JP3613538B2 - Steel pipe retraction method - Google Patents
Steel pipe retraction method Download PDFInfo
- Publication number
- JP3613538B2 JP3613538B2 JP23759696A JP23759696A JP3613538B2 JP 3613538 B2 JP3613538 B2 JP 3613538B2 JP 23759696 A JP23759696 A JP 23759696A JP 23759696 A JP23759696 A JP 23759696A JP 3613538 B2 JP3613538 B2 JP 3613538B2
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- steel pipe
- shaft
- preparation
- drawn
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Description
【0001】
【産業上の利用分野】
本発明は、ガス等の流通管路となる鋼管を非開削により地中に敷設するための鋼管引込み工法に関する。
【0002】
【従来の技術】
非開削による管の敷設工法として、路上設置型の推進機を地上に設置して第1工程では地中にボーリング孔を掘進し、第2工程では掘進したボーリング孔に管を引込む工法が従来提案されている。
【0003】
図5(A)(B)は上述の引き込み工法を示しており、(A)はボーリング孔の掘進工程,(B)は管の引込み工程を示す。管の敷設経路には、一方側に発進立坑a,他方側に到達立坑bが設けられ、発進立坑aの側の地上に、路上設置型の推進機cが設置される。この推進機cには、回転するロッドを所要の推進力で繰出したり、又は所要の引込み力で引戻す作用を行うガイドドリルユニットを備えている。
【0004】
図5(A)に示す掘進工程では、推進機cから繰り出されるロッドeの先端にドリルヘッドfが取付けられ、ドリルヘッドfを回転させつつ地中に進入させて発進立坑aの側から到達立坑bに至る経路にドリルヘッドfを進行させる。この際に、ドリルヘッドfの先端からベントナイト泥水をジェット噴射し、その水流により土壌を切り崩しながら進行させ、順次ロッドeを継ぎ足して到達立坑bに至る経路の地中にボーリング孔を掘進させるようにしている。
この掘進時には、ドリルヘッドfに組み込んだ発信器からの信号gを、地上の検知器hで検知してボーリングの先端位置を確認し、地上からの遠隔操作で掘進中の方向修正を行いながら掘進するようにしている。
【0005】
次いで図5(B)に示す引込み工程では、到達立坑bの側でドリルヘッドfを取外し、これに代えてロッドeの端部に、埋設管径に合わせた拡孔リーマnと、引込み対象の管(鋼管)mとを直列に連結した状態にして、推進機cによる引込み力でロッドeを引き戻す。そして引込みが完了した後クレーンjにより再び鋼管mを吊降ろし、溶接した後に再び引込みを開始する。この際に、拡孔リーマnから再度ベントナイト泥水をジェット噴射しながら引き戻し、この工程で引込み対象管mがボーリング孔に引込まれるようにしている。
【0006】
【発明が解決しようとする課題】
ところで、上述の路上設置型推進機を使用した工法の場合、引込み対象管が鋼管であると推進機の性能上、1日の引込み距離が約80m程度である。
また上述の工法の場合、到達立坑内に鋼管(全長12m程度)を1本づつ吊り降ろして、順次溶接しながら引込むようにしていることから、到達立坑の大きさは最低でも12m以上必要となる。ここで、この到達立坑を形成するためには、おおよそ6時間かかり、また、埋戻しをするには4時間かかる。そのため、施工が完了するまでは、覆工板と称する鉄板で塞ぐのが通例とされている。
【0007】
このような施工事情を考慮して、例えば320mの鋼管引込みを行うとした場合に、施工日数は4日かかり、また到達立坑も4つ形成しなくてはならない。そのため、到達立坑の形成費用及び覆工板の費用が多大にかかるという問題点が派生する。
【0008】
本発明は、上述の問題点を解決すべく案出されたもので、路上設置型の推進機を有効活用する着想に立って、鋼管の引込みが適正かつ安価に施工できる鋼管の引込み工法を提供することを目的とするものである。
【0009】
【課題を解決するための手段】
上記の目的を達成するため、本発明による工法は、管敷設経路に形成した作業立坑の区間に亘って鋼管を引込む鋼管の引込み工法であって、
第1工程では、地面に形成された複数の作業立坑の立坑区間毎に準備管を引込み、引込まれた準備管を前記立坑内で互いに連結して1本の連結準備管とし、
第2工程では、前記連結準備管内に鋼管を引込むように施工することを特徴とするものである。
【0010】
また、具体的な工法としては、上記作業立坑の一方の側の地上に、回転するロッドを所要の推進力で繰出したり又は所要の引込み力で引戻す作用を行うガイドドリルユニットを有した路上設置型の推進機を設置し、
第1工程では、上記路上設置型の推進機から繰り出される回転ロッドの先端にドリルヘッドを取付け、該ドリルヘッドを回転させつつ地中に進入させて一方の側の作業立坑から他方の側の作業立坑に至る経路の地中にボーリング孔を掘進させ、他方の側の作業立坑の側でドリルヘッドを取外し、これに代えてロッド端部に準備管径に合わせた拡孔リーマと、準備管とを直列に連結させた状態にして、推進機による前方からの引込み力でロッドを引き戻して準備管をボーリング孔に引込み、
管敷設経路に形成された全ての作業立坑の区間に亘って準備管の敷設が完了した後に、引込まれた準備管を前記立坑内で互いに連結して1本の連結準備管とし、
第2工程では、前記連結準備管内に鋼管を引込むように施工することを特徴とするものである。
【0011】
さらに、上記準備管はポリエチレン管とし、また、上記準備管内に鋼管を引込む手段としては、終端側の作業立坑内に設置したウインチを用いて行い、必要に応じて前記ポリエチレン管の内面に潤滑材を塗布した後に鋼管を引込むことを特徴とするものである。
【0012】
【作用】
上述のような引込み工法によると、鋼管を引込む前段として、ポリエチレン管等の準備管を土中に引込み、その後,該準備管内に鋼管を引込むようにしている。そのため、鋼管は土中と接触せずに、準備管のみと接触することになり、鋼管引込みによる摩擦抵抗が低減され、1日の鋼管引込み距離(80m)の距離延長化が可能となる。また、準備管内に潤滑材を塗布した場合、引込みによる摩擦抵抗がより低減され、さらなる鋼管引込み距離の距離延長化が可能となる。
【0013】
また、準備管にポリエチレン管を使用した場合、該ポリエチレン管は屈曲可能なことから、到達立坑の大きさとして12mも必要とせず、口径200Aのポリエチレン管を引込むための到達立坑の大きさは約5mですむ。そのため、到達立坑を形成するための費用を低減させることができ、さらには、即日の埋戻しも可能なことかから、覆工板も必要とせず、施工費用を大幅に低減させることができる。
【0014】
【実施例】
以下、本発明の実施例を、図面に基いて説明する。
図1において、符号1は第1作業立坑,符号2は第2作業立坑,符号3は第3作業立坑である。
本実施例では、前記第1作業立坑1と前記第3作業立坑3との間に鋼管を敷設するものとする。
【0015】
まず第1工程として、前記第1作業立坑1と第3作業立坑3との間に準備管としてポリエチレン管4を引込む。ここで前記ポリエチレン管4の内径は、引込み対象の鋼管の外径より若干大きいものとする。
図1に示すように、第1立坑1の地上に、路上設置型の推進機5を設置する。この推進機5は、従来と同様に回転するロッド6を、所要の推進力で繰出したり、また所要の引込み力で引き戻す作用を行わせるガイドドリルユニット51を装備しており、他に、図示していないが動力源となるパワーユニットトラックを設備している。そして推進機5から繰り出される回転ロッド6の先端にドリルヘッド7を取付け、該ドリルヘッド7を回転させつつ地中に進入させ、第1立坑1から第2立坑2に至る経路の地中にボーリング孔を掘進させる。次に、第2立坑2の側でドリルヘッド7を取外し、これに代えてロッド端部にポリエチレン管4の径に合わせた拡孔リーマ8と、ポリエチレン管4とを直列に連結させた状態にして、推進機5による前方からの引込み力でロッド6を引き戻してポリエチレン管4をボーリング孔に引込む。さらに、第2立坑2と第3立坑3との間でも前述したと同様にして、ポリエチレン管4を敷設する。
そして、第2立坑2にて、敷設したポリエチレン管4を互いに連結して、第1作業立坑1と第3作業立坑3との間にポリエチレン管4の敷設を完了させる。
【0016】
また、前記第1作業立坑1と第3作業立坑3との間にポリエチレン管4を引込む他の方法として、図2に示すように、まず第1立坑1と第2立坑との間で、推進機5から繰り出される回転ロッド6の先端にドリルヘッド7を取付け、探知機8にて方向を確認しながら該ドリルヘッド7を回転させつつ地中に進入させ、ボーリング孔を形成する。そして次に、推進機5を第2立坑2の側に移動させ、第2立坑2と第3立坑3との間に第2回転ロッド6’を推進させてボーリング孔を形成する。そして図3に示すように、第2立坑2内にて前記第1回転ロッド6と第2回転ロッド6’とを連結させる。そして、該連結ロッドの終端にポリエチレン管4の径に合わせた拡孔リーマ8と、ポリエチレン管4とを直列に連結させた状態にして、推進機5による前方からの引込み力で連結ロッドを引き戻してポリエチレン管4をボーリング孔に引込む。
そして、第1作業立坑1と第3作業立坑3との間にポリエチレン管4の敷設を完了させる。
【0017】
次に第2工程として第1工程で敷設したポリエチレン管4内に鋼管11を引込む。
図4に示すように、まずポリエチレン管4内に牽引ワイヤ13を挿通させる。次に初段の鋼管11を第3立坑3内に設置させる。そして前記牽引ワイヤ13の一端を第1立坑1内に設置したウインチ12に連結し、ワイヤ13の他端を鋼管11の先端部に連結させる。そして前記ウインチ12を操作して初段の鋼管11をポリエチレン管4内に引込み、ある程度引込んだ時点で、一旦引込みを停止し、第3立坑3付近の地上に設置したクレーン10にて次段の鋼管11を吊降ろし、そして鋼管11の端部を溶接した後、再び引込みを再開して鋼管の引込みを行う。このようにして順次,ポリエチレン管4内に鋼管11の引込みを行うようにする。
【0018】
上述のような引込み工法によると、鋼管11を土中に引込む前段として、ポリエチレン管4を土中に引込み、その後,該ポリエチレン管4内に鋼管11を引込むようにしている。そのため、鋼管11は土中と接触せずに、ポリエチレン管4のみと接触することになり、鋼管11の引込みによる摩擦抵抗が低減され、1日の鋼管引込み距離の距離延長化が可能となる。また、鋼管11を引込む前に、ポリエチレン管4内に潤滑材を塗布しておくことで、さらに摩擦抵抗が低減され、鋼管引込み距離のさらなる距離延長化が可能となる。
【0019】
また、ポリエチレン管4は屈曲可能なことから、作業立坑の大きさとして12mも必要とせず、口径200Aのポリエチレン管4を引込むための作業立坑の大きさは約5mですむ。そのため、第1立坑及び第2立坑2を形成するための費用を低減させることができ、さらには、即日の埋戻しも可能なことかから、覆工板も必要とせず、施工費用を大幅に低減させることができる。
【0020】
以上本発明の実施例を詳細に説明したが、上記実施例において、作業立坑として、第1立坑1,第2立坑2,第3立坑3を用いて説明したが、本発明はこれに限らず、4つ以上の複数の作業立坑を形成した場合にも適応できる。
【0021】
【発明の効果】
かくて本発明によれば、鋼管を引込む前段として、ポリエチレン管等の準備管を土中に引込み、その後,該準備管内に鋼管を引込むようにしている。そのため、鋼管は土中と接触せずに、準備管のみと接触することになり、鋼管引込みによる摩擦抵抗が低減され、1日の鋼管引込み距離(80m)の距離延長化が可能となる。また、準備管内に潤滑材を塗布した場合、引込みによる摩擦抵抗がより低減され、さらなる鋼管引込み距離の距離延長化が可能となる。
【0022】
また、結果として敷設された鋼管は準備管によって覆われているため、雨水等の外部要因による腐食等の老朽化を防止することができる。
さらに、準備管にポリエチレン管を使用した場合、該ポリエチレン管は屈曲可能なことから、到達立坑の大きさとして12mも必要とせず、口径200Aのポリエチレン管を引込むための到達立坑の大きさは約5mですむ。そのため、到達立坑を形成するための費用を低減させることができ、さらには、即日の埋戻しも可能なことかから、覆工板も必要とせず、施工費用を大幅に低減させることができる。
【図面の簡単な説明】
【図1】本発明による第1工程の説明図
【図2】本発明による他の第1工程の説明図
【図3】本発明による他の第1工程の説明図
【図4】本発明による第2工程の説明図
【図5】従来例の説明図
【符号の説明】
1 第1作業立坑
2 第2作業立坑
3 第3作業立坑
4 ポリエチレン管
5 路上設置型の推進機
51 ガイドドリルユニット
6 ロッド
7 ドリルヘッド
8 拡孔リーマ
9 探知機
10 クレーン
11 鋼管
12 ウインチ
13 牽引ワイヤ[0001]
[Industrial application fields]
The present invention relates to a steel pipe retracting method for laying a steel pipe that becomes a distribution pipe for gas or the like in the ground by non-open cutting.
[0002]
[Prior art]
As a method of laying pipes by non-open cutting, a conventional method has been proposed in which a road-mounted type propulsion machine is installed on the ground, drilling a borehole into the ground in the first process, and drawing the pipe into the drilled borehole in the second process. Has been.
[0003]
5 (A) and 5 (B) show the above-described drawing method, (A) shows the drilling process of the borehole, and (B) shows the pipe drawing process. The pipe laying path is provided with a start shaft a on one side and a reaching shaft b on the other side, and a road-mounted propulsion device c is installed on the ground on the start shaft a side. The propulsion unit c includes a guide drill unit that performs an action of feeding a rotating rod with a required propulsive force or pulling it back with a required pulling force.
[0004]
In the excavation process shown in FIG. 5 (A), a drill head f is attached to the tip of a rod e fed out from a propulsion device c, and the drill head f enters the ground while rotating to reach the reaching shaft from the start shaft a. The drill head f is advanced along the path leading to b. At this time, bentonite muddy water is jetted from the tip of the drill head f, and the water flow advances while cutting the soil, and rods e are sequentially added so that a borehole is dug into the ground of the route to the reaching shaft b. ing.
During this excavation, the signal g from the transmitter incorporated in the drill head f is detected by the ground detector h to confirm the tip position of the boring, and the excavation is performed while correcting the direction during excavation by remote control from the ground. Like to do.
[0005]
Next, in the retraction process shown in FIG. 5 (B), the drill head f is removed on the side of the reaching shaft b, and instead of this, at the end of the rod e, a hole expansion reamer n adapted to the buried pipe diameter, and the retraction target With the pipe (steel pipe) m connected in series, the rod e is pulled back by the pulling force of the propulsion unit c. Then, after the drawing is completed, the steel pipe m is suspended again by the crane j, and after the welding, the drawing is started again. At this time, the bentonite mud is pulled back from the expanded reamer n while jetting again, and in this step, the drawing target pipe m is drawn into the borehole.
[0006]
[Problems to be solved by the invention]
By the way, in the case of the construction method using the above-mentioned road-mounted propulsion device, when the pull-in target pipe is a steel pipe, the pull-in distance per day is about 80 m due to the performance of the propulsion device.
In the case of the above-mentioned construction method, steel pipes (about 12 m in total length) are suspended one by one in the reaching shaft and are pulled in while being sequentially welded. Therefore, the size of the reaching shaft is required to be at least 12 m. Here, it takes about 6 hours to form this reach shaft, and it takes 4 hours to backfill. Therefore, until construction is completed, it is customary to close with an iron plate called a lining plate.
[0007]
In consideration of such construction circumstances, for example, when a 320 m steel pipe is pulled in, the construction takes 4 days, and four reaching shafts must be formed. Therefore, the problem that the cost of forming the reaching shaft and the cost of the lining board are enormous is derived.
[0008]
The present invention has been devised to solve the above-mentioned problems, and provides a steel pipe retraction method that allows steel pipe retraction to be performed appropriately and inexpensively based on the idea of effectively using a road-mounted propulsion device. It is intended to do.
[0009]
[Means for Solving the Problems]
In order to achieve the above object, the construction method according to the present invention is a steel pipe retraction method for drawing a steel pipe over a section of a work shaft formed in a pipe laying path,
In the first step, a preparation pipe is drawn into each shaft section of a plurality of work shafts formed on the ground, and the drawn-in preparation pipes are connected to each other in the shaft to form one connection preparation pipe,
In the 2nd process, it constructs so that a steel pipe may be drawn in in the above-mentioned connection preparation pipe.
[0010]
Also, as a concrete construction method, on the ground on one side of the above work shaft, installed on the road with a guide drill unit that performs the action of feeding out the rotating rod with the required propulsive force or pulling it back with the required retracting force Type propulsion machine,
In the first step, a drill head is attached to the tip of a rotating rod fed out from the road-mounted propulsion device, and the drill head is rotated and entered into the ground to work from one side work shaft to the other side. Drill a boring hole into the ground to the shaft, remove the drill head from the work shaft on the other side, and replace it with an expanded reamer that matches the diameter of the prepared tube at the rod end, and a prepared tube In a state where they are connected in series, the rod is pulled back by the pulling force from the front by the propulsion device, and the preparation tube is pulled into the boring hole,
After laying of the preparation pipe is completed over all work shaft sections formed in the pipe laying path, the drawn preparation pipes are connected to each other in the shaft to form one connection preparation pipe,
In the 2nd process, it constructs so that a steel pipe may be drawn in in the above-mentioned connection preparation pipe.
[0011]
Further, the preparatory pipe is a polyethylene pipe, and as a means for drawing the steel pipe into the preparatory pipe, a winch installed in the work shaft on the terminal side is used, and if necessary, a lubricant is provided on the inner surface of the polyethylene pipe. The steel pipe is retracted after the coating is applied.
[0012]
[Action]
According to the above-described drawing method, a preparation pipe such as a polyethylene pipe is drawn into the soil before the steel pipe is drawn, and then the steel pipe is drawn into the preparation pipe. Therefore, the steel pipe is not in contact with the soil but is in contact with only the preparation pipe, the frictional resistance due to the steel pipe drawing is reduced, and the distance of the steel pipe drawing distance (80 m) per day can be extended. In addition, when a lubricant is applied in the preparation pipe, the frictional resistance due to the pull-in is further reduced, and the steel pipe pull-in distance can be further extended.
[0013]
Further, when a polyethylene pipe is used as the preparation pipe, the polyethylene pipe can be bent, so that the size of the reaching shaft is not required as much as 12 m, and the size of the reaching shaft for drawing the polyethylene pipe having a diameter of 200A is about 5m is enough. Therefore, it is possible to reduce the cost for forming the reaching shaft, and further, since the backfilling on the same day is possible, the lining plate is not required, and the construction cost can be greatly reduced.
[0014]
【Example】
Embodiments of the present invention will be described below with reference to the drawings.
In FIG. 1,
In this embodiment, a steel pipe is laid between the
[0015]
First, as a first step, a
As shown in FIG. 1, a road-mounted propulsion device 5 is installed on the ground of the
Then, the laid
[0016]
As another method of drawing the
Then, the laying of the
[0017]
Next, the
As shown in FIG. 4, first, the pulling
[0018]
According to the drawing method as described above, the
[0019]
Moreover, since the
[0020]
As mentioned above, although the Example of this invention was described in detail, in the said Example, although demonstrated using the
[0021]
【The invention's effect】
Thus, according to the present invention, as a stage before drawing the steel pipe, a preparation pipe such as a polyethylene pipe is drawn into the soil, and then the steel pipe is drawn into the preparation pipe. Therefore, the steel pipe is not in contact with the soil but is in contact with only the preparation pipe, the frictional resistance due to the steel pipe drawing is reduced, and the distance of the steel pipe drawing distance (80 m) per day can be extended. In addition, when a lubricant is applied in the preparation pipe, the frictional resistance due to the pull-in is further reduced, and the steel pipe pull-in distance can be further extended.
[0022]
Moreover, since the laid steel pipe is covered with the preparation pipe, it is possible to prevent aging such as corrosion due to external factors such as rainwater.
Further, when a polyethylene pipe is used as the preparation pipe, the polyethylene pipe can be bent, so that the size of the reaching shaft is not required as much as 12 m, and the size of the reaching shaft for drawing the polyethylene pipe having a diameter of 200A is about 5m is enough. Therefore, it is possible to reduce the cost for forming the reaching shaft, and further, since the backfilling on the same day is possible, the lining plate is not required, and the construction cost can be greatly reduced.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram of a first step according to the present invention. FIG. 2 is an explanatory diagram of another first step according to the present invention. FIG. 3 is an explanatory diagram of another first step according to the present invention. Explanatory drawing of the second step [Fig.
DESCRIPTION OF
Claims (5)
第1工程では、地面に形成された複数の作業立坑の立坑区間毎に準備管を引込み、引込まれた準備管を前記立坑内で互いに連結して1本の連結準備管とし、
第2工程では、前記連結準備管内に鋼管を引込むように施工することを特徴とする鋼管の引込み工法。A steel pipe drawing method for drawing a steel pipe over a section of a work shaft formed in a pipe laying path,
In the first step, a preparation pipe is drawn into each shaft section of a plurality of work shafts formed on the ground, and the drawn-in preparation pipes are connected to each other in the shaft to form one connection preparation pipe,
In the 2nd process, it constructs so that a steel pipe may be drawn in in the above-mentioned connection preparation pipe.
第1工程では、上記路上設置型の推進機から繰り出される回転ロッドの先端にドリルヘッドを取付け、該ドリルヘッドを回転させつつ地中に進入させて一方の側の作業立坑から他方の側の作業立坑に至る経路の地中にボーリング孔を掘進させ、他方の側の作業立坑の側でドリルヘッドを取外し、これに代えてロッド端部に準備管径に合わせた拡孔リーマと、準備管とを直列に連結させた状態にして、推進機による前方からの引込み力でロッドを引き戻して準備管をボーリング孔に引込み、
管敷設経路に形成された全ての作業立坑の区間に亘って準備管の敷設が完了した後に、引込まれた準備管を前記立坑内で互いに連結して1本の連結準備管とし、
第2工程では、前記連結準備管内に鋼管を引込むように施工することを特徴とする請求項1記載の鋼管の引込み工法。On the ground on one side of the work shaft, a road-installed type propulsion unit having a guide drill unit that performs an action of feeding a rotating rod with a required propulsive force or retracting with a required pulling force,
In the first step, a drill head is attached to the tip of a rotating rod fed out from the road-mounted propulsion device, and the drill head is rotated and entered into the ground to work from one side work shaft to the other side. Drill a boring hole into the ground to the shaft, remove the drill head from the work shaft on the other side, and replace it with an expanded reamer that matches the diameter of the prepared tube at the rod end, and a prepared tube In a state where they are connected in series, the rod is pulled back by the pulling force from the front by the propulsion device, and the preparation tube is pulled into the boring hole,
After laying of the preparation pipe is completed over all work shaft sections formed in the pipe laying path, the drawn preparation pipes are connected to each other in the shaft to form one connection preparation pipe,
In the 2nd process, it constructs so that a steel pipe may be drawn in in the said connection preparation pipe, The drawing-in method of the steel pipe of Claim 1 characterized by the above-mentioned.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP23759696A JP3613538B2 (en) | 1996-09-09 | 1996-09-09 | Steel pipe retraction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP23759696A JP3613538B2 (en) | 1996-09-09 | 1996-09-09 | Steel pipe retraction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH1082480A JPH1082480A (en) | 1998-03-31 |
JP3613538B2 true JP3613538B2 (en) | 2005-01-26 |
Family
ID=17017672
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP23759696A Expired - Fee Related JP3613538B2 (en) | 1996-09-09 | 1996-09-09 | Steel pipe retraction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3613538B2 (en) |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01172690A (en) * | 1987-12-28 | 1989-07-07 | Hisao Hashimoto | Installation of double piping in pipeline fluid transportation |
JP2717476B2 (en) * | 1992-03-12 | 1998-02-18 | 東京瓦斯株式会社 | Main pipe drawing method in the propulsion pipe |
JPH05346188A (en) * | 1992-06-15 | 1993-12-27 | Hitachi Zosen Corp | Introducing method of coated pipe |
JPH07119384A (en) * | 1993-10-27 | 1995-05-09 | Tokyo Gas Co Ltd | Driving method of curved pipe line |
JPH07150890A (en) * | 1993-11-26 | 1995-06-13 | Tokyo Gas Co Ltd | Propusion method for curved pipe line |
JP3247788B2 (en) * | 1994-02-28 | 2002-01-21 | 東京瓦斯株式会社 | Construction method of underground piping |
JPH07247788A (en) * | 1994-03-14 | 1995-09-26 | Tokyo Gas Co Ltd | Method of forming lining |
-
1996
- 1996-09-09 JP JP23759696A patent/JP3613538B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH1082480A (en) | 1998-03-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
RU2392390C2 (en) | Trenchless pipe driving method | |
CN111306360A (en) | Trenchless pipeline jacking and laying construction method | |
EP2115338B1 (en) | Method for laying pipes in the ground | |
US20030070841A1 (en) | Shallow depth, coiled tubing horizontal drilling system | |
CN111911712A (en) | Push pipe type trenchless pipeline construction method | |
KR20030045695A (en) | Method for Digging a Tunnel | |
US7699123B2 (en) | Bore hole sleeve reaming apparatus and method | |
JP3613538B2 (en) | Steel pipe retraction method | |
US5494118A (en) | Placement of pipes in the ground | |
JPH07150890A (en) | Propusion method for curved pipe line | |
JP3779035B2 (en) | Excavator and pipe drawing method using it | |
CN116642054B (en) | Auxiliary device for connecting reinforced concrete pipelines and construction method thereof | |
JPH09195677A (en) | Underground laying engineering method of steel pipe | |
JPH09195676A (en) | Propulsive method of rod for drilling boring hole pushed in by propulsive machine | |
JP3819600B2 (en) | Piping laying method | |
DE19858509C1 (en) | Method for trench-free forming of pressure-sealed domestic gas/water pipe connections uses robots to place whip stock, drill string with head, draw head, and milling cutter robots | |
JP3519829B2 (en) | Underground pipe peripheral friction reduction method | |
JP2506580B2 (en) | Non-open cutting pipeline renewal / expansion method for underground pipes | |
JPS6160238B2 (en) | ||
JPH1018766A (en) | Pipe draw-in process | |
JPH0237915Y2 (en) | ||
JP3633725B2 (en) | Pipe retractor | |
JPH07119384A (en) | Driving method of curved pipe line | |
JPH09158674A (en) | Laying construction method of piping by unopened-cut excavation | |
JPH09195678A (en) | Underground drawing jig of steel pipe and drawing engineering method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20041014 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20041022 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20041025 |
|
R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071105 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081105 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091105 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091105 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101105 Year of fee payment: 6 |
|
LAPS | Cancellation because of no payment of annual fees |