Sleeve wall balcony and construction method

Info

Publication number
JP2806276B2
JP2806276B2 JP25991894A JP25991894A JP2806276B2 JP 2806276 B2 JP2806276 B2 JP 2806276B2 JP 25991894 A JP25991894 A JP 25991894A JP 25991894 A JP25991894 A JP 25991894A JP 2806276 B2 JP2806276 B2 JP 2806276B2
Authority
JP
Japan
Prior art keywords
girder
sleeve wall
wall
sleeve
balcony
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP25991894A
Other languages
Japanese (ja)
Other versions
JPH08120768A (en
Inventor
雄一 安田
茂宏 北山
Original Assignee
三協アルミニウム工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 三協アルミニウム工業株式会社 filed Critical 三協アルミニウム工業株式会社
Priority to JP25991894A priority Critical patent/JP2806276B2/en
Publication of JPH08120768A publication Critical patent/JPH08120768A/en
Application granted granted Critical
Publication of JP2806276B2 publication Critical patent/JP2806276B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)
  • Steps, Ramps, And Handrails (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、建物の入隅部に構築さ
れる袖壁バルコニーに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a sleeve-wall balcony constructed at a corner of a building.

【0002】[0002]

【従来の技術】近年、建物の入隅部に設置された袖壁バ
ルコニーを有する建物が増えている。従来、このような
バルコニーとして、実開昭63−174201号のもの
のように、袖壁に付き当てる前桁の端部に入隅部方向へ
取付片が突出したブラケットを取付け、取付片に挿通し
たボルトを袖壁内側の柱に螺入して前桁を袖壁に固定す
るバルコニーが知られている。しかし、このものは、バ
ルコニーの自重及び積載荷重を前桁と柱の接続部及び袖
壁に対向する妻梁の基部の2点で支持しているため強度
が低いものである。
2. Description of the Related Art In recent years, buildings having sleeve-wall balconies installed at corners of buildings have increased. Conventionally, as such a balcony, a bracket having a mounting piece protruding in the direction of a corner is attached to an end of a front girder abutting on a sleeve wall, such as that of Japanese Utility Model Laid-Open No. 63-174201, and inserted through the mounting piece. A balcony is known in which a bolt is screwed into a pillar inside a sleeve wall to fix a front spar to the sleeve wall. However, this is low in strength because the weight of the balcony and the load on the balcony are supported at two points: the connection between the front spar and the column and the base of the girder beam facing the sleeve wall.

【0003】そこで、前桁の端部を袖壁に固定するほか
に、袖壁に沿って他の妻梁を配置し、この妻梁の先端と
前桁の端部を連結したバルコニーが提案されている。こ
のようなバルコニーを施工するには、袖壁の外面に桁固
定具を取付けた後、袖壁に沿って妻梁を配置し、次いで
桁の端部を桁固定具に固定すると共に妻梁の先端に連結
する。
Therefore, in addition to fixing the end of the front girder to the sleeve wall, another balcony has been proposed in which another girder is arranged along the sleeve wall and the tip of the girder is connected to the end of the front girder. ing. In order to construct such a balcony, a girder fixing device is attached to the outer surface of the sleeve wall, a girder beam is arranged along the sleeve wall, and then the ends of the girder are fixed to the girder fixing device and the girder fixing member is attached. Connect to the tip.

【0004】しかし、このものは、桁固定具の袖壁に対
する取り付け位置の位置決めが困難であり、外観を繕う
上から中空の桁の端部内に桁固定具を嵌合する構造の場
合、桁の両側に袖壁が配置されていると、桁を両袖間に
おいて水平に嵌め込むことができないので、桁の両端を
妻梁の先端に一致させて、しかも桁固定具を桁の内部に
嵌合するのは非常に難しく、このため、施工が面倒であ
って、桁の端部周壁に固定具挿入用の溝を形成するなど
の加工を施さなければならない。
However, in this structure, it is difficult to position the attachment position of the girder fixing device to the sleeve wall, and in the case of a structure in which the girder fixing device is fitted into the end of the hollow girder from above, the appearance of the girder is improved. If sleeve walls are arranged on both sides, the girder cannot be fitted horizontally between both sleeves, so both ends of the girder should be aligned with the ends of the girder beams, and the girder fixture should be fitted inside the girder. It is very difficult to do so, so the construction is troublesome, and it is necessary to perform processing such as forming a groove for inserting a fixture in the end peripheral wall of the girder.

【0005】[0005]

【発明が解決しようとする課題】本発明は、袖壁側にも
妻梁を有して頑丈であると共に妻梁および袖壁に対する
前桁の取付けが容易な袖壁バルコニーの提供を課題とす
る。
SUMMARY OF THE INVENTION It is an object of the present invention to provide a sleeve wall balcony which has a gable beam on the side of the sleeve wall, is sturdy, and can easily be attached to the girder and the girder to the sleeve wall. .

【0006】[0006]

【課題を達成するための手段】[Means for achieving the object]

〔方法〕建物の入隅部に設置するバルコニーに関する。
相対して配置された妻梁の少なくとも一方を袖壁側外壁
に固定する。妻梁の先端間に前桁を取り付ける。このと
き前桁の袖壁側端部に、袖壁に対する取付け部と前後方
向の突片を備えた固定金具を予め取り付けておく。固定
金具の突片を袖壁側妻梁の先端に係合させて前桁の袖壁
側を妻梁に仮置きしてから取付け部を袖壁に固定する。
[Method] Concerning balconies installed in the corners of buildings.
At least one of the facing beams is fixed to the outer wall on the sleeve wall side. Install the front spar between the ends of the girder. At this time, a fixing bracket having a mounting portion to the sleeve wall and a protruding piece in the front-rear direction is previously mounted on the end of the front girder on the side of the sleeve wall. The projecting piece of the fixing fitting is engaged with the tip of the girder on the sleeve wall side to temporarily place the sleeve wall side of the front girder on the girder beam, and then the mounting portion is fixed to the sleeve wall.

【0007】なお、少なくとも袖壁側の妻梁の先端部に
固定金具の突片が挿入されて係合する位置決め部が設け
られ、前桁を取り付ける時、固定金具の突片を袖壁側妻
梁の先端に挿入して位置決め部に係合させ、前桁の袖壁
側を妻梁に位置決めしてから取付け部を袖壁に固定する
ことがある。
A positioning portion is provided at least at the end of the girder beam on the side of the sleeve wall, into which the projection of the fixing bracket is inserted and engaged. When attaching the front spar, the projection of the fixing bracket is attached to the sleeve wall side. There is a case where the mounting portion is fixed to the sleeve wall after being inserted into the tip of the beam and engaged with the positioning portion, and positioning the sleeve wall side of the front girder on the end beam.

【0008】〔装置〕建物の入隅部に設置されたバルコ
ニーに関する。左右の妻梁が少なくとも一方は袖壁側外
壁に固定されて相対して配置される。左右の妻梁の先端
に前桁が取り付けられる。袖壁側妻梁の先端と前桁の袖
壁側端部とが固定金具で結合されると共に袖壁に固定さ
れる。固定金具は、袖壁に対する取付け部と前後方向の
突片および左右方向の前桁取付け部を一体に備え、固定
金具の前桁取付け部を前桁の先端部に固定し、突片を妻
梁の先端部形成された位置決め部に係合させ、取付け部
が袖壁側外壁に固定される。
[Device] The present invention relates to a balcony installed at a corner of a building. At least one of the right and left end beams is fixed to the outer wall on the side of the sleeve wall and arranged to face each other. Front girders are attached to the ends of the left and right girder beams. The front end of the side wall of the sleeve wall and the end of the front girder on the side of the sleeve wall are connected by a fixing metal and fixed to the sleeve wall. The fixing bracket is integrally provided with a mounting part to the sleeve wall, a front and rear projection, and a left and right front girder mounting part.The front girder mounting part of the fixing bracket is fixed to the front end of the front girder, and the protruding part is a girder beam. The mounting portion is fixed to the sleeve-wall-side outer wall by engaging with the positioning portion formed at the distal end of the sleeve.

【0009】[0009]

【作用】前桁の袖壁側端部に固定金具を装着して、前桁
の袖壁側端部の仮置きあるいは位置決めをする過程は、
建物の袖壁部における前桁の取付けを容易にする。妻梁
の少なくとも一方を建物の袖壁に配設し、前桁と妻梁と
外壁を固定金具で連結した構成は、バルコニーの自重及
び積載荷重を袖壁と前桁の接合部及び妻梁の基部の3点
もしくは4点で分散して支持する。
[Function] The process of temporarily fixing or positioning the end of the front girder on the sleeve wall side by attaching the fixing bracket to the end of the front girder on the side of the sleeve wall is as follows.
Facilitating the mounting of the front spar on the sleeve wall of the building. The structure in which at least one of the girder beams is arranged on the sleeve wall of the building, and the front girder, the girder beam and the outer wall are connected by fixing brackets, is to reduce the weight and load of the balcony by the joint between the sleeve wall and the front girder and the girder beam. It is dispersed and supported at three or four points on the base.

【0010】[0010]

【実施例】図3は、片側のみに袖壁2が位置する片袖タ
イプの袖壁バルコニー1を示す。袖壁バルコニー1は、
図1及び2に示すように、建物の外壁6から平行に室外
方向へ張り出される左右相対した妻梁3(a,b)と、
妻梁3(a,b)の先端間に架設される前桁4と、建物
の外壁6、左右の妻梁3(a,b)及び前桁4の内側に
張設される床板5を備える。
FIG. 3 shows a one-sleeved sleeve wall balcony 1 in which a sleeve wall 2 is located only on one side. The sleeve wall balcony 1
As shown in FIGS. 1 and 2, left and right opposed girder beams 3 (a, b) projecting in parallel from the outer wall 6 of the building in the outdoor direction,
It comprises a front girder 4 erected between the ends of the girder 3 (a, b), a building outer wall 6, left and right girder 3 (a, b) and a floor plate 5 stretched inside the front girder 4. .

【0011】妻梁3aは、その断面において、図2に示
すように、袖壁2の外面に沿う垂直壁7を有し、垂直壁
7の下端から水受け片8がバルコニー1の内周方向に水
平に張り出され、水受け片8の先端から上方に逆L形の
床板支持片9が立設されている。また、垂直壁7の内周
面上端から被覆材取り付けフランジ19が、内周面中間
部から位置決め部10がそれぞれ袖壁バルコニー1の内
周方向に向けて張り出されている。さらに、図1に示す
ように、妻梁3aの水受け片8の前桁4寄りにドレーン
11が設けられ、ドレーン11に図示しない樋が接続さ
れる。水受け片8の両端上面には、水受け片8と床板支
持片9と垂直壁7で構成される溝部を閉塞する目隠し板
35が取付けられている。
As shown in FIG. 2, the girder beam 3a has a vertical wall 7 along the outer surface of the sleeve wall 2, and a water receiving piece 8 extends from the lower end of the vertical wall 7 in the inner circumferential direction of the balcony 1. , And an inverted L-shaped floor plate support piece 9 is provided upright from the tip of the water receiving piece 8. A covering member mounting flange 19 extends from the upper end of the inner peripheral surface of the vertical wall 7, and a positioning portion 10 projects from the middle of the inner peripheral surface toward the inner peripheral direction of the sleeve wall balcony 1. Further, as shown in FIG. 1, a drain 11 is provided near the front spar 4 of the water receiving piece 8 of the end beam 3a, and a gutter (not shown) is connected to the drain 11. On the upper surfaces of both ends of the water receiving piece 8, blind plates 35 for closing a groove formed by the water receiving piece 8, the floor plate supporting piece 9 and the vertical wall 7 are attached.

【0012】外壁6の左右の妻梁3(a,b)の基端部
間に横架材12が架設され、一方の妻梁3aは、その垂
直壁7の適宜箇所において袖壁2に固定されると共に、
基端部が横架材12に固定されている。他方の妻梁3b
は基端部を横架材12に固定されて室外方向に突出して
いる。横架材12は、外壁6内に配置されている桁に取
り付けられる外壁当接壁13と、外壁当接壁13の上端
から室外方向下向きに張り出す傾斜庇14と、外壁当接
壁13の室外側面中間部に突設される梁支持片15とを
有し、傾斜庇14によって妻梁3(a,b)の被覆材取
り付けフランジ19の下面を支持し、梁支持片15の上
端で位置決め部10の下面を支持する。
A transverse member 12 is provided between the base ends of the left and right end beams 3 (a, b) of the outer wall 6, and one end beam 3 a is fixed to the sleeve wall 2 at an appropriate position of the vertical wall 7. As well as
The base end is fixed to the horizontal member 12. The other wife beam 3b
Has a base end fixed to the horizontal member 12 and protrudes in the outdoor direction. The horizontal member 12 includes an outer wall contact wall 13 attached to a girder disposed in the outer wall 6, an inclined eave 14 projecting downward from the upper end of the outer wall contact wall 13 in the outdoor direction, and an outer wall contact wall 13. A beam support piece 15 protruding from an intermediate portion of the outdoor side surface, and a lower surface of the covering material mounting flange 19 of the end beam 3 (a, b) is supported by the inclined eave 14 and positioned at an upper end of the beam support piece 15. The lower surface of the part 10 is supported.

【0013】前桁4は、断面略角型の中空材より成り、
その下端から室外方向にカバー取り付け部16が突設さ
れると共に、前桁4の室外側面を覆うカバー17の下端
がこのカバー取り付け部16の上面に載置され係止され
ており、前桁4の室内側面中間部に断面逆L形の床板係
止突起18が突設されている。また、前桁4の袖壁2側
の端部に固定金具21が取付けられている。固定金具2
1は、図4及び図5に示すように、袖壁2の外面に固定
される取り付け部22と、前桁4の端部内側に挿入固定
される前桁取付け部23と、袖壁側妻梁3aの先端部内
周に挿入される突片24を有する。
The front spar 4 is made of a hollow material having a substantially square cross section.
A cover mounting portion 16 projects from the lower end in the outdoor direction, and a lower end of a cover 17 that covers the outdoor side surface of the front spar 4 is placed and locked on the upper surface of the cover mounting portion 16. A floor plate engaging projection 18 having an inverted L-shaped cross section protrudes from the middle part of the indoor side surface. A fixing member 21 is attached to the end of the front girder 4 on the side of the sleeve wall 2. Fixture 2
As shown in FIGS. 4 and 5, reference numeral 1 denotes a mounting portion 22 fixed to the outer surface of the sleeve wall 2, a front girder mounting portion 23 inserted and fixed inside the end of the front girder 4, It has a protruding piece 24 inserted into the inner periphery of the distal end of the beam 3a.

【0014】前桁取付け部23は、前桁4の内周面の上
壁と側壁に沿うように断面略L形をなし、その水平部の
中央部にネジ孔25が穿設されると共に、水平部下面に
ネジ孔25と連通するナット26が固定されている。突
片24は、前桁取付け部23の垂直部の袖壁2寄り端縁
から室内方向に延び、図1、図2に示すように、妻梁3
aの垂直壁7内面に沿って被覆材取り付けフランジ19
と位置決め部10の間に挿入される。
The front spar attachment portion 23 has a substantially L-shaped cross section along the upper wall and the side wall of the inner peripheral surface of the front spar 4, and a screw hole 25 is formed in the center of the horizontal portion. A nut 26 communicating with the screw hole 25 is fixed to the lower surface of the horizontal portion. The protruding piece 24 extends from the vertical edge of the front girder mounting portion 23 toward the sleeve wall 2 toward the interior of the room, and as shown in FIGS.
a covering material mounting flange 19 along the inner surface of the vertical wall 7 of FIG.
And between the positioning part 10.

【0015】取付け部22は、前桁取付け部23の水平
部の袖壁2寄り端縁から上方に延び、その上端部と中間
部にそれぞれ固定孔27が穿設されている。また、取付
け部22と前桁取付け部23の交線の中央部に補強リブ
28が形成されている。すなわち、固定金具21は、袖
壁2に対する上下方向の取付け部22と前後方向の突片
24および左右方向の前桁取付け部23を一体に備えた
金具である。固定金具21は、図6に示すように、前桁
取付け部23を前桁4の袖壁側端部の内側に挿入して前
桁4の上壁と前桁取付け部23の水平部を重ね、前桁4
の上方から前桁取付け部23のネジ孔25及びナット2
6にボルト29を螺合して前桁4に取付ける。
The mounting portion 22 extends upward from an edge near the sleeve wall 2 of the horizontal portion of the front girder mounting portion 23, and has fixing holes 27 formed at its upper end portion and intermediate portion, respectively. A reinforcing rib 28 is formed at the center of the line of intersection between the mounting portion 22 and the front girder mounting portion 23. That is, the fixing fitting 21 is a fitting integrally provided with a vertically attaching portion 22 to the sleeve wall 2, a protruding piece 24 in the front and rear direction, and a front girder attaching portion 23 in the left and right direction. As shown in FIG. 6, the fixing bracket 21 inserts the front girder mounting portion 23 inside the end of the front girder 4 on the side of the sleeve wall, and overlaps the upper wall of the front girder 4 with the horizontal portion of the front girder mounting portion 23. , Front digit 4
Screw hole 25 and nut 2 of front spar attachment portion 23 from above
The bolt 29 is screwed into 6 and attached to the front spar 4.

【0016】符号20は手摺壁で(図1、図2)、他方
の妻梁3b及び前桁4の上面に適宜間隔毎に立設された
支柱30、支柱30の上端間に架設された笠木31、笠
木31の上面に適宜間隔毎に立設された上部支柱32お
よび上部支柱32の上端間に架設される手摺バー33と
で構成されている。手摺壁20には、図3に示すよう
に、必要に応じて支柱30の外面にサイディングボード
34が取付けられる。
Reference numeral 20 denotes a handrail wall (FIGS. 1 and 2), a support 30 erected on the upper surface of the other cross beam 3b and the front spar 4 at appropriate intervals, and a bridge mounted between upper ends of the support 30. An upper support 32 is provided on the upper surface of the cap 31 at appropriate intervals, and a handrail bar 33 is provided between the upper ends of the upper support 32. As shown in FIG. 3, a siding board 34 is attached to the outer surface of the support 30 as needed, as shown in FIG. 3.

【0017】この袖壁バルコニー1は次のように施工さ
れる。外壁6に横架材12を取り付け、横架材12の両
端部から室外方向に左右の妻梁3(a,b)を張り出
す。図1に示すように、妻梁3(a,b)の被覆材取り
付けフランジ19及び位置決め部10の下面が横架材1
2の傾斜庇14及び梁支持片15で支持され、横架材1
2の梁支持片15の下面に妻梁3の床板支持片9の先端
上面が当接されている。一方の妻梁3aは、その垂直壁
7が袖壁2の外面に当接されて固定される。
The sleeve wall balcony 1 is constructed as follows. The horizontal member 12 is attached to the outer wall 6, and the left and right end beams 3 (a, b) are extended from both ends of the horizontal member 12 in the outdoor direction. As shown in FIG. 1, the covering material mounting flange 19 of the end beam 3 (a, b) and the lower surface of the positioning portion 10 are
2 supported by the inclined eaves 14 and the beam support pieces 15,
The upper surface of the tip of the floor plate support piece 9 of the end beam 3 is in contact with the lower surface of the second beam support piece 15. The vertical wall 7 of one end beam 3a is fixed to the outer surface of the sleeve wall 2 in contact with the outer wall.

【0018】前桁4の袖壁2側の端部に固定金具21
が、前桁取付け部23を前桁4の内側に差し込み、その
水平部及び垂直部をそれぞれ前桁4の上壁及び室内側片
の内面に当接し、ボルト29を固定金具21のネジ孔2
5及びナット26に螺合して固定される。固定金具21
の取り付け片22は上方に向けられ、突片24を室内方
向に向けられる。
At the end of the front girder 4 on the side of the sleeve wall 2, a fixing bracket 21 is provided.
However, the front girder mounting part 23 is inserted into the inside of the front girder 4, the horizontal part and the vertical part abut on the upper wall of the front girder 4 and the inner surface of the indoor side piece, respectively, and the bolt 29 is screwed into the screw hole 2 of the fixing bracket 21.
5 and nut 26 to be fixed. Fixing bracket 21
The mounting piece 22 is directed upward, and the protruding piece 24 is directed toward the room.

【0019】前桁4を室内方向へ略水平移動してその両
端を左右の妻梁3(a,b)の先端に接近させ、固定金
具21の突片24をその下端面が袖壁側妻梁3aの位置
決め部10の上面に当接するように妻梁3aに先端から
挿入して仮置きする。同時に取り付け片22を袖壁2の
外面に当接する。固定金具21の取付け片22の固定孔
27から袖壁2の柱、貫等ににコーチねじ36を打ち込
み、前桁4を袖壁2に固定する。これにより、一方の妻
梁3aの先端と前桁4の袖壁側端部が結合され、かつ、
これらが袖壁2に固定される。
The front spar 4 is moved substantially horizontally in the room direction so that both ends thereof are close to the ends of the left and right beams 3 (a, b). The beam 3a is inserted into the end beam 3a from the tip so as to come into contact with the upper surface of the positioning portion 10 and temporarily placed. At the same time, the mounting piece 22 contacts the outer surface of the sleeve wall 2. The front spar 4 is fixed to the sleeve wall 2 by driving a coach screw 36 into a pillar, a pier or the like of the sleeve wall 2 from the fixing hole 27 of the mounting piece 22 of the fixing member 21. As a result, the tip of one end beam 3a and the end of the front girder 4 on the side of the sleeve wall are joined, and
These are fixed to the sleeve wall 2.

【0020】袖壁2と対向する側の端部において、前桁
4は壁に接合されないので、L形金物等を用いて前桁4
と妻梁3bを結合する。必要に応じて前桁4の端部内側
と妻梁3bの先端内側に嵌合される結合金具を用いるこ
とがある。前桁4と妻梁3(a,b)を組み立てたら、
妻梁3(a,b)の床板支持片9の先端部上面に床板5
の両側端縁を載置し、床板5の室外側端部の下面に形成
された突起を前桁4の床板係止突起18に係合する。次
に、図2に示すように、妻梁3(a,b)の被覆材取り
付けフランジ19の上面に帯状の被覆材37の一側端部
を載置し、妻梁3(a,b)と床板5の間の間隙を覆
う。最後に、前桁4及び他方の妻梁3bの上面に手摺壁
20を取付ける。
At the end on the side facing the sleeve wall 2, the front spar 4 is not joined to the wall.
And the girder beam 3b. If necessary, a coupling fitting fitted to the inside of the end of the front spar 4 and the inside of the tip of the end beam 3b may be used. After assembling the front girder 4 and the girder beam 3 (a, b),
The floor plate 5 is provided on the upper surface of the tip of the floor plate support piece 9 of the girder 3 (a, b).
And the projections formed on the lower surface of the outdoor end of the floor panel 5 are engaged with the floor panel locking projections 18 of the front spar 4. Next, as shown in FIG. 2, one end of the band-shaped covering material 37 is placed on the upper surface of the covering material mounting flange 19 of the girder 3 (a, b), and the girder 3 (a, b) is placed. And the gap between the floor plate 5. Finally, the handrail wall 20 is attached to the upper surface of the front beam 4 and the other end beam 3b.

【0021】また、両側に袖壁2が位置することとなる
両袖タイプの袖壁バルコニー1の場合は、左右の妻梁3
(a,b)を袖壁2に沿って配置し、前桁4の両端部に
固定金具21を用い、片袖壁2の場合と同様にして前桁
4の両端部を妻梁3(a,b)及び袖壁2に接合すれば
良い。なお、妻梁(a,b)及び前桁4の断面形状は上
記実施例に限定されるものではなく、妻梁3aの内側の
中間部に位置決め部を形成せず、型材よりなる妻梁3a
の下端のフランジに固定金具21の突片24を当接して
前桁4の位置決めを行うようにしても良い。固定金具2
1における前桁取付け部23は実施例のように挿入する
タイプではなく、前桁4の端部外面にボルト止め等で固
定するタイプであっても良い。
In the case of the double-sleeved sleeve wall balcony 1 in which the sleeve walls 2 are located on both sides, the left and right girder beams 3 are provided.
(A, b) are arranged along the sleeve wall 2 and both ends of the front spar 4 are fixed to the both ends of the front spar 4 in the same manner as in the case of the single sleeve wall 2. , B) and the sleeve wall 2. The cross-sectional shapes of the girder (a, b) and the front spar 4 are not limited to those in the above-described embodiment, and the positioning member is not formed in the middle part inside the girder 3a, and the girder 3a made of a shape member is used.
The positioning of the front spar 4 may be performed by abutting the protruding piece 24 of the fixture 21 on the flange at the lower end of the front spar. Fixture 2
The front spar mounting portion 23 in 1 is not a type to be inserted as in the embodiment, but may be a type to be fixed to the outer surface of the end of the front spar 4 by bolting or the like.

【0022】[0022]

【発明の効果】請求項1の構成によれば、袖壁バルコニ
ーを施工するとき、前桁の袖壁側端部を袖壁側妻梁の先
端に仮置きすることにより、前桁の荷重から解放されて
前桁の端部を袖壁に固定する作業を行えるので、施工が
容易であり、また、正確に行える。さらに、高所作業と
なっても危険が少なくなる。請求項2の構成によれば、
前桁を妻梁先端に仮置きすることで取付け位置も定まる
ので、施工がさらに容易に、かつ、正確になる。請求項
3の構成によれば、袖壁バルコニーの構築を簡単に行
え、また、袖壁バルコニーの自重及び積載荷重を袖壁と
前桁の取付け部及び妻梁の基部の3点もしくは4点に分
散して支持することができるので、バルコニーが頑丈で
安全性が高い。
According to the first aspect of the present invention, when a sleeve wall balcony is constructed, the end of the front girder on the side of the sleeve wall is temporarily placed at the tip of the girder on the sleeve wall, thereby reducing the load on the front girder. Since the work of fixing the end of the front spar to the sleeve wall can be performed after being released, the construction is easy and accurate. In addition, danger is reduced even when working at heights. According to the configuration of claim 2,
By temporarily placing the front girder at the tip of the girder beam, the mounting position is also determined, so that the construction becomes easier and more accurate. According to the configuration of claim 3, the construction of the sleeve wall balcony can be easily performed, and the own weight and the loading load of the sleeve wall balcony are reduced to three or four points at the attachment part of the sleeve wall and the front girder and at the base of the girder. Balcony is sturdy and secure because it can be dispersed and supported.

【0023】前桁を室内方向に水平移動して妻梁間に架
設することができるので、両側に袖壁がある場合にも施
工しやすい。また、前桁の端部に妻梁との接合用金具を
挿入するためのガイド溝等を形成する必要が無く、この
ため、バルコニーを構成する部材の加工が簡単で製造コ
ストを低減できる。
Since the front spar can be horizontally moved in the room direction and installed between the girder beams, it is easy to construct even when there are sleeve walls on both sides. In addition, there is no need to form a guide groove or the like at the end of the front girder for inserting a metal fitting for joining with the girder, and therefore, the members constituting the balcony can be easily processed and the manufacturing cost can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例を示すバルコニーの側断面図FIG. 1 is a side sectional view of a balcony showing an embodiment of the present invention.

【図2】図1のA−A線に沿った断面見通し図FIG. 2 is a sectional perspective view taken along line AA of FIG. 1;

【図3】本発明の実施例を示すバルコニーの正面図
(イ)、平面図(ロ)
FIG. 3 is a front view (a) and a plan view (b) of a balcony showing an embodiment of the present invention.

【図4】固定金具の側面図FIG. 4 is a side view of a fixing bracket.

【図5】固定金具の正面図FIG. 5 is a front view of a fixing bracket.

【図6】前桁に装着された固定金具の側面図FIG. 6 is a side view of a fixing bracket attached to the front spar.

【符号の簡単な説明】[Brief description of reference numerals]

1 バルコニー 2 袖壁 3(a,b) 妻梁 4 前桁 5 床板 6 外壁 7 垂直壁 8 水受け片 9 床板支持片 10 位置決め部 11 ドレーン 12 横架材 13 外壁当接壁 14 傾斜庇 15 梁支持片 16 カバー取り付け部 17 カバー 18 床板係止突起 19 被覆材取り付けフランジ 20 手摺壁 21 固定金具 22 取付け部 23 前桁取付け部 24 突片 25 ネジ孔 26 ナット 27 固定孔 28 補強用リブ 29 ボルト 30 支柱 31 笠木 32 上部支柱 33 手摺バー 34 サイディングボード 35 目隠し板 36 コーチねじ 37 被覆材 DESCRIPTION OF SYMBOLS 1 balcony 2 sleeve wall 3 (a, b) girder beam 4 front girder 5 floor board 6 outer wall 7 vertical wall 8 water receiving piece 9 floor board support piece 10 positioning part 11 drain 12 horizontal member 13 outer wall contact wall 14 inclined eaves 15 beam Supporting piece 16 Cover mounting portion 17 Cover 18 Floor plate locking projection 19 Coating material mounting flange 20 Handrail wall 21 Fixing bracket 22 Mounting portion 23 Front spar mounting portion 24 Protrusion piece 25 Screw hole 26 Nut 27 Fixing hole 28 Reinforcement rib 29 Bolt 30 Support 31 Kasagi 32 Upper support 33 Handrail bar 34 Siding board 35 Blind board 36 Coach screw 37 Coating material

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 建物の入隅部に設置するバルコニーに関
し、少なくとも一方を袖壁側外壁に固定し相対して配置
された妻梁の先端に前桁を取り付ける時、前桁の袖壁側
端部に袖壁に対する取付け部と前後方向の突片を備えた
固定金具を予め取り付けておき、突片を袖壁側妻梁の先
端に係合させて前桁の袖壁側を妻梁に仮置きしてから取
付け部を袖壁に固定することを特徴とした袖壁バルコニ
ーの施工方法。
1. A balcony installed at a corner of a building, wherein at least one of the balconies is fixed to an outer wall on a sleeve wall side and a front girder is attached to a tip of a girder beam arranged opposite to the sleeve wall side of the front girder. Attach the mounting part to the sleeve wall and the fixing bracket provided with a protrusion in the front and rear direction in advance, and engage the protrusion with the tip of the girder on the sleeve wall side to temporarily attach the sleeve wall side of the front girder to the girder beam. A method of constructing a balcony on a sleeve wall, wherein the mounting portion is fixed to a sleeve wall after being placed.
【請求項2】 少なくとも袖壁側の妻梁は先端部に、固
定金具の突片が挿入されて係合する位置決め部が設けら
れ、前桁を取り付ける時、固定金具の突片を袖壁側妻梁
の先端に挿入して位置決め部に係合させ、前桁の袖壁側
を妻梁に位置決めしてから取付け部を袖壁に固定するこ
とを特徴とした請求項1に記載の袖壁バルコニーの施工
方法。
2. A positioning part for inserting and engaging a projection of a fixing bracket is provided at at least a tip end of the end beam on the sleeve wall side, and when attaching a front spar, the projection of the fixing bracket is attached to the sleeve wall side. The sleeve wall according to claim 1, wherein the sleeve is inserted into the end of the girder to engage with the positioning part, and the sleeve wall side of the front girder is positioned on the girder, and then the mounting part is fixed to the sleeve wall. Balcony construction method.
【請求項3】 建物の入隅部に設置されたバルコニーで
あって、妻梁は左右のうち少なくとも一方は袖壁側外壁
に固定されて相対して配置されると共に左右の妻梁の先
端に前桁が取り付けられた構造を有し、袖壁側妻梁の先
端と前桁の袖壁側端部とが、袖壁に対する取付け部と前
後方向の突片および左右方向の前桁取付け部を一体に備
えた固定金具で、固定金具の前桁取付け部を前桁の先端
部に固定し、突片を妻梁の先端部形成された位置決め部
に係合させて結合され、取付け部が袖壁側外壁に固定さ
れて、妻梁の先端と前桁の袖壁側端部とが共に袖壁に固
定されていることを特徴とした袖壁バルコニー。
3. A balcony installed at an inside corner of a building, wherein at least one of the left and right girder beams is fixed to the outer wall on the side of the sleeve wall and disposed opposite to each other and at the tip of the left and right girder beams. The front girder has a structure attached, and the tip of the girder on the sleeve wall side and the end on the sleeve wall side of the front girder form a mounting portion with respect to the sleeve wall, a protrusion in the front-rear direction, and a front girder mounting portion in the horizontal direction. With the fixing bracket provided integrally, the front girder mounting part of the fixing bracket is fixed to the front end of the front girder, and the protruding piece is engaged with the positioning part formed at the front end of the girder beam and joined, and the mounting part is sleeved A sleeve-wall balcony fixed to the wall-side outer wall, wherein both the tip of the girder beam and the sleeve-wall-side end of the front girder are fixed to the sleeve wall.
JP25991894A 1994-10-25 1994-10-25 Sleeve wall balcony and construction method Expired - Fee Related JP2806276B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25991894A JP2806276B2 (en) 1994-10-25 1994-10-25 Sleeve wall balcony and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25991894A JP2806276B2 (en) 1994-10-25 1994-10-25 Sleeve wall balcony and construction method

Publications (2)

Publication Number Publication Date
JPH08120768A JPH08120768A (en) 1996-05-14
JP2806276B2 true JP2806276B2 (en) 1998-09-30

Family

ID=17340744

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25991894A Expired - Fee Related JP2806276B2 (en) 1994-10-25 1994-10-25 Sleeve wall balcony and construction method

Country Status (1)

Country Link
JP (1) JP2806276B2 (en)

Also Published As

Publication number Publication date
JPH08120768A (en) 1996-05-14

Similar Documents

Publication Publication Date Title
JP2806276B2 (en) Sleeve wall balcony and construction method
JPH0752820Y2 (en) Lightweight cellular concrete plate mounting structure
JPH08239928A (en) Non-scaffolding contruction method for exterior wall material
JP2557161B2 (en) Roof unit with parapet
JP2001065049A (en) Roof balcony unit
JP2614021B2 (en) Roof panel support structure at doorway
JP2561112Y2 (en) Drainage structure such as balcony
JPS5834882Y2 (en) Assembly structure of verandas, balconies, etc.
JP2603413Y2 (en) Balcony mounting structure
JPH0142596Y2 (en)
JPH0337320Y2 (en)
JPH0625540Y2 (en) Roof structure mounting structure
JP2705866B2 (en) Construction method of roof structure
JPH1072927A (en) Decorative structure for corner column
JP3201820B2 (en) Gable cover mounting structure for rooftop structure
JPH0625539Y2 (en) Roof structure mounting structure
JPH0519449Y2 (en)
JPH0643298Y2 (en) Roof mounting structure for attached structures
JPH0567740B2 (en)
JPH0615041Y2 (en) Balcony structure
JPH044103Y2 (en)
JP3037195B2 (en) Eave ceiling mounting structure
JP2504476Y2 (en) Handrail wall mounting structure
JPH0512411Y2 (en)
JPH06482Y2 (en) Balcony floor beam structure

Legal Events

Date Code Title Description
S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080724

Year of fee payment: 10

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090724

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100724

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100724

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110724

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120724

Year of fee payment: 14

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130724

Year of fee payment: 15

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130724

Year of fee payment: 15

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130724

Year of fee payment: 15

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130724

Year of fee payment: 15

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130724

Year of fee payment: 15

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140724

Year of fee payment: 16

LAPS Cancellation because of no payment of annual fees