Method of using tundish for continuous casting machine, remodeling method and casting floor equipment

Info

Publication number
JP2856075B2
JP2856075B2 JP16815294A JP16815294A JP2856075B2 JP 2856075 B2 JP2856075 B2 JP 2856075B2 JP 16815294 A JP16815294 A JP 16815294A JP 16815294 A JP16815294 A JP 16815294A JP 2856075 B2 JP2856075 B2 JP 2856075B2
Authority
JP
Japan
Prior art keywords
tundish
casting
hot
continuous casting
maintenance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP16815294A
Other languages
Japanese (ja)
Other versions
JPH0833957A (en
Inventor
正志 河本
敦 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Sumitomo Metal Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Industries Ltd filed Critical Sumitomo Metal Industries Ltd
Priority to JP16815294A priority Critical patent/JP2856075B2/en
Publication of JPH0833957A publication Critical patent/JPH0833957A/en
Application granted granted Critical
Publication of JP2856075B2 publication Critical patent/JP2856075B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Casting Support Devices, Ladles, And Melt Control Thereby (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、取鍋からの溶鋼をタ
ンディッシュを介してモールドに鋳込みスラブやビレッ
ト等を連続的に鋳造する連続鋳造機におけるタンディッ
シュ使用方法,既設の連続鋳造機の改造方法および連続
鋳造機の鋳込床設備に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of using a tundish in a continuous casting machine for continuously casting slabs, billets and the like by casting molten steel from a ladle into a mold via a tundish, and to a method of using an existing continuous casting machine. The present invention relates to a remodeling method and a casting floor facility of a continuous casting machine.

【0002】[0002]

【従来の技術】連続鋳造法においては、図4に示すよう
に、転炉等の製鋼炉で溶製された溶鋼を取鍋1に入れて
連続鋳造機の上方まで輸送し、連続鋳造機上では取鍋1
をレードルターレット2やレードルカーなどで支持し、
取鍋内の溶鋼をタンディッシュ3を介してモールド4内
に注入している。タンディッシュ3は、上部にタンディ
ッシュ注入管5(取鍋とタンディッシュ間の溶鋼流をA
rガスシールするための大径パイプ),下部にスライデ
ィングノズル装置6および浸漬ノズル7を備え、取鍋か
らの溶鋼をいったん貯留し、溶鋼流れを一定に整流し、
注入流量を制御してモールド内に送り込む中間容器であ
り、また同時に複数本の鋳片を製造するマルチストラン
ドでは分配容器の役目も果たしている。
2. Description of the Related Art In a continuous casting method, as shown in FIG. 4, molten steel produced in a steelmaking furnace such as a converter is put into a ladle 1 and transported to a position above the continuous casting machine. Then ladle 1
With a ladle turret 2 or ladle car,
The molten steel in the ladle is poured into the mold 4 via the tundish 3. The tundish 3 has a tundish injection pipe 5 (a molten steel flow between the ladle and the tundish at the top).
a large-diameter pipe for gas sealing), equipped with a sliding nozzle device 6 and a submerged nozzle 7 at the lower part to temporarily store molten steel from a ladle and to rectify the flow of molten steel to a constant level.
It is an intermediate container that controls the injection flow rate and feeds it into the mold, and also serves as a distribution container in a multi-strand that simultaneously manufactures a plurality of slabs.

【0003】このような連続鋳造機において、近年の鋼
に対するユーザーニーズの高級化・多様化に伴う小ロッ
ト生産では、1トライの連続鋳造が終了すると、鋳造に
使用したタンディッシュをタンディッシュ整備ヤードに
運んで必要な整備を行い、この整備の間には、予熱待機
させておいた新しいタンディッシュに交換して次の連続
鋳造を続行している。
[0003] In such a continuous casting machine, in the small-lot production in accordance with the gradual and diversification of user needs for steel in recent years, when the continuous casting of one trial is completed, the tundish used for casting is removed from the tundish maintenance yard. Carrying the necessary maintenance and replacing it with a new tundish that has been kept on standby during this maintenance, the next continuous casting is continued.

【0004】即ち、図3に示すのは、従来の既設の2ス
トランド連続鋳造機における鋳込床設備の概略平面図で
あり、鋳込床10上における連鋳機センターラインCL
に対して左右の2箇所b,cにそれぞれタンディッシュ
予熱装置11−1,11−2を設置し、2台のタンディ
ッシュカー12−1,12−2を鋳込み位置aにおける
モールド上方と前記予熱待機位置b,cとの間を往復走
行可能に配置し、さらに鋳込床10より低い位置のタン
ディッシュ整備ヤードdにタンディッシュ整備設備13
を設置し、次のようにタンディッシュの交換,整備を行
っている(図5参照)。
That is, FIG. 3 is a schematic plan view of a casting floor facility in a conventional existing two-strand continuous casting machine, and shows a continuous casting machine center line CL on a casting floor 10.
Tundish preheating devices 11-1 and 11-2 are installed at two places b and c on the left and right, respectively, and two tundish cars 12-1 and 12-2 are placed above the mold at the casting position a and the preheating. The tundish maintenance equipment 13 is disposed so as to be able to reciprocate between the standby positions b and c, and is located in a tundish maintenance yard d lower than the casting floor 10.
The tundish is exchanged and maintained as follows (see FIG. 5).

【0005】(1) 2台のタンディッシュカー12−1,
12−2上に、事前整備されたタンディッシュ3−1,
3−2を載せ、左右2台のうちの一方のNo.1タンディッ
シュ3−1で連続鋳造を行い、他方のNo.2タンディッシ
ュ3−2をタンディッシュ予熱装置11−2の予熱バー
ナーで予熱し、待機させておく。
(1) Two tundish cars 12-1,
12-2, pre-maintained tundish 3-1
3-2 is mounted, and continuous casting is performed with one No. 1 tundish 3-1 of the two right and left units, and the other No. 2 tundish 3-2 is heated with a preheating burner of a tundish preheating device 11-2. Preheat and wait.

【0006】(2) 1トライの連続鋳造が終了すると、使
用していたNo.1タンディッシュ3−1を予熱待機位置b
に戻し、ここからクレーン14で吊り上げて移動させ、
棟替え台車15でタンディッシュ整備ヤードdまで運搬
し、タンディッシュ整備設備13により、温間または冷
間整備を行う。
(2) When the continuous casting of one trial is completed, the used No. 1 tundish 3-1 is placed in the preheating standby position b.
From here, lifted and moved by crane 14 from here,
It is transported to the tundish maintenance yard d by the rebuilding trolley 15, and the tundish maintenance equipment 13 performs warm or cold maintenance.

【0007】冷間整備作業としては、タンディッシュ3
内の残鋼・残滓の廃棄,浸漬ノズル7の取外し,タンデ
ィッシュ注入管5・タンディッシュ蓋8の取外し,タン
ディシュ3の水冷,タンディッシュ3の地金除去,スラ
イディングノズル装置6のカセットプレート・上ノズル
交換,タンディッシュ3の耐火物吹き付け補修,タンデ
ィッシュ注入管5・タンディッシュ蓋8の取付け,浸漬
ノズル7の取付けなどがある。
The cold maintenance work includes a tundish 3
Disposal of residual steel and residue, removal of immersion nozzle 7, removal of tundish injection pipe 5 and tundish lid 8, water cooling of tundish 3, removal of metal in tundish 3, cassette plate of sliding nozzle device 6 The nozzle replacement, the refractory spraying repair of the tundish 3, the installation of the tundish injection pipe 5 and the tundish lid 8, the installation of the immersion nozzle 7, and the like are included.

【0008】(3) この整備の間に、予熱待機位置cで待
機しているNo.2タンディッシュ3−2をタンディッシュ
カー12−2で鋳込み位置aまで移動させ、次の連続鋳
造を行い、操業を継続する。さらに、予熱待機位置bで
空いてるタンディッシュカー12−1上には、整備ヤー
ドで既に整備が完了したNo.3タンディッシュ3ー3を持
ってきて、次の鋳込みのための予熱を行い、予熱完了後
は待機させておく。
(3) During this maintenance, the No. 2 tundish 3-2 waiting at the preheating standby position c is moved to the casting position a by the tundish car 12-2, and the next continuous casting is performed. Continue the operation. Further, on the tundish car 12-1 vacant at the preheating standby position b, bring the No. 3 tundish 3-3 already completed in the maintenance yard and perform preheating for the next casting, After completion of preheating, it is kept on standby.

【0009】以上のように、5〜6基のタンディッシュ
3を順に使用し、使用後はタンディッシュ整備ヤードd
で温間または冷間整備し、5〜6トライが終了すると
(約20時間)、最初に整備したタンディッシュ3−1
が鋳込みを行うようにしている。
As described above, five to six tundishes 3 are used in order, and after use, the tundish maintenance yard d is used.
After 5 or 6 tries are completed (about 20 hours), the first tundish 3-1
Is trying to cast.

【0010】しかしながら、このような従来のタンディ
ッシュ使用方法では、近年の小ロット生産に対応すべ
く、タンディッシュを1トライ毎に頻繁に交換し、温間
または冷間整備するため、 タンディッシュを多数用
意しなければならない、 整備による耐火物の損耗や
温度変化による耐火物疲労などにより、タンディッシュ
内耐火物の寿命が低下し、耐火物コストもかかる、
タンディッシュの冷却と加熱を繰り返し行うため熱ロス
が増大する、 タンディッシュの整備専用の要員を必
要とするなどの問題点がある。
However, in such a conventional method of using a tundish, the tundish is frequently changed every trial and the tundish is maintained in a warm or cold state in order to cope with recent small lot production. A large number of items must be prepared.The life of refractories in the tundish is reduced due to wear of refractories due to maintenance and refractory fatigue due to temperature changes.
There are problems such as increased heat loss due to repeated cooling and heating of the tundish, and the need for dedicated staff for tundish maintenance.

【0011】このような問題点を解消する手段として、
特公平5−26589号公報には、鋳造終了後のタンデ
ィッシュを熱間整備し、この熱間整備したタンディッシ
ュで鋳造を行う連続鋳造法が提案されている。
As a means for solving such a problem,
Japanese Patent Publication No. 5-26589 proposes a continuous casting method in which a tundish after completion of casting is hot-maintained and casting is performed with the tundish that has been hot-maintained.

【0012】この連続鋳造法では、鋳造終了直後の熱間
状態で、タンディッシュ内の残滓・残鋼の排出,内面洗
浄・スラグ除去などの残鋼処理,スライディングノズル
や浸漬ノズルの交換,さらに必要に応じてタンディッシ
ュ内面に耐火物を局部的に吹付ける内面補修等の整備を
行い、この熱間整備したタンディッシュをモールド上に
セットして次の鋳造を行っている。さらに、鋳造開始に
際しては、溶鋼を注入したタンディッシュをモールドの
側方に移動させ、ここでプラズマトーチ等により溶鋼を
無酸化加熱し、かつスターラ等で攪拌し、溶鋼温度分布
の均一化と溶鋼内のスラグ・酸化物の分離浮上を図って
いる。
[0012] In this continuous casting method, in the hot state immediately after the end of casting, the residue and residual steel in the tundish is discharged, the residual steel is treated such as cleaning the inner surface and slag is removed, and the sliding nozzle and the immersion nozzle are replaced. In accordance with the above, maintenance such as inner surface repair of spraying refractories locally on the inner surface of the tundish is performed, and the tundish thus hot maintained is set on a mold to perform the next casting. Furthermore, at the start of casting, the tundish into which the molten steel has been poured is moved to the side of the mold, where the molten steel is heated non-oxidatively by a plasma torch or the like, and stirred with a stirrer, etc. Separation and floating of slag and oxide inside.

【0013】[0013]

【発明が解決しようとする課題】しかしながら、前述の
ような従来のタンディッシュ熱間整備方法では、実際の
連続鋳造機に適用すると、次のような問題点が生じる。
However, when the conventional tundish hot maintenance method as described above is applied to an actual continuous casting machine, the following problems occur.

【0014】 2ストランド以上のマルチストランド
マシンでは、タンディッシュの形状が大きく、また複雑
となり、タンディッシュの熱間整備(排滓も含む)に時
間を要し(30〜50分)、連続鋳造機の鋳込み間時間
(10〜15分)とマッチングしないため、図6に示す
ように、連続鋳造機のセンターラインCLに対して両サ
イドにタンディッシュ熱間整備設備100を必要とし、
多大のイニシャルコストがかかる。
In a multi-strand machine having two or more strands, the shape of the tundish is large and complicated, and it takes time (30 to 50 minutes) for hot maintenance of the tundish (including waste) (30 to 50 minutes). 6, the tundish hot maintenance equipment 100 is required on both sides of the center line CL of the continuous casting machine as shown in FIG.
Significant initial cost is required.

【0015】 さらに、タンディッシュの数は実質3
基としているが、2ストランド以上では4〜5基が必要
である。前述のように、タンディッシュの形状が大き
く、タンディッシュのコストがイニシャル・ランニング
共に高くなる。さらに、タンディッシュを搭載するタン
ディッシュカーも一段と大きくなり、と相まって連鋳
設備全体がコスト高となる。
Further, the number of tundish is substantially 3
However, 4 or 5 groups are required for two or more strands. As described above, the shape of the tundish is large, and the cost of the tundish is high for both initial and running. Furthermore, the size of the tundish car on which the tundish is mounted is further increased, which in turn increases the cost of the entire continuous casting facility.

【0016】 両サイドにタンディッシュ熱間整備設
備100を設置し、しかもタンディッシュを4〜5基配
置しなければならず、連続鋳造機の鋳込床10が極端に
広くなり、既設の連続鋳造設備には物理的に採用できな
い。
[0016] Tundish hot maintenance equipment 100 must be installed on both sides and 4 to 5 tundishes must be arranged. The casting floor 10 of the continuous casting machine becomes extremely wide, and the existing continuous casting is performed. Equipment cannot be physically employed.

【0017】この発明は、前述のような問題点を解消す
べくなされたもので、その目的は、タンディッシュを熱
間整備して連続使用する連続鋳造において、マルチスト
ランドでも、鋳込床設備をコンパクトで安価な構成とす
ることができ、既設の鋳込床でもタンディッシュの熱間
整備を行うことができる連続鋳造機のタンディッシュ使
用方法,改造方法および鋳込床設備を提供することにあ
る。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems. It is an object of the present invention to provide a continuous casting method in which a tundish is continuously hot-maintained and used continuously. An object of the present invention is to provide a tundish use method, a remodeling method, and a cast floor facility of a continuous casting machine that can be compact and inexpensive and can perform hot maintenance of a tundish even on an existing cast floor. .

【0018】[0018]

【課題を解決するための手段】この発明に係る連続鋳造
機のタンディッシュ使用方法は、取鍋内の溶鋼をタンデ
ィッシュを介してモールド内に鋳込み、鋳込み終了後、
この鋳込みに使用したタンディッシュに残存する滓のみ
を、または滓および鋼を熱間排出すると共に、このタン
ディッシュに対して実質的に冷却しない熱間整備を行
い、この熱間整備したタンディッシュを用いて次の鋳造
を行う連続鋳造法において、図1に示すように、連続鋳
造機の鋳込床10における連鋳機センターラインCLを
挟んで一方の側にタンディッシュ熱間排滓・熱間整備設
備20を設け、他方の側にタンディッシュ予熱装置11
を設け、鋳込み終了後の第1タンディッシュ3−1に対
してタンディッシュ熱間排滓・熱間整備設備20で残滓
または残鋼の処理とタンディッシュ消耗部品の取替(浸
漬ノズルの交換,タンディッシュ注入管の交換)とを行
って次の鋳込みを行い、この第1タンディッシュ3−1
による鋳込みを複数回繰り返すと、第1タンディッシュ
3−1に対してタンディッシュ熱間排滓・熱間整備設備
20で耐火物の補修等(スライディッグノズル装置のカ
セット耐火物交換,タンディッシュ内面の溶射・吹付け
補修)を行うと共に、前記タンディッシュ予熱装置11
で予熱・待機させておいた第2タンディッシュ3−2で
鋳込みを継続する。
A method for using a tundish of a continuous casting machine according to the present invention is to cast molten steel in a ladle through a tundish into a mold, and after completion of the casting,
Only the slag remaining in the tundish used for the casting, or the slag and steel are hot-discharged, and the tundish is hot-maintained without substantially cooling. In the continuous casting method in which the following casting is carried out using a continuous casting machine, as shown in FIG. A maintenance facility 20 is provided, and a tundish preheating device 11 is provided on the other side.
After the casting, the first tundish 3-1 after the casting is processed by the tundish hot waste and hot maintenance equipment 20 to treat the residue or the remaining steel and replace the tundish consumable parts (replacement of the immersion nozzle, The following casting is performed, and the first tundish 3-1 is replaced.
Is repeated a plurality of times, the first tundish 3-1 is repaired with refractory by the tundish hot waste / hot maintenance equipment 20 (replacement of the refractory of the cassette of the slide-dig nozzle device, inner surface of the tundish, etc.). Spraying / spray repair) and the tundish preheating device 11
The casting is continued with the second tundish 3-2 that has been preheated and kept on standby.

【0019】この発明に係る連続鋳造機の改造方法は、
図3の既存の連続鋳造機の鋳込床設備において連鋳機セ
ンターラインCLを挟んで両側に配設されているタンデ
ィッシュ予熱装置11−1,11−2およびタンディッ
シュカー12−1,12−1のうちの、一方の側のタン
ディッシュ予熱装置11−1を撤去してタンディッシュ
熱間排滓・熱間整備設備20を追設し、他方の側のタン
ディッシュ予熱装置11−2(11)とタンディッシュ
カー12−2とを残して活用する。
A method for converting a continuous casting machine according to the present invention is as follows.
In the casting floor equipment of the existing continuous casting machine shown in FIG. 3, the tundish preheating devices 11-1 and 11-2 and the tundish cars 12-1 and 12 are disposed on both sides of the continuous casting machine center line CL. -1, the tundish preheating device 11-1 on one side is removed, the tundish hot waste / hot maintenance equipment 20 is additionally installed, and the tundish preheating device 11-2 ( 11) and the tundish car 12-2 are used.

【0020】この発明に係る連続鋳造機の鋳込床設備
は、連続鋳造機のセンターラインCLを挟んで一方の側
にタンディッシュ予熱装置11と予熱専用タンディッシ
ュカー12−2を配置し、他方の側には鋳込専用タンデ
ィッシュカー12−1とタンディッシュ熱間排滓・熱間
整備設備20を設けて構成する。
In the casting floor equipment of the continuous casting machine according to the present invention, the tundish preheating device 11 and the preheating tundish car 12-2 are arranged on one side of the center line CL of the continuous casting machine, and the other. Is provided with a casting-only tundish car 12-1 and a tundish hot waste / hot maintenance facility 20.

【0021】[0021]

【作用】以上のような構成において、熱間排滓・熱間整
備設備のある側に配置された鋳造専用タンディッシュカ
ー12−1に搭載した第1タンディッシュ3−1で、例
えば5トライ使用し、その間はタンディッシュを無補修
で、タンディッシュの注入管・浸漬ノズルの交換のみを
行い、第1タンディッシュ3−1を予熱することなく連
続使用する。連続鋳造機の鋳込終了から次の鋳込スター
トまでの鋳込間時間は15〜17分程度であり、この間
のうち10〜12分程度で前記熱間整備を行える。
In the above construction, the first tundish 3-1 mounted on the tundish car 12-1 dedicated to casting disposed on the side where the hot waste / hot maintenance equipment is located, for example, five trials are used. In the meantime, the tundish is not repaired, only the injection tube and the immersion nozzle of the tundish are replaced, and the first tundish 3-1 is continuously used without preheating. The casting time from the end of casting of the continuous casting machine to the start of the next casting is about 15 to 17 minutes, and the hot maintenance can be performed in about 10 to 12 minutes.

【0022】第1タンディッシュ3−1を5トライ使用
すると、あるいは耐火物などに異常が発生した場合、前
述のタンディッシュの注入管・浸漬ノズルの交換に加え
てスライディングノズル装置のカセット耐火物,タンン
ディッシュ底部の溶射・吹付け補修などの熱間整備を行
う。この熱間補修は20〜30分程度かかる。
When the first tundish 3-1 is used for 5 trials, or when an abnormality occurs in the refractory, etc., in addition to the replacement of the injection pipe and the immersion nozzle of the tundish, the cassette refractory of the sliding nozzle device, Perform hot maintenance such as thermal spraying and spray repair of the bottom of the tundish. This hot repair takes about 20 to 30 minutes.

【0023】この第1タンディッシュ3−1の消耗部品
の交換、耐火物の溶射・吹付け補修などの熱間整備に
は、合計30〜60分程度かかるため、第1タンディッ
シュの5トライが終了すると同時に、タンディッシュ予
熱装置11の位置で予熱・待機している第2タンディッ
シュ3−2をオーバーヘッドクレーンで鋳造専用タンデ
ィッシュカー12−1に移載して浸漬ノズル等を取付
け、この第2タンディッシュ3−2を第1タンディッシ
ュと同様に5トライ、無補修で消耗品の交換のみで連続
使用する。
It takes about 30 to 60 minutes for hot maintenance such as replacement of consumable parts of the first tundish 3-1 and thermal spraying / spraying of refractories, so that 5 trials of the first tundish are required. At the same time, the second tundish 3-2 preheated and waiting at the position of the tundish preheating device 11 is transferred to a casting tundish car 12-1 by an overhead crane, and an immersion nozzle or the like is attached thereto. As with the first tundish, 2 tundishes 3-2 are used continuously, with 5 trials, no repairs, and only replacement of consumables.

【0024】熱間補修の終了した第1タンディッシュ3
−1は、オーバーヘッドクレーンで予熱専用タンディッ
シュカー12−2まで運搬し、次のトライに使用できる
ように、予熱・待機させておく。以上を繰り返すことに
より、2基のタンディッシュで高効率で安定した操業が
行われる。
First tundish 3 after hot repair
-1 is transported to a preheating tundish car 12-2 by an overhead crane, and is preheated and put on standby so that it can be used for the next trial. By repeating the above, stable operation with high efficiency is performed with two tundishes.

【0025】鋳込床10には、一方の側にタンディッシ
ュ熱間排滓・熱間整備設備20、他方の側にタンディッ
シュ予熱装置11と予熱専用タンディッシュカー12−
2を配置し、かつタンディッシュは2基で済むため、鋳
込床設備をコンパクトで安価な構成とすることができ、
既設の連続鋳造機の鋳込床を改造することも可能とな
る。
The cast floor 10 has a tundish hot waste / hot maintenance facility 20 on one side, and a tundish preheating device 11 and a preheating tundish car 12- on the other side.
2 and two tundishes are sufficient, so that the cast floor equipment can be made compact and inexpensive,
It is also possible to modify the casting floor of an existing continuous casting machine.

【0026】[0026]

【実施例】以下、この発明を図示する一実施例に基づい
て詳細に説明する。これは、既設の2ストランドの連続
鋳造機を改造した例である。なお、従来と同一または相
当する部分については同一符号を付する。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a block diagram showing a first embodiment of the present invention; This is an example in which an existing two-strand continuous casting machine is modified. Note that the same reference numerals are given to the same or corresponding parts as those in the related art.

【0027】図1はこの発明に係る鋳込床設備を示す概
略平面図であり、本発明では、図3の従来既設の連続鋳
造機の鋳込床における予熱待機位置bのタンディッシュ
予熱装置11−1を除去し、予熱待機位置cにおけるタ
ンディッシュ予熱装置11−2とタンディッシュカー1
2−2とを残し、1基のタンディッシュ予熱装置11
と、2台のタンディッシュカー12−1,12−2を使
用する。
FIG. 1 is a schematic plan view showing a casting floor facility according to the present invention. In the present invention, a tundish preheating apparatus 11 at a preheating standby position b in a casting floor of a conventional existing continuous casting machine shown in FIG. -1 and the tundish preheating device 11-2 and the tundish car 1 at the preheating standby position c.
2-2 and one tundish preheating device 11
And two tundish cars 12-1 and 12-2.

【0028】b側のタンディッシュカー12−1は鋳造
専用とし、鋳込み位置aと後述する位置b−2を往復走
行可能とする。c側のタンディッシュカー12−2は予
熱専用とし、往復走行させず、定置させてタンディッシ
ュ3を支持する支持架台として使用する。
The tundish car 12-1 on the b side is dedicated to casting, and can reciprocate between a casting position a and a position b-2 described later. The c-side tundish car 12-2 is dedicated to preheating, does not reciprocate, is fixed, and is used as a support base for supporting the tundish 3.

【0029】さらに、鋳込床10の鋳造専用タンディッ
シュカー12−1側を若干増設し、ここにタンディッシ
ュ熱間排滓・熱間整備設備20を設置する。このタンデ
ィッシュ熱間排滓・熱間整備ヤードは、鋳込み位置aの
横に順に連続する中間待機位置b−1,補修位置b−2
と、補修位置b−2に平行に位置する傾転位置b−3か
ら構成する。
Further, a side of the casting floor 10 dedicated to the casting tundish car 12-1 is slightly added, and a tundish hot waste / hot maintenance facility 20 is installed there. The tundish hot waste / hot maintenance yard has an intermediate standby position b-1 and a repair position b-2 which are successively arranged in the side of the casting position a.
And a tilt position b-3 located parallel to the repair position b-2.

【0030】中間待機位置b−1には、注入管交換装置
21,浸漬ノズル交換装置22などを設置する。補修位
置b−2には、スライディングノズルのカセット耐火物
交換装置23と耐火物溶射・吹付け装置24などを設け
る。傾転位置b−3には、タンディッシュ3を傾転させ
る傾転装置25と、残滓・残鋼を受ける滓パンを設置
し、傾転装置25は補修位置b−2まで往復移動する天
井走行クレーン構造とする。
At the intermediate standby position b-1, an injection pipe exchange device 21, an immersion nozzle exchange device 22, and the like are installed. At the repair position b-2, a cassette refractory exchanging device 23 for a sliding nozzle, a refractory spraying / spraying device 24, and the like are provided. At the tilting position b-3, a tilting device 25 for tilting the tundish 3 and a slag pan for receiving the residue and the residual steel are installed, and the tilting device 25 reciprocates to the repair position b-2. Crane structure will be used.

【0031】なお、注入管交換装置21,浸漬ノズル交
換装置22,スライディングノズルのカセット耐火物交
換装置23,耐火物溶射・吹付け装置24は自動ロボッ
トなどの自動で作業を行うものでもよいし、手動で作業
を行うものでもよい。
The injection pipe changing device 21, the immersion nozzle changing device 22, the sliding nozzle cassette refractory changing device 23, and the refractory spraying / spraying device 24 may be operated automatically by an automatic robot or the like. The work may be performed manually.

【0032】以上のような構成において、次のように連
続鋳造を行う(図2参照)。
With the above configuration, continuous casting is performed as follows (see FIG. 2).

【0033】(1) 鋳造専用タンディッシュカー12−1
を鋳込み位置aに移動させ、取鍋1からの溶鋼をNo.1タ
ンディッシュ3−1を介してモールド内に注入する。こ
こで、鋳造開始に際しては、取鍋1の溶鋼をタンディッ
シュ3内に注入し、溶鋼流によってタンディッシュ3内
面の付着スラグおよび酸化物を溶鋼内に取り込み、分離
浮上させ、規定量の溶鋼を貯留した後、モールド4内に
注入して鋳込みをスタートさせる。なお、付着スラグお
よび酸化物の分離浮上を促進するため、加熱や攪拌を行
うようにしてもよい。
(1) Tundish car for casting 12-1
Is moved to the pouring position a, and molten steel from the ladle 1 is poured into the mold through the No. 1 tundish 3-1. At the start of casting, the molten steel in the ladle 1 is poured into the tundish 3, and the slag and oxides adhered to the inner surface of the tundish 3 are taken into the molten steel by the molten steel flow, separated and floated, and a specified amount of molten steel is formed. After being stored, it is poured into the mold 4 to start casting. Heating or stirring may be performed to promote the separation and floating of the attached slag and oxide.

【0034】(2) 1トライの連続鋳造が終了すると、中
間待機位置bまで鋳造専用タンディッシュカー12−1
を移動させる。この移動中に浸漬ノズル7と、タンディ
ッシュ注入管5を取り外す。なお、タンディッシュ蓋8
は付けたままとする。
(2) When one trial of continuous casting is completed, the casting-only tundish car 12-1 reaches the intermediate standby position b.
To move. During this movement, the immersion nozzle 7 and the tundish injection tube 5 are removed. The tundish lid 8
Is left attached.

【0035】(3) 鋳造専用タンディッシュカー12−1
をさらに補修位置b−2まで移動させ、この位置からN
o.1タンディッシュ3−1を傾転装置25で吊り上げ、
傾転位置b−3まで移動させ、ここで傾転させることに
より排滓等を行う。
(3) Tundish car for casting 12-1
Is further moved to the repair position b-2, and N
o.1 The tundish 3-1 is lifted by the tilting device 25,
It is moved to the tilting position b-3, where the waste is discharged by tilting.

【0036】(4) 残滓等の処理が終了すると、傾転装置
25によりNo.1タンディッシュ3−1を補修位置b−2
に戻し、鋳造専用タンディッシュカー12−1上に載せ
る。続いて、鋳造専用タンディッシュカー12−1を中
間待機位置b−1に移動させ、ここでタンディッシュ下
面の浸漬ノズル7を取付け、同時にタンディッシュ上面
のタンディッシュ注入管5を取付ける。
(4) When the processing of the residue is completed, the tilting device 25 moves the No. 1 tundish 3-1 to the repair position b-2.
And put on the tundish car 12-1 for casting. Subsequently, the casting-only tundish car 12-1 is moved to the intermediate standby position b-1, where the dipping nozzle 7 on the lower surface of the tundish is attached, and at the same time, the tundish injection pipe 5 on the upper surface of the tundish is attached.

【0037】以上により、次回鋳造の準備が完了し、こ
の間(鋳造終了から鋳造準備完了まで)10〜12分で
前記一連のタンディッシュ熱間整備を完了することがで
きた。鋳造終了後、直ちに熱間状態で前記簡易整備を実
施するため、次の鋳造終了までの間に、タンディッシュ
の温度低下は極くわずかであり、予熱をする必要がな
い。なお、鋳込終了から次の鋳込スタートまでの時間
は、ダミーバーの挿入などで15〜17分かかるが、こ
の時間内でタンディッシュの準備が完了する。
As described above, the preparation for the next casting was completed, and during this period (from the end of casting to the completion of casting preparation), the series of hot maintenance of the tundish was completed in 10 to 12 minutes. Immediately after the end of casting, the above-mentioned simple maintenance is performed in a hot state. Therefore, the temperature of the tundish decreases very little until the end of the next casting, and there is no need for preheating. The time from the end of casting to the start of the next casting takes 15 to 17 minutes due to insertion of a dummy bar or the like, but preparation of the tundish is completed within this time.

【0038】(5) 以上のような熱間整備されたNo.1タン
ディッシュ3−1を例えば5トライ連続使用する。この
連続鋳造を5トライ繰り返すと、鋳造終了後のNo.1タン
ディッシュ3−1を、中間待機位置b−1での浸漬ノズ
ル7等の取り外し、傾転位置b−3での排滓後、補修位
置b−2で鋳造専用タンディッシュカー12−1から降
ろして床置きし、耐火物の溶射・吹付け補修を行い、ス
ライディングノズル装置6のスライディングカセットの
耐火物交換を行う。鋳造専用タンディッシュカー12−
1は中間待機位置b−1に移動させておく。
(5) The No. 1 tundish 3-1 which has been hot-prepared as described above is continuously used, for example, for 5 trials. When this continuous casting is repeated for 5 trials, the No. 1 tundish 3-1 after completion of casting is removed from the immersion nozzle 7 and the like at the intermediate standby position b-1 and the waste is discharged at the tilting position b-3. At the repair position b-2, the caster is lowered from the casting-only tundish car 12-1 and placed on the floor to perform thermal spraying / spray repair of the refractory, and replace the refractory of the sliding cassette of the sliding nozzle device 6. Casting tundish car 12-
1 is moved to the intermediate standby position b-1.

【0039】(6) このような補修と耐火物交換を行う
と、30〜60分の時間を要するため、予熱専用タンデ
ィッシュカー12−2においてタンディッシュ予熱装置
11で予熱・待機させておいたNo.2タンディッシュ3−
2を、オーバーヘッドクレーン14で中間待機位置b−
1に待機している鋳造専用タンディッシュカー12−1
に運搬し、ここで浸漬ノズル7を取付け、鋳造専用タン
ディッシュカー12−1を鋳込み位置aに移動させ、こ
のNo.2タンディッシュ3−2で、次の連続鋳造を行い、
複数回トライを繰り返す。
(6) It takes 30 to 60 minutes to perform such repair and refractory replacement. Therefore, the tundish preheating device 11 in the tundish preheating device 12 in the preheating dedicated tundish car 12-2 is used. No.2 tundish 3-
2 at the intermediate standby position b-
Casting tundish car 12-1 waiting at 1
Then, the immersion nozzle 7 is attached, the casting-only tundish car 12-1 is moved to the casting position a, and the next continuous casting is performed with this No. 2 tundish 3-2.
Repeat multiple times.

【0040】(7) 一方、補修あるいは耐火物交換の終了
したNo.1タンディッシュ3−1は、オーバーヘッドクレ
ーン14で予熱専用タンディッシュカー12−2上に移
載し、タンディッシュ予熱装置11で予熱し、次の鋳造
への準備体制を整え待機させておく。
(7) On the other hand, the No. 1 tundish 3-1 whose repair or refractory replacement has been completed is transferred onto a preheating dedicated tundish car 12-2 by an overhead crane 14, and It is preheated and ready for the next casting.

【0041】以上のように、2基のタンディッシュ3で
常に15〜17分で回転させ、高能率鋳造を行うことが
できた。ここで、容量85トンのタンディッシュを用い
た場合、従来の既存の連鋳機における鋳込床設備(図
3)に比較すると、次のような効果が得られた。
As described above, the two tundishes 3 were constantly rotated for 15 to 17 minutes to perform high-efficiency casting. Here, when a tundish having a capacity of 85 tons was used, the following effects were obtained as compared with the casting floor equipment (FIG. 3) in a conventional existing continuous casting machine.

【0042】 タンディッシュを熱間で繰り返し使用
するので、タンディッシュの個数を大幅に減少させるこ
とができる。
Since the tundish is repeatedly used while hot, the number of the tundish can be greatly reduced.

【0043】 タンディッシュ内面の温度が残鋼・残
滓が付着する温度まで低下しないので、付着物剥ぎ取り
作業がなく、耐火物損耗がなくなり、さらに従来のよう
に整備ヤードまでの運搬がないため、タンディッシュ内
面の温度変化を少なくできることなどから、タンディッ
シュ耐火物の寿命を向上させることができる。
Since the temperature of the inner surface of the tundish does not decrease to a temperature at which the residual steel and the residue adhere, there is no work to remove the adhered substance, there is no wear of the refractory, and there is no transportation to the maintenance yard unlike the conventional case. Since the temperature change on the inner surface of the tundish can be reduced, the life of the tundish refractory can be improved.

【0044】 耐火物寿命の向上、タンディッシュ個
数の減少により、タンディッシュ耐火物コストを従来の
1/8以下にすることができる。
By improving the life of the refractory and reducing the number of tundishes, the cost of the tundish refractory can be reduced to 1/8 or less of the conventional cost.

【0045】 タンディッシュを熱間で繰り返し使用
するため、タンディッシュを実質的に予熱することがな
いので、タンディッシュ加熱のためのCガス,電力,酸
素使用量の低減を図れる。
Since the tundish is repeatedly used while hot, the tundish is not substantially preheated, so that the amount of C gas, electric power, and oxygen used for heating the tundish can be reduced.

【0046】 タンディッシュを整備ヤードまで搬送
する必要がないので、タンディッシュの整備要員を低減
できる。
Since there is no need to transport the tundish to the maintenance yard, the number of maintenance personnel for the tundish can be reduced.

【0047】さらに、従来の熱間整備方法と比較して次
のような効果を奏する。
Further, the following effects can be obtained as compared with the conventional hot maintenance method.

【0048】 従来の熱間整備方法では、広い鋳込床
を必要とし新設による連続鋳造機にしか適用できなかっ
たが、既設の連続鋳造機にも適用できるようになった。
The conventional hot maintenance method requires a wide casting floor and can be applied only to a newly installed continuous casting machine. However, it can be applied to an existing continuous casting machine.

【0049】 改造コストは、新設コストの1/8〜
1/10で可能となり、タンディッシュ熱間再使用を低
コストで実施できるようになった。
The remodeling cost is 1/8 of the new construction cost
1/10 has become possible, and the tundish hot reuse can be performed at low cost.

【0050】 マルチストランドでは、従来、タンデ
ィッシュを4〜5基必要であったものが、2基で済み、
また運転要員・整備管理要員の兼用化で要員を減少させ
ることができた。
In the case of a multi-strand, four to five tundishes were conventionally required, but only two are required.
In addition, the number of personnel was reduced by using both operating and maintenance personnel.

【0051】 改造工期を最小限にでき、1週間〜1
0日間(5日間×2回)で改造工事・停機(既設製造設
備を長期間停機させることは、製鉄所にとってはとと大
問題である)を短縮化できた。
The remodeling period can be minimized, and one week to one
In 0 days (5 days x 2 times), it was possible to shorten the time required for remodeling work and stoppages (stopping existing production facilities for a long time is a serious problem for steelworks).

【0052】[0052]

【発明の効果】前述の通り、この発明は、連鋳機のセン
ターラインを挟んで一方の側に鋳造専用タンディッシュ
カーとタンディッシュ熱間排滓・熱間整備設備を設置
し、他方の側に予熱専用タンディッシュカーとタンディ
ッシュ予熱装置を配置し、第1タンディッシュを熱間状
態で繰り返し使用し、第1タンディッシュに対して熱間
補修が必要になると、第2タンディッシュを繰り返し使
用して鋳造を継続するようにしたため、次のような効果
を奏する。
As described above, according to the present invention, a tundish car for exclusive use of casting and a tundish hot waste and hot maintenance facility are installed on one side of the center line of the continuous casting machine, and the other side is provided. A tundish car and a tundish preheating device are placed in the tundish, and the first tundish is repeatedly used in a hot state. If the first tundish needs hot repair, the second tundish is repeatedly used. As a result, the following effects can be obtained.

【0053】(1) 従来の熱間整備方法のように、タンデ
ィッシュ熱間排滓・熱間整備設備を連鋳機の両サイドに
配設する必要がなく、また既存の連続鋳造機の一方の側
のタンディッシュ予熱装置とタンディッシュカーを利用
でき、設備コストの低減を図ることができる。
(1) Unlike the conventional hot maintenance method, it is not necessary to dispose tundish hot waste / hot maintenance equipment on both sides of the continuous caster, and it is not necessary to dispose one of the existing continuous casters. The tundish preheating device and the tundish car on the side can be used, and the equipment cost can be reduced.

【0054】(2) マルチストランドの場合、従来の熱間
整備方法では、4〜5基のタンディッシュが必要であっ
たが、本発明では2基のタンディッシュで高効率で安定
した操業を行うことができる。
(2) In the case of a multi-strand, four to five tundishes are required in the conventional hot maintenance method, but in the present invention, two tundishes are used to perform highly efficient and stable operation. be able to.

【0055】(3) 1基のタンディッシュ熱間排滓・熱間
整備設備と2基のタンディッシュにより、鋳込床設備を
コンパクトで簡単な構成とすることができ、既存の連続
鋳造機にも適用できる。また、設備コストや改造コスト
の低減、改造工事の迅速化を図れる。
(3) The cast floor equipment can be made compact and simple with one tundish hot waste / hot maintenance equipment and two tundishes. Can also be applied. In addition, equipment costs and remodeling costs can be reduced, and remodeling work can be speeded up.

【0056】(4) 一方の側にのみ熱間排滓・熱間整備設
備を配設し、タンディッシュも2台で済むため、タンデ
ィッシュ要員の低減を図れる。
(4) Since hot waste / hot maintenance equipment is provided only on one side and only two tundish units are required, the number of tundish personnel can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明に係る連鋳機の鋳込床設備を示す概略
平面図である。
FIG. 1 is a schematic plan view showing a casting floor facility of a continuous casting machine according to the present invention.

【図2】この発明に係るタンディッシュ使用方法を示す
フローチャートである。
FIG. 2 is a flowchart showing a method for using a tundish according to the present invention.

【図3】従来の既存の鋳込床設備を示す概略平面図であ
る。
FIG. 3 is a schematic plan view showing a conventional existing casting floor facility.

【図4】図3の鋳込床設備の部分断面図である。FIG. 4 is a partial sectional view of the cast floor equipment of FIG. 3;

【図5】図3の鋳込床設備におけるタンディッシュ使用
方法を示すフローチャートである。
5 is a flowchart showing a method of using a tundish in the cast floor facility of FIG.

【図6】従来の熱間整備を行う鋳込床設備を示す概略平
面図である。
FIG. 6 is a schematic plan view showing a conventional cast floor facility for performing hot maintenance.

【符号の説明】[Explanation of symbols]

1…取鍋 2…レードルターレット 3…タンディッシュ 4…モールド 5…タンディッシュ注入管 6…スライディングノズル装置 7…浸漬ノズル 8…タンディッシュ蓋 10…鋳込床 11…タンディッシュ予熱装置 12−1…鋳造専用タンディッシュカー 12−2…予熱専用タンディッシュカー 14…オーバーヘッドクレーン 20…タンディッシュ熱間排滓・熱間整備設備 21…注入管交換装置 22…浸漬ノズル交換装置 23…スライディングノズルのカセット耐火物交換装置 24…耐火物溶射・吹付け装置 25…傾転装置 DESCRIPTION OF SYMBOLS 1 ... Ladle 2 ... Ladle turret 3 ... Tundish 4 ... Mold 5 ... Tundish injection pipe 6 ... Sliding nozzle device 7 ... Immersion nozzle 8 ... Tundish lid 10 ... Casting floor 11 ... Tundish preheating device 12-1 ... Casting tundish car 12-2 ... Preheating tundish car 14 ... Overhead crane 20 ... Tundish hot waste / hot maintenance equipment 21 ... Injection pipe exchange device 22 ... Immersion nozzle exchange device 23 ... Sliding nozzle cassette fireproof Material exchange device 24: Refractory spraying and spraying device 25: Tilting device

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.6,DB名) B22D 11/10 310 B22D 41/00 B22D 43/00──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int. Cl. 6 , DB name) B22D 11/10 310 B22D 41/00 B22D 43/00

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 取鍋内の溶鋼をタンディッシュを介して
モールド内に鋳込み、鋳込み終了後、この鋳込みに使用
したタンディッシュに残存する滓のみを、または滓およ
び鋼を熱間排出すると共に、このタンディッシュに対し
て実質的に冷却しない熱間整備を行い、この熱間整備し
たタンディッシュを用いて次の鋳造を行う連続鋳造法に
おいて、 連続鋳造機の鋳込床における連鋳機センターラインを挟
んで一方の側にタンディッシュ熱間排滓・熱間整備設備
を設け、他方の側にタンディッシュ予熱装置を設け、鋳
込み終了後の第1タンディッシュに対してタンディッシ
ュ熱間排滓・熱間整備設備で残滓または残鋼の処理とタ
ンディッシュ消耗部品の取替とを行って次の鋳込みを行
い、この第1タンディッシュによる鋳込みを複数回繰り
返すと、第1タンディッシュに対してタンディッシュ熱
間排滓・熱間整備設備で耐火物の補修等を行うと共に、
前記タンディッシュ予熱装置で予熱・待機させておいた
第2タンディッシュで鋳込みを継続することを特徴とす
る連続鋳造機のタンディッシュ使用方法。
1. Casting molten steel in a ladle into a mold via a tundish, and after casting is completed, only the slag remaining in the tundish used for the casting, or slag and steel are hot-discharged, and In the continuous casting method in which hot maintenance without substantially cooling the tundish is performed and the next casting is performed using the tundish thus maintained, the center line of the continuous casting machine in the casting floor of the continuous casting machine is used. A tundish hot waste / hot maintenance facility is provided on one side with the tundish preheating device provided on the other side, and the tundish hot waste / When the next casting is performed by performing the processing of the residue or the remaining steel and the replacement of the tundish consumable parts in the hot maintenance equipment, and the casting by the first tundish is repeated a plurality of times, Performs the repair or the like of the refractory material in the tundish hot Haikasu-hot maintenance equipment for a tundish,
A method for using a tundish in a continuous casting machine, wherein casting is continued in a second tundish that has been preheated and waited in the tundish preheating device.
【請求項2】 既存の連続鋳造機の鋳込床設備において
連鋳機センターラインを挟んで両側に配設されているタ
ンディッシュ予熱装置およびタンディッシュカーのうち
の、一方の側のタンディッシュ予熱装置を撤去してタン
ディッシュ熱間排滓・熱間整備設備を追設し、他方の側
のタンディッシュ予熱装置とタンディッシュカーとを残
して活用することを特徴とする連続鋳造機の改造方法。
2. A tundish preheating device on one side of a tundish preheating device and a tundish car disposed on both sides of a continuous casting machine center line in a casting floor facility of an existing continuous casting machine. A method for remodeling a continuous casting machine, which comprises removing a device, adding a hot-draining and hot-maintenance facility for a tundish, and using a tundish preheating device and a tundish car on the other side. .
【請求項3】 連続鋳造機のセンターラインを挟んで一
方の側にタンディッシュ予熱装置と予熱専用タンディッ
シュカーを配置し、他方の側には鋳込専用タンディッシ
ュカーとタンディッシュ熱間排滓・熱間整備設備を設け
たことを特徴とする連続鋳造機の鋳込床設備。
3. A tundish preheating device and a preheating-only tundish car are disposed on one side of the center line of the continuous casting machine, and a casting-only tundish car and a tundish hot waste are disposed on the other side. -Casting floor equipment for continuous casting machines characterized by hot maintenance equipment.
JP16815294A 1994-07-20 1994-07-20 Method of using tundish for continuous casting machine, remodeling method and casting floor equipment Expired - Fee Related JP2856075B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16815294A JP2856075B2 (en) 1994-07-20 1994-07-20 Method of using tundish for continuous casting machine, remodeling method and casting floor equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16815294A JP2856075B2 (en) 1994-07-20 1994-07-20 Method of using tundish for continuous casting machine, remodeling method and casting floor equipment

Publications (2)

Publication Number Publication Date
JPH0833957A JPH0833957A (en) 1996-02-06
JP2856075B2 true JP2856075B2 (en) 1999-02-10

Family

ID=15862789

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16815294A Expired - Fee Related JP2856075B2 (en) 1994-07-20 1994-07-20 Method of using tundish for continuous casting machine, remodeling method and casting floor equipment

Country Status (1)

Country Link
JP (1) JP2856075B2 (en)

Also Published As

Publication number Publication date
JPH0833957A (en) 1996-02-06

Similar Documents

Publication Publication Date Title
RU2530578C2 (en) Flexible electric arc furnace with minimum electric power consumption and method of steel products fabrication
KR100736940B1 (en) Vacuum Degas Apparatus Having Duplex Vessel
JP2856075B2 (en) Method of using tundish for continuous casting machine, remodeling method and casting floor equipment
EP0413894B1 (en) Pneumatic steelmaking vessel and method of producing steel
JPH0829402B2 (en) Continuous casting method
US4064930A (en) Continuous casting method using a ladle bogie
JP3147335B2 (en) Refractory changer for molten metal storage pan
JP3273427B2 (en) Method for replacing refractory for molten metal container and apparatus for replacing refractory for molten metal container
JP3088928B2 (en) Hot reuse facility for tundish in continuous caster
JP3379635B2 (en) Exhaust heat device of immersion nozzle exchange device
JP2006322021A (en) Method for operating converter facility, and converter facility
JPS61103653A (en) Slag removal of tundish
US3477705A (en) Steel making apparatus
JP2695882B2 (en) Waste transfer equipment in continuous casting equipment
JPH0526589B2 (en)
JPS591612A (en) Operating method of arc furnace
JPH0750044Y2 (en) Continuous casting equipment
JP2559111Y2 (en) Continuous casting equipment
JPS6347402Y2 (en)
JPH05318054A (en) Hot reusing equipment for tundish in continuous caster
JP2782490B2 (en) Gutter refractory construction method and apparatus
JPS5836047B2 (en) Continuous steel manufacturing method
JPH10146653A (en) Apparatus for circulatively using tundish in continuous casting equipment
JPH067905A (en) Continuous casting device
JPH10225765A (en) Method for reusing continuous casting tundish

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees