JP3412153B2 - Hoisting equipment - Google Patents

Hoisting equipment

Info

Publication number
JP3412153B2
JP3412153B2 JP36975099A JP36975099A JP3412153B2 JP 3412153 B2 JP3412153 B2 JP 3412153B2 JP 36975099 A JP36975099 A JP 36975099A JP 36975099 A JP36975099 A JP 36975099A JP 3412153 B2 JP3412153 B2 JP 3412153B2
Authority
JP
Japan
Prior art keywords
wire
main winding
winding wire
load
jib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP36975099A
Other languages
Japanese (ja)
Other versions
JP2001180885A (en
Inventor
和洋 飛田
Original Assignee
日立プラント建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日立プラント建設株式会社 filed Critical 日立プラント建設株式会社
Priority to JP36975099A priority Critical patent/JP3412153B2/en
Publication of JP2001180885A publication Critical patent/JP2001180885A/en
Application granted granted Critical
Publication of JP3412153B2 publication Critical patent/JP3412153B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、建設現場において
重量物の昇降作業に使用する巻上装置に関する。
The present invention relates to relates to a hoisting apparatus for use in lifting a heavy object in a construction site.

【0002】[0002]

【従来の技術】従来、火力発電所の建設現場などにおい
ては、一般にジブクレーンを使用して重量物の昇降作業
を行っている。ジブクレーンは、重量物を吊上げる主巻
ワイヤを有している。前記主巻ワイヤには、重量物に連
結するためのフックを先端部に設けている。また、ジブ
クレーンには、補巻ワイヤを有するものがある。この補
巻ワイヤは、先端を主巻ワイヤのフックに連結し、クレ
ーンの不使用時に、フックをブーム(ジブ)の先端部に
固定するために使用される。
2. Description of the Related Art Conventionally, at a construction site of a thermal power plant or the like, a jib crane is generally used for lifting and lowering heavy objects. The jib crane has a main winding wire for hoisting heavy objects. The main winding wire is provided with a hook at its tip for connecting to a heavy load. Further, some jib cranes have auxiliary winding wires. This auxiliary winding wire is used for connecting the tip to the hook of the main winding wire and for fixing the hook to the tip portion of the boom (jib) when the crane is not used.

【0003】このようなジブクレーンにより、火力発電
所のボイラなどを組立てる場合、格子状に組んだ鉄骨建
屋の上にジブクレーンを設置し、建屋の格子状に組んだ
鉄骨の間(桝目)から主巻ワイヤを挿入して、フックに
重量物を連結する。そして、主巻ワイヤを巻き上げてフ
ックに取付けられた重量物を吊上げるのである。
When assembling a boiler or the like of a thermal power plant with such a jib crane, the jib crane is installed on a steel frame building assembled in a grid shape, and main windings are made between the steel frames assembled in the grid shape of the building (cells). Insert wires and connect heavy items to hooks. Then, the main winding wire is rolled up to lift the heavy object attached to the hook.

【0004】[0004]

【発明が解決しようとする課題】従来においては、以下
のような問題点があった。上記したように鉄骨組みした
建屋内において重量物を昇降する場合、格子状に組まれ
た鉄骨の間隔に余裕がなく、シーブを使用できない箇所
もあるため、従来は一本の主巻ワイヤで昇降作業を行う
のが一般的である。従って、クレーンの吊上げ荷重は、
主巻ワイヤに部材の荷重が直接かかるため、主巻ワイヤ
の許容荷重により制限されてしまう。
In the past, there have been the following problems. As described above, when lifting or lowering heavy objects in a steel framed building, since there is no space in the lattice-shaped steel frames and there are places where sheaves cannot be used, the conventional method is to use a single main winding wire to move up and down. It is common to work. Therefore, the lifting load of the crane is
Since the load of the member is directly applied to the main winding wire, it is limited by the allowable load of the main winding wire.

【0005】しかし、建設現場においては、大型構造物
の組立などの際に、主巻ワイヤの許容荷重よりも重い重
量物を吊上げたい場合がある。このような場合、主巻ワ
イヤの径を大きくすることで主巻ワイヤの許容荷重を増
加させることが考えられるが、主巻ワイヤの径を大きく
すると主巻ワイヤを巻き取るウインチのドラム径も大き
くなってしまう。このため、主巻ワイヤの径を変えると
現状使用しているウインチの交換が必要となってしま
う。これは、クレーン全体に対する改造が必要となって
しまうため、コスト負担が非常に大きくなり現実的では
ない。
However, at the construction site, when assembling a large structure, it is sometimes desired to lift a heavy object that is heavier than the allowable load of the main winding wire. In such a case, increasing the diameter of the main winding wire may increase the allowable load of the main winding wire. However, increasing the diameter of the main winding wire also increases the drum diameter of the winch that winds the main winding wire. turn into. Therefore, if the diameter of the main winding wire is changed, it is necessary to replace the winch that is currently used. This is not realistic because the cost burden becomes very large because the whole crane needs to be modified.

【0006】ところで、動滑車を使用して主巻ワイヤを
2本がけにすれば許容荷重を2倍にできる。そして、前
記した補巻ワイヤによって主巻ワイヤの先端部を支持し
て主巻ワイヤをループ化し、主巻ワイヤを2本がけにす
ることが考えられる。ところが、補巻ワイヤの許容荷重
は、例えば主巻ワイヤの許容荷重が20トンである場
合、1.5トン程度と主巻ワイヤの10分の1以下であ
り、重量物を支持することができない。
By the way, the allowable load can be doubled by using a moving pulley to cover two main winding wires. Then, it is conceivable that the main winding wire is looped by supporting the tip end portion of the main winding wire by the auxiliary winding wire described above, and the main winding wire is made into two bars. However, when the allowable load of the main winding wire is 20 tons, the allowable load of the auxiliary winding wire is about 1.5 tons, which is one tenth or less of that of the main winding wire, and cannot support a heavy load. .

【0007】そこで従来は、建屋の鉄骨に主巻ワイヤの
先端を連結してループ化し、これに吊り具を取付けて主
巻ワイヤを実質的に2本掛けとすることにより、主巻ワ
イヤの許容荷重より大きな重量物を吊上げるようにして
いる。しかし、このような場合、建屋の外に配置した重
量物を吊上げるときには適用できない。また、建屋の内
に配置した重量物を吊上げる場合においても、主巻ワイ
ヤの先端を連結した位置までしか揚程をとることができ
ない。従って、主巻ワイヤ先端部の連結位置より上方の
ジブの高さが無駄となる。
[0007] Therefore, conventionally, the main winding wire is permitted by connecting the tip of the main winding wire to a steel frame of a building to form a loop, and attaching a hanging tool to this to substantially hang the main winding wire. A heavy object that is larger than the load is hoisted. However, in such a case, it cannot be applied when lifting a heavy object placed outside the building. Further, even when a heavy object placed inside the building is hoisted, the lifting height can be taken only up to the position where the tip of the main winding wire is connected. Therefore, the height of the jib above the connecting position of the tip of the main winding wire is wasted.

【0008】一方、従来の吊り具においては、ワイヤを
巻きかけるプーリと、重量物を掛止するフックとが一体
化していた。このためワイヤをループ化する前に、吊り
具にワイヤを通す必要があり脱着が不便であった。ま
た、ループ化したワイヤに、吊り具を後付けする要望が
発生していた。
On the other hand, in the conventional hanging device, the pulley around which the wire is wound and the hook for hanging the heavy object are integrated. For this reason, it was necessary to pass the wire through the hanger before looping the wire, which was inconvenient to attach and detach. Further, there has been a demand for retrofitting a suspender to the looped wire.

【0009】本発明の目的は、本体部を変更することな
く揚重量を増大させることができるとともに、十分な揚
程を確保することのできる巻上装置を提供することに
る。
An object of the present invention, it is possible to increase the lifting weight without changing the main body portion, Oh to provide a hoisting device which can ensure sufficient lift
It

【0010】[0010]

【課題を解決するための手段】本発明における巻上装置
においては、本体部から吊下げられて重量物を昇降させ
る荷吊りワイヤと、前記荷吊りワイヤの先端部に着脱可
能に結合される連結部材と、前記本体部から吊下げされ
て前記連結部材に結合され、連結部材を昇降させる連結
ワイヤと、前記本体部に設けられ、前記連結ワイヤによ
り吊上げられた前記連結部材を係止する係止部と、を有
する構成とした。
In the hoisting device according to the present invention, a load suspending wire for suspending and lifting a heavy object from a main body and a connection detachably coupled to the tip end of the load suspending wire. A member, a connecting wire that is suspended from the main body part and connected to the connecting member, and that raises and lowers the connecting member, and a lock that locks the connecting member that is provided on the main body part and that is hung by the connecting wire. And a part.

【0011】上記構成においては、連結ワイヤに取付け
られた連結部材を、荷吊りワイヤの先端部に連結するこ
とにより、荷吊りワイヤを連結ワイヤと一体的に移動で
きる。次に、荷吊りワイヤに連結した連結部材を、連結
ワイヤを巻き取ることで上昇させる。そして、本体部に
設けた係止部に前記連結部を係止させ、荷吊りワイヤの
先端側の支持を連結ワイヤから係止部に切り替える。こ
れにより、荷吊りワイヤを本体部にてループ化すること
ができるため、吊り具についての2本掛けが可能とな
り、許容荷重を倍増させることができる。また、荷吊り
ワイヤの先端部を本体部に連結してループ化することに
より、荷吊りワイヤの揚程を本体部の高さまで確保させ
ることができる。
In the above structure, the load-hanging wire can be moved integrally with the connecting wire by connecting the connecting member attached to the connecting wire to the tip of the load-hanging wire. Next, the connecting member connected to the load hanging wire is raised by winding the connecting wire. Then, the connecting portion is locked to the locking portion provided on the main body, and the support of the tip end side of the load hanging wire is switched from the connecting wire to the locking portion. As a result, the load-hanging wire can be looped in the main body portion, so that it is possible to hang two pieces of the hanging device, and the allowable load can be doubled. Further, by connecting the distal end portion of the load hanging wire to the main body to form a loop, the lifting height of the load hanging wire can be secured up to the height of the main body.

【0012】また、係止部は、前記連結部材に形成した
ピン孔に挿入する係止ピンと、遠隔操作により前記係止
ピンを軸方向に移動し、前記連結部材の係脱をするアク
チュエータとを有する構成とすることができる。
The locking portion includes a locking pin to be inserted into a pin hole formed in the connecting member, and an actuator for axially moving the locking pin by remote operation to engage and disengage the connecting member. It can be configured to have.

【0013】上記構成においては、アクチュエータによ
り係止部の係止ピンを連結部材に形成したピン孔に遠隔
操作で挿入することができる。このため、連結部材の係
止部への係止作業を空中において行うことができる。ま
た、前記係止部は、前記連結部材の側部に設けた位置決
め凸部と係合する係合凹部と、この係合凹部に連続して
形成され、前記位置決め凸部を係合凹部に案内するガイ
ド部とを有する構成とすることができる。
In the above structure, the locking pin of the locking portion can be remotely inserted by the actuator into the pin hole formed in the connecting member. Therefore, the work of locking the connecting member to the locking portion can be performed in the air. Further, the locking portion is formed continuously with the engaging concave portion that engages with the positioning convex portion provided on the side portion of the coupling member, and guides the positioning convex portion to the engaging concave portion. It can be configured to have a guide portion that operates.

【0014】上記構成においては、連結部材を係止部に
係止させる際に、ガイド部により位置決め凸部を係合凹
部に確実に案内することができ、連結部材の位置決め凸
部を係合凹部に沿って挿入させることで連結部材のピン
孔と係止ピンとの位置合わせが容易となる。従って、係
止ピンをピン孔に確実に挿入することができる。
In the above structure, when the connecting member is locked to the locking portion, the positioning convex portion can be reliably guided to the engaging concave portion by the guide portion, and the positioning convex portion of the connecting member is engaged to the engaging concave portion. By aligning the pin hole of the connecting member with the engaging pin, the position of the engaging pin can be easily adjusted. Therefore, the locking pin can be reliably inserted into the pin hole .

【0015】[0015]

【0016】[0016]

【発明の実施の形態】本発明の実施形態について、図面
に従って詳細に説明する。図1は本実施形態に係る巻上
装置であるジブクレーンの側面図である。図2、図3は
本実施形態におけるジブクレーンの工程説明図である。
図4は本実施形態におけるプラグ部材の説明図である。
図5、図6はソケット部材の説明図である。図7、図8
はそれぞれ本実施形態における吊り具の正面図及び側面
図である。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a side view of a jib crane which is a hoisting device according to this embodiment. 2 and 3 are process explanatory diagrams of the jib crane according to the present embodiment.
FIG. 4 is an explanatory diagram of the plug member in this embodiment.
5 and 6 are explanatory views of the socket member. 7 and 8
3A and 3B are a front view and a side view, respectively, of the suspender in the present embodiment.

【0017】本実施形態においては、火力発電所の建設
現場に使用するジブクレーンの許容荷重を増加する場合
について説明する。本実施形態においては、ジブクレー
ンの荷吊りワイヤである主巻ワイヤの先端部を、本体部
であるジブに連結してループ化することにより許容荷重
を増加させるのである。
In this embodiment, the case where the allowable load of a jib crane used at a construction site of a thermal power plant is increased will be described. In the present embodiment, the allowable load is increased by connecting the tip end of the main winding wire, which is the load suspending wire of the jib crane, to the jib, which is the main body, to form a loop.

【0018】図1に示すように、ジブクレーン1は、ベ
ース10に本体部をなすジブ12を基端部にて枢設して
いる。前記ジブ12の先端部には、ジブプーリ13が回
動可能に取付けられており、当該ジブプーリ13に荷吊
りワイヤである主巻ワイヤ14を巻きかけている。前記
主巻ワイヤ14の基端側は、前記ジブ12の後方側に設
置された主巻ウインチ16に巻き取られている。前記主
巻ワイヤ14の先端側は、前記ジブプーリ13の先端か
ら吊下げられている。これにより、主巻ワイヤ14はジ
ブ12の起伏に従って昇降するのである。本実施形態に
おける主巻ワイヤ14は、例えば20トン程度の吊下げ
荷重のものを想定している。
As shown in FIG. 1, the jib crane 1 has a base 10 on which a jib 12 forming a main body is pivoted at its base end. A jib pulley 13 is rotatably attached to the tip of the jib 12, and a main winding wire 14 that is a load-hanging wire is wound around the jib pulley 13. The base end side of the main winding wire 14 is wound around a main winding winch 16 installed on the rear side of the jib 12. The tip side of the main winding wire 14 is suspended from the tip of the jib pulley 13. As a result, the main winding wire 14 moves up and down according to the ups and downs of the jib 12. The main winding wire 14 in the present embodiment is assumed to have a hanging load of, for example, about 20 tons.

【0019】前記主巻ワイヤ14の先端部に主巻フック
28を設けている。前記主巻フック28は、図4(a)
に示すように、先細りした直方形状の板状に形成してあ
る。このようにすることで、火力発電所における格子状
の鉄骨間を挿通可能としているのである。主巻フック2
8の側面部には貫通孔29を有している。前記貫通孔2
9に図示しないワイヤを介して重量物と連結すること
で、重量物を吊上げることができるのである。
A main winding hook 28 is provided at the tip of the main winding wire 14. The main winding hook 28 is shown in FIG.
As shown in FIG. 5, it is formed in a tapered rectangular plate shape. By doing so, it is possible to insert between the grid-shaped steel frames in the thermal power plant. Main winding hook 2
The side surface of 8 has a through hole 29. The through hole 2
It is possible to lift the heavy object by connecting the heavy object through a wire not shown in FIG.

【0020】前記ジブ12は、先端側に突設された延長
プレート22を有している。前記延設プレート22は、
上面に延長巻き掛けプーリ24,26を回動可能に配置
している。そして、前記延長プレート22の延長巻き掛
けプーリ24,26には、連結ワイヤである補巻ワイヤ
18を巻きかけ、当該補巻ワイヤ18を延長プレート2
2先端側より吊下げている。これにより、補巻ワイヤ1
8は主巻ワイヤ14よりも延長プレート22分だけ外方
に吊下げることができ、吊り具48の取付け間隔を確保
させることができる。ここで、延長プレート22の長さ
は、吊り具48の直径と同程度の長さのものを好ましく
用いることができる。なお、補巻ワイヤ18の基端側
は、補巻ウインチ20により巻き取り、巻出しが行われ
る。前記補巻ウインチ20は、前記ベース10上の主巻
ウインチ16の後方側に設置されている。本実施形態に
おいては、補巻ワイヤ18は、例えば1.5トン程度の
吊下げ荷重のものを想定している。
The jib 12 has an extension plate 22 protruding from the tip side. The extension plate 22 is
Extension winding pulleys 24 and 26 are rotatably arranged on the upper surface. The auxiliary winding wire 18, which is a connecting wire, is wound around the extension winding pulleys 24 and 26 of the extension plate 22, and the auxiliary winding wire 18 is attached to the extension plate 2.
2 Suspended from the tip side. As a result, the auxiliary winding wire 1
8 can be hung outwardly from the main winding wire 14 by an amount corresponding to the extension plate 22 so that the attachment interval of the suspenders 48 can be secured. Here, as the length of the extension plate 22, a length approximately equal to the diameter of the hanging tool 48 can be preferably used. The base end side of the auxiliary winding wire 18 is wound and unwound by the auxiliary winding winch 20. The auxiliary winding winch 20 is installed on the rear side of the main winding winch 16 on the base 10. In the present embodiment, the auxiliary winding wire 18 is assumed to have a hanging load of, for example, about 1.5 tons.

【0021】前記補巻ワイヤ18は、先端部にて連結部
材であるプラグ部材30の基端部と連結している。前記
プラグ部材30は、主巻フック28と結合される連結部
材であって、基端部の中心に補巻ワイヤ18の先端部を
挿入している。補巻ワイヤ18の先端部は、スラストベ
アリング37により回動可能に連結している。このた
め、前記プラグ部材30は、補巻ワイヤ18と一体的に
昇降可能となっている。プラグ部材30の基端部は先細
形状となっており、プラグ部材30を係止するソケット
部材32への案内を容易にさせている。
The auxiliary winding wire 18 is connected at its tip end to the base end of a plug member 30 which is a connecting member. The plug member 30 is a connecting member that is coupled to the main winding hook 28, and the tip end portion of the auxiliary winding wire 18 is inserted into the center of the base end portion. The tip of the auxiliary winding wire 18 is rotatably connected by a thrust bearing 37. Therefore, the plug member 30 can be raised and lowered integrally with the auxiliary winding wire 18. The base end of the plug member 30 has a tapered shape to facilitate the guide to the socket member 32 that locks the plug member 30.

【0022】図4(b)、図4(c)に示したように前
記プラグ部材30の中央部には、ソケット部材32との
係止をなすための係止ピン連結孔44が貫通して設けて
ある。前記係止ピン連結孔44は、長細形状とされ、後
述するようにソケット部材32に係止するプラグ係止ピ
ン42の挿入を容易としている。また、前記係止ピン連
結孔44の両側面側には、断面凸形状の張り出しプレー
ト40を設けている。前記張り出しプレート40は、位
置決め凸部であってソケット部材32の係合凹部である
係合溝38に係合可能な形状に形成している(図5
(a)参照)。
As shown in FIGS. 4 (b) and 4 (c), a locking pin connecting hole 44 for locking with the socket member 32 penetrates through the central portion of the plug member 30. It is provided. The locking pin connection hole 44 has an elongated shape, and facilitates insertion of the plug locking pin 42 that locks to the socket member 32 as described later. Further, projecting plates 40 having a convex cross section are provided on both side surfaces of the locking pin connecting hole 44. The projecting plate 40 is formed in a shape that can be engaged with the engaging groove 38 that is the positioning projection and the engagement recess of the socket member 32 (FIG. 5).
(See (a)).

【0023】また、プラグ部材30の先端部は、断面コ
の字形状の板材形状に形成し、両側面に主巻フック連結
孔31を設けている。前記プラグ部材30は、先端部に
て主巻フック28の先端側を挿入可能となっている。前
記主巻フック28の貫通孔29は、主巻フック連結孔3
1と芯合わせしてピンにて結合可能であり、これにより
主巻フック28との一体化を可能としている。
Further, the tip end of the plug member 30 is formed into a plate material having a U-shaped cross section, and main winding hook connection holes 31 are provided on both side surfaces. The tip end of the plug member 30 can be inserted into the tip side of the main winding hook 28. The through hole 29 of the main winding hook 28 is the main winding hook connecting hole 3
It is possible to align with 1 and to be coupled by a pin, which enables integration with the main winding hook 28.

【0024】次に、ソケット部材32について説明す
る。前記ソケット部材32は、前記プラグ部材30を係
止して固定保持を行う係止部となっている。前記ソケッ
ト部材32は、図5に示したように、フレーム70上面
の両端部を2本の荷重受けワイヤ34の下端部に連結さ
れ、当該荷重受けワイヤ34にて吊下げ支持されてい
る。前記荷重受けワイヤ34の上端部は延長プレート2
2の両側に連結され、荷重受けワイヤ34が受ける荷重
を、延長プレート22を介してジブ12に伝えている。
従って、ソケット部材32は、ジブ12に支持されてい
る。本実施形態においては、前記荷重受けワイヤ34
は、一本あたり10トンの吊下げ荷重を有したものを用
いている。これにより、主巻ワイヤ14と同等以上の吊
上げ荷重を確保することができる。なお、荷重受けワイ
ヤ34は、全体で主巻ワイヤ14と同等以上の吊下げ荷
重を確保できれば任意の配置形態でよい。
Next, the socket member 32 will be described. The socket member 32 is a locking portion that locks and holds the plug member 30. As shown in FIG. 5, the socket member 32 has both ends of the upper surface of the frame 70 connected to the lower ends of two load receiving wires 34, and is suspended and supported by the load receiving wires 34. The upper end of the load receiving wire 34 is the extension plate 2
The load received by the load receiving wire 34 is connected to both sides of the wire 2 and is transmitted to the jib 12 via the extension plate 22.
Therefore, the socket member 32 is supported by the jib 12. In the present embodiment, the load receiving wire 34
Uses one having a suspension load of 10 tons per one. As a result, a lifting load equal to or higher than that of the main winding wire 14 can be secured. It should be noted that the load receiving wire 34 may have any arrangement as long as it can ensure a suspension load equal to or higher than that of the main winding wire 14 as a whole.

【0025】前記ソケット部材32は、前記フレーム7
0の中心部に円筒状のソケット本体72を設けている。
前記ソケット本体72は、内部にプラグ部材30を挿入
可能としているのである。また、フレーム70には、ソ
ケット本体72上方にブラケット74を介してカバー7
6が取付けてある。前記カバー76の軸中心はプラグ挿
入孔36を有しており、プラグ部材30の基端部を挿入
可能となっている。
The socket member 32 corresponds to the frame 7
A cylindrical socket body 72 is provided at the center of 0.
The socket body 72 allows the plug member 30 to be inserted therein. In addition, the frame 70 has a cover 7 above the socket body 72 via a bracket 74.
6 is attached. The shaft center of the cover 76 has a plug insertion hole 36 so that the base end portion of the plug member 30 can be inserted.

【0026】前記カバー76の上面には、プラグリミッ
トスイッチ47が配置してある。前記プラグリミットス
イッチ47は、プラグ部材30がソケット部材32の所
定位置まで挿入されたことを検知するものである。
A plug limit switch 47 is arranged on the upper surface of the cover 76. The plug limit switch 47 detects that the plug member 30 has been inserted to a predetermined position of the socket member 32.

【0027】前記フレーム70には、ソケット本体72
の一側に、プラグ係止ピン42がソケット本体72に直
交させて軸方向移動自在に設けてある。ソケット本体7
2には、プラグ係止ピン42を貫通させる係止ピン挿入
孔78が設けてある。また、フレーム70には、ソケッ
ト本体72の他側にソケット本体72を貫通したプラグ
係止ピン42の先端部が接触する係止ピンリミットスイ
ッチ45が設けてある。
The frame 70 has a socket body 72.
On one side, a plug locking pin 42 is provided so as to be orthogonal to the socket body 72 and movable in the axial direction. Socket body 7
2 has a locking pin insertion hole 78 through which the plug locking pin 42 passes. Further, the frame 70 is provided with a locking pin limit switch 45 on the other side of the socket main body 72, with which the tip of the plug locking pin 42 penetrating the socket main body 72 comes into contact.

【0028】ソケット本体72には、係止ピン挿入孔7
8を設けた方向と直交する方向に係合溝38を設けてい
る。ソケット本体72は、前記係合溝38の下方側に、
係合溝38に連なり下方向に拡開させた案内ガイド39
を有している。前記案内ガイド(ガイド部)39は、プ
ラグ部材30の張り出しプレート40を係合溝38に案
内する。これにより、プラグ部材30の張り出しプレー
ト40が係合溝38に沿って円滑に挿入される。したが
って、ソケット部材32の係止ピン挿入孔78とプラグ
部材30の係止ピン連結孔44とが芯合わせでき、プラ
グ係止ピン42を前記孔44,78内に確実に挿入させ
ることができる。従って、プラグ部材30の挿入を空中
においても、確実に行うことができる。
The socket body 72 has a locking pin insertion hole 7
The engaging groove 38 is provided in a direction orthogonal to the direction in which the 8 is provided. The socket body 72 is provided on the lower side of the engagement groove 38,
A guide guide 39 connected to the engagement groove 38 and expanded downward
have. The guide guide (guide portion) 39 guides the projecting plate 40 of the plug member 30 into the engagement groove 38. As a result, the projecting plate 40 of the plug member 30 is smoothly inserted along the engagement groove 38. Therefore, the locking pin insertion hole 78 of the socket member 32 and the locking pin connecting hole 44 of the plug member 30 can be aligned with each other, and the plug locking pin 42 can be reliably inserted into the holes 44 and 78. Therefore, the plug member 30 can be reliably inserted even in the air.

【0029】前記プラグ係止ピン42は、図6に示した
ように、電動シリンダ46に接続され、当該電動シリン
ダ46を作動することによりプラグ係止ピン42の出入
りの制御がなされる。電動シリンダ46は駆動モータ4
9により駆動され、ピストンロッド51の出し入れを行
う。これにより、ピストンロッド51に連結シャフト5
3により連結されたプラグ係止ピン42の軸方向移動が
行われるのである。プラグ係止ピン42が軸方向に移動
してプラグ部材30を貫通し、前記係止ピンリミットス
イッチ45にプラグ係止ピン42が当接することにより
差込完了を検知するのである。
As shown in FIG. 6, the plug locking pin 42 is connected to an electric cylinder 46, and the plug locking pin 42 is controlled to move in and out by operating the electric cylinder 46. The electric cylinder 46 is the drive motor 4
9 drives the piston rod 51 to move in and out. As a result, the connecting shaft 5 is connected to the piston rod 51.
Thus, the plug locking pin 42 connected by 3 is moved in the axial direction. When the plug locking pin 42 moves in the axial direction and penetrates the plug member 30 and the plug locking pin 42 comes into contact with the locking pin limit switch 45, the completion of insertion is detected.

【0030】このように、ソケット部材32がプラグ部
材30を連結することにより、主巻ワイヤ14をループ
化することができる。前記ループ化した主巻ワイヤ14
に吊り具48が取付けられ、これにより許容荷重の倍加
が図られる。
Thus, the main winding wire 14 can be looped by connecting the plug member 30 with the socket member 32. The looped main winding wire 14
A suspending device 48 is attached to the above, thereby doubling the allowable load.

【0031】前記吊り具48は図7、図8に示したよう
に、シーブ部80と、フック部82とからなっている。
シーブ部80は、主巻巻き掛けプーリ50がその両側に
配置した略ホームベース状のブラケット54にプーリ中
心軸52を介して回転自在に取付けてある。ブラケット
54の外側には、プーリ中心軸52に枢着したリンクプ
レート56が配置してある。前記ブラケット54とリン
クプレート56とは、下方が開放され、ループ状にした
主巻ワイヤ14を主巻巻き掛けプーリ50に巻き掛ける
ことができるようになっている。リンクプレート56の
下部には、脱着孔84を設けてあり、この脱着孔84を
介してフック部82のフック連結プレート62が着脱可
能かつ揺動自在にリンク脱着ピン58により連結でき
る。
As shown in FIGS. 7 and 8, the suspender 48 comprises a sheave portion 80 and a hook portion 82.
The sheave portion 80 is rotatably attached via a pulley center shaft 52 to a substantially home-base shaped bracket 54 on which the main winding pulley 50 is arranged on both sides thereof. On the outside of the bracket 54, a link plate 56 pivotally attached to the pulley center shaft 52 is arranged. The bracket 54 and the link plate 56 are open at the bottom so that the looped main winding wire 14 can be wound around the main winding pulley 50. An attachment / detachment hole 84 is provided in the lower portion of the link plate 56, and the hook connection plate 62 of the hook portion 82 can be detachably and swingably connected by the link attachment / detachment pin 58 via the attachment / detachment hole 84.

【0032】吊り具48は、不使用時にシーブ部80と
フック部82とが分離してある。フック部82と分離さ
せたシーブ部80は、吊り具受け台64に支持させてあ
る。受け台64は、フック部82を配置するベース枠8
6と、ベース枠86に立設した一対の支持脚88とを有
する。各脚88の上部には、支持板90が渡してあり、
当該支持板90には支持ピン66が突設してなる。そし
て、プーリ50は、支持孔94に支持ピン66を挿通さ
せることにより、支持ピン92に支持される。支持ピン
66の先端には、押えキャップ96が着脱可能に螺着さ
れ、プーリ50の脱落を防止させている。
The suspender 48 has a sheave portion 80 and a hook portion 82 which are separated when not in use. The sheave portion 80 separated from the hook portion 82 is supported by the hanger support 64. The cradle 64 has a base frame 8 on which the hook portion 82 is arranged.
6 and a pair of support legs 88 provided upright on the base frame 86. A support plate 90 is provided above each leg 88,
Support pins 66 are provided on the support plate 90 so as to project therefrom. The pulley 50 is supported by the support pin 92 by inserting the support pin 66 into the support hole 94. A presser cap 96 is detachably attached to the tip of the support pin 66 to prevent the pulley 50 from falling off.

【0033】フック部82は、フック60とフック連結
プレート62とを有し、両者がトラニオン63を介して
枢着してなる。前記フック60は、重量物に玉掛けした
ワイヤを掛合させる一対の掛止部92を有する錨状をな
している。ベース枠86には、トラニオン受け100と
フック受け65とが設けてあって、シーブ部80から分
離したフック部82のトラニオン63と掛止部92を支
持するようにしてある。
The hook portion 82 has a hook 60 and a hook connecting plate 62, both of which are pivotally attached via a trunnion 63. The hook 60 is in the shape of an anchor having a pair of hook portions 92 for hooking a wire slung over a heavy object. The base frame 86 is provided with a trunnion receiver 100 and a hook receiver 65 so as to support the trunnion 63 and the hook portion 92 of the hook portion 82 separated from the sheave portion 80.

【0034】以上のように説明した本実施形態における
作用は以下のようになる。主巻ワイヤ14の許容荷重内
の重量物を吊上げる場合には、図2(a)に示したよう
に、主巻ワイヤ14の先端に設けた主巻フック28に重
量物を連結して、主巻ワイヤ14により吊上げ作業を行
う。上記したように、主巻フック28は長細形状として
いるので、格子状の鉄骨組みされた建屋においても、昇
降を容易に行うことができる。
The operation of the present embodiment described above is as follows. When lifting a heavy object within the allowable load of the main winding wire 14, as shown in FIG. 2A, the heavy object is connected to the main winding hook 28 provided at the tip of the main winding wire 14, The hoisting work is performed by the main winding wire 14. As described above, since the main winding hook 28 has a long and thin shape, it can be easily moved up and down even in a building with a lattice-shaped steel frame.

【0035】主巻ワイヤ14の許容荷重を超える重量物
を吊上げる場合には、以下のように行う。まず、図2
(b)に示すように作業場に主巻フック28を降ろす。
そして、図2(c)に示したように、補巻ワイヤ18を
下降してプラグ部材30を作業場に降ろす。そして、前
記主巻フック28の先端部とプラグ部材30の先端部と
をピンにて連結して一体化を行う。そこで、図3(a)
に示したように、補巻ワイヤ18をジブ12先端側へ巻
き上げる。これにより、補巻ワイヤ18に連結された主
巻ワイヤ14は、主巻ワイヤ14の先端側より巻き上げ
られる。
In the case of lifting a heavy object that exceeds the allowable load of the main winding wire 14, the procedure is as follows. First, FIG.
As shown in (b), the main winding hook 28 is lowered to the work place.
Then, as shown in FIG. 2C, the auxiliary winding wire 18 is lowered to lower the plug member 30 to the work place. Then, the leading end of the main winding hook 28 and the leading end of the plug member 30 are connected by a pin to integrate them. Therefore, FIG. 3 (a)
The auxiliary winding wire 18 is wound up to the tip side of the jib 12 as shown in FIG. As a result, the main winding wire 14 connected to the auxiliary winding wire 18 is wound up from the tip side of the main winding wire 14.

【0036】上記したように、ジブ12先端側にはソケ
ット部材30が設けられ、当該ソケット部材30を補巻
ワイヤ18が貫通している。このため、補巻ワイヤ18
の先端部に設けたプラグ部材30は、補巻ワイヤ18を
巻き上げることでソケット部材32のプラグ挿入孔36
に案内される。そして、前記プラグ部材32はソケット
部材32のガイド部39に案内され、プラグ部材30の
張り出しプレート40がソケット部材32の係合溝38
に係合されつつ挿入される。プラグ部材30の上端(基
端)がカバー76から突出したプラグリミットスイッチ
47に接触することで、補巻ウインチ20が停止され
る。これにより、プラグ部材30の係止ピン連結孔44
がソケット部材32のピン挿入孔78に、図5(b)に
示すように自動的に位置を一致させることができる。
As described above, the socket member 30 is provided on the tip side of the jib 12, and the auxiliary winding wire 18 penetrates the socket member 30. Therefore, the auxiliary winding wire 18
The plug member 30 provided at the tip end of the plug member has a plug insertion hole 36 of the socket member 32 when the auxiliary winding wire 18 is wound up.
Will be guided to. The plug member 32 is guided by the guide portion 39 of the socket member 32, and the projecting plate 40 of the plug member 30 is engaged with the engaging groove 38 of the socket member 32.
Is inserted while being engaged with. When the upper end (base end) of the plug member 30 comes into contact with the plug limit switch 47 protruding from the cover 76, the auxiliary winding winch 20 is stopped. Thereby, the locking pin connecting hole 44 of the plug member 30
The position can be automatically aligned with the pin insertion hole 78 of the socket member 32 as shown in FIG. 5B.

【0037】そして、図示しない遠隔操作部を操作し
て、電動シリンダ46を作動させる。前記電動シリンダ
46により、プラグ係止ピン42が係止ピン連結孔44
内に差込案内される。前記プラグ係止ピン42が係止ピ
ンリミットスイッチ45に接触すると、電動シリンダ4
6の作動が停止して前記プラグ係止ピン42の移動が停
止される。ゆえに、プラグ部材30をソケット部材32
に係止させることができる。これにより、主巻ワイヤ1
4がループ化されるのである。
Then, the remote control unit (not shown) is operated to operate the electric cylinder 46. The electric cylinder 46 causes the plug locking pin 42 to move into the locking pin connecting hole 44.
You will be guided in the inside. When the plug locking pin 42 contacts the locking pin limit switch 45, the electric cylinder 4
The operation of 6 is stopped and the movement of the plug locking pin 42 is stopped. Therefore, the plug member 30 is replaced with the socket member 32.
Can be locked to. Thereby, the main winding wire 1
4 is looped.

【0038】このあと、補巻ワイヤ18を緩めることに
より、主巻ワイヤ14の支持を補巻ワイヤ18からソケ
ット部材32に切り替える。前記ソケット部材32はジ
ブ12に支持されているため、主巻ワイヤ14の先端側
の支持をジブ12にて行わせることができる。従って、
主巻ウインチ16のドラム径を従来と変えることなく許
容荷重の増加を図ることが出来る。その後、図3(c)
に示したように、ループ化した主巻ワイヤ14に吊り具
48を取付ける。吊り具48は吊り具受け台64にて支
持されている。まず、主巻ワイヤ14をシーブ部80の
主巻巻き掛けプーリ50に巻き掛ける。
Then, by loosening the auxiliary winding wire 18, the support of the main winding wire 14 is switched from the auxiliary winding wire 18 to the socket member 32. Since the socket member 32 is supported by the jib 12, the tip end side of the main winding wire 14 can be supported by the jib 12. Therefore,
The allowable load can be increased without changing the drum diameter of the main winding winch 16 from the conventional one. After that, FIG. 3 (c)
As shown in FIG. 5, the suspending device 48 is attached to the looped main winding wire 14. The hanging device 48 is supported by a hanging device support 64. First, the main winding wire 14 is wound around the main winding pulley 50 of the sheave portion 80.

【0039】次に、ベース枠86上に配置してあるフッ
ク部82のフック連結プレート62を起してピン58に
より連結する。主巻ワイヤ14を巻き上げると、図7の
左側に示したように、フック部82がシーブ部80に吊
下げられる。これにより、主巻ワイヤ14は、吊り具4
8に2本掛けにされた状態となり、許容荷重が2倍とな
る。以上説明したように、主巻ワイヤをジブに接続して
ループ化するので、揚程をジブ本来の高さまで確保して
吊上げ作業を行うことができる。
Next, the hook connecting plate 62 of the hook portion 82 arranged on the base frame 86 is raised and connected by the pin 58. When the main winding wire 14 is wound up, as shown on the left side of FIG. 7, the hook portion 82 is hung on the sheave portion 80. As a result, the main winding wire 14 is attached to the suspension 4
It becomes a state that it is hung on 8 and the allowable load is doubled. As described above, since the main winding wire is connected to the jib to form a loop, the lifting work can be performed while ensuring the lifting height to the original height of the jib.

【0040】また、ジブクレーンのウインチドラムにか
かる負担は従来と変わらないので、本体部に変更を加え
ることなく許容荷重を倍加することができる。また、プ
ラグ部材をソケット部材に係止部を設けたことにより、
プラグ部材をソケット部材に円滑に挿入することができ
るため、主巻ワイヤのジブへの連結を地上から離れた空
中にて円滑に行うことができる。
Further, since the load applied to the winch drum of the jib crane is the same as the conventional one, the allowable load can be doubled without changing the main body. Also, by providing the plug member with the locking portion on the socket member,
Since the plug member can be smoothly inserted into the socket member, the main winding wire can be smoothly connected to the jib in the air away from the ground.

【0041】本実施形態における吊り具においては、フ
ック部を取り外してプーリを開放状態にできるので、主
巻ワイヤをループ化した後においても、吊り具の取付け
を容易に行うことができる。なお、本発明は火力発電所
等の鉄骨建屋において、特に好適に用いることができる
が、適用対象はこれに限らず、本体部の水平移動困難な
場所において、許容荷重を増加する場合に好ましく用い
ることができる。また、実施形態においては、ソケット
部材はジブの先端側より吊下げる構成としたが、ジブに
一体化させてもよい。また、実施形態においては、ジブ
の外方側に主巻ワイヤのループを形成させたが、これに
限らずジブの内方側や水平側に主巻ワイヤのループを形
成させてもよい。実施形態においては連結補巻ワイヤを
用いて主巻ワイヤのループ化を行ったが、新たな部材を
用いて主巻ワイヤのループ化を行ってもよい。さらに、
巻上装置としては、ジブクレーンに限らず、タワー型ク
レーン、ラフタレーンクレーン等を用いてもよい。
In the hanging device of this embodiment, the hook portion can be removed to open the pulley, so that the hanging device can be easily attached even after the main winding wire is looped. Note that the present invention can be particularly preferably used in a steel frame building such as a thermal power plant, but the application target is not limited to this, and is preferably used when increasing the allowable load in a place where horizontal movement of the main body is difficult. be able to. Further, in the embodiment, the socket member is configured to be hung from the tip end side of the jib, but it may be integrated with the jib. Further, in the embodiment, the main winding wire loop is formed on the outer side of the jib, but the present invention is not limited to this, and the main winding wire loop may be formed on the inner side or the horizontal side of the jib. In the embodiment, the main winding wire is looped using the connecting auxiliary winding wire, but the main winding wire may be looped using a new member. further,
The hoisting device is not limited to a jib crane, but a tower crane, a laphthalene crane, or the like may be used.

【0042】[0042]

【発明の効果】本発明においては、荷吊りワイヤをルー
プ化して本体部に接続するため、揚程を本来部の高さま
で確保することができるとともに、荷吊りワイヤが2本
がけされるため、本体部を変更することなく揚重量を増
大することができる。
According to the present invention, since the load-hanging wire is looped and connected to the main body, the lifting height can be secured up to the original height of the load, and since the two load-hanging wires are removed, the main body can be secured. Lifting weight can be increased without changing parts.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施形態におけるジブクレーンの側面
図である。
FIG. 1 is a side view of a jib crane according to an embodiment of the present invention.

【図2】本発明の実施形態におけるジブクレーンの工程
説明図である。
FIG. 2 is a process explanatory diagram of the jib crane according to the embodiment of the present invention.

【図3】本発明の実施形態におけるジブクレーンの工程
説明図である。
FIG. 3 is a process explanatory diagram of the jib crane according to the embodiment of the present invention.

【図4】本発明の実施形態におけるプラグ部材の説明図
である。
FIG. 4 is an explanatory diagram of a plug member according to the embodiment of the present invention.

【図5】本発明の実施形態におけるソケット部材の断面
正面図及び側面図である。
FIG. 5 is a sectional front view and a side view of the socket member according to the embodiment of the present invention.

【図6】本発明の実施形態におけるソケット部材の断面
平面図である。
FIG. 6 is a cross-sectional plan view of the socket member according to the embodiment of the present invention.

【図7】本発明の実施形態における吊り具の正面図であ
る。
FIG. 7 is a front view of the suspender according to the embodiment of the present invention.

【図8】本発明の実施形態における吊り具の正面図であ
る。
FIG. 8 is a front view of the suspender according to the embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 ジブクレーン 10 ベース 12 ジブ 13 ジブプーリ 14 主巻ワイヤ 16 主巻ウインチ 18 補巻ワイヤ 20 補巻ウインチ 22 延長プレート 24 延長巻き掛けプーリ 26 延長巻き掛けプーリ 28 主巻フック 30 プラグ部材 32 ソケット部材 34 荷重受けワイヤ 36 プラグ挿入孔 37 スラストベアリング 38 係合溝 39 ガイド部 40 張り出しプレート 42 プラグ係止ピン 44 係止ピン連結孔 45 係止ピンリミットスイッチ 46 電動シリンダ 47 プラグリミットスイッチ 48 吊り具 49 駆動モータ 50 主巻巻き掛けプーリ 51 ピストンロッド 52 プーリ中心軸 53 連結シャフト 54 ブラケット 56 リンクプレート 58 リンク脱着ピン 60 フック 62 フック連結プレート 63 トラニオン 64 吊り具受け台 65 フック受け 66 支持ピン 70 フレーム 72 ソケット本体 74 ブラケット 76 カバー 78 ピン挿入孔 80 シーブ部 82 フック部 84 脱着孔 86 ベース枠 88 支持脚 90 支持板 92 係止部 94 支持孔 96 押えキャップ 100 トラニオン受け 1 jib crane 10 base 12 jib 13 jib pulley 14 Main winding wire 16 Main winch 18 auxiliary winding wire 20 auxiliary winding winch 22 Extension plate 24 Extension winding pulley 26 Extension winding pulley 28 Main winding hook 30 plug members 32 Socket member 34 Load receiving wire 36 Plug insertion hole 37 Thrust bearing 38 Engagement groove 39 Guide part 40 Overhang plate 42 Plug locking pin 44 Lock pin connection hole 45 Locking pin limit switch 46 electric cylinder 47 plug limit switch 48 hanging equipment 49 drive motor 50 Main winding pulley 51 piston rod 52 Pulley center axis 53 Connection shaft 54 bracket 56 link plate 58 Link removable pin 60 hooks 62 Hook connection plate 63 trunnion 64 Hanging support 65 hook receiver 66 Support pin 70 frames 72 Socket body 74 bracket 76 cover 78 pin insertion hole 80 sheave part 82 Hook part 84 Desorption hole 86 base frame 88 support legs 90 Support plate 92 Locking part 94 Support hole 96 Presser cap 100 trunnion receiver

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) B66C 1/34 B66C 13/00 B66C 23/66 ─────────────────────────────────────────────────── ─── Continuation of front page (58) Fields surveyed (Int.Cl. 7 , DB name) B66C 1/34 B66C 13/00 B66C 23/66

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 本体部から吊下げられて重量物を昇降さ
せる荷吊りワイヤと、 前記荷吊りワイヤの先端部に着脱可能に結合される連結
部材と、 前記本体部から吊下げされて前記連結部材に結合され、
連結部材を昇降させる連結ワイヤと、 前記本体部に設けられ、前記連結ワイヤにより吊上げら
れた前記連結部材を係止する係止部と、 を有することを特徴とする巻上装置。
1. A load-hanging wire which is hung from a main body to lift and lower a heavy object, a connecting member which is detachably connected to a tip end of the load-hanging wire, and the connection which is hung from the main body. Coupled to a member,
A hoisting device, comprising: a connecting wire that raises and lowers the connecting member; and a locking portion that is provided in the main body and that locks the connecting member that is hung by the connecting wire.
【請求項2】 前記係止部は、前記連結部材に形成した
ピン孔に挿入する係止ピンと、 遠隔操作により前記係止ピンを軸方向に移動し、前記連
結部材の係脱をするアクチュエータとを有することを特
徴とする請求項1に記載の巻上装置。
2. The locking portion includes a locking pin that is inserted into a pin hole formed in the connecting member, and an actuator that axially moves the locking pin by remote control to engage and disengage the connecting member. The hoisting device according to claim 1, further comprising:
【請求項3】 前記係止部は、前記連結部材の側部に設
けた位置決め凸部と係合する係合凹部と、 この係合凹部に連続して形成され、前記位置決め凸部を
係合凹部に案内するガイド部とを有することを特徴とす
る請求項2に記載の巻上装置。
3. The engaging portion is formed continuously with the engaging concave portion that engages with the positioning convex portion provided on the side portion of the connecting member, and engages the positioning convex portion. The hoisting device according to claim 2, further comprising a guide portion that guides the concave portion.
JP36975099A 1999-12-27 1999-12-27 Hoisting equipment Expired - Fee Related JP3412153B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP36975099A JP3412153B2 (en) 1999-12-27 1999-12-27 Hoisting equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP36975099A JP3412153B2 (en) 1999-12-27 1999-12-27 Hoisting equipment

Publications (2)

Publication Number Publication Date
JP2001180885A JP2001180885A (en) 2001-07-03
JP3412153B2 true JP3412153B2 (en) 2003-06-03

Family

ID=18495237

Family Applications (1)

Application Number Title Priority Date Filing Date
JP36975099A Expired - Fee Related JP3412153B2 (en) 1999-12-27 1999-12-27 Hoisting equipment

Country Status (1)

Country Link
JP (1) JP3412153B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015145307A (en) * 2014-02-04 2015-08-13 日本車輌製造株式会社 Re-hanging method of auxiliary hoist rope
CN106144964B (en) * 2015-04-23 2019-10-15 南通中集特种运输设备制造有限公司 Top cover suspender, unlatch and close hard open top container top cover operating method

Also Published As

Publication number Publication date
JP2001180885A (en) 2001-07-03

Similar Documents

Publication Publication Date Title
JP3412153B2 (en) Hoisting equipment
KR101834137B1 (en) Electromagnet for being mounted to hoist
JP3009375B2 (en) Jib attachment / detachment device for crane beam
CN113264458A (en) Tower crane system and method for removing attachment rod thereof
JP4789462B2 (en) Electric equipment lifting device
CN211971577U (en) Tower crane system
JP2000274080A (en) Wall member fitting method for building skeleton and wall member fitting traverser
JPH092774A (en) Heavy object suspending device
CN218145401U (en) Simple cable reel lifting appliance
JPH09227069A (en) Hung-moving method and device therefor
JPH0111670Y2 (en)
JP2008074498A (en) Jib crane
CN214141322U (en) Steel construction hoisting accessory
CN214570045U (en) Adjustable modularization prefabricated cabin hoist
JP3326733B2 (en) Movable hanging jig for steel frame construction and steel frame construction method using the same
CN211998486U (en) Foldable small-sized movable lifting device
CN211946001U (en) House building material lifting device
CN213834212U (en) Assembled building hoisting accessory
CN212503693U (en) Tower crane is attached to ann and is torn open hoisting accessory
CN216235650U (en) Lifting equipment for maintenance of diesel generator in gas station
CN211393522U (en) Hook assembly for manual unhooking
CN211444796U (en) Glass curtain wall mounting crane
JPS5811823Y2 (en) Counterweight beam starting device using crane hoisting device
JPH072549Y2 (en) Crane lifting equipment
JPS6122407Y2 (en)

Legal Events

Date Code Title Description
S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080328

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090328

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090328

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100328

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110328

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110328

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120328

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130328

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140328

Year of fee payment: 11

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees