JP3146702U - Temporary storage area for remaining soil - Google Patents

Temporary storage area for remaining soil Download PDF

Info

Publication number
JP3146702U
JP3146702U JP2008006502U JP2008006502U JP3146702U JP 3146702 U JP3146702 U JP 3146702U JP 2008006502 U JP2008006502 U JP 2008006502U JP 2008006502 U JP2008006502 U JP 2008006502U JP 3146702 U JP3146702 U JP 3146702U
Authority
JP
Japan
Prior art keywords
soil
space
remaining
temporary storage
remaining soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2008006502U
Other languages
Japanese (ja)
Inventor
伸二 楠木
Original Assignee
株式会社楠建
株式会社Tmo
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社楠建, 株式会社Tmo filed Critical 株式会社楠建
Priority to JP2008006502U priority Critical patent/JP3146702U/en
Application granted granted Critical
Publication of JP3146702U publication Critical patent/JP3146702U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract


【課題】適切な土質で必要な量を、現場工程に合致させ、供給できる残土在庫スペースを設置して、盛土材として不適切な残土は、残土在庫スペースにおいて加工し、再利用可能な材料とする残土の仮置き場である。
【解決手段】残土発生が予定され、盛土材が必要とされる工事現場の近傍に、適宜な広さを有するスペース1を取り囲み手段2で囲い、該スペースには数種類の残土Xを仮置きでき、土質の異なる残土Xaごとに、それぞれ周囲を大型土のう等の仕切材3で囲む残土仮置きスペース4と、盛土には不適切な材の改良を行う改良スペース4aとを設け、前記スペースへの出入り口には、ゲート5を設け、該ゲートに、あるいは、ゲート近傍に、ダンプ計量所6を設け、前記スペースへの搬出・入する車両の特定を行う手段7と、車両に積載された積載量を計測する手段8と共に、搬出・入の管理を行う管理手段9を備えた残土の仮置き場。
【選択図】 図1

[PROBLEMS] To establish a residual soil inventory space that can be supplied with an appropriate amount of soil with the required amount according to the on-site process. It is a temporary storage place for the remaining soil.
SOLUTION: A space 1 having an appropriate size is surrounded by a surrounding means 2 in the vicinity of a construction site where a surplus soil is expected and a filling material is required, and several kinds of remaining soil X can be temporarily placed in the space. For each of the remaining soils Xa having different soil properties, a remaining soil temporary storage space 4 surrounded by a partition material 3 such as a large sandbag and an improved space 4a for improving materials inappropriate for embankment are provided. A gate 5 is provided at the entrance, a dump weighing station 6 is provided at or near the gate, means 7 for specifying a vehicle to be carried into and out of the space, and a load capacity loaded on the vehicle Temporary storage place for the remaining soil, which includes management means 9 for managing unloading / in / out as well as means 8 for measuring the load.
[Selection] Figure 1

Description

この考案は、残土の仮置き場に関する。   This invention relates to a temporary storage place for remaining soil.

従来、建築工事から発生する「余分な土」(以下、残土と称する)を、どのように有効利用するかというテーマは、建築工事に携わる関係者には、大きな課題である。   Conventionally, the theme of how to effectively use “excess soil” (hereinafter referred to as “remaining soil”) generated from construction work is a major issue for those involved in construction work.

これらの問題については、2002年5月より施工されている建設リサイクル法をはじめ、発生残土の有効活用に関連する諸法律も整備され、関係官庁をはじめ業界全体で取り組んでいる。   These issues, including the Construction Recycling Law, which has been in place since May 2002, have been developed and various laws related to the effective use of the generated surplus soil are being addressed throughout the industry, including relevant government agencies.

しかし、発生する残土の「量」や、その「土質」及び「時期」と受入側(盛土条件)との条件が合わないということがあった。
即ち,受入れ現場(盛土条件)で使用する「量」など、使用する(盛土作業)工事側には当該工事における品質確保や工程管理上、諸々の適切条件が必要となる。
However, there were cases where the amount of residual soil generated, the “soil quality” and “time”, and the conditions on the receiving side (filling conditions) did not match.
That is, the appropriate amount of conditions (such as “amount”) used at the receiving site (filling condition) is necessary for the work (filling work) to ensure quality and process management.

反面、発生する側にも諸条件があり、発生する側(搬出側)と受入側(盛土作業側)の条件を一致させることは非常に困難である。   On the other hand, there are various conditions on the generating side, and it is very difficult to match the conditions on the generating side (unloading side) and the receiving side (filling work side).

以上のことから現場では、いろいろな問題が発生しており、残土の有効な利用がされていなのが現実であった。   As a result, various problems have occurred in the field, and the reality is that the remaining soil has not been effectively used.

そこで、この考案は、適切な土質で必要な量を、現場工程に合致させ、供給できる残土在庫スペースを設置して、適宜供給できるようにし、盛土材として不適切な残土は、残土在庫スペースにおいて加工し、再利用可能な材料とする残土の仮置き場を設けることにある。   In view of this, the present invention is designed so that the necessary amount of soil with the appropriate soil quality can be matched to the on-site process, and can be supplied as appropriate, so that it can be supplied as appropriate. The purpose is to provide a temporary storage place for the remaining soil to be processed and reused.

この考案は、残土発生が予定される工事と盛土材が必要とされる工事(事業)周辺に、残土を仮置きできるスペースを以下の条件で確保する。
1) 数種類の残土が仮置きでき、盛土不適切材の改良スペースを合わせ、ダンプ搬出・搬入が可能なスペースを確保する。
2) 可能な限り、民家に隣接する場所や常時多数の人が出入りする施設がある場所は避ける。
This device secures a space where temporary soil can be temporarily placed around the construction (business) where construction of the residual soil is planned and the embankment material is required under the following conditions.
1) A few types of remaining soil can be temporarily placed, and an improved space for inappropriate embankment materials is combined with a space for dump dumping and loading.
2) Avoid locations that are adjacent to private houses and facilities where many people come and go at all times.

そして、残土在庫スペースには、以下の設備を設ける。
1) 敷地内排水。必要に応じて防塵シート・防音シート及び境界フェンスなどを設置する。
2) 残置する残土は、その土質ごとに一定場所に残置して管理する。周辺は大型土のうで囲う。
3) 残置する残土量は、種類毎に適宜一定場所に残置して保管する。
4) 残土の積み込みや改良・移動に必要な重機の確保。
The remaining equipment inventory space will be equipped with the following facilities.
1) On-site drainage. Install dustproof sheets, soundproof sheets, boundary fences, etc. as necessary.
2) The remaining soil to be retained is managed by leaving it in a certain place for each soil quality. Surround the area with large sandbags.
3) The amount of remaining soil to be retained is stored in a certain place as appropriate for each type.
4) Secure heavy machinery necessary for loading, improving and moving the remaining soil.

この考案によると、
1) 残土処分の費用が不要となり、工事原価を削減し、かつ、エコに貢献できる。
2) 盛土材搬入工事において、工程と盛土の品質向上に寄与できる。
3) 表土やシルトなどの盛土不適切残土も、使用が可能となる。
4) 大型土嚢等災害時の資材料を常備し、災害発生時にすぐに対応できる。
5) 災害時の流出土砂を即ヤードに撤去し、復旧工事に再利用でき、早期復旧に貢献 できる。
6) 残土搬出入時作業をコンピューター管理し、省力化を実現する、
等の極めて有益なる効果を奏するものである。
According to this device,
1) The cost of disposal of residual soil is not required, construction costs can be reduced, and the environment can be contributed to.
2) Contributing to improving the quality of the process and banking in the banking work.
3) Unfilled surplus soil such as topsoil and silt can be used.
4) Materials for disasters such as large sandbags are always available and can be dealt with immediately in the event of a disaster.
5) Sediment in case of a disaster can be removed immediately to the yard and reused for restoration work, contributing to early restoration.
6) Computer management of the work at the time of carrying in and out of the remaining soil to realize labor saving.
It has a very beneficial effect.

先ず、残土発生が予定される工事現場と、盛土材が必要とされる工事現場の近傍に、適宜な広さを有するスペースを取り囲み手段で囲って設け、該スペースには数種類の残土を仮置きでき、土質の異なる残土ごとに、それぞれ周囲を大型土のう等の仕切材で囲む残土仮置きスペースと、盛土には不適切な材の改良を行う改良スペースとを設け、前記スペースへの出入り口には、ゲートを設け、該ゲートに、あるいは、ゲート近傍に、ダンプ計量所を設け、該スペースへの搬出・入する車両の特定を行う手段と、車両に積載された積載量を計測する手段と共に、搬出・入の管理を行う管理手段を備えたことを特徴とする残土の仮置き場である。   First, in the vicinity of a construction site where residual soil is scheduled to be generated and a construction site where embankment material is required, a space having an appropriate area is surrounded by surrounding means, and several types of residual soil are temporarily placed in the space. For each remaining soil of different soil quality, there is a temporary storage space for surrounding soil surrounded by a partition material such as a large sandbag, and an improved space for improving materials inappropriate for embankment, and at the entrance to the space A gate is provided, a dump weighing station is provided at or near the gate, a means for specifying a vehicle to be carried into and out of the space, and a means for measuring the load loaded on the vehicle, This is a temporary storage place for the remaining soil, characterized by having a management means for managing carry-out / in.

この考案の一実施例を図面に従って詳述すると、残土発生が予定される工事現場と、盛土材が必要とされる工事現場の近傍に、適宜な広さを有するスペース(1)を取り囲み手段(2)で囲って設け、該スペースには数種類の残土(X)を仮置きでき、土質の異なる残土(Xa)ごとに、それぞれ周囲を大型土のう等の仕切材(3)で囲む残土仮置きスペース(4)と、盛土には不適切な材の改良を行う改良スペース(4a)とを設け、前記スペース(1)への出入り口には、ゲート(5)を設け、該ゲート(5)に、あるいは、ゲート近傍に、ダンプ計量所(6)を設け、前記スペース(1)への搬出・入する車両の特定を行う手段(7)と、車両に積載された積載量を計測する手段(8)と共に、搬出・入の管理を行う管理手段(9)を備えたことを特徴とする残土の仮置き場から構成される。   An embodiment of the present invention will be described in detail with reference to the drawings. A space (1) having an appropriate size is enclosed in the vicinity of a construction site where residual soil is expected to be generated and a construction site where embankment is required. 2) Surrounded by a space for temporary storage of several types of residual soil (X), and for each residual soil (Xa) with different soil properties, the surrounding space is surrounded by a partition material (3) such as a large sandbag. (4) and an improved space (4a) for improving materials inappropriate for embankment are provided, and a gate (5) is provided at the entrance to the space (1), and the gate (5) Alternatively, a dump weighing place (6) is provided in the vicinity of the gate, a means (7) for specifying a vehicle to be carried into and out of the space (1), and a means (8) for measuring the load loaded on the vehicle. ) And management means (9) for carrying out management Composed from the temporary storage of waste soil, characterized in that was example.

そして、前記取り囲み手段(2)が、防塵シート、防音シート、境界フェンスから選ばれた1または、複数の部材であり、必要に応じて設けるものである。   The surrounding means (2) is one or a plurality of members selected from a dustproof sheet, a soundproof sheet, and a boundary fence, and is provided as necessary.

盛土には不適切な材の改良を行う改良スペース(4a)には、適宜な土に改良するトロンメルやスケルトンバケット等の土木機械等の機材を常備しておき、必要に応じて、ボンテラン工法などの土質改良施設を設置するものである。   In the improvement space (4a) where materials that are inappropriate for embankment are improved, equipment such as civil engineering machines such as trommels and skeleton buckets that are improved to appropriate soil are always available. A soil improvement facility will be installed.

又、この考案に使用する,車両の特定を行う手段(7)とは、センサーで感知し、搬出・入の車両(ダンプ)の積載量と車両のナンバープレート等を撮影するセンサーカメラを用いて行うものである。   Also, the vehicle identification means (7) used in this device is a sensor camera that senses with a sensor and photographs the loading / unloading vehicle (dump) loading capacity, vehicle license plate, etc. Is what you do.

また、この考案に使用する,積載量を計測する手段(8)とは、計量機を用いて計測し、そのデータはコンピューター(図示せず)を用いて管理し、データの分析・集積を行うものである。   Also, the means (8) for measuring the load capacity used in this device is measured using a weighing machine, the data is managed using a computer (not shown), and the data is analyzed and accumulated. Is.

さらに、搬出・入の管理を行う管理手段(7)とは、搬出・搬入車両並びに積載量をコンピューター(図示せず)を用いて管理し、データの分析・集積をし、また、管理者と当該現場がリアルに閲覧可能となるようテステム設定するものである。   In addition, the management means (7) for managing the carry-out / in is to manage the carry-out / carry-in vehicle and the load amount using a computer (not shown), analyze and accumulate data, and The system is set so that the site can be viewed in real life.

また、このスペースを利用して、災害発生時に備え、大型土のう袋、ブルーシート、スコップ等の被災準備用具やダンプトラック・油圧ショベル等の土木機械器具の収納スペース(10)を常時完備しておけば、災害発生時には、即座に出動可能な状態としておく。   In addition, using this space, in case of a disaster, you should always have a storage space (10) for disaster preparation equipment such as large sandbags, blue sheets, and scoops, and civil engineering machinery and equipment such as dump trucks and hydraulic excavators. For example, in the event of a disaster, it should be ready for immediate dispatch.

この考案の残土の仮置き場を設置し、その技術を実施することにより、土木業界の活性化を通じて産業上の利用可能性がある。   By installing a temporary storage site for the remaining soil of this device and implementing the technology, there is industrial applicability through the activation of the civil engineering industry.

この考案の一実施例を示す平面図である。It is a top view which shows one Example of this device. この考案の一実施例を示す側面図である。It is a side view which shows one Example of this device.

符号の説明Explanation of symbols

1 スペース
2 取り囲み手段
3 仕切材
4 残土仮置きスペース
4a 改良スペース
5 ゲート
6 ダンプ計量所
7 車両の特定を行う手段
8 積載量を計測する手段
9 搬出・入の管理を行う管理手段
10 土木機械器具の収納スペース
X 残土
Xa 土質の異なる残土
DESCRIPTION OF SYMBOLS 1 Space 2 Surrounding means 3 Partition material 4 Temporary-soil temporary storage space 4a Improvement space 5 Gate 6 Dump weighing place 7 Means to specify a vehicle 8 Means to measure a load amount 9 Management means to manage carry-out / entry
10 Storage space for civil engineering machinery and equipment X Remaining soil Xa Remaining soil with different soil properties

Claims (2)

残土発生が予定される工事現場と、盛土材が必要とされる工事現場の近傍に、適宜な広さを有するスペース(1)を取り囲み手段(2)で囲って設け、該スペースには数種類の残土(X)を仮置きでき、土質の異なる残土(Xa)ごとに、それぞれ周囲を大型土のう等の仕切材(3)で囲む残土仮置きスペース(4)と、盛土には不適切な材の改良を行う改良スペース(4a)とを設け、前記スペース(1)への出入り口には、ゲート(5)を設け、該ゲート(5)に、あるいは、ゲート近傍に、ダンプ計量所(6)を設け、前記スペース(1)への搬出・入する車両の特定を行う手段(7)と、車両に積載された積載量を計測する手段(8)と共に、搬出・入の管理を行う管理手段(9)を備えたことを特徴とする残土の仮置き場。   A space (1) having an appropriate area is provided by surrounding means (2) in the vicinity of the construction site where the remaining soil is expected to be generated and the construction site where the embankment material is required. The remaining soil (X) can be temporarily placed, and for each remaining soil (Xa) of different soil quality, the remaining soil temporarily placing space (4) surrounding the surrounding area with a partition material (3) such as a large sandbag, and materials suitable for embankment An improvement space (4a) for improvement is provided, a gate (5) is provided at the entrance to the space (1), and a dump weighing station (6) is provided at or near the gate (5). Provided with a means (7) for specifying a vehicle to be carried into and out of the space (1) and a means (8) for measuring the load loaded on the vehicle, as well as a management means for managing carry-out / in ( 9) A temporary storage place for remaining soil, characterized by comprising 取り囲み手段(2)が、防塵シート、防音シート、境界フェンスから選ばれた1または、複数の部材であることを特徴とする請求項1記載の残土の仮置き場。 The temporary storage place for residual soil according to claim 1, wherein the surrounding means (2) is one or a plurality of members selected from a dustproof sheet, a soundproof sheet, and a boundary fence.
JP2008006502U 2008-09-16 2008-09-16 Temporary storage area for remaining soil Expired - Fee Related JP3146702U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008006502U JP3146702U (en) 2008-09-16 2008-09-16 Temporary storage area for remaining soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008006502U JP3146702U (en) 2008-09-16 2008-09-16 Temporary storage area for remaining soil

Publications (1)

Publication Number Publication Date
JP3146702U true JP3146702U (en) 2008-11-27

Family

ID=43296400

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008006502U Expired - Fee Related JP3146702U (en) 2008-09-16 2008-09-16 Temporary storage area for remaining soil

Country Status (1)

Country Link
JP (1) JP3146702U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017095061A (en) * 2015-11-27 2017-06-01 日立建機株式会社 Dump truck

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017095061A (en) * 2015-11-27 2017-06-01 日立建機株式会社 Dump truck

Similar Documents

Publication Publication Date Title
JP3146702U (en) Temporary storage area for remaining soil
Grubb et al. Field evaluation of crushed glass–dredged material blends
District Corps of Engineers
TW202134986A (en) Waterworks management system, notification device, waterworks management method, and program
Palermo et al. Sediment dredging, treatment and disposal
Matsimbe Optimization of shovel-truck productivity in quarries
JP2015222001A (en) Structure and method for mooring dust-proof building
KR101473711B1 (en) Underground excavation method of constructing underground structure for radioactive waste storage
DE102020101891A1 (en) PROVIDING INSTRUCTIONS FOR PIPING
Gunnarsson et al. Backfilling and closure of the deep repository. Assessment of backfill concepts
Smedley et al. Quality management during closure works at the Telfer mine: a case study
Winter et al. Application of tyre bales to slope failure repair
Kang et al. Productivity assessment of rock transportation trucks using simulation technology
Holt Preconstruction surveys
Pariyar Excavated soil management from road construction in rural part of Nepal: Case-Kusum Nirman Sewa
Kaliannan et al. Developing a DMS (Dredged Marine Sediments) Management Framework for Beneficial Reuse in Artificial Land Creation
Compernolle Reference: License SMB-91 1; Docket No. 40-7580 License Conditions 37 c Dear Mr. Shepherd: Pursuant to License SMB-911 the licensee, FMRI, Inc.(" FMRI"), submits the following information in the attachment
Mohd Noor Piling work, construction of foundation and ancillary work
Davies et al. Geosynthetic clay liners: use and abuse in South Africa
Unit Post-Closure Inspection Report for
Tateyama et al. Precision Construction in Japan-Utilization of Information and Communication Technology
Wall et al. 1.7 QUALITY CONTROL
Weidner INEL support to the plutonium in soil integrated demonstration (Nevada). Interim report
Sugita et al. The Japanese approach to developing clay-based repository concepts–An example of design studies for the assessment of sealing strategies
Rosengard et al. A Parametric Model For Estimating Costs For Remediating Contaminated Sediment Sites Using A Dredging Method-A Budgetary & Planning Tool For Decision-Makers

Legal Events

Date Code Title Description
R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111105

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141105

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees