JP2808426B2 - How to build underground structures - Google Patents

How to build underground structures

Info

Publication number
JP2808426B2
JP2808426B2 JP7278715A JP27871595A JP2808426B2 JP 2808426 B2 JP2808426 B2 JP 2808426B2 JP 7278715 A JP7278715 A JP 7278715A JP 27871595 A JP27871595 A JP 27871595A JP 2808426 B2 JP2808426 B2 JP 2808426B2
Authority
JP
Japan
Prior art keywords
underground structure
underground
jack
pit
roof cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP7278715A
Other languages
Japanese (ja)
Other versions
JPH09119285A (en
Inventor
誠 植村
新市 丸田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP7278715A priority Critical patent/JP2808426B2/en
Publication of JPH09119285A publication Critical patent/JPH09119285A/en
Application granted granted Critical
Publication of JP2808426B2 publication Critical patent/JP2808426B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、鉄道、道路等の下
部地中に大幅員の地下構造物を横断方向に掘進建設する
際に上部交通に支障を与えることなく施工することがで
きる地下構造物の構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an underground structure which can be constructed without hindrance to upper traffic when a large underground structure such as a railway or a road is excavated in a transverse direction. It relates to a method of constructing an object.

【0002】[0002]

【従来の技術】鉄道、道路等の下部地中に大幅員の地下
構造物を横断方向に掘進させるには、上部交通を支承す
るための防護工が必要となり、かかる防護工として従来
鋼管等を水平に並列させるパイプルーフを設けることな
どが挙げられるが、地中に掘進させる地下構造物の防護
工を別工事として施工することなく、地下構造物の掘進
と同時に行うので安全かつ確実に、しかも安価に工事が
でき、また土被りも浅く施工できるものとして、次のよ
うな工法が知られている。
2. Description of the Related Art In order to excavate underground structures of a large number of members in the underground such as railways and roads in the transverse direction, protective works for supporting upper traffic are required. Although it is possible to provide a pipe roof that is parallel to the horizontal, etc., it is safe and reliable because the protective work of the underground structure to be excavated underground is not performed as a separate work, but simultaneously with the excavation of the underground structure The following construction methods are known as those which can be constructed at low cost and can be constructed with shallow earth covering.

【0003】これは図4にも示すように、鉄道等上部交
通1の脇に土留め鋼矢板2を打設して、発進坑3と到達
坑4を築造し、該発進坑3内に圧入機5を設置してこれ
でルーフ用筒体6を到達坑4に向けて圧入させる。
As shown in FIG. 4, a steel retaining sheet pile 2 is placed beside an upper traffic 1 such as a railway to construct a starting pit 3 and a reaching pit 4, and press-fit into the starting pit 3. The roof cylinder 6 is press-fitted toward the reaching pit 4.

【0004】ルーフ用筒体6は鋼管による略正方形断面
の箱型筒体であり、側面に鉤状の継手を介して長手方向
に連続して形成し、上面にフリクションカッター7を設
けたもので、長さ方向に順次接続して必要長を埋設する
ことができ、さらに継手を介して横方向に並列させる。
この並べ方は一例として図7に示すような一文字型であ
る。
The roof cylinder 6 is a box-shaped cylinder having a substantially square cross section made of a steel pipe, formed continuously in the longitudinal direction via a hook-shaped joint on a side surface, and provided with a friction cutter 7 on an upper surface. The required length can be buried by sequentially connecting in the length direction, and furthermore, it is arranged side by side through a joint.
This arrangement is, for example, a one-character type as shown in FIG.

【0005】次いで、図5に示すように発進坑3内に反
力壁8、コンクリート函体による地下構造物9をセット
し、反力壁8と地下構造物9との間には推進ジャッキ10
を設け、地下構造物9の先端に刃口11を設けるとともに
地下構造物9の先端と前記ルーフ用筒体6との間に小ジ
ャッキ12を介在させる。
Next, as shown in FIG. 5, a reaction wall 8 and an underground structure 9 made of a concrete box are set in the starting pit 3, and a propulsion jack 10 is provided between the reaction wall 8 and the underground structure 9.
Is provided at the tip of the underground structure 9, and a small jack 12 is interposed between the tip of the underground structure 9 and the roof cylinder 6.

【0006】図中13はルーフ用筒体6の支持材、14はフ
リクションカッター7の止め部材でこれらは発進坑3側
に設け、一方、到達坑4側に受台15を設ける。
In FIG. 1, reference numeral 13 denotes a support member for the roof cylinder 6, and reference numeral 14 denotes a stopper for the friction cutter 7, which is provided on the starting shaft 3 side, while a receiving stand 15 is provided on the reaching shaft 4 side.

【0007】小ジャッキ12を伸長して地下構造物9を反
力としてフリクションカッター7を残しながらルーフ用
筒体6を1本ずつ順次押し進め、一通り筒体6が前進し
たならば、小ジャッキ12を縮め、今度は推進ジャッキ10
を伸長して地下構造物9を掘進させる。図中16は推進ジ
ャッキ10と地下構造物9間に介在させるストラットを示
す。
The small jack 12 is extended to push the roof cylinders 6 one by one while leaving the friction cutter 7 with the underground structure 9 as a reaction force. , This time promotion jack 10
To extend the underground structure 9. In the figure, reference numeral 16 denotes a strut interposed between the propulsion jack 10 and the underground structure 9.

【0008】このようにして、ルーフ用筒体6の前進と
地下構造物9の前進とを交互に繰り返しながら、到達坑
4に出たルーフ用筒体6は順次撤去する。
[0008] In this way, the roof cylinders 6 that have come out to the reaching pit 4 are sequentially removed while the advance of the roof cylinder 6 and the advance of the underground structure 9 are alternately repeated.

【0009】そして、地下構造物9の先端が到達坑4に
達したならば、刃口11等を撤去し適宜裏込めグラウトを
行って施工を完了する。
Then, when the tip of the underground structure 9 reaches the reaching pit 4, the cutting edge 11 and the like are removed and backfill grouting is performed as appropriate to complete the construction.

【0010】なお、地下構造物9はプレキャスト製のコ
ンクリート函体を発進坑3内に順次吊り下ろして接続し
ていくようにしてもよいし、発進坑3内でコンクリート
を打設して必要長を増設するようにしてもよい。
The underground structure 9 may be connected by suspending a precast concrete box in the starting pit 3 one by one or by placing concrete in the starting pit 3. May be added.

【0011】また、地下構造物9の前進方法について、
到達坑4側に反力壁及びセンターホール式の牽引ジャッ
キを設け、一端を地下構造物9に定着したPC鋼線によ
る牽引部材をこの牽引ジャッキで引くことにより到達坑
4側から地下構造物9を引き込むようにする工法もあ
る。
[0011] Further, regarding the method of moving the underground structure 9,
A reaction wall and a center-hole type traction jack are provided on the reaching pit 4 side, and a traction member made of a PC steel wire having one end fixed to the underground structure 9 is pulled by the traction jack. There is also a construction method to draw in.

【0012】[0012]

【発明が解決しようとする課題】後方のジャッキでルー
フ用筒体6や地下構造物9を推進する工法では、発進坑
3側に反力壁8、推進ジャッキ10を設ける必要があり、
また、到達坑4側からPC鋼線で地下構造物9を引き込
む工法では、到達坑4側に反力壁を設ける必要があり、
いずれの場合も発進坑3側または到達坑4側に反力壁を
設置することになり、推進や牽引に必要な反力体巾を確
保しなければならず、施工可能な場所が限定される。
In the method of propelling the roof cylinder 6 and the underground structure 9 with the rear jack, it is necessary to provide the reaction wall 8 and the propulsion jack 10 on the starting pit 3 side.
Also, in the construction method in which the underground structure 9 is drawn from the reaching pit 4 side with a PC steel wire, it is necessary to provide a reaction wall on the reaching pit 4 side,
In either case, a reaction wall will be installed on the starting pit 3 side or the reaching pit 4 side, and the reaction force width necessary for propulsion and traction must be secured, and the place where construction is possible is limited. .

【0013】本発明の目的は前記従来例の不都合を解消
し、ルーフ用筒体を先行させて後続の複数に分割された
地下構造物を掘進させる地下構造物の構築方法におい
て、ルーフ用筒体及び各地下構造物をジャッキで推進ま
たは牽引するための反力壁の設置が不要となり、発進坑
側や到達坑側のスペースが小さくても施工が可能な地下
構造物の構築方法を提供することにある。
An object of the present invention is to solve the inconvenience of the prior art, and to provide a method for constructing an underground structure in which a roof cylinder is advanced and a plurality of subsequent underground structures are excavated. It is not necessary to install a reaction wall for propelling or towing each underground structure with a jack, and to provide a method of constructing an underground structure that can be constructed even if the space on the start pit side or the arrival pit side is small. It is in.

【0014】[0014]

【課題を解決するための手段】本発明は前記目的を達成
するため、ルーフ用筒体を発進坑から地中に水平方向に
圧入して並列させ、発進坑に残るルーフ用筒体の後方に
地下構造物を配設し、ルーフ用筒体を先行させて後続の
複数に分割された地下構造物を掘進させる地下構造物の
構築方法において、ルーフ用筒体と地下構造物の間、及
び複数の地下構造物間に推進ジャッキを介在させ、最後
部の地下構造物に牽引ジャッキを設け、PC鋼線等の牽
引部材を定着具で最前部の地下構造物に定着し、最前部
の地下構造物で反力をとってルーフ用筒体と地下構造物
の間の推進ジャッキを伸長してルーフ用筒体を前進さ
せ、次に最前部の地下構造物をその後方の地下構造物で
反力をとって地下構造物間の推進ジャッキを伸長して掘
進させ、その後、複数の地下構造物についてもそれぞれ
の後方に位置する地下構造物で反力をとりながら推進ジ
ャッキの伸長により順次掘進させ、最後部の地下構造物
については、最前部の地下構造物で反力をとって牽引ジ
ャッキによりPC鋼線で到達坑側に引き込むことで掘進
させることを要旨とするものである。
According to the present invention, in order to achieve the above object, a roof cylinder is horizontally pressed into a ground from a starting pit and is arranged in parallel with the roof cylinder. In a method of constructing an underground structure in which an underground structure is provided, and a roof cylinder is advanced and a plurality of subsequent underground structures are excavated, the underground structure is provided between the roof cylinder and the underground structure, and A propulsion jack is interposed between the underground structures, and a traction jack is provided at the last underground structure. The propulsion jack between the roof cylinder and the underground structure is extended by the reaction with the object and the roof cylinder is advanced, and then the foreground underground structure is reacted by the underground structure behind it. To extend the propulsion jack between the underground structures and excavate it. As for the underground structures, the excavation jack is extended to excavate sequentially while taking the reaction force at the underground structures located at the rear, and the reaction force is taken at the foremost underground structure at the rearmost underground structure. The gist is to pull the steel wire into the reaching pit side by using a towing jack to reach the pit.

【0015】請求項1記載の本発明によれば、最後部以
外の地下構造物とルーフ用筒体は後方の地下構造物から
反力をとって推進ジャッキで前進し、最後部の地下構造
物は最前部の地下構造物から反力をとって牽引ジャッキ
によりPC鋼線等の牽引部材で到達坑側に引き込む。よ
って、前進のための反力は各地下構造物からとれるか
ら、反力をとるための反力壁が不要となる。
According to the first aspect of the present invention, the underground structure and the roof cylinder other than the rearmost portion take a reaction force from the rear underground structure and advance with the propulsion jack, and the rearmost underground structure. Takes a reaction force from the foreground underground structure and pulls it toward the arriving pit with a pulling member such as a PC steel wire by a pulling jack. Therefore, the reaction force for advancing can be obtained from each underground structure, so that there is no need for a reaction wall for taking the reaction force.

【0016】[0016]

【発明の実施の形態】以下、図面について本発明の実施
形態を詳細に説明する。図1は本発明の地下構造物の構
築方法の実施形態を示す第1工程の縦断側面図で、図
中、図4〜図6に示した従来例と同一の構成要素につい
ては同一の参照符号を付してある。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a vertical sectional side view of a first step showing an embodiment of a method for constructing an underground structure according to the present invention. In the figure, the same reference numerals are used for the same components as those in the conventional example shown in FIGS. Is attached.

【0017】本発明の構築方法も図1に示すように鉄道
等上部交通1の脇に土留め鋼矢板2を打設して、発進坑
3と到達坑4を築造し、該発進坑3内に圧入機を設置し
てこれでルーフ用筒体6を到達坑4に向けて圧入させ、
ルーフ用筒体6をコンクリート函体による地下構造物9
に先行させてルーフ用筒体6を推進するもので、コンク
リート函体による地下構造物9は複数に分割される。
As shown in FIG. 1, a construction method according to the present invention also includes a steel sheet pile 2 placed beside an upper traffic 1 such as a railway to construct a starting pit 3 and a reaching pit 4. And the roof cylinder 6 is press-fitted toward the reaching pit 4 with this,
An underground structure 9 composed of a roof cylinder 6 and a concrete box
The underground structure 9 made of a concrete box is divided into a plurality of parts.

【0018】そして、ルーフ用筒体5と最前部の地下構
造物9との間に推進ジヤッキ17を介在させるとともに、
複数の各地下構造物9の間にも推進ジャッキ18a,18b
を介在させ、最後部の地下構造物9に牽引ジャッキ19を
設け、その牽引部材である例えばPC鋼線20を定着具21
で最前部の地下構造物9に定着する。
A propulsion jack 17 is interposed between the roof cylinder 5 and the foreground underground structure 9.
The propulsion jacks 18a, 18b are also provided between the plurality of underground structures 9.
And a traction jack 19 is provided in the rearmost underground structure 9, and the traction member, for example, a PC steel wire 20 is fixed to the fixing tool 21.
Then, it is fixed to the underground structure 9 at the forefront.

【0019】以上のようにして地下構造物9を前進させ
るには、図2に示すように最前部の地下構造物9で反力
をとって推進ジャッキ17を伸長しルーフ用筒体6を前進
させ、次に最前部の地下構造物9を掘進させる。この場
合は、その後方の地下構造物9で反力をとって推進ジャ
ッキ18aを伸長し、推進ジャッキ17は縮める。
In order to advance the underground structure 9 as described above, as shown in FIG. 2, the foremost underground structure 9 takes a reaction force to extend the propulsion jack 17 and advance the roof cylinder 6 forward. Then, the foreground underground structure 9 is dug. In this case, the propulsion jack 18a is extended and the propulsion jack 17 is contracted by taking a reaction force by the underground structure 9 behind it.

【0020】最後部の地下構造物9については、最前部
の地下構造物9で反力をとって牽引ジャッキ19によりP
C鋼線20で到達坑4側に引き込む。
The rearmost underground structure 9 takes a reaction force at the foreground underground structure 9 to generate a P by a towing jack 19.
The steel wire 20 is drawn into the reaching shaft 4 side.

【0021】こうしてルーフ用筒体6及び複数の地下構
造物9をその後方の地下構造物9で反力をとりながら推
進ジャッキ17,18a…を順次伸長、縮める動作を繰り返
して、ルーフ用筒体6及び複数の地下構造物9を順次掘
進させる。
In this way, the roof cylinder 6 and the plurality of underground structures 9 are subjected to a reaction force with the rear underground structure 9 while the propulsion jacks 17, 18a. 6 and a plurality of underground structures 9 are sequentially excavated.

【0022】ルーフ用筒体6の1ピース分が到達坑4側
に出たならば、長さ方向で分割してそのまま横方向にず
らせて分離し、図3に示すように水平状態で吊り上げて
順次撤去する。
When one piece of the roof cylinder 6 comes out to the arrival shaft 4, it is divided in the length direction, separated as it is in the horizontal direction, and lifted in a horizontal state as shown in FIG. Remove sequentially.

【0023】そして、地下構造物9の先端が到達坑4に
達したならば、刃口11等を撤去し、適宜裏込めグラウト
を行って施工を完了する。
Then, when the tip of the underground structure 9 reaches the reaching pit 4, the cutting edge 11 and the like are removed, and backfill grout is performed as appropriate to complete the construction.

【0024】[0024]

【発明の効果】以上述べたように本発明の地下構造物の
構築方法は、ルーフ用筒体を先行させて後続の複数に分
割された地下構造物を掘進させる場合に、ルーフ用筒体
及び複数の地下構造物は、他の地下構造物で反力をとっ
て掘進するから、発進坑や到達坑に反力壁などを設置す
る必要がなく、発進坑や到達坑に十分なスペースが確保
できなくても施工が可能なものである。
As described above, the method of constructing an underground structure according to the present invention provides a method of constructing a roof cylinder and a plurality of subsequent subterranean structures which are preceded by a roof cylinder. Multiple underground structures are excavated by taking reaction force from other underground structures, so there is no need to install reaction walls at the start pit or the reach pit, and sufficient space is secured at the start pit or the reach pit Construction is possible even if it is not possible.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の地下構造物の構築方法の実施形態を示
す第1工程の縦断側面図である。
FIG. 1 is a vertical side view of a first step showing an embodiment of a method for constructing an underground structure according to the present invention.

【図2】本発明の地下構造物の構築方法の実施形態を示
す第2工程の縦断側面図である。
FIG. 2 is a vertical sectional side view of a second step showing an embodiment of the method for constructing an underground structure according to the present invention.

【図3】本発明の地下構造物の構築方法の実施形態を示
す第3工程の縦断側面図である。
FIG. 3 is a vertical sectional side view of a third step showing the embodiment of the method for constructing an underground structure according to the present invention.

【図4】従来の地下構造物の構築方法の第1工程の縦断
側面図である。
FIG. 4 is a longitudinal sectional side view of a first step of a conventional method of constructing an underground structure.

【図5】従来の地下構造物の構築方法の第2工程の縦断
側面図である。
FIG. 5 is a vertical sectional side view of a second step of the conventional method of constructing an underground structure.

【図6】従来の地下構造物の構築方法の第3工程の縦断
側面図である。
FIG. 6 is a vertical sectional side view of a third step of the conventional method of constructing an underground structure.

【図7】筒体の配列状態の一例を示す正面図である。FIG. 7 is a front view showing an example of an arrangement state of cylinders.

【符号の説明】[Explanation of symbols]

1…上部交通 2…土留め鋼矢
板 3…発進坑 4…到達坑 5…圧入機 6…ルーフ用筒
体 7…フリクションカッター 8…反力壁 9…地下構造物 10…推進ジャッ
キ 11…刃口 12…小ジャッキ 13…支持材 14…止め部材 15…受台 16…ストラット 17…推進ジャッキ 18a,18b…推
進ジャッキ 19…牽引ジャッキ 20…PC鋼線 21…定着具
DESCRIPTION OF SYMBOLS 1 ... Upper traffic 2 ... Earth retaining sheet pile 3 ... Starting pit 4 ... Destination pit 5 ... Press-fitting machine 6 ... Roof cylinder 7 ... Friction cutter 8 ... Reaction wall 9 ... Underground structure 10 ... Propulsion jack 11 ... Cutting edge 12 ... Small jack 13 ... Support material 14 ... Stopping member 15 ... Receiving stand 16 ... Strut 17 ... Propulsion jack 18a, 18b ... Propulsion jack 19 ... Towing jack 20 ... PC steel wire 21 ... Fixing tool

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.6,DB名) E21D 9/04 E21D 9/06 311──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 6 , DB name) E21D 9/04 E21D 9/06 311

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 ルーフ用筒体を発進坑から地中に水平方
向に圧入して並列させ、発進坑に残るルーフ用筒体の後
方に地下構造物を配設し、ルーフ用筒体を先行させて後
続の複数に分割された地下構造物を掘進させる地下構造
物の構築方法において、ルーフ用筒体と地下構造物の
間、及び複数の地下構造物間に推進ジャッキを介在さ
せ、最後部の地下構造物に牽引ジャッキを設け、PC鋼
線等の牽引部材を定着具で最前部の地下構造物に定着
し、最前部の地下構造物で反力をとってルーフ用筒体と
地下構造物の間の推進ジャッキを伸長してルーフ用筒体
を前進させ、次に最前部の地下構造物をその後方の地下
構造物で反力をとって地下構造物間の推進ジャッキを伸
長して掘進させ、その後、複数の地下構造物についても
それぞれの後方に位置する地下構造物で反力をとりなが
ら推進ジャッキの伸長により順次掘進させ、最後部の地
下構造物については、最前部の地下構造物で反力をとっ
て牽引ジャッキによりPC鋼線で到達坑側に引き込むこ
とで掘進させることを特徴とする地下構造物の構築方
法。
1. A roof cylinder is horizontally pressed into the ground from a starting pit to be parallel, and an underground structure is disposed behind a roof cylinder remaining in the starting pit. In the method of constructing an underground structure in which a plurality of divided underground structures are excavated, a propulsion jack is interposed between the roof cylinder and the underground structure, and between the plurality of underground structures, and A traction jack is installed in the underground structure of the above, and the traction member such as PC steel wire is fixed to the foreground underground structure with the fixing tool, and the foreground underground structure takes a reaction force and the roof cylinder and the underground structure The propulsion jack between the objects is extended to advance the roof cylinder, and then the foreground underground structure reacts with the underground structure behind it to extend the propulsion jack between the underground structures. Excavated, and then multiple underground structures are located behind each The underground structure is excavated sequentially by elongating the propulsion jack while taking a reaction force, and for the last underground structure, the reaction force is taken at the foreground underground structure and the tow jack is used to pull the PC steel wire to the arriving pit side. A method of constructing an underground structure, characterized in that the structure is excavated by being retracted.
JP7278715A 1995-10-26 1995-10-26 How to build underground structures Expired - Lifetime JP2808426B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7278715A JP2808426B2 (en) 1995-10-26 1995-10-26 How to build underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7278715A JP2808426B2 (en) 1995-10-26 1995-10-26 How to build underground structures

Publications (2)

Publication Number Publication Date
JPH09119285A JPH09119285A (en) 1997-05-06
JP2808426B2 true JP2808426B2 (en) 1998-10-08

Family

ID=17601189

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7278715A Expired - Lifetime JP2808426B2 (en) 1995-10-26 1995-10-26 How to build underground structures

Country Status (1)

Country Link
JP (1) JP2808426B2 (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3050385B2 (en) * 1989-07-21 2000-06-12 株式会社日立製作所 Electron gun for color picture tube
JP2670734B2 (en) * 1992-11-19 1997-10-29 植村技研工業株式会社 Protective construction method for box body propulsion method

Also Published As

Publication number Publication date
JPH09119285A (en) 1997-05-06

Similar Documents

Publication Publication Date Title
JP4317843B2 (en) Construction method for underground structures
JP2808426B2 (en) How to build underground structures
JP3382183B2 (en) Construction method for underground structure and roof cylinder used therefor
JP3074374B2 (en) How to build underground structures
JP4134089B2 (en) Construction method for underground structures
JP3887383B2 (en) Construction method for underground structures
JP3702265B2 (en) Roof subsidence prevention apparatus and subsidence prevention method in construction method of underground structure
JP2789523B2 (en) How to build underground structures
JP2670734B2 (en) Protective construction method for box body propulsion method
JP6441871B2 (en) Box roof deflection reduction method for box roof method
JPH06229187A (en) Constructing method of subsurface structure
JP3106302B2 (en) How to build underground structures
JP4220317B2 (en) Construction method for underground structures
JPH0642286A (en) Method and device for constructing underground structure
JP3598293B2 (en) Face protection method for construction of underground structures
JPH02272192A (en) Execution of underground construction
JP5394454B2 (en) Open shield method
JP2645683B2 (en) How to start the box
JP2565478B2 (en) Underground box promotion method
JPH0726407B2 (en) Construction method of large section underground structure
JPH0681878B2 (en) Construction method of underground structure
JPH09317374A (en) Method of construction of subsurface structure
JPH0759875B2 (en) Construction method of underground structure and propulsion device for roof cylinder
KR0181964B1 (en) Underground construction
JPH02261194A (en) Method of construction for underground structure and cylindrical body for roof

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080731

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090731

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100731

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100731

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110731

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130731

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130731

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140731

Year of fee payment: 16

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term