JP2776669B2 - Hook overwind prevention device - Google Patents

Hook overwind prevention device

Info

Publication number
JP2776669B2
JP2776669B2 JP34324491A JP34324491A JP2776669B2 JP 2776669 B2 JP2776669 B2 JP 2776669B2 JP 34324491 A JP34324491 A JP 34324491A JP 34324491 A JP34324491 A JP 34324491A JP 2776669 B2 JP2776669 B2 JP 2776669B2
Authority
JP
Japan
Prior art keywords
weight
rope
hook
hanging
suspension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP34324491A
Other languages
Japanese (ja)
Other versions
JPH05178579A (en
Inventor
松音 佐々
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Construction Machinery Co Ltd
Original Assignee
Hitachi Construction Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Construction Machinery Co Ltd filed Critical Hitachi Construction Machinery Co Ltd
Priority to JP34324491A priority Critical patent/JP2776669B2/en
Publication of JPH05178579A publication Critical patent/JPH05178579A/en
Application granted granted Critical
Publication of JP2776669B2 publication Critical patent/JP2776669B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Jib Cranes (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、クレーンなどにおいて
フックの過巻きを防止装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus for preventing a hook from being overwound in a crane or the like.

【0002】[0002]

【従来の技術】従来のフック過巻き防止装置としては、
図8に示すようなものが知られている。このフック過巻
き防止装置は、図示しないブームの先端部のトップシー
ブ(不図示)から巻上げロープ1が吊り下げられてお
り、この巻上げロープ1の下端にはフック(不図示)が
取り付けられている。2は重錐であり、重錘2の貫通孔
に巻上げロープ1が貫通されている。この重錘2には連
結棒3の一端が連結され、この連結棒3の他端には、ブ
ームに装着されている検出器5に他端が連結される重錘
吊りロープ4の一端が連結されている。このような構成
において、巻上げロープ1が所定量以上巻上げられてフ
ックにより重錘2が持ち上げられると、重錘吊りロープ
4の張力が低減して検出器5に内蔵のマイクロスイッチ
が動作する。これにより、警報信号が出力されて巻き上
げが停止される。
2. Description of the Related Art Conventional hook overwind prevention devices include:
The one shown in FIG. 8 is known. In this hook overwinding prevention device, a hoisting rope 1 is suspended from a top sheave (not shown) at the tip of a boom (not shown), and a hook (not shown) is attached to a lower end of the hoisting rope 1. . Reference numeral 2 denotes a weight cone, and the hoisting rope 1 passes through a through hole of the weight 2. One end of a connecting rod 3 is connected to the weight 2, and the other end of the connecting rod 3 is connected to one end of a weight suspension rope 4 whose other end is connected to a detector 5 mounted on a boom. Have been. In such a configuration, when the hoisting rope 1 is hoisted by a predetermined amount or more and the weight 2 is lifted by the hook, the tension of the weight hanging rope 4 is reduced and the microswitch built in the detector 5 operates. As a result, an alarm signal is output and winding is stopped.

【0003】このような従来の過巻き防止装置では、重
錘2側に剛体からなる連結棒3を連結することにより、
重錘2が巻上げロープ1のまわりを回転しても連結棒3
が巻上げロープ1に当たり、それ以上回転しにくくし、
このような作用によって、重錘吊りロープ4の巻き付き
によるフック過巻き防止装置の誤動作を防止している。
また、実開昭60−177197号の出願明細書には、
重錘をその幅方向中心で吊下げ、重錘の左右に設けられ
た略平行の軸を前後方向2本のフックブロック巻上げ用
のフックロープでガイドすることでロープへの絡みつき
を防止する内容が開示されている。
[0003] In such a conventional overwinding prevention device, a connecting rod 3 made of a rigid body is connected to the weight 2 side.
Connecting rod 3 even when weight 2 rotates around hoisting rope 1
Hits the hoisting rope 1, making it harder to rotate further,
By such an operation, the malfunction of the hook overwinding prevention device due to the winding of the weight suspension rope 4 is prevented.
Also, in the specification of Japanese Utility Model Application No. Sho 60-177197,
The weight is suspended at the center in the width direction, and the substantially parallel axes provided on the left and right sides of the weight are guided by two hook ropes for winding up hook blocks in the front-rear direction to prevent the rope from being entangled with the rope. It has been disclosed.

【0004】[0004]

【発明が解決しようとする課題】ところで、周知のよう
にクローラクレーンは、クレーン作業の他にクラムシュ
ル作業などの掘削作業にも使用され、巻上げや旋回の頻
度や速度などが各作業によってまちまちである。このた
め、上記従来のフック過巻き防止装置では、特定の作業
においては重錘吊りロープ4の巻上げロープ1への巻付
けを防止できても、ある種の作業においては巻付けを完
全には防止できず、フック過巻き防止装置の誤動作を充
分に防止できないという問題点があった。また、上述し
た実開昭60−177197号の出願明細書に記載のフ
ック過巻防止装置にあっては、フックロープが前後方向
に2本有しているもの(2本掛け)を対象としたもので
あって、1本掛け(1本吊りフック)に適用した場合に
は、重錘とガイド部との偏心によって重錘がフックロー
プを中心として回転し易く、重錘がフックロープに絡み
付くという問題は改善できない。
As is well known, crawler cranes are used not only for crane operations but also for excavation operations such as clam-shull operations, and the frequency and speed of hoisting and turning vary depending on the operation. . For this reason, in the above-mentioned conventional device for preventing overwinding of the hook, even when the winding of the weight suspension rope 4 around the hoisting rope 1 can be prevented in a specific operation, the winding is completely prevented in a certain operation. However, there is a problem that the malfunction of the hook overwinding prevention device cannot be sufficiently prevented. Also, the hook overwinding prevention device described in the application specification of Japanese Utility Model Application Laid-Open No. Sho 60-177197 is intended for a device having two hook ropes in the front-rear direction (two hooks). When applied to a single hook (one hanging hook), the weight tends to rotate around the hook rope due to the eccentricity of the weight and the guide portion, and the weight is entangled with the hook rope. The problem cannot be improved.

【0005】本発明の目的は、作業状況に応じて最適な
巻き付き防止方式を講じることができ、いかなる作業状
況においても誤動作を充分に防止できるフック過巻き防
止装置を提供することにある。
An object of the present invention is to provide a hook overwinding prevention device capable of taking an optimum winding prevention method according to a work situation and sufficiently preventing a malfunction in any work situation.

【0006】[0006]

【課題を解決するための手段】一実施例を示す図1,図
4および図5に対応付けて説明すると、本発明に係るフ
ック過巻き防止装置は、ブーム先端に装着した検出器1
5を重錐21に連結するための連結部材を一対の連結棒
20A,20Bで構成し、一対の連結棒20A,20B
の下端には重錘21にそれぞれ連結されるように下端連
結部20bをそれぞれ形成し、上端には連結器具19に
より一体結合されまたは連結器具19を取外して別体に
されるように上端連結部20aをそれぞれ形成し、図1
に示すように各連結棒20A,20Bの上端を連結器具
19により一体結合して重錐吊りロープ16に連結する
第1の吊り下げ形態と、図5に示すように連結器具16
を取外して各連結棒20A,20Bの上端を分離し一方
を重錐吊りロープ16Aに連結するとともに他方を他の
重錐吊りロープ16Bを介してブーム先端に連結する第
2の吊り下げ形態とを選択して使用するように構成した
ものである。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Referring to FIGS. 1, 4 and 5 showing an embodiment, a hook overwinding prevention device according to the present invention is provided with a detector 1 attached to the tip of a boom.
5 is connected to the weight 21 by a pair of connecting rods 20A and 20B.
A lower end connecting portion 20b is formed at a lower end of the upper end connecting portion 20b so as to be connected to the weight 21, and an upper end connecting portion is integrally connected to the upper end by a connecting device 19 or separated from the connecting device 19 to be separated. 20a are formed respectively, and FIG.
As shown in FIG. 5, a first hanging form in which the upper ends of the connecting rods 20A and 20B are integrally connected by a connecting device 19 and connected to a heavy-cone suspension rope 16, and as shown in FIG.
A second suspension form in which the upper ends of the connecting rods 20A and 20B are separated and one is connected to the heavy cone hanging rope 16A and the other is connected to the boom tip via the other heavy cone hanging rope 16B. It is configured to be used selectively.

【0007】[0007]

【作用】重錘21の両側にそれぞれ連結された一対の連
結棒20A,20Bの上端をそれぞれ連結器具19で一
体に連結し、この連結器具19を重錘吊りロープ16に
連結すれば第1の吊り下げ方式が実現できる。また、連
結器具19を取外して連結棒20A,20Bの上端をそ
れぞれ別々に重錘吊りロープ16A,16Bに連結すれ
ば第2の吊り下げ方式を実現できる。
The upper ends of a pair of connecting rods 20A and 20B respectively connected to both sides of the weight 21 are integrally connected by a connecting device 19, and the connecting device 19 is connected to the weight hanging rope 16 by a first method. A hanging system can be realized. In addition, if the connecting device 19 is removed and the upper ends of the connecting rods 20A and 20B are separately connected to the weight suspension ropes 16A and 16B, the second suspension method can be realized.

【0008】第1の吊り下げ方式では、重錘21が回転
しようとすると連結棒20A,20Bが巻上げロープ1
にぶつかり、重錘21の回転を防止できる。一方、第2
の吊り下げ方式では、重錐21は一対の重錘吊りロープ
16A,16Bにより互いに逆方向に引張られるため、
重錘21の回転を第1の吊り下げ方式以上に確実に防止
することができる。連結器具19の着脱により連結棒2
0A,20Bの上端を結合するか分離するかにより、作
業状況に応じて2つの吊り下げ方式のうち作業に最適な
方式を容易かつ迅速に選択することができる。
In the first suspension system, when the weight 21 is about to rotate, the connecting rods 20A and 20B are pulled up by the hoisting rope 1.
And the rotation of the weight 21 can be prevented. On the other hand, the second
In the hanging method, the weight cone 21 is pulled in opposite directions by a pair of weight hanging ropes 16A and 16B.
The rotation of the weight 21 can be prevented more reliably than in the first suspension method. Connecting rod 2 by attaching / detaching connecting instrument 19
Depending on whether the upper ends of 0A and 20B are combined or separated, an optimal system for the work can be easily and quickly selected from the two suspension systems depending on the work situation.

【0009】なお、本発明の構成を説明する上記課題を
解決するための手段と作用の項では、本発明を分かり易
くするために実施例の図を用いたが、これにより本発明
が実施例に限定されるものではない。
In the means and means for solving the above problems which explain the constitution of the present invention, the drawings of the embodiments are used to make the present invention easy to understand. However, the present invention is not limited to this.

【0010】[0010]

【実施例】以下、図面を参照して、本発明の実施例につ
いて詳細に説明する。なお、従来例と同一構成の部分に
は同一符号を付して、その説明を省略する。図1〜図7
は、本発明に係るフック過巻き防止装置を示している。
このフック過巻き防止装置は2つの使用方式、すなわち
重錘一本吊り方式と重錘二本吊り方式とを作業状況に応
じて容易かつ簡単に選択できる点に特徴がある。したが
って、以下、重錘一本吊り方式を図1〜図4に、重錘二
本吊り方式を図5〜図7に示して説明する。
Embodiments of the present invention will be described below in detail with reference to the drawings. The same components as in the conventional example are denoted by the same reference numerals, and description thereof will be omitted. 1 to 7
Shows a hook overwinding prevention device according to the present invention.
The hook overwinding prevention device is characterized in that it can easily and easily select one of two use methods, that is, a one-weight suspension method and a two-weight suspension method according to the work situation. Therefore, the single weight suspension method will be described below with reference to FIGS. 1 to 4, and the double weight suspension method will be described with reference to FIGS. 5 to 7.

【0011】まず、重錘一本吊り方式を示す図1〜4に
おいて、符号10はブームの先端を示す。このブーム1
0の先端にはトップシーブ11が設けられており、この
トップシーブ11には巻上げロープ1が巻き掛けられて
いる。巻上げロープ1の下端には吊荷13を吊り下げる
ためのフックブロック12が連結されている。一方、ブ
ーム10の先端には検出器支持部材14が設けられ、こ
の検出器支持部材14に検出器15が吊り下げられてい
る。検出器15はマイクロスイッチを内蔵しており、こ
のマイクロスイッチは検出器15に連結された重錘吊り
ロープ16の張力によってオン・オフする。
First, in FIGS. 1 to 4 showing a single weight suspension method, reference numeral 10 denotes a tip of a boom. This boom 1
The top sheave 11 is provided with a top sheave 11, and the hoisting rope 1 is wound around the top sheave 11. A hook block 12 for hanging a suspended load 13 is connected to a lower end of the hoisting rope 1. On the other hand, a detector support member 14 is provided at the tip of the boom 10, and a detector 15 is suspended from the detector support member 14. The detector 15 has a built-in micro switch, and this micro switch is turned on / off by the tension of the weight suspension rope 16 connected to the detector 15.

【0012】この重錘吊りロープ16の下端には図4に
示すようにリング状のシンブル17が設けられ、ロープ
クリップ18で結束されている。シンブル17にはシャ
ックル(連結器具)19のシャックル本体19aが引っ
掛けられており、このシャックル本体19aには、一対
の連結棒20A,20Bがそれら各連結棒20A,20
Bの先端部の取付孔20aにシャックル用ボルト19b
を挿通することで連結されている。
As shown in FIG. 4, a ring-shaped thimble 17 is provided at the lower end of the weight suspension rope 16, and is bound by a rope clip 18. A shackle main body 19a of a shackle (connecting device) 19 is hooked on the thimble 17, and a pair of connecting rods 20A and 20B are connected to the shackle main body 19a.
B, a shackle bolt 19b is provided in the mounting hole 20a at the tip end.
Are connected by inserting.

【0013】連結棒20A,20Bの下端部には重錐2
1が取り付けられている。重錐21は略円筒状に形成さ
れ、中心部に巻上げロープ1を貫通させるための貫通孔
21aが設けられている。重錘21の上面の径方向両端
にはそれぞれ取付孔21bが設けられ、これらの取付孔
21bには、連結棒20A,20Bの下端部にそれぞれ
設けられた取付孔に挿入された取付ピン20bが嵌合さ
れ、割りピン21c,座金21dで取付ピン20bの抜
け止めがなされている。したがって、連結棒20は重錐
21に対して揺動可能に連結されている。なお、重錘2
1の貫通孔21aは切欠部21eを介して外部と連通さ
れており、この切欠部21eから巻上げロープ1が重錐
21に挿通される。この切欠部21eにはブロック21
fが嵌め込まれ、このブロック21fは締結具21gで
固定される。
At the lower ends of the connecting rods 20A and 20B, a double cone 2 is provided.
1 is attached. The weight cone 21 is formed in a substantially cylindrical shape, and is provided with a through hole 21a at the center portion for allowing the hoisting rope 1 to pass therethrough. Mounting holes 21b are provided at both ends in the radial direction of the upper surface of the weight 21, and mounting pins 20b inserted into the mounting holes provided at the lower ends of the connecting rods 20A and 20B are provided in these mounting holes 21b. The mounting pin 20b is prevented from coming off by the fitting pin 21c and the washer 21d. Therefore, the connecting rod 20 is swingably connected to the weight 21. The weight 2
The first through hole 21a is communicated with the outside through a notch 21e, and the hoisting rope 1 is inserted into the heavy cone 21 from the notch 21e. The notch 21e has a block 21
f is fitted, and this block 21f is fixed with a fastener 21g.

【0014】このような構成において、巻上げロープ1
が一定量以上巻き上げられるとフックブロック12が重
錘21を突き上げる。このため、重錘吊りロープ16の
張力が失われて検出器15に内蔵のマイクロスイッチが
動作し、マイクロスイッチから警報信号が出力されて巻
上げが停止され、これにより、フックブロック12の過
巻きが防止される。
In such a configuration, the hoisting rope 1
Is wound up by a certain amount or more, the hook block 12 pushes up the weight 21. For this reason, the tension of the weight hanging rope 16 is lost, the micro switch built in the detector 15 is operated, an alarm signal is output from the micro switch, and the winding is stopped. Is prevented.

【0015】以上のような重錘一本吊り方式にあって
は、重錘21が回転しようとすると連結棒20A,20
Bが巻上げロープ1にぶつかり、重錘21の回転が防止
される。このとき、重錘21の径方向両端に2本の連結
棒20A,20Bの下端がそれぞれ連結されているの
で、重錘21の回転に対して大きなモーメントで復元力
を作用させることができ、1本の連結棒の場合に比べて
重錘21の回転が効果的に防止される。さらに、重錘2
1が軸対称の円筒状に形成されているから、重錘の重心
が偏心している場合に比べ重錐が回転を始めても慣性力
がつきにくく、回転を容易に止めることができる。した
がって、重錘吊りロープ16の巻上げロープ1への巻き
つきを効果的に防止でき、フック過巻き防止装置の誤動
作を防止できる。
In the single weight suspension system described above, when the weight 21 attempts to rotate, the connecting rods 20A, 20A
B hits the hoisting rope 1 and rotation of the weight 21 is prevented. At this time, since the lower ends of the two connecting rods 20A and 20B are respectively connected to both ends in the radial direction of the weight 21, the restoring force can be applied with a large moment to the rotation of the weight 21. The rotation of the weight 21 is effectively prevented as compared with the case of the book connecting rod. Furthermore, weight 2
Since 1 is formed in an axially symmetric cylindrical shape, inertial force is less likely to be applied even when the weight cone starts to rotate as compared with the case where the center of gravity of the weight is eccentric, and the rotation can be stopped easily. Therefore, it is possible to effectively prevent the weight suspension rope 16 from being wound around the hoisting rope 1 and prevent the hook overwinding prevention device from malfunctioning.

【0016】次に、重錘二本吊り方式について図5〜図
7により説明する。なお、重錘一本吊り方式を示す図1
〜4と同一構成の部分には同一符号を付してその説明を
省略する。この使用状態は図5、図7に端的に示すよう
に、連結棒20A,20Bの上下を1本吊り方式の場合
とは逆にし、その上端を別々の重錘吊りロープ16A,
16Bに連結し、上方に向かうにしたがい両者の間隔が
開くように略V字状に吊り下げるものである。ここで、
一方の重錘吊りロープ16Aは検出器15を介して検出
器支持体14Aに連結され、他方の重錘吊りロープ16
Bは検出器支持体14Bへ直接連結される。
Next, the two-weight suspension method will be described with reference to FIGS. FIG. 1 shows a single-weight suspension method.
The same reference numerals are given to the same components as those in Nos. 1 to 4, and description thereof will be omitted. In this use state, as shown in FIGS. 5 and 7, the upper and lower portions of the connecting rods 20A and 20B are reversed from those in the case of a single suspension system, and the upper ends thereof are separated by separate weight suspension ropes 16A and 20A.
16B, and is suspended in a substantially V-shape so that the interval between them increases as going upward. here,
One weight suspension rope 16A is connected to a detector support 14A via a detector 15, and the other weight suspension rope 16A
B is connected directly to detector support 14B.

【0017】このように、重錘二本吊り方式にあって
は、一対の連結棒20A,20Bおよび重錘吊りロープ
16A,16Bを上方へ向かうにしたがい巻上げロープ
1から離間するように吊り下げているから、重錐21に
は互に逆方向に引っ張り力が作用して重錘21の回転に
対して強い復元力が働き、1本吊り方式に比べて重錘2
1の回転を確実に防止できる。したがって、重錘吊りロ
ープ16A,16Bの巻上げロープ1への巻きつきを1
本吊り方式よりも確実に防止でき、検出器15の誤動作
を確実に防止できる。この使用状態は、激しい作業や上
下振動の多い、例えばハンマグラブ、アースドリル、バ
ッケット作業等に適している。この第2の吊り方式で
は、巻上げロープ1が図7中矢印A方向に揺れると、検
出器15側の重錐吊りロープ16Aが緩んで張力が失わ
れて検出器15が誤動作する場合がある。このため、ク
レーン作業等のように旋回速度が速く巻上げロープ1が
横揺れしやすい作業の場合には、この2本吊り方式より
も上述した1本吊り方式が好ましい。すなわち、この2
本吊り方式は巻上げロープの横揺れがあまり大きくなら
ないような作業に好適である。
As described above, in the double weight suspension method, the pair of connecting rods 20A, 20B and the weight suspension ropes 16A, 16B are suspended from the hoisting rope 1 as they move upward. Therefore, a pulling force acts on the weight cone 21 in the opposite direction to each other, and a strong restoring force acts on the rotation of the weight 21, so that the weight 2 is smaller than the single hanging type.
1 can surely be prevented from rotating. Therefore, the winding of the weight suspension ropes 16A and 16B around the hoisting rope 1 is reduced by one.
This can be more reliably prevented than in the case of the main suspension method, and the malfunction of the detector 15 can be reliably prevented. This use state is suitable for heavy work and a lot of vertical vibrations, for example, for work such as a hammer club, an earth drill, and a bucket. In the second suspension system, when the hoisting rope 1 swings in the direction of arrow A in FIG. 7, the heavy-cone suspension rope 16A on the detector 15 side may loosen and lose tension, and the detector 15 may malfunction. For this reason, in the case of work such as crane work in which the turning speed is high and the hoisting rope 1 is likely to sway, the above-described single suspension system is preferable to the two suspension system. That is, this 2
This suspension system is suitable for work in which the roll of the hoisting rope does not become so large.

【0018】以上説明したように、本実施例にあって
は、重錘21上面の径方向両端に一対の連結棒20A,
20Bの下端部をそれぞれ連結し、連結棒20A,20
Bの上端部をシャックル19を介して重錘吊りロープに
連結するようにしているので、シャックル19のボルト
19bを外すだけで連結棒20の上端部を容易に着脱す
ることができる。このため、重錘一本吊り方式と、重錘
二本吊り方式とを容易かつ迅速に選択することができ
る。したがって、通常のクレーン作業では、重錘一本吊
り方式で作業をし、巻上げロープ1の横揺れがあまり激
しくない場合で誤動作を確実に防止したい場合には、重
錘二本吊り方式で使用することができる。このようにし
て、作業状況に応じて、それぞれの特徴を有する2つの
使用方式のうち最適な方式を容易かつ迅速に選択するこ
とができ、全体としてフック過巻き防止装置の誤動作を
充分に防止することができる。また、本実施例のよう
に、一対の連結棒20A,20Bの上下を逆にするだけ
で容易に1本吊り方式と2本吊り方式とを切換え可能に
すれば、部品点数を増加させることなく2つの方式を選
択することができる。
As described above, in the present embodiment, a pair of connecting rods 20A,
The lower ends of 20B are connected to each other to form connecting rods 20A, 20B.
Since the upper end of B is connected to the weight hanging rope via the shackle 19, the upper end of the connecting rod 20 can be easily attached and detached only by removing the bolt 19b of the shackle 19. Therefore, it is possible to easily and quickly select the single-weight suspension method and the double-weight suspension method. Therefore, in a normal crane operation, work is performed with a single weight suspension method, and when it is desired that the hoisting rope 1 is not so severely swayed and a malfunction is reliably prevented, use the double weight suspension method. be able to. In this manner, the most suitable method can be easily and quickly selected from the two use methods having the respective characteristics according to the work situation, and the malfunction of the hook overwinding prevention device is sufficiently prevented as a whole. be able to. Further, as in the present embodiment, if it is possible to easily switch between the single suspension system and the two suspension system simply by reversing the pair of connecting rods 20A, 20B, the number of parts is not increased. Two methods can be selected.

【0019】なお、連結器具としてシャックル19を採
用しているが、連結器具はこれに限る必要はなく、連結
棒20と重錘吊りロープ16とを容易に着脱できるもの
であれば他の器具でもよい。
Although the shackle 19 is used as the connecting device, the connecting device is not limited to this, and other devices can be used as long as the connecting rod 20 and the weight hanging rope 16 can be easily attached and detached. Good.

【0020】[0020]

【発明の効果】以上説明したように、本発明によれば、
重錘の両側に一対の連結棒の下端をそれぞれ連結し、こ
の連結棒の上端を着脱自在な連結器具を介して重錘吊り
ロープに連結するようにしているので、一対の連結棒の
上端をまとめて連結器具に連結し重錘吊りロープに連結
する第1の吊り方式と、一対の連結棒の上端を別々に重
錘吊りロープに連結する第2の吊り方式とを容易かつ迅
速に選択することができる。したがって、作業状況に応
じて最適な使用状態を採用することができ、全体として
フック過巻き防止装置の誤動作を充分に防止することが
できる。
As described above, according to the present invention,
The lower ends of the pair of connecting rods are respectively connected to both sides of the weight, and the upper ends of the connecting rods are connected to the weight suspension rope via a detachable connecting device. A first suspending method of connecting the connecting device to the weight hanging rope and a second hanging method of separately connecting the upper ends of the pair of connecting rods to the weight suspending rope are easily and quickly selected. be able to. Therefore, the optimum use state can be adopted according to the work situation, and the malfunction of the hook overwinding prevention device can be sufficiently prevented as a whole.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係るフック過巻き防止装置の一実施例
において重錘一本吊りの使用状態を示す斜視図である。
FIG. 1 is a perspective view showing a use state of hanging a single weight in an embodiment of a hook overwinding prevention device according to the present invention.

【図2】図1に示す一実施例において重錘一本吊りの使
用状態を示す側面図である。
FIG. 2 is a side view showing a use state of a single weight suspended in the embodiment shown in FIG. 1;

【図3】図1に示す一実施例において重錘一本吊りの使
用状態を示す正面図である。
FIG. 3 is a front view showing a use state of hanging one weight in the embodiment shown in FIG. 1;

【図4】図1に示す一実施例の連結棒および連結器具を
示す斜視図である。
FIG. 4 is a perspective view showing the connecting rod and the connecting device of the embodiment shown in FIG. 1;

【図5】本発明に係るフック過巻き防止装置の一実施例
において重錘二本吊りの使用状態を示す斜視図である。
FIG. 5 is a perspective view showing a use state of a double weight suspension in the embodiment of the hook overwinding prevention device according to the present invention.

【図6】図5に示す一実施例において重錘二本吊りの使
用状態を示す側面図である。
FIG. 6 is a side view showing a use state of the double weight suspension in the embodiment shown in FIG. 5;

【図7】図5に示す一実施例において重錘二本吊りの使
用状態を示す正面図である。
FIG. 7 is a front view showing a use state of the double weight suspension in the embodiment shown in FIG. 5;

【図8】従来のフック過巻き防止装置を示す側面図であ
る。
FIG. 8 is a side view showing a conventional hook overwinding prevention device.

【符号の説明】[Explanation of symbols]

1 巻上げロープ 10 ブーム 12 フックブロック 15 検出器 16,16A,16B 重錘吊りロープ 19 連結器具 20A,20B 連結棒 21 重錘 DESCRIPTION OF SYMBOLS 1 Hoisting rope 10 Boom 12 Hook block 15 Detector 16, 16A, 16B Weight hanging rope 19 Connection device 20A, 20B Connection rod 21 Weight

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 ブーム先端に検出器を装着し、この検出
器に重錐吊りロープおよび連結部材を介して重錘を吊り
下げ、この重錘に巻上げロープを貫通させ、巻上げロー
プの巻上げにより重錐が持上げられて前記検出器に作用
する荷重が低減すると検出器が動作して警報信号を出力
するフック過巻き防止装置において、 前記連結部材は一対の連結棒からなり、一対の連結棒の
下端には前記重錘にそれぞれ連結されるように下端連結
部がそれぞれ形成され、上端には連結器具により一体結
合されまたは連結器具を取外して別体にされるように上
端連結部がそれぞれ形成され、 各連結棒の上端を前記連結器具により一体結合して前記
重錐吊りロープに連結する第1の吊り下げ形態と、前記
連結器具を取外して各連結棒の上端を分離し一方を前記
重錐吊りロープに連結するとともに他方を他の重錐吊り
ロープを介して前記ブーム先端に連結する第2の吊り下
げ形態とを選択して使用するように構成したことを特徴
とするフック過巻き防止装置。
1. A detector is attached to the end of a boom, a weight is hung from the detector via a weight hanging rope and a connecting member, a hoisting rope is passed through the weight, and the weight is raised by winding the hoisting rope. In a hook overwinding prevention device that operates when a load acting on the detector is reduced by lifting the cone and outputs an alarm signal, the connecting member includes a pair of connecting rods, and lower ends of the pair of connecting rods. A lower end connecting portion is formed respectively so as to be connected to the weight, and an upper end connecting portion is formed at the upper end so as to be integrally connected by a connecting device or detached from the connecting device to be separated from each other, A first hanging mode in which the upper ends of the connecting rods are integrally connected by the connecting device and connected to the heavy cone suspension rope; And a second hanging form in which the other is connected to the end of the boom via another heavy-pyramid hanging rope. .
JP34324491A 1991-12-25 1991-12-25 Hook overwind prevention device Expired - Fee Related JP2776669B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP34324491A JP2776669B2 (en) 1991-12-25 1991-12-25 Hook overwind prevention device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP34324491A JP2776669B2 (en) 1991-12-25 1991-12-25 Hook overwind prevention device

Publications (2)

Publication Number Publication Date
JPH05178579A JPH05178579A (en) 1993-07-20
JP2776669B2 true JP2776669B2 (en) 1998-07-16

Family

ID=18360037

Family Applications (1)

Application Number Title Priority Date Filing Date
JP34324491A Expired - Fee Related JP2776669B2 (en) 1991-12-25 1991-12-25 Hook overwind prevention device

Country Status (1)

Country Link
JP (1) JP2776669B2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100721859B1 (en) * 2001-07-31 2007-05-28 주식회사 포스코 Apparatus for preventing of rolled weight wire of crane
JP2006349117A (en) * 2005-06-17 2006-12-28 Jtekt Corp Differential gear device for vehicle
WO2013020259A1 (en) * 2011-08-05 2013-02-14 长沙中联重工科技发展股份有限公司 Limiting weight of over-wind protection switch of crane
JP5794950B2 (en) * 2012-06-07 2015-10-14 日立住友重機械建機クレーン株式会社 Overwinding prevention tool
JP6554341B2 (en) * 2015-06-22 2019-07-31 植田基工株式会社 Construction method of foundation pile
JP7137115B2 (en) * 2018-03-27 2022-09-14 コベルコ建機株式会社 Crane overwinding detection weight
JP7379908B2 (en) * 2019-08-01 2023-11-15 コベルコ建機株式会社 Overwinding detection device and construction machinery
JP7136135B2 (en) * 2020-01-17 2022-09-13 コベルコ建機株式会社 Overwinding detection structure for suspended load ropes of heavy weights and construction machinery

Also Published As

Publication number Publication date
JPH05178579A (en) 1993-07-20

Similar Documents

Publication Publication Date Title
JP2776669B2 (en) Hook overwind prevention device
JP5117815B2 (en) Crane hook device
JP4600374B2 (en) Crane boom head
JP2553328Y2 (en) Arm type work machine
JPH1036081A (en) Hook steadying device for crane
JP3338559B2 (en) crane
JP2003312987A (en) Floating crane
CN106715316B (en) Crane
JPH0442358Y2 (en)
RU2078020C1 (en) Boom variable ratio load sheave-block
JPH06294129A (en) Suspension rope guide device for excavation machine
JP2003300695A (en) Hook oscillation prevention device of marine crane
JP2594579B2 (en) Adjustable hanging tool
JPH09132381A (en) Device for preventing rope from coming off crane
JP3036563U (en) Jib crane
JP2022155625A (en) Wire rope, connecting member, mounting method of wire rope
JP3012132B2 (en) Method and apparatus for assembling ground drill
JP2001302184A (en) Swing preventing tag line device of construction machinery
JPH0338234Y2 (en)
JPH11228076A (en) Device and method for changing number of winding time of wire rope for crane
JP3092473U (en) Crane hook blocks and cranes
JP3612099B2 (en) Retraction mechanism of upper device
JP2021191707A (en) Auxiliary cylinder control device, work machine equipped with the same, and auxiliary cylinder control method
JPH08324976A (en) Construction machine having a frame
JPH07488Y2 (en) Windproof snow fence deployment storage device

Legal Events

Date Code Title Description
FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080501

Year of fee payment: 10

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20090501

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20090501

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100501

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 13

Free format text: PAYMENT UNTIL: 20110501

LAPS Cancellation because of no payment of annual fees