JP2709551B2 - Prefabricated foundation member and its construction method - Google Patents
Prefabricated foundation member and its construction methodInfo
- Publication number
- JP2709551B2 JP2709551B2 JP14485092A JP14485092A JP2709551B2 JP 2709551 B2 JP2709551 B2 JP 2709551B2 JP 14485092 A JP14485092 A JP 14485092A JP 14485092 A JP14485092 A JP 14485092A JP 2709551 B2 JP2709551 B2 JP 2709551B2
- Authority
- JP
- Japan
- Prior art keywords
- prefabricated
- fitting hole
- foundation
- prefabricated foundation
- holes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Foundations (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、プレファブ基礎部材
と、このプレファブ基礎部材を利用して建築物の基礎を
形成する施工方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a prefabricated foundation member and a construction method for forming a foundation of a building using the prefabricated foundation member.
【0002】[0002]
【従来の技術】従来の住宅などの建築物においては、基
礎フ−チング上に基礎立上り部を形成した布基礎を利用
するのが一般的であるが、地盤の軟弱な場所などでは、
布基礎で囲まれた部分全面にコンクリ−トを打設するべ
た基礎とする例が多い。2. Description of the Related Art In conventional buildings such as houses, it is common to use a cloth foundation in which a foundation rising portion is formed on a foundation footing.
In many cases, a concrete is cast on the entire surface surrounded by a cloth foundation.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、このべ
た基礎を施工する場合には、まず周囲の布基礎を形成す
るための作業が必要である。この布基礎の立上り部を構
築するためには、型枠の組み立て作業と、コンクリ−ト
の打設硬化後の型枠の脱型作業とが必要となり、作業が
煩雑となり、長時間を要していた。本発明は、かかる従
来の問題点を解決しうるプレファブ基礎部材とその施工
方法を提供することを目的とするものである。However, when this solid foundation is constructed, an operation for forming a surrounding cloth foundation is first required. In order to construct the rising portion of the cloth foundation, it is necessary to assemble the formwork and remove the formwork after casting and hardening the concrete, which makes the work complicated and takes a long time. I was An object of the present invention is to provide a prefabricated foundation member capable of solving such a conventional problem and a method for constructing the prefabricated foundation member.
【0004】[0004]
【課題を解決するための手段】上記目的を達成するた
め、本発明に係るプレファブ基礎部材においては、所定
の基礎高さを有し、所定長さの四角柱形状にあらかじめ
成形され、両端部側面に各々接合バンドの挿通孔が形成
され、両端部端面に各々接合用丸棒の第1嵌着孔が形成
されてなることを特徴とする。In order to achieve the above object, in a prefabricated foundation member according to the present invention, a prefabricated base is formed in advance into a quadrangular prism shape having a predetermined foundation height and a predetermined length. Are formed with insertion holes for the joining bands, and first fitting holes for the round bars for joining are respectively formed on the end faces of both ends.
【0005】なお、前記挿通孔及び前記第1嵌着孔が相
互に高さ位置をずらせて、各々上下に2か所形成され、
両端部側面には、前記第1嵌着孔と同じ高さ位置に同一
径の第2嵌着孔が形成されている構成とするのが望まし
い。[0005] The insertion hole and the first fitting hole are formed at upper and lower positions, respectively, at two different heights.
It is preferable that a second fitting hole having the same diameter is formed at the same height position as the first fitting hole on both side surfaces.
【0006】また、上記目的を達成するため、本発明に
係るプレファブ基礎部材の施工方法においては、所定の
基礎高さを有し、所定長さの四角柱形状にあらかじめ成
形され、両端部側面に各々接合バンドの挿通孔が上下2
か所形成され、両端部端面に各々接合用丸棒の第1嵌着
孔が上下2か所形成され、両端部側面には前記第1嵌着
孔と同じ高さ位置に同一径の第2嵌着孔が上下2か所形
成されているプレファブ基礎部材を、所定個数基礎フ−
チング上に設置し、直線部では隣接するプレファブ基礎
部材相互の前記第1嵌着孔に接合用丸棒を嵌着して水平
に連結し、対向する一対の前記挿通孔に接合バンドを挿
通して連結し、補助木材を介して緊締して一体化し、コ
−ナ−部では、直交して設置された一対のプレファブ基
礎部材の一方の端部側面に形成された前記第2嵌着孔か
ら他方のプレファブ基礎部材の端部端面に形成された第
1嵌着孔に向けて接合用丸棒を嵌着して水平に連結し、
対向する一対の前記挿通孔に接合バンドを挿通して連結
し、補助木材を介して緊締して一体化し、しかる後に各
プレファブ基礎部材で画成された部分にコンクリ−トを
打設硬化させて建築物の基礎を形成することを特徴とす
る。In order to achieve the above object, in a method for constructing a prefabricated foundation member according to the present invention, the prefabricated foundation member has a predetermined foundation height, is formed in advance into a quadrangular prism shape having a predetermined length, and is formed on both side surfaces. The insertion holes of the joining bands are upper and lower 2
The first fitting holes of the round bar for joining are respectively formed at two upper and lower portions on the end surfaces of both ends, and the second fitting holes of the same diameter are formed on the side surfaces of both ends at the same height position as the first fitting holes. A predetermined number of prefabricated base members having two upper and lower fitting holes are formed.
In the straight portion, a joining round bar is fitted in the first fitting holes of the adjacent prefabricated foundation members and connected horizontally, and a joining band is inserted through the pair of opposed insertion holes. In the corner portion, the second fitting hole formed on the side surface at one end of a pair of prefabricated foundation members installed at right angles. The connecting round bar is fitted horizontally toward the first fitting hole formed on the end face of the other prefabricated base member,
A joining band is inserted and connected to the pair of opposed insertion holes, tightened and integrated via auxiliary wood, and then concrete is cast and hardened on a portion defined by each prefabricated foundation member. It is characterized by forming the foundation of a building.
【0007】[0007]
【実施例】以下、本発明の好適な実施例を図面により説
明する。図1及び図2は本発明の一実施例を示すもので
あり、図中1は本実施例に係るプレファブ基礎部材であ
る。プレファブ基礎部材1は、図1に示すように所定の
基礎高さHと厚さWを有し、所定長さLを有する四角柱
形状にあらかじめ成形されている。なお、長さLについ
てはあらかじめ、数種類の長さのものを用意しておき、
これらを組み合わせて使用するようになっている。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described below with reference to the drawings. 1 and 2 show an embodiment of the present invention. In the drawings, reference numeral 1 denotes a prefabricated base member according to the present embodiment. As shown in FIG. 1, the prefabricated base member 1 has a predetermined base height H and a predetermined thickness W, and is formed in advance into a quadrangular prism shape having a predetermined length L. For the length L, several lengths are prepared in advance,
These are used in combination.
【0008】本実施例では、プレファブ基礎部材1は、
コンクリ−ト系の材質で形成されており、この場合には
上記基礎厚さWは5cm程度でよい。材質的には、この他
に硬質EPS(Expanding ポリエステル)等を使用する
ことができる。In this embodiment, the prefabricated base member 1 is
It is made of a concrete material. In this case, the base thickness W may be about 5 cm. As for the material, hard EPS (Expanding polyester) or the like can be used in addition to this.
【0009】プレファブ基礎部材1の両端部側面には、
各々後述する接合バンドの挿通孔2が上下に2か所形成
されている。また、プレファブ基礎部材1の両端部端面
には、各々後述する接合用丸棒の第1嵌着孔3が上下に
2か所形成されている。前記各挿通孔2と前記各第1嵌
着孔3とは、相互に高さ位置をずらせて形成されてい
る。また、プレファブ基礎部材1の両端部側面には、前
記挿通孔2よりも端部側位置で、第1嵌着孔3と同じ高
さ位置に同一径の第2嵌着孔4が形成されている。On both side surfaces of the prefabricated base member 1,
Two insertion holes 2 for a bonding band, which will be described later, are formed in two places at the top and bottom. In addition, first fitting holes 3 of a round bar for connection, which will be described later, are formed at two locations on the end surfaces of both ends of the prefabricated base member 1. Each of the insertion holes 2 and each of the first fitting holes 3 are formed so that their height positions are shifted from each other. A second fitting hole 4 having the same diameter as the first fitting hole 3 is formed on both end side surfaces of the prefabricated base member 1 at a position closer to the end than the insertion hole 2 and at the same height as the first fitting hole 3. I have.
【0010】次に、かかる構成からなるプレファブ基礎
部材1を使用して建築物の基礎を構築する施工手順につ
き説明する。図2は、施工手順を説明するために、便宜
上実際のものよりも小規模の模式図としたものであり、
施工の手順としては、まずプレファブ基礎部材1を、所
定個数だけ基礎フ−チング(図示せず)上に設置する。
この、基礎フ−チングは、図2で各プレファブ基礎部材
1の設置されるべき位置にあらかじめ形成されるもので
ある。Next, a construction procedure for constructing a foundation of a building using the prefabricated foundation member 1 having such a configuration will be described. FIG. 2 is a schematic diagram of a smaller scale than the actual one for convenience of explanation of the construction procedure.
As a construction procedure, first, a predetermined number of prefabricated foundation members 1 are set on a foundation footing (not shown).
The foundation footing is formed in advance at the position where each prefabricated foundation member 1 is to be installed in FIG.
【0011】各プレファブ基礎部材1は、直線部ではま
ず、隣接するプレファブ基礎部材1、1相互の前記第1
嵌着孔3に接合用丸棒5を嵌着して水平に連結する。各
プレファブ基礎部材1相互の水平を正確に確保するため
に、図示しないくさび型パッキン材を使用してプレファ
ブ基礎部材1の底面の所定位置に打ち込み、水平精度を
調整する。In the straight section, each prefabricated base member 1 firstly adjoins the first prefabricated base member 1, 1
The round bar 5 for joining is fitted in the fitting hole 3 and connected horizontally. In order to accurately maintain the horizontal position of each prefabricated foundation member 1, a wedge-shaped packing material (not shown) is used to drive the prefabricated foundation member 1 into a predetermined position on the bottom surface of the prefabricated foundation member 1 to adjust the horizontal accuracy.
【0012】しかる後に、プレファブ基礎部材1の端部
相互の対向する一対の前記挿通孔2、2間に図示の如く
接合バンド6を挿通して連結し、補助木材7を介して緊
締して一体化する。この接合バンド6としては、公知の
既製品である、梱包用の樹脂もしくは金属バンドを使用
することができ、これらの接合バンド6用に市販されて
いる締付工具を用いて緊締すれば良い。Thereafter, as shown in the figure, a joining band 6 is inserted between the pair of opposed through holes 2 and 2 of the end portion of the prefabricated base member 1 and connected to each other. Become As the bonding band 6, a well-known off-the-shelf product, such as a resin or metal band for packing, can be used, and it is sufficient to tighten with a commercially available tightening tool for the bonding band 6.
【0013】次に、コ−ナ−部では、図2に示すよう
に、直交して設置された一対のプレファブ基礎部材1、
1の一方のプレファブ基礎部材1の端部側面に形成され
た前記第2嵌着孔4から他方のプレファブ基礎部材1の
端部端面に形成された第1嵌着孔3に向けて接合用丸棒
5を嵌着して水平に連結し、上記したのと同様のくさび
型パッキン材を使用してプレファブ基礎部材1の底面の
所定位置に打ち込み、水平精度を調整する。次に、対向
する一対の前記挿通孔2、2間に接合バンド6を挿通し
て連結し、補助木材7を介して緊締して一体化する。Next, in the corner portion, as shown in FIG. 2, a pair of prefabricated foundation members 1,
1 from the second fitting hole 4 formed on the side surface of the end of one prefabricated base member 1 to the first fitting hole 3 formed on the end surface of the end of the other prefabricated base member 1. The rod 5 is fitted and connected horizontally, and is driven into a predetermined position on the bottom surface of the prefabricated base member 1 using the same wedge-shaped packing material as described above to adjust the horizontal accuracy. Next, the joining band 6 is inserted and connected between the pair of opposed insertion holes 2, 2, and tightened via the auxiliary wood 7 to be integrated.
【0014】このようにして、図2の如く外周部に各プ
レファブ基礎部材1を連結、配置し、しかる後に各プレ
ファブ基礎部材1で画成された部分にコンクリ−トを打
設硬化させてべた基礎を形成する。なお、べた基礎部分
8には、コンクリ−トを打設する前に、所定位置にアン
カ−ボルトや、各種配管類を配置しておき、その一部も
しくは全部をコンクリ−ト内に埋設する。In this way, as shown in FIG. 2, each prefabricated base member 1 is connected and arranged on the outer peripheral portion, and then a concrete is cast and hardened on the portion defined by each prefabricated base member 1. Form the basis Before the concrete is cast on the solid base portion 8, anchor bolts and various pipes are arranged at predetermined positions, and a part or all of them are embedded in the concrete.
【0015】上述した如く構成された本実施例において
は、外周部に配置されたプレファブ基礎部材1を型枠代
わりにして、べた基礎用のコンクリ−トを打設すること
ができ、べた基礎の形成後にプレファブ基礎部材1はそ
の一部としてそのまま使用できるため、従来のような型
枠の脱型作業が不要となり、工期を短縮することができ
る。In this embodiment constructed as described above, the prefabricated foundation member 1 arranged on the outer peripheral portion can be used as a formwork, and a concrete for a solid foundation can be cast. After the formation, the prefabricated base member 1 can be used as a part of the prefabricated base member 1 as it is, so that the work of removing the formwork as in the related art becomes unnecessary, and the construction period can be shortened.
【0016】また、プレファブ基礎部材1相互の連結
は、接合用丸棒5と接合バンド6だけで可能であり、構
成部材が単純で、接合方法も簡易であるため、熟練労働
者でなくとも施工を簡単に行うことができる。Further, the connection of the prefabricated foundation members 1 can be performed only by the joining round bar 5 and the joining band 6, and since the constituent members are simple and the joining method is also simple, the prefabricated foundation members 1 can be connected even if they are not skilled workers. Can be done easily.
【0017】なお、本発明は上記実施例に限定されるも
のではなく、挿通孔2や嵌着孔3の数やその形成位置な
どは設計条件に応じて自由に設定することができる等、
本発明の要旨を逸脱しない範囲内で種々の変形例が可能
なことは言うまでもない。The present invention is not limited to the above embodiment, and the number of insertion holes 2 and fitting holes 3 and their formation positions can be freely set according to design conditions.
It goes without saying that various modifications can be made without departing from the scope of the present invention.
【0018】[0018]
【発明の効果】本発明は上述した如く構成されており、
以下の効果を奏し得る。 (1) プレファブ基礎部材を型枠代わりに利用でき、型枠
の脱型作業が不要となるためり、工期を短縮することが
できる。 (2) プレファブ基礎部材相互の連結は、接合用丸棒と接
合バンドだけで可能であり、構成部材が単純で、接合方
法も簡易であるため、熟練労働者でなくとも施工を簡単
に行うことができる。The present invention is configured as described above,
The following effects can be obtained. (1) The prefabricated foundation member can be used instead of the formwork, and the work of removing the formwork is not required, so that the construction period can be shortened. (2) Prefabricated foundation members can be connected to each other only with round bars and bands, and the components are simple and the joining method is simple. Can be.
【図1】本発明の一実施例に係るプレファブ基礎部材の
構成を示す説明図である。FIG. 1 is an explanatory view showing a configuration of a prefabricated base member according to one embodiment of the present invention.
【図2】プレファブ基礎部材の接合態様を示す説明図で
ある。FIG. 2 is an explanatory view showing a joining mode of a prefabricated base member.
1 プレファブ基礎部材 2 挿通孔 3 第1嵌着孔 4 第2嵌着孔 5 接合用丸棒 6 接合バンド 7 補助木材 8 べた基礎 DESCRIPTION OF SYMBOLS 1 Prefab foundation member 2 Insertion hole 3 1st fitting hole 4 2nd fitting hole 5 Round bar for joining 6 Joining band 7 Auxiliary wood 8 Solid foundation
Claims (4)
形状にあらかじめ成形され、両端部側面に各々接合バン
ドの挿通孔が形成され、両端部端面に各々接合用丸棒の
第1嵌着孔が形成されてなることを特徴とするプレファ
ブ基礎部材。1. A square pillar having a predetermined base height and a predetermined length is formed in advance, and a through hole for a bonding band is formed at each side surface of both ends, and a round bar for bonding is formed at each end surface of both ends. A prefabricated base member having a first fitting hole formed therein.
さ位置をずらせて、各々上下に2か所形成されている請
求項1記載のプレファブ基礎部材。2. The prefabricated base member according to claim 1, wherein said insertion hole and said first fitting hole are formed at two positions, each being vertically shifted from each other.
さ位置に同一径の第2嵌着孔が形成されている請求項1
記載のプレファブ基礎部材。3. A second fitting hole having the same diameter as that of the first fitting hole is formed on both side surfaces of the both ends.
A prefabricated base member as described.
形状にあらかじめ成形され、両端部側面に各々接合バン
ドの挿通孔が上下2か所形成され、両端部端面に各々接
合用丸棒の第1嵌着孔が上下2か所形成され、両端部側
面には前記第1嵌着孔と同じ高さ位置に同一径の第2嵌
着孔が上下2か所形成されているプレファブ基礎部材
を、所定個数基礎フ−チング上に設置し、直線部では隣
接するプレファブ基礎部材相互の前記第1嵌着孔に接合
用丸棒を嵌着して水平に連結し、対向する一対の前記挿
通孔に接合バンドを挿通して連結し、補助木材を介して
緊締して一体化し、コ−ナ−部では、直交して設置され
た一対のプレファブ基礎部材の一方の端部側面に形成さ
れた前記第2嵌着孔から他方のプレファブ基礎部材の端
部端面に形成された第1嵌着孔に向けて接合用丸棒を嵌
着して水平に連結し、対向する一対の前記挿通孔に接合
バンドを挿通して連結し、補助木材を介して緊締して一
体化し、しかる後に各プレファブ基礎部材で画成された
部分にコンクリ−トを打設硬化させて建築物の基礎を形
成することを特徴とするプレファブ基礎部材の施工方
法。4. A square pillar having a predetermined base height and a predetermined length is formed in advance, and two through holes are respectively formed at upper and lower sides of both end side surfaces, and are respectively connected to both end end surfaces. The first fitting hole of the round bar is formed at two upper and lower positions, and the second fitting hole having the same diameter is formed at the same height position at the upper and lower sides at both ends. A predetermined number of prefabricated foundation members are placed on a predetermined number of foundation footings, and in a straight portion, connecting round bars are fitted in the first fitting holes of the adjacent prefabricated foundation members to be horizontally connected and opposed. A joining band is inserted into and connected to the pair of insertion holes, tightened and integrated through auxiliary wood, and at a corner portion, a side surface of one end of a pair of prefabricated foundation members installed orthogonally. Formed on the end face of the other prefabricated foundation member from the second fitting hole formed in A round bar for joining is fitted to one fitting hole and connected horizontally, and a joining band is inserted and connected to the pair of opposed through holes, which are tightened and integrated via auxiliary wood. A method for constructing a prefabricated foundation member, characterized by forming a foundation of a building by casting and hardening a concrete on a portion defined by each prefabricated foundation member.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14485092A JP2709551B2 (en) | 1992-05-11 | 1992-05-11 | Prefabricated foundation member and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14485092A JP2709551B2 (en) | 1992-05-11 | 1992-05-11 | Prefabricated foundation member and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH05311674A JPH05311674A (en) | 1993-11-22 |
JP2709551B2 true JP2709551B2 (en) | 1998-02-04 |
Family
ID=15371874
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP14485092A Expired - Fee Related JP2709551B2 (en) | 1992-05-11 | 1992-05-11 | Prefabricated foundation member and its construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2709551B2 (en) |
-
1992
- 1992-05-11 JP JP14485092A patent/JP2709551B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH05311674A (en) | 1993-11-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3199827A (en) | Forms for plastic material | |
US3288428A (en) | Preassembled tie construction | |
US4378664A (en) | System for constructing a building | |
JP2709551B2 (en) | Prefabricated foundation member and its construction method | |
JP3039295B2 (en) | Manufacturing method of prefabricated member of mixed structure | |
JPH07102668A (en) | Thin walled precast concrete placing formwork wall plate size assembling method | |
JPH0657710A (en) | Construction of concrete main tower | |
JPH06185111A (en) | Precast concrete beam and column and construction method of earthquake-proof wall using them | |
JPH0371537B2 (en) | ||
US4020132A (en) | Construction joint for reinforced concrete structures | |
JP3190455B2 (en) | Precast concrete member joining method | |
JPH0673786A (en) | Junction of precast concrete column | |
JP2004285581A (en) | Steel framed foundation material for building and formation method of concrete foundation for building making use of steel framed base foundation material | |
JP2649205B2 (en) | Anchor bolt burying method | |
JP2579838B2 (en) | Construction method of columns and beams in buildings | |
JP3245824B2 (en) | Column and beam joint structure of RC structure and its construction method | |
JPH0841985A (en) | Method of binding precast beam to column | |
JP2829242B2 (en) | Construction method of retaining wall | |
JPH04371635A (en) | Connection of floorslab and post | |
JP3119117B2 (en) | PC version driving formwork and formwork method | |
JP2579944Y2 (en) | Load-bearing wall assembly structure | |
JPS6168954A (en) | Construction of outer wall using precast truss plate | |
JPH0449253Y2 (en) | ||
JPS62121251A (en) | Building ramen | |
JP2004353254A (en) | Foundation structure of building and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071024 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 11 Free format text: PAYMENT UNTIL: 20081024 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091024 Year of fee payment: 12 |
|
LAPS | Cancellation because of no payment of annual fees |