JP3548426B2 - Apparatus and method for mounting stanchion pole - Google Patents

Apparatus and method for mounting stanchion pole Download PDF

Info

Publication number
JP3548426B2
JP3548426B2 JP16203398A JP16203398A JP3548426B2 JP 3548426 B2 JP3548426 B2 JP 3548426B2 JP 16203398 A JP16203398 A JP 16203398A JP 16203398 A JP16203398 A JP 16203398A JP 3548426 B2 JP3548426 B2 JP 3548426B2
Authority
JP
Japan
Prior art keywords
stanchion pole
mounting
main body
pin
pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP16203398A
Other languages
Japanese (ja)
Other versions
JPH11350743A (en
Inventor
和弥 小澤
知宏 榎本
貫一 伊東
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Kasei Homes Corp
Original Assignee
Asahi Kasei Homes Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Kasei Homes Corp filed Critical Asahi Kasei Homes Corp
Priority to JP16203398A priority Critical patent/JP3548426B2/en
Publication of JPH11350743A publication Critical patent/JPH11350743A/en
Application granted granted Critical
Publication of JP3548426B2 publication Critical patent/JP3548426B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は鉄骨系建築工事の施工時の安全を確保するために安全ロープを張りめぐらす際に、用いられる安全治具の一種であるスタンションポールを躯体に取り付ける取付装置及びその取付方法に係り、特にピン固定方式を採用することによってスタンションポールが工具を使用せずに簡単かつ短時間で躯体に着脱することが出来る取付装置と取付方法に関するものである。
【0002】
【従来の技術】
従来のこの種のスタンションポールの取付装置は、例えば図5乃至図7(A),(B)に示す如く、所定位置に複数のボルト穴51を有する水平フランジ52と、所定位置に複数のボルト長穴53を有する垂直フランジ54、及びこれ等の両側面に設けられたほぼ3角状の側板55とよりなるアタッチメント56と、及び前記水平フランジ52上に載置し得る複数のボルト孔51を持った平板57と、この平板57の中心部に一体的に起立された棒材58とよりなるスタンションポール59とより構成されていた。
【0003】
そして、前述のアタッチメント56を躯体側の鉄骨梁60に取付固定する場合には、アタッチメント56の水平フランジ52を鉄骨梁60のフランジ60aの下面に当接すると共に、垂直フランジ54を鉄骨梁60のウェブ60bの側面に当接し、ボルト61及びナット62を介してアタッチメント56を鉄骨梁60に取付固定していた。
【0004】
また、スタンションポール59をアタッチメント56に取り付けるに当たっては、鉄骨梁60のフランジ60aより外方に突出されたアタッチメント56の水平フランジ52の先端部にスタンションポール59の平板57を載置し、両者のボルト孔51,51を相互に合致させると共に、これ等のボルト孔51,51にボルト61を挿通し、その先端部にナット62を螺合することによって、スタンションポール59をアタッチメント56に取付固定していた。
【0005】
【発明が解決しようとする課題】
然るに、前述の従来のスタンションポールの取付装置及び取付方法は、アタッチメント56と及びスタンションポール59とを夫々取付固定するに当たっては、ボルト61とナット62を必要とすると共に、ボルト締めに当たってはボルト締め等の工具を必要とする問題があった。かつ、これ等のアタッチメント56に取付固定したり、使用後にこれ等を取り外すためには、建物躯体の上階と下階とに各1人づつの作業者が必要であり、そのために作業性が悪く、しかも着脱作業に危険が伴う等の問題があった。
【0006】
本発明に係るスタンションポールの取付装置及びその取付方法は、前述の多くの問題点に鑑み開発された全く新しい技術であって、特にスタンションポールを上方から差し込んで装着する装着部を有する本体に、上下方向に伸縮可能なピン部を設け、このピン部を伸長して鉄骨梁の上下フランジに夫々設けた孔に差し込むことにより本体を鉄骨梁に着脱可能に取り付けるようにしたスタンションポールの取付装置及びその取付方法の技術を提供するものである。
【0007】
【課題を解決するための手段】
本発明に係るスタンションポールの装置は、前述の従来の問題点を根本的に改善した全く新しい技術であって、その第1発明の要旨は、鉄骨系建築物を施工する際に使用される安全用のスタンションポールの取付装置において、上方からスタンションポールを差し込んで装着する装着部を有する本体に上下方向に伸縮可能なピン部が設けられ、ピン部を伸長して各先端部を鉄骨梁の上下フランジにそれぞれ設けた孔に差し込むことにより本体を鉄骨梁に着脱可能に取り付けるようになされていることを特徴とするスタンションポールの取付装置である。
【0008】
前記第1発明のスタンションポールの装置に於いては、スタンションポールを差し込んで装着することが出来る装置部を有する本体に上下方向に伸縮可能なピン部を設けて構成したので、前記ピン部を伸長して鉄骨梁の上下フランジに夫々設けた孔に差し込むことによって、前記本体を鉄骨梁に簡単に着脱出来るように取り付けることが出来る。
【0009】
本発明に係るスタンションポールの取付装置の第2発明の要旨は、ピン部が本体から上方に突出する固定ピンと、該固定ピンにスライド可能に装着されると共に本体の下側から突出できる可動ピンを有し、該可動ピンにはスライド操作用の把手と前記突出方向に可動ピンをスプリング、自重等で押圧する押圧手段が設けられている第1発明に記載のスタンションポールの取付装置である。
【0010】
前記第2発明のスタンションポールの取付装置に於いては、前記ピン部が本体から上方に突出する固定ピンと、該固定ピンにスライド可能に装着されると共に本体の下側から突出できる可動ピンとより形成されているので、上方に突出している固定ピンは鉄骨梁の上フランジの孔に差し込み、下方に突出している可動ピンは鉄骨梁の下フランジの孔に差し込むことによって本体を鉄骨梁に簡単に、かつ1人の作業者のみで容易に取り付けることが出来る。
【0011】
また、前記本体に設けられた可動ピンにはスライド操作用の把手と前記突出方向に可動ピンをスプリング、自重等で押圧する押圧手段が設けられているので、該把手を持って可動ピンを容易に操作しながら、該可動ピンを鉄骨梁の下フランジの孔に簡単かつ確実に挿入することが出来る。
【0012】
本発明に係るスタンションポールの取付方法は、前述の従来の取付方法を根本的に改善した技術であって、その発明の要旨は、鉄骨系建築物を施工する際に使用される安全用のスタンションポールを取り付ける方法において、前記第1発明または前記第2発明に記載のスタンションポールの取付装置を使用し、そのピン部の各先端部を鉄骨梁の上下フランジにそれぞれ設けた孔に差し込と共に、本体の装着部にスタンションポールを装着することを特徴とするスタンションポールの取付方法である。
【0013】
前述のスタンションポールの取付方法は、スタンションポールを上方から差し込んで装着する装着部を有する本体に上下方向にスライドして伸縮可能なピン部を設けた取付装置を使用し、その上下のピン部の各先端部を鉄骨梁の上下フランジに設けた孔に差し込むようにしたので、ピン部を介して鉄骨梁の側部に簡単に取り付けることが出来る。
【0014】
また、この本体にはスタンションポールを上方から差し込んで装着することが出来る装着部が予め設けられており、この装着部にスタンションポールを装着するようにしたので、スタンションポールを本体に極めて簡単な方法で装着することが出来る。
【0015】
【発明の実施の形態】
図により本発明に係るスタンションポールの取付装置の一実施例を具体的に説明すると、図1は本発明に係る取付装置の斜視説明図、図2(A),(B)は夫々図1の取付装置に設けられたスタンションポールの装着部の実施例を示す側面図、図3は図1の取付装置の本体を鉄骨梁に取り付ける状態の説明図、図4は図3の取付装置の本体にスタンションポールを装着した状態の説明図である。
【0016】
本発明に係るスタンションポールの取付装置を図1により説明すると次の通りである。即ち、1はほぼ方形枠状の本体であって、鉄骨梁2の上下フランジ2a,2bの内面に当接し得る上枠3と下枠4と、これ等の上下枠3,4を結ぶ垂直枠5と及び有底の筒体6とより形成されている。また、本体1の片側面には窓15aを有する側板15が設けられている。
【0017】
7はスタンションポールであって、その下部は筒体6に挿入して装着し得るように形成されている。このスタンションポール7の上端には安全ロープを挿通出来るリング7aが設けられている。該筒体6の一部にはネジ穴8が設けられており、このネジ穴8にはロックボルト9をネジ込むことが出来、このロックボルト9の先端によって筒体6内に挿入されたスタンションポール7を締め付けすることが出来るように構成されている。
【0018】
本体1の上枠3には、鉄骨梁2の上フランジ2aに設けられた孔10に挿通することが出来る固定ピン11が起立突設されている。本体1内には、前記固定ピン11の下方に垂直枠5に沿って可動ピン用ガイド管12が設けられている。
【0019】
この可動ピン用ガイド管12内には可動ピン13が挿入されており、かつこの可動ピン13の下部は本体1の下枠4の下面より突出させ、前記鉄骨梁2の下フランジ2bの孔10に挿通し得るように構成されている。前記可動ピン用ガイド管12内にはスプリング(図示せず)が内蔵されており、このスプリングで可動ピン13を下方向に付勢している。可動ピン13の側面にはレバーハンドル14が突設されている。
【0020】
本体1に設けられる筒体6は、図2(A)に示す如く、対応する位置にある垂直枠5の高さとほぼ等しい高さに形成することも、或いは同図(B)に示す上枠3より上方に突出させ、即ち、筒体6の長さをより大きく構成することも可能である。
【0021】
前述のスタンションポールの取付装置を鉄骨梁2に取り付ける操作について説明すると次の通りである。即ち、図3及び図4に示す如く、本体1の側板15の窓15aに指先を挿入しながら片手で持ち、かつ他方で手でレバーハンドル14を操作して可動ピン13を押し上げながら鉄骨梁2の上下フランジ2a,2b間に本体1を挿入し、上方に突出した固定ピン11を上フランジ2aの孔10内に挿通する。
【0022】
次にレバーハンドル14を操作して可動ピン13を下方に伸ばしながら、その可動ピン13の下端部を下フランジ2bの孔10に挿通して、本体1を鉄骨梁2の側方に取付固定する。その後で、筒体6の上方からスタンションポール7の下部を挿入し、ロックボルト9をネジ穴8にネジ込んで、その先端部でスタンションポール7を締め付けることによってスタンションポール7を筒体6に固定して本体1に取り付けることが出来る。
【0023】
前述のように、本発明に係る取付装置は、本体1の上部のピンを固定ピン11としたので、仮に鉄骨梁2の上フランジ2aより突出した固定ピン11の上部を作業者が踏みつけても、動かないようにすることが出来る。そして下部のピンを可動ピン13で構成している。
【0024】
また、前記可動ピン13は可動ピン用ガイド管12に内蔵されたスプリングによって、レバーハンドル14を操作しない限りは動かないように構成されている。前述の実施例に於いては、可動ピン用ガイド管12にスプリングを内蔵させて、このスプリングの作用で可動ピン13を下方向に付勢したが、スプリングを使用せずに、可動ピン13の自重を利用して下方向に不勢したり、或いは可動ピン用ガイド管12の周壁に設けた縦溝及び横溝(図示せず)を利用することによって、可動ピン13を伸縮させることも可能である。
【0025】
前述の本体1を鉄骨梁2に着脱するに当たっては、その上部の固定ピン11を上フランジ2aの孔10に差し込んだ後で、この固定ピン11を軸にして回転させながら着脱するので、本体1の垂直枠5を下枠4とで形成するコーナー部をR形状とした方がより効果的である。
【0026】
本発明に係る取付装置を使用した場合には、この取付装置を取り付ける際にボルト及びナットが全く不要である。従って、ボルトを締め付ける工具等も必要としない。更に本体1を鉄骨梁2に取り付ける場合には、レバーハンドル14の操作のみで施工することが出来るので、1人の作業員で簡単かつ安全に、しかも短時間で作業を行うことが出来る。
【0027】
【発明の効果】
本発明に係るスタンションポールの取付装置及びその取付方法は、前述のような構成と作用とを有するので、スタンションポールの取付装置を躯体側に簡単に取り付けたり、或いは取り外したりすることが出来る。
【0028】
また、スタンションポールの取付装置の着脱作業は1人の作業員が短時間の作業で行うことが出来る。かつボルト締付工具等の工具を一切使用することなく施工することが出来る。従って、施工性能を著しく向上させることが出来ると共に、作業員の安全性を確保することが出来る等の特徴を有するものである。
【図面の簡単な説明】
【図1】本発明に係る取付装置の斜視説明図である。
【図2】図2(A)、(B)は夫々図1の取付装置に設けられたスタンションポールの装着部の実施例を示す側面図である。
【図3】図1の取付装置の本体を鉄骨梁に取り付ける状態の説明図である。
【図4】図3の取付装置の本体にスタンションポールを装着した状態の説明図である。
【図5】従来のスタンンションポール用のアタッチメントを示す説明図である。
【図6】従来のスタンションポールの構成を示す説明図である。
【図7】図7(A),(B)は前記アタッチメント及びスタンションポールの取付状態を示す説明図である。
【符号の説明】
1 本体
2 鉄骨梁
2a 上フランジ
2b 下フランジ
3 上枠
4 下枠
5 垂直枠
6 筒体
7 スタンションポール
8 ネジ穴
9 ロックボルト
10 孔
11 固定ピン
12 可動ピン用ガイド管
13 可動ピン
14 レバーハンドル
15 側板
15a 窓
51 ボルト穴
52 水平フランジ
53 ボルト長穴
54 垂直フランジ
55 側板
56 アタッチメント
57 平板
58 棒材
59 スタンションポール
60 鉄骨梁
61 ボルト
62 ナット
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a mounting device and a mounting method for mounting a stanchion pole, which is a kind of a safety jig, to a skeleton when a safety rope is stretched in order to secure safety during construction of a steel-based building construction, and in particular, The present invention relates to a mounting device and a mounting method in which a stanchion pole can be easily and quickly attached to and detached from a body without using a tool by employing a pin fixing method.
[0002]
[Prior art]
A conventional stanchion pole mounting device of this type includes a horizontal flange 52 having a plurality of bolt holes 51 at predetermined positions and a plurality of bolts at predetermined positions as shown in FIGS. 5 to 7A and 7B. An attachment 56 consisting of a vertical flange 54 having an elongated hole 53 and substantially triangular side plates 55 provided on both side surfaces thereof, and a plurality of bolt holes 51 which can be placed on the horizontal flange 52 are provided. A stanchion pole 59 made up of a flat plate 57 having the same, and a bar member 58 erected integrally at the center of the flat plate 57.
[0003]
When the above-mentioned attachment 56 is attached and fixed to the steel beam 60 on the skeleton side, the horizontal flange 52 of the attachment 56 is in contact with the lower surface of the flange 60 a of the steel beam 60, and the vertical flange 54 is connected to the web of the steel beam 60. The attachment 56 is attached and fixed to the steel beam 60 via the bolt 61 and the nut 62 while being in contact with the side surface of the steel beam 60b.
[0004]
When attaching the stanchion pole 59 to the attachment 56, the flat plate 57 of the stanchion pole 59 is placed on the tip of the horizontal flange 52 of the attachment 56 projecting outward from the flange 60a of the steel beam 60, and both bolts The stanchion pole 59 is attached and fixed to the attachment 56 by aligning the holes 51, 51 with each other, inserting a bolt 61 into the bolt holes 51, 51, and screwing a nut 62 into the tip end. Was.
[0005]
[Problems to be solved by the invention]
However, the above-described conventional stanchion pole mounting apparatus and mounting method require the bolts 61 and the nuts 62 to mount and fix the attachment 56 and the stanchion pole 59, respectively. There was a problem that required tools. In addition, in order to attach and fix these attachments 56 and to remove them after use, one worker is required on each of the upper floor and the lower floor of the building frame, and therefore, workability is increased. There was a problem that it was bad and that the attaching / detaching operation was dangerous.
[0006]
The mounting device and the mounting method of the stanchion pole according to the present invention is a completely new technology developed in view of the above-mentioned many problems, particularly, a main body having a mounting portion for mounting by inserting the stanchion pole from above, A stanchion pole mounting device in which a vertically extensible pin portion is provided, and the main body is detachably attached to the steel beam by extending the pin portion and inserting the pin portion into holes provided in upper and lower flanges of the steel beam, and The technique of the attachment method is provided.
[0007]
[Means for Solving the Problems]
The stanchion pole device according to the present invention is a completely new technology that fundamentally improves the above-mentioned conventional problems, and the gist of the first invention is the safety used when constructing a steel frame building. In a stanchion pole mounting device, a main body having a mounting portion into which a stanchion pole is inserted from above is provided with a vertically expandable and contractible pin portion, and the tip portion is extended to extend each tip portion up and down of a steel beam. A stanchion pole mounting device characterized in that a main body is detachably mounted on a steel beam by being inserted into holes provided in respective flanges.
[0008]
In the stanchion pole device according to the first aspect of the present invention, the main body having the device portion into which the stanchion pole can be inserted and mounted is provided with a vertically extensible pin portion. Then, the main body can be attached to the steel beam so that it can be easily attached and detached by inserting the main body into the holes provided in the upper and lower flanges of the steel beam.
[0009]
The gist of the second invention of the stanchion pole mounting device according to the present invention is that a fixed pin whose pin portion protrudes upward from the main body, and a movable pin that is slidably mounted on the fixed pin and protrudes from the lower side of the main body. The stanchion pole mounting device according to the first invention, wherein the movable pin is provided with a handle for sliding operation and a pressing means for pressing the movable pin in the projecting direction by a spring, its own weight or the like.
[0010]
In the mounting device for a stanchion pole according to the second aspect of the present invention, the pin portion includes a fixing pin projecting upward from the main body, and a movable pin slidably mounted on the fixing pin and protruding from the lower side of the main body. Since the fixed pin protruding upward is inserted into the hole of the upper flange of the steel beam, the movable pin protruding downward is inserted into the hole of the lower flange of the steel beam, so that the main body can be easily inserted into the steel beam, And it can be easily attached by only one worker.
[0011]
Further, the movable pin provided on the main body is provided with a handle for sliding operation and a pressing means for pressing the movable pin in the protruding direction by a spring, its own weight or the like, so that the movable pin can be easily held by holding the handle. The movable pin can be easily and securely inserted into the hole of the lower flange of the steel beam while operating.
[0012]
The method of mounting a stanchion pole according to the present invention is a technique which is a fundamental improvement of the above-described conventional mounting method, and the gist of the invention is a safety stanchion used when constructing a steel-framed building. In the method of mounting the pole, using the stanchion pole mounting apparatus according to the first invention or the second invention, each tip of the pin portion is inserted into holes provided in upper and lower flanges of the steel beam, respectively, A stanchion pole is attached to a mounting portion of a main body.
[0013]
The mounting method of the above-mentioned stanchion pole uses a mounting device provided with a pin portion which can be extended and contracted by sliding vertically in a main body having a mounting portion in which the stanchion pole is inserted from above and mounted. Since each tip is inserted into the hole provided in the upper and lower flanges of the steel beam, it can be easily attached to the side of the steel beam via the pin portion.
[0014]
In addition, this body is provided with a mounting part in which a stanchion pole can be inserted from above and mounted. The stanchion pole is mounted on this mounting part, so the stanchion pole can be attached to the main body in a very simple way. Can be installed with
[0015]
BEST MODE FOR CARRYING OUT THE INVENTION
FIG. 1 is a perspective view of a mounting device according to the present invention, and FIGS. 2A and 2B are perspective views of the mounting device according to the present invention. FIG. 3 is a side view showing an embodiment of a mounting portion of the stanchion pole provided on the mounting device, FIG. 3 is an explanatory view showing a state where the main body of the mounting device of FIG. 1 is mounted on a steel beam, and FIG. It is explanatory drawing of the state which mounted the stanchion pole.
[0016]
The stanchion pole mounting device according to the present invention will be described below with reference to FIG. That is, reference numeral 1 denotes a substantially rectangular frame-shaped main body, which is an upper frame 3 and a lower frame 4 which can contact the inner surfaces of the upper and lower flanges 2a and 2b of the steel beam 2, and a vertical frame connecting these upper and lower frames 3 and 4. 5 and a bottomed cylindrical body 6. A side plate 15 having a window 15a is provided on one side surface of the main body 1.
[0017]
Reference numeral 7 denotes a stanchion pole, the lower portion of which is formed so as to be inserted into and attached to the cylindrical body 6. A ring 7a through which a safety rope can be inserted is provided at the upper end of the stanchion pole 7. A screw hole 8 is provided in a part of the cylindrical body 6, and a lock bolt 9 can be screwed into the screw hole 8, and the stanchion inserted into the cylindrical body 6 by the tip of the lock bolt 9. It is configured such that the pole 7 can be tightened.
[0018]
On the upper frame 3 of the main body 1, a fixing pin 11 that can be inserted into a hole 10 provided in the upper flange 2a of the steel beam 2 is provided to stand up. A movable pin guide tube 12 is provided in the main body 1 along the vertical frame 5 below the fixed pin 11.
[0019]
A movable pin 13 is inserted into the movable pin guide tube 12, and a lower portion of the movable pin 13 projects from a lower surface of the lower frame 4 of the main body 1, and a hole 10 of the lower flange 2 b of the steel beam 2 is formed. It is configured so that it can be inserted through. A spring (not shown) is built in the movable pin guide tube 12, and the spring biases the movable pin 13 downward. A lever handle 14 protrudes from a side surface of the movable pin 13.
[0020]
The cylindrical body 6 provided in the main body 1 may be formed at a height substantially equal to the height of the vertical frame 5 at the corresponding position as shown in FIG. 2 (A), or the upper frame shown in FIG. 2 (B). It is also possible to protrude above 3, that is, to make the length of the cylinder 6 larger.
[0021]
The operation of attaching the above-described stanchion pole attachment device to the steel beam 2 will be described below. That is, as shown in FIGS. 3 and 4, while holding a fingertip into the window 15 a of the side plate 15 of the main body 1 while holding it with one hand, and operating the lever handle 14 with the other hand to push up the movable pin 13, the steel beam 2 The main body 1 is inserted between the upper and lower flanges 2a and 2b, and the fixing pins 11 protruding upward are inserted into the holes 10 of the upper flange 2a.
[0022]
Next, while operating the lever handle 14 to extend the movable pin 13 downward, the lower end of the movable pin 13 is inserted into the hole 10 of the lower flange 2b to attach and fix the main body 1 to the side of the steel beam 2. . Thereafter, the lower part of the stanchion pole 7 is inserted from above the cylinder 6, the lock bolt 9 is screwed into the screw hole 8, and the stanchion pole 7 is fixed to the cylinder 6 by tightening the stanchion pole 7 at the tip. And can be attached to the main body 1.
[0023]
As described above, in the mounting device according to the present invention, since the upper pin of the main body 1 is the fixing pin 11, even if the operator steps on the upper portion of the fixing pin 11 protruding from the upper flange 2 a of the steel beam 2. , Can be immobile. The lower pin is constituted by the movable pin 13.
[0024]
Further, the movable pin 13 is configured not to move unless a lever handle 14 is operated by a spring built in the movable pin guide tube 12. In the above-described embodiment, a spring is built in the movable pin guide tube 12, and the movable pin 13 is urged downward by the action of the spring. The movable pin 13 can be expanded and contracted by utilizing its own weight to be depressed downward, or by using a vertical groove and a horizontal groove (not shown) provided on the peripheral wall of the movable pin guide tube 12. is there.
[0025]
When attaching and detaching the main body 1 to and from the steel beam 2, the upper fixing pin 11 is inserted into the hole 10 of the upper flange 2a, and then the main body 1 is attached and detached while rotating about the fixing pin 11 as an axis. It is more effective to make the corner formed by the vertical frame 5 and the lower frame 4 into an R shape.
[0026]
When the mounting device according to the present invention is used, no bolts and nuts are required when mounting the mounting device. Therefore, no tools or the like for tightening bolts are required. Further, when the main body 1 is attached to the steel beam 2, the work can be performed only by operating the lever handle 14, so that one worker can perform the work easily, safely, and in a short time.
[0027]
【The invention's effect】
Since the stanchion pole mounting device and the mounting method according to the present invention have the above-described configuration and operation, the stanchion pole mounting device can be easily mounted on or removed from the skeleton side.
[0028]
Also, the attachment and detachment of the mounting device for the stanchion pole can be performed by one worker in a short time. And it can be installed without using any tools such as bolt tightening tools. Therefore, the construction performance can be remarkably improved, and the safety of workers can be ensured.
[Brief description of the drawings]
FIG. 1 is an explanatory perspective view of a mounting device according to the present invention.
2 (A) and 2 (B) are side views showing an embodiment of a mounting portion of a stanchion pole provided in the mounting device of FIG. 1, respectively.
FIG. 3 is an explanatory view of a state in which a main body of the mounting device of FIG. 1 is mounted on a steel beam.
FIG. 4 is an explanatory view of a state in which a stanchion pole is mounted on a main body of the mounting device of FIG. 3;
FIG. 5 is an explanatory view showing a conventional attachment for a stanchion pole.
FIG. 6 is an explanatory view showing a configuration of a conventional stanchion pole.
FIGS. 7A and 7B are explanatory views showing the attachment state of the attachment and the stanchion pole.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Main body 2 Steel beam 2a Upper flange 2b Lower flange 3 Upper frame 4 Lower frame 5 Vertical frame 6 Cylindrical body 7 Stantion pole 8 Screw hole 9 Lock bolt 10 Hole 11 Fixed pin 12 Movable pin guide tube 13 Movable pin 14 Lever handle 15 Side plate 15a Window 51 Bolt hole 52 Horizontal flange 53 Bolt long hole 54 Vertical flange 55 Side plate 56 Attachment 57 Flat plate 58 Bar material 59 Stantion pole 60 Steel beam 61 Bolt 62 Nut

Claims (3)

鉄骨系建築物を施工する際に使用される安全用のスタンションポールの取付装置において、上方からスタンションポールを差し込んで装着する装着部を有する本体に上下方向に伸縮可能なピン部が設けられ、ピン部を伸長して各先端部を鉄骨梁の上下フランジにそれぞれ設けた孔に差し込むことにより本体を鉄骨梁に着脱可能に取り付けるようになされていることを特徴とするスタンションポールの取付装置。In a mounting device of a stanchion pole for safety used when constructing a steel-based building, a pin portion that is vertically expandable and contractible is provided on a main body having a mounting portion for inserting and mounting a stanchion pole from above, An installation device for a stanchion pole, characterized in that the body is detachably attached to the steel beam by extending the portion and inserting each end into holes provided in upper and lower flanges of the steel beam. ピン部が本体から上方に突出する固定ピンと、該固定ピンにスライド可能に装着されると共に本体の下側から突出できる可動ピンを有し、該可動ピンにはスライド操作用の把手と前記突出方向に可動ピンを押圧する押圧手段が設けられている請求項1に記載のスタンションポールの取付装置。A pin portion has a fixed pin projecting upward from the main body, and a movable pin slidably mounted on the fixed pin and capable of projecting from a lower side of the main body. 2. The stanchion pole mounting device according to claim 1, further comprising a pressing means for pressing the movable pin. 鉄骨系建築物を施工する際に使用される安全用のスタンションポールを取り付ける方法において、請求項1または請求項2に記載のスタンションポールの取付装置を使用し、そのピン部の各先端部を鉄骨梁の上下フランジにそれぞれ設けた孔に差し込と共に、本体の装着部にスタンションポールを装着することを特徴とするスタンションポールの取付方法。In a method of mounting a safety stanchion pole used when constructing a steel-frame building, the stanchion pole mounting device according to claim 1 or 2 is used, and each tip of the pin portion is formed of a steel frame. A method of mounting a stanchion pole, wherein the stanchion pole is mounted on a mounting portion of a main body while being inserted into holes provided in upper and lower flanges of a beam.
JP16203398A 1998-06-10 1998-06-10 Apparatus and method for mounting stanchion pole Expired - Lifetime JP3548426B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16203398A JP3548426B2 (en) 1998-06-10 1998-06-10 Apparatus and method for mounting stanchion pole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16203398A JP3548426B2 (en) 1998-06-10 1998-06-10 Apparatus and method for mounting stanchion pole

Publications (2)

Publication Number Publication Date
JPH11350743A JPH11350743A (en) 1999-12-21
JP3548426B2 true JP3548426B2 (en) 2004-07-28

Family

ID=15746813

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16203398A Expired - Lifetime JP3548426B2 (en) 1998-06-10 1998-06-10 Apparatus and method for mounting stanchion pole

Country Status (1)

Country Link
JP (1) JP3548426B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4854306B2 (en) * 2006-01-17 2012-01-18 旭化成ホームズ株式会社 Master rope attachment device
JP2010185185A (en) * 2009-02-10 2010-08-26 Sekisui House Ltd Temporary handrail and its construction method
JP6188544B2 (en) * 2013-11-06 2017-08-30 トヨタホーム株式会社 Prop support device
JP6406577B2 (en) * 2014-12-04 2018-10-17 キョーワ株式会社 jig
KR102027572B1 (en) * 2018-02-14 2019-10-01 박정윤 Handrail guide-fastening device for mold

Also Published As

Publication number Publication date
JPH11350743A (en) 1999-12-21

Similar Documents

Publication Publication Date Title
US5918843A (en) Scaffold bracket
JP3548426B2 (en) Apparatus and method for mounting stanchion pole
JP3751708B2 (en) Curing scaffold plate support assembly
KR20090122078A (en) Toe board of gang form workbench for architecture
JP3068799B2 (en) Scaffolding connection structure
JP2009174199A (en) Step fitting for tower pole
JP6694774B2 (en) Scaffolding for scaffolding
JP4250073B2 (en) Level adjustment jig
KR20150010900A (en) Sockets for construction materials support including cast and system support using thereof
JP4318788B2 (en) Anchor bolt installation method
JPH071426Y2 (en) Hollow scaffolding support hardware
KR102304974B1 (en) Portable multi-tensioning device
KR100460231B1 (en) Safety Working Foothold for a Line Scaffold
JPH04106267A (en) Form device of column
JPH0736004Y2 (en) Hollow scaffolding support hardware
JP4321947B2 (en) Ladder equipment
JPH0711236Y2 (en) Scaffolding equipment
JP2560863Y2 (en) Walkway fixtures
JPH0738567Y2 (en) Parent rope
CN206500814U (en) Workpiece locating mechanism
JPH07331862A (en) Handrail for workbench
JPH071425Y2 (en) Hollow scaffolding support hardware
JP3212548B2 (en) Ladder mounting device
JP2587333Y2 (en) Work scaffold mountings
JPH0715218B2 (en) Scaffold construction method and scaffolding equipment

Legal Events

Date Code Title Description
RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20031217

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040114

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040203

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040413

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040416

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080423

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090423

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090423

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100423

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110423

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110423

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120423

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120423

Year of fee payment: 8

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120423

Year of fee payment: 8

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120423

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130423

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130423

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140423

Year of fee payment: 10

EXPY Cancellation because of completion of term