JP2989413B2 - Tunnel junction segment, tunnel junction structure and tunnel connection method - Google Patents

Tunnel junction segment, tunnel junction structure and tunnel connection method

Info

Publication number
JP2989413B2
JP2989413B2 JP5052287A JP5228793A JP2989413B2 JP 2989413 B2 JP2989413 B2 JP 2989413B2 JP 5052287 A JP5052287 A JP 5052287A JP 5228793 A JP5228793 A JP 5228793A JP 2989413 B2 JP2989413 B2 JP 2989413B2
Authority
JP
Japan
Prior art keywords
steel wire
tunnel
segment
fixing
shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP5052287A
Other languages
Japanese (ja)
Other versions
JPH06264696A (en
Inventor
彰男 志関
幸司 多田
徹 谷口
雅弘 中川
裕次 舘川
誠 請川
雅一 福若
高志 平本
秀幸 小林
修身 橋本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Toda Corp
Original Assignee
Toda Corp
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp, Kawasaki Steel Corp filed Critical Toda Corp
Priority to JP5052287A priority Critical patent/JP2989413B2/en
Publication of JPH06264696A publication Critical patent/JPH06264696A/en
Application granted granted Critical
Publication of JP2989413B2 publication Critical patent/JP2989413B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明はトンネル内をライニング
するためのトンネル接合用セグメント及びトンネル接合
構造並びにトンネル接続方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel junction segment for lining a tunnel and a tunnel junction.
The present invention relates to a structure and a tunnel connection method.

【0002】[0002]

【従来の技術】近年、都市部における地下鉄道等の構築
は開削工法にかわってシールド工法が多用されるように
なっている。このようなシールド工法により地下鉄道の
駅部等の大断面を構築する場合はルーフシールド工法、
かんざし桁工法、円形多連シールド工法等の各種の工法
が用いられている。しかし、これらの工法はいずれもト
ンネルの断面が円形であり、それによる種々の問題があ
る。そこで、本願出願人は上記の問題を解決するため
に、特願平4−104039号等の工法を開発した。
2. Description of the Related Art In recent years, a shield method has been frequently used in the construction of a subway or the like in an urban area in place of a digging method. When constructing a large section such as a subway station by such a shield method, the roof shield method,
Various construction methods, such as a bridge girder construction method and a circular multiple shield construction method, are used. However, all of these construction methods have a circular cross section of the tunnel, which causes various problems. In order to solve the above problem, the applicant of the present application has developed a method such as Japanese Patent Application No. 4-104039.

【0003】このような工法においてPC構造を採用す
る場合は、図5に示すように、並列状に近接させて構築
した断面矩形のシールドトンネル20間の地山30を掘
削して、その対向するセグメント20aを解体した後、
これらのシールドトンネル20間にわたってPC鋼線4
0を配設し、シールドトンネル20の内面にコンクリー
トを覆工するものである。
[0003] When employing the PC structure in such a method, as shown in FIG. 5, by drilling a natural ground 30 between a rectangular cross section of the shield tunnel 20 constructed in close proximity to the parallel form, opposite its After dismantling the segment 20a
PC steel wire over between these shield tunnel 20 4
0 and place concrete on the inner surface of shield tunnel 20
To lining

【0004】[0004]

【発明が解決しようとする課題】しかし、上記の工法に
おいては、PC鋼線の定着部の構造が非常に重要であ
り、かつセグメントも一体構造として緊張することが望
ましいが、現状ではPC鋼線を定着する作業が困難であ
り、またセグメントが一体構造として緊張されていな
い。本発明は上記のような問題点に鑑みてなされたもの
であり、その目的は、PC鋼線の定着作業を容易に行え
とともに、セグメントがシールドトンネルの一体構造
として緊張されるトンネル接合用セグメント及びトンネ
ル接合構造並びにトンネル接続方法に関するものであ
る。
However, in the above-mentioned construction method, the structure of the anchoring portion of the PC steel wire is very important, and it is desirable that the segments be tensioned as an integral structure. Is difficult to fix, and the segments are not tensioned as an integral structure. The present invention has been made in view of the above problems, its object, along with enable easy fixing work of PC steel wire, segment is the tunnel junction for segments and tension as a unitary structure of the shield tunnel Tonne
The junction structure and tunnel connection method.
You.

【0005】[0005]

【課題を解決するための手段】以上の課題を解決するた
めの手段は、トンネル接合用セグメントが、並列かつ近
接して構築されたシールドトンネルをPC鋼線によって
一体的に接合するためのセグメントであって、セグメン
ト本体の裏面に内側に突出したPC鋼線用定着金具を設
け、該PC鋼線用定着金具の両側に開口部が形成される
とともに、PC鋼線用定着金具の上面には前記PC鋼線
の挿入孔が設けられたことを特徴とする。またトンネル
接合構造が、並列かつ近接して構築された断面矩形のシ
ールドトンネル間の地山の掘削と、これらのシールドト
ンネルに覆工された鋼製セグメントの内側に打設された
コンクリートとにより前記シールドトンネル同士が連通
され、前記コンクリート中に埋設され、かつ一端が両側
のシールドトンネルのセグメントに定着されたPC鋼線
が、シールドトンネル間の中央部における定着体に緊張
定着されことを特徴とする。 トンネル接続方法が、適宜
間隔をもって削孔した立坑間に並列かつ近接した断面矩
形のシールドトンネルを構築する工程と、これらシール
ドトンネルの長辺方向に位置した対向壁のセグメントの
解体と、地山の開放掘削とを行ってシールドトンネル同
士を連通させる工程と、前記両側のシールドトンネルの
セグメントにPC鋼線の一端部を定着する工程と、前記
シールドトンネルの内側にコンクリートを打設してその
中に前記PC鋼線を埋設する工程と、該コンクリートの
硬化後に前記シールドトンネル間の中央部における定着
体に前記PC鋼線の他端部を緊張定着する工程とからな
ることを特徴とする
A means for solving the above problems is that the segments for tunnel junction are parallel and close to each other.
Shield tunnel constructed in contact with PC steel wire
A segment for joining together
A fixing bracket for PC steel wire is provided on the back of the
Openings are formed on both sides of the fixing bracket for PC steel wire.
At the same time, on the upper surface of the fixing bracket for PC steel wire, the PC steel wire
Is provided. Also tunnel
The joint structure is a rectangular cross-section
Excavation between the tunnels and the shield tunnels
Cast inside steel segments lined with channels
The shield tunnels communicate with each other by concrete
Buried in the concrete, and one end on both sides
Steel wire anchored in a segment of a shield tunnel in Japan
Tensions the anchor in the middle between the shield tunnels
It is characterized by being fixed. Tunnel connection method is appropriate
Parallel and close cross section rectangles between shafts drilled at intervals
Of building a shield tunnel with a shape
Of the opposite wall segment located along the long side of the tunnel
Demolition and open excavation of the ground were carried out, and
And the shield tunnels on both sides
Fixing one end of the PC steel wire to the segment;
Cast concrete inside the shield tunnel
Burying the PC steel wire in the concrete,
Fixation at the center between the shield tunnels after curing
Fixing the other end of the PC steel wire to the body.
It is characterized by that .

【0006】[0006]

【作用】而して、セグメントの裏面にPC鋼線用定着金
具を設けたことにより、PC鋼線の定着作業を容易に行
うことができると共に、セグメントをシールドトンネル
の一体構造として緊張することができる。
By providing the fixing member for the PC steel wire on the back surface of the segment, the fixing operation of the PC steel wire can be easily performed, and the segment can be tensioned as an integral structure of the shield tunnel. it can.

【0007】[0007]

【実施例】以下、本発明の一実施例を図面に基づいて説
明する。図1は本発明の第1実施例のセグメントの背面
図、図2の(1)及び(2)はPC鋼線用定着金具の拡
大断面図、図4は隣接したシールドトンネル間にPC鋼
線を配設した断面図である。
An embodiment of the present invention will be described below with reference to the drawings. 1 is a rear view of a segment according to a first embodiment of the present invention, (1) and (2) of FIG. 2 are enlarged cross-sectional views of a fixing bracket for a PC steel wire, and FIG. 4 is a PC steel wire between adjacent shield tunnels. It is sectional drawing in which was arrange | positioned.

【0008】本発明のセグメント1は鋼製セグメントで
あり、周面にフランジ1aが突設され、このフランジ1
aにはセグメント同士を接続するためのボルト孔1bを
備えるとともに、背面側に複数のPC鋼線用定着金具2
を備えている。このPC鋼線用定着金具2は両側に開口
部3が形成され、その上面にPC鋼線の挿入孔4を備え
ている。そして、PC鋼線5の定着端部をナット6で止
める場合は、図2の(1)に示すように、PC鋼線5の
端部をPC鋼線用定着金具2の挿入孔4に挿入してネジ
部5aにナット6を螺合することにより定着するものと
する。また、PC鋼線5の定着端部をくさびで止める場
合は、図2の(2)に示すように、PC鋼線用定着金具
2に取り付けたアンカーヘッド7にPC鋼線5の端部を
挿入し、かつくさび7aを嵌合することにより定着する
ものとする。そしてこのような定着作業は全てPC鋼線
用定着金具2の両側の開口部3から行うものとする。
The segment 1 of the present invention is a steel segment, and has a flange 1a protruding from a peripheral surface thereof.
a is provided with bolt holes 1b for connecting the segments, and a plurality of fixing members 2 for PC steel wires are provided on the back side.
It has. The fixing member 2 for a PC steel wire has openings 3 on both sides, and has an insertion hole 4 for a PC steel wire on the upper surface thereof. When fixing the fixing end of the PC steel wire 5 with the nut 6, the end of the PC steel wire 5 is inserted into the insertion hole 4 of the fixing bracket 2 for the PC steel wire as shown in (1) of FIG. Then, the fixing is performed by screwing the nut 6 into the screw portion 5a. When the fixing end of the PC steel wire 5 is stopped by a wedge, as shown in FIG. 2B, the end of the PC steel wire 5 is attached to the anchor head 7 attached to the fixing bracket 2 for the PC steel wire. The fixing is performed by inserting and fitting the wedge 7a. All such fixing operations are performed from the openings 3 on both sides of the fixing member 2 for PC steel wire.

【0009】次に、これらのセグメント1を使用して構
築したシールドトンネル8を接合する場合について説明
する。これは図3に示すような矩形状のシールド掘進機
9で、適宜間隔をもって削孔した立坑間に並列かつ近接
したトンネルを掘削し、そこに鋼製セグメンを覆工して
断面矩形のシールドトンネル8を近接して構築する。
Next, the case where the shield tunnel 8 constructed by using these segments 1 is joined will be described. This is a rectangular shield tunneling machine 9 as shown in FIG. 3, which excavates parallel and adjacent tunnels between the shafts drilled at appropriate intervals, and wraps steel segments there to form a shield tunnel having a rectangular cross section. Build 8 closely.

【0010】そして、この左右のシールドトンネル8を
構築したら地山の適宜範囲を地盤改良して止水した後、
長辺方向における対向壁のセグメント1を解体し、これ
らのセグメント1の解体と同時にシールドトンネル8間
に山留鋼板10を掛け渡すことにより、地山の開放掘削
を行う。
After the left and right shield tunnels 8 are constructed, the appropriate area of the ground is improved and the water is stopped.
Open excavation of the ground is performed by dismantling the segments 1 of the opposing wall in the long-side direction and, at the same time, dismantling these segments 1, and bridging the retaining steel plate 10 between the shield tunnels 8.

【0011】次に、前記地山を掘削してこれら左右のシ
ールドトンネル8が連通したら、セグメント1のPC鋼
線用定着金具2にPC鋼線5の端部を定着すると共に、
シールドトンネル8の内側に内型枠を形成する。この際
シールドトンネル8間の中央部に緊張ジャッキの配置部
8aも形成する。
Next, when the ground tunnel is excavated and the left and right shield tunnels 8 communicate with each other, the end of the PC steel wire 5 is fixed to the fixing bracket 2 for the PC steel wire of the segment 1, and
An inner mold is formed inside the shield tunnel 8. At this time, an arrangement portion 8a of the tension jack is also formed at the center between the shield tunnels 8.

【0012】そして、この型枠内にコンクリート11を
打設し、該コンクリート11の硬化後にPC鋼線5を前
記配置部8aに配置した緊張ジャッキで緊張して定着体
12に定着することにより、左右のシールドトンネル8
を一体的に接合することができる。
Then, concrete 11 is poured into the formwork, and after the concrete 11 is hardened, the PC steel wire 5 is tensioned by the tension jack arranged in the arrangement portion 8a and is fixed to the fixing body 12. Left and right shield tunnel 8
Can be integrally joined.

【0013】[0013]

【発明の効果】セグメントの裏面にPC鋼線用定着金具
を設けたことにより、PC鋼線の定着作業を容易に行え
ると共に、セグメントをシールドトンネルの一体構造と
して緊張することができる。また、近接したシールドト
ンネルを一体的に接合することができる。
By providing a fixing member for PC steel wire on the back surface of the segment, the fixing operation of the PC steel wire can be easily performed, and the segment can be tightened as an integral structure of the shield tunnel. Also, close shielded
The channels can be integrally joined.

【図面の簡単な説明】[Brief description of the drawings]

【図1】セグメントの背面図である。FIG. 1 is a rear view of a segment.

【図2】(1)及び(2)はPC鋼線用定着金具の拡大
断面図である。
FIGS. 2A and 2B are enlarged cross-sectional views of a fixing bracket for a PC steel wire.

【図3】シールド掘進機の正面図である。FIG. 3 is a front view of the shield machine.

【図4】覆工したシールドトンネルの断面図である。FIG. 4 is a cross-sectional view of the shield tunnel that has been lining.

【図5】従来の接合工法を示すシールドトンネルの断面
図である。
FIG. 5 is a sectional view of a shield tunnel showing a conventional joining method.

【符号の説明】[Explanation of symbols]

1 セグメント 2 PC鋼線用定着金具 3 開口部 4 挿入孔 5 PC鋼線 DESCRIPTION OF SYMBOLS 1 Segment 2 Fixing bracket for PC steel wire 3 Opening 4 Insertion hole 5 PC steel wire

───────────────────────────────────────────────────── フロントページの続き (72)発明者 谷口 徹 東京都中央区京橋1−7−1 戸田建設 株式会社内 (72)発明者 中川 雅弘 東京都中央区京橋1−7−1 戸田建設 株式会社内 (72)発明者 舘川 裕次 東京都中央区京橋1−7−1 戸田建設 株式会社内 (72)発明者 請川 誠 東京都中央区京橋1−7−1 戸田建設 株式会社内 (72)発明者 福若 雅一 東京都千代田区内幸町2丁目2番3号 川崎製鉄株式会社 東京本社内 (72)発明者 平本 高志 東京都千代田区内幸町2丁目2番3号 川崎製鉄株式会社 東京本社内 (72)発明者 小林 秀幸 東京都千代田区内幸町2丁目2番3号 川崎製鉄株式会社 東京本社内 (72)発明者 橋本 修身 東京都千代田区内幸町2丁目2番3号 川崎製鉄株式会社 東京本社内 (56)参考文献 特開 平4−1400(JP,A) 特開 平3−212599(JP,A) (58)調査した分野(Int.Cl.6,DB名) E21D 11/14 E21D 9/06 301 E21D 11/04 ────────────────────────────────────────────────── ─── Continued on the front page (72) Inventor Toru Taniguchi 1-7-1 Kyobashi, Chuo-ku, Tokyo Toda Construction Co., Ltd. (72) Inventor Masahiro Nakagawa 1-7-1 Kyobashi, Chuo-ku, Tokyo Toda Construction Co., Ltd. (72) Inventor Yuji Tategawa 1-7-1 Kyobashi, Chuo-ku, Tokyo Toda Construction Co., Ltd. (72) Inventor Makoto Enkawa 1-7-1 Kyobashi, Chuo-ku, Tokyo Toda Construction Co., Ltd. (72) Inventor Masakazu Fukuwaka 2-3-2 Uchisaiwaicho, Chiyoda-ku, Tokyo Kawasaki Steel Corporation Tokyo headquarters (72) Inventor Takashi Hiramoto 2-3-2 Uchisaiwaicho, Chiyoda-ku Tokyo Tokyo headquarters (72) Inventor Hideyuki Kobayashi 2-3-2 Uchisaiwai-cho, Chiyoda-ku, Tokyo Kawasaki Steel Corporation Tokyo Main Office (72) Inventor Osamu Hashimoto 2-Uchisaiwai-cho, Chiyoda-ku, Tokyo No.2-3 Kawasaki Steel Corporation Tokyo Head Office (56) References JP-A-4-1400 (JP, A) JP-A-3-212599 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E21D 11/14 E21D 9/06 301 E21D 11/04

Claims (5)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 並列かつ近接して構築されたシールドト
ンネルをPC鋼線によって一体的に接合するためのセグ
メントであって、セグメント本体の裏面に内側に突出し
たPC鋼線用定着金具を設け、該PC鋼線用定着金具の
両側に開口部が形成されるとともに、PC鋼線用定着金
具の上面には前記PC鋼線の挿入孔が設けられたことを
特徴とするトンネル接合用セグメント。
1. A shield constructed in parallel and close proximity
Seg for integrally connecting channels with PC steel wire
And projecting inward from the back of the segment body
The fixing bracket for PC steel wire is provided, and the fixing bracket for PC steel wire is provided.
Openings are formed on both sides, and fixing metal for PC steel wire
That the PC steel wire insertion hole was provided on the upper surface of the tool
Characteristic segment for tunnel junction.
【請求項2】 請求項1において、前記PC鋼線用定着2. The fixing device for a PC steel wire according to claim 1, wherein
金具は、前記PC鋼線の定着部を前記挿入孔に挿入してThe metal fitting is formed by inserting the fixing portion of the PC steel wire into the insertion hole.
ナットで止めることにより、前記PC鋼線を定着したこFixing the PC steel wire by fixing with nut
とを特徴とするトンネル接合用セグメント。And a segment for a tunnel junction.
【請求項3】 請求項1において、前記PC鋼線用定着3. The fixing device for a PC steel wire according to claim 1, wherein
金具は、前記PC鋼線の定着部を前記挿入孔に挿入してThe metal fitting is formed by inserting the fixing portion of the PC steel wire into the insertion hole.
くさびで嵌合することにより、前記PC鋼線を定着したThe PC steel wire was fixed by fitting with a wedge
ことを特徴とするトンネル接合用セグメント。A segment for a tunnel junction, characterized in that:
【請求項4】 並列かつ近接して構築された断面矩形の4. A rectangular cross section constructed in parallel and close to
シールドトンネル間の地山の掘削と、これらのシールドExcavation of ground between shield tunnels and these shields
トンネルに覆工された鋼製セグメントの内側に打設されPoured inside a steel segment lining a tunnel
たコンクリートとにより前記シールドトンネル同士が連The shield tunnels are linked by
通され、前記コンクリート中に埋設され、かつ一端が両And buried in the concrete, one end of which
側のシールドトンネルのセグメントに定着されたPC鋼PC steel anchored in the side shield tunnel segment
線が、シールドトンネル間の中央部における定着体に緊The wire is tight against the anchor in the center between the shield tunnels.
張定着されことを特徴とするトンネル接合構造。Tunnel junction structure characterized by being stretched and fixed.
【請求項5】 適宜間隔をもって削孔した立坑間に並列
かつ近接した断面矩形のシールドトンネルを構築する工
程と、これらシールドトンネルの長辺方向に位置した対
向壁のセグメントの解体と、地山の開放掘削とを行って
シールドトンネル同士を連通させる工程と、前記両側の
シールドトンネルのセグメントにPC鋼線の一端部を定
着する工程と、前記シールドトンネルの内側にコンクリ
ートを打設してその中に前記PC鋼線を埋設する工程
と、該コンクリートの硬化後に前記シールドトンネル間
の中央部における定着体に前記PC鋼線の他端部を緊張
定着する工程とからなることを特徴とする トンネル接続
方法。
5. Parallel between shafts drilled at appropriate intervals
To construct a shield tunnel with a rectangular cross section
And the pair located in the long side direction of these shield tunnels
Dismantling the facing wall segment and excavating the ground
Communicating the shield tunnels with each other;
Fix one end of PC steel wire to segment of shield tunnel
And a concrete step inside the shield tunnel.
A step of casting a sheet and embedding the PC steel wire therein.
And after the concrete has hardened, between the shield tunnels
Tension the other end of the PC steel wire to the fixing body at the center of the
Fixing the tunnel.
JP5052287A 1993-03-12 1993-03-12 Tunnel junction segment, tunnel junction structure and tunnel connection method Expired - Lifetime JP2989413B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5052287A JP2989413B2 (en) 1993-03-12 1993-03-12 Tunnel junction segment, tunnel junction structure and tunnel connection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5052287A JP2989413B2 (en) 1993-03-12 1993-03-12 Tunnel junction segment, tunnel junction structure and tunnel connection method

Publications (2)

Publication Number Publication Date
JPH06264696A JPH06264696A (en) 1994-09-20
JP2989413B2 true JP2989413B2 (en) 1999-12-13

Family

ID=12910590

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5052287A Expired - Lifetime JP2989413B2 (en) 1993-03-12 1993-03-12 Tunnel junction segment, tunnel junction structure and tunnel connection method

Country Status (1)

Country Link
JP (1) JP2989413B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3979591B2 (en) * 2002-09-06 2007-09-19 日本水産株式会社 Combined feed and method for producing the same

Also Published As

Publication number Publication date
JPH06264696A (en) 1994-09-20

Similar Documents

Publication Publication Date Title
JP3705903B2 (en) Earth anchor combined earth retaining structure
JP2989413B2 (en) Tunnel junction segment, tunnel junction structure and tunnel connection method
JPH09217594A (en) Timbering method for tunnel
JP3628411B2 (en) segment
JP4958044B2 (en) Installation structure and installation method for shield tunnel approach
JPS62182398A (en) Shielded tunnel
JP2593356B2 (en) Tunnel construction method
JPH086873Y2 (en) Joint structure of hexagonal segment
JP2989412B2 (en) Tunnel junction segment and tunnel connection method
JP2670486B2 (en) Structure of tubular wall for digging hole lining
JPS63134784A (en) Method of tunnel expansion shield construction
JP3233859B2 (en) Tunnel connection method
JP2002061170A (en) Underground outer wall of structure and its construction method
JP2891915B2 (en) Tunnel connection method and tunnel connection segment
JP2954781B2 (en) Segment joint structure
JP2698317B2 (en) Tunnel connection method and tunnel connection segment
JP2581933B2 (en) Duct extension and its construction method
JP2839439B2 (en) Tunnel connection method and tunnel connection segment
JP3027276B2 (en) Tunnel connection segment and tunnel connection method
JP2618180B2 (en) Shield method
JP2935941B2 (en) segment
JP2781839B2 (en) Tubular wall for excavation hole lining
JP2544999B2 (en) Shield method
JP2000110478A (en) Forepiling construction method using curved cable bolt
JP2777540B2 (en) Tunnel connection method and tunnel connection segment