに於ける立上り部5〜7と同一である。
【0032】
同図(b)の地下車庫Bは、1階スラブ2に設けた梁4が、該1階スラブ2の上面側に突出して形成されている。このため、プレハブ住宅の躯体を取り付ける立上り部6は特別に形成されることなく、前記梁4と兼ねて構成されている。この実施例であっても、立上り部7は地下壁3の上部にまたがる鉄筋15を配筋して構成されており、地下室Aの構造と変わることはない。
【0033】
次に、本発明に係る施工方法について、地下室Aを構築する場合について図3,図4によって説明する。
【0034】
前述したように、地下室Aを構築する場合、地盤を掘削した後、第1段階で耐圧スラブ1が構築され、その後、他の部位が構築される。即ち、耐圧スラブ1に対する鉄筋8の配筋を行なった後、コンクリート10を打設し、打設されたコンクリート10が硬化して1階スラブ2を構築する型枠を支持し得る硬度を発揮したとき、他の部位を構築する。
【0035】
耐圧スラブ1に配筋された鉄筋8に地下壁3の鉄筋8が接続されると共に、予め設定された地下壁3の配筋が行なわれる。地下壁3に対応する鉄筋8の配筋作業が終了すると、地下壁3の内周に沿って内型枠21が配置される。また内型枠21の上部には1階スラブ2の内型枠22及び梁4の内型枠23が配置され、これらの内型枠21〜23は夫々公知の手段で支持される。
【0036】
内型枠22,23の上部に、1階スラブ2に配置される鉄筋8、梁4に配置される鉄筋12,8が配筋され、更に、立上り部5に対応する位置に該立上り部5に配置される鉄筋11が、立上り部6に対応する位置に該立上り部6に配置される鉄筋13が配筋され、且つ鉄筋13に沿って予め設定された位置にアンカーボルト14が配筋される。
【0037】
また地下壁3の上端部分に対応する位置には、1階スラブ2に配筋された鉄筋8の端部でL字状に形成された部分が配置されると共に、該L字部分が地下壁3の鉄筋8に接続される。同様に地下壁3に配筋された鉄筋8の端部でL字状に形成された部分が1階スラブ2に配置されると共に、該L字部分が1階スラブ2の鉄筋8に接続される。
【0038】
地下壁3の上端部位に配筋された鉄筋8に沿って立上り部7の鉄筋15が配置され、差し込まれた状態で保持される。このとき、鉄筋15の上端側は予め設定された立上り部7の天端近傍に達している。また鉄筋15に沿って予め設定された位置には、アンカーボルト14が予め平板の所定位置に孔が形成されたアンカーボルト固定プレート9によって位置決めされると共に、上端側が予め設定された立上り部7の天端からの突出長さを保持した状態で差し込まれている。特に、鉄筋15,アンカーボルト14と鉄筋8とが接続されていないため、これらの間に適度な隙間が形成され、該隙間にコンクリートが浸透して充分なかぶり厚さを実現し、高い信頼性を発揮することが可能となる。
【0039】
上記の如くして地下壁3の鉄筋8と1階スラブ2の鉄筋8及び立上り部5,6の鉄筋11,13を接続した後、地下壁3の外型枠24、梁4の外型枠25を夫々設置する。
【0040】
次に、各立上り部5〜7に対応する部位に夫々立上り部5〜7の型枠26を設置する。このとき、各型枠26の下端部の高さを正確に1階スラブ2の上面レベルに一致させることが必要であり、このため、図4に示す受け金具31〜33を選択的に利用することが好ましい。
【0041】
受け金具31は立上り部5を形成するために設ける一対の型枠26を支持することを目的として構成されたものであり、端部に螺合させたネジ部材31bを回転させることで高さ調整可能に構成された2本の脚31aと、脚31aの上端部位に固着され上面に型枠26の位置を規定する2つの規定部材31dを設けた支持片31cと、を有する門型に形成されている。特に、立上り部5の下方に地下壁3や梁4が形成される場合、受け金具31はこれらの地下壁3や梁4を跨いで型枠26を支持し得るように構成されている。
【0042】
また受け金具32は下側に梁4や地下壁3が連続的に接続する立上り部6,7を形成するために設ける一対の型枠26を支持することを目的として構成されたものであり、端部に螺合させたネジ部材32bを回転させることで高さ調整可能に構成された1本の脚32aと、脚32aの上端部位に固着され上面に型枠26の位置を規定する2つの規定部材32dを設けた支持片32cと、を有するL型に形成されている。
【0043】
受け金具31,32に於いて、支持片31c,32cは丸棒(支持片31c)或いは平板(支持片32c)によって構成されている。これら丸棒,平板の何れであっても上部に型枠を載置して支持することが可能である。特に、平板からなる支持片では型枠を安定して支持することが可能となる。
【0044】
また受け金具33は各立上り部5〜7を形成する型枠26を単独で支持し得るようにしたものであり、両端部分にネジ部を形成した脚33aと、脚33aのネジ部に螺合するネジ部材33bとによって構成され、ネジ部材33bを回転させることで高さ調整可能に構成されている。この受け金具33では、木製型枠を支持する際に有効である。
【0045】
上記の如く構成された受け金具31は、立上り部5に沿って且つ1階スラブ2の内型枠22上に配置され、ネジ部材31bを回転させて該ネジ部材31bの底部と支持片31cの上面との距離が1階スラブ2の厚さと等しくなるように調整される。その後、支持片31cの上部に型枠26が載置され、且つ規定部材31dに当接して設置される。
【0046】
また受け金具32は立上り部6,7に沿って且つ1階スラブ2の内型枠22上に配置され、ネジ部材32bを回転させて該ネジ部材32bの底部と支持片32cの上面との距離が1階スラブ2の厚さと等しくなるように調整される。特に、立上り部7に対応して配置された受け金具32の支持片32cの自由端は、地下壁3の外型枠24の上端に載置され、立上り部6に対応して配置された受け金具32の自由端は、梁4の外型枠26の上端に載置される。
【0047】
また受け金具33は立上り部5〜7の型枠26に沿って且つ1階スラブ2の内型枠22上に配置され、ネジ部材33bを回転させて一対のネジ部材33bの間隔が1階スラブ2の厚さと等しくなるように調整される。その後、上方のネジ部材33bに型枠26が載置されて設置される。
【0048】
上記の如くして、地下壁3に対応する部位に内型枠21,外型枠24、1階図2に対応する部位に内型枠22、梁4に対応する部位に内型枠23,外型枠25を設置すると共に、立上り部5〜7に型枠26を設置した後、地下壁3,1階スラブ2,梁4の各型枠21〜25の上方からコンクリート16を打設し、地下壁3の隅々に充分に充填し、且つ梁4,1階スラブ2にコンクリート16を充填する。次いで、1階スラブ2に打設されたコンクリート16が硬化する以前に、各立上り部5〜7の型枠26の上方からコンクリート16を打設し、1階スラブ2に打設されたコンクリート16と充分に馴染ませる。
【0049】
上記の如くして、地下壁3と該地下壁3の上部に設けた立上り部7を鉄筋15を介して一体化させた地下室Aを構築することが可能である。尚、各立上り部5〜7を形成する型枠26を支持した受け金具31〜33は1階スラブ2に埋め殺しされる。
【0050】
図5は、地下壁3の上部に形成された立上り部7が、地下室Aの外周側に偏心した場合を示すものである。この場合、地下壁3の外型枠24が地下壁3の長さよりも長く形成されており、上端部分が立上り部7の外型枠として機能し得るように構成されている。従って、立上り部7を形成する際に、型枠26は内周面側に配置される1枚で良く、型枠の設置が簡単になる。
【0051】
立上り部7を形成する型枠26を支持する受け金具33は、前述した受け金具32と同様にL字状に形成されるものの、支持片33cには1枚の型枠26が載置されるのみであり、自由端側は地下壁3の外型枠24の上端に載置されて固定される。即ち、支持片33cには1つの規定部材があれば良く、且つ自由端と規定部材との距離は、立上り部7の厚さと1枚の型枠26の厚さの和となる。
【0052】
このように、地下壁3の外周面と立上り部7の外周面とを同一面とし、且つ外部に露出した面となるような場合、これらの外面が連続的な同一面として形成されるため、外観性能を向上させることが可能である。
【0053】
【発明の効果】
以上詳細に説明したように、本発明に係るプレハブ住宅に於ける構造地下室では、プレハブ住宅の地下部位に構築される構造地下室の構造であって、プレハブ住宅の荷重を耐圧スラブに伝達する地下壁と、プレハブ住宅の荷重を地下壁に伝達する梁とを有し、地下壁及び梁の上部から、地下壁及び梁の上部に形成された1階基礎立上り部に跨がる鉄筋が配筋され、または1階スラブ上面に突出した梁が1階基礎立上り部を兼ねて構成され、各1階基礎立上り部にはアンカーボルトが配置され、且つ地下壁,1階スラブ,梁,1階基礎立上り部が連続して打設されたコンクリートによって一体化されるため、信頼性の高い基礎立上り部を構成することが出来、且つ住宅の荷重を梁,地下壁を介して耐圧スラブに伝達することが出来る。特に、地下壁,梁及び1階基礎立上り部のコンクリートが一体化しているため、各1階立上り部に埋設されたアンカーボルトに高い引抜き強度を確保することが出来る。
【0054】
また本発明に係る構造地下室の施工方法では、プレハブ住宅の荷重が梁及び地下壁を介して伝達される耐圧スラブを構築した後、地下壁と1階スラブ,梁,地下壁の上部に設ける1階基礎立上り部及び梁の上部に設ける1階基礎立上り部まで一度のコンクリート打設によって構築することが出来るため、施工し易く、コンクリートの継目等がないため仕上がりが良い。更に、地下壁の上部に設けた1階基礎立上り部の鉄筋が、地下壁にまで跨がって配筋されるため、コンクリートの付着長さを充分にとることが出来、安定した強度を確保することが出来る。
【図面の簡単な説明】
【図1】ドライエリアを設けた地下室の構成を説明する断面図である。
【図2】地下車庫の構成を説明する断面図である。
【図3】図1の地下室を構築する際の型枠を説明する図である。
【図4】地下壁の上部に構成される立上り部の型枠を受ける受け金具を説明する図である。
【図5】地下壁と立上り部の外周面が同一面となる例を説明する図である。
【符号の説明】
A 地下室
B 地下車庫
C 内部空間
D 外部空間
E 開口部
1 耐圧スラブ
2 1階スラブ
3 地下壁
4 梁
5〜7 立上り部
8 鉄筋
9 アンカーボルト固定プレート
10,16 コンクリート
11〜13,15 鉄筋
14 アンカーボルト
21〜23 内型枠
24,25 外型枠
26 型枠
31〜33 受け金具
31a,32a 脚
31b,32b ネジ部材
31c〜33c 支持片
31d,32d 規定部材[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a structure of a basement such as a basement or an underground garage constructed in a basement part of a prefabricated house and a construction method, and in particular, a first floor slab, a beam, and a first floor are continuously provided on an upper part of a basement wall continuous with a pressure slab. The present invention relates to a structure having a foundation rising portion and a construction method.
[0002]
[Prior art]
Prefabricated houses are low-rise buildings that are built using a large number of components manufactured by an industrialized production system. They improve comfortability and durability, and increase the degree of freedom in floor plan with longer life. It has been developed mainly for the pursuit of a rational building structure to realize it and cost reduction.
[0003]
Recently, there is an increasing demand for prefabricated houses provided with a structural basement such as a reinforced concrete structure (RC) basement or underground garage in order to utilize the underground part. When constructing a structural basement in the basement of a prefabricated house, there are problems that the cost for excavating the ground and the cost required for backfilling after constructing the structural basement are large.
[0004]
For this reason, when building a basement in an underground part of a prefabricated house, in order to reduce the amount of excavation and reduce excavation costs and backfilling costs, the basement depth of the basement is set to be small It is common. In this case, the distance from the ceiling slab of the basement to the floor of the first floor of the prefabricated house can be reduced, and the first floor foundation rising portion can be formed on the ceiling slab to form the foundation of the prefabricated house.
[0005]
When an underground garage is constructed in an underground part of a prefabricated house, a road surface is set as the reference level of the underground garage. For this reason, the connection relationship between the underground garage and the prefabricated house does not necessarily coincide with the relationship between the basement and the prefabricated house described above. However, in addition to installing an underground garage on the basis of the road surface, a prefabricated house may be constructed with the ceiling slab of the underground garage as the first floor slab. In this case, the relationship between the basement and the prefabricated house is the same as described above. .
[0006]
The present applicant has already applied for a patent by developing a construction method that integrates the basement and the foundation of the upper structure of the basement (Japanese Patent Laid-Open No. 8-113951). In this technology, a basement unit with a formwork and bar arrangement corresponding to the basement is constructed on the ground in advance, and after this basement unit is installed at a predetermined position, the basement unit is arranged on the part corresponding to the ceiling slab of the basement. In addition, the bar is arranged at the part corresponding to the foundation in the ceiling slab and the receiving bracket is arranged, and the formwork is installed on the receiving bracket, and then in the basement unit formwork and the foundation formwork. By placing concrete, the basement and foundation can be integrated. This basement and integral foundation construction method is intended for the case where the foundation is formed on the upper side of the ceiling slab and on the inner plane (position separated from the wall of the basement).
[0007]
[Problems to be solved by the invention]
When building a prefabricated house in the upper part of a basement or underground garage or other structural basement, the first floor foundation rising part is not necessarily formed on the inner side of the ceiling slab but on the upper part of the basement wall There is also. Thus, when a 1st-floor foundation rising part is formed in the upper part of a basement wall, there exists a problem that the technique disclosed by the said gazette cannot respond.
[0008]
An object of the present invention is to provide a structure of a structural basement in which a first-floor foundation rising portion is formed in the upper part of the basement wall of the structural basement and a construction method when constructing the basement of the prefabricated house.
[0009]
[Means for Solving the Problems]
In order to solve the above problems, a structure of a structural basement according to the present invention is a structure of a structural basement constructed in an underground part of a prefabricated house, and transmits the load of the prefabricated house to a pressure-resistant slab, and the prefabricated house And a beam that transmits the load of the steel to the underground wall, the reinforcing bar is arranged from the upper part of the underground wall to the first floor foundation rising part formed on the upper part of the underground wall, and the reinforcing bar is the upper part of the beam From the top of the basement to the first floor foundation riser, or from the top of the underground wall to the top of the first floor foundation riser Beams that are arranged and project on the upper surface of the first-floor slab are configured to serve as the first-floor foundation rising portions, anchor bolts are arranged on the first-floor foundation rising portions, and the first-floor slab, beams, and the first floor from the underground wall Concrete placed continuously up to the foundation rise Therefore those configured.
[0010]
The basement structure has a basement wall that transmits the load of the prefabricated house to the pressure-resistant slab and a beam that transmits the load of the prefabricated house to the basement wall, and is formed from the basement wall to the top of the basement wall. Reinforcing bars that extend from the first floor foundation riser and the upper part of the beam to the first floor foundation riser, or the rebar is formed from the underground wall to the upper part of the underground wall Beams arranged at the foundation riser and projecting from the upper surface of the first floor slab are also constructed as the first floor foundation riser, anchor bolts are arranged at each first floor riser, and the underground wall and the first floor slab (structure basement Since the ceiling slab), beams, and the first floor foundation riser are integrated with concrete that is continuously placed, a highly reliable foundation riser can be constructed, and the load of the house can be used as a beam and underground wall. To the pressure slab via Door can be.
[0011]
In particular, an anchor bolt embedded in the first floor foundation rising portion is formed in the upper portion of the underground wall and beam by forming the first floor foundation rising portion continuous with the underground wall and beam. Along with the integration of the concrete of the floor foundation rising part, high pulling strength can be secured.
[0012]
In addition, the construction method of the structural basement is a construction method of the structural basement constructed in the basement part of the prefabricated house, and after constructing the pressure-resistant slab in which the load of the prefabricated house is transmitted through the beam and the basement wall, The basement wall, the first floor slab, and the rebar arrangement and formwork corresponding to the beam are constructed, and the first floor foundation rising part formed on the upper part of the basement wall is extended from the upper part of the basement wall. The first floor foundation rising section is arranged from the top of the beam to the first floor foundation rising section formed from the upper part of the beam or from the upper part of the underground wall. The first floor foundation rising part is arranged across the first floor foundation rising part formed in the upper part of the underground wall, and the beam protruding from the upper surface of the first floor slab also serves as the first floor foundation rising part. Anchor bolts are placed on each 1st floor foundation riser, and the 1st floor foundation rises. The first-floor foundation rising part formwork is arranged along the bottom and the lower end of the formwork is held at a height corresponding to the upper surface of the first-floor slab, and then the first-floor slab, beams and It is characterized by placing concrete continuously up to the first floor foundation rising part.
[0013]
In the construction basement construction method described above, after constructing a pressure-resistant slab in which the load of the prefabricated house is transmitted through the beam and the basement wall, the basement wall constituting the basement and the first floor slab configured on the top of the basement wall and Arranged in the beam and constructed the formwork, straddled from the upper part of the underground wall to the first floor foundation rising part formed on the upper part of the underground wall, and formed from the upper part of the beam to the upper part of the beam. If the beam is straddling over the first floor foundation rising part, or the beam protruding from the upper surface of the first floor slab is also used as the first floor foundation rising part, the beam is arranged and each 1 After placing anchor bolts on the rising floor, constructing the formwork and placing concrete, the continuous underground wall, the first floor slab, the beam, and the first floor foundation rising section are constructed by placing the concrete once. I can do it.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, a preferred embodiment of the structure of the structure basement will be described with reference to the drawings, and a construction method will be described together. FIG. 1 is a cross-sectional view illustrating the structure of a basement provided with a dry area. FIG. 2 is a cross-sectional view illustrating the configuration of the underground garage. FIG. 3 is a view for explaining a formwork when the basement of FIG. 1 is constructed. FIG. 4 is a view for explaining a receiving metal fitting for receiving the form of the rising portion formed in the upper part of the underground wall. FIG. 5 is a diagram for explaining an example in which the outer peripheral surface of the underground wall and the rising portion is the same surface.
[0015]
The structure of the structural basement according to the present invention includes a basement wall that constitutes a structural basement such as a basement or a basement garage, and a first-floor basic rising part (hereinafter simply referred to as a “rising part”) disposed on the upper part of the basement wall. These are connected by rising reinforcing bars, which are reinforcing bars that straddle both, and are integrally formed by continuous concrete. For this reason, it is possible to ensure high pulling strength of the anchor bolt embedded in the rising portion, and even when connecting the pillar constituting the casing of the upper structure to the anchor bolt, the vertical force In addition, it is possible to exhibit a stable strength against horizontal force.
[0016]
This will be specifically described below with reference to the drawings. FIG. 1 shows a basement A as a structural basement, and FIG. 2 shows an underground garage B. In the basement A and the underground garage B, there is an internal space C that serves as a living room, a warehouse, or a housing for a car, and a dry area or road that is open to the ground facing one side of the space C. The external space D is arranged. And between the internal space C and the external space D, the opening part E which consists of a window, a shutter, etc. is comprised.
[0017]
In FIG. 1, the basement A corresponds to the ceiling and the pressure-
[0018]
Reinforcing
[0019]
Reinforcing
[0020]
The rising
[0021]
The rising
[0022]
The rising portion 7 is provided above the
[0023]
In the present embodiment, the rising portion 7 is configured to support a vertical load and a horizontal load transmitted from the housing by attaching a housing of the prefab house.
[0024]
Reinforcing
[0025]
Further,
[0026]
The thickness of the rising portion 7 is smaller than the thickness of the
[0027]
For example, when the center of the rising portion 7 and the center of the
[0028]
The
[0029]
As described above, since the
[0030]
FIGS. 2A and 2B are cross-sectional views illustrating the configuration of an underground garage B as a structural basement. In addition, in the figure, the same code | symbol is attached | subjected to the part and the part which has the same function as the above-mentioned basement A, and description is abbreviate | omitted.
[0031]
The structure of the underground garage B in FIG. 5A is substantially the same as the basement A described above. That is, in the present embodiment, two rising
[0032]
In the underground garage B of FIG. 5B, a
[0033]
Next, the construction method according to the present invention will be described with reference to FIGS.
[0034]
As described above, when the basement A is constructed, after excavating the ground, the pressure-
[0035]
The reinforcing
[0036]
Reinforcing
[0037]
In addition, at the position corresponding to the upper end portion of the
[0038]
The reinforcing bars 15 of the rising portion 7 are arranged along the reinforcing
[0039]
After connecting the reinforcing
[0040]
Next, the
[0041]
The
[0042]
The receiving metal fitting 32 is configured to support a pair of
[0043]
In the receiving
[0044]
In addition, the receiving
[0045]
The receiving
[0046]
The
[0047]
The
[0048]
As described above, the
[0049]
As described above, it is possible to construct the basement A in which the
[0050]
FIG. 5 shows a case where the rising portion 7 formed in the upper part of the
[0051]
Although the receiving metal fitting 33 that supports the
[0052]
As described above, when the outer peripheral surface of the
[0053]
【The invention's effect】
As explained in detail above, the structural basement in the prefabricated house according to the present invention is a structure of the structural basement constructed in the basement part of the prefabricated house, and transmits the load of the prefabricated house to the pressure-resistant slab And a beam that transmits the load of the prefabricated house to the underground wall, and reinforcing bars that extend from the basement wall and the upper part of the beam to the first floor foundation rising part formed on the basement wall and the upper part of the beam are arranged. Or, the beam that protrudes from the upper surface of the first floor slab is configured to serve as the first floor foundation riser, and anchor bolts are arranged on each first floor foundation riser, and the underground wall, first floor slab, beam, first floor foundation rise Since the parts are integrated by the concrete that has been continuously cast, it is possible to construct a highly reliable foundation rising part and to transmit the load of the house to the pressure-resistant slab through the beam and underground wall. I can do it. In particular, since the concrete of the underground wall, the beam, and the first floor foundation rising portion are integrated, high pullout strength can be secured for the anchor bolts embedded in each first floor rising portion.
[0054]
Moreover, in the construction method of the structural basement according to the present invention, after constructing a pressure-resistant slab in which the load of the prefabricated house is transmitted through the beam and the underground wall, it is provided on the underground wall and the first floor slab, the beam, and the upper part of the underground wall. Since it can be constructed by one-time concrete placement up to the first floor foundation riser and the first floor foundation riser provided on the upper part of the beam, it is easy to construct and there is no concrete joints, so the finish is good. In addition, the reinforcement of the first floor foundation riser provided on the upper part of the basement wall is extended to the basement wall, so that the concrete adhesion length can be taken sufficiently and stable strength is secured. I can do it.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view illustrating the structure of a basement provided with a dry area.
FIG. 2 is a cross-sectional view illustrating the configuration of an underground garage.
FIG. 3 is a diagram for explaining a formwork for constructing the basement of FIG. 1;
FIG. 4 is a view for explaining a receiving metal fitting for receiving a form of a rising portion formed on the upper part of the underground wall.
FIG. 5 is a diagram illustrating an example in which an outer peripheral surface of a basement wall and a rising portion is the same surface.
[Explanation of symbols]
A basement
B underground garage
C interior space
D External space
E opening
1 Pressure slab
2 1st floor slab
3 underground wall
4 Beam
5-7 Rising part
8 Reinforcing bars
9 Anchor bolt fixing plate
10, 16 Concrete
11-13, 15 Rebar
14 Anchor bolt
21-23 inner formwork
24, 25 Outer formwork
26 Formwork
31-33 Bracket
31a, 32a legs
31b, 32b Screw member
31c ~ 33c Supporting piece
31d, 32d Regulatory member
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001209432A JP3653483B2 (en) | 2001-07-10 | 2001-07-10 | Structure of basement and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001209432A JP3653483B2 (en) | 2001-07-10 | 2001-07-10 | Structure of basement and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003020660A JP2003020660A (en) | 2003-01-24 |
JP3653483B2 true JP3653483B2 (en) | 2005-05-25 |
Family
ID=19045087
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001209432A Expired - Lifetime JP3653483B2 (en) | 2001-07-10 | 2001-07-10 | Structure of basement and construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3653483B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5972636B2 (en) * | 2012-03-29 | 2016-08-17 | 住友林業株式会社 | Underground space structure |
JP6954936B2 (en) * | 2019-01-25 | 2021-10-27 | 日立建機株式会社 | Construction machinery |
CN110965823A (en) * | 2019-12-26 | 2020-04-07 | 陈雨 | Underground garage with protruding corridor |
CN117513396B (en) * | 2023-11-08 | 2024-06-11 | 中信建筑设计研究总院有限公司 | Foundation-free structure at junction of basements of different layers |
-
2001
- 2001-07-10 JP JP2001209432A patent/JP3653483B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JP2003020660A (en) | 2003-01-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8132388B2 (en) | Modular concrete building | |
US8490363B2 (en) | Modular concrete building | |
KR101973702B1 (en) | Assembling type pier | |
KR20180078769A (en) | Assembling type pier | |
JP5574328B2 (en) | Tokai seismic wall and its construction method | |
KR102227414B1 (en) | Joint structure of underground exterior wall and slab | |
JP3653483B2 (en) | Structure of basement and construction method | |
JP2002121747A (en) | Semi-fixed direct foundation of steel column and pile foundation structure | |
KR101862567B1 (en) | Standardization of Mat Foundation assembling House system | |
JP2001262586A (en) | Foundation structure of dwelling house | |
KR100829954B1 (en) | Utility system in modular housing | |
JP3950024B2 (en) | Bonding structure between foundation and wall | |
KR20020062245A (en) | assembly type steel frame ladder of reinforcement concrete building and construction method thereof | |
KR200368283Y1 (en) | Mounting structure for steel-frame stair | |
KR100464594B1 (en) | The method of constructing the prefabricated step on reinforced concrete building | |
KR200414712Y1 (en) | Joint fittings for roof truss of apartment building | |
KR950009611B1 (en) | Assembling high apartments joining structure | |
JP4191864B2 (en) | Sash frame built-in wall panel and installation structure of sash frame built-in wall panel | |
JP4145733B2 (en) | Exterior wall construction method | |
JP2000008576A (en) | Fitting structure for precast concrete rising wall | |
KR100441285B1 (en) | Constructing method for extension of underground parking lot in apartment by using of precast concrete | |
KR100386354B1 (en) | method of apartment construction for the slip form construction method | |
JP2002364000A (en) | Precast foundation | |
KR20090121507A (en) | Watertight projection | |
JP2020176479A (en) | Precast construction method of balcony floor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040721 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040727 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040927 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20041109 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20041224 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050222 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050228 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3653483 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080304 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090304 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090304 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100304 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110304 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110304 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120304 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120304 Year of fee payment: 7 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120304 Year of fee payment: 7 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120304 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130304 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140304 Year of fee payment: 9 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
EXPY | Cancellation because of completion of term |