JP2987798B2 - Underground drilling method and apparatus - Google Patents

Underground drilling method and apparatus

Info

Publication number
JP2987798B2
JP2987798B2 JP7250271A JP25027195A JP2987798B2 JP 2987798 B2 JP2987798 B2 JP 2987798B2 JP 7250271 A JP7250271 A JP 7250271A JP 25027195 A JP25027195 A JP 25027195A JP 2987798 B2 JP2987798 B2 JP 2987798B2
Authority
JP
Japan
Prior art keywords
tip
water
pipe
guide
guide hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP7250271A
Other languages
Japanese (ja)
Other versions
JPH0988467A (en
Inventor
紀喜 櫻田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SAKURADA SEISAKUSHO JUGEN
Original Assignee
SAKURADA SEISAKUSHO JUGEN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SAKURADA SEISAKUSHO JUGEN filed Critical SAKURADA SEISAKUSHO JUGEN
Priority to JP7250271A priority Critical patent/JP2987798B2/en
Publication of JPH0988467A publication Critical patent/JPH0988467A/en
Application granted granted Critical
Publication of JP2987798B2 publication Critical patent/JP2987798B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は下水管等の地中配管
を埋設するための地中穿孔方法および装置に関するもの
である。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an underground drilling method and apparatus for burying an underground pipe such as a sewer pipe.

【0002】[0002]

【従来の技術】下水本管から各家庭の下水溜等に至る下
水枝管のような地中配管を埋設するために、地面を堀返
して埋設する方法が行われているが、この方法では埋設
に際して交通の妨げになるほか、埋め戻し後の路面を車
両が通行すると、敷設した配管が沈下するおそれがあ
る。
2. Description of the Related Art In order to bury an underground pipe such as a sewage branch pipe from a sewage main pipe to a sewage reservoir in each household, a method of burrowing the ground to bury the ground is used. In addition to hindering traffic when burying, when vehicles pass on the road surface after backfilling, the laid pipes may sink.

【0003】掘削機を用いて地中に穿孔し、配管を挿入
する方法もあるが、通常の掘削機では地中に存在する石
等の障害物により直線状に穿孔することは困難であり、
配管の挿入が困難になるほか、掘削のスピードも低く、
効率よく穿孔を行うことができない。
[0003] There is also a method of drilling into the ground using an excavator and inserting pipes. However, it is difficult for a normal excavator to drill in a straight line due to obstacles such as stones existing in the ground.
In addition to the difficulty of inserting pipes, the drilling speed is low,
Drilling cannot be performed efficiently.

【0004】[0004]

【発明が解決しようとする課題】本発明の目的は、簡単
な操作により、直線状の孔を効率よく、高スピードで穿
孔することができ、配管の挿入も容易な地中穿孔方法を
提案することである。本発明の他の目的は、簡単な構造
および操作により直線状の孔を効率よく、高スピードで
穿孔することが可能な地中穿孔装置を提案することであ
る。
SUMMARY OF THE INVENTION An object of the present invention is to propose a method of drilling underground in which a straight hole can be efficiently drilled at a high speed by a simple operation, and the pipe can be easily inserted. That is. Another object of the present invention is to propose an underground drilling device capable of efficiently drilling a straight hole at a high speed with a simple structure and operation.

【0005】[0005]

【発明が解決しようとする課題】(1)先端および周辺
部に掘削刃および水噴出口を有する先端部材が先端に取
付られた管部材を回転させるとともに、水噴出口から水
を噴出させながら前進させ、新たな管部材を接続して上
記操作を繰返し、ガイド孔を穿孔する工程と、ガイド孔
から前記管部材を引抜く工程と、ガイド部材の後側に水
噴出口および掘削刃を有するカッタが先端に取付けられ
た管部材を、ガイド部材を前記ガイド孔に挿入した状態
で回転させるとともに、水噴出口から水を噴出させなが
ら前進させ、前記ガイド孔より大きい径の本孔を穿孔す
る工程とを含むことを特徴とする地中穿孔方法。 (2) 先端部において先端部材を接合し、後端部にお
いて他の管部材を接合可能な管部材と、先端および周辺
部に掘削刃および水噴出口を有し、前記管部材の先端に
取付けられるガイド孔穿孔用の先端部材と、ガイド孔に
挿入可能なガイド部材の後部に水噴出口および掘削刃を
有し、前記管部材の先端に取付けられる本孔穿孔用のカ
ッターと、前記管部材を回転させる回転装置と、前記管
部材の回転状態で内部に給水する給水装置と、前記回転
装置を前進または後退させる前進後退装置とを含む上記
(1)記載の地中穿孔方法用地中穿孔装置。
(1) A tip member having a digging blade and a water spout at the tip and the periphery rotates a pipe member attached to the tip and advances while spouting water from the water spout. And connect a new pipe member
Repeating the above operation to form a guide hole,
A step of pulling out the pipe member from, and rotating a pipe member having a cutter having a water ejection port and an excavating blade attached to the tip of the guide member on the rear side, with the guide member inserted into the guide hole, Drilling a main hole having a diameter larger than that of the guide hole by ejecting water from a water outlet and moving forward. (2) joining the distal end member at the distal end has a tubular member capable joining other tubular member at a rear end, a digging edge and water spout the tip and the peripheral portion, attached to the tip of the tube member A tip member for drilling a guide hole, a water jet port and a drilling blade at the rear of the guide member insertable into the guide hole, and a cutter for drilling a main hole attached to the tip of the pipe member; above, including a rotary device for rotating and a water supply device for supplying water to the inside rotation state of the tube member, and a forward and backward device for advancing or retracting the rotary device
(1) underground drilling method for underground drilling apparatus according.

【0006】本発明における穿孔は下水本管から各家庭
等に伸びる下水枝管等の地中配管を埋設するための穿孔
として適しているが、他の目的の穿孔にも適用できる。
孔の方向は水平方向のほか、傾斜方向その他の任意の方
向とすることができる。孔径は制限はないが、25〜4
00mm、好ましくは50〜300mm程度の穿孔に適
している。
[0006] The perforation in the present invention is suitable as a perforation for burying an underground pipe such as a sewage branch pipe extending from a sewage main pipe to each home or the like, but can also be applied to perforations for other purposes.
The direction of the hole may be a horizontal direction, an inclined direction, or any other direction. The pore size is not limited, but 25 to 4
It is suitable for perforation of about 00 mm, preferably about 50 to 300 mm.

【0007】本発明において穿孔に使用する管部材とし
ては、外径19〜60mm、好ましくは29〜50mm
のものが適しており、一端部にオネジ、他端部にメネジ
を有し、軸方向に接合可能な剛性を有するものが使用で
きる。
In the present invention, the pipe member used for perforation has an outer diameter of 19 to 60 mm, preferably 29 to 50 mm.
Are suitable. A male screw having an external thread at one end and a female thread at the other end and having rigidity capable of being joined in the axial direction can be used.

【0008】ガイド孔穿孔用の先端部材は、管部材の先
端にねじ付けられるように、メネジを有する先細の砲弾
状のものが好ましく、その先端および周辺部にガイド孔
穿孔用の掘削刃を有し、掘削刃の回転前方に水噴出孔を
有するものが好ましい。ガイド孔の孔径は20〜70m
m、好ましくは30〜60mm程度が好適であり、その
穿孔が可能なように先端部材およびそれに形成する掘削
刃の寸法を定める。
The tip member for drilling the guide hole is preferably a tapered shell having a female thread so that it can be screwed to the tip of the pipe member, and has a drilling blade for drilling the guide hole at the tip and the periphery. And what has a water ejection hole in front of rotation of a drilling blade is preferable. Guide hole diameter is 20-70m
m, preferably about 30 to 60 mm, and the dimensions of the tip member and the excavation blade formed therein are determined so that the hole can be drilled.

【0009】本孔穿孔用のカッタは、ガイド孔に挿入さ
れるガイド部材の後側に水噴出孔および掘削刃を有する
もので、ガイド孔より大きい本孔を掘削できるように構
成される。ガイド部材としてはガイド孔に挿入可能なロ
ッド状部材が好ましく、掘削刃および水噴出口を有しな
い先端部材を管部材に取付けたものが使用できる。ガイ
ド部材の後側に設ける掘削刃は環状体に刃を取付けたも
のが好ましい。
The main hole drilling cutter has a water ejection hole and an excavation blade on the rear side of a guide member inserted into the guide hole, and is configured to excavate a main hole larger than the guide hole. As the guide member, a rod-shaped member that can be inserted into the guide hole is preferable, and a member in which a tip member having no excavating blade and a water jet port is attached to a pipe member can be used. The digging blade provided on the rear side of the guide member preferably has a blade attached to an annular body.

【0010】上記の掘削刃としてはダイヤチタニットの
ような切削材料を使用する。回転装置としてはモータが
使用でき、給水装置としては水封式ジャケット状のもの
が使用できる。また前進後退装置としては、管部材を取
付けた回転装置をレール上で走行させるものが使用でき
る。
A cutting material such as diamond titanite is used as the excavating blade. A motor can be used as the rotating device, and a water-sealed jacket-like device can be used as the water supply device. Further, as the forward / backward device, a device in which a rotating device provided with a pipe member travels on a rail can be used.

【0011】本発明の穿孔装置による地中穿孔方法は、
ガイド孔穿孔用の先端部材を先端に取付けた管部材を回
転装置に装着して回転させ、給水装置から管部材内部に
給水して水噴出口から噴出させながら、前進後退装置に
より、回転装置を前進させることにより、掘削を行う。
回転装置は前進位置で管部材を外して後退させ、新たに
管部材を接続して上記操作を繰返し、ガイド孔を穿孔す
る。
An underground drilling method using a drilling device according to the present invention comprises:
The pipe member with the tip member for guide hole drilling attached to the tip is attached to the rotating device and rotated, and while the water is supplied from the water supply device to the inside of the tube member and is ejected from the water outlet, the rotating device is moved by the forward / backward retracting device. Excavation is performed by moving forward.
The rotating device removes and retracts the tube member at the forward position, connects a new tube member, and repeats the above operation to perforate the guide hole.

【0012】その後管部材および先端部材を引抜き、カ
ッタに取付けられるガイド部材をガイド孔に挿入した状
態で、カッタを接続した管部材を回転装置に装着して回
転させ、給水装置から管部材内部に給水して水噴出孔か
ら噴出させながら、前進後退装置により回転装置を前進
させることにより掘削を行う。回転装置は前進位置で管
部材を外して後退させ、新たに管部材を接続して上記操
作を繰返し、本孔を穿孔する。
Thereafter, the pipe member and the distal end member are pulled out, and the guide member attached to the cutter is inserted into the guide hole, and the pipe member connected to the cutter is mounted on the rotating device and rotated, so that the pipe member is inserted from the water supply device into the pipe member. Excavation is performed by advancing a rotating device by an advancing and retreating device while supplying water and ejecting it from a water ejection hole. The rotating device removes and retracts the pipe member at the forward position, newly connects the pipe member, and repeats the above operation to drill a main hole.

【0013】上記のガイド孔穿孔では、水を噴出しなが
ら掘削刃により管部材より1〜10mm大きい径のガイ
ド孔を穿孔するので、直線状のガイド孔を形成すること
ができる。そしてガイド孔形成後にカッタのガイド部材
をガイド孔に挿入してガイドさせながら、水を噴出させ
て本孔を掘削することにより、ガイド孔に沿って直線状
の本孔を形成することができる。
In the above-described guide hole drilling, since a guide hole having a diameter larger by 1 to 10 mm than the pipe member is drilled by the excavating blade while water is jetted out, a linear guide hole can be formed. Then, while the guide member of the cutter is inserted into and guided by the guide hole after the formation of the guide hole, the main hole can be formed linearly along the guide hole by ejecting water and excavating the main hole.

【0014】本孔形成後は、配管を埋設する場合は管を
接合しながら挿入すると、本孔は直線状にかつきれいな
掘削面で形成されているので、管は容易に挿入され配管
の埋設が行われる。
After the main hole is formed, when the pipe is buried, if the pipe is inserted while being joined, the main hole is formed in a straight and clean excavation surface, so that the pipe is easily inserted and the pipe is buried. Done.

【0015】[0015]

【発明の実施の形態】以下、本発明の実施の形態を図面
により説明する。図1(a)はガイド孔穿孔用の先端部
材と管部材の組合せを示す分解斜視図、(b)はガイド
部材とカッタの組合せを示す分解斜視図、図2(a)は
図1(b)のA−A矢視図、(b)は管の斜視図、図3
は穿孔装置を示す垂直断面図で図4のB−B断面を示
し、図4は図3の架台の平面図である。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1A is an exploded perspective view showing a combination of a tip member for drilling a guide hole and a tube member, FIG. 1B is an exploded perspective view showing a combination of a guide member and a cutter, and FIG. ) In the direction of arrows AA, (b) is a perspective view of the tube, FIG.
4 is a vertical sectional view showing the punching device, and shows a BB section of FIG. 4, and FIG. 4 is a plan view of the gantry of FIG.

【0016】図中、1は管部材で、鋼管の一端部にオネ
ジ1aが形成され、他端部に形成された大径部1bには
メネジ1cが形成されており、複数を端部で接合して軸
方向に長尺化できるように構成されている。
In the figure, reference numeral 1 denotes a pipe member, in which a male screw 1a is formed at one end of a steel pipe, and a female screw 1c is formed at a large diameter portion 1b formed at the other end. And it can be made longer in the axial direction.

【0017】2はガイド孔穿孔用の先端部材であって、
オネジ1aに係合するメネジ2aを有し、先細の砲弾状
に形成されている。その先端部に1個、側部の周辺部に
2個の掘削刃2bを有し、周辺部の掘削刃2bの回転前
方には水噴出口2cを有する。
2 is a tip member for drilling a guide hole,
It has a female screw 2a that engages with the male screw 1a, and is formed in a tapered shell shape. It has one excavating blade 2b at its tip and two peripherals at the side, and has a water jet 2c in front of the rotation of the peripheral excavating blade 2b.

【0018】3はガイド部材で、管部材1の先端にガイ
ド用先端部材4がねじ付けられた構造となっている。先
端部材4は掘削刃2bおよび水噴出口2cがない先端部
材2とほぼ同形状の先細砲弾状に形成され、基部にオネ
ジ1aにねじ付けられるメネジ4aが形成されている。
Reference numeral 3 denotes a guide member having a structure in which a guide tip member 4 is screwed to the tip of the tube member 1. The tip member 4 is formed in the shape of a tapered cannonball having substantially the same shape as the tip member 2 without the excavating blade 2b and the water jet port 2c, and a female screw 4a to be screwed to the male screw 1a is formed at the base.

【0019】カッタ5はガイド部材3の後部に取付られ
るるようにそのメネジ部1cにねじ付けられるオネジ部
5aを一端部に有し、管部材1のオネジ部1aがねじ付
けられるメネジ部5bを他端部に有する。そしてオネジ
部5a側から水噴出口5cおよび掘削部材6を有する。
掘削部材6はパイプを輪切りにした形状の環状体6a
が、軸5dから伸びる支持体6b、6cによって固着さ
れている。環状体6aおよび支持体6bの前部には、掘
削刃6dが回転により土砂を削り取り、かつ中心(回転
軸)側に集めるように、傾斜して取付けられている。
The cutter 5 has, at one end, a male thread portion 5a screwed to the female thread portion 1c so as to be attached to the rear portion of the guide member 3, and has a female thread portion 5b to which the male thread portion 1a of the pipe member 1 is screwed. At the other end. The water outlet 5c and the excavation member 6 are provided from the male screw portion 5a side.
The excavation member 6 is an annular body 6a having a shape obtained by cutting a pipe into rings.
Are fixed by supports 6b and 6c extending from the shaft 5d. An excavating blade 6d is attached to the front of the annular body 6a and the support 6b at an angle so as to scrape the earth and sand by rotation and collect the earth and sand toward the center (rotation axis).

【0020】10は掘削装置を示し、回転装置としての
モータ11が架台12に設けられたレール13上を走行
して前進後退するようになっている。モータ11のケー
シング14には水封ジャケット式の給水装置15が固着
され、給水管16が接続している。モータ11の回転軸
に直結するレジューサ17の中空管17aが給水装置1
5に、回転可能かつ給水可能に取付けられている。レジ
ューサ17の先端部にはオネジ部17bが形成され、管
部材1のメネジ部1cにねじ付けられるようになってい
る。16aは弁である。
Reference numeral 10 denotes an excavator, in which a motor 11 as a rotating device travels on a rail 13 provided on a gantry 12 and moves forward and backward. A water seal jacket type water supply device 15 is fixed to a casing 14 of the motor 11, and a water supply pipe 16 is connected thereto. The hollow pipe 17a of the reducer 17 directly connected to the rotating shaft of the motor 11
5 is rotatably and water-supplied. A male screw portion 17b is formed at the tip of the reducer 17, and is screwed to the female screw portion 1c of the tube member 1. 16a is a valve.

【0021】モータ11はレール13上を摺動する摺動
台18に支持されている。摺動台18にはピニオン19
が取付けられて、レール13上に設けられたラック20
にかみ合っており、ハンドル21の回転により回転して
摺動台18を前進後退させるようになっている。架台1
2の前方にはガイド支柱22が設けられており、管部材
1の通過を許容するガイド口23が形成されている。ま
た架台12の下部の四隅には取付孔24が形成され、固
定ピン25により基盤26に固定されるようになってい
る。
The motor 11 is supported on a slide 18 that slides on the rail 13. A pinion 19 is provided on the slide 18.
Is mounted on the rack 20 provided on the rail 13.
The slide 21 is rotated by the rotation of the handle 21 to move the slide table 18 forward and backward. Stand 1
A guide column 22 is provided in front of 2, and a guide port 23 that allows passage of the pipe member 1 is formed. In addition, mounting holes 24 are formed at the four lower corners of the gantry 12, and are fixed to a base 26 by fixing pins 25.

【0022】上記の装置による地中穿孔方法は、図1
(a)に示すガイド孔穿孔用の先端部材2を管部材1の
先端にねじ付け、これを図3に示すように掘削装置10
のレジューサ17の先端にねじ付けて装着する。このと
きモータ11を後退位置において回転させ、給水管16
から給水すると、水は給水装置15からレジューサ17
および管部材1の内部を通って水噴出口2cから噴出
し、管部材1および先端部材2は回転する。
The underground drilling method using the above-described apparatus is shown in FIG.
A tip member 2 for drilling a guide hole shown in (a) is screwed to the tip of the pipe member 1, and this is connected to the excavator 10 as shown in FIG.
And attached to the tip of the reducer 17. At this time, the motor 11 is rotated at the retracted position,
When water is supplied from the water supply device, the water is supplied from the water supply device 15 to the reducer 17.
Then, the water is spouted from the water jet port 2c through the inside of the pipe member 1, and the pipe member 1 and the tip member 2 rotate.

【0023】この状態でハンドル21を回転させて摺動
台18を前進させると、掘削刃2bの回転により土砂が
削り取られ、これが噴出する水によって流動化して手前
に流される。このため小さい抵抗で先端部材2が前進
し、直線状のガイド孔が掘削される。
When the slide 21 is advanced by rotating the handle 21 in this state, the earth and sand is scraped off by the rotation of the excavating blade 2b, which is fluidized by the jetted water and is washed away. Therefore, the tip member 2 moves forward with a small resistance, and a linear guide hole is excavated.

【0024】モータ11が前進を終った位置で、管部材
1をそのままにしてレジューサ17を外し、モータ11
を後退させる。そして別の管部材1をレジューサ17に
接続するとともに、前進位置の管部材1にも接続する。
この状態で前記と同様にして前進させて掘削を行い、こ
れを繰返す。
At the position where the motor 11 has moved forward, the reducer 17 is removed while the pipe member 1 is left as it is, and the motor 11
Retreat. Then, another tube member 1 is connected to the reducer 17 and also to the tube member 1 in the advanced position.
In this state, excavation is performed by moving forward in the same manner as described above, and this is repeated.

【0025】先端部材2が目的地に達してガイド孔が貫
通した段階で、給水を停止してモータ11を後退させ
て、最後端の管部材1を外す。その状態でモータ11を
前進させて、残っている管部材1にレジューサ17をね
じ付け、モータを後退させて管部材1を外す操作を繰返
す。
At the stage where the tip member 2 reaches the destination and the guide hole penetrates, the water supply is stopped, the motor 11 is retracted, and the rearmost tube member 1 is removed. In this state, the motor 11 is advanced, the reducer 17 is screwed to the remaining tube member 1, and the operation of retracting the motor and removing the tube member 1 is repeated.

【0026】このようにして管部材1を引抜く操作を行
い、最後の管部材1を後退させた段階で、先端部材2お
よび管部材1をレジューサ17から外す。そしてこれに
代って図1(b)に示す先端部材4を管部材1の先端に
ねじ付けて一体化したガイド部材3を、カッタ5の先端
にねじ付けて接続し、カッタ5のメネジ部5bにレジュ
ーサ17のオネジ部17bをねじ付けて装着する。
In this manner, the operation of pulling out the tube member 1 is performed, and when the last tube member 1 is retracted, the distal end member 2 and the tube member 1 are removed from the reducer 17. Then, instead of this, the guide member 3 in which the tip member 4 shown in FIG. 1B is screwed to the tip of the tube member 1 and integrated with the tip of the cutter 5 by screwing, is connected. The male thread portion 17b of the reducer 17 is screwed and mounted on 5b.

【0027】この状態でハンドル21を回転させてモー
タ11を前進させると、先端部材4と管部材1が一体化
したガイド部材3は、すでに穿孔されたガイド孔に挿入
される。モータの前進位置で、レジューサ17をカッタ
5から外して後退させる。そして別の管部材1をカッタ
5およびレジューサ17間にねじ付けて接続し、モータ
11を回転させるとともに給水装置15から給水して前
進させる。
When the motor 21 is advanced by rotating the handle 21 in this state, the guide member 3 in which the distal end member 4 and the tube member 1 are integrated is inserted into the guide hole that has already been drilled. At the forward position of the motor, the reducer 17 is removed from the cutter 5 and retracted. Then, another pipe member 1 is screwed and connected between the cutter 5 and the reducer 17, and the motor 11 is rotated and water is supplied from the water supply device 15 to move forward.

【0028】これによりガイド部材3にガイドされて、
水噴出口5cがガイド孔内で回転しながら水を噴出し、
これと同時に掘削部材6が回転することにより、掘削刃
6dが土砂を削り取る。削り取られた土砂は水により流
動化して手前に流れる。このときガイド部材3がすでに
形成された直線状のガイド孔に沿って進むので、カッタ
5はガイド孔の周囲の土砂を一定の範囲で削り取り、直
線状の本孔が形成される。
As a result, it is guided by the guide member 3,
The water spout 5c spouts water while rotating in the guide hole,
At the same time, when the excavating member 6 rotates, the excavating blade 6d scrapes the earth and sand. The shaved sand is fluidized by water and flows toward the front. At this time, since the guide member 3 advances along the already formed linear guide hole, the cutter 5 scrapes the earth and sand around the guide hole in a certain range to form a linear main hole.

【0029】モータ11の前進位置でレジューサ17を
管部材1から外し、モータ11を後退させ、新しい管部
材1を接続して前進させ、これを繰返すことにより、本
孔が貫通する。本孔貫通後は、前記ガイド孔の場合と同
様にして管部材1を引抜き、最終的にカッタ5およびガ
イド部材3も引抜き、穿孔が完了する。
At the forward position of the motor 11, the reducer 17 is detached from the tube member 1, the motor 11 is retracted, a new tube member 1 is connected and moved forward, and the main hole is penetrated by repeating this. After penetrating the main hole, the pipe member 1 is pulled out in the same manner as in the case of the guide hole, and finally the cutter 5 and the guide member 3 are also pulled out, and the perforation is completed.

【0030】本孔に管を埋設する場合は、上記により形
成された本孔に管を挿入して埋設する。図2(b)にお
いて、7はポリ塩化ビニル製の管であり、その一端部7
aから本孔に挿入し、他端に形成された拡大径部7bの
内面7cに接着剤を塗布して他の管7の一端部7aを挿
入して接合しながら挿入することにより、管の埋設は完
了する。
When a pipe is buried in the main hole, the pipe is inserted into the main hole formed as described above and buried. In FIG. 2 (b), reference numeral 7 denotes a tube made of polyvinyl chloride, and one end portion 7 thereof.
a into the main hole, apply an adhesive to the inner surface 7c of the enlarged diameter portion 7b formed at the other end, insert the one end 7a of the other tube 7 and insert it while joining, so that the tube is inserted. Burial is completed.

【0031】この場合本孔は直線状に形成されるため、
本孔と拡大径部7bの径がほぼ一致する管7を容易に挿
入することができる。その場合、地層との間隙が小さい
ので、間隙に土砂の埋戻しを要することなく、埋設が完
了する。この場合の埋設管は、地層との間隙が小さいた
め埋設後の沈下は少ない。
In this case, since the main hole is formed in a straight line,
The tube 7 whose main hole and the enlarged diameter portion 7b have substantially the same diameter can be easily inserted. In this case, since the gap with the stratum is small, the embedding is completed without requiring backfill of earth and sand in the gap. In this case, the buried pipe has little settlement after burial because the gap with the stratum is small.

【0032】上記の操作において、ガイド孔と本孔の径
が大幅に相違するときは、中間径のカッタ5を用いるこ
とにより、中間径のガイド孔を穿孔することもできる。
また管部材1、先端部材2、4、ガイド部材3、カッタ
5等の構造は図示のものに限定されず、変更可能であ
る。
In the above operation, when the diameter of the guide hole is largely different from that of the main hole, an intermediate diameter guide hole can be formed by using the intermediate diameter cutter 5.
Further, the structures of the tube member 1, the tip members 2, 4, the guide member 3, the cutter 5, and the like are not limited to those shown in the drawings, and can be changed.

【0033】上記の説明は水平方向に穿孔する場合のも
のであるが、基盤26または架台12を傾斜させること
により、傾斜方向の穿孔が可能である。また上記の説明
は管を埋設する例について行ったが、他の目的の穿孔に
も適用できる。
Although the above description is for the case of drilling in the horizontal direction, by drilling the base 26 or the gantry 12, drilling in the inclined direction is possible. Although the above description has been made with respect to an example in which a pipe is buried, the present invention can be applied to perforation for other purposes.

【0034】[0034]

【発明の効果】本発明の地中穿孔方法は、掘削刃と水噴
出孔を有する先端部材を取付けた管部材を回転させなが
ら前進させてガイド孔を穿孔したのち、ガイド部材によ
ってガイドされるカッタにより水を噴出させながら掘削
するようにしたので、掘削の抵抗を小さくして直線状の
ガイド孔を形成でき、これに沿って小さい抵抗で一定範
囲の土砂を削り取って直線状の本孔を形成することがで
き、簡単な操作で効率よく、高スピードで穿孔すること
ができる。
According to the underground drilling method of the present invention, a cutter provided with a drilling blade and a tip member having a water ejection hole is advanced while rotating while rotating a pipe member, and then a cutter guided by the guide member. Excavation while jetting water, so that the resistance of excavation can be reduced and a linear guide hole can be formed, and a small range of soil is removed with a small resistance to form a straight main hole The drilling can be performed efficiently with a simple operation at a high speed.

【0035】本発明の地中穿孔装置は、先端部材を取付
けた管部材、またはガイド部材とカッタを取付けた管部
材をモータに装着して前進、後退可能としたため、簡単
な構造および操作により直線状の孔を効率よく、高スピ
ードで穿孔することが可能である。
In the underground drilling device of the present invention, the pipe member provided with the tip member or the tube member provided with the guide member and the cutter is mounted on the motor so as to be able to move forward and backward. Hole can be efficiently drilled at high speed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】(a)はガイド孔用先端部材と管部材の組合せ
を示す分解斜視図、(b)はガイド部材とカッタの組合
せを示す分解斜視図である。
FIG. 1A is an exploded perspective view showing a combination of a guide hole tip member and a pipe member, and FIG. 1B is an exploded perspective view showing a combination of a guide member and a cutter.

【図2】(a)は図1(b)のA−A矢視図、(b)は
管の斜視図である。
2 (a) is a view taken in the direction of arrows AA in FIG. 1 (b), and FIG. 2 (b) is a perspective view of a tube.

【図3】穿孔装置の垂直断面図である。FIG. 3 is a vertical sectional view of the punching device.

【図4】図3の架台の平面図である。FIG. 4 is a plan view of the gantry of FIG. 3;

【符号の説明】[Explanation of symbols]

1 管部材 1a、5a、17b オネジ部 1b 大径部 1c、2a、4a、5b メネジ部 2b、6d 掘削刃 2c、5c 水噴出口 2、4 先端部材 3 ガイド部材 5 カッタ 5d 軸 6 掘削部材 6a 環状体 6b、6c 支持体 7 管 10 掘削装置 11 モータ 12 架台 13 レール 14 ケーシング 15 給水装置 16 給水管 16a 弁 17 レジューサ 18 摺動台 19 ピニオン 20 ラック 21 ハンドル 22 ガイド支柱 23 ガイド口 24 取付孔 25 固定ピン 26 基盤 DESCRIPTION OF SYMBOLS 1 Pipe member 1a, 5a, 17b Male thread part 1b Large diameter part 1c, 2a, 4a, 5b Female thread part 2b, 6d Drilling blade 2c, 5c Water jet port 2, 4 Tip member 3 Guide member 5 Cutter 5d Shaft 6 Drilling member 6a Annular body 6b, 6c Support body 7 Pipe 10 Excavator 11 Motor 12 Mount 13 Rail 14 Casing 15 Water supply device 16 Water supply pipe 16a Valve 17 Reducer 18 Slide table 19 Pinion 20 Rack 21 Handle 22 Guide post 23 Guide opening 24 Mounting hole 25 Fixing pin 26 Base

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 先端および周辺部に掘削刃および水噴出
口を有する先端部材が先端に取付られた管部材を回転さ
せるとともに、水噴出口から水を噴出させながら前進さ
せ、新たな管部材を接続して上記操作を繰返し、ガイド
孔を穿孔する工程と、ガイド孔から前記管部材を引抜く工程と、 ガイド部材の後側に水噴出口および掘削刃を有するカッ
タが先端に取付けられた管部材を、ガイド部材を前記ガ
イド孔に挿入した状態で回転させるとともに、水噴出口
から水を噴出させながら前進させ、前記ガイド孔より大
きい径の本孔を穿孔する工程とを含むことを特徴とする
地中穿孔方法。
1. A tip member having an excavation blade and a water jet at a tip and a peripheral portion rotates a pipe member attached to the tip and advances while jetting water from the water jet port to advance a new pipe member. A step of connecting and repeating the above operation to drill a guide hole, a step of pulling out the pipe member from the guide hole, and a pipe having a cutter having a water jet port and a cutting blade at the rear end of the guide member attached to the tip. Rotating the member while the guide member is inserted into the guide hole, moving the member forward while ejecting water from a water outlet, and perforating a main hole having a diameter larger than the guide hole. Underground drilling method.
【請求項2】 先端部において先端部材を接合し、後
部において他の管部材を接合可能な管部材と、 先端および周辺部に掘削刃および水噴出口を有し、前記
管部材の先端に取付けられるガイド孔穿孔用の先端部材
と、 ガイド孔に挿入可能なガイド部材の後部に水噴出口およ
び掘削刃を有し、前記管部材の先端に取付けられる本孔
穿孔用のカッターと、 前記管部材を回転させる回転装置と、 前記管部材の回転状態で内部に給水する給水装置と、 前記回転装置を前進または後退させる前進後退装置とを
含む請求項1記載の地中穿孔方法用地中穿孔装置。
Joining the tip member 2. A distal end portion includes a tubular member capable joining other tubular member at a rear end, a digging edge and water spout the tip and the peripheral portion, the distal end of the tube member A tip member for drilling a guide hole, which is attached to a guide member; a cutter for drilling a main hole, which has a water jet port and a drilling blade at the rear of the guide member that can be inserted into the guide hole, and is attached to the tip of the pipe member; 2. The underground drilling method according to claim 1 , further comprising: a rotation device configured to rotate the pipe member; a water supply device configured to supply water to the inside of the pipe member in a rotating state; and a forward retraction device configured to advance or retreat the rotation device. Perforator.
JP7250271A 1995-09-28 1995-09-28 Underground drilling method and apparatus Expired - Fee Related JP2987798B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7250271A JP2987798B2 (en) 1995-09-28 1995-09-28 Underground drilling method and apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7250271A JP2987798B2 (en) 1995-09-28 1995-09-28 Underground drilling method and apparatus

Publications (2)

Publication Number Publication Date
JPH0988467A JPH0988467A (en) 1997-03-31
JP2987798B2 true JP2987798B2 (en) 1999-12-06

Family

ID=17205421

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7250271A Expired - Fee Related JP2987798B2 (en) 1995-09-28 1995-09-28 Underground drilling method and apparatus

Country Status (1)

Country Link
JP (1) JP2987798B2 (en)

Also Published As

Publication number Publication date
JPH0988467A (en) 1997-03-31

Similar Documents

Publication Publication Date Title
US4993503A (en) Horizontal boring apparatus and method
JP2987798B2 (en) Underground drilling method and apparatus
JP2004285563A (en) Enlarged excavation method, method embedding pile and bit
JP4522909B2 (en) Tubular unit for excavation and ground improvement method using the same
JP2004107880A (en) Drilling method and drilling device
JP2006152745A (en) Rectangular boring machine
JP2000248893A (en) Pipe laying by non-cut and cover method
JP4140938B2 (en) Slant jet method
JP2004232304A (en) One-way tunneling universal pipe-jacking tool, one-way tunneling pipe-jacking method and laying construction method for pipe
JP5153678B2 (en) Method to reduce oil concentration in oil contaminated part
JP2808288B2 (en) Ground drilling equipment
JP4349522B2 (en) Ground improvement method
US7389829B2 (en) Method and apparatus for forming bored hole
JP2005213848A (en) Excavating tool and excavating apparatus
JP2005344450A (en) Build-up device of pipe in ground and ground improving method using the same
JP3865344B2 (en) Diameter expansion jig for propulsion method
JP3790566B2 (en) Excavator used for guide boring method
JPH09119279A (en) Method of propulsive construction of screw auger for excavating gallery
JPH0665958A (en) Method for connecting drain pipe to main pipe of sewerage system
JPS636315Y2 (en)
JP3841675B2 (en) Removal method of installed lead pipe and replacement replacement method
JP5290667B2 (en) Multiple receiving material installation equipment
JPH11190190A (en) Laying construction method for wiping by unopened-cut excavation
JPH05106386A (en) Connecting/burying device for fitting pipe to buried pipe
JPH08218477A (en) Fitting hole boring/core recovering device for fitting pipe to existing pipe

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081008

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091008

Year of fee payment: 10

LAPS Cancellation because of no payment of annual fees