JP3569854B2 - Roof fixing nail - Google Patents
Roof fixing nail Download PDFInfo
- Publication number
- JP3569854B2 JP3569854B2 JP03873895A JP3873895A JP3569854B2 JP 3569854 B2 JP3569854 B2 JP 3569854B2 JP 03873895 A JP03873895 A JP 03873895A JP 3873895 A JP3873895 A JP 3873895A JP 3569854 B2 JP3569854 B2 JP 3569854B2
- Authority
- JP
- Japan
- Prior art keywords
- hammering head
- tile
- pile
- fixing nail
- head
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Joining Of Building Structures In Genera (AREA)
Description
【0001】
【産業上の利用分野】
この発明は、瓦を瓦桟等に固定する瓦固定釘に関するものである。
【0002】
【従来の技術】
図10に示すように、従来例の瓦固定釘Cは、杭部1の側方へ延出した槌打頭部2を有し、前記槌打頭部2の先端に下降傾斜した折曲部4を形成したものである。また、前記杭部1の周面には、図11に示すように、前記杭部1の打込み方向に縮径するように傾斜した上面部1aと、該上面部1aに前記杭部1の打込み方向に隙間を開けて対面すると共に前記打込み方向に略直交した下面部1bとを有する周溝1cが形成されている。
【0003】
上記例示の瓦固定釘Cを用いて瓦を敷設するには、以下の手順によって行われる。すなわち、図12及び図13に示すように、先ず、第1の瓦D1の上縁部の表面側に、その上方に存する第2の瓦D2の下縁部を重合させて載置する。この状態で、前記瓦固定釘Cを、第1の瓦D1と第2の瓦D2との重合部の右側上方から、この重合部の真下に位置する瓦桟5に打ち込み、同時に、該瓦固定釘Cの槌打頭部2を第2の瓦D2の表面に係止させる。次に、第2の瓦D2の上縁部に形成された挿通孔6にスクリュー釘Eを打ち込む。以上の工程を軒先側から棟側に向かって繰り返すようにする。
【0004】
【発明が解決しようとする課題】
従来例の瓦固定釘Cでは、瓦桟5への打込みを前記槌打頭部2を金槌等で真上から打撃することによって行え、これと同時に、前記槌打頭部2を瓦の表面に係止できるので、作業性に優れているのであるが、しかしながら、金槌等による打撃が繰り返されると、前記槌打頭部2が下方へ折曲して瓦の表面に沿って係止できなくなったり、或いは、前記槌打頭部2が金属疲労等により破断したりするという問題がある。このような問題が施工中に起こると、瓦桟5に一旦打ち込んだ瓦固定釘Cを抜き取って新たな瓦固定釘Cを打ち直さなければならず、多くの手間と時間を費やすことになった。また、金槌等の打力を弱めると瓦固定釘Cの打込み要する時間が不要に長くなった。
【0005】
この発明の目的は、耐久性に優れた瓦固定釘を提供することである。
【0006】
請求項1記載の瓦固定釘は、先端を尖らせた鋼製の円形断面を有する線材からなる杭部の後端部を直角に一方向に折曲して先端が下降傾斜した折曲部を有する槌打頭部を形成すると共に、該槌打頭部の基端付近の上面から該槌打頭部の突出方向へ延びる凸条を設けたものである。
【0007】
請求項2記載の瓦固定釘は、先端を尖らせた鋼製の円形断面を有する線材からなる杭部の後端部を直角に一方向に折曲して先端が下降傾斜した折曲部を有する槌打頭部を形成すると共に、該槌打頭部の基端付近の肉厚を上方へ膨出して前記杭部の打込み方向に増加し、且つ、基端付近の幅寸法を先端付近より減少したことにある。
【0008】
【作用】
請求項1記載の瓦固定釘によると、槌打頭部の基端付近の上面に設けた凸条が槌打頭部の補強リブとして作用するので、杭部の打込み方向から受ける衝撃に対して高い強度を確保することができる。
【0009】
請求項2記載の瓦固定釘によると、槌打頭部の基端付近の肉厚が上方へ膨出して杭部の打込み方向に増加しているので、杭部の打込み方向から受ける衝撃に対して高い強度を確保することができる。
【0010】
【実施例】
以下にこの発明の瓦固定釘の実施例について説明する。従来例と同様の構成は同符号を付して説明を省略し、施工手順についても従来例と同様であるため省略する。
【0011】
図1に示すように、この発明の第1の実施例の瓦固定釘Aは、先端1aを尖らせた鋼製の円形断面を有する線材からなる杭部1の後端部を直角に折曲することにより槌打頭部2を形成すると共に、図2及び図3に示すように、前記槌打頭部2の基端付近2aの上面に、該槌打頭部2の突出方向へ延びる凸条3を設けたものである。前記凸条3は、前記槌打頭部2と一体に形成することが部品点数を増加することなく好ましいが、金属片等をロウ付けする等して形成してもよい。また、前記凸条3の本数や配置等については、図3に示すものに限定されるのではなく、例えば、図4に示すように槌打頭部2の両側に配置してもよい。
【0012】
このように構成した瓦固定釘Aによれば、前記凸条3が前記槌打頭部2の補強リブとして作用するため、前記槌打頭部2が金槌等の衝撃によって折曲するのを防止できる。また、金槌等で前記槌打頭部2の基端付近2aを打撃すると、前記凸条3が先に潰れて衝撃を緩和して前記槌打頭部2の基端付近2aを保護するので、前記槌打頭部2が破断するのを防止できる。また、前記杭部1と前記槌打頭部2とを鋼製の線材を屈曲することにより一体成形しているので、製造が極めて簡単である。
【0013】
更にまた、前記凸条3を前記槌打頭部2の基端付近2aに設け先端付近2bには設けていないので、前記杭部1を瓦桟等に打ち込むに際して、金槌等に対して前記槌打頭部2の基端付近2aが先端付近2bよりも相対的に高く位置することになる。このため、金槌等を多少傾けて使用しても基端付近2aのみを確実に打撃できるので、先端付近2bを不用意に打撃しないように作業員等が注意を払う必要がない。従って、当該瓦固定釘Aを用いて瓦の敷設を行えば、足場の不安定な高所においても容易に施工が行える。
【0014】
尚、上記第1の実施例では、凸条3を槌打頭部2の上面に設けたが、図5に示すように槌打頭部2の下面の幅方向の中央に設けてもよく、或いは、図6に示すように槌打頭部2の下面の両側に分けて設けてもよい。この場合、上述のように槌打頭部2を金槌等で打撃する際に凸条3が先に潰れて衝撃を緩和すること、及び、金槌等を多少傾けて使用しても槌打頭部2の基端付近2aのみを確実に打撃できるという利点は失われるが、杭部1の全長を凸条3の立上り分増加することなく槌打頭部2の撓み剛性を向上できるという利点が得られる。また、従来例と同様に杭部1の周面に沿って周溝1cを設けることにより、杭部1を瓦桟等に打ち込んだ際の摩擦力を増大して、杭部1が容易に抜けないようにしてもよい。
【0015】
次に、図7乃至図9に示すように、この発明の第2の実施例の瓦固定釘Bは、前記槌打頭部2の基端付近2aを上方へ膨出することにより基端付近2aの肉厚Tを先端付近2bよりも杭部1の打込み方向に増加する共に、基端付近2aの幅寸法Wを先端付近2bよりも減少させたものである。前記杭部1及び槌打頭部2は、上記第1の実施例と同様に、円形断面を有する線材からなる杭部1の後端部を直角に折曲することにより一体に形成されている。
【0016】
このように構成した瓦固定釘Bによれば、杭部1の打込み方向から受ける衝撃に対して高い強度を確保できるので、前記槌打頭部2が金槌等の衝撃により折曲するのを防止できる。しかも、金槌等で槌打頭部2の基端付近2aが繰り返し打撃されても、基端付近が薄く潰れて強度不足となったり破断したりすることがない。また、前記凸条3を前記槌打頭部2の基端付近2aのみを上方へ膨出しているので、上記第1の実施例と同様に、前記杭部1を瓦桟等に打ち込むに際して、金槌等に対して前記槌打頭部2の基端付近2aが先端付近2bよりも相対的に高く位置することになる。従って、槌打頭部2の先端付近2bを不用意に打撃しないように作業員等が注意を払う必要がなく、足場の不安定な高所においても容易に施工が行える。
【0017】
尚、上記第2の実施例では、槌打頭部2の基端付近2aを上方に膨出したが、槌打頭部2の下方に膨出するようにしてもよい。この場合、金槌等を多少傾けて使用しても槌打頭部2の基端付近2aのみを確実に打撃できるという利点は失われるが、杭部1の全長を基端付近2aが膨出した分増加することなく槌打頭部2の撓み剛性を向上できるという利点が得られる。また、従来例と同様に杭部1の周面に沿って周溝1cを設けることにより、杭部1を瓦桟等に打ち込んだ際の摩擦力を増大して、杭部1が容易に抜けないようにしてもよい。
【0018】
【発明の効果】
請求項1記載の瓦固定釘によれば、金槌等で打撃した際の衝撃によって槌打頭部が折曲したり破断したりするのを防止できるため、施工中に新たな瓦固定釘を打ち直す手間と時間を節約することができる。また、金槌等の打力を一層強くすることにより、瓦固定釘を瓦桟等に打込むのに要する時間を短縮することができる。更に金槌等で槌打頭部の基端付近を打撃すると、凸条が先に潰れて衝撃を緩和して槌打頭部の基端部付近を保護できる。更に又、杭部と槌打頭部とを鋼製の線材を屈曲することにより一体成形しているので、製造が極めて簡単である。加えて、凸条を槌打頭部の基端付近に設け先端付近には設けていないので、杭部を瓦桟等に打ち込むに際して、金槌等に対して槌打頭部の基端付近が先端付近より相対的に高く位置することになり、金槌等を多少傾けて使用しても基端付近のみを確実に打撃でき、容易に施工できる。
【0019】
請求項2記載の瓦固定釘によれば、杭部の打込み方向から受ける衝撃に対して高い強度を確保できるため、金槌等で打撃した際の衝撃によって槌打頭部が折曲したり破断したりすることがなく、施工中に新たな瓦固定釘を打ち直す手間と時間を節約することができる。また、金槌等の打力を一層強くすることにより、瓦固定釘を瓦桟等に打込むのに要する時間を短縮することができる。又、請求項1の瓦固定釘と同様に槌打頭部の基端付近が先端付近よりも相対的に高い位置となっているので、金槌等を多少傾けて使用しても先端付近を不用意に打撃することなく基端付近のみを確実に打撃でき、施工が容易である。
【図面の簡単な説明】
【図1】この発明の第1の実施例の瓦固定釘の側面図。
【図2】図1のa−a断面図。
【図3】図1のb−b断面図。
【図4】槌打頭部の一の変形例を示す断面図。
【図5】槌打頭部の他の変形例を示す断面図。
【図6】槌打頭部の更に他の変形例を示す断面図。
【図7】この発明の第2の実施例の瓦固定釘の要部の側面図。
【図8】図7のc−c断面図。
【図9】図7のd−d断面図。
【図10】従来例の瓦固定釘の側面図。
【図11】従来例の瓦固定釘の杭部の縦断面図。
【図12】従来例の瓦固定釘を用いて第1及び第2の瓦を固定した状態を示す斜視図。
【図13】図12の平面図。
【符号の説明】
1 杭部
2 槌打頭部
2a 基端付近
3 凸条[0001]
[Industrial applications]
The present invention relates to a tile fixing nail for fixing a tile to a tile crosspiece or the like.
[0002]
[Prior art]
As shown in FIG. 10, the tile fixing nail C of the conventional example has a
[0003]
In order to lay a tile using the above-described tile fixing nail C, the following procedure is performed. That is, as shown in FIGS. 12 and 13, first, the lower edge of the second roof tile D2 located above the first roof tile D1 is superposed on the surface side of the upper edge of the first roof tile D1. In this state, the tile fixing nail C is driven into the
[0004]
[Problems to be solved by the invention]
In the tile fixing nail C of the conventional example, the
[0005]
An object of the present invention is to provide a tile fixing nail excellent in durability.
[0006]
The tile fixing nail according to
[0007]
The roof fixing nail according to
[0008]
[Action]
According to tile locking nail according to claim 1 wherein, the protrusions provided on the upper surface near the proximal end of the hammering head acts as a reinforcing rib of the hammering head against impact received from driving direction of the pile portion High strength can be ensured.
[0009]
According to the tile fixing nail according to the second aspect, since the thickness near the base end of the hammering head bulges upward and increases in the driving direction of the pile, the impact received from the driving direction of the pile is High strength can be ensured.
[0010]
【Example】
Hereinafter, an embodiment of the tile fixing nail of the present invention will be described. The same components as those in the conventional example are denoted by the same reference numerals, and the description thereof will be omitted.
[0011]
As shown in FIG. 1, a tile fixing nail A according to a first embodiment of the present invention is configured such that a rear end portion of a
[0012]
According to the roof fixing nail A configured as described above, since the
[0013]
Furthermore, since the
[0014]
In the first embodiment, the
[0015]
Next, as shown in FIG. 7 to FIG. 9, the roof fixing nail B of the second embodiment of the present invention The thickness T of 2a is increased in the driving direction of the
[0016]
According to the tile fixing nail B configured as described above, a high strength can be secured against the impact received from the driving direction of the
[0017]
In the second embodiment, the vicinity of the
[0018]
【The invention's effect】
According to the tile fixing nail according to the first aspect, since the hammering head can be prevented from being bent or broken by an impact when hit with a hammer or the like, a new tile fixing nail is re-punched during construction. Saves time and effort. Further, by further increasing the hitting force of a hammer or the like, the time required for driving the tile fixing nail into the tile crosspiece or the like can be reduced. Further, when the vicinity of the base end of the hammering head is hit with a hammer or the like, the ridge is crushed first to reduce the impact and protect the vicinity of the base end of the hammering head. Further, since the pile portion and the hammering head are integrally formed by bending a steel wire rod, manufacturing is extremely simple. In addition, since the ridge is provided near the base end of the hammering head and not near the tip, when driving the pile into a tile bar etc. Since it is located relatively higher than the vicinity, even when a hammer or the like is used with a slight inclination, only the vicinity of the base end can be reliably hit and the construction can be easily performed.
[0019]
According to the tile fixing nail according to the second aspect, since high strength can be secured against the impact received from the driving direction of the pile, the hammering head is bent or broken by the impact when hit with a hammer or the like. This eliminates the need for reworking new tile fixing nails during construction and saves time and effort. Further, by further increasing the hitting force of a hammer or the like, the time required for driving the tile fixing nail into the tile crosspiece or the like can be reduced. Also, similar to the tile fixing nail of
[Brief description of the drawings]
FIG. 1 is a side view of a tile fixing nail according to a first embodiment of the present invention.
FIG. 2 is a sectional view taken along line aa of FIG.
FIG. 3 is a sectional view taken along line bb of FIG. 1;
FIG. 4 is a sectional view showing a modification of the hammering head.
FIG. 5 is a sectional view showing another modification of the hammering head.
FIG. 6 is a sectional view showing still another modified example of the hammering head.
FIG. 7 is a side view of a main part of a tile fixing nail according to a second embodiment of the present invention.
FIG. 8 is a sectional view taken along the line cc of FIG. 7;
FIG. 9 is a sectional view taken along line dd of FIG. 7;
FIG. 10 is a side view of a conventional tile fixing nail.
FIG. 11 is a longitudinal sectional view of a pile portion of a conventional tile fixing nail.
FIG. 12 is a perspective view showing a state in which first and second roof tiles are fixed using a conventional roof tile fixing nail.
FIG. 13 is a plan view of FIG. 12;
[Explanation of symbols]
DESCRIPTION OF
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP03873895A JP3569854B2 (en) | 1995-02-27 | 1995-02-27 | Roof fixing nail |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP03873895A JP3569854B2 (en) | 1995-02-27 | 1995-02-27 | Roof fixing nail |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH08232404A JPH08232404A (en) | 1996-09-10 |
JP3569854B2 true JP3569854B2 (en) | 2004-09-29 |
Family
ID=12533671
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP03873895A Expired - Lifetime JP3569854B2 (en) | 1995-02-27 | 1995-02-27 | Roof fixing nail |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3569854B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011162976A (en) * | 2010-02-08 | 2011-08-25 | Kmew Co Ltd | Nail and construction structure of roof material |
-
1995
- 1995-02-27 JP JP03873895A patent/JP3569854B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH08232404A (en) | 1996-09-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5010791A (en) | Shingle pry bar | |
JP3569854B2 (en) | Roof fixing nail | |
US4785488A (en) | Lever bar adapted for performing multiple functions | |
US8113488B2 (en) | Hammer and hammer head having a frontal extractor | |
KR100811381B1 (en) | Panel holding member | |
US6488266B2 (en) | Prying bar with transitional portion | |
US9377043B2 (en) | Fastening method using a nail-shaped fastening element | |
WO1992004160A1 (en) | Hand hammer | |
JP2555263B2 (en) | nail | |
US20070113515A1 (en) | Fastening member and external wall construction structure | |
KR200205747Y1 (en) | Reonforced structure of steel pipe piles | |
US20060115346A1 (en) | Easily operated nail | |
US6708461B1 (en) | Pinch clamp | |
EP0489499A1 (en) | Tile clip | |
JP4404541B2 (en) | Concrete pin | |
JP3847246B2 (en) | Scaffolding member and scaffolding device | |
US5765807A (en) | Gutter hammer | |
JP3082446U (en) | Exposed rebar cover | |
JP4592054B2 (en) | Nail with cushioning properties | |
NZ222195A (en) | Brick veneer wall tie with timber penetrating spikes | |
JP2507170B2 (en) | tile | |
KR200315919Y1 (en) | Head cover for a concrete pile | |
JP4436578B2 (en) | bar | |
JP3058749U (en) | Roof snow stopper | |
JP3034860U (en) | Attachment for driving slope anchor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20031210 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040108 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040308 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20040511 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20040610 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100702 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110702 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120702 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130702 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |