JP3177906B2 - Preceding partition wall construction method in the ceiling - Google Patents
Preceding partition wall construction method in the ceilingInfo
- Publication number
- JP3177906B2 JP3177906B2 JP19768493A JP19768493A JP3177906B2 JP 3177906 B2 JP3177906 B2 JP 3177906B2 JP 19768493 A JP19768493 A JP 19768493A JP 19768493 A JP19768493 A JP 19768493A JP 3177906 B2 JP3177906 B2 JP 3177906B2
- Authority
- JP
- Japan
- Prior art keywords
- wall
- ceiling
- partition wall
- equipment
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Building Environments (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、上方スラブの裏面から
天井内先行間仕切壁を形成する工法に関するものであ
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for forming a precedent partition in a ceiling from the back surface of an upper slab.
【0002】[0002]
【従来の技術】従来、居室等を区画する間仕切壁におい
ては、上方スラブの裏面からスラブ面に亘って形成され
ることが多い。そしてこのような間仕切壁はスラブ面が
形成されたフロアにおいて、スラブ面に墨出しした芯墨
や仕上げ墨などに基づいてを鋼製壁下地材(スタッド)
を組み上げ、これに下張りボードや上張りボードを張っ
て形成されている。また、天井内に位置することになる
部分にあっては、前記鋼製壁下地材と天井内を引き回す
配管やダクトなどの設備関連部材との取り合いを考慮し
ながら鋼製壁下地材を配置しており、こののち、前記鋼
製壁下地材に対して石膏ボードやリブラスなどの面材を
張り、所要の被覆加工を施してこの部分を耐火壁構造と
したり、遮音壁構造として構成している。このようにし
て間仕切壁が形成されたのちに、つぎの天井工事の段階
に移行している。2. Description of the Related Art Conventionally, a partition wall for partitioning a living room or the like is often formed from the back surface of an upper slab to the slab surface. Such a partition wall is made of a steel wall base material (stud) on a floor on which a slab surface is formed, based on a black ink or a finished black ink which is inked on the slab surface.
It is formed by assembling a lower board or an upper board. Further, in the portion to be located in the ceiling, the steel wall base material is arranged in consideration of the connection between the steel wall base material and equipment-related members such as pipes and ducts running around the ceiling. After that, a surface material such as a gypsum board or rib lath is attached to the steel wall base material, and a required coating process is performed to form a fire-resistant wall structure or a sound insulation wall structure. After the partition walls are formed in this way, the process proceeds to the next ceiling construction stage.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、細かく
区画された小部屋が多い建物の間仕切壁を形成する場
合、天井内に配置される設備関連部材と鋼製壁下地材と
の取り合い部分が多くなり、このためフロアの上下方向
に渡す鋼製壁下地材に対して、現場にて前記取り合いに
応じながら切り落としなどの加工を施す必要があり、端
材も多く発生して不経済になり易い。また前記取り合い
部分では、設備関係部材(配管やダクトなど)周りで鋼
製壁下地材を組み上げ、面材等を張ったのちに、耐火性
や遮音性を高めるための被覆作業を行うことになる。こ
のため、設備関係材料が邪魔になって前記被覆作業が困
難になり易いという問題も生じている。However, in the case of forming a partition wall of a building having many small rooms which are finely divided, a large number of portions between the equipment-related members arranged in the ceiling and the steel wall base material increase. For this reason, it is necessary to perform processing such as cutting off the steel wall base material to be passed in the vertical direction of the floor while responding to the above-mentioned arrangement at the site, and a large amount of offcuts are generated, which tends to be uneconomical. Further, in the connection portion, a steel wall base material is assembled around equipment-related members (such as pipes and ducts), and after covering the surface materials and the like, coating work is performed to enhance fire resistance and sound insulation. . For this reason, there also arises a problem that the equipment-related materials are in the way and the coating work is likely to be difficult.
【0004】そこで本発明は上記した事情に鑑み、天井
内となる部分に設備スリーブ枠を有する間仕切壁の一部
を予め下がり壁として形成し、設備関連部材の配置前に
この下がり壁に被覆加工が施せるようにするとともに、
前記下がり壁の形成に際して定尺物の鋼製壁下地材が使
用できるようにすることを課題とし、鋼製壁下地材の経
済的な利用を図るとともに、耐火、遮音工事の作業性を
向上させることを目的とする。[0004] In view of the above circumstances, the present invention forms a part of a partition wall having an equipment sleeve frame in a part inside the ceiling as a down wall in advance, and coats the down wall before placing the equipment related members. Be able to apply
An object of the present invention is to make it possible to use a fixed-length steel wall base material when forming the falling wall, to economically use the steel wall base material, and to improve workability of fireproof and sound insulation work. The purpose is to:
【0005】[0005]
【課題を解決するための手段】本発明は上記した課題を
考慮してなされたもので、上方スラブの裏面側から天井
仕上げ高さの上方位置までに、間仕切壁における天井内
下がり壁の軸組を行い、該軸組に設備スリーブ枠を取り
付け、面材を張ったのち、所要の被覆加工を施して天井
内下がり壁を形成し、前記天井内下がり壁の設備スリー
ブに天井内配管ダクトなどの設備関連部材を通して設置
することにより、上記した課題を解消するものである。SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems, and has a structure in which a ceiling inner lower wall of a partition wall is provided from a rear surface of an upper slab to a position above a ceiling finishing height. After mounting the equipment sleeve frame to the frame, and covering the surface material, perform the required coating process to form a ceiling inner falling wall, the ceiling inner lower wall equipment sleeve to the ceiling piping duct etc. The above-mentioned problem is solved by installing through the equipment-related members.
【0006】[0006]
【作用】本発明においては、間仕切壁を設置する場所で
まず天井内となる部分に設備スリーブ枠を有する下がり
壁を形成する。そしてその下がり壁に耐火被覆を施した
り遮音被覆を施したりする作業に移る。そののち設備関
連部材を前記下がり壁に開口している設備スリーブに通
すことにより、天井内となる部分においての間仕切壁が
形成される。According to the present invention, at the place where the partition wall is to be installed, first, a descending wall having an equipment sleeve frame is formed in a portion inside the ceiling. Then, work is performed to apply a fireproof coating or a sound insulation coating to the descending wall. Thereafter, by passing the equipment-related member through the equipment sleeve that opens to the lower wall, a partition wall is formed in a portion inside the ceiling.
【0007】[0007]
【実施例】つぎに本発明を図1から図5に示す一実施例
に基づいて詳細に説明する。図1と図2とは完成した間
仕切壁1を示すもので、該間仕切壁1は、上方スラブa
の裏面となるフロアデッキbと天井仕上げ高さcから所
要量d(130mm程度)上方に上がった位置eとの間
に亘る下がり壁2と、この下がり壁2の下端に連結され
てスラブ面(床面)fに達する間仕切壁本体3とからな
るものである。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, the present invention will be described in detail based on one embodiment shown in FIGS. FIGS. 1 and 2 show a completed partition wall 1, which is composed of an upper slab a
A lower wall 2 extending between a floor deck b serving as a back surface of the lower wall and a position e rising upward from the ceiling finishing height c by a required amount d (about 130 mm), and a slab surface ( (Floor surface) f.
【0008】図2に示すように下がり壁2は、上方スラ
ブaに沿ってアンカーピン3にて固定されたランナー
(鋼製[型部材)4と下端側に位置するランナー5との
間に鋼製壁下地材(スタッド:C型部材)6を配置し
て、この鋼製壁下地材6と前記ランナー4,5とを溶接
した軸組を有し(図中溶接個所を・印にて示す)、これ
を上方スラブa側から降ろしたブレース7にて支えるよ
うにするとともに、側面それぞれにリブラスなどの面材
8を張っている。そして前記面材8に岩綿モルタル9を
吹き付けて耐火壁構造とされている。間仕切壁本体3
は、図2に示すように上記下がり壁2の下端に位置する
下端継ぎ材10に溶接されたランナー(鋼製[型部材)
11とスラブ面fに固定されたランナー12との間に鋼
製壁下地材(C型部材)13を配置し、この鋼製壁下地
材13とランナー11,12とを溶接した軸組を有し、
この両面に石膏ボードからなる下張りボード14、上張
りボード15を張ったものとされている。そして図1に
示すように下がり壁2と間仕切壁本体3との連続部分に
岩綿モルタル16が吹き付けられて覆っている。As shown in FIG. 2, a falling wall 2 is provided between a runner (steel [mold member] 4) fixed by an anchor pin 3 along an upper slab a and a runner 5 located at a lower end side. There is a shaft assembly in which a steel wall base material (stud: C-shaped member) 6 is arranged and the steel wall base material 6 is welded to the runners 4 and 5 (welded portions are indicated by marks in the figure). ), This is supported by a brace 7 lowered from the upper slab a side, and a face material 8 such as a rib lath is provided on each side surface. The face material 8 is sprayed with rock wool mortar 9 to form a fire-resistant wall structure. Partition wall body 3
Is a runner (steel [mold member]) welded to the lower end joint member 10 located at the lower end of the falling wall 2 as shown in FIG.
A steel wall base material (C-shaped member) 13 is disposed between the runner 11 and the runner 12 fixed to the slab surface f, and the steel wall base material 13 and the runners 11 and 12 are welded to each other. And
A lower board 14 and an upper board 15 made of a gypsum board are provided on both sides. Then, as shown in FIG. 1, rock wool mortar 16 is sprayed and covers the continuous portion between the descending wall 2 and the partition wall main body 3.
【0009】上記した構造の間仕切壁1はつぎのように
して形成される。 (下がり壁の形成)まず、スラブ面に間仕切壁の芯墨及
び仕上げ墨を墨出しし、これらに合わせて空調、電気、
防災用配管などの設備関連部材の墨出しもスラブ面に行
う。前記間仕切壁の地墨に基づいて、天井仕上げ高さか
ら例えば130mm程度上がった位置を下端として、上
方スラブの裏面(フロアデッキb)から前記位置までの
間に上述したランナー4,5と鋼製壁下地材6、下端継
ぎ材10により下がり壁の軸組を行うとともに、この軸
組17に合わせて前記設備関連部材の地墨に基づきなが
ら設備スリーブ枠18を設置する(図3参照)。軸組1
7が完成するとリブラスからなる面材8を張って全体に
岩綿モルタル9を吹き付けて被覆し、これによって下が
り壁2が得られる(図4参照)。間仕切壁に対して設定
される性能に合わせて面材8としての素材や被覆材料が
適宜に選択されるものである。なお、説明を容易にする
ため、図4においては、特定の下がり壁のみに岩綿モル
タルを吹き付けた状態で示したが、この岩綿モルタルの
吹付けはフロアデッキや鉄骨梁などに対しても行われる
ものである。The partition wall 1 having the above structure is formed as follows. (Formation of falling wall) First, black ink and finishing ink of the partition wall are inked on the slab surface, and air conditioning, electricity,
Marking of equipment-related members such as piping for disaster prevention is also performed on the slab surface. The runners 4 and 5 described above and steel are used between the back surface of the upper slab (floor deck b) and the above position, with the lower end being a position raised by about 130 mm from the ceiling finishing height, based on the black ink of the partition wall. The lower wall is assembled with the wall base material 6 and the lower end joining material 10, and the equipment sleeve frame 18 is installed in accordance with the shaft assembly 17 based on the ground color of the equipment-related member (see FIG. 3). Frame 1
When 7 is completed, a face material 8 made of rib brass is stretched, and the whole is sprayed with rock wool mortar 9 to cover, thereby obtaining the falling wall 2 (see FIG. 4). The material and the covering material as the face material 8 are appropriately selected according to the performance set for the partition wall. In addition, in order to facilitate the explanation, FIG. 4 shows a state in which the rock wool mortar is sprayed only on the specific descending wall, but the spraying of the rock wool mortar is also applied to the floor deck, the steel beam and the like. Is what is done.
【0010】(関連設備部材の設置)上述したように下
がり壁2が完成したのちは、フロアへ配管やダクトなど
の各種設備関連部材を運び込み、これらを前記下がり壁
2の設備スリーブ19に通して所要位置に設置する(図
5)。これらの作業はスラブ面上に間仕切壁本体が形成
されていないことから、無人搬送車などの台車を利用し
て部材を運び込み、ローリングタワーや作業用リフトな
どの機器を利用しながら設置が行われる。そして設備関
連部材の種類に応じて必要なものに関しては保温工事を
行うことになる。(Installation of Related Equipment Members) After the falling wall 2 is completed as described above, various equipment related members such as pipes and ducts are carried to the floor, and these are passed through the equipment sleeve 19 of the falling wall 2. Install at the required position (Fig. 5). In these operations, since the partition wall main body is not formed on the slab surface, the members are carried using a cart such as an automatic guided vehicle, and the installation is performed using equipment such as a rolling tower and a work lift. . Then, heat insulation work will be performed on those necessary according to the type of equipment-related members.
【0011】(間仕切壁本体の形成)設備関連部材の設
置が終了したのちは間仕切壁本体の形成となる。上述し
たように下がり壁2の下端からスラブ面fの間にランナ
ー11,12、鋼製壁下地材13により間仕切本体の軸
組を行い、この軸組の両面に下張りボード、上張りボー
ドを張って間仕切壁本体3が得られ(図1参照)、上記
下がり壁2とこれに連続する間仕切壁本体3の形成によ
り間仕切壁1が完成する。こののち下がり壁2と間仕切
壁本体3との連続部分に岩綿モルタル16が吹き付けら
れる。(Formation of Partition Wall Body) After the installation of the equipment-related members is completed, the partition wall body is formed. As described above, the partition body is framed by the runners 11 and 12 and the steel wall base material 13 between the lower end of the falling wall 2 and the slab surface f, and a lower board and an upper board are stretched on both sides of the frame. As a result, the partition wall main body 3 is obtained (see FIG. 1), and the partition wall 1 is completed by forming the above-mentioned descending wall 2 and the partition wall main body 3 continuous therewith. Thereafter, rock wool mortar 16 is sprayed on a continuous portion between the descending wall 2 and the partition wall main body 3.
【0012】[0012]
【発明の効果】以上説明したように、本発明によれば、
上方スラブの裏面側から天井仕上げ高さの上方位置まで
に、間仕切壁における天井内下がり壁の軸組を行い、該
軸組に設備スリーブ枠を取り付け、面材を張ったのち、
所要の被覆加工を施して天井内下がり壁を形成し、前記
天井内下がり壁の設備スリーブに天井内配管ダクトなど
の設備関連部材を通して設置することを特徴とするもの
である。As described above, according to the present invention,
From the back side of the upper slab to the upper position of the ceiling finishing height, perform the frame assembly of the ceiling lowering wall in the partition wall, attach the equipment sleeve frame to the frame, and stretch the surface material,
A required covering process is performed to form a ceiling inner falling wall, and the equipment sleeve of the ceiling lower wall is installed through a facility-related member such as a ceiling piping duct.
【0013】このように間仕切壁を設ける位置におい
て、天井内となる部分には、天井仕上げ高さより上方位
置を下端として下がり壁を間仕切壁本体とは別個に形成
することから、上方スラブからスラブ面まで亘る長尺な
鋼板壁下地材を設備関連部材との取り合いによって長さ
調整しなければならないという必要性がなくなり、そし
て下がり壁の高さ寸法を一定のものとすることにより、
その高さ方向に亘る鋼製壁下地材として、予め一定長さ
に切断したものを使用することができるようになり、特
に天井高さが一定となる小部屋が多く設定されている場
合には、部材を極めて有効に使用できるようになる。ま
た鋼製壁下地材や面材などの部材寸法が一定となれば、
一定寸法に作成されている既製品を使用できるようにな
り、切り落としなどの残材の発生が極めて少なくなって
清掃費用、産業廃棄物処理費用を低減できるようにな
る。[0013] In the position where the partition wall is provided, in the portion inside the ceiling, the lower wall is formed with the lower position above the ceiling finishing height as a lower end, and the wall is formed separately from the partition wall main body. Eliminating the need to adjust the length of the long steel plate wall base material up to the length of the installation-related members, and making the height of the falling wall constant,
As a steel wall base material over the height direction, it is possible to use a material cut in advance to a fixed length, especially when many small rooms with a fixed ceiling height are set. , Members can be used very effectively. Also, if the dimensions of steel wall base materials and face materials are constant,
It is possible to use an off-the-shelf product having a certain size, and it is possible to reduce the cost of cleaning and the cost of treating industrial waste, by minimizing the generation of residual materials such as cut-off.
【0014】さらに配管やダクトなどの設備関連部材が
設置される前にこれらの部材が貫通配置されることにな
る下がり壁が完成しているため、前記設備関連部材に邪
魔されることなく、天井内となる部分の耐火、遮音工事
が行えるようになりその施工が容易になる。また、間仕
切壁本体が形成される前に設備関連部材の搬入、設置を
広いフロアで行え、無人搬送車や大型運搬台車、ローリ
ングタワー、作業リフトなどの機器の使用が可能となっ
て、効率的に作業を行えるようになるなど、実用性に極
めて優れた効果を奏するものである。Further, before the installation of the equipment-related members such as pipes and ducts, the falling walls through which these members are disposed are completed, so that the ceiling-wall is not disturbed by the equipment-related members. Fireproofing and sound insulation work can be performed on the inner part, which facilitates the work. In addition, equipment related members can be loaded and installed on a large floor before the partition wall body is formed, making it possible to use equipment such as automatic guided vehicles, large transport vehicles, rolling towers, work lifts, etc. This makes it possible to carry out the work in a short time, and has an effect extremely excellent in practicality.
【図1】本発明に係る天井内先行間仕切壁工法による間
仕切壁を示す説明図である。FIG. 1 is an explanatory view showing a partition wall by a precedent partition wall construction method according to the present invention.
【図2】下がり壁を示す説明図である。FIG. 2 is an explanatory view showing a falling wall.
【図3】下がり壁の軸組を示す説明図である。FIG. 3 is an explanatory view showing a shaft set of a descending wall.
【図4】被覆を行った下がり壁を示す説明図である。FIG. 4 is an explanatory view showing a falling wall that has been coated.
【図5】設備関連部材を設置した状態を示す説明図であ
る。FIG. 5 is an explanatory diagram showing a state where equipment-related members are installed.
1…間仕切壁 2…下がり壁 3…間仕切壁本体 4,5,11,12…ランナー 6,13…鋼製壁下地材 8…面材 9,16…岩綿モルタル 10…下端継ぎ材 18…設備スリーブ枠 DESCRIPTION OF SYMBOLS 1 ... Partition wall 2 ... Falling wall 3 ... Partition wall main body 4, 5, 11, 12 ... Runner 6, 13 ... Steel wall base material 8 ... Face material 9, 16 ... Rock wool mortar 10 ... Lower end joining material 18 ... Equipment Sleeve frame
フロントページの続き (56)参考文献 特開 昭63−308289(JP,A) 特開 昭60−47144(JP,A) 特開 平3−249495(JP,A) 実開 昭62−163208(JP,U) 実開 平4−120808(JP,U) 登録実用新案3004736(JP,U) 特許2915664(JP,B2) 特公 平1−40190(JP,B2) 実公 平7−48277(JP,Y2) 実公 昭62−12013(JP,Y2) 実公 平1−25132(JP,Y2) (58)調査した分野(Int.Cl.7,DB名) E04B 2/82 501 E04B 1/94 E04B 2/74 541 E04B 2/74 551 F16L 5/02 Continuation of the front page (56) References JP-A-63-308289 (JP, A) JP-A-60-47144 (JP, A) JP-A-3-249495 (JP, A) Jpn. , U) Japanese Utility Model Hei 4-120808 (JP, U) Registered Utility Model 3004736 (JP, U) Patent No. 2915664 (JP, B2) Japanese Patent Publication No. 1-40190 (JP, B2) Japanese Utility Model Utility Model No. 7-48277 (JP, U.S.A.) Y2) Jiko 62-12013 (JP, Y2) Jiko 1-25132 (JP, Y2) (58) Fields investigated (Int. Cl. 7 , DB name) E04B 2/82 501 E04B 1/94 E04B 2/74 541 E04B 2/74 551 F16L 5/02
Claims (1)
上方位置までに、間仕切壁における天井内下がり壁の軸
組を行い、該軸組に設備スリーブ枠を取り付け、面材を
張ったのち、所要の被覆加工を施して天井内下がり壁を
形成し、 前記天井内下がり壁の設備スリーブに天井内配管ダクト
などの設備関連部材を通して設置することを特徴とする
天井内先行間仕切壁工法。(1) From the back side of an upper slab to a position above a ceiling finishing height, a frame of a ceiling inner lowering wall in a partition wall is set, an equipment sleeve frame is attached to the frame, and a face material is stretched. A preparatory partitioning method in the ceiling, wherein a required covering process is performed to form an in-ceiling inferior wall, and equipment-related members such as in-ceiling piping ducts are installed in the in-ceiling inferior wall equipment sleeve.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19768493A JP3177906B2 (en) | 1993-07-16 | 1993-07-16 | Preceding partition wall construction method in the ceiling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19768493A JP3177906B2 (en) | 1993-07-16 | 1993-07-16 | Preceding partition wall construction method in the ceiling |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0734572A JPH0734572A (en) | 1995-02-03 |
JP3177906B2 true JP3177906B2 (en) | 2001-06-18 |
Family
ID=16378631
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP19768493A Expired - Fee Related JP3177906B2 (en) | 1993-07-16 | 1993-07-16 | Preceding partition wall construction method in the ceiling |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3177906B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5588653B2 (en) * | 2009-10-13 | 2014-09-10 | ミサワホーム株式会社 | How to renovate unit buildings |
JP6553859B2 (en) * | 2014-10-02 | 2019-07-31 | 株式会社フジタ | Seismic support structure for partition walls |
WO2016118653A1 (en) | 2015-01-20 | 2016-07-28 | Aditazz, Inc. | Modular interior partition for a structural frame building |
JP6078110B2 (en) * | 2015-06-19 | 2017-02-08 | 新菱冷熱工業株式会社 | Partition wall construction method using wall penetration sleeve unit |
-
1993
- 1993-07-16 JP JP19768493A patent/JP3177906B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH0734572A (en) | 1995-02-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
HUT77563A (en) | Metal support framework for low profile raised panel flooring and a method for creating the support structures | |
JPH11247324A (en) | Refractory structural wall | |
JP3177906B2 (en) | Preceding partition wall construction method in the ceiling | |
US2034265A (en) | Prefabricated house and building construction | |
JPH10140704A (en) | Stud for assembling fire-resisting wall and fire-resisting wall structure | |
JPH083537Y2 (en) | Fireproof coating and fireproof coated steel frame | |
JP2594658B2 (en) | Building unit ceiling structure | |
JP3115417B2 (en) | Vertical joint structure | |
JP3577061B2 (en) | Insulation composite panel with earthquake and fire resistance | |
JP3147673B2 (en) | Installation method of fire-resistant partition wall in steel frame building | |
JPH08260659A (en) | Fireproof wall structure | |
JPH0748277Y2 (en) | Penetration structure such as duct between lower beams | |
JPH0213629Y2 (en) | ||
JPH0216218Y2 (en) | ||
JP2842706B2 (en) | Floor structure and floor construction method of wooden building | |
JP3752657B2 (en) | building | |
JPH0438348A (en) | Execution method of equipment duct utilizing hollow slab | |
JPS6130100B2 (en) | ||
JP2984738B2 (en) | Installation structure of sprinkler equipment in buildings | |
JPH04127094U (en) | Fire protection structure of the hull living quarters | |
JPH02108748A (en) | Fireproof covering structural steelwork | |
JP2000110250A (en) | Roof panel and unit building | |
JP2867316B2 (en) | Access wall and architectural wiring structure | |
JP4143846B2 (en) | Steel beam fireproof coating structure | |
JP3036660U (en) | Insulation sheet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |