Method for assembling concrete pole ring reinforcement and apparatus, jig and metal fitting used therefor Download PDFInfo
- Publication number
- JP3634924B2 JP3634924B2 JP21169496A JP21169496A JP3634924B2 JP 3634924 B2 JP3634924 B2 JP 3634924B2 JP 21169496 A JP21169496 A JP 21169496A JP 21169496 A JP21169496 A JP 21169496A JP 3634924 B2 JP3634924 B2 JP 3634924B2
- Authority
- JP
- Japan
- Prior art keywords
- ring
- bar
- concrete pole
- spacer
- assembling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
- Wire Processing (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、リング筋で縦鉄筋を横拘束したコンクリートポールのリング筋の組立てにおいて、リング筋の組立方法並びにその組立方法に使用するリング筋組立装置、リング筋配置装置、スペーサー受け装置、リング筋連結金具及びリング筋集合治具に関する。
【0002】
【従来の技術】
大地震によっても破壊されない高強度を有するコンクリートポール、パイル等の長尺コンクリート製品あるいは細径であっても高強度を有する長尺コンクリート製品を得るため、縦鉄筋の横拘束筋としてリング筋が採用されつつある。
【0003】
図9はリング筋を用いたコンクリートポールの鉄筋の概略図で、ポールの上部及び下部は荷重の影響が少ないので、らせん筋が縦鉄筋及び補助縦鉄筋の外周に巻いてある。曲げモーメントが大きい部分には、リング筋で横拘束して強度を上げるため、第1のブロックのリング筋にダブルリング筋、第2及び第3のブロックのリング筋に丸状リング筋を用いて組立てている。曲げモーメントの大きさに応じてリング筋の強度、数、断面形状等を変化させて必要な強度を確保している。
【0004】
ところで、縦鉄筋をリング筋で横拘束するコンクリートポールは、最近製造されるようになったため、リング筋の組立て作業は手作業で行われているのが現状である。
【0005】
リング筋の手作業による組立て方法は、コンクリートポールにリング筋を配置するブロック毎に必要な数(通常十本を越える。)のリング筋を集合させ、リング筋の集合体の外周を固定治具で挟みボルトで固定し、縦鉄筋の所定のブロックの位置にリング筋の集合体を配置する。次いで、全ての縦鉄筋をリング筋の集合体の内部及び所定の間隔で配置される縦鉄筋を位置決めし保持するスペーサーに通した後、固定治具を外し、リング筋の集合体からリング筋を一本づつ分離して間隔揃え治具の溝に保持して所定の位置に配置する。配置が終了すると、極細鉄線で縦鉄筋とリング筋の結束を行って縦鉄筋とリング筋とを固定し、間隔揃え治具を外して、リング筋の組立てを終了する。
【0006】
【発明が解決しようとする課題】
従来のリング筋組立て作業が手作業であることから明らかなとおり、リング筋の位置決め配置及びリング筋の固定作業に時間を要するとともに、手作業によるため、リング筋の間隔精度がばらつくという欠点がある。また、テーパー状のコンクリートポールの場合、リング筋の集合体の内部及びスペーサーに縦鉄筋を通す時、縦鉄筋を軸方向にテーパー状に通すために、集合してテーパー状となっているリング筋集合体の径の小さいリング筋と縦鉄筋との摩擦が増大し、縦鉄筋が通しにくくなる。
【0007】
そこで、本発明は、コンクリートポールのリング筋の位置決め配置を自動化し、リング筋を結束作業をすることなく固定して作業時間を短縮し、リング筋間隔精度を向上させるコンクリートポールのリング筋の組立方法並びにそれに使用する装置、治具及び金具を提供するものである。
【0008】
【課題を解決するための手段】
本発明は、リング筋配置装置のリング筋保持体にリング筋を保持するとともに、スペーサー受け装置のスペーサー受台にスペーサーを保持し、縦鉄筋をスペーサー及びリング筋の内側に通した後、リング筋保持体を拡げてリング筋を所定間隔で位置決めし、位置決めしたリング筋をリング筋連結金具のクリップで挟持してコンクリートポールのリング筋を組立てる。
【0009】
コンクリートポールのリング筋組立装置は、リング筋配置装置及び複数のスペーサー受け装置が配置され、リング筋配置装置は、所定数のリング筋保持体からなっており、各リング筋保持体は連結環で互いに連結され、一対のエアシリンダの各ピストンロッドの先端には、それぞれ両端のリング筋保持体に固定され、エアシリンダの駆動により各リング筋保持体が所定間隔に移動する。
【0010】
スペーサー受け装置は、スペーサーを支持する複数のローラーが配置された昇降自在のスペーサー受台で構成される。
【0011】
リング筋連結金具は、リング筋を挟む所定数のクリップが形成された金属バンドからなる。
【0012】
リング筋集合治具は、リング筋の半円部分に接触する、位置決め切り欠きを有する位置決め板が両端の支持板に支持され、支持板の上部には、位置決めされた所定数のリング筋を保持するための保持棒を通す孔が形成されている。
【0013】
なお、本発明は、コンクリートポールのリング筋の組立てだけでなく、リング筋を利用したパイル等の長尺コンクリート製品のリング筋の組立てにも利用することができる。
【0014】
【発明の実施の形態】
図1は本発明のコンクリートポールのリング筋組立装置の一実施例の全体図で、リング筋組立装置は複数のリング筋配置装置1及び複数のスペーサー受装置2が交互に所定位置に配置され、両端には螺旋鉄筋コイル移動装置3が配置されている。
【0015】
図2はリング筋配置装置の正面図で、右半分はリング筋保持体を拡げた状態、左半分はリング筋保持体が閉じられた状態を示し、図3はリング筋保持体の概略図で、リング筋配置装置1は、リフター4上に設けられ、昇降可能となっている。リング筋配置装置1は、所定数のリング筋保持体5からなっている。
【0016】
各リング筋保持体5は、リング筋をはめ込み保持する半円弧状の溝6が形成され、上下の4隅のロッド7にその軸方向に摺動自在に支持されている。なお、リング筋保持体5及びそれに支持したリング筋の重量によりロッド7が撓むのを防止するため、リング筋保持体5の下部に車輪付脚8を設けてリング筋保持体5を支えてもよい。
【0017】
各リング筋保持体5は、楕円状の連結環9で隣接するリング筋保持体5と互いに連結されている。
【0018】
各リング筋保持体5を移動させてリング筋を所定間隔に位置決めする手段として、各リング筋保持体5の外側の中央部には一対のシリンダ10a,10bが各ピストンロッド11a,11bの作動方向が反対方向となるように固定されており、各ピストンロッド11a,11bの先端11c,11dは、それぞれ両端のリング筋保持体5a,5bに固定されており、シリンダ10a,10bを作動させ各リング筋保持体5を移動させて、図2に示す左半分のリング筋保持体が閉じられた状態から右半分のリング筋保持体を拡げた状態にして各リング筋保持体5を所定の間隔に拡げる。
【0019】
なお、各リング筋保持体5,5a,5bを移動させてリング筋を所定間隔に位置決めする手段としては、シリンダ以外の周知の移動機構で実施してもよい。
【0020】
図4はスペーサー受け装置の概略図で、スペーサー受け装置2は、スペーサーSを3点で支持するため、3個のローラー12a,12b,12cが配置されたスペーサー受台12とスペーサー受台12を昇降させるシリンダ13とからなり、各ローラー12a,12b,12cはスペーサーSの横断面の外形と一致する形状の溝が形成されている。
【0021】
図5はリング筋連結金具の斜視図で、リング筋連結金具14は、金属バンド14aを板金加工してリング筋を挟むクリップ15を形成したもので、クリップ15はリング筋に押付けるだけでリング筋を挟むことができるように、末広がりのガイド片16a,16bを形成する。
【0022】
図6はリング筋集合治具の上方から見た斜視図で、図7はリング筋集合治具の下方から見た斜視図で、リング筋配置装置のリング筋保持体にリング筋をセットするためのリング筋集合治具17は、リング筋を3点で位置決めするため、リング筋の半円部分に接触する3枚の位置決め板18a,18b,18cが両端の支持板19a,19bに支持され、位置決め板18a,18b,18cには、リング筋保持体5のピッチに合わせた位置決め用切り欠き20a,20b,20cが形成されており、支持板19a,19bの上部には、位置決めされたリング筋を保持するための保持棒21を通す孔22a,22bが形成されている。
【0023】
次に、リング筋の組立てについて説明する。
【0024】
図8は本発明のリング筋組立装置によるリング筋Rの組立て工程の説明図で、所定のリング筋Rをリング筋集合治具17の位置決め板18a,18b,18cの位置決め用切り欠き20a,20b,20cに配置した後、支持板19a,19bの孔22a,22bに保持棒21を通してリング筋Rの集合体を保持する。
【0025】
リング筋Rの集合体を保持したリング筋集合治具17をリング筋配置装置1のリング筋保持体5上に置くと、各リング筋Rはリング筋保持体5野溝に収まり、リング筋集合治具17から保持棒21を引き抜きリング筋集合治具17を持ち上げると、リング筋Rはリング筋保持体5に保持される。
【0026】
スペーサー受け装置2のスペーサー受台12にスペーサーをセットする。
【0027】
縦鉄筋をスペーサーS及びリング筋の内側に通す。シリンダ10a,10bを作動させて、ピストンロッドを移動させると、連結環9で連結されたリング筋保持体5が左右に拡がり、リング筋が所定間隔に位置決めされる。
【0028】
位置決めしたリング筋をリング筋連結金具14のクリップ15で挟持して連結する。連結箇所は断面等角度で3ヶ所が好ましい。
【0029】
リング筋配置装置1をリフター4で降下させた後、両端にらせん筋を移動させて巻く。
【0030】
【発明の効果】
(1) 縦鉄筋とリング筋及びスペーサーの摩擦が小さくなるため、縦鉄筋の通しが容易となる。
【0031】
(2) リング筋の所定間隔配置に間隔揃え治具及び手作業がなくなるので、作業時間の短縮とリング筋間隔精度が向上する。
【0032】
(3) ワンタッチ式リング筋連結金具を使用することで、結束作業がなくなるので、作業時間の短縮とリング筋配置間隔が連結金具のクリップ間隔で決まるため、リング筋間隔の変化に対する対応及び間隔精度が向上する。
【0033】
(4) スペーサー受け部に回転機能を付加しているので、鉄筋籠全体がスムースに回転することとなり、その他の作業が容易になる。
【図面の簡単な説明】
【図1】本発明のリング筋組立装置の一実施例の全体図である。
【図2】リング筋組立装置の正面図で、右半分はリング筋保持体を拡げた状態、左半分はリング筋保持体が閉じられた状態を示す正面図である。
【図3】リング筋保持体の概略図である。
【図4】スペーサー受け装置の概略図である。
【図5】リング筋連結金具の斜視図である。
【図6】リング筋集合治具の上方から見た斜視図である。
【図7】リング筋集合治具の下方から見た斜視図である。
【図8】本発明の装置によるリング筋の組立て工程の説明図である。
【図9】リング筋を用いたコンクリートポールの鉄筋の概略図である。
【符号の説明】
1 リング筋配置装置
2 スペーサー受け装置
3 螺旋鉄筋コイル移動装置
4 リフター
5,5a,5b リング筋保持体
6 溝
7 ロッド
8 車輪付脚
9 連結環
10a,10b エアシリンダ
11a,11b ピストンロッド
11c,11d ロッドの先端
12 スペーサー受台
12a,12b,12c ローラー
13 シリンダ
14 リング筋連結金具
14a 金属バンド
15 クリップ
16 ガイド片
17 リング筋集合治具
18a,18b,18c 位置決め板
19a,19b 支持板
20a,20b,20c 位置決め用切り欠き
21 保持棒
22a,22b 孔
R リング筋
S スペーサー[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method of assembling a ring bar, a ring bar assembling device, a ring bar placing device, a spacer receiving device, and a ring bar in the assembly of a ring bar of a concrete pole in which a vertical bar is laterally restrained by a ring bar. The present invention relates to a connection fitting and a ring reinforcing jig.
[0002]
[Prior art]
In order to obtain long concrete products such as concrete poles and piles that have high strength that will not be destroyed by large earthquakes or long concrete products that have high strength even with small diameters, ring bars are adopted as lateral restraint bars for the vertical bars. It is being done.
[0003]
FIG. 9 is a schematic diagram of a reinforcing bar of a concrete pole using ring bars. Since the upper part and the lower part of the pole are less affected by the load, the spiral bars are wound around the outer circumferences of the vertical bars and the auxiliary vertical bars. In order to increase the strength by laterally constraining the portion with a large bending moment with a ring reinforcement, a double ring reinforcement is used for the ring reinforcement of the first block, and a circular ring reinforcement is used for the ring reinforcement of the second and third blocks. Assembling. The required strength is ensured by changing the strength, number, cross-sectional shape, etc. of the ring streaks according to the magnitude of the bending moment.
[0004]
By the way, since the concrete pole which restrains a vertical reinforcing bar laterally with a ring reinforcement came to be manufactured recently, the assembly work of a ring reinforcement is currently performed manually.
[0005]
Assembling the ring bars manually, collect the required number (usually more than ten) of ring bars for each block where the ring bars are placed on the concrete pole, and fix the outer circumference of the ring bar assembly to the fixture. Then, the ring bars are fixed with pinching bolts, and a set of ring bars is arranged at a predetermined block position of the vertical bars. Next, after passing all the vertical reinforcing bars through the spacers that position and hold the vertical reinforcing bars arranged at predetermined intervals inside the ring reinforcing bars, the fixing jig is removed, and the ring reinforcing bars are removed from the ring reinforcing bars. They are separated one by one and are held in the grooves of the interval aligning jig and arranged at predetermined positions. When the arrangement is completed, the vertical reinforcing bar and the ring reinforcing bar are bound with the extra fine iron wire to fix the vertical reinforcing bar and the ring reinforcing bar, and the interval aligning jig is removed to finish the assembly of the ring reinforcing bar.
[0006]
[Problems to be solved by the invention]
As is apparent from the conventional ring muscle assembling work is manual work, it takes time for the positioning and positioning of the ring muscle and the fixing work of the ring muscle, and because it is by manual work, there is a disadvantage that the accuracy of the ring muscle spacing varies. . Also, in the case of tapered concrete poles, when the longitudinal bars are passed through the inside of the aggregate of ring bars and the spacer, the ring bars are gathered and tapered to pass the longitudinal bars in a taper shape in the axial direction. Friction between the ring bars having a small diameter of the aggregate and the vertical bars increases, and the vertical bars are difficult to pass.
[0007]
Therefore, the present invention automates the positioning and arrangement of the ring bars of the concrete pole, fixes the ring bars without binding, shortens the work time, and improves the accuracy of the ring bars spacing accuracy. The present invention provides a method and an apparatus, jig and metal fitting used therefor.
[0008]
[Means for Solving the Problems]
The present invention holds a ring line on a ring line holding body of a ring line arrangement device, holds a spacer on a spacer base of a spacer receiving device, passes a vertical reinforcing bar inside the spacer and the ring line, The ring body of the concrete pole is assembled by expanding the holding body and positioning the ring bars at predetermined intervals, and holding the positioned ring bars with the clip of the ring bar connecting bracket.
[0009]
A concrete pole ring rebar assembly device includes a ring rebar placement device and a plurality of spacer receiving devices, and the ring rebar placement device includes a predetermined number of ring rebar holders, and each ring rebar holder is a connecting ring. Connected to each other, the ends of the piston rods of the pair of air cylinders are fixed to the ring bar holders at both ends, respectively, and the ring bar holders move at predetermined intervals by driving the air cylinder.
[0010]
The spacer receiving device includes a vertically movable spacer receiving base on which a plurality of rollers supporting the spacer are arranged.
[0011]
The ring bar connecting metal fitting is made of a metal band on which a predetermined number of clips sandwiching the ring bar are formed.
[0012]
In the ring bar assembly jig, positioning plates with positioning notches that contact the semicircular portion of the ring bar are supported by support plates at both ends, and a predetermined number of positioned ring bars are held on the upper part of the support plate. A hole is formed through which a holding rod is inserted.
[0013]
The present invention can be used not only for assembling the ring bars of concrete poles but also for assembling ring bars of long concrete products such as piles using ring bars.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 is an overall view of an embodiment of a concrete pole ring rebar assembling apparatus according to the present invention. In the ring rebar assembling apparatus, a plurality of ring
[0015]
FIG. 2 is a front view of the ring streak arrangement device, the right half shows a state in which the ring streak holding body is expanded, the left half shows a state in which the ring streak holding body is closed, and FIG. 3 is a schematic view of the ring streak holding body. The ring
[0016]
Each ring
[0017]
Each ring
[0018]
A pair of
[0019]
In addition, you may implement by a well-known moving mechanism other than a cylinder as a means to move each ring
[0020]
FIG. 4 is a schematic diagram of the spacer receiving device. Since the
[0021]
FIG. 5 is a perspective view of a ring bar connecting metal fitting. The ring bar connecting metal fitting 14 is a
[0022]
6 is a perspective view of the ring muscle assembly jig as viewed from above, and FIG. 7 is a perspective view of the ring muscle assembly jig as viewed from below, in order to set the ring muscle on the ring muscle holder of the ring muscle assembly device. In order to position the ring line at three points, the ring
[0023]
Next, assembly of the ring line will be described.
[0024]
FIG. 8 is an explanatory view of a process of assembling the ring reinforcement R by the ring reinforcement assembly apparatus of the present invention. A predetermined ring reinforcement R is notched 20a, 20b for positioning the
[0025]
When the ring
[0026]
A spacer is set on the
[0027]
The vertical rebar is passed through the spacer S and the inside of the ring rebar. When the
[0028]
The positioned ring line is clamped and connected by the
[0029]
After the ring
[0030]
【The invention's effect】
(1) Since the friction between the vertical reinforcing bar, the ring reinforcing bar, and the spacer is reduced, the vertical reinforcing bar can be easily passed.
[0031]
(2) Since the interval aligning jig and the manual operation are eliminated in the predetermined interval arrangement of the ring lines, the working time is shortened and the ring line interval accuracy is improved.
[0032]
(3) By using the one-touch type ring bar connecting bracket, the bundling work is eliminated, so the work time is shortened and the ring bar layout interval is determined by the clip interval of the connecting bar. Will improve.
[0033]
(4) Since a rotation function is added to the spacer receiving portion, the entire rebar rod rotates smoothly, and other operations are facilitated.
[Brief description of the drawings]
FIG. 1 is an overall view of an embodiment of a ring muscle assembling apparatus of the present invention.
FIG. 2 is a front view of the ring muscle assembling apparatus, in which the right half is a state in which the ring muscle holder is expanded, and the left half is a front view showing a state in which the ring muscle holder is closed.
FIG. 3 is a schematic view of a ring muscle holder.
FIG. 4 is a schematic view of a spacer receiving device.
FIG. 5 is a perspective view of a ring bar connecting metal fitting.
FIG. 6 is a perspective view as seen from above the ring reinforcing jig.
FIG. 7 is a perspective view as seen from below the ring bar assembly jig.
FIG. 8 is an explanatory diagram of an assembly process of ring bars by the apparatus of the present invention.
FIG. 9 is a schematic view of a concrete pole rebar using ring bars.
[Explanation of symbols]
DESCRIPTION OF
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP21169496A JP3634924B2 (en) | 1996-08-09 | 1996-08-09 | Method for assembling concrete pole ring reinforcement and apparatus, jig and metal fitting used therefor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP21169496A JP3634924B2 (en) | 1996-08-09 | 1996-08-09 | Method for assembling concrete pole ring reinforcement and apparatus, jig and metal fitting used therefor |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH1052815A JPH1052815A (en) | 1998-02-24 |
JP3634924B2 true JP3634924B2 (en) | 2005-03-30 |
Family
ID=16610048
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP21169496A Expired - Lifetime JP3634924B2 (en) | 1996-08-09 | 1996-08-09 | Method for assembling concrete pole ring reinforcement and apparatus, jig and metal fitting used therefor |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3634924B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113719419B (en) * | 2021-10-09 | 2024-09-27 | 重庆大学 | Steel-concrete combined structure switching section of wind generating set |
CN115415795B (en) * | 2022-10-12 | 2024-04-09 | 建华建材(中国)有限公司 | Processing equipment and processing method for prestressed concrete support pile reinforcement cage |
-
1996
- 1996-08-09 JP JP21169496A patent/JP3634924B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH1052815A (en) | 1998-02-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20110120048A1 (en) | Rebar installation system and method of securing rebar | |
JP3634924B2 (en) | Method for assembling concrete pole ring reinforcement and apparatus, jig and metal fitting used therefor | |
JP2014050881A (en) | Reinforcement pulling-in device and reinforced cage horizontal assembling method thereof | |
EP0432121B1 (en) | Method for producing reinforcement for concrete members, preferably concrete piles, reinforcement and a strut member incorporated therein | |
CN211166982U (en) | Support arrangement suitable for assembly type structure | |
CN219074217U (en) | Copper stranded wire shaping device | |
CN108787966B (en) | Machine tool for manufacturing hollow hexagonal brick lead wire | |
JPH08197181A (en) | Device for assembling reinforcing bar cage | |
CN218029097U (en) | Steel reinforcement cage support bar structure | |
CN212769176U (en) | Winding device for winding and unwinding large-section cable | |
JPS6163329A (en) | Method and equipment for assembling reinforcement cage for concrete columnar | |
CN215657553U (en) | Portable bar straightener | |
CN214078969U (en) | Building circular stirrup processing device | |
JPH11347672A (en) | Holding apparatus for assembling reinforcing bar cage | |
CN219058115U (en) | Winding mechanism of full-automatic winding displacement machine | |
CN218798775U (en) | Bending device for reinforcing steel bars inside bridge pier | |
CN220725787U (en) | Reinforcing bar location structure for construction | |
CN220825426U (en) | Reinforcement cage main reinforcement positioner | |
CN216949112U (en) | Square column steel reinforcement cage locating rack | |
CN220928435U (en) | A building reinforcing bar location structure for cemetery construction | |
CN216042779U (en) | Temporary fixing device for reinforcement cage | |
CN213003243U (en) | Reducing bar penetrating disc of reinforcement cage seam welder | |
CN110303288B (en) | Steel reinforcement cage binding, welding and positioning device and using method thereof | |
CN215918969U (en) | Auxiliary device is used in wire pole steel reinforcement cage processing | |
CN215614691U (en) | Quick-correcting rebar straightening device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040813 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040903 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20041028 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20041126 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20041227 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090107 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100107 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110107 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110107 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120107 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130107 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |