JP3023357U - Horizontal sheet pile for mountain retaining wall - Google Patents

Horizontal sheet pile for mountain retaining wall

Info

Publication number
JP3023357U
JP3023357U JP1995011308U JP1130895U JP3023357U JP 3023357 U JP3023357 U JP 3023357U JP 1995011308 U JP1995011308 U JP 1995011308U JP 1130895 U JP1130895 U JP 1130895U JP 3023357 U JP3023357 U JP 3023357U
Authority
JP
Japan
Prior art keywords
sheet pile
retaining wall
pile body
mountain retaining
horizontal sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1995011308U
Other languages
Japanese (ja)
Inventor
栄 五島
Original Assignee
栄 五島
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 栄 五島 filed Critical 栄 五島
Priority to JP1995011308U priority Critical patent/JP3023357U/en
Application granted granted Critical
Publication of JP3023357U publication Critical patent/JP3023357U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

(57)【要約】 【課題】 仮設山留め壁の構築作業能率を向上させ、山
留め仮設工事の安全性を向上させる。 【解決手段】 先行用横矢板1と継ぎ足し用横矢板2は
横矢板本体3の中央部に水抜き穴7と引き抜き用穴8と
雌ねじ9を形成し、下端部と上端部に係合穴10と11
を形成する。先行用横矢板本体3の係合穴10に受具1
3を離脱可能に取り付ける。先行用横矢板本体3の上方
に継ぎ足し用横矢板本体3を係合穴11,10と係合具
12の係合により離脱可能に接続する。打設済みのH型
鋼16の溝の上部に先行用横矢板本体3の下端両側部を
挿入し、パワーショベルのバケット等で受具13を下方
へ押圧して先行用横矢板本体3をH型鋼16の溝18に
沿って地中に圧入する。この圧入の途中で、若しくはあ
らかじめ先行用横矢板本体3の上部に継ぎ足し用横矢板
本体3を接続することにより、先行用横矢板本体3およ
び継ぎ足し用横矢板本体3を連続して圧入することがで
きる。
(57) [Abstract] [Problem] To improve the construction work efficiency of a temporary mountain retaining wall and improve the safety of temporary mountain retaining work. SOLUTION: A preceding horizontal sheet pile 1 and a lateral cross sheet pile 2 for addition form a drain hole 7, a pull-out hole 8 and a female screw 9 in a central portion of a horizontal sheet pile body 3, and engaging holes 10 in a lower end portion and an upper end portion. And 11
To form. The receiving tool 1 is provided in the engaging hole 10 of the leading side sheet pile main body 3.
Attach 3 detachably. The additional side sheet pile main body 3 is detachably connected by engaging the engaging holes 11 and 10 with the engaging tool 12 above the preceding side sheet pile main body 3. Insert both sides of the lower end of the leading horizontal sheet pile body 3 into the upper part of the groove of the cast H-shaped steel 16, and push the receiving tool 13 downward with a bucket or the like of a power shovel to move the leading horizontal sheet pile body 3 into the H-shaped steel sheet. It is pressed into the ground along the groove 18 of 16. During this press-fitting or by connecting the extension side sheet pile body 3 to the upper portion of the advance side sheet pile body 3 in advance, the advance side sheet pile body 3 and the extension side sheet pile body 3 can be continuously press-fitted. it can.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【考案の属する技術分野】[Technical field to which the device belongs]

本考案は、土木、建築等の山留め仮設工事に用いる山留め壁用横矢板(土留め 板)に関するものである。 The present invention relates to a horizontal sheet pile (earth retaining plate) for a retaining wall used for temporary retaining work for civil engineering and construction.

【0002】[0002]

【従来の技術】[Prior art]

従来、この種の山留め仮設工事においては、まず、山留め壁構築予定箇所に沿 ってH型鋼を所望間隔ごとに地中に打設し、次に、パワーショベルおよび人力に より打設済みのH型鋼の内側を結ぶ線に沿うように土砂等を掘削し、次に、隣り 合うH型鋼のフランジ間の溝に木製の横矢板を下方から順次挿入する。 Conventionally, in this type of temporary earth retaining work, H-shaped steel was first driven into the ground at desired intervals along the planned site of construction of the retaining wall, and then H excavators and human-powered H The earth and sand are excavated along the line connecting the insides of the shape steels, and then wooden horizontal sheet piles are inserted from below in the grooves between the flanges of the adjacent H-shaped steels.

【0003】 そして、上記のように山留め仮設工事が終了すると、H型鋼のフランジに矢板 金物を取り付け、この矢板金物に地中梁を構築するためのコンクリート用型枠の セパレータを取り付けるようになっている。[0003] When the mountain retaining work is completed as described above, a sheet metal product is attached to an H-shaped steel flange, and a separator of a concrete formwork for constructing an underground beam is attached to the sheet metal product. There is.

【0004】[0004]

【考案が解決しようとする課題】[Problems to be solved by the device]

しかしながら、上記のような従来の山留め仮設工事においては、上下方向の幅 が狭い横矢板を隣り合うH型鋼の間に順次下方より挿入するため、仮設山留め壁 の構築作業能率に劣り、また、横矢板を順次挿入する際、H型鋼の間の土砂が崩 れ落ちるため、軟弱な地盤や隣地と近接している場所では土砂崩壊のおそれがあ り、安定している地盤が土圧のモーメントにより動く危険性があるなどの問題が あった。更に、コンクリート用型枠の取付け作業に手数を要し、工事終了後に横 矢板を引き抜くのが困難であり、埋め殺しにしているため、再利用することがで きず、非経済的であるなどの問題もあった。 However, in the conventional temporary earth retaining work, the horizontal sheet piles with a narrow vertical width are sequentially inserted between the adjacent H-shaped steels from below, so the construction efficiency of the temporary earth retaining wall is inferior and the horizontal retaining wall is inferior. When the sheet piles are sequentially inserted, the sediment between the H-shaped steels collapses, so there is a risk of sediment collapse at the soft ground or in a place close to the adjacent land, and the stable ground is affected by the moment of earth pressure. There was a problem such as the risk of moving. Furthermore, the work of installing the concrete formwork is troublesome, and it is difficult to pull out the horizontal sheet pile after the completion of the construction, and since it is buried, it cannot be reused and it is uneconomical. There was also a problem.

【0005】 本考案は、上記のような従来の問題を解決するものであり、仮設山留め壁の構 築作業能率を向上させることができ、また、仮設山留め壁の構築に際し、土砂の 崩壊を防止して山留め仮設工事の安全性を向上させることができるようにした山 留め壁用横矢板を提供することを目的とするものである。The present invention solves the above-mentioned conventional problems, can improve the work efficiency of constructing a temporary earth retaining wall, and prevents the collapse of earth and sand when constructing a temporary earth retaining wall. The purpose of the present invention is to provide a lateral sheet pile for a mountain retaining wall that is capable of improving the safety of temporary construction of the mountain retaining wall.

【0006】[0006]

【課題を解決するための手段】[Means for Solving the Problems]

上記目的を達成するための本考案の技術的手段は、打設されたH型鋼の溝に両 側部が上方から挿入される横矢板本体と、この横矢板本体に設けられ、上方から の押圧力を受ける圧入用受け手段とを備えたものである。 The technical means of the present invention for achieving the above-mentioned object are a horizontal sheet pile body in which both sides are inserted from above into a groove of a cast H-shaped steel, and a horizontal sheet pile body which is provided in the horizontal sheet pile body and is pushed from above. And a receiving means for press-fitting which receives pressure.

【0007】 上記目的を達成するための本考案の他の技術的手段は、上記技術的手段におい て、横矢板本体が先行用横矢板本体と継ぎ足し用横矢板本体とからなり、下位の 横矢板本体の上部と上位の横矢板本体の下部を接続する接続手段を備えたもので ある。Another technical means of the present invention for attaining the above-mentioned object is, in the above-mentioned technical means, a horizontal sheet pile main body consisting of a preceding horizontal sheet pile body and a supplementary side sheet pile body, and a lower horizontal sheet pile. It is provided with a connecting means for connecting the upper part of the main body and the lower part of the upper horizontal sheet pile structure.

【0008】 上記目的を達成するための本考案の他の技術的手段は、上記各技術的手段にお いて、横矢板本体が水抜き穴を有するものである。Another technical means of the present invention for achieving the above object is the above technical means, in which the transverse sheet pile main body has a drain hole.

【0009】 上記目的を達成するための本考案の他の技術的手段は、上記各技術的手段にお いて、横矢板本体が引き抜き用の穴を有するものである。Another technical means of the present invention for achieving the above object is the above technical means, in which the transverse sheet pile body has a hole for pulling out.

【0010】 上記目的を達成するための本考案の更に他の技術的手段は、上記各技術的手段 において、横矢板本体がコンクリート型枠のセパレータを取り付けるための雌ね じを有するものである。[0010] Still another technical means of the present invention for achieving the above-mentioned object is, in each of the above-mentioned technical means, a transverse sheet pile main body having a female screw for attaching a separator of a concrete formwork.

【0011】 そして、上記各技術的手段において、横矢板本体の下端縁を中央部から両側端 部側に至るに従い、上方へ傾斜するように形成するのが好ましい。In each of the above technical means, it is preferable that the lower end edge of the horizontal sheet pile main body be formed so as to incline upward from the central portion toward both end portions.

【0012】 また、上記各技術的手段における接続手段として、下位の横矢板本体の上端縁 部と上位の横矢板本体の下端縁部に一体に係合部を形成し、または下位の横矢板 本体の上端部と上位の横矢板本体の下端部に形成された係合穴と、両係合穴に跨 って離脱可能に係合される係合具とから構成することができる。Further, as the connecting means in each of the above technical means, an engaging portion is integrally formed at the upper edge of the lower horizontal sheet pile body and the lower edge of the upper horizontal sheet pile body, or the lower horizontal sheet pile body is formed. And an engaging hole formed in the upper end portion of the upper side sheet and the lower end portion of the upper horizontal sheet pile main body, and an engaging tool that is detachably engaged across both engaging holes.

【0013】 また、上記各技術的手段における圧入用受け手段として、横矢板本体に形成さ れた係合穴と、この係合穴に離脱可能に係合される受具とから構成するのが好ま しい。Further, as the press-fitting receiving means in each of the above-mentioned technical means, it is composed of an engaging hole formed in the transverse sheet pile main body and a receiving tool which is detachably engaged with the engaging hole. I like it.

【0014】 また、上記各技術的手段において、横矢板本体を、下縁部と上縁部が金属板に より補強されたプラスチックにより形成し、または発泡スチロール等の軽量な合 成樹脂材の表裏が補強骨を介挿したアルミニウム等の軽量な金属材により挟まれ た材料により形成することができる。In each of the above technical means, the main body of the transverse sheet pile is formed of plastic whose lower and upper edges are reinforced by a metal plate, or the front and back sides of a lightweight synthetic resin material such as Styrofoam. It can be made of a material sandwiched between lightweight metal materials such as aluminum with reinforcing bones interposed.

【0015】 上記のように構成された本考案によれば、打設済みの隣り合うH型鋼の溝の上 部に横矢板本体の下端両側部を挿入し、パワーショベルのバケット等で圧入用受 け手段を下方へ押圧して横矢板本体をH型鋼の溝に沿って地中に圧入する。複数 枚の横矢板を用いる場合には、圧入の途中で、若しくはあらかじめ先行用横矢板 本体の上部に接続手段により継ぎ足し用横矢板本体を接続することにより、先行 用横矢板本体および継ぎ足し用横矢板本体を連続して圧入することができる。こ のように横矢板本体を上方から圧入することにより仮設山留め壁を構築すること ができ、また、横矢板本体を上方から圧入することにより土砂の崩壊を防止する ことができる。According to the present invention configured as described above, the lower end both sides of the transverse sheet pile main body are inserted into the upper portions of the adjacent H-shaped steel grooves that have been punched, and the press-fitting receiving member is inserted with a bucket or the like of the power shovel. The transverse sheet pile main body is press-fitted into the ground along the groove of the H-shaped steel by pressing the clamping means downward. When using multiple side sheet piles, the side sheet pile for advance and the side sheet pile for extension are connected in the middle of press-fitting or by connecting the side sheet pile for addition to the upper side of the body for advance sheet by connecting means in advance. The main body can be pressed in continuously. As described above, the temporary pile retaining wall can be constructed by press-fitting the horizontal sheet pile body from above, and the collapse of earth and sand can be prevented by press-fitting the horizontal sheet pile body from above.

【0016】[0016]

【考案の実施の形態】[Embodiment of device]

以下、本考案の実施形態について図面を参照しながら説明する。 まず、本考案の第1の実施形態について説明する。図1および図2は本考案の 第1の実施形態における山留め壁用横矢板を示し、図1は施工状態の一部斜視図 、図2は施工状態の一部断面図である。 Hereinafter, embodiments of the present invention will be described with reference to the drawings. First, a first embodiment of the present invention will be described. 1 and 2 show a lateral sheet pile for a mountain retaining wall according to a first embodiment of the present invention, FIG. 1 is a partial perspective view of a construction state, and FIG. 2 is a partial cross-sectional view of the construction state.

【0017】 図1および図2に示すように、本考案の山留め壁用横矢板(土留め板)は、一 枚の先行用横矢板1と、一枚、若しくは複数枚の継ぎ足し用横矢板2とから構成 されている。先行用横矢板1および継ぎ足し用横矢板2の横矢板本体3は主体部 分4がポリ塩化ビニル等のプラスチックからなり、主体部分4の下縁部と上縁部 が薄肉の金属板5と6により一体的に被覆されて補強されている。各横矢板本体 3の下端縁は中央部から両側端部側に至るに従い、上方へ傾斜するように形成さ れ、かつ断面において中央部が下方へ突出するように形成されている。各横矢板 本体3の上端縁は下端縁に対応して中央部から両側端部側に至るに従い、上方へ 傾斜するように形成され、かつ断面において中央部が下方へ凹入するように形成 されている。各横矢板本体3の中央部には水抜き穴7が複数箇所に形成され、各 横矢板本体3の中央部の下端部と上端部には引き抜き用穴8が形成され、両側部 にはコンクリート型枠のセパレータを取り付けるための雌ねじ9が複数箇所に形 成されている。各横矢板本体3の下端両側部と上端両側部には係合穴10と11 が形成されている。As shown in FIG. 1 and FIG. 2, a lateral sheet pile (earth retaining sheet) for a mountain retaining wall according to the present invention includes one preceding sheet pile 1 and one or a plurality of additional sheet piles 2 for addition. It consists of and. In the main body 3 of the preceding horizontal sheet pile 1 and the additional side sheet pile 2, the main body portion 4 is made of plastic such as polyvinyl chloride, and the lower and upper edges of the main body portion 4 are thin metal plates 5 and 6. Are integrally covered with and reinforced. The lower end edge of each transverse sheet pile body 3 is formed so as to incline upward from the central portion toward both end portions, and the central portion projects downward in cross section. The upper edge of each horizontal sheet pile body 3 is formed so as to incline upward as it goes from the central portion to both end portions in correspondence with the lower edge, and the central portion is formed to be recessed downward in cross section. ing. Drainage holes 7 are formed at a plurality of locations in the center of each horizontal sheet pile body 3, and extraction holes 8 are formed in the lower end and upper end of the center portion of each horizontal sheet pile body 3, and concrete holes are formed on both sides. Female screws 9 for attaching the separator of the mold are formed at a plurality of positions. Engagement holes 10 and 11 are formed in both sides of the lower end and both sides of the upper end of each horizontal sheet pile body 3.

【0018】 接続手段に用いられる係合具12は金属製で、リングの一部が切除されたC型 に形成されている。そして、開放側端部が下位の横矢板本体3の上端両側部の係 合穴11と上位の横矢板本体3の下端両側部の係合穴10に跨って離脱可能に係 合されることにより、下位と上位の横矢板本体3同士が離脱可能に接続されるよ うになっている。The engaging tool 12 used for the connecting means is made of metal, and is formed in a C-shape in which a part of the ring is cut off. The open side end is detachably engaged across the engaging holes 11 on both upper ends of the lower horizontal sheet pile body 3 and the engaging holes 10 on both lower ends of the upper horizontal sheet pile body 3. The lower and upper lateral sheet pile bodies 3 are detachably connected to each other.

【0019】 圧入用受け手段に用いられる受け具13は金属製で、先端部に受部14が形成 され、基端部に係合部15が形成されている。そして、受具13が係合部15側 から下位の先行用横矢板本体3の下端両側部の係合穴10に挿通され、係合部1 5が先行用横矢板本体3の背面に離脱可能に係合され、この係合状態で受部14 が先行用横矢板本体3の前方へ突出されるようになっている。The receiving tool 13 used as the press-fitting receiving means is made of metal, and the receiving portion 14 is formed at the distal end portion, and the engaging portion 15 is formed at the proximal end portion. Then, the receiving tool 13 is inserted from the side of the engaging portion 15 into the engaging holes 10 on both sides of the lower end of the preceding horizontal sheet pile body 3, and the engaging portion 15 can be detached from the rear surface of the preceding sheet pile body 3. In this engaged state, the receiving portion 14 is projected to the front of the leading side sheet pile main body 3.

【0020】 上記のように接続手段に用いる係合具12と圧入用受け手段に用いる受具13 を横矢板本体3と別箇に形成することにより、横矢板本体3を扁平形状に形成す ることができ、したがって、輸送や保管の際に安定状態で、しかも、死空間を少 なくして高く積み重ねることができる。By forming the engaging tool 12 used for the connecting means and the receiving tool 13 used for the press-fitting receiving means separately from the horizontal sheet pile body 3 as described above, the horizontal sheet pile body 3 is formed in a flat shape. Therefore, it can be stacked in a stable state at the time of transportation and storage, and can be stacked high with a small dead space.

【0021】 以上のように構成された本考案の山留め壁用横矢板を用いて山留め仮設工事を 行うには、まず、山留め壁構築予定箇所に沿ってH型鋼16を所望間隔ごとに地 中に打設する。次に、パワーショベルおよび人力により打設済みのH型鋼の内側 を結ぶ線に沿うように土砂等を掘削する。次に、隣り合うH型鋼16のフランジ 17間の溝18の上部に先行用横矢板本体3の下端両側部を挿入し、油圧式等の パワーショベル19のバケット20等で受具13の受部14を下方へ押圧して先 行用横矢板本体3をH型鋼16の溝18に沿って地中に圧入する。このとき、先 行用横矢板本体3の下端縁は上記のように中央部から両側部側に至るに従い、上 方へ傾斜され、しかも、断面において、中央部が下方へ突出するように形成され ているので、土砂の抵抗を軽減することができ、圧入作業を容易に、かつ迅速に 行うことができる。この圧入の途中で、若しくはあらかじめ先行用横矢板本体3 の上部に上記のように係合具12により継ぎ足し用横矢板3を一枚、若しくは複 数枚順次接続することにより、先行用横矢板1および継ぎ足し用横矢板2を連続 して圧入することができる。この圧入作業はパワーショベル等による掘削作業と 同時に行うことができる。In order to perform a temporary earth retaining work using the lateral sheet pile for mountain retaining wall of the present invention constructed as described above, first, H-shaped steel 16 is ground at desired intervals along the planned site of constructing the mountain retaining wall. To set. Next, excavate the earth and sand along the line connecting the inside of the H-section steel that has been cast by a power shovel and human power. Next, the lower end both sides of the preceding horizontal sheet pile body 3 are inserted into the upper portion of the groove 18 between the flanges 17 of the adjacent H-shaped steels 16, and the receiving portion of the receiving tool 13 is received by the bucket 20 of the hydraulic excavator 19 or the like. 14 is pushed downward to press the leading transverse sheet pile main body 3 into the ground along the groove 18 of the H-shaped steel 16. At this time, the lower edge of the forward sheet pile 3 is inclined upward as it goes from the center to both sides as described above, and the center is formed so as to project downward in the cross section. Therefore, the resistance of the soil can be reduced, and the press-fitting work can be performed easily and quickly. During the press-fitting, or in advance, by connecting one or a plurality of the horizontal sheet piles 3 for addition to the upper portion of the main body 3 of the preceding sheet by the engagement tool 12 as described above, the horizontal sheet piles 1 for the preceding sheets are sequentially connected. And the horizontal sheet pile 2 for replenishment can be continuously press-fitted. This press-fitting work can be performed at the same time as excavation work using a power shovel or the like.

【0022】 このように横矢板1,2を上方から連続的に圧入することにより仮設山留め壁 を構築することができるので、作業能率を向上させることができるとともに、土 砂の崩壊を防止して山留め仮設工事の安全性を向上させることができる。As described above, since the temporary mountain retaining wall can be constructed by continuously press-fitting the horizontal sheet piles 1 and 2 from above, the work efficiency can be improved and the collapse of the earth and sand can be prevented. It is possible to improve the safety of temporary construction work for mountain retaining.

【0023】 そして、上記のように山留め仮設工事が終了すると、雌ねじ9を利用してコン クリート型枠のセパレータ(共に図示省略)を取り付け、コンクリート型枠とH 型鋼16および横矢板1,2との間にコンクリートを充填して地中梁等を構築す る。この間、水抜き穴7により地下水等を抜いて水圧を軽減することができるの で、横矢板1,2等を安定状態に維持することができる。Then, when the temporary mountain clasp construction is completed as described above, a concrete form separator (both not shown) is attached using the female screw 9, and the concrete form and the H-shaped steel 16 and the side sheet piles 1 and 2 are attached. Concrete beams are filled in between to construct underground beams. During this time, the water pressure can be reduced by draining groundwater or the like through the drain hole 7, so that the horizontal sheet piles 1, 2 and the like can be maintained in a stable state.

【0024】 構築後、引き抜き用穴8を利用して継ぎ足し用横矢板2および先行用横矢板1 をH型鋼16から上方へ除去することができ、したがって、再利用することがで きる。After construction, the pull-out holes 8 can be used to remove the add-on side sheet pile 2 and the preceding side sheet pile 1 upwardly from the H-section steel 16 and thus be reused.

【0025】 次に、本考案の第2の実施形態について説明する。図3および図4は本考案の 第2の実施形態における山留め壁用横矢板を示し、図3は施工状態の一部斜視図 、図4は施工状態の一部断面図である。Next, a second embodiment of the present invention will be described. 3 and 4 show a lateral sheet pile for a mountain retaining wall according to a second embodiment of the present invention, FIG. 3 is a partial perspective view of a construction state, and FIG. 4 is a partial cross-sectional view of the construction state.

【0026】 本実施形態の特徴とするところは、図3、図4に示すように、各横矢板本体3 を、発泡スチロール等の軽量な合成樹脂材21の表裏が補強骨22を介挿したア ルミニウム等の軽量な金属材23により挟まれた材料により形成し、下位の横矢 板本体3の上端縁部と上位の横矢板本体3の下端縁部に対称的で反対側に突出す るように一体に形成した係合部24と25を離脱可能に係合して接続するように し、補強骨22に取り付けたナット26によりセパレータ取付け用の雌ねじを形 成するようにした点にあり、その他の構成については上記第1の実施形態と同様 にあるので、同一部分には同一符号を付してその説明を省略する。The feature of this embodiment is that, as shown in FIGS. 3 and 4, each side sheet pile body 3 is made of a lightweight synthetic resin material 21 such as Styrofoam, the front and back of which are reinforced bones 22. It is made of a material sandwiched between light-weight metal materials 23 such as luminium, so that it projects symmetrically to the upper edge of the lower horizontal sheet pile body 3 and the lower edge of the upper horizontal sheet pile body 3 on opposite sides. It is that the integrally formed engaging portions 24 and 25 are detachably engaged and connected, and that the nut 26 attached to the reinforcing bone 22 forms a female screw for attaching the separator. Since the configuration is the same as that of the first embodiment, the same parts are designated by the same reference numerals and the description thereof will be omitted.

【0027】 なお、上記第1、第2の実施形態では、先行用横矢板本体3と継ぎ足し用横矢 板本体3を同じ形状に形成して兼用するようにしているが、別々に形成すること ができ、したがって、先行用横矢板本体3の上端縁部と継ぎ足し用横矢板本体3 の下端縁はほぼ水平となる直線状に形成してもよく、第2の実施形態における先 行用横矢板本体3の下端縁は係合部25を設けることなく、第1の実施形態の先 行用横矢板本体3の下端縁と同様の形状に形成してもよい。また、横矢板本体3 は上記第1、第2実施形態のほか、薄鋼板にリブを突設して補強し、または薄肉 の合成樹脂板にリブを一体に設けて補強するなど、種々の構成を用いることがで きる。また、上記第1、第2の実施形態は各部を入れ替えるなど、適宜組み合わ せることができる。更に、上記第1、第2の実施形態では、先行用横矢板1と継 ぎ足し用横矢板2を用いているが、山留め壁の高さによっては横矢板を一枚のみ 圧入するようにしてもよい。本考案は、このほか、その基本的技術思想を逸脱し ない範囲で種々設計変更することができる。In the first and second embodiments described above, the leading lateral sheet pile body 3 and the supplementary lateral sheet pile body 3 are formed to have the same shape and are also used, but they may be formed separately. Therefore, the upper edge portion of the preceding horizontal sheet pile body 3 and the lower edge of the supplementary horizontal sheet pile body 3 may be formed in a straight line which is substantially horizontal. The lower end edge of 3 may be formed in the same shape as the lower end edge of the advance transverse sheet pile body 3 of the first embodiment without providing the engaging portion 25. In addition to the first and second embodiments described above, the horizontal sheet pile body 3 has various structures such as ribs protruding from a thin steel plate for reinforcement, or ribs integrally provided on a thin synthetic resin plate for reinforcement. Can be used. Further, the first and second embodiments can be combined as appropriate by exchanging the respective parts. Further, in the above first and second embodiments, the preceding side sheet pile 1 and the additional side sheet pile 2 are used, but depending on the height of the mountain retaining wall, only one side sheet pile may be press-fitted. Good. Besides, the present invention can be variously modified in design without departing from the basic technical idea.

【0028】[0028]

【考案の効果】 以上説明したように本考案によれば、打設済みの隣り合うH型鋼の溝の上部に 横矢板本体の下端両側部を挿入し、パワーショベルのバケット等で圧入用受け手 段を下方へ押圧して横矢板本体をH型鋼の溝に沿って地中に圧入する。複数枚の 横矢板を用いる場合には、圧入の途中で、若しくはあらかじめ先行用横矢板本体 の上部に接続手段により継ぎ足し用横矢板本体を接続することにより、先行用横 矢板本体および継ぎ足し用横矢板本体を連続して圧入することができる。このよ うに横矢板本体を上方から圧入することにより仮設山留め壁を構築することがで き、したがって、作業能率を向上させることができ、また、横矢板を上方から圧 入することにより土砂の崩壊を防止することができ、したがって、山留め仮設工 事の安全性を向上させることができる。As described above, according to the present invention, the lower end both sides of the horizontal sheet pile body are inserted into the upper portions of the grooves of the adjacent H-shaped steels that have been punched, and the press-fitting receiving step is performed by the bucket of the power shovel or the like. Is pressed downward to press the transverse sheet pile body into the ground along the groove of the H-shaped steel. When using multiple horizontal sheet piles, the side sheet pile for advance and the side sheet pile for extension are connected by connecting means to the upper side of the main body of the preceding side sheet pile by connecting means in advance or in advance. The main body can be pressed in continuously. In this way, the temporary pile retaining wall can be constructed by press-fitting the horizontal sheet pile body from above, and therefore the work efficiency can be improved. Therefore, it is possible to improve the safety of the temporary work for retaining the mountain.

【0029】 また、横矢板本体に水抜き穴を形成することにより、水圧を軽減することがで き、したがって、仮設山留め壁を安定状態に維持することができる。Further, the water pressure can be reduced by forming the water drain hole in the horizontal sheet pile body, and therefore the temporary mountain retaining wall can be maintained in a stable state.

【0030】 また、横矢板本体に引き抜き用の穴を形成することにより、工事終了後に引き 抜き用穴を利用して引き抜くことができ、したがって、再利用による経済性の向 上等を図ることができる。Further, by forming the pull-out hole in the main body of the transverse sheet pile, the pull-out hole can be used to pull out after the construction is completed, and therefore, the economical efficiency due to reuse can be achieved. it can.

【0031】 また、横矢板本体にコンクリート型枠のセパレータを取り付けるための雌ねじ を設けることにより、コンクリート型枠の取付け作業を簡単に、かつ迅速に行う ことができる。Further, by providing the horizontal sheet pile body with the female screw for attaching the separator of the concrete formwork, the work of attaching the concrete formwork can be performed easily and quickly.

【0032】 また、横矢板本体の下端縁を中央部から両側端部側に至るに従い、上方へ傾斜 するように形成することにより、土に圧入する際の抵抗を少なくし、圧入作業を 容易に行うことができる。Further, by forming the lower edge of the horizontal sheet pile main body so as to incline upward from the center to both end sides, the resistance when press-fitting into the soil is reduced and the press-fitting work is facilitated. It can be carried out.

【0033】 また、接続手段として、下位の横矢板本体の上端縁部と上位の横矢板本体の下 端縁部に一体に形成した係合部を用いることにより、接続作業を簡単に、かつ迅 速に行うことができる。Further, as the connecting means, by using the engaging portion integrally formed on the upper end edge of the lower horizontal sheet pile main body and the lower end edge of the upper horizontal sheet pile main body, the connecting work can be performed easily and quickly. It can be done quickly.

【0034】 また、接続手段として、下位の横矢板本体の上端部と上位の横矢板本体の下端 部に形成された係合穴と、両係合穴に跨って離脱可能に係合される係合具とから 構成し、また、圧入用受け手段として、横矢板本体に形成された係合穴と、この 係合穴に離脱可能に係合される受具とから構成することにより、横矢板本体を運 搬、保管の際に容易に積み重ねることができ、しかも、嵩張らないようにするこ とができる。In addition, as connecting means, engaging holes formed in the upper end portion of the lower horizontal sheet pile body and the lower end portion of the upper horizontal sheet pile body are engaged with each other so as to be detachably engaged across both the engaging holes. And a receiving member for press-fitting, which includes an engaging hole formed in the body of the horizontal sheet pile and a receiving member that is detachably engaged with the engaging hole. The main bodies can be easily stacked for transportation and storage, and can be made bulky.

【0035】 また、横矢板本体を、下縁部と上縁部が金属板により補強されたプラスチック により形成することにより、軽量化を図り、持ち運びの便等を図ることができる 。Further, by forming the lateral sheet pile main body from plastic whose lower edge portion and upper edge portion are reinforced by the metal plate, it is possible to reduce the weight and facilitate the convenience of carrying.

【0036】 また、横矢板本体を、発泡スチロール等の軽量な合成樹脂材の表裏が補強骨を 介挿したアルミニウム等の軽量な金属材により挟まれた材料により形成すること により、軽量化を図り、持ち運びの便等を図ることができる。Further, by forming the horizontal sheet pile body by a material in which the front and back of a lightweight synthetic resin material such as Styrofoam are sandwiched between lightweight metal materials such as aluminum with reinforcing bones interposed, the weight is reduced, It is easy to carry around.

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案の第1の実施形態における山留め壁用横
矢板を示す施工状態の一部斜視図である。
FIG. 1 is a partial perspective view of a construction state showing a lateral sheet pile for a mountain retaining wall according to a first embodiment of the present invention.

【図2】同山留め壁用横矢板を示す施工状態の一部断面
図である。
FIG. 2 is a partial cross-sectional view of a construction state showing a horizontal sheet pile for the mountain retaining wall.

【図3】本考案の第2の実施形態における山留め壁用横
矢板を示す施工状態の一部斜視図である。
FIG. 3 is a partial perspective view of a lateral sheet pile for a mountain retaining wall according to a second embodiment of the present invention in a construction state.

【図4】同山留め壁用横矢板を示す施工状態の一部断面
図である。
FIG. 4 is a partial cross-sectional view of a construction state showing a horizontal sheet pile for the mountain retaining wall.

【符号の説明】[Explanation of symbols]

1 先行用横矢板 2 継ぎ足し用横矢板 3 横矢板本体 7 水抜き穴 8 引き抜き用穴 9 雌ねじ 10 係合穴 11 係合穴 12 係合具 13 受具 16 H型鋼 1 Horizontal Sheet Pile for Advance 2 Side Sheet Pile for Replenishment 3 Sheet Pile Body 7 Drain Hole 8 Extraction Hole 9 Female Thread 10 Engagement Hole 11 Engagement Hole 12 Engagement Tool 13 Receiver 16 H-Shaped Steel

Claims (11)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 打設されたH型鋼の溝に両側部が上方か
ら挿入される横矢板本体と、この横矢板本体に設けら
れ、上方からの押圧力を受ける圧入用受け手段とを備え
た山留め壁用横矢板。
1. A horizontal sheet pile main body whose both sides are inserted from above into a groove of a cast H-shaped steel, and a press-fitting receiving means which is provided in the horizontal sheet pile body and receives a pressing force from above. Horizontal sheet pile for mountain retaining wall.
【請求項2】 横矢板本体が先行用横矢板本体と継ぎ足
し用横矢板本体とからなり、下位の横矢板本体の上部と
上位の横矢板本体の下部を接続する接続手段を備えた請
求項記載の山留め壁用横矢板。
2. The horizontal sheet pile body comprises a preceding sheet pile body and a supplementary sheet pile body, and a connecting means for connecting an upper portion of the lower sheet pile body to a lower portion of the upper sheet pile body. Horizontal sheet pile for mountain retaining wall.
【請求項3】 横矢板本体が水抜き穴を有する請求項1
または2記載の山留め壁用横矢板。
3. The horizontal sheet pile body has a drain hole.
Alternatively, the horizontal sheet pile for the mountain retaining wall described in 2.
【請求項4】 横矢板本体が引き抜き用の穴を有する請
求項1ないし3のいずれかに記載の山留め壁用横矢板。
4. The side sheet pile for a mountain retaining wall according to claim 1, wherein the side sheet pile body has a hole for pulling out.
【請求項5】 横矢板本体がコンクリート型枠のセパレ
ータを取り付けるための雌ねじを有する請求項1ないし
4のいずれかに記載の山留め壁用横矢板。
5. The lateral sheet pile for a mountain retaining wall according to claim 1, wherein the lateral sheet pile body has a female screw for attaching a separator of a concrete formwork.
【請求項6】 横矢板本体の下端縁が中央部から両側端
部側に至るに従い、上方へ傾斜するように形成された請
求項1ないし5のいずれかに記載の山留め壁用横矢板。
6. The lateral sheet pile for a mountain retaining wall according to claim 1, wherein the lower edge of the lateral sheet pile main body is formed so as to incline upward from the central portion toward both end portions.
【請求項7】 接続手段が、下位の横矢板本体の上端縁
部と上位の横矢板本体の下端縁部に一体に形成された係
合部である請求項2ないし6のいずれかに記載の山留め
壁用横矢板。
7. The connecting means is an engaging portion integrally formed at an upper end edge of a lower horizontal sheet pile body and a lower end edge of an upper horizontal sheet pile body. Horizontal sheet pile for mountain retaining wall.
【請求項8】 接続手段が、下位の横矢板本体の上端部
と上位の横矢板本体の下端部に形成された係合穴と、両
係合穴に跨って離脱可能に係合される係合具とから成る
請求項2ないし6のいずれかに記載の山留め壁用横矢
板。
8. The engagement means, wherein the connecting means is engaged with the engaging holes formed in the upper end portion of the lower horizontal sheet pile body and the lower end portion of the upper horizontal sheet pile body, and is detachably engaged across both the engaging holes. The lateral sheet pile for a mountain retaining wall according to any one of claims 2 to 6, which comprises a fitting.
【請求項9】 圧入用受け手段が、横矢板本体に形成さ
れた係合穴と、この係合穴に離脱可能に係合される受具
とから成る請求項1ないし8のいずれかに記載の山留め
壁用横矢板。
9. The press-fitting receiving means comprises an engaging hole formed in the lateral sheet pile main body and a receiving member removably engaged with the engaging hole. Horizontal sheet pile for mountain retaining wall.
【請求項10】 横矢板本体が、下縁部と上縁部を金属
板により補強したプラスチックにより形成された請求項
1ないし9のいずれかに記載の山留め壁用横矢板。
10. The lateral sheet pile for a mountain retaining wall according to claim 1, wherein the lateral sheet pile main body is formed of plastic in which a lower edge portion and an upper edge portion are reinforced by a metal plate.
【請求項11】 横矢板本体は、発泡スチロール等の軽
量な合成樹脂材の表裏を補強骨が介挿されたアルミニウ
ム等の軽量な金属材により挟んだ材料により形成された
請求項1ないし9のいずれかに記載の山留め壁用横矢
板。
11. The transverse sheet pile main body is formed of a material in which a front and back of a lightweight synthetic resin material such as Styrofoam are sandwiched by a lightweight metal material such as aluminum with reinforcing bones interposed. Horizontal sheet pile for mountain retaining wall described in crab.
JP1995011308U 1995-09-29 1995-09-29 Horizontal sheet pile for mountain retaining wall Expired - Lifetime JP3023357U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1995011308U JP3023357U (en) 1995-09-29 1995-09-29 Horizontal sheet pile for mountain retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1995011308U JP3023357U (en) 1995-09-29 1995-09-29 Horizontal sheet pile for mountain retaining wall

Publications (1)

Publication Number Publication Date
JP3023357U true JP3023357U (en) 1996-04-16

Family

ID=43158628

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1995011308U Expired - Lifetime JP3023357U (en) 1995-09-29 1995-09-29 Horizontal sheet pile for mountain retaining wall

Country Status (1)

Country Link
JP (1) JP3023357U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017197951A (en) * 2016-04-27 2017-11-02 戸田建設株式会社 Countermeasure wall against drawn-in subsidence and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017197951A (en) * 2016-04-27 2017-11-02 戸田建設株式会社 Countermeasure wall against drawn-in subsidence and construction method thereof

Similar Documents

Publication Publication Date Title
KR101640795B1 (en) Furlable earth retaining structure for provisional facilities and construction method thereof
JP3023357U (en) Horizontal sheet pile for mountain retaining wall
KR101677236B1 (en) Double-layered steel plate cutoff wall structure and construction method of cutoff wall of temporary facility using the same
KR100458821B1 (en) The length adjustable lagging and its using method of braced wall construction
KR20110022956A (en) Pile structure having changing section and retaining wall using the same
KR100928566B1 (en) Roof assembly and constructing method thereof
CN214783958U (en) Foundation ditch stagnant water curtain structure
JPH11190024A (en) Earth retaining work
JP2625004B2 (en) Waterway construction method for soft ground and waterway block used therefor
JPH0721196B2 (en) Reverse construction method of underground structure
EP0910710B1 (en) Process for carrying out a sheet piling underneath an existing bearing wall or partition
JP3009414U (en) Non-collapse steel sheet pile
KR101557038B1 (en) Construction method for underground structure
JP3072651U (en) Concrete block for earth retaining
JP3000495B2 (en) Large-scale, deep steel continuous basement wall and method of constructing the same
JPS5847091Y2 (en) Earth retention shoring device for excavated trenches
JPS6017898B2 (en) Construction method of pile foundation with underground wall
JP2004124554A (en) Basement structure
JP2707326B2 (en) Locking box for underground wall construction
JP3422974B2 (en) Earth retaining plate
JP2584682Y2 (en) Work frame for excavation work
JPH1088592A (en) Concrete retaining wall
JP4097646B2 (en) Concrete wall
JP4195215B2 (en) Mountain retaining method and foundation construction method
JP2000144718A (en) Concrete composite sheet pile