Authority
JP
Japan
Prior art keywords
fitting
support pipe
joint
tapered surface
lower support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000001479A
Other languages
Japanese (ja)
Other versions
JP2001196197A (en
Inventor
常一 三木
寛 園山
Original Assignee
東京避雷針工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 東京避雷針工業株式会社 filed Critical 東京避雷針工業株式会社
Priority to JP2000001479A priority Critical patent/JP3401469B2/en
Publication of JP2001196197A publication Critical patent/JP2001196197A/en
Application granted granted Critical
Publication of JP3401469B2 publication Critical patent/JP3401469B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】 【0001】 【産業上の利用分野】本発明は、多段式避雷針の支持管
の継手装置に関する。 【0002】 【従来の技術】従来の多段式避雷針の支持管の継手装置
は、図3に示されるように、下段支持管51に下部が前
記下段支持管51に嵌入するとともに段部54を介して
上部が上段支持管52に遊嵌する径とされる環状継手金
具53を下段支持管51に予め工場等で溶接しておき、
このように継手53を溶着した下段支持管51を施工現
場へ持ち運び、施工現場において、該継手金具53を溶
着した下段支持管51内に上段支持管52を遊嵌し、前
記継手金具53の上部に穿設された複数のボルト孔5
5,55、55に固設されるナット56にボルト57,
57,57を締結して下段支持管51と上段支持管52
を接続し、下段支持管51と上段支持管52との電気的
接続のために継手金具53と上段支持管52とを溶着5
8している。 【0003】上記した施工現場における溶着としてはア
ーク溶接あるいはテルミット溶接等が行なわれている
が、何れにしても上記した従来の多段式避雷針の継ぎ部
分の接続である施工現場における溶接には、溶接火花の
問題があり、この溶接火花により施工現場近傍の建築物
の表層材料を汚したり、傷めたりすることがあるので、
溶接の際に建築物の表層材料を完全に防護する必要があ
る。 【0004】また、多段式避雷針を取り付ける建築施工
現場の屋上は、アーク溶接に使用する電源の確保に制約
を受ける場合が多く、電源を取得するために長距離にわ
たり電線ケーブルを敷設する等多大の労力を必要とする
し、さらには、前記した上段支持管52と継手金具53
との溶接によって溶接箇所における溶接変形により、下
段支持管51と上段指示管52とを組み立てる際に調整
された真直性が損なわれ、避雷針全体が湾曲する恐れが
残るという問題があった。 【0005】 【発明が解決しようとする課題】上述したように、従来
の多段式避雷針の継ぎ部分の接続には溶接の熟練性が要
請されるとともに、作業効率の低下の一因ともなってい
た。そこで、本発明は、上記した問題点を解決するため
に、下段支持管と上段支持管との継ぎ部分の接続は、建
築施工現場におけるアーク溶接あるいはテルミット溶接
を用いることなく電気的、機械的接続を得るようにした
多段式避雷針の支持管継手装置の提供を目的とするもの
である。 【0006】 【課題を解決するための手段】本発明に係る多段式避雷
針の支持管継手装置は、先端に先細状のテーパ面が形成
され、該テーパ面と連続して下方に下段支持管が嵌入可
能な筒部を備えた第一継手金具と、上部に上段支持管が
嵌入可能な上部筒部と該筒部に連続して前記第一継手金
具のテーパー面と同一角度の末広がり状のテーパー面が
形成され、該テーパー面に連続して前記第一継手金具の
筒部が嵌入可能な筒部を設けるとともに、該筒部の周囲
に複数のボルト挿通孔を穿設した第二継手金具とを備
え、周囲に複数のボルト挿通用孔を穿設した下段支持管
を前記の第一継手金具の筒部内に嵌入のうえ溶着し、前
記第二継手金具内に嵌入・溶着した上部支持管を、前記
下段支持管を嵌入した第一継手金具の先端より挿入し、
前記第一継手金具のテーパー面と第二継手金具のテーパ
ー面とを密接せしめ、下段支持管及び第二継手金具のボ
ルト挿通用孔に設けられたナットにボルトをねじ込み、
第二継手金具と第一継手金具及び下段支持管と上段支持
管とを固定したことをその特徴とするものである。 【0007】 【発明の実施の態様】本発明の実施の態様を図に基づい
て説明すると、1は、多段式避雷針の下段支持管4が嵌
入可能な内径を有する筒部2と該筒部2に連続して絞り
加工等によって先端が先細状のテーパー面3が形成され
た第一継手金具であり、前記した下段支持管4はその下
部周囲に等間隔に複数のボルト挿通孔5,5,5,・・
を設け、該ボルト挿通孔5,5,5,・・・にナット
6,6,6,・・・をアーク溶接等により固設してあ
る。そして、前記した下段支持管4の先端を第一継手金
具1の筒部2の上端にいたるまで嵌入し、嵌入後第一継
手金具1と下段支持管4とをアーク溶接20等により固
設する。 【0008】7は第二継手金具であり、該第二継手金具
7は、上部に前記下段支持管4に挿通可能な外径を有す
る上段支持管11が嵌入可能な内径を有する上部筒部8
と、該上部筒部8の下方に連続して前記第一継手金具1
のテーパー面3と同一角度を有する下方に向かって末広
がり状をなすテーパー面9を形成し、該テーパー面9に
連続して下方に前記第一継手金具1の筒部2が嵌入可能
な内径を有する下部筒部10が形成されている。 【0009】前記した第二継手金具7の下部筒部10の
周辺にはボルト挿通孔が設けられ、該ボルト挿通孔にナ
ット12,12,12,・・・・・がアーク溶接等によ
り固設されている。そして第二継手金具7内に上段支持
管11を嵌入し、嵌入後第二継手金具7の上部筒部8と
上段支持管11とをアーク溶接21して両者を固設す
る。 【0010】上記した第一継手金具1と下段支持管4と
のアーク溶接20による両者の固設、また、前記第二継
手金具7と上段支持管11とのアーク溶接等による固設
は、何れも予め工場等で実施されるものであり、このよ
うに第一継手金具1を先端に固設した下段支持管4及び
第二継手金具7を固設した上段支持管11を工場で製作
してある。 【0011】上記した工場で製作された第一継手金具1
を先端に固設した下段支持管4及び第二継手金具7を固
設した上段支持管11を建築施工現場へ搬入して、多段
式避雷針を施工するには、前記搬入された上段支持管1
1及び下段支持管4を屋上にクレーン等で吊り上げそれ
らを屋上で横にした状態で下段支持管4の上部に固設の
第一継手金具1のテーパー面部3の上方側より上段支持
管11を挿入し、第一継手金具1のテーパー面3と上段
支持管11に固設の第二継手金具7のテーパー面9が密
接するまで挿入する。 【0012】上記の上段支持管11に固設の第二継手金
具7のテーパー面9と下段支持管4に固設の第一継手金
具1のテーパー面3とが密接した状態で下段支持管4と
上段支持管11とを接続させ、真直性をみたうえで第二
継手金具7の下部筒部10の周辺のボルト挿通孔に溶着
されたナット12,12,12にボルト22,22,2
2をねじ込み、第二継手金具7に挿入された第一継手金
具1の筒部2をボルト22で強固に固定し、第二継手金
具7と第一継手金具1を一体化する。 【0013】次いで、前記下段支持管4の周囲に穿設さ
れたボルト挿通用孔5,5,5に溶着等によって固設さ
れたナット6,6,6にボルト13,13,13をねじ
込み、下段支持管4と該下段支持管4内に挿着された上
段支持管11とを固定し両者を一体化することにより建
築現場における屋上での多段式避雷針の組立を行うもの
である。そして、このように屋上で横にした状態で組み
立てられた多段式避雷針は屋上の所定位置に建立される
ことになる。本実施の態様においては、下段支持管と上
段支持管の二本の管について説明したが、前記した上段
支持管の先端に第一継手金具を溶着し、第三番目の支持
管に第二継手金具を溶着することによって3本の支持管
を継ぐことができ、同様にして複数の支持管を順次継ぎ
足すことができるものである。 【0014】上記したように下段支持管4と上段支持管
11とが一体化された避雷針が屋上に建立されるが、こ
の建立された状態においては前記した上段支持管11に
固設の第二継手金具7のテーパー面9と下段支持管4に
固設の第一継手金具1のテーパー面3とは同一角度のテ
ーパー面での接触であるため、上段支持管11の重量に
よって接触面の面圧が保たれることが期待できるもので
ある。 【0015】本実施の態様による多段式避雷針が雷電流
を受けたとき、上段支持管より該上段支持管に溶着され
た第二継手金具を介して該第二継手金具とテーパー面で
接触されている第一継手金具を通電して、該第一継手金
具と溶着されている下段支持管よりアース線へと流れる
もので、本実施の態様においては雷電流の流れは面接触
されている継手部とともにそれぞれの継手金具と各支持
管とを溶着しているため雷電流の流れはきわめて良好と
なるものである。 【0016】上記したように、本実施の態様によるとき
は、アーク溶接の作業はすべて生産工場で実施され、多
段式避雷針を施工する建築現場においてはボルトによる
締め付けのみの作業であり、アーク溶接等の作業を施工
現場で行なはないので、溶接による火花の飛散の恐れは
全くなく、従来のように建築物の表層材料に対する溶接
時の防護作業の必要がなく、また、溶接用電源の確保等
の労力を削減できるものである。また、下段支持管と上
段支持管との接続は、両支持管に固設された第一継手金
具と第二継手金具に形成されたテーパー面同士の面接触
であり、従来のような溶接変形による避雷針の曲がりは
ない。 【0017】 【発明の効果】本発明に係る多段式避雷針の支持管継手
装置は、第一継手金具のテーパー面と第二継手金具のテ
ーパー面とを同一角度とし、下段支持管に第一継手金具
を、上部に上段支持管側に第二継手金具を予め生産工場
で溶接しておき、建築現場において上段支持管と下段支
持管とを組み立てる際に、第一継手金具と第二継手金具
のテーパー面とを面接触させて接続させるものであるの
で、前記の面接触にあっては上段支持管の重量によって
接触面の面圧を上げ、その接触状態を保持するのに、第
一継手金具と第二継手金具を該第二継手金具の外側より
ボルトによって両者を強固に固定し、充分な電気的、機
械的な効果を得ることができるものである。 【0018】本発明においては、上記したように溶接作
業はすべて工場等で予め行なわれるもので、避雷針の施
工現場においては単にボルト締めという機械的作業のみ
であるので、溶接等による火花の飛散等は全くなく、そ
のための建築表層材料にたいする防護作業あるいは溶接
用電源の確保等の労力の必要はなく、さらに、施工現場
において溶接をしないので、溶接変形による避雷針の曲
がりもなく真直性を保証されるものである。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a joint device for a support pipe of a multistage lightning rod. 2. Description of the Related Art As shown in FIG. 3, a conventional multi-stage lightning rod support pipe coupling device has a lower portion fitted into the lower support tube 51 and a step portion 54 interposed therebetween. An annular joint fitting 53 whose upper portion has a diameter that is loosely fitted to the upper support tube 52 is welded to the lower support tube 51 in advance at a factory or the like,
The lower support tube 51 with the joint 53 welded in this way is carried to the construction site, and at the construction site, the upper support tube 52 is loosely fitted into the lower support tube 51 with the joint bracket 53 welded thereto. Bolt holes 5 drilled in
Bolts 57, 55 are attached to nuts 56 fixed to 5, 55, 55.
The lower support tube 51 and the upper support tube 52 are fastened by fastening
And a joint metal fitting 53 and an upper support tube 52 are welded for electrical connection between the lower support tube 51 and the upper support tube 52.
8 As welding at the construction site, arc welding or thermit welding is performed. In any case, the welding at the construction site, which is the connection of the joint of the conventional multistage lightning rod, is performed by welding. There is a problem of sparks, and this welding spark may stain or damage the surface material of the building near the construction site,
It is necessary to completely protect the building surface material during welding. On the roof of a building construction site where a multi-stage lightning rod is installed, there are many cases where the power source used for arc welding is restricted, and a great deal of time is required, such as laying electric cables over long distances to obtain the power source. It requires labor, and furthermore, the above-mentioned upper support pipe 52 and the joint fitting 53
This causes a problem that the straightness adjusted when assembling the lower support pipe 51 and the upper indicator pipe 52 is impaired due to welding deformation at the welding location, and the entire lightning rod may be bent. [0005] As described above, the connection of the joint portion of the conventional multi-stage lightning rod requires the skill of welding and also contributes to a decrease in work efficiency. Therefore, in order to solve the above-described problems, the present invention provides a method for connecting a joint between a lower support pipe and an upper support pipe by using electrical or mechanical connection without using arc welding or thermit welding at a construction site. It is an object of the present invention to provide a multi-stage lightning rod supporting pipe joint device which can obtain the following. [0006] A multi-stage lightning rod supporting pipe joint device according to the present invention has a tapered surface formed at the tip, and a lower supporting tube is provided below the tapered surface continuously with the tapered surface. A first joint fitting having a fittable tubular portion, an upper tubular portion into which an upper support tube can be fitted at an upper portion, and a divergent taper having the same angle as the tapered surface of the first joint fitting continuously connected to the tubular portion; A second joint fitting having a surface formed thereon and a tubular portion into which the tubular portion of the first joint fitting can be fitted continuously to the tapered surface, and a plurality of bolt insertion holes formed in the periphery of the tubular portion. The lower support pipe having a plurality of bolt insertion holes formed therearound is fitted and welded into the cylindrical portion of the first fitting, and the upper support pipe fitted and welded in the second fitting is provided. , Inserted from the tip of the first fitting fitting into which the lower support tube has been fitted,
The taper surface of the first fitting and the taper surface of the second fitting are brought into close contact with each other, and a bolt is screwed into a lower support pipe and a nut provided in a bolt insertion hole of the second fitting.
The second joint fitting, the first joint fitting, and the lower support tube and the upper support tube are fixed. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described with reference to the drawings. 1 is a cylindrical portion 2 having an inner diameter into which a lower supporting pipe 4 of a multi-stage lightning rod can be fitted; The lower support pipe 4 has a plurality of bolt insertion holes 5, 5, 5, 5, 5, 5. 5, ...
Are fixed to the bolt insertion holes 5, 5, 5,... By arc welding or the like. Then, the distal end of the lower support pipe 4 is fitted to the upper end of the cylindrical portion 2 of the first fitting 1, and after the fitting, the first fitting 1 and the lower support pipe 4 are fixed by arc welding 20 or the like. . Reference numeral 7 denotes a second joint fitting. The second joint fitting 7 has an upper cylindrical portion 8 having an inner diameter into which an upper support pipe 11 having an outer diameter capable of being inserted into the lower support pipe 4 can be fitted.
And the first joint fitting 1 continuously below the upper tubular portion 8.
A tapered surface 9 having the same angle as the tapered surface 3 and diverging downward is formed, and the inner diameter at which the cylindrical portion 2 of the first fitting 1 can be fitted downwardly continuously to the tapered surface 9. A lower cylindrical portion 10 is formed. A bolt insertion hole is provided around the lower cylindrical portion 10 of the second joint fitting 7, and nuts 12, 12, 12,... Are fixed to the bolt insertion hole by arc welding or the like. Have been. Then, the upper support tube 11 is fitted into the second fitting 7, and after the fitting, the upper tubular portion 8 of the second fitting 7 and the upper support tube 11 are arc welded 21 to fix them together. The first joint fitting 1 and the lower support pipe 4 are fixed together by arc welding 20 and the second joint fitting 7 is fixed to the upper support pipe 11 by arc welding. This is also carried out in advance in a factory or the like. In this way, the lower support pipe 4 having the first fitting 1 fixed to the tip and the upper support pipe 11 having the second fitting 7 fixed are manufactured at the factory. is there. The first fitting 1 manufactured in the above factory
In order to carry the lower support pipe 4 having the fins fixed at the tip thereof and the upper support pipe 11 having the second joint fitting 7 fixed thereto to the construction site and construct a multi-stage lightning rod, the loaded upper support pipe 1 is required.
1 and the lower support pipe 4 are lifted on the roof by a crane or the like, and the upper support pipe 11 is fixed to the upper part of the lower support pipe 4 from the upper side of the tapered surface portion 3 of the first joint fitting 1 while being laid on the roof. It is inserted until the tapered surface 3 of the first joint fitting 1 and the tapered surface 9 of the second joint fitting 7 fixed to the upper support tube 11 come into close contact. When the tapered surface 9 of the second fitting 7 fixed to the upper supporting tube 11 and the tapered surface 3 of the first fitting 1 fixed to the lower supporting tube 4 are in close contact with each other, the lower supporting tube 4 is closed. And the upper support pipe 11 are connected to each other, and after checking the straightness, bolts 22, 22, 2 are attached to nuts 12, 12, 12 welded to bolt insertion holes around the lower cylindrical portion 10 of the second joint fitting 7.
Then, the cylindrical portion 2 of the first fitting 1 inserted into the second fitting 7 is firmly fixed with the bolt 22 to integrate the second fitting 7 and the first fitting 1. Next, bolts 13, 13, 13 are screwed into nuts 6, 6, 6 which are fixed by welding or the like to bolt insertion holes 5, 5, 5 drilled around the lower support tube 4, respectively. By fixing the lower support tube 4 and the upper support tube 11 inserted in the lower support tube 4 and integrating them, a multi-stage lightning rod at the rooftop of a building site is assembled. Then, the multi-stage lightning rod assembled in a state of being laid down on the roof is erected at a predetermined position on the roof. In the present embodiment, the two pipes of the lower support pipe and the upper support pipe have been described, but the first fitting is welded to the tip of the upper support pipe, and the second fitting is attached to the third support pipe. By welding the metal fittings, three support pipes can be connected, and a plurality of support pipes can be sequentially added in the same manner. As described above, a lightning rod in which the lower support pipe 4 and the upper support pipe 11 are integrated is erected on the roof. In this erected state, the second lightning rod fixed to the upper support pipe 11 is used. Since the tapered surface 9 of the fitting 7 and the tapered surface 3 of the first fitting 1 fixed to the lower support tube 4 are in contact at the same angle taper surface, the surface of the contact surface depends on the weight of the upper support tube 11. It is expected that pressure will be maintained. When the multistage lightning rod according to the present embodiment receives a lightning current, it comes into contact with the second joint fitting via a second joint fitting welded to the upper supporting pipe from the upper supporting pipe at a tapered surface. The first joint fitting is energized to flow from the lower support pipe welded to the first joint fitting to the ground wire, and in the present embodiment, the flow of the lightning current is caused by the joint part in surface contact. In addition, since the joint fittings and the support pipes are welded, the flow of the lightning current is extremely good. As described above, according to the present embodiment, all the arc welding work is performed at the production factory, and at the construction site where the multi-stage lightning rod is to be constructed, the work is only fastening with bolts. Work is not performed at the construction site, so there is no risk of sparks being scattered by welding, so there is no need to protect the building surface material during welding as in the past, and secure a power supply for welding. Etc. can be reduced. In addition, the connection between the lower support pipe and the upper support pipe is a surface contact between the tapered surfaces formed on the first joint metal fitting and the second joint metal fitting fixed to both the support pipes. There is no bending of the lightning rod due to According to the multi-stage lightning rod supporting pipe joint device of the present invention, the taper surface of the first joint metal fitting and the taper surface of the second joint metal fitting have the same angle, and the first joint metal fitting is attached to the lower supporting pipe. The metal fittings are previously welded to the upper support pipe side with the second joint fitting at the upper part at the production factory, and when assembling the upper support pipe and the lower support pipe at the construction site, the first fitting metal fitting and the second fitting metal fitting are assembled. Since the tapered surface is brought into surface contact with the connection, the surface pressure of the contact surface is increased by the weight of the upper support pipe in the above-mentioned surface contact, and the first joint fitting is used to maintain the contact state. And the second joint fitting are firmly fixed with bolts from the outside of the second joint fitting, and sufficient electrical and mechanical effects can be obtained. In the present invention, as described above, the welding work is all performed in advance at a factory or the like. At the construction site of the lightning rod, only the mechanical work of bolting is performed. There is no need for any work such as protection work on the surface material of the building or securing of a power supply for welding.Therefore, since welding is not performed at the construction site, there is no bending of the lightning rod due to welding deformation, and straightness is guaranteed. Things.

【図面の簡単な説明】 【図1】第一継手金具が溶着された下段支持管及び第二
継手金具が溶着された上段支持管の説明図。 【図2】下段支持管に上段支持管を接続した説明図。 【図3】従来の多段式避雷針の継手装置の説明図。 【符号の説明】 1 第一継手金具 2 筒部 3 テーパー面 4 下段支
持管 7 第二継手金具 8 上部筒
部 9 テーパー面 10 下部筒
部 11 上段支持管
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is an explanatory view of a lower support pipe to which a first fitting is welded and an upper support pipe to which a second fitting is welded. FIG. 2 is an explanatory diagram in which an upper support tube is connected to a lower support tube. FIG. 3 is an explanatory view of a conventional multi-stage lightning rod coupling device. [Description of Signs] 1 First fitting 2 Cylindrical part 3 Tapered surface 4 Lower supporting pipe 7 Second fitting 8 Upper cylindrical part 9 Tapered surface 10 Lower cylindrical part 11 Upper supporting pipe

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) H05F 3/04 F16B 7/14 H02G 13/00 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 7 , DB name) H05F 3/04 F16B 7/14 H02G 13/00

Claims (1)

(57)【特許請求の範囲】 【請求項1】先端に先細状のテーパ面が形成され、該テ
ーパ面と連続して下方に下段支持管が嵌入可能な筒部を
備えた第一継手金具と、上部に上段支持管が嵌入可能な
上部筒部と該筒部に連続して前記第一継手金具のテーパ
ー面と同一角度の末広がり状のテーパー面が形成され、
該テーパー面に連続して前記第一継手金具の筒部が嵌入
可能な筒部を設けるとともに、該筒部の周囲に複数のボ
ルト挿通用孔を穿設した第二継手金具とを備え、周囲に
複数のボルト挿通用孔を穿設した下段支持管を前記の第
一継手金具の筒部内に嵌入のうえ溶着し、前記第二継手
金具内に嵌入・溶着した上部支持管を、前記下段支持管
を嵌入した第一継手金具の先端より挿入し、前記第一継
手金具のテーパー面と第二継手金具のテーパー面とを密
接せしめ、下段支持管及び第二継手金具のボルト挿通用
孔に設けられたナットにボルトをねじ込み、第二継手金
具と第一継手金具及び下段支持管と上段支持管とを固定
したことを特徴とする多段式避雷針の支持管継手装置。
(1) A first joint fitting having a cylindrical portion having a tapered surface formed at a tip thereof and having a lower support pipe fitted downwardly continuously with the tapered surface. And, a divergent tapered surface having the same angle as the tapered surface of the first joint fitting is formed continuously with the upper cylindrical portion in which the upper support tube can be fitted in the upper portion and the cylindrical portion,
A second joint fitting having a plurality of bolt insertion holes formed around the cylindrical part is provided with a tubular part into which the tubular part of the first joint fitting can be fitted continuously to the tapered surface. The lower support pipe having a plurality of bolt insertion holes formed therein is fitted and welded into the cylindrical portion of the first fitting, and the upper support pipe fitted and welded in the second fitting is provided with the lower support. The pipe is inserted from the tip of the first fitting fitting into which the pipe is inserted, and the tapered surface of the first fitting fitting and the tapered surface of the second fitting fitting are brought into close contact with each other, and are provided in the lower support pipe and the bolt insertion holes of the second fitting fitting. A multi-stage lightning rod support pipe joint device, wherein a bolt is screwed into a nut, and the second joint fitting, the first joint fitting, and the lower support pipe and the upper support pipe are fixed.
JP2000001479A 2000-01-07 2000-01-07 Multi-stage lightning rod support pipe joint device Expired - Fee Related JP3401469B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000001479A JP3401469B2 (en) 2000-01-07 2000-01-07 Multi-stage lightning rod support pipe joint device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000001479A JP3401469B2 (en) 2000-01-07 2000-01-07 Multi-stage lightning rod support pipe joint device

Publications (2)

Publication Number Publication Date
JP2001196197A JP2001196197A (en) 2001-07-19
JP3401469B2 true JP3401469B2 (en) 2003-04-28

Family

ID=18530709

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000001479A Expired - Fee Related JP3401469B2 (en) 2000-01-07 2000-01-07 Multi-stage lightning rod support pipe joint device

Country Status (1)

Country Link
JP (1) JP3401469B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101621501B1 (en) * 2014-06-05 2016-05-16 주식회사 에스디 An assembly lightning rod
TWI651271B (en) 2016-05-27 2019-02-21 比利時商烏明克公司 Method for producing small-diameter nickel-lithium metal composite oxide powder
JP6596034B2 (en) * 2017-05-09 2019-10-23 日建リース工業株式会社 Joint member and frame structure

Also Published As

Publication number Publication date
JP2001196197A (en) 2001-07-19

Similar Documents

Publication Publication Date Title
US6340141B1 (en) Cable support systems, methods, and rack therefor
KR101563159B1 (en) Pile coupler
US10283881B2 (en) Electrical connection devices with welded wire leads
JP3401469B2 (en) Multi-stage lightning rod support pipe joint device
KR101126009B1 (en) Jointing structure of steel pipes and steel pipe pole with the structure
KR101343504B1 (en) Supporting device for establishing road facility
JP4878161B2 (en) Steel tube column joining method and joining jig
JP5877573B1 (en) Prop fixture
CN215009491U (en) Fixing part for installing wire pipe
CN1781002A (en) Pipe fixing system
JP3251928B2 (en) Lightning protection method for the outer wall side of high-rise building.
JP2009102896A (en) Structure and method for electrical connection at connection part of precast concrete column
CN207032255U (en) Bracing members anti-drop device
JPH06108701A (en) Different-diameter steel-pipe column
JP6800175B2 (en) How to install the jig for installing the prefabricated structure and the terminal junction box on the power cable
US20040112621A1 (en) Easy installation sub-grade conduit connector
JP2000045572A (en) Temporary electric pole for dwelling construction
JP3947504B2 (en) Lightning mounting hardware
JP3510162B2 (en) How to install fittings
JP2912928B2 (en) Support structure of lightning rod in lightning rod
CN219874964U (en) Electrical circuit junction box
KR102214930B1 (en) steel pipe pole installed over concrete pole and construction method
JP4332896B2 (en) Foundation concrete reinforcement method
JP2534138B2 (en) Piping trench and its construction method
JP2609510B2 (en) Roof construction method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees