JP3110102B2 - Product production planning equipment in batch plant - Google Patents

Product production planning equipment in batch plant

Info

Publication number
JP3110102B2
JP3110102B2 JP24952291A JP24952291A JP3110102B2 JP 3110102 B2 JP3110102 B2 JP 3110102B2 JP 24952291 A JP24952291 A JP 24952291A JP 24952291 A JP24952291 A JP 24952291A JP 3110102 B2 JP3110102 B2 JP 3110102B2
Authority
JP
Japan
Prior art keywords
order
manufacturing
product
neck
job
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP24952291A
Other languages
Japanese (ja)
Other versions
JPH05314143A (en
Inventor
健二 内山
健一 石川
健二郎 森
良夫 戸塚
強二 新垣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zeon Corp
Fujitsu Ltd
Original Assignee
Zeon Corp
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zeon Corp, Fujitsu Ltd filed Critical Zeon Corp
Priority to JP24952291A priority Critical patent/JP3110102B2/en
Publication of JPH05314143A publication Critical patent/JPH05314143A/en
Application granted granted Critical
Publication of JP3110102B2 publication Critical patent/JP3110102B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明はバッチプラントにおける
製品生産計画装置に係わり、特に最適な製品生産計画を
自動的に作成するバッチプラントにおける製品生産計画
装置に関する。
The present invention relates to a batch plant.
Relates to the product production plan device, particularly optimal product production plans automatically product production plan in a batch plant to create
Related to the device .

【0002】[0002]

【従来の技術】近年の製品種類の増加、生産納期の短縮
に伴い、石油プラント、化学プラント等の製造業におい
て、多品種少量生産の傾向が強まり、特に、バッチプラ
ントでその傾向が強くなっている。尚、バッチプラント
とは、バッチ方式に従って製品を製造するプラントであ
り、ある工程の作業が終了したら次工程のタンクに現工
程のタンクの中身を移して次工程作業を行い、以後同様
にして製品を生産するものである。
2. Description of the Related Art With the recent increase in product types and shortened production delivery times, the trend of small-lot, high-mix production in petroleum plants and chemical plants has increased, especially in batch plants. I have. Note that a batch plant is a plant that manufactures products according to a batch method.When the work of a certain process is completed, the contents of the tank of the current process are transferred to the tank of the next process, and the next process work is performed. Is to produce.

【0003】図10は化学業種のバッチプラントの例で
あり、工程として原料調合工程、原料を化学的に反応
させる重合工程、未反応の原料を回収する回収工程
、重合により得られた製品(液体)をタンクに貯蔵す
る貯蔵工程、製品を乾燥して固形物にする乾燥工程
、固形物を包装する包装工程があり、各工程にはそ
れぞれ数十個のタンクTijが配置され、各タンク毎に所
定のスケジュ−ルに従って各工程の作業を行い、最終的
にオ−ダに見合った数量の製品を納期に間に合うように
製造するようになっている。
[0003] Fig. 10 shows an example of a batch plant in the chemical industry, which includes a raw material preparation step, a polymerization step for chemically reacting raw materials, a recovery step for recovering unreacted raw materials, and a product (liquid) obtained by polymerization. ) In a tank, a drying step of drying the product into a solid, and a packaging step of packing the solid. In each step, dozens of tanks Tij are arranged. The operations of each process are performed according to a predetermined schedule, and finally, a quantity of products corresponding to the order is manufactured in time for the delivery date.

【0004】かかるバッチプラントでは、各装置(タン
ク)の使用方法や使用順番の選択によって、生産コス
ト、生産時間の結果に大幅な違いが生じる。このため、
最適な製品生産計画を立案する必要があり、大部分の企
業では、(1) その作業を特定の専門家に任せており、ま
た、(2) 一部の企業ではスケジュ−ル問題としてORを
用いて最適な生産計画を作成し、あるいは(3) 各製造現
場毎にアルゴリズムを検討して従来の手続言語(フォル
トラン、コボル)を使用して、独自のシステムを構築し
ている。
[0004] In such a batch plant, the results of production cost and production time vary greatly depending on the method of use and the order of use of each device (tank). For this reason,
It is necessary to formulate an optimal product production plan, most companies (1) leave the work to a specific expert, and (2) some companies use OR as a scheduling problem. (3) Considering algorithms for each manufacturing site and constructing a unique system using conventional procedural languages (Fortran, Kobol).

【0005】[0005]

【発明が解決しようとする課題】しかし、第1の方法で
はノウハウが個人に集中しすぎているため、ノウハウが
隠匿され、又、専門家がいないと生産計画が立たない状
態に陥る問題がある。又、第2の方法では大まかな時間
内での資源配分の最適な解は計算できるが、より詳細な
各作業の順序を決定することは膨大な計算量を必要とす
るため、非現実的であり、第3の方法では、個々のシス
テムを独自に作る必要があり、工数/費用が掛りすぎる
のと、製品/設備等の変更によりシステムの再構築が必
要になる危険性が強い。
However, in the first method, since the know-how is concentrated too much on the individual, the know-how is concealed, and there is a problem that a production plan cannot be established without an expert. . In the second method, an optimal solution of resource allocation within a rough time can be calculated. However, determining a more detailed order of each operation requires an enormous amount of calculation. In the third method, it is necessary to make each system independently, and it takes too much man-hour / cost, and there is a strong risk that the system needs to be reconfigured due to a change in a product / equipment or the like.

【0006】以上から本発明の目的は、専門家に頼る必
要が無く、しかも生産順序まで生産計画ができ、更に
は、システムの構築工数の削減が可能なバッチプラント
における製品生産計画装置を提供することである。
Accordingly, it is an object of the present invention to provide a product production planning apparatus in a batch plant which does not require the assistance of an expert, can perform a production plan up to the production sequence, and can further reduce the number of system construction steps. That is.

【0007】[0007]

【課題を解決するための手段】図1は本発明の原理説明
図である。11は工程分割処理部、21はネック工程決
定処理部、22はネック工程製造順序決定処理部、23
が工程群製造順序決定処理部、24は製造順序調整処理
部であり、PRDはバッチプラントを構成する工程の内
容を示す工程データ、WKDは今までの各工程の稼働実
績データ、RTDは各工程における各種制約データ、O
RDはオ−ダ(製品名、数量、納期)、IRDは製造現
場の設備/資源データである。
FIG. 1 is a diagram illustrating the principle of the present invention. 11 is a process division processing unit, 21 is a neck process determination processing unit, 22 is a neck process manufacturing order determination processing unit, 23
Is a process group manufacturing sequence determination processing unit, 24 is a manufacturing sequence adjustment processing unit, PRD is process data indicating the contents of the processes constituting the batch plant, WKD is the operation result data of each process up to now, and RTD is each process. Various constraint data in O
RD is order (product name, quantity, delivery date), and IRD is equipment / resource data at the manufacturing site.

【0008】[0008]

【作用】工程分割処理部11により全工程をバッファ工
程を境に複数の工程グル−プに分割し、ネック工程決定
処理部21により稼働実績データと制約データを参照し
て全工程のうち稼働率及び制約条件の多いネック工程を
求める。ついで、ネック工程製造順序決定処理部22に
より、オ−ダ、制約データ、設備/資源データ等を参照
し、各種制約条件(各オ−ダの納期を含む)を満たすよ
うに、ネック工程の各装置(タンク)における製造順序
を決定する。しかる後、工程群製造順序決定処理部23
により、各工程グル−プにおける製造順序をネック工程
の製造順序に基づいて決定する。そして、該決定された
製造順序で製造する時に不具合が生じる場合には、製造
順序調整処理部24により該不具合が生じた工程グル−
プの製造順序を調整する。これにより、専門家に頼る必
要が無く、しかも生産順序まで生産計画ができ、更に
は、システムの構築工数の削減が可能となる。
The whole process is divided into a plurality of process groups by the process dividing unit 11 with the buffer process as a boundary, and the operation ratio of all the processes is referred to by the neck process determining unit 21 by referring to the operation result data and the constraint data. In addition, a neck process having many constraints is determined. Next, the neck process manufacturing order determination processing unit 22 refers to the order, constraint data, equipment / resource data, and the like, and adjusts each of the neck processes so as to satisfy various constraints (including the delivery date of each order). Determine the production order in the device (tank). Thereafter, the process group manufacturing order determination processing unit 23
Thus, the manufacturing order in each process group is determined based on the manufacturing order of the neck process. If a problem occurs when manufacturing is performed in the determined manufacturing sequence, the manufacturing sequence adjustment processing unit 24 causes the process group in which the problem occurs to occur.
Adjust the production order of the pumps. As a result, it is not necessary to rely on an expert, and the production planning can be performed up to the production sequence, and further, the number of man-hours for constructing the system can be reduced.

【0009】[0009]

【実施例】【Example】

(a) 全体の構成 図2は本発明のバッチプラントにおける製品生産計画シ
ステムの実施例構成図である。図中、11はバッチプラ
ントの工程内容を示すデータ(工程名等)PRDに基づ
いて全工程をバッファ工程(貯蔵工程)を境に複数の工
程グル−プに分割する工程分割処理部、12は製品生産
計画の対象タンク数を少なくして部分問題に帰着させる
装置分割処理部である。13は初期状態設定部であり、
オ−ダのバッチ分割設定処理と仕掛り関連の設定処理を
行う。14はバッチプラントの製品生産計画を立案する
生産計画立案部、15は立案された生産計画において不
都合な部分を修正する立案結果修正処理部である。
(a) Overall Configuration FIG. 2 is a configuration diagram of an embodiment of a product production planning system in a batch plant according to the present invention. In the figure, reference numeral 11 denotes a process division processing unit which divides all processes into a plurality of process groups with a buffer process (storage process) as a boundary based on data (process name etc.) PRD indicating the process contents of the batch plant. This is a device division processing unit that reduces the number of target tanks in a product production plan to result in a partial problem. 13 is an initial state setting unit,
It performs order batch division setting processing and in-process related setting processing. Reference numeral 14 denotes a production plan drafting unit that drafts a product production plan of a batch plant, and 15 denotes a drafting result correction processing unit that corrects an inconvenient part in the drafted production plan.

【0010】生産計画立案部 生産計画立案部14は、データ記憶部14a、制約条件
記憶部14b、製品生産計画決定部14cを備えてい
る。データ記憶部14aには、製造現場に実際に存在す
る各種装置(タンク)等を特定する設備/資源データI
RD、過去の各工程の稼働実績データWKD、設備/資
源を用いて製造現場で作られる製品に関する製品データ
MGD、製造現場に与えられるオ−ダ(製品名、数量、
納期)ORD、立案過程及び立案結果の状態を表現する
製造現場状況データMFDが記憶される。
Production Planning Unit The production planning unit 14 includes a data storage unit 14a, a constraint storage unit 14b, and a product production plan determination unit 14c. The data storage unit 14a stores equipment / resource data I that specifies various devices (tanks) and the like that actually exist at the manufacturing site.
RD, past operation results data WKD of each process, product data MGD relating to products manufactured at the manufacturing site using equipment / resources, orders given to the manufacturing site (product name, quantity,
Delivery date) ORD, manufacturing site situation data MFD expressing the state of the planning process and the planning result are stored.

【0011】制約条件記憶部14bには各種制約RT
D、例えば、納期等どうしても守らなければならない制
約(MUST条件)や満たした方がよい制約(WANT
条件)が記憶されている。
The various constraint RTs are stored in the constraint condition storage unit 14b.
D, for example, a constraint (MUST condition) that must be observed, such as a delivery date, or a constraint that should be satisfied (WANT)
Condition) is stored.

【0012】製品生産計画決定部14cは、稼働実績デ
ータWKDと制約データRTDを参照して全工程のうち
稼働率が高く、かつ制約条件の多い工程をネック工程と
して決定するネック工程決定処理部21と、オ−ダ、制
約データ、設備/資源データ等を参照し、各種制約条件
を満たすように、ネック工程の各装置(タンク)におけ
る製造順序を決定するネック工程製造順序決定処理部2
2と、分割処理部11で分割された各工程グル−プにお
ける製造順序をネック工程の製造順序に基づいて決定す
る工程群製造順序決定処理部23と、該決定された製造
順序で製造する時に不具合が生じる場合には、該不具合
が生じた工程グル−プの製造順序を調整する製造順序調
整処理部24と、バッファ(貯蔵)部分の計画を立案す
る全体工程製造順序決定処理部25と、貯蔵タンク繰り
対応処理部26を備えている。
The product production plan determination unit 14c refers to the operation result data WKD and the constraint data RTD, and determines a process having a high operation rate and many constraints among all processes as a neck process. And the order, constraint data, equipment / resource data, etc., and determines the manufacturing order of the neck process in each device (tank) so as to satisfy various constraints.
2, a process group manufacturing order determination processing unit 23 for determining the manufacturing order in each of the process groups divided by the division processing unit 11 based on the manufacturing order of the neck process, and when manufacturing in the determined manufacturing order. If a problem occurs, a manufacturing sequence adjustment processing unit 24 for adjusting the manufacturing sequence of the process group having the problem, an overall process manufacturing sequence determination processing unit 25 for planning a buffer (storage) portion, A storage tank repetition processing unit 26 is provided.

【0013】ネック工程製造順序決定処理部22は、ネ
ック工程に関する制約ばかりでなく、他工程の制約も事
前に簡易的にチェックして、製造順番を決定する。又、
工程群製造順序決定処理部23は、バッチプラント特有
の処理としてオ−ダをバッチに分割した時、そのバッチ
の製造をどのような装置でどのように製造するかをネッ
ク工程の製品製造順序に基づいて決定し、製造順序調整
処理部24はバッチ調整による製造順序調整処理を行
う。貯蔵タンク繰り対応処理部26は、バッチプラント
特有の処理として工程間の待ちが発生しバッファとして
の機能を有するタンク群があるため、これらタンクの取
り方を知識として収集し、全体工程製造順序決定処理部
25に提供する。
The neck step manufacturing order determination processing section 22 simply checks in advance not only restrictions on the neck step but also restrictions on other steps in advance, and determines the manufacturing order. or,
When the order is divided into batches as a process unique to the batch plant, the process group manufacturing order determination processing unit 23 determines what kind of apparatus and how to manufacture the batches in the product manufacturing order of the neck process. The production order adjustment processing unit 24 performs a production order adjustment process by batch adjustment. The storage tank repetition processing unit 26 has a group of tanks having a function as a buffer due to waiting between processes as a process unique to the batch plant. Provided to the processing unit 25.

【0014】(b) 全体の動作工程分割処理 図3はバッチプラントにおける工程が重合工程、回収工
程、貯蔵工程、乾燥工程等を有しているとした場合の工
程分割処理の説明図である。複数の工程を有するバッチ
プラントでは、各工程に複数の装置(タンク)が存在
し、どの装置を使うかに関して多数の選択肢がある。こ
のため、例えば重合工程PR1のタンク数をi,回収工
程PR2のタンク数をj、貯蔵工程PR3のタンク(ブ
レンドタンク)数をk、乾燥工程のタンク数をm・・・
とすると、各工程の全体の組み合わせ数は i・j・k
・m・・・ となり、計算量が莫大となる。そのため、
本発明では、問題を単純化するために、処理の単位が異
なる工程群を別々に考えるようにしている。
(B) Overall operation process division process FIG. 3 is an explanatory diagram of the process division process in the case where the processes in the batch plant include a polymerization process, a recovery process, a storage process, a drying process, and the like. In a batch plant having multiple processes, there are multiple devices (tanks) for each process and there are many options as to which device to use. Therefore, for example, the number of tanks in the polymerization step PR1 is i, the number of tanks in the recovery step PR2 is j, the number of tanks (blend tanks) in the storage step PR3 is k, and the number of tanks in the drying step is m ...
Then, the total number of combinations in each process is i · j · k
・ M ・ ・ ・ The amount of calculation becomes enormous. for that reason,
In the present invention, in order to simplify the problem, a process group having a different processing unit is considered separately.

【0015】バッチプラントでは、処理の単位であるタ
ンクの容量でオ−ダを分割し(チャ−ジャ分割、あるい
はバッチ分割という)、これらチャ−ジを一旦タンクに
溜め込んで、まとめて処理する工程(Σチャ−ジとい
う)が存在し、図3の例ではΣチャ−ジ工程は乾燥工程
である。このように、途中にバッファ(溜め込み)用の
タンクを境に処理の単位の違う作業をしている場合、処
理単位の同じ工程群をグル−プで考えることができる。
In a batch plant, the order is divided according to the capacity of the tank, which is the unit of processing (referred to as charger division or batch division), and these charges are temporarily stored in a tank and processed collectively. (Referred to as “charging”), and in the example of FIG. 3, the charging process is a drying process. As described above, in the case where work is performed in different units of processing with a buffer (reservoir) tank as a boundary, a group of processes having the same processing unit can be considered as a group.

【0016】そこで、工程分割処理部11は工程データ
PRDを参照して、バッファタンクを境にして処理単位
が異なる工程群があるか否かを判断し、あれば該バッフ
ァタンクを境に全工程を複数の工程群に分割する。図3
の例では、バッファタンク(貯蔵工程PR3)を境にし
て、前工程と、後工程に分割する。これにより、後述す
るように立案処理部14は前工程と後工程で別々に生産
計画を立案できる。
Therefore, the process division processing unit 11 refers to the process data PRD to determine whether or not there is a process group having a different processing unit with respect to the buffer tank. Is divided into a plurality of process groups. FIG.
In the example, the process is divided into a pre-process and a post-process with the buffer tank (storage process PR3) as a boundary. As a result, the planning processing unit 14 can separately draft a production plan for the pre-process and the post-process as described later.

【0017】装置分割処理 製品生産計画を立案するには対象となるタンク数が少な
い程良い。そこで、以下の(1)〜(3)の指針 (1) 製造方式の違いにより分割する、(2) 装置の使い方
により分割する、(3) 製品と装置(タンク)の関係に基
づいて排他的なグル−プは分割する、に基づいて、装置
分割処理部12はタンクを分割して製品生産計画の対象
タンク数を少なくして部分問題に帰着させている。
[0017] In order to formulate a production plan for the device division processing product, the smaller the number of target tanks, the better. Therefore, the following guidelines (1) to (3): (1) division based on the difference in manufacturing method, (2) division based on how to use the device, (3) exclusive based on the relationship between the product and the device (tank) Based on the fact that the group is divided, the apparatus division processing unit 12 divides the tanks to reduce the number of target tanks in the product production plan, resulting in a partial problem.

【0018】例えば、連続方式による製造のみに係わる
タンクは、バッチプラントの製品生産計画対象から除外
し、別に生産計画を立案する。又、製品と装置(タン
ク)の関係に基づいて排他的なタンクグル−プは互いに
分割し、それぞれ別々の部分問題に帰着させる。例え
ば、図4に示すように、「製品あ」、「製品い」、「製
品う」、・・・が、工程1でタンク1Aとタンク1Bを
使用し、工程2でタンク2Aとタンク2Cを使用し、・
・・工程NでタンクNAを使用している場合において、
「製品れ」、「製品ろ」、「製品わ」・・・が、工程1
でタンク1Cを使用し、工程2でタンク2Bを使用し、
・・・工程NでタンクNBを使用している場合、図5に
示すように、全工程で「製品あ、い、う」が使用するタ
ンクと「製品れ、ろ、わ」が使用するタンクが異なる。
かかる場合、排他的な関係があり、「製品あ、い、う」
については、タンク1A,1B,2A,2C,・・・N
Aのみをバッチプラントの製品生産計画対象タンクと
し、「製品れ、ろ、わ」についてはタンク1C、2B、
・・・NBのみを対象タンクとする。従って、オ−ダが
「製品あ、い、う」のみの場合には、タンク1C、2
B、・・・NBは、バッチプラントの製品生産計画対象
タンクから除外する。
For example, tanks involved only in continuous production are excluded from the product production planning targets of a batch plant, and a separate production plan is prepared. Also, based on the relationship between the product and the equipment (tank), the exclusive tank groups are split from one another, each resulting in a separate subproblem. For example, as shown in FIG. 4, “product a”, “product i”, “product u”,... Use tank 1A and tank 1B in step 1 and tank 2A and tank 2C in step 2. use,·
..When tank NA is used in process N,
“Product”, “Product”, “Product” ...
Using tank 1C, using tank 2B in step 2,
... When tank NB is used in process N, as shown in FIG. 5, tanks used by "products a, i, u" and tanks used by "products, ro, wa" in all processes Are different.
In such a case, there is an exclusive relationship and "product a, i, u"
For tanks 1A, 1B, 2A, 2C,.
Only A is a target tank for product production planning of a batch plant, and “Products, ro, wa” are tanks 1C, 2B,
... Only NB is the target tank. Therefore, in the case where the order is only "product a, u, u", the tanks 1C, 2C
B,... NB are excluded from tanks targeted for product production planning of the batch plant.

【0019】初期状態設定処理 生産計画立案部14で生産計画を立案する前に、事前準
備処理として、バッチプラント特有のチャ−ジ分割(バ
ッチ分割)処理及び仕掛り状況設定処理等を行う必要が
ある。与えられたオ−ダをこなすためには、複数の装置
(タンク)で対応可能であり、しかも、各タンクの処理
能力(容量)に違いがあり、このため、オ−ダのバッチ
分割の選択肢は多数存在する。そこで、初期状態設定部
13は、各タンクの容量、各製品(オ−ダ)の優先順位
に従った分割を行い、最適な分割を計算して結果をディ
スプレイ画面に表示して、端末より修正できるようにし
ている。
Initial state setting processing Before the production plan drafting section 14 drafts a production plan, it is necessary to carry out a batch plant-specific charge division (batch division) processing, in-process status setting processing, and the like as advance preparation processing. is there. In order to fulfill a given order, a plurality of devices (tanks) can be used, and the processing capacity (capacity) of each tank is different. There are many. Therefore, the initial state setting unit 13 performs division according to the capacity of each tank and the priority of each product (order), calculates the optimal division, displays the result on the display screen, and corrects the result from the terminal. I can do it.

【0020】又、生産計画立案処理において、仕掛り作
業の残作業も新規作業と同様に考慮するためには、設備
単位で仕掛り状況を把握して設定する必要があり、そこ
で、初期状態設定部13は仕掛り中の残作業を把握して
設定するようにしている。
In the production planning process, in order to consider the remaining work in progress as well as the new work, it is necessary to grasp and set the work in progress for each equipment. The unit 13 grasps and sets the remaining work in progress.

【0021】図6は1つのオ−ダに対する製造現場の状
況を表現するためのデータの構造図であり、オ−ダをタ
ンクの容量等に基づいてバッチ分割し、各工程毎に工程
ジョブ、占有ジョブ、切替ジョブを生成してデータ記憶
部14aに記憶する。図6において、「品名ジョブ」は
1回のオ−ダに対応し、「品名分割ジョブ」は、1回の
オ−ダを複数回の作業に分けて実行する場合に対応し、
通常、1回のオ−ダは一連の作業で実行するので品名分
割ジョブは1個であり、M=1となる。又、「工程ジョ
ブ」は各工程の作業に対応し、通常は工程ジョブ数と品
名分割ジョブ数の比はN:1である。尚、Nは工程のタ
ンクの容量に依存するもので、1個の品名分割ジョブの
数量を例えば100t、工程のタンクの容量を20tと
すると、N=5となり、1つの品名分割ジョブに対して
5個の工程ジョブが生成される。
FIG. 6 is a diagram showing the structure of data for expressing the situation of the manufacturing site for one order. The orders are divided into batches based on the capacity of the tank and the like, and the process job, An exclusive job and a switching job are generated and stored in the data storage unit 14a. In FIG. 6, "article name job" corresponds to one order, and "article name division job" corresponds to a case where one order is divided into a plurality of operations and executed.
Normally, one order is executed by a series of operations, so that the number of product name division jobs is one, and M = 1. The “process job” corresponds to the work of each process, and the ratio of the number of process jobs to the number of product name division jobs is normally N: 1. Note that N depends on the capacity of the process tank. If the quantity of one product name division job is, for example, 100 t and the capacity of the process tank is 20 t, N = 5, and one product name division job Five process jobs are generated.

【0022】「占有ジョブ」は生産計画立案処理により
各工程ジョブに実際の作業開始時刻等が設定されるもの
で、工程ジョブ数と占有ジョブ数の比は工程1〜工程3
(チャ−ジ工程、重合工程、回収工程)では1:1、工
程4〜工程5(貯蔵工程、乾燥工程)では1:Nであ
る。「切替ジョブ」は各占有ジョブにより製造順序が決
定された時、前のジョブとの切替に対応し、各占有ジョ
ブに1つ生成される。この切替ジョブにタンク清掃の有
無等が設定される。例えば、前のジョブと異なる製品を
製造する時にはタンクの清掃が必要になり、その旨が切
替ジョブに設定される。「資源ジョブ」には、オ−ダを
生産する際に必要な各種資源情報が設定される。
The “occupied job” is the one in which the actual work start time and the like are set for each process job by the production plan drafting process.
(Charge step, polymerization step, recovery step) is 1: 1, and steps 4 to 5 (storage step, drying step) are 1: N. When the production order is determined by each occupation job, one “switching job” is generated for each occupation job, corresponding to switching with the previous job. Whether or not tank cleaning is performed is set in this switching job. For example, when a product different from the previous job is manufactured, the tank needs to be cleaned, and that effect is set in the switching job. In the “resource job”, various kinds of resource information necessary for producing an order are set.

【0023】以上により、100tのオ−ダがあり、工
程1〜工程3のタンクの能力が20t、工程4〜工程5
のタンクの能力が100tであるとすると、工程1〜工
程3のそれぞれに5つの工程ジョブが生成され、工程4
〜工程5のそれぞれに1つの工程ジョブが生成される。
As described above, there is an order of 100 tons, the capacity of the tank in step 1 to step 3 is 20 t, and the capacity of step 4 to step 5
Assuming that the capacity of the tank is 100 t, five process jobs are generated in each of process 1 to process 3 and
One process job is generated for each of the processes.

【0024】ネック工程決定処理 全ての工程を一括して考えると、計算量が莫大となる。
そこで、稼働率及び制約条件の多い工程をネック工程と
して選び、該ネック工程における製品製造順序を決定
し、該ネック工程の製造順序に基づいて全体の製造順序
を決定する。
Neck Step Determination Process If all steps are considered together, the amount of calculation becomes enormous.
Therefore, a process having a high operating rate and constraints is selected as a neck process, a product manufacturing order in the neck process is determined, and an overall manufacturing sequence is determined based on the manufacturing order of the neck process.

【0025】このため、ネック工程決定処理部21は、
稼働実績データWKDと制約データRTDを参照して全
工程のうち稼働率及び制約条件の多い工程をネック工程
として決定する。制約データには、MUST条件とWA
NT条件があり、MUST条件には100点が、WAN
T条件には100点未満の点がつけられ、点の合計によ
り制約条件の多少が判断される。尚、MUST条件とし
ては納期等があり、WANT条件としては(1) 製品A、
Bは同時に同一の工程で製造してはならない(工程競
合)、(2) 資源の競合があってはならない(資源競合)
等がある。
For this reason, the neck step determination processing section 21
With reference to the operation result data WKD and the constraint data RTD, a process having many operation rates and constraints among all the processes is determined as a bottleneck process. The constraint data includes the MUST condition and WA
There is an NT condition, and 100 points in the MUST condition
Less than 100 points are given to the T condition, and the total of the points determines the degree of the constraint condition. The MUST condition includes a delivery date, etc., and the WANT condition includes (1) Product A,
B must not be manufactured in the same process at the same time (process competition). (2) There must be no resource competition (resource competition).
Etc.

【0026】ネック工程製造順序決定処理 ネック工程製造順序決定処理部22は、オ−ダ、制約デ
ータ、設備/資源データ等を参照し各種制約条件を満た
すように、ネック工程の各装置(タンク)における製造
順序を決定する。
Neck Step Manufacturing Order Determination Processing The neck step manufacturing order determination processing section 22 refers to the order, constraint data, equipment / resource data, etc., and satisfies various constraint conditions so that each device (tank) of the neck step can be satisfied. To determine the manufacturing order.

【0027】図7はネック工程の製造順序決定処理の流
れ図である。設備/資源データIRDを参照して、ネッ
ク工程の各工程ジョブをネック工程の各装置に均等に山
積みし、能力以上に工程ジョブが山積みされた装置につ
いては、予め設定されている装置選択ノウハウENHに
基づいて他の装置(山積みした負荷の低い方の装置)に
設定し直し、最終的にネック工程の各ジョブ群を実行す
るための装置を決定する(ステップ101)。
FIG. 7 is a flow chart of the manufacturing order determination processing in the neck step. With reference to the equipment / resource data IRD, each process job of the neck process is evenly stacked on each device of the neck process, and as for the devices having the process jobs stacked more than the capacity, the device selection know-how ENH set in advance is set. Is reset to another device (the device with the lower load piled up) based on the above, and finally, the device for executing each job group of the neck process is determined (step 101).

【0028】ついで、各装置に割り当てられた工程ジョ
ブのうち、最初に実行すべき工程ジョブをジョブ選択ノ
ウハウJNH(例えば納期順)に基づいて決定する(ス
テップ102)。しかる後、該工程ジョブの作業開始時
刻を仮設定し(占有ジョブの生成、ステップ103)、
その状態で、制約条件が全て満たされているかチェック
し(ステップ104)、満たされている場合には、工程
ジョブを設定して(ステップ105)、以後ステップ1
02に戻り、次の工程ジョブについて同様の処理を行
う。
Next, of the process jobs assigned to each apparatus, the process job to be executed first is determined based on the job selection know-how JNH (for example, order of delivery date) (step 102). Thereafter, the work start time of the process job is provisionally set (generation of exclusive job, step 103),
In this state, it is checked whether all the constraint conditions are satisfied (Step 104). If so, a process job is set (Step 105).
Returning to step 02, similar processing is performed for the next process job.

【0029】一方、制約条件が満たされない場合には、
該制約条件について予め設定してある制約退避ノウハウ
(制約を退避する方法を記述した制約退避プログラム)
に従って、退避案を生成する(ステップ105)。すな
わち、制約条件を満たすように所定工程ジョブの作業開
始時刻を変更する。
On the other hand, if the constraints are not satisfied,
Restriction saving know-how set in advance for the constraint condition (a constraint saving program describing a method for saving a constraint)
, An evacuation plan is generated (step 105). That is, the work start time of the predetermined process job is changed so as to satisfy the constraint condition.

【0030】ついで、各案を評価し、最適と思われる案
を採択し(ステップ106〜108)、ステップ110
で工程ジョブの設定を行い、以後ステップ102に戻
り、次の工程ジョブについて同様の処理を行う。しか
し、制約条件を満たす退避案がなければ、装置選択が間
違っていたとみなし(ステップ109)、以後ステップ
101に戻り、装置選択処理をしなおす。
Next, each plan is evaluated, and a plan considered to be optimal is adopted (steps 106 to 108).
To set the process job, and thereafter, return to step 102 and perform the same processing for the next process job. However, if there is no evacuation plan that satisfies the constraint conditions, it is determined that the device selection has been made incorrect (step 109), and thereafter, the process returns to step 101 to perform the device selection process again.

【0031】図8及び図9はネック工程の製造順序決定
の簡単な説明図である。尚、ネック工程は乾燥工程であ
るとし、この乾燥工程に1回の乾燥能力が100tの3
つの乾燥装置(装置1〜装置3)があるものとする。
又、オ−ダとして品名ジョブ1〜3の3つが存在し、そ
れぞれの内容が 品名ジョブ1:製品A、数量300t、納期9/1 品名ジョブ2:製品B、数量400t、納期9/3 品名ジョブ3:製品A、数量200t、納期9/3 であるとし、製品Aと製品Bは同時に乾燥工程で製造
(乾燥)してはならないとする。
FIGS. 8 and 9 are simple explanatory diagrams for determining the manufacturing order of the neck process. It is assumed that the neck step is a drying step.
It is assumed that there are two drying apparatuses (apparatus 1 to apparatus 3).
Also, there are three orders, ie, product name jobs 1 to 3, each of which has the following content: product name job 1: product A, quantity 300t, delivery date 9/1 product name job 2: product B, quantity 400t, delivery date 9/3 Job 3: Product A, quantity 200t, delivery time 9/3, and product A and product B must not be manufactured (dried) in the drying process at the same time.

【0032】初期状態設定部13のバッチ分割処理等に
より、図8に示すように、品名ジョブ1の乾燥工程にお
いては3つの工程ジョブ JOB11,JOB12,JOB13が生成され、品名
ジョブ2の乾燥工程においては4つの工程ジョブ JOB21,JOB22,JOB23,JOB24が生
成され、品名ジョブ3の乾燥工程においては2つの工程
ジョブ JOB31,JOB32が生成される。そして、ネック
工程製造順序決定処理により、各工程ジョブは納期順に
各乾燥装置1〜3に割り当てられ、図9(a)に示すよう
に各工程ジョブの設定(装置、作業開始時期等の設定)
がなされたとする。
As shown in FIG. 8, three process jobs JOB11, JOB12, and JOB13 are generated in the drying process of the product name job 1 by the batch division process of the initial state setting unit 13 and the like. Generates four process jobs JOB21, JOB22, JOB23, and JOB24. In the drying process of the product name job 3, two process jobs JOB31 and JOB32 are generated. Each process job is assigned to each of the drying devices 1 to 3 in order of delivery date by the neck process manufacturing order determination process, and as shown in FIG. 9A, setting of each process job (setting of device, work start time, etc.)
Is done.

【0033】この製造順序について制約条件をチェック
すると、納期は全てのオ−ダについて満足されている
が、9月2日において製品A,Bが同時に製造されてい
るため、工程競合の制約条件を満たさない。そこで、図
9(b)に示すようにJOB31,JOB32を9月3日
に移動する。このようにすれば、納期、工程競合、資源
競合との全ての制約が満たされる。しかし、この製造順
序では、装置が扱う製品の変化により5回の清掃(矢印
で示している)が必要になり、切替ジョブが多くなる。
そこで、図9(c)に示すように各工程ジョブを設定す
る。このようにすれば、3回の清掃で済み、しかも納
期、工程競合、資源競合の全ての制約が満たされるか
ら、これをネック工程の製造順序として決定する。
When the constraints on the manufacturing order are checked, the delivery date is satisfied for all orders. However, since products A and B are manufactured at the same time on September 2, the constraints on the process competition are not satisfied. Do not meet. Therefore, as shown in FIG. 9B, JOB31 and JOB32 are moved on September 3. In this way, all the constraints of the delivery date, process competition, and resource competition are satisfied. However, in this manufacturing order, five cleanings (indicated by arrows) are required due to changes in the products handled by the apparatus, and the number of switching jobs increases.
Therefore, each process job is set as shown in FIG. In this way, three cleanings are sufficient, and all the constraints of the delivery date, the process competition, and the resource competition are satisfied, and this is determined as the production order of the neck process.

【0034】工程群製造順序決定処理 ネック工程製造順序の決定により大体の製造順序が決ま
る。従って、工程群製造順序決定処理部23はネック工
程製造順序に基づいて前工程群、後工程群の製造順序を
決定し、不具合が生じた時、製造順序調整処理部24で
バッチ調整による製造順序調整処理を行う。尚、工程群
製造順序決定に際しては、以下の点が考慮されている。
すなわち、 (1) 1つのバッチについて各工程で工程ジョブが設定さ
れるが、これら各工程ジョブは連続的に実行されるよう
に製造順序を決定する。 (2) 製造時刻を早めるために、できるだけバッチプロセ
ス特有の複数のタンクの同時並列運転を行うように製造
順序を決定する、 (3) 工程の製造順序に不整合が生じないように、例え
ば、清掃があまり生じないように、納期割れが生じない
ように、前回の結果を順守するように、製造順序を試行
錯誤的手法で決定する、 (4) 安定運転にするために、あるバッチ数以上の連続運
転が行われるように製造順序を決定する、 (5) 最終バッチは調整に使用するため、環境が変わらな
いように前のバッチと同一の装置を使用するように製造
順序を決定する、 等を考慮してネック工程製造順序に基づいて前工程群、
後工程群の製造順序を決定する。
Process Group Manufacturing Order Determination Process Neck The determination of the manufacturing order determines the approximate manufacturing order. Accordingly, the process group manufacturing order determination processing unit 23 determines the manufacturing order of the pre-process group and the post-process group based on the neck process manufacturing order. Perform adjustment processing. The following points are taken into consideration when determining the production order of the process groups.
That is, (1) Process jobs are set in each process for one batch, and the production order is determined so that these process jobs are executed continuously. (2) In order to advance the production time, determine the production sequence so as to perform simultaneous parallel operation of multiple tanks specific to the batch process as much as possible. (3) To prevent inconsistency in the production sequence of the process, for example, Determine the production order by trial and error so as to adhere to the previous results so as not to cause too much cleaning and not to break the delivery date. (4) To ensure stable operation, a certain number of batches or more (5) The final batch is used for adjustment, so that the same equipment as that of the previous batch is used so that the environment does not change. The previous process group based on the neck process manufacturing order taking into account etc.
The production order of the post-process group is determined.

【0035】全体工程製造順序決定処理 以上により、前後の工程群の製造順序が決定されると、
全体工程製造順序決定処理部25はその中間に存在する
バッファ(貯蔵タンク)部分の対応について計画を立案
する。バッチプロセスでは、バッファ部分の対応が難し
い場合が多いが、以下の基準を考慮して決定される。す
なわち、(1) 使用する貯蔵タンクの順番は空いているも
のより順に選択する、(2) 全貯蔵タンクを一群のまとま
りと考え、全貯蔵タンクの合計使用量が全貯蔵タンクの
総能力を越えないように決定する。すなわち、個々のタ
ンクを意識せず、合計量のみを意識して使用タンクを決
定する、 (3) 邪魔しているものがあればどかして使用タンクを決
定する(玉突)、等を考慮して貯蔵タンクの使用順序を決
定する。
Overall Process Manufacturing Order Determination Process By the above, when the manufacturing order of the preceding and succeeding process groups is determined,
The whole process manufacturing order determination processing unit 25 drafts a plan for a buffer (storage tank) portion existing in the middle. In the batch process, it is often difficult to deal with the buffer portion, but it is determined in consideration of the following criteria. In other words, (1) the order of storage tanks to be used is selected in the order of availability, (2) all storage tanks are considered as a group, and the total usage of all storage tanks exceeds the total capacity of all storage tanks. Decide not to. In other words, consider the tanks to be used without considering individual tanks and only the total amount. (3) Determine the tanks to be used if there is something in the way (thrust). To determine the order of use of storage tanks.

【0036】立案結果修正処理 以上により決定した製品生産計画を工程表(ガントチャ-
ト)でディスプレイ画面に表示し、必要に応じてオペレ
−タが修正する。これにより、現状に合った生産計画の
立案が可能なる。
The product production plan determined by the above-described process is modified to a process chart (Gantcha-
) Is displayed on the display screen, and the operator corrects it if necessary. This makes it possible to draft a production plan that matches the current situation.

【0037】(c) 適用例 本発明を図10の化学業種のバッチプラントに適用する
と、貯蔵工程を境に前工程群と後工程群に分割され、
乾燥工程がネック工程となる。そして、乾燥工程におい
ては以下の制約条件 (1) 納期制約・・オ−ダで与えられた納期までに終了す
る (2) 最早開始条件・・前工程や前のバッチの関連でそれ
以前に作れない、 (3) 資源競合制約・・同一工程内の違った装置で作業す
るJOBの使用する資源の競合、 (4) 人員制約・・作業員の数が確保できなければ作業で
きないJOBがある、 (5) 休日制約・・休日に行える作業と行えない作業があ
る、 (6) 停止制約・・停止作業をする為の時間帯や前後のJ
OBが特殊である、 (7) 他工程競合制約・・重合工程の簡単なチェックを行
う 等を考慮している。
(C) Application Example When the present invention is applied to a batch plant in the chemical industry shown in FIG. 10, the storage process is divided into a pre-process group and a post-process group,
The drying step is the neck step. Then, in the drying process, the following constraints (1) Delivery deadline ... End by the deadline given in the order (2) Earliest start condition ... No, (3) Resource contention constraints-Competition of resources used by JOBs working on different devices in the same process, (4) Personnel restrictions-Some jobs cannot be performed unless the number of workers can be secured, (5) Restrictions on holidays: There are tasks that can and cannot be performed on holidays. (6) Stop restrictions.
The OB is special. (7) Considering the restrictions on competition in other processes and performing a simple check of the polymerization process.

【0038】又、前工程群の製造順序決定処理に際して
は、重合工程を中心に以下の点 (1) なるべく並行処理を行う、この例では2つの装置の
並行運転を優先する、(2) 連続運転を意識して、最低3
バッチは続けて行う、(3) 最後の3バッチは同一タンク
で行う、(4) 最後のバッチは前のバッチから一定時間間
隔をおく、を考慮し、ネック工程の製造順序に基づいて
製造順序を決定する。すなわち、乾燥工程(ネック工
程)において生産終了時刻が最も早い順番のものから割
り当てる。ついで、重合工程の最後のバッチ割り当て時
刻が、乾燥工程仮割り当て結果の乾燥開始時刻より前で
あるかにより、割り当て結果の可否を判断し、前になら
なければ割り当ては成立しないとする。不成立の場合に
は、割り当てバッチ数が一番少ない装置に割り当てられ
ている品名(工程ジョブ)を外す。この場合、外された
品名の納期割れが生じたならば、再割り当て処理を行
う。
In the process for determining the production order of the preceding process group, the following points are mainly performed in the polymerization step. (1) Parallel processing is performed as much as possible. In this example, parallel operation of two devices is prioritized. At least 3
Considering (3) the last three batches in the same tank, (4) the last batch at a fixed time interval from the previous batch, and taking the production sequence based on the production sequence of the neck process To determine. That is, in the drying process (neck process), the production end time is assigned in the order of earliest. Next, it is determined whether or not the allocation result is possible depending on whether the last batch allocation time of the polymerization process is before the drying start time of the drying process temporary allocation result. If not satisfied, the product name (process job) assigned to the device with the smallest assigned batch number is removed. In this case, if the delivery date of the removed product name falls, the reassignment process is performed.

【0039】更に全工程順序決定処理においては、(1)
空いているタンクより順に選択する、(2) 重合開始時刻
の早い工程ジョブから順にタンクを割り当てる、を考慮
してバッファタンクの使用順序を決定する。以上、本発
明を実施例により説明したが、本発明は請求の範囲に記
載した本発明の主旨に従い種々の変形が可能であり、本
発明はこれらを排除するものではない。
Further, in the process order determination process, (1)
Determine the order in which the buffer tanks are used, taking into account that the tanks are selected in order from the empty tanks and (2) tanks are allocated in order from the process job with the earliest polymerization start time. As described above, the present invention has been described with reference to the embodiments. However, the present invention can be variously modified in accordance with the gist of the present invention described in the claims, and the present invention does not exclude these.

【0040】[0040]

【発明の効果】以上本発明によれば、全工程をバッファ
工程を境に複数の工程グル−プに分割し、全工程のうち
稼働率の高い工程をネック工程として求め、各オ−ダの
納期を含む制約条件を満たすように、ネック工程におけ
る各装置の製造順序を決定し、工程グル−プの製造順序
をネック工程の製造順序に基づいて決定し、決定した各
工程グル−プの製造順序で製造すると不具合が生じる
時、該不具合が生じた工程グル−プの製造順序を調整し
て製品生産計画を立案するように構成したから、専門家
に頼る必要が無く、しかも生産順序まで生産計画がで
き、更には、システムの構築工数の削減が可能となる。
As described above, according to the present invention, all processes are divided into a plurality of process groups with a buffer process as a boundary, and a process having a high operation rate among all processes is determined as a bottleneck process. The manufacturing order of each device in the neck process is determined so as to satisfy the constraint condition including the delivery date, the manufacturing order of the process group is determined based on the manufacturing order of the neck process, and the determined manufacturing of each process group is performed. When troubles occur when manufacturing in order, the production sequence is adjusted by adjusting the manufacturing sequence of the process group in which the troubles occur. Therefore, there is no need to rely on specialists, and the production sequence is completed. A plan can be made, and furthermore, the man-hours for building the system can be reduced.

【0041】又、本発明によれば、複雑なバッチプラン
トの生産計画を立案する場合、バッチプラントの特徴を
考慮して一般的な製品生産計画の立案をすることがで
き、しかもワ−クステ−ションでも、実時間内で満足で
きる解を得ることができ、利用価値が大きい。
Further, according to the present invention, when a production plan of a complicated batch plant is prepared, a general product production plan can be prepared in consideration of the characteristics of the batch plant. Even in the application, a satisfactory solution can be obtained in real time, and the utility value is great.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の原理説明図である。FIG. 1 is a diagram illustrating the principle of the present invention.

【図2】本発明の実施例構成図である。FIG. 2 is a configuration diagram of an embodiment of the present invention.

【図3】工程分割処理の説明図である。FIG. 3 is an explanatory diagram of a process dividing process.

【図4】装置分割処理の第1の説明図表である。FIG. 4 is a first explanatory diagram of a device dividing process.

【図5】装置分割処理の第2の説明図表である。FIG. 5 is a second explanatory diagram of the device dividing process.

【図6】オ−ダに対する製造現場の状況を表現するため
のデータ構造図である。
FIG. 6 is a data structure diagram for expressing a situation of a manufacturing site for an order.

【図7】ネック工程における製造順序決定処理の流れ図
である。
FIG. 7 is a flowchart of a manufacturing order determination process in a neck process.

【図8】ネック工程の製造順序決定の第1の説明図であ
る。
FIG. 8 is a first explanatory diagram of determining a manufacturing order in a neck step.

【図9】ネック工程の製造順序決定の第2の説明図であ
る。
FIG. 9 is a second explanatory diagram of determining a manufacturing order in a neck step.

【図10】バッチプラントの工程説明図である。FIG. 10 is a process explanatory view of a batch plant.

【符号の説明】[Explanation of symbols]

11・・工程分割処理部 21・・ネック工程決定処理部 22・・ネック工程製造順序決定処理部 23・・工程群製造順序決定処理部 24・・製造順序調整処理部 11. Process division processing unit 21 Neck process determination processing unit 22 Neck process manufacturing sequence determination processing unit 23 Process group manufacturing sequence determination processing unit 24 Manufacturing sequence adjustment processing unit

───────────────────────────────────────────────────── フロントページの続き (72)発明者 森 健二郎 神奈川県川崎市川崎区夜光一丁目2番1 号 日本ゼオン株式会社内 (72)発明者 戸塚 良夫 神奈川県川崎市中原区上小田中1015番地 富士通株式会社内 (72)発明者 新垣 強二 神奈川県川崎市中原区上小田中1015番地 富士通株式会社内 (56)参考文献 特開 平3−104544(JP,A) 特開 昭60−135165(JP,A) 特開 昭63−298665(JP,A) 特開 平3−196948(JP,A) 特開 平3−166026(JP,A) (58)調査した分野(Int.Cl.7,DB名) G06F 17/60 B23Q 41/08 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Kenjiro Mori 1-2-1, Yakko, Kawasaki-ku, Kawasaki-shi, Kanagawa Prefecture Inside Zeon Corporation (72) Inventor Yoshio Totsuka 1015 Kamiodanaka, Nakahara-ku, Kawasaki-shi, Kanagawa Fujitsu Inside (72) Inventor Kenji Aragaki 1015 Uedanaka, Nakahara-ku, Kawasaki City, Kanagawa Prefecture Inside Fujitsu Limited (56) References JP-A-3-104544 (JP, A) JP-A-60-135165 (JP, A) JP-A-63-298665 (JP, A) JP-A-3-196948 (JP, A) JP-A-3-166026 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) ) G06F 17/60 B23Q 41/08

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 バッファ工程を含む複数の工程を経て製
品を製造するバッチプラントにおける製品生産計画装置
において、 全工程をバッファ工程を境に複数の工程グル−プに分割
する手段と、 全工程のうち稼働効率の高い工程をネック工程として求
める手段と、 各オ−ダの納期を含む制約条件を満たすように、ネック
工程における各装置の製造順序を決定する手段と、 前記分割した工程グル−プの製造順序を前記ネック工程
の製造順序に基づいて決定する手段と、 前記決定した各工程グル−プの製造順序で製造すると不
具合が生じた時、工程グル−プの製造順序を調整する
段と、 を有することを特徴とするバッチプラントにおける製品
生産計画装置
1. A product production planning apparatus in a batch plant for manufacturing a product through a plurality of processes including a buffer process, means for dividing all processes into a plurality of process groups with a buffer process as a boundary. Means for determining, as a neck step, a step having a high operating efficiency among all the steps; means for determining a manufacturing order of each device in the neck step so as to satisfy constraints including the delivery date of each order; Means for determining the manufacturing order of the process group based on the manufacturing order of the neck process; and, if a problem occurs when manufacturing is performed in the determined manufacturing order of each process group, the manufacturing order of the process group is changed. Hand to adjust
And a stage, wherein the product in a batch plant
Production planning equipment .
JP24952291A 1991-09-27 1991-09-27 Product production planning equipment in batch plant Expired - Lifetime JP3110102B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24952291A JP3110102B2 (en) 1991-09-27 1991-09-27 Product production planning equipment in batch plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24952291A JP3110102B2 (en) 1991-09-27 1991-09-27 Product production planning equipment in batch plant

Publications (2)

Publication Number Publication Date
JPH05314143A JPH05314143A (en) 1993-11-26
JP3110102B2 true JP3110102B2 (en) 2000-11-20

Family

ID=17194231

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24952291A Expired - Lifetime JP3110102B2 (en) 1991-09-27 1991-09-27 Product production planning equipment in batch plant

Country Status (1)

Country Link
JP (1) JP3110102B2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07192057A (en) * 1993-12-27 1995-07-28 Sekisui Chem Co Ltd Production equipment verification simulator
JP2001134313A (en) * 1999-11-08 2001-05-18 Sumitomo Metal Ind Ltd Method and device for managing operation and recording medium
JP4546654B2 (en) * 2001-02-14 2010-09-15 シャープ株式会社 Production control method
JP4318162B2 (en) * 2002-03-26 2009-08-19 日東電工株式会社 Production schedule planning management method and production schedule planning management program
JP5028991B2 (en) * 2006-12-14 2012-09-19 富士電機株式会社 Manufacturing plan creation system and manufacturing plan creation method
JP5003135B2 (en) * 2006-12-14 2012-08-15 富士電機株式会社 Summary order issuing method and issuing system
JP5163203B2 (en) * 2008-03-18 2013-03-13 富士電機株式会社 Manufacturing plan creation system and manufacturing plan creation method
JP7082530B2 (en) * 2018-06-08 2022-06-08 三菱重工業株式会社 Scheduling device, scheduling method and program
CN111932105B (en) * 2020-08-05 2024-02-06 万华化学(宁波)有限公司 Intermittent chemical product scheduling method, storage medium and system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60135165A (en) * 1983-12-26 1985-07-18 Hitachi Ltd Distributed scheduling system
JPS63298665A (en) * 1987-05-29 1988-12-06 Kanebo Ltd Production planning device
JP2885381B2 (en) * 1989-09-18 1999-04-19 鐘淵化学工業株式会社 Production schedule planning support method
JP2697204B2 (en) * 1989-11-22 1998-01-14 トヨタ自動車株式会社 Work sorting device
JPH03196948A (en) * 1989-12-25 1991-08-28 Matsushita Electric Works Ltd Production planning preparation method

Also Published As

Publication number Publication date
JPH05314143A (en) 1993-11-26

Similar Documents

Publication Publication Date Title
Arbel et al. Performance evaluation of flexible manufacturing systems
EP0755537B1 (en) Priority queue filtering system and method of operation
US5943484A (en) Advanced material requirements planning in microelectronics manufacturing
JP3110102B2 (en) Product production planning equipment in batch plant
WO2020144879A1 (en) Warehousing and shipping management device, warehousing and shipping management system, warehousing and shipping management method, and program
CN110110978A (en) A kind of MES system for cabinet automatic assembly line
JP2004046308A (en) Process load control device and method, and program
Ram et al. Modelling furnace operations using simulation and heuristics
Xiao-Feng et al. A rule-based heuristic finite capacity scheduling system for semiconductor backend assembly
JP2002099685A (en) Optimizing method for scheduling and scheduling device
Krockert et al. Agent-based Decentral Production Planning and Control: A New Approach for Multi-resource Scheduling.
JPH11333674A (en) Production plan forming method for multistage job shop type production
JPH0573574A (en) Production controller
Vargas et al. Managing uncertainty in multilevel manufacturing systems
JP3110103B2 (en) Product production planning equipment in batch plant
JPH07192051A (en) Manufacturing schedule preparation device
JPH05181873A (en) Automatic process design system
JPH08157072A (en) Cargo handling plan preparing device
JPH0877259A (en) Method and device for planning production
JP2816021B2 (en) Equipment load equalization scheduling method
JPS61243701A (en) Method for carrying out of automatic warehouse
JP2885381B2 (en) Production schedule planning support method
JPS62177605A (en) Constituting method for allocation control function of carrier to transport request
Tóth et al. AN EXTENDED PRODUCTION PLANNING MODEL BASED ON THE SIMULATION OF HUMAN CAPABILITIES
JPH08147366A (en) Production planning device

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20000829

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080914

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080914

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090914

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090914

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100914

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100914

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110914

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120914

Year of fee payment: 12

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120914

Year of fee payment: 12