JP2797274B2 - Shaft for propulsion method and its construction method - Google Patents
Shaft for propulsion method and its construction methodInfo
- Publication number
- JP2797274B2 JP2797274B2 JP9607996A JP9607996A JP2797274B2 JP 2797274 B2 JP2797274 B2 JP 2797274B2 JP 9607996 A JP9607996 A JP 9607996A JP 9607996 A JP9607996 A JP 9607996A JP 2797274 B2 JP2797274 B2 JP 2797274B2
- Authority
- JP
- Japan
- Prior art keywords
- shaft
- block
- nozzle unit
- propulsion
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Earth Drilling (AREA)
Description
【0001】[0001]
【発明が属する技術分野】 本発明は下水道工事など用
いられる推進工法において発進部や到達部に設けられる
立坑の構造とその施工方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a shaft provided at a starting portion and a reaching portion in a propulsion method used for sewerage work and the like, and a method of constructing the shaft.
【0002】[0002]
【従来の技術】 従来の推進工法で使用される立坑壁の
平面形状は円形状もしくは矩形状であった。2. Description of the Related Art A vertical shaft used in a conventional propulsion method has a circular or rectangular planar shape.
【0003】立坑に収容される推進機械の平面外郭形状
はおおむね細長いため、平面形状が矩形状の立坑では、
内部に無駄な空間を発生することなく推進機械を収容す
ることが可能である。また、壁面が平面なので削坑や推
進方向の決定が容易であり、推進管の発進側立坑として
用いる際には有利である。しかしながら、平面形状が矩
形状の立坑を推進管の到達側立坑として用いるときに
は、推進管が立坑のコーナー部に到達してしまう場合、
到達用開口の削孔に苦慮して作業能率が低下するという
問題があった。[0003] Since the planar outer shape of a propulsion machine housed in a shaft is generally elongated, a vertical shaft having a rectangular shape has
The propulsion machine can be accommodated without generating a useless space inside. Further, since the wall surface is flat, it is easy to determine the digging and the propulsion direction, which is advantageous when used as a starting shaft of the propulsion pipe. However, when a vertical shaft is used as the arrival shaft of the propulsion tube when the vertical shaft is used, when the propulsion tube reaches the corner of the shaft,
There is a problem that the working efficiency is reduced due to difficulty in drilling the access opening.
【0004】 平面形状が円形状の立坑では、円形の持
つ等方性から推進管の到達自由度は高い。しかしなが
ら、細長い推進機械を収容するためには立坑の半径を大
きく設定する必要があるため、推進機械の収容や作業自
体には不必要な無駄空間を生じてしまう。また、矩形状
の立坑に比べて作業占有スペース幅が広くなるため、狭
い道路等においては最悪の場合、交通遮断等の交通規制
を行なう必要が生じる。In a shaft having a circular planar shape, the propulsion pipe has a high degree of freedom of arrival because of the circular isotropy. However, in order to accommodate the elongated propulsion machine, it is necessary to set the radius of the shaft to be large, so that unnecessary waste space is generated for accommodating the propulsion machine and for the operation itself. In addition, since the work occupied space width is wider than that of a rectangular shaft, in the worst case on narrow roads and the like, it is necessary to restrict traffic such as blocking traffic.
【0005】 油圧ジャッキを搭載した圧入装置によっ
て立坑壁ブロックを地中に圧入し、所要段数に建て込む
ようにした従来の立坑施工方法では、土質状況により立
坑壁ブロックの圧入が不可能となった場合には、別途用
意した高圧流体の噴射設備やオーガー等の機械によって
固い地盤を先行掘削する必要があるが、これら機械の準
備や段取りに相当の時間がとられ、全体の工期が長くな
るという問題がある。In a conventional shaft construction method in which a shaft block is pressed into the ground by a press-in device equipped with a hydraulic jack and is built at a required number of steps, it is impossible to press-fit the shaft block due to soil conditions. In such cases, it is necessary to excavate hard ground in advance using a machine such as a high-pressure fluid injection facility or auger prepared separately, but it takes considerable time to prepare and set up these machines, and the overall construction period will be longer There's a problem.
【0006】[0006]
【発明が解決しようとする課題】 したがって本発明の
目的は、作業スペース幅を縮小でき、推進管の発進側立
坑と到達側立坑のいずれにも好適な推進工法用立坑と、
必要に応じて高圧流体を直ちに噴射できるため、土質状
況に応じて立坑壁ブロックの圧入を作業能率良く行なえ
る立坑施工方法を提供することにある。SUMMARY OF THE INVENTION Accordingly, an object of the present invention is to provide a propulsion method vertical shaft which can reduce the working space width and is suitable for both a starting shaft and a reaching shaft of a propulsion pipe.
An object of the present invention is to provide a shaft construction method capable of efficiently injecting a shaft wall block according to a soil condition because a high-pressure fluid can be immediately injected as needed.
【0007】[0007]
【課題を解決するための手段】 本発明の推進工法用立
坑は、矩形の一辺が円弧で置き換えられた平面形状が中
空蒲鉾型の立坑壁ブロック1,2を所要段数に積み上げ
て築造したものである。Means for Solving the Problems The shaft for propulsion method of the present invention is constructed by stacking hollow shaft-shaped shaft blocks 1 and 2 in a plane shape in which one side of a rectangle is replaced by an arc into a required number of steps. is there.
【0008】推進工法に使用する機械設備は、矩形と円
弧で合成された水平断面が中空蒲鉾型の細長い立坑底部
内に無駄な空間を生じさせずに収容される。この立坑を
発進側立坑として用いる場合には、最下部の立坑壁ブロ
ック1の矩形側壁部分10の3面が発進用開口の削孔部
位として任意に選択され、円弧側壁部分9には削孔され
ない。到達側立坑として用いる場合には、最下部の立坑
壁ブロック1の円弧側壁部分9が推進管の接続用開口の
削孔部位として利用され、矩形側壁部分10の3面やコ
ーナー部には削孔されない。中継点の立坑として用いる
場合には、円弧側壁部分9と矩形側壁部分10がそれぞ
れ到達用と発進用に削孔される。[0008] The mechanical equipment used for the propulsion method is accommodated in the hollow bottom of the elongate shaft with a horizontal section composed of a rectangle and an arc without creating a useless space. When this shaft is used as the starting side shaft, three surfaces of the rectangular side wall portion 10 of the lowermost shaft wall block 1 are arbitrarily selected as drilling portions of the opening for starting, and the arc side wall portion 9 is not drilled. . When used as the arrival shaft, the arc-shaped side wall portion 9 of the lowermost shaft wall block 1 is used as a hole for drilling the connection opening of the propulsion pipe, and holes are drilled on three surfaces and corners of the rectangular side wall portion 10. Not done. When used as a vertical shaft at a junction point, the arc side wall portion 9 and the rectangular side wall portion 10 are drilled for reaching and starting, respectively.
【0009】本発明2の施工方法では、矩形の一辺が円
弧で置き換えられた平面形状が中空蒲鉾型の立坑壁ブロ
ック1,2は地中に順次圧入されて所要段数に建て込ま
れる。最下部の立坑壁ブロック1の下面側には予めノズ
ルユニット3を設けてあり、立坑壁ブロック1,2の壁
内部に予め設けた配管6,7または立坑壁ブロック1,
2の内側空間に予め設けた配管8は、ノズルユニット3
の内部配管5に連絡している。固い地盤に打ち当たって
立坑壁ブロック1,2の圧入抵抗が過大になったり、圧
入が不可能になった場合には、上記配管より供給した高
圧流体をノズルユニット3のノズル4から土質状況に応
じて適時噴射することによって地盤を軟化させ、立坑壁
ブロック1,2の圧入作業を続行する。In the construction method according to the second aspect of the present invention, the pit wall blocks 1 and 2 having a hollow shape of a hollow kamaboko with one side of a rectangle replaced by an arc are sequentially pressed into the ground and built into a required number of steps. A nozzle unit 3 is provided on the lower surface side of the lowermost shaft wall block 1 in advance, and the pipes 6 and 7 or the shaft wall block 1 provided beforehand inside the walls of the shaft walls 1 and 2 are provided.
The pipe 8 previously provided in the inner space of the nozzle unit 3
Is connected to the internal piping 5. In the case where the press-in resistance of the shaft wall blocks 1 and 2 becomes excessive due to hit against the hard ground or the press-in becomes impossible, the high-pressure fluid supplied from the above-mentioned pipe is changed from the nozzle 4 of the nozzle unit 3 to the soil condition. The ground is softened by timely injection in response thereto, and the press-fitting work of the shaft wall blocks 1 and 2 is continued.
【0010】最下部の立坑壁ブロック1の矩形側壁部分
10に予め発進用開口18を設けて置き、土砂が流入し
ないように該開口18を閉塞した状態で圧入作業を行な
い、全段の圧入完了後に該開口18の閉塞を解くように
すれば、遅滞なく推進工法を開始することができる。[0010] A starting opening 18 is provided in advance in the rectangular side wall portion 10 of the lowermost shaft wall block 1, and press-fitting is performed with the opening 18 closed so that earth and sand do not flow in. If the blockage of the opening 18 is later released, the propulsion method can be started without delay.
【0011】[0011]
【発明の実施の形態】 立坑壁ブロック1,2は基本的
には鉄筋コンクリート製であるが、最下部の立坑壁ブロ
ック1については発進用開口や到達用開口の削孔作業を
容易にするため、削孔対象の側壁下半部の鉄筋数を減ら
すか鉄筋を省略することがある。このように鉄筋を減数
または省略した場合には、立坑壁ブロック1の側壁上半
部の内面に補強用鉄板25を添接固定するのが望まし
い。高圧流体の供給用配管6,7を立坑壁ブロック1,
2の側壁内部に設けるときには、図1に示したように発
進用開口や到達用開口の削孔の支障とならないようにコ
ーナー部に配置するのが望ましい。BEST MODE FOR CARRYING OUT THE INVENTION The shaft shaft blocks 1 and 2 are basically made of reinforced concrete. However, the shaft shaft block 1 at the lowermost portion is formed in order to facilitate the work of drilling a starting opening and a reaching opening. The number of reinforcing bars in the lower half of the side wall to be drilled may be reduced or the reinforcing bars may be omitted. When the reinforcing bars are reduced or omitted as described above, it is desirable that the reinforcing iron plate 25 be attached and fixed to the inner surface of the upper half of the side wall of the shaft wall block 1. The high pressure fluid supply pipes 6 and 7 are
When it is provided inside the side wall 2, it is desirable to dispose it at the corner so as not to hinder the drilling of the starting opening and the reaching opening as shown in FIG.
【0012】立坑壁ブロック1,2の圧入作業は、図3
2と図33に示したように4基の油圧ジャッキ44を搭
載した圧入装置13によって行なわれる。最下部の立坑
壁ブロック1を地上の所定位置に設置した圧入装置13
によって地盤に圧入し、立坑壁ブロック1の内側空間の
土砂を所定深さまで掘削する。この立坑壁ブロック1に
順次上段側の立坑壁ブロック2を積み重ね、圧入装置1
3によって一体的に圧入し、立坑壁ブロック1,22の
内部空間の土砂を掘削する。この圧入・掘削作業を繰り
返すことによって所要深さの立坑が築造されるのである
が、地盤の土質状況によってはノズルユニット3から高
圧流体を適時噴射して、圧入進行方向の地盤を軟化させ
る。高圧流体としては、高圧水や圧搾空気、泥水スラリ
ー等が使用される。The press-fitting of the shaft shaft blocks 1 and 2 is performed as shown in FIG.
As shown in FIGS. 2 and 33, this is performed by the press-fitting device 13 equipped with four hydraulic jacks 44. A press-fitting device 13 in which the lowermost shaft wall block 1 is installed at a predetermined position on the ground
To excavate earth and sand in the inner space of the shaft wall block 1 to a predetermined depth. The shaft shaft block 2 on the upper stage side is sequentially stacked on the shaft wall block 1 and the press-fitting device 1
3 to excavate earth and sand in the internal space of the shaft wall blocks 1 and 22 integrally. By repeating the press-in and excavation work, a shaft having a required depth is built. However, depending on the soil condition of the ground, high-pressure fluid is injected from the nozzle unit 3 as needed to soften the ground in the press-in progress direction. As the high-pressure fluid, high-pressure water, compressed air, mud slurry, or the like is used.
【0013】全ての立坑壁ブロック1,2が垂直方向に
連続して圧入された後、コンクリートの打設によって底
版14が形成され、立坑壁ブロック2の内側面には必要
に応じてステップ19が設置される。矩形側壁部分10
に推進工法の発進用開口が削孔され、円弧側壁部分9に
到達用開口が削孔され、削孔によるコンクリート砕片は
立坑底部から運び上げられる。After all the pit wall blocks 1 and 2 have been successively press-fitted in the vertical direction, the bottom slab 14 is formed by casting concrete, and a step 19 is provided on the inner surface of the pit wall block 2 as necessary. Will be installed. Rectangular side wall part 10
The starting opening of the propulsion method is drilled, and the reaching opening is drilled in the arc side wall portion 9, and concrete crushed by the drilling is carried from the bottom of the shaft.
【0014】[0014]
【実施例】 図1から図12に示した実施例では、立坑
壁ブロック1,2は正方形の一片を半円で置き換えた平
面形状を有する筒状の鉄筋コンクリート部材であり、円
弧側壁部分9,11と矩形側壁部分10,12とで構成
されている。立坑壁ブロック1,2の上面には接合用凹
部31が設けられており、下面には該凹部31と係合す
る接合用凸部31が設けられている。ノズルユニット3
の内部配管5に連絡する配管6は、立坑壁ブロック1の
肉厚内に内蔵して設けられ、該配管6に連絡する配管7
が立坑壁ブロック2の肉厚内に内蔵されている。矩形側
壁部分10,12の配管6,7は発進用開口の削孔に干
渉しないようにコーナー部に設けられている。圧入中に
固い地盤に当たったときには、最上段の立坑壁ブロック
2の配管7に接続された耐圧ホースから高圧水や圧搾空
気などが供給される。In the embodiment shown in FIGS. 1 to 12, the vertical shaft wall blocks 1 and 2 are cylindrical reinforced concrete members having a planar shape in which a piece of a square is replaced by a semicircle, and arc side wall portions 9 and 11 are shown. And rectangular side wall portions 10 and 12. A joining recess 31 is provided on the upper surface of the shaft wall blocks 1 and 2, and a joining protrusion 31 engaging with the recess 31 is provided on the lower surface. Nozzle unit 3
A pipe 6 communicating with the internal pipe 5 is provided so as to be built in the wall thickness of the vertical shaft wall block 1, and a pipe 7 communicating with the pipe 6 is provided.
Is built in the wall thickness of the shaft wall block 2. The pipes 6, 7 of the rectangular side wall portions 10, 12 are provided at the corners so as not to interfere with the drilling of the starting opening. When it hits the hard ground during the press-fitting, high-pressure water, compressed air or the like is supplied from a pressure-resistant hose connected to the pipe 7 of the shaft shaft block 2 at the top.
【0015】立坑壁ブロック1,2の矩形側壁部分1
0,12には、U字棒形のステップ19の取付用インサ
ート20が埋め込まれ、立坑壁ブロック1,2をクレー
ン等による吊上げ孔21が設けられている。また、最下
部の立坑壁ブロック1の矩形側壁部分10の3面のうち
円弧側壁部分9に対面する面には、推進管の発進用開口
18が内外に貫通して予め設けられている。該開口18
には圧入作業時に土砂等が侵入するのを防止するために
発泡スチロール板26が詰め込まれ、外壁面には開口1
8を被覆するように薄鉄板25が貼り付けられている。
推進工法の開始時に推進管で発泡スチロール板26と薄
鉄板25を突き破る。The rectangular side wall portion 1 of the shaft wall blocks 1 and 2
A mounting insert 20 of a U-shaped step 19 is buried in 0 and 12, and a lifting hole 21 for lifting the vertical shaft wall blocks 1 and 2 by a crane or the like is provided. In addition, a starting opening 18 of a propulsion pipe is provided in advance on a surface facing the arc side wall portion 9 among three surfaces of the rectangular side wall portion 10 of the lowermost shaft wall block 1. The opening 18
Is filled with a styrofoam plate 26 to prevent earth and sand from entering during the press-fitting operation, and an opening 1 is formed in the outer wall surface.
8 is covered with a thin iron plate 25.
At the start of the propulsion method, the styrofoam plate 26 and the thin iron plate 25 are pierced by a propulsion tube.
【0016】ノズルユニット3は鋼材を溶接して一体形
成されている。ノズルユニット3は最下部の立坑壁ブロ
ック1の下面側に嵌め込み装着され、ノズルユニット3
の全周にわたって形成されたノズル4は、圧入刃先とな
るように垂直断面が直角三角形になっている。ノズル4
の内部には適所に透孔を有する配管5が挿入されてお
り、ノズル4の内向き斜面壁に高圧流体の噴出孔22が
適当な間隔を置いて設けられている。また、配管5の入
口管部23は立坑壁ブロック1の内蔵配管6に対応する
位置に設けられている。ノズルユニット3には鋼材製の
底版支持部15が設けられており、既製底版14が該底
版支持部15上に設置されている。The nozzle unit 3 is integrally formed by welding a steel material. The nozzle unit 3 is fitted and mounted on the lower surface side of the lowermost shaft wall block 1.
The nozzle 4 formed over the entire circumference has a right-angled triangular cross section so as to be a press-fitting blade. Nozzle 4
A pipe 5 having a through-hole is inserted at an appropriate position inside the inside of the nozzle 4, and a high-pressure fluid ejection hole 22 is provided at an appropriate interval on an inward slope wall of the nozzle 4. The inlet pipe 23 of the pipe 5 is provided at a position corresponding to the built-in pipe 6 of the shaft wall block 1. The nozzle unit 3 is provided with a bottom plate support 15 made of steel, and a ready-made bottom plate 14 is installed on the bottom plate support 15.
【0017】図13から図24に示した別の実施例で
は、立坑壁スブロック1,2は前記実施例における配管
6,7は内蔵されていない。ノズルユニット3の配管5
の入口管部23に接続された配管8は、図15に示した
ように立坑壁ブロック1,2の内側空間に露出させてあ
る。高圧流体の供給装置からの耐圧ホースは該配管8に
接続される。最下部の立坑壁ブロック1の側壁下部に底
版用鉄筋16が全周にわたって埋め込まれている。これ
らの鉄筋16は立坑壁ブロックの圧入・掘削作業後に図
31に示したように水平に掘り起こされる。図30に示
したように該鉄筋16には鉄筋27,鉄筋28が交差方
向に渡され、これらの鉄筋16,27,28を包み込む
ようにコンクリートが打設されて立坑の底版14が形成
される。鉄筋16の掘り起こしによって内壁面に生じた
溝部は片面粘着テープを貼って塞ぎ、底版形成時のコン
クリートの流出を防止する。底版14と立坑壁ブロック
1は鉄筋16を介して一体に連結され、強固な立坑が築
造される。In another embodiment shown in FIGS. 13 to 24, the shaft blocks 1 and 2 do not include the pipes 6 and 7 in the above embodiment. Piping 5 of nozzle unit 3
The pipe 8 connected to the inlet pipe section 23 is exposed to the inner space of the pit wall blocks 1 and 2 as shown in FIG. A pressure-resistant hose from the high-pressure fluid supply device is connected to the pipe 8. In the lower part of the side wall of the lowermost shaft wall block 1, a reinforcing bar 16 for a bottom plate is embedded all around. These rebars 16 are excavated horizontally as shown in FIG. 31 after the press-in and excavation work of the shaft wall block. As shown in FIG. 30, a reinforcing bar 27 and a reinforcing bar 28 are passed over the reinforcing bar 16 in a crossing direction, and concrete is poured into the reinforcing bar 16 so as to wrap the reinforcing bars 16, 27 and 28 to form a bottom plate 14 of a shaft. . The groove formed on the inner wall surface by excavating the reinforcing bar 16 is covered with a single-sided adhesive tape to prevent the concrete from flowing out when the bottom slab is formed. The bottom slab 14 and the shaft wall block 1 are integrally connected via a reinforcing bar 16, and a strong shaft is built.
【0018】本実施例では、底版14の打設前に立坑壁
ブロック1の底部にベースコンクリート29を打設し、
該ベースコンクリート29の硬化後に推進機械を設置し
て推進工法を実施する。ノズルユニット3は複数のピー
スに分割して鋳物で作成されているため、短期間に大量
生産でき、コストの節減が可能である。また、ピース毎
にコンパクトに保管されるので、ストックスペースの有
効利用が可能である。各ピースはボルト24によって接
合され、溶接歪み等が生じないため、立坑壁ブロック1
への装着作業が寸法不適合の問題を起こすことなく的確
かつ迅速に行なえる。ノズルユニット3の上部には、溝
型鋼材で作成された支持段部3aが設けられ、立坑壁ブ
ロック1の接合用凸部32が係合するようになってい
る。その他の構成は前記した実施例と同様である。In this embodiment, a base concrete 29 is cast on the bottom of the shaft wall block 1 before the bottom slab 14 is cast.
After the base concrete 29 has hardened, a propulsion machine is installed to perform a propulsion method. Since the nozzle unit 3 is divided into a plurality of pieces and is made of a casting, it can be mass-produced in a short time and cost can be reduced. Also, since the pieces are stored compactly, the stock space can be effectively used. Since the pieces are joined by bolts 24 and welding distortion and the like do not occur, the shaft shaft block 1
Work can be performed accurately and quickly without causing dimensional mismatch problems. At the upper part of the nozzle unit 3, a supporting step 3 a made of a channel-shaped steel material is provided, and the joining projection 32 of the shaft wall block 1 is engaged. Other configurations are the same as those of the above-described embodiment.
【0019】前記各実施例において、最上段の立坑壁ブ
ロック2の上面開口部は、図25から図27に示した鉄
筋コンクリート製の床版30によって閉塞される。床版
30の底面には立坑壁ブロック2の接合用凹部31と係
合する接合用凸部33を設けてあり、上面にはクレーン
による吊上げ孔45が設けられている。円形の出入り口
34は縦方向に貫通しており、出入り口34の内壁面に
はステップ19が設けられている。出入り口34上端周
辺部には円形段差部36が設けられており、図13に示
したように高さ調整リング35を利用する際には、該段
差部36に高さ調整リング35の底面突起が嵌め込まれ
る。高さ調整リング35の上面には蓋ユニット40が設
置される。In each of the above embodiments, the upper opening of the shaft shaft block 2 at the top is closed by the reinforced concrete floor slab 30 shown in FIGS. The bottom surface of the floor slab 30 is provided with a joining projection 33 that engages with the joining recess 31 of the shaft wall block 2, and a lifting hole 45 by a crane is provided on the top surface. The circular entrance 34 penetrates in the vertical direction, and a step 19 is provided on the inner wall surface of the entrance 34. A circular step 36 is provided around the upper end of the entrance 34, and when the height adjustment ring 35 is used as shown in FIG. 13, the bottom projection of the height adjustment ring 35 is attached to the step 36. It is fitted. On the upper surface of the height adjustment ring 35, a lid unit 40 is installed.
【0020】図28に示した斜壁用床版37では、床版
上面には環状溝部39が出入り口34に対して偏心して
設けられ、図3に示したように斜壁ブロック38を利用
する際には該環状溝部39に斜壁ブロック38の下面突
起が嵌め込まれる。この嵌め込みに際しては適当な材料
によってシール処理がなされる。斜壁ブロック38の上
面には高さ調整リング35または蓋ユニット40が設置
される。図29に示した床版41にも同様な環状溝部4
2が設けられている。いずれの実施例においても、図3
4に示したように、立坑壁ブロック1,2同士または立
坑壁ブロック2と床版30,37,41との接合面には
止水パッキング43をはさみ込み、地下水や地表面から
の浸透水の侵入を防止する。In the swash wall floor slab 37 shown in FIG. 28, an annular groove 39 is eccentrically provided on the upper surface of the slab with respect to the entrance 34, and when the swash wall block 38 is used as shown in FIG. The lower surface projection of the inclined wall block 38 is fitted into the annular groove 39. At the time of this fitting, a sealing process is performed with an appropriate material. A height adjusting ring 35 or a lid unit 40 is installed on the upper surface of the sloping wall block 38. A similar annular groove 4 is also provided on the floor slab 41 shown in FIG.
2 are provided. In each of the embodiments, FIG.
As shown in FIG. 4, a waterproof packing 43 is inserted between the shaft wall blocks 1 and 2 or the joint surface between the shaft wall blocks 2 and the floor slabs 30, 37 and 41, and groundwater or seepage water from the ground surface is inserted. Prevent intrusion.
【0021】[0021]
【発明の効果】 請求項1の推進工法用立坑は、矩形の
一辺が円弧で置き換えられた平面形状が中空蒲鉾型の立
坑壁1,2を所要段数に積み上げて築造されるものであ
り、矩形と円形の合成によって全体として細長い形状を
しているため、おおむね細長い推進機械を収容する際に
無駄な空間が生じないとともに、立坑壁ブロック1,2
の幅を可及的に小さくできるため、作業スペース幅が小
さくなり、交通遮断などを行わずに狭い場所での施工も
可能である。According to the first aspect of the present invention, the shaft for propulsion method is constructed by stacking the hollow shaft-shaped shaft walls 1 and 2 to a required number of steps, where one side of the rectangle is replaced by an arc, and And a circular shape, the overall shape is elongated, so that no wasteful space is generated when accommodating the elongated propulsion machine, and the shaft wall blocks 1 and 2 are formed.
Since the width of the work space can be made as small as possible, the width of the work space becomes small, and construction in a narrow place is possible without interrupting traffic.
【0022】 さらに、矩形側壁部分10,12が円弧
側壁部分9,11に接線上で接続されているため、円弧
側壁部分9,11または円弧側壁部分9,11とそれに
隣接した矩形側壁部分10,12を推進管の到達面とし
て使用すれば、推進方向の自由度が広く確保されること
になり、また、到達面に角部がないので到達管の削孔作
業性が良くなる。Further, since the rectangular side wall portions 10 and 12 are tangentially connected to the arc side wall portions 9 and 11, the arc side wall portions 9 and 11 or the arc side wall portions 9 and 11 and the rectangular side wall portions 10 and 11 adjacent thereto are formed. If 12 is used as the arrival surface of the propulsion pipe, a wide degree of freedom in the propulsion direction can be ensured, and since the arrival surface has no corners, the workability of drilling the arrival pipe is improved.
【0023】請求項2の推進工法用立坑の施工方法で
は、立坑壁ベースブロック1の下部にノズルユニット3
を予め設けてあり、ノズルユニット3の内部配管5に連
絡する配管6,7を立坑壁ベースブロック1と立坑壁中
間ブロック2の各内部もしくはそれらの内側空間に設け
てあるため、固い地盤に打ち当たって圧入が不可能にな
ったときには、直ちにノズルユニット3のノズル4から
高圧流体を噴射して地盤を軟化させることができ、圧入
作業を遅滞なく続行することができる。高圧流体の噴射
設備やオーガー等を別途用意して先行掘削する必要がな
く、その準備や段取りに時間を取られることがないた
め、工事が中断することがなく進められ、工期の短縮が
可能である。According to the construction method of the shaft for the propulsion method of the second aspect, the nozzle unit 3 is provided below the shaft block base block 1.
Since the pipes 6 and 7 connected to the internal pipe 5 of the nozzle unit 3 are provided in each of the inside of the vertical shaft base block 1 and the vertical shaft intermediate block 2 or in the space inside them, the ground 6 When the press-fitting becomes impossible, the high-pressure fluid can be immediately injected from the nozzle 4 of the nozzle unit 3 to soften the ground, and the press-fitting operation can be continued without delay. There is no need to separately prepare high-pressure fluid injection equipment or augers, etc., and perform pre-drilling, and there is no time required for preparation and setup, so construction can be proceeded without interruption and the construction period can be shortened. is there.
【0024】請求項3の推進工法用立坑の施工方法で
は、立坑壁ベースブロック1の矩形側壁部分10に予め
発進用開口18を設け、土砂が流入しないように該開口
18を閉塞した状態で圧入作業を行ない、推進工法の開
始時に該開口18の閉塞を解くようにしたので、立坑壁
中間ブロック2の建て込み後、直ちに推進工法に着手す
ることができて工期の短縮が可能であるとともに、発進
用開口の削孔時に生じるコンクリート破片を運び上げる
手間が省ける。According to the third aspect of the present invention, a starting opening 18 is provided in the rectangular side wall portion 10 of the shaft wall base block 1 in advance, and the opening 18 is closed with the opening 18 closed so that earth and sand do not flow. Since the work was performed and the opening 18 was unblocked at the start of the propulsion method, the propulsion method could be started immediately after the erection wall intermediate block 2 was erected, and the construction period could be shortened. This eliminates the need to carry concrete debris generated when drilling the starting opening.
【図1】 本発明の一実施例に係る推進工法用立坑の分
解斜視図である。FIG. 1 is an exploded perspective view of a shaft for a propulsion method according to an embodiment of the present invention.
【図2】 図1の立坑の平面図である。FIG. 2 is a plan view of the shaft of FIG.
【図3】 図2のA−A線断面図である。FIG. 3 is a sectional view taken along line AA of FIG. 2;
【図4】 図2のB−B線断面図である。FIG. 4 is a sectional view taken along line BB of FIG. 2;
【図5】 図1の立坑で用いるノズルユニットの平面図
である。FIG. 5 is a plan view of a nozzle unit used in the shaft of FIG.
【図6】 図5のC−C線断面図である。FIG. 6 is a sectional view taken along line CC of FIG. 5;
【図7】 図1の立坑の最下部に用いる立坑壁ブロック
の平面図である。FIG. 7 is a plan view of a shaft wall block used at the bottom of the shaft of FIG. 1;
【図8】 図7の立坑壁ブロックの右側面図である。FIG. 8 is a right side view of the shaft wall block of FIG. 7;
【図9】 図7のD−D線断面図である。FIG. 9 is a sectional view taken along line DD of FIG. 7;
【図10】 図1の立坑の2段目以上に用いる立坑壁ブ
ロックの平面図である。10 is a plan view of a shaft wall block used for the second stage or more of the shaft of FIG. 1. FIG.
【図11】 図10の立坑壁ブロックの右側面図であ
る。FIG. 11 is a right side view of the shaft wall block of FIG. 10;
【図12】 図10の立坑壁ブロックの正面図である。FIG. 12 is a front view of the shaft shaft block of FIG. 10;
【図13】 本発明の別の実施例に係る立坑の縦断面図
である。FIG. 13 is a longitudinal sectional view of a shaft according to another embodiment of the present invention.
【図14】 図13の立坑のE−E線断面図である。FIG. 14 is a sectional view taken along the line EE of the shaft of FIG.
【図15】 図13の立坑に用いるノズルユニットの平
面図である。FIG. 15 is a plan view of a nozzle unit used for the shaft of FIG.
【図16】 図15のF−F線断面図である。16 is a sectional view taken along line FF of FIG.
【図17】 図13の立坑の最下部に用いる立坑壁ブロ
ックの平面図である。FIG. 17 is a plan view of a shaft wall block used at the bottom of the shaft of FIG. 13;
【図18】 図17のG−G線断面図である。FIG. 18 is a sectional view taken along line GG of FIG. 17;
【図19】 図17のH−H線断面図である。FIG. 19 is a sectional view taken along line HH of FIG. 17;
【図20】 図13の立坑の2段目以上に用いる立坑壁
ブロックの平面図である。20 is a plan view of a shaft wall block used for the second stage or more of the shaft of FIG.
【図21】 図20の立坑壁ブロックの右側面図であ
る。FIG. 21 is a right side view of the shaft wall block of FIG. 20.
【図22】 図20の立坑壁ブロックの正面図である。FIG. 22 is a front view of the shaft shaft block of FIG. 20.
【図23】 図13の立坑に用いたノズルユニットの平
面図である。FIG. 23 is a plan view of a nozzle unit used in the shaft of FIG.
【図24】 図23のI−I線断面図である。FIG. 24 is a sectional view taken along line II of FIG. 23;
【図25】 前記立坑に用いられる調整リング用床版の
平面図である。FIG. 25 is a plan view of a floor slab for an adjusting ring used in the shaft.
【図26】 図25の調整リング用床版の右側面図であ
る。FIG. 26 is a right side view of the floor slab for the adjustment ring of FIG. 25.
【図27】 図25の調整リング用床版の正面図であ
る。FIG. 27 is a front view of the adjustment ring floor slab of FIG. 25.
【図28】 前記立坑に用いられる斜壁ブロック用床版
の平面図である。FIG. 28 is a plan view of a slab for a ramp wall block used in the shaft.
【図29】 前記立坑に用いられる別の床版の平面図で
ある。FIG. 29 is a plan view of another floor slab used for the shaft.
【図30】 図17の立坑壁ブロックにおいて底板用鉄
筋を掘り起こしたときの平面図である。FIG. 30 is a plan view when the bottom plate rebar is dug up in the shaft wall block of FIG. 17;
【図31】 図30の鉄筋部分の拡大縦断面図である。FIG. 31 is an enlarged longitudinal sectional view of a reinforcing bar portion of FIG. 30.
【図32】 立坑壁ブロックの圧入作業を示す平面図で
ある。FIG. 32 is a plan view showing a press-fitting operation of the shaft wall block.
【図33】 図32のJ−J線断面図である。FIG. 33 is a sectional view taken along line JJ of FIG. 32.
【図34】 立坑壁ブロックの接合部の拡大縦断面図で
ある。FIG. 34 is an enlarged vertical sectional view of a joint of a shaft shaft block.
【図35】 図23のノズルユニットのノズル部の拡大
縦断面図である。FIG. 35 is an enlarged longitudinal sectional view of a nozzle portion of the nozzle unit of FIG. 23.
1 立坑壁ブロック 2 立坑壁ブロック 3 ノズルユニット 4 ノズル 5 ノズルの内部配管 6 立坑壁ブロックの内蔵配管 7 立坑壁ブロックの内蔵配管 8 立坑壁ブロックの内側空間内の配管 9 円弧側壁部分 10 矩形側壁部分 11 円弧側壁部分 12 矩形側壁部分 13 圧入装置 14 立坑の底版 15 ノズルユニットの底版支持部 16 底板用鉄筋 18 発進用開口 19 ステップ 20 ステップ取付用インサート 21 吊上げ孔 22 ノズルユニットの噴出孔 23 開口部 24 ノズルユニットの接合ボルト 25 補強用鉄板 26 発進用開口の閉塞用発泡スチロール板 27 底板用鉄筋 28 底板用鉄筋 29 ベースコンクリート 30 調整リング用床版 31 接合用凹部 32 接合用凸部 33 凸部 34 出入り口 35 高さ調整リング 36 段差部 37 斜壁用床版 38 斜壁ブロック 39 溝部 40 蓋ユニット 41 床版 42 環状溝部 43 止水パッキング 44 油圧ジャッキ 45 吊上げ孔 DESCRIPTION OF SYMBOLS 1 Vertical shaft block 2 Vertical shaft block 3 Nozzle unit 4 Nozzle 5 Internal piping of a nozzle 6 Built-in piping of a vertical shaft block 7 Built-in piping of a vertical shaft block 8 Piping in the inner space of a vertical shaft block 9 Arc side wall portion 10 Rectangular side wall portion DESCRIPTION OF SYMBOLS 11 Arc side wall part 12 Rectangular side wall part 13 Press-fitting device 14 Bottom plate of vertical shaft 15 Bottom plate support part of nozzle unit 16 Reinforcing bar for bottom plate 18 Starting opening 19 Step 20 Step mounting insert 21 Lifting hole 22 Spout hole of nozzle unit 23 Opening 24 Nozzle unit joining bolts 25 Reinforcing iron plate 26 Styrofoam plate for closing start-up opening 27 Reinforcing bar for bottom plate 28 Reinforcing bar for bottom plate 29 Base concrete 30 Floor plate for adjusting ring 31 Joining recess 32 Joining protrusion 33 Convex portion 34 Inlet 35 Height adjustment ring 36 steps 37 oblique wall slab 38 inclined wall block 39 groove 40 cover unit 41 bed plate 42 an annular groove 43 waterproofing packing 44 hydraulic jack 45 lifting holes
Claims (3)
形状が中空蒲鉾型の立坑壁ブロック1,2を所要段数に
積み上げて築造された推進工法用立坑。1. A shaft for a propulsion method constructed by stacking hollow shaft blocks 1 and 2 in a plane shape having a rectangular shape in which one side of a rectangle is replaced by an arc and having a required number of stages.
形状が中空蒲鉾型の立坑壁ブロック1,2を所要段数に
積み上げて地中に圧入するとき、最下部の立坑壁ブロッ
ク1の下面側に予めノズルユニット3を設け、立坑壁ブ
ロック1,2の壁内部に設けた配管6,7または立坑壁
ブロック1,2の内側空間に設けた配管8からノズルユ
ニット3の内部配管5に高圧流体を供給し、ノズルユニ
ット3のノズル4から土質状況に応じて高圧流体を適時
噴射する推進工法用立坑の施工方法。2. The lower side of the lowermost shaft wall block 1 when stacking up a required number of stages of hollow shaft blocks 1 and 2 having a rectangular shape in which one side of a rectangle is replaced by an arc and pressing it into the ground. The nozzle unit 3 is provided in advance, and high-pressure fluid is supplied to the internal piping 5 of the nozzle unit 3 from the pipes 6 and 7 provided inside the walls of the shaft blocks 1 and 2 or the pipe 8 provided in the inner space of the shaft blocks 1 and 2. And a method for constructing a shaft for a propulsion method in which high-pressure fluid is injected from the nozzle 4 of the nozzle unit 3 according to the soil condition in a timely manner.
10に予め発進用開口18を設け、土砂が流入しないよ
うに該開口18を閉塞した状態で圧入作業を行ない、推
進工法の開始時に該開口18の閉塞を解くことを特徴と
する請求項2に記載の施工方法。3. A starting opening 18 is provided in advance in the rectangular side wall portion 10 of the shaft wall base block 1, and a press-fitting operation is performed in a state where the opening 18 is closed so as to prevent inflow of earth and sand. The construction method according to claim 2, wherein the blockage of the 18 is released.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9607996A JP2797274B2 (en) | 1996-03-26 | 1996-03-26 | Shaft for propulsion method and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9607996A JP2797274B2 (en) | 1996-03-26 | 1996-03-26 | Shaft for propulsion method and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH09256773A JPH09256773A (en) | 1997-09-30 |
JP2797274B2 true JP2797274B2 (en) | 1998-09-17 |
Family
ID=14155398
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9607996A Expired - Fee Related JP2797274B2 (en) | 1996-03-26 | 1996-03-26 | Shaft for propulsion method and its construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2797274B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101054450B1 (en) * | 2010-11-23 | 2011-08-05 | 박정규 | Precasting structure |
-
1996
- 1996-03-26 JP JP9607996A patent/JP2797274B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH09256773A (en) | 1997-09-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR102097919B1 (en) | Melioration wall and replacement wall mixed retaining wall construction method | |
JP2797274B2 (en) | Shaft for propulsion method and its construction method | |
JPH05230845A (en) | L-shaped block retaining wall structure and construction method thereof | |
KR100531023B1 (en) | Constructing method for anchor as foundation | |
JPH10152985A (en) | Constructing method of retaining wall | |
JP4485006B2 (en) | Construction method for underground structures | |
JP3776987B2 (en) | Vertical shaft construction method using a manhole wall combined tubular body | |
JP3355282B2 (en) | Construction method of perforated sheet pile and continuous underground wall having permeation section using this sheet pile | |
JPH0474489B2 (en) | ||
JPH05132930A (en) | Developing method of foundation pile with drain layer | |
JP4086400B2 (en) | Propulsion shaft, its construction method and propulsion method | |
JPH1088592A (en) | Concrete retaining wall | |
KR100538739B1 (en) | Pile for sheet-pile wall and construction method using that | |
KR100272838B1 (en) | The method for constructing a bearing wall with variable thickness | |
KR200348730Y1 (en) | Square vertical culvert tunnel using steel waterproof plate and concrete | |
JPH10195865A (en) | Method for constructing continuous underground wall, and press fitting plate | |
JP2552860B2 (en) | Basement method | |
JPH0465932B2 (en) | ||
KR960002378B1 (en) | A working method for a protective structure | |
JP4344069B2 (en) | Reinforced concrete L-type retaining wall | |
JP2001323485A (en) | Method of constructing underground structure | |
JP4809741B2 (en) | manhole | |
JPH06137084A (en) | Contruction method of tunnel opening | |
JP3239947B2 (en) | Construction method of foundation work | |
RU2313631C1 (en) | Method for deepened structure mounting |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080703 Year of fee payment: 10 |
|
LAPS | Cancellation because of no payment of annual fees |