JP2729131B2 - Precast concrete column construction method - Google Patents
Precast concrete column construction methodInfo
- Publication number
- JP2729131B2 JP2729131B2 JP13447892A JP13447892A JP2729131B2 JP 2729131 B2 JP2729131 B2 JP 2729131B2 JP 13447892 A JP13447892 A JP 13447892A JP 13447892 A JP13447892 A JP 13447892A JP 2729131 B2 JP2729131 B2 JP 2729131B2
- Authority
- JP
- Japan
- Prior art keywords
- precast concrete
- mortar
- concrete column
- connecting steel
- footing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Foundations (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明はコンクリート基礎上にプ
レキャストコンクリート柱等を建てる際の建方工法に関
するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a precast concrete column or the like on a concrete foundation.
【0002】[0002]
【従来の技術】プレキャストコンクリート柱の建方工法
は、図4に示すような工法が一般に用いられていた。こ
れは、基礎コンクリート20上に連結用鋼棒30を突設
して台座ブロック40を設置する。そしてこの台座ブロ
ック40上にプレキャストコンクリート柱50を立設す
る。この立設はプレキャストコンクリート柱50をクレ
ーンで吊り上げて支えながら前記連結用鋼棒30により
基礎コンクリート20に固定すると共に、PC鋼線60
でプレストレスを付与するものである。2. Description of the Related Art As a method of constructing a precast concrete column, a construction method as shown in FIG. 4 has been generally used. In this method, a connecting steel bar 30 is protruded from a foundation concrete 20 and a pedestal block 40 is installed. Then, a precast concrete column 50 is erected on the pedestal block 40. In this standing, the precast concrete column 50 is fixed to the foundation concrete 20 by the connecting steel bar 30 while being supported by being lifted by a crane.
Is to give a prestress.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、上記の
ようなプレキャストコンクリート柱の建方工法は、プレ
キャストコンクリート柱を建込む際に、該プレキャスト
コンクリート柱をクレーン等で支えながら連結用鋼棒で
固定するため極めて作業能率が悪いという問題があっ
た。本発明は上記のような問題に鑑みてなされたもので
あり、その目的は、プレキャストコンクリート柱を建て
る際に、効率良く建込むことができその作業能率を高め
ることである。However, in the method of constructing a precast concrete column as described above, when the precast concrete column is erected, the precast concrete column is fixed by a connecting steel bar while being supported by a crane or the like. Therefore, there is a problem that work efficiency is extremely poor. The present invention has been made in view of the above-described problems, and an object of the present invention is to efficiently build a precast concrete pillar when building it, and to increase the work efficiency.
【0004】[0004]
【課題を解決するための手段】以上の課題を解決するた
めの手段は、連結用鋼棒が上面に突出したコンクリート
基礎上に凹溝を形成し、凹溝にモルタルを打設するとと
もに、フーチングを備えたプレキャストコンクリート柱
を建込んで、前記連結用鋼棒をフーチングの挿通孔に挿
入してプレキャストコンクリート柱を自立させた後、前
記モルタルの硬化前に連結用鋼棒をフーチングとの間で
一次緊張してプレキャストコンクリート柱を仮固定し、
モルタルの硬化後に連結用鋼棒を二次緊張して固定した
ことに存する。Means for solving the above-mentioned problem is that concrete steel bars having a connecting steel bar projecting from the upper surface thereof are used.
When a groove is formed on the foundation and mortar is cast in the groove
Precast concrete columns with footings
And insert the connecting steel rod into the insertion hole of the footing.
After the precast concrete pillars are
Before hardening the mortar, connect the connecting steel bar to the footing.
Temporarily fix the precast concrete columns by primary tension,
After the mortar has hardened, the connecting steel rods are secondarily tensioned and fixed .
【0005】[0005]
【作用】モルタルを打設した凹溝にフーチングを備えた
プレキャストコンクリート柱を建込むことにより、該プ
レキャストコンクリート柱が自立してコンクリート基礎
上への建込み作業を容易かつ効率良くすることができる
と共に、該プレキャストコンクリート柱を前記モルタル
の硬化前に連結用鋼棒で一次緊張して仮固定することに
より、モルタルの不陸を調整することができるので、建
込み精度の向上を図ることができる。[Action] The molar barrel in the concave groove which is Da設by writing denominated precast concrete column having a footing, can the precast concrete pillar to easily and efficiently denominated included work on concrete foundation by self At the same time, the precast concrete column is temporarily tensioned and temporarily fixed with the connecting steel bar before the mortar is hardened, so that unevenness of the mortar can be adjusted, so that the mounting accuracy can be improved. .
【0006】[0006]
【実施例】以下、本発明のプレキャストコンクリート柱
の建込工法の一実施例を図面に基づいて詳細に説明す
る。図1は本発明のプレキャストコンクリート柱を建込
んだ際の断面図を示すものである。BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view showing a construction method of a precast concrete column according to the present invention. FIG. 1 is a cross-sectional view when a precast concrete column of the present invention is built.
【0007】先ず初めに構築現場において常法により基
礎コンクリート1を打設する。このコンクリート基礎1
上におけるプレキャストコンクリート柱2の建込み箇所
には深さ数十cmの凹溝3が形成され、該凹溝3の底面
には上面が水平仕上げされたモルタル4が柔らかい状態
で打設されている。この凹溝3は後述するプレキャスト
コンクリート柱2におけるフーチング5よりやや大き
く、下端が基礎コンクリート1中に埋設された連結用鋼
棒6が底面から突出されている。First, a foundation concrete 1 is cast at a construction site by a conventional method. This concrete foundation 1
A concave groove 3 having a depth of several tens of cm is formed at a location where the precast concrete column 2 is built, and a mortar 4 whose upper surface is horizontally finished is poured into the bottom surface of the concave groove 3 in a soft state. . The concave groove 3 is slightly larger than the footing 5 of the precast concrete column 2 described later, and a connecting steel rod 6 whose lower end is buried in the foundation concrete 1 projects from the bottom surface.
【0008】そしてこのような凹溝3内において硬化前
のモルタル4上にプレキャストコンクリート柱2を立設
する。このプレキャストコンクリート柱2は建物の2層
分程度の長さに予め一体形成され、柱の四角部に挿通さ
れたPC鋼線2aにより予めプレストレスが付与された
ものであり、各階の高さごとに大梁受け用突起2bを突
設すると共に、その下端部にはフーチング5を備えてい
る。Then, the precast concrete column 2 is erected on the mortar 4 before hardening in the concave groove 3. The precast concrete column 2 is integrally formed in advance with a length of about two layers of a building, and is pre-stressed by a PC steel wire 2a inserted into a square portion of the column. A projection 2b for projecting a girder is provided at the lower end thereof, and a footing 5 is provided at the lower end thereof.
【0009】このフーチング5の四隅には上下に貫通し
た挿通孔5aが形成され、その挿通孔5aに前記連結用
鋼棒6が挿入されて凹溝3内にプレキャストコンクリー
ト柱2が自立される。また、このフーチング5には空気
抜き用溝5bが設けられ、該空気抜き用溝5bはその底
面に中央から外側に向かって放射状に形成されて空気を
外側に逃がす働きをする。この空気抜き用溝5bは前記
のように放射状に限らず、図3の(2)に示すように格
子状又は十字状に形成することもできる。At the four corners of the footing 5, insertion holes 5a penetrating vertically are formed. The connecting steel bars 6 are inserted into the insertion holes 5a, and the precast concrete columns 2 are self-standing in the concave grooves 3. The footing 5 is provided with an air vent groove 5b. The air vent groove 5b is formed on the bottom surface of the footing 5 radially from the center to the outside, and functions to release air to the outside. The air vent groove 5b is not limited to the radial shape as described above, and may be formed in a lattice shape or a cross shape as shown in FIG. 3 (2).
【0010】次に、前記挿通孔5aに挿入された連結用
鋼棒6を凹溝3のモルタル4が柔らかいうちに緊張ジャ
ッキで一次緊張せしめ、その上端にナット6aを螺合し
てプレキャストコンクリート柱2を仮固定する。この緊
張はプレキャストコンクリート柱2が自立に必要な程度
の緊張力であり、モルタル上面の不陸を調整しながら緊
張すると、モルタル4が押し出されてフーチング5の周
面と凹溝3の内面との間に盛り上げられ、このままの状
態で硬化される。Next, while the mortar 4 of the concave groove 3 is soft, the connecting steel rod 6 inserted into the insertion hole 5a is primarily tensioned by a tension jack, and a nut 6a is screwed onto the upper end thereof to screw the precast concrete column. 2 is temporarily fixed. This tension is a tension required for the precast concrete column 2 to be self-supporting. If the tension is adjusted while adjusting the unevenness of the upper surface of the mortar, the mortar 4 is pushed out and the peripheral surface of the footing 5 and the inner surface of the concave groove 3 are moved. It is raised in the middle and cured as it is.
【0011】前記のようにプレキャストコンクリート柱
2を仮固定した後、前記モルタル4が硬化したら、前記
連結用鋼棒6を緊張ジャッキにより二次緊張せしめて最
終的な固定をする。このことによりプレキャストコンク
リート柱2と基礎コンクリート1とは力学的に一体化さ
れたキャンチレバー構造となる。そして、このように立
設されたプレキャストコンクリート柱2に予め突設され
た大梁受け用突起2bに大梁の顎部を支持させてプレキ
ャストコンクリート柱2間に大梁を架設するものであ
る。After the precast concrete column 2 is temporarily fixed as described above, when the mortar 4 is hardened, the connecting steel bar 6 is secondarily tensioned by a tension jack to be finally fixed. As a result, the precast concrete column 2 and the foundation concrete 1 have a cantilever structure that is mechanically integrated. The girders are supported between the precast concrete columns 2 by supporting the jaws of the girders on the girder receiving projections 2b projecting in advance from the precast concrete columns 2 thus erected.
【0012】[0012]
【発明の効果】連結用鋼棒が上面に突出したコンクリー
ト基礎上に凹溝を形成し、凹溝にモルタルを打設すると
ともに、フーチングを備えたプレキャストコンクリート
柱を建込んで、前記連結用鋼棒をフーチングの挿通孔に
挿入してプレキャストコンクリート柱を自立させた後、
前記モルタルの硬化前に連結用鋼棒をフーチングとの間
で一次緊張してプレキャストコンクリート柱を仮固定
し、モルタルの硬化後に連結用鋼棒を二次緊張して固定
したことにより、プレキャストコンクリート柱を効率良
く、施工時間を短くかつ安全に建込むことができるので
作業能率を高めることができる。According to the present invention, a concrete bar in which a connecting steel bar projects from the upper surface.
When a groove is formed on the foundation and mortar is cast into the groove
Both are precast concrete with footing
Install the pillar and insert the connecting steel rod into the footing insertion hole.
After inserting and making the precast concrete columns self-supporting,
Before hardening of the mortar, the connecting steel rod is
To temporarily fix precast concrete columns
After the mortar is hardened, the connecting steel bar is fixed with secondary tension.
By doing so, the precast concrete columns can be efficiently built, the construction time can be shortened, and the work efficiency can be increased, because the construction time can be shortened.
【0013】凹溝にフーチングを備えたプレキャストコ
ンクリート柱を建込むことにより、該プレキャストコン
クリート柱が自立した状態で仮固定及び最終固定を行う
ことができる。By installing a precast concrete column provided with a footing in the concave groove, the precast concrete column can be temporarily fixed and finally fixed in a self-standing state.
【0014】モルタルが硬化する前、即ち柔らかい状態
で一次緊張して仮固定をすることにより、モルタル上面
の不陸を調整しながら一次緊張することができるので、
プレキャストコンクリート柱の建込み精度を向上させる
ことができる。Since the mortar is hardened, that is, temporarily tensioned and temporarily fixed in a soft state, the primary tension can be adjusted while adjusting the unevenness of the upper surface of the mortar.
The accuracy of precast concrete pillars can be improved.
【図1】コンクリート基礎上に建込んだプレキャストコ
ンクリート柱の断面図である。FIG. 1 is a sectional view of a precast concrete pillar built on a concrete foundation.
【図2】(1)は図1のa−a線断面図、(2)は他の
実施例を示すプレキャストコンクリート柱である。 2A is a sectional view taken along line aa of FIG. 1, and FIG.
It is a precast concrete column showing an example.
【図3】(1)はフーチングの底面図であり、(2)は
他の実施例を示すフーチングの底面図である。FIG. 3A is a bottom view of a footing, and FIG. 3B is a bottom view of a footing showing another embodiment.
【図4】従来の建込工法で建込んだプレキャストコンク
リート柱の断面図である。FIG. 4 is a cross-sectional view of a precast concrete column built by a conventional building method.
1 コンクリート基礎 2 プレキャストコンクリート柱 3 凹溝 4 モルタル 5 フーチング 6 連結用鋼棒 DESCRIPTION OF SYMBOLS 1 Concrete foundation 2 Precast concrete column 3 Groove 4 Mortar 5 Footing 6 Steel bar for connection
Claims (3)
ト基礎上に凹溝を形成し、凹溝にモルタルを打設すると
ともに、フーチングを備えたプレキャストコンクリート
柱を建込んで、前記連結用鋼棒をフーチングの挿通孔に
挿入してプレキャストコンクリート柱を自立させた後、
前記モルタルの硬化前に連結用鋼棒をフーチングとの間
で一次緊張してプレキャストコンクリート柱を仮固定
し、モルタルの硬化後に連結用鋼棒を二次緊張して固定
したことを特徴とするプレキャストコンクリート柱の建
方工法。1. A concrete concrete in which a connecting steel bar projects from an upper surface.
When a groove is formed on the foundation and mortar is cast into the groove
Both are precast concrete with footing
Install the pillar and insert the connecting steel rod into the footing insertion hole.
After inserting and making the precast concrete columns self-supporting,
Before hardening of the mortar, the connecting steel rod is
To temporarily fix precast concrete columns
After the mortar is hardened, the connecting steel bar is fixed with secondary tension.
The method of building precast concrete columns, characterized by the following:
ストレストコンクリート柱であることを特徴とする請求
項1に記載のプレキャストコンクリート柱の建方工法。2. The method according to claim 1, wherein the precast concrete columns are prestressed concrete columns.
ト柱が自立可能な緊張力で緊張せしめることを特徴とす
る請求項1に記載のプレキャストコンクリート柱の建方
工法。3. The method for constructing a precast concrete column according to claim 1, wherein the primary tension is caused by a tension that allows the precast concrete column to stand by itself.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13447892A JP2729131B2 (en) | 1992-04-28 | 1992-04-28 | Precast concrete column construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13447892A JP2729131B2 (en) | 1992-04-28 | 1992-04-28 | Precast concrete column construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH05302357A JPH05302357A (en) | 1993-11-16 |
JP2729131B2 true JP2729131B2 (en) | 1998-03-18 |
Family
ID=15129269
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP13447892A Expired - Fee Related JP2729131B2 (en) | 1992-04-28 | 1992-04-28 | Precast concrete column construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2729131B2 (en) |
-
1992
- 1992-04-28 JP JP13447892A patent/JP2729131B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH05302357A (en) | 1993-11-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4918891A (en) | Precast concrete foundation elements and system and method of using same | |
JP3131816B2 (en) | How to build a steel column | |
JP3384820B2 (en) | Prefabricated bridge pier | |
JP3044459B2 (en) | Tower structure construction method | |
JP2729131B2 (en) | Precast concrete column construction method | |
JP3342891B2 (en) | Construction method of horizontal beam erected on columnar structure | |
JPH02164934A (en) | Foundation construction method | |
JP2000160687A (en) | Construction method for composite structure and precast concrete column | |
JPH0371537B2 (en) | ||
JPH10311041A (en) | Column base foundation of precast concrete column | |
JP2649205B2 (en) | Anchor bolt burying method | |
JP4424953B2 (en) | Foundation structure | |
JPH08209712A (en) | Level adjustment body | |
JPH02164933A (en) | Architecture foundation construction method | |
JP2733632B2 (en) | How to build a stilt house foundation | |
JPS6039816B2 (en) | Anchor bolt burial method | |
JPS6192265A (en) | Root winding method of iron pillar leg | |
JPH02282572A (en) | Erection method for precast concrete pillar | |
JPH038954A (en) | Concrete panel for wall, and constructing method for wall using concrete panel | |
JP2555216Y2 (en) | Retaining wall with protective fence | |
JP2724891B2 (en) | Construction method of pillar half PCa formwork | |
JPH01315525A (en) | Snowslide preventing and slope stabilizing structure | |
JPH0762669A (en) | Method for constructing column base of precast concrete | |
JP2847620B2 (en) | PC basic construction method | |
JP2604189Y2 (en) | Buttress wall construction structure for reactor containment vessel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071212 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081212 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081212 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 12 Free format text: PAYMENT UNTIL: 20091212 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091212 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101212 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 14 Free format text: PAYMENT UNTIL: 20111212 |
|
LAPS | Cancellation because of no payment of annual fees |