JP2682778B2 - Construction method - Google Patents
Construction methodInfo
- Publication number
- JP2682778B2 JP2682778B2 JP4336332A JP33633292A JP2682778B2 JP 2682778 B2 JP2682778 B2 JP 2682778B2 JP 4336332 A JP4336332 A JP 4336332A JP 33633292 A JP33633292 A JP 33633292A JP 2682778 B2 JP2682778 B2 JP 2682778B2
- Authority
- JP
- Japan
- Prior art keywords
- column
- unloading
- roof
- additional
- hydraulic cylinder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、コンクリート基礎上で
屋根部を先行して完成させ、建築用ジャッキ装置で屋根
部を持ち上げた後、持ち上げた屋根部の下方空間に壁軸
組や外壁材などを組み付ける建方工法に関するものであ
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure in which a roof portion is first completed on a concrete foundation, and the roof portion is lifted by a jacking device for construction. It is related to the erection method of assembling.
【0002】[0002]
【従来の技術】プレハブ住宅などの施行方法として、例
えば、トラッククレーンで建築資材を吊り上げながら1
階から屋根部に向かって順に家屋を組み立てる工法が知
られている。2. Description of the Related Art As a method of implementing a prefabricated house, for example, 1
A construction method of assembling houses in order from the floor to the roof is known.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、クレー
ン車を利用して建築作業を行うためには、建築現場にク
レーン車を搬入させることができ、しかも、クレーン車
が作業することのできる空間を必要とする。したがっ
て、住宅密集地や進入道路が狭い場合には、クレーン車
を搬入することができない他、クレーン車を搬入できた
としても、敷地面積が狭小な場合には、その使用ができ
ないものである。また、1階から屋根部に向かって順に
積み上げる作業であることから、高所作業が不可欠とな
り、安全ネットや高所作業用足場などの仮設設備が必要
となり、仮設設備を構築することのできる敷地面積を確
保しなければならない他、その構築費用が必要となる。
本発明は、上記のような問題点に鑑みてなされたもの
で、クレーン車などの作業機械を使用することなく、狭
小地であっても作業者の安全性を確保して家屋を建築す
ることのできる建方工法に関するものである。However, in order to perform construction work using a mobile crane, it is necessary to have a space in which the mobile crane can be carried into a construction site and where the mobile crane can work. And Therefore, when the residential area is dense or the approach road is narrow, the crane vehicle cannot be carried in, and even if the crane vehicle can be carried in, it cannot be used if the site area is small. In addition, since the work is to be piled up in order from the first floor to the roof, work at high places is indispensable, and temporary facilities such as safety nets and scaffolds for work at high places are required. In addition to having to secure the area, the construction cost is required.
The present invention has been made in view of the above problems, and to build a house while ensuring the safety of the worker even in a small land without using a working machine such as a crane truck. It relates to the construction method that can be done.
【0004】[0004]
【課題を解決するための手段】本発明は、ピストンロッ
ドの先端をそれぞれベースに並設して連結した2本の油
圧シリンダと、これらの油圧シリンダのシリンダチュー
ブに連結されたクロスビームとからなり、このクロスビ
ームにピンを介して揚荷柱を着脱自在に連結するととも
に、ベースに支持柱を立設して構成された複数個の建築
用ジャッキ装置をそれぞれ所定位置に設置し、コンクリ
ート基礎の上に仮設材を介して載置された小屋梁の少な
くとも4箇所を各建築用ジャッキ装置に連結された揚荷
柱で支持した後、小屋梁の上に屋根部を組み立てて完成
させ、次いで、建築用ジャッキ装置の油圧シリンダを伸
長させて屋根部および小屋梁を揚荷柱を介して持ち上げ
た後、揚荷柱と支持柱との間に第1の継ぎ足し揚荷柱を
接続し、クロスビームと揚荷柱との連結を解除して油圧
シリンダを縮小させて屋根部および小屋梁を揚荷柱、第
1の継ぎ足し揚荷柱および支持柱を介して支持し、次い
で、クロスビームと第1の継ぎ足し揚荷柱とを連結した
後、再び油圧シリンダを伸長させて屋根部および小屋梁
を揚荷柱および第1の継ぎ足し揚荷柱を介して持ち上
げ、第1の継ぎ足し揚荷柱と支持柱との間に第2の継ぎ
足し揚荷柱を接続し、以上の設定本数の継ぎ足し揚荷柱
の接続作業、クロスビームと継ぎ足し揚荷柱との連結と
その解除作業および油圧シリンダの伸縮作業を繰り返し
て屋根部および小屋梁を設定高さ位置まで上昇させた
後、小屋梁とコンクリート基礎との間に壁軸組、外壁
材、窓枠サッシ、玄関ドアなどの組み付けを行うことを
特徴とするものである。SUMMARY OF THE INVENTION The present invention comprises two hydraulic cylinders in which the tips of piston rods are arranged side by side on a base and connected to each other, and a cross beam connected to the cylinder tubes of these hydraulic cylinders. , The cross-beam is detachably connected to the unloading column via a pin, and a plurality of construction jack devices each having a supporting column erected on the base are installed at predetermined positions. After supporting at least four points of the hut beam placed via the temporary material on the unloading columns connected to each jacking device for construction, the roof part is assembled on the hut beam to be completed, and then, After extending the hydraulic cylinder of the construction jack device to lift the roof and the shed beam through the unloading column, the first additional unloading column is connected between the unloading column and the supporting column, and Release the connection between the column and the unloading column to reduce the hydraulic cylinder to support the roof and shed beam through the unloading column, the first additional unloading column and the supporting column, and then the cross beam and the After connecting the first additional unloading column, the hydraulic cylinder is extended again to lift the roof portion and the shed beam through the unloading column and the first additional unloading column, and the first additional unloading column is supported. Connect the second additional unloading column to the column, connect the additional unloading columns with the above set number, connect the cross beam to the additional unloading column and release it, and expand and contract the hydraulic cylinder. Characteristically, after repeatedly raising the roof and the shed beam to the set height position, the wall shaft assembly, outer wall material, window frame sash, entrance door, etc. are assembled between the shed beam and the concrete foundation. It is a thing.
【0005】[0005]
【作用】コンクリート基礎上で屋根部を先行して完成さ
せた後、建築用ジャッキ装置を伸縮させるとともに、複
数本の継ぎ足し揚荷柱を接続して屋根部を設定高さ位置
まで持ち上げ、持ち上げた屋根部の下方空間に壁軸組や
外壁材などを組み付ける。[Operation] After the roof part is completed on the concrete foundation first, the construction jack device is expanded and contracted, and a plurality of extension loading columns are connected to lift the roof part to the set height position. Assemble wall shafts and outer wall materials in the space below the roof.
【0006】したがって、クレーン車などの作業機械を
使用する必要がなく、また、高所作業用足場などの仮設
設備が不要となり、狭小地であっても平屋建ての家屋を
建築することができる他、ほとんど地上およびその近傍
での作業となることから、作業者は安全に作業すること
ができるとともに、高所作業用足場などの仮設設備が不
要となり、建築費用を削減することができる。しかも、
屋根部を先行して完成させるため、風雨などによって資
材が濡れて品質の低下を招くことがなく、天候に左右さ
れずに施行することが可能となり、工期を短縮すること
ができる。Therefore, it is not necessary to use a working machine such as a crane truck, and temporary equipment such as a scaffold for working at high places is not required, so that a flat house can be constructed even in a small land. Since the work is performed almost on the ground and in the vicinity thereof, the worker can work safely, and temporary equipment such as a scaffold for working at high places is not required, and the construction cost can be reduced. Moreover,
Since the roof part is completed in advance, the quality of the material will not be deteriorated due to weather and rain, and the construction can be performed regardless of the weather, and the construction period can be shortened.
【0007】[0007]
【実施例】図面は本発明に係る建方工法の一実施例を示
すものである。BRIEF DESCRIPTION OF THE DRAWINGS The drawings show one embodiment of the construction method according to the present invention.
【0008】コンクリート基礎1の上にスペーサである
仮設材4を介して2階の床梁3を載置し、この床梁3の
上にさらにスペーサである仮設材4を介して小屋梁2を
載置している。A second floor floor beam 3 is placed on a concrete foundation 1 via a temporary material 4 serving as a spacer, and the hut beam 2 is further placed on the floor beam 3 via a temporary material 4 serving as a spacer. It is mounted.
【0009】仮設材4および小屋梁2、床梁3はH形鋼
で形成したもので、1個の高さが100mm〜200mmで
ある。The temporary member 4, the shed beam 2 and the floor beam 3 are made of H-shaped steel, and each of them has a height of 100 mm to 200 mm.
【0010】31は床梁3の梁つなぎで、21は小屋梁
2の梁つなぎである。Reference numeral 31 denotes a beam connection of the floor beam 3, and reference numeral 21 denotes a beam connection of the hut beam 2.
【0011】小屋梁2は、図1、図2および図10にお
いて、地上約500mm〜1000mmの所に載置してあ
る。この状態で、小屋梁2を建築用ジャッキ装置100
Aの揚荷柱117で支持する。床梁3はたわみを防止す
るため、建築用ジャッキ装置100Aに備えた支持柱1
70で支持している。The hut beam 2 is placed at a position of about 500 mm to 1000 mm above the ground in FIGS. 1, 2 and 10. In this state, the hut beam 2 is connected to the building jack device 100.
It is supported by the unloading column 117 of A. In order to prevent the deflection of the floor beam 3, the support pillar 1 provided in the architectural jack device 100A is used.
It is supported at 70.
【0012】屋根部A1を形成するとき、建築用ジャッ
キ装置100Aは、図19に例示するように、床梁3の
4個所に配置している。When the roof portion A1 is formed, the construction jack device 100A is arranged at four positions on the floor beam 3 as illustrated in FIG.
【0013】しかし、建屋上部A2を仕上げると、バル
コニー部分等に新たに建築用ジャッキ装置100Bを補
充して大きな荷重に耐えるようにするとよい。However, when the upper part A2 of the building is finished, it is preferable to newly add a building jack device 100B to a balcony or the like so as to withstand a large load.
【0014】本発明に係る建方工法は、上物である屋根
部A1から順にコンクリート基礎1上で組み立て、この
組み立てたものを建築用ジャッキ装置100A,100
Bで順次上昇させて建屋を築くことに特徴がある。According to the construction method according to the present invention, a roof part A1 is assembled on a concrete foundation 1 in order from an upper object, and the assembled parts are assembled into building jack devices 100A and 100A.
The feature is that the building is constructed by gradually ascending in B.
【0015】仕上げた建屋の上部から順次上方へ押し上
げる建築用ジャッキ装置100(100A,100B)
について説明する。An architectural jack device 100 (100A, 100B) that is sequentially pushed upward from the top of the finished building.
Will be described.
【0016】101は並列に立設した2本の油圧シリン
ダである。油圧シリンダ101はシリンダチューブ10
2とシリンダチューブ102から下向きに突出するピス
トンロッド103からなり、油圧配管201を介してシ
リンダチューブ102にポンプ200から作動油を供給
することにより2本のピストンロッド103を同期的に
伸縮させる。202は制御装置で、203は制御コード
である(図19参照)。Reference numeral 101 denotes two hydraulic cylinders standing in parallel. The hydraulic cylinder 101 is a cylinder tube 10.
2 and a piston rod 103 protruding downward from the cylinder tube 102. By supplying hydraulic oil from the pump 200 to the cylinder tube 102 via the hydraulic pipe 201, the two piston rods 103 are extended and contracted synchronously. Reference numeral 202 denotes a control device, and reference numeral 203 denotes a control code (see FIG. 19).
【0017】シリンダチューブ102同士は上部におい
て、クロスビーム104を用いて所定の間隔で連結して
いる。クロスビーム104は二つ割りで構成されてシリ
ンダチューブ102に着脱可能となされている。10
8,180はクロスビーム104係止用のフランジであ
る。The upper portions of the cylinder tubes 102 are connected at predetermined intervals using a cross beam 104. The cross beam 104 is divided into two parts and is detachable from the cylinder tube 102. 10
8, 180 are flanges for locking the cross beam 104.
【0018】ピストンロッド103の下端同士は平板部
材のベース105により連結される。The lower ends of the piston rods 103 are connected by a base 105 of a flat plate member.
【0019】ベース105にはピストンロッド103の
間に台座106が固定され、油圧シリンダ101と並列
に立設される支持柱170および継ぎ足し支持柱を支持
する。A pedestal 106 is fixed to the base 105 between the piston rods 103, and supports a support column 170 and an extension support column that are erected in parallel with the hydraulic cylinder 101.
【0020】クロスビーム104をシリンダチューブ1
02の上部に形成したフランジ108と中央部に形成し
たフランジ180の位置に着け換えることができる。The cross beam 104 is connected to the cylinder tube 1
The position of the flange 108 formed in the upper part of the upper part 02 and the position of the flange 180 formed in the central part can be changed.
【0021】クロスビーム104の中央には、揚荷柱1
17、継ぎ足し揚荷柱107、支持柱170および継ぎ
足し支持柱を直立状に貫き通す通孔140を形成してい
る。揚荷柱117と継ぎ足し揚荷柱107、継ぎ足し揚
荷柱107同士、支持柱170と継ぎ足し支持柱17
1、継ぎ足し支持柱171同士はいずれも同じ径のパイ
プで形成し、互いに上下に連結することができる。In the center of the cross beam 104, the loading column 1
17, an additional loading column 107, a supporting column 170, and a through hole 140 that penetrates the extending supporting column upright. Unloading column 117, additional unloading column 107, additional unloading columns 107, support column 170 and additional support column 17
1. The support pillars 171 can be formed of pipes having the same diameter, and can be connected to each other vertically.
【0022】なお、支持柱170は長さにおいて異なる
が揚荷柱117と全く同じ構成である。また、長さにお
いて異なるが継ぎ足し支持柱171は継ぎ足し揚荷柱1
07と全く同じ構成である。The supporting column 170 has exactly the same structure as the unloading column 117, though the length differs. In addition, although the lengths are different, the additional support columns 171 are additional load columns 1
It is the same configuration as 07.
【0023】継ぎ足し揚荷柱107および継ぎ足し支持
柱171はピストンロッド103の全ストローク量より
若干短いパイプ状部材で構成し、先端には径を徐々に縮
小したテーパ部130を設け、基端内側にはテーパ部1
30の外周に嵌合する形状のソケット131を設けて継
ぎ足し可能となしている。The extension column 107 and the extension column 171 are formed of a pipe-like member slightly shorter than the entire stroke of the piston rod 103, and a tapered portion 130 whose diameter is gradually reduced is provided at the tip, and is provided inside the base end. Is the tapered part 1
A socket 131 having a shape that fits around the outer periphery of 30 is provided so that it can be added.
【0024】なお、揚荷柱117の下端にも同様に、継
ぎ足し揚荷柱107のテーパ部130に嵌合する形状の
ソケット131を設けている。The lower end of the unloading column 117 is similarly provided with a socket 131 having a shape that fits into the tapered portion 130 of the reloading column 107.
【0025】ベース105上に固定した台座106も径
を上方に行くに従って徐々に縮小したテーパ部161と
なし、支持柱170および継ぎ足し支持柱171の下端
に形成したソケット131を嵌合させる。また、床梁3
上にもこの台座106と同様の台座160を固定し、揚
荷柱117および継ぎ足し揚荷柱107に形成したソケ
ット131を嵌合させる。The pedestal 106 fixed on the base 105 also has a tapered portion 161 gradually reduced in diameter as going upward, and the support column 170 and the socket 131 formed at the lower end of the extension column 171 are fitted. In addition, floor beam 3
A pedestal 160 similar to the pedestal 106 is fixed on the upper side, and the socket 131 formed on the unloading column 117 and the reloading unloading column 107 is fitted.
【0026】なお、揚荷柱117の上端と支持柱17
0、継ぎ足し支持柱171の上端には図示しない受け部
材を設け、小屋梁2および床梁3を支持する。The upper end of the unloading column 117 and the supporting column 17
0, a receiving member (not shown) is provided at the upper end of the extension supporting column 171 to support the hut beam 2 and the floor beam 3.
【0027】揚荷柱117、継ぎ足し揚荷柱107、支
持柱170の外周面の所定位置に係合孔150を形成
し、クロスビーム104に設けたピン111を突入させ
る。このピン111はクロスビーム104の通孔140
内に臨ませ、図示しないハンドルの操作でピン111の
入退出を行う。ピン111はハンドルの操作で作動する
ラチット機構により通孔140へ容易に入退出すること
ができるようになされている。An engaging hole 150 is formed at a predetermined position on the outer peripheral surface of the unloading column 117, the extended unloading column 107, and the support column 170, and the pin 111 provided on the cross beam 104 is made to protrude. This pin 111 is provided with a through hole 140 of the cross beam 104.
The pin 111 is moved in and out by operating the handle (not shown). The pin 111 can be easily moved in and out of the through hole 140 by a ratchet mechanism operated by operating a handle.
【0028】係合孔150の形成位置は、揚荷柱117
と支持柱170においては外周面の上部で、継ぎ足し揚
荷柱107においては外周面の下部で、継ぎ足し支持柱
171においては外周面の中央よりやや上部である。The formation position of the engagement hole 150 is determined by the unloading column 117.
And the supporting column 170, at the upper portion of the outer peripheral surface, at the extension column 107, at the lower portion of the outer peripheral surface, and at the extending column 171, slightly above the center of the outer peripheral surface.
【0029】通孔140内に貫き通した揚荷柱117な
どに形成した係合孔150にピン111を突入係止させ
ると油圧シリンダ101の伸縮力が揚荷柱117などに
伝えられる。When the pin 111 is pushed into and engaged with the engaging hole 150 formed in the unloading column 117 penetrating through the through hole 140, the expansion and contraction force of the hydraulic cylinder 101 is transmitted to the unloading column 117 and the like.
【0030】ピン111と係合孔150の係合状態はク
ロスビーム104に設けた図示しない近接スイッチで検
出して、制御コード203から制御装置202に信号が
送られ、確認ができる。The state of engagement between the pin 111 and the engagement hole 150 is detected by a proximity switch (not shown) provided on the cross beam 104, and a signal is sent from the control code 203 to the control device 202 so that it can be confirmed.
【0031】揚荷柱117、継ぎ足し揚荷柱107、支
持柱170、継ぎ足し支持柱171の基端外周に切り欠
き凹部190を形成し、台座106,160のテーパ部
161に形成した凸部162と係合することができるよ
うになしている。この切り欠き凹部190が凸部162
と係合したとき、揚荷柱117、継ぎ足し揚荷柱10
7、支持柱170、継ぎ足し支持柱171に形成した係
合孔150とクロスビーム104のピン111が対向す
ることができるようになしている。A notch recess 190 is formed in the outer periphery of the base end of the loading column 117, the extension column 107, the support column 170, and the extension column 171, and the convex portion 162 formed in the tapered portion 161 of the pedestals 106 and 160. It can be engaged. This notched concave portion 190 is a convex portion 162
When engaged with the unloading column 117, the reloading unloading column 10
7, the support pillar 170, the engaging hole 150 formed in the extension support pillar 171 and the pin 111 of the cross beam 104 can be opposed to each other.
【0032】油圧シリンダ101の一方の側方には油圧
シリンダ101と同期して伸縮し、ピストンロッド10
3の伸縮量を検出するストロークセンサ120を並列的
に立設している。ストロークセンサ120はシリンダチ
ューブ102の側方に固定した筒状部材で形成されたガ
イド121と、上部をガイド121の内部と摺接し、下
端をベース105に固定したロッド122で構成されて
いる。ガイド121の内部を摺動するロッド122の上
端には近接スイッチがガイド121の内周に近接して固
定され、この近接スイッチはガイド121の側面を貫通
して所定の間隔で設けられた検出孔123を通過する度
に制御コード203から制御装置202に信号を送る。On one side of the hydraulic cylinder 101, the piston rod 10 extends and contracts in synchronization with the hydraulic cylinder 101.
A stroke sensor 120 for detecting the amount of expansion and contraction of the third sensor is provided in parallel. The stroke sensor 120 includes a guide 121 formed of a cylindrical member fixed to the side of the cylinder tube 102, and a rod 122 having an upper portion slidably in contact with the inside of the guide 121 and a lower end fixed to the base 105. A proximity switch is fixed to the upper end of the rod 122 that slides inside the guide 121 in proximity to the inner circumference of the guide 121. The proximity switch penetrates the side surface of the guide 121 and is provided with detection holes provided at predetermined intervals. A signal is sent from the control code 203 to the control device 202 each time the signal passes through 123.
【0033】上記した建築用ジャッキ装置100Aで床
梁3および小屋梁2を支持した後、小屋梁2の上に屋根
部A1を組み立てる。小屋梁2を地上約500mm〜10
00mmの所に載置しているため、屋根部A1の組み立て
は、高い所でも約1000mm〜2000mmくらいの所で
安全に作業を行うことができる。After the floor beam 3 and the hut beam 2 are supported by the above-mentioned jack device for construction 100A, the roof section A1 is assembled on the hut beam 2. Hut beam 2 is approximately 500mm-10 above ground
Since it is placed at a location of 00 mm, the roof A1 can be safely assembled at a location of about 1000 mm to 2000 mm even at a high place.
【0034】屋根部A1の構成は、例えば、小屋梁2の
上に束22を立てて母屋23等を組み合わせ、この上に
野地板24や屋根材25を葺いている。26は軒先の腕
木で、27は破風である(図1参照)。The structure of the roof part A1 is, for example, that a bundle 22 is erected on the hut beam 2 and a main house 23 is combined therewith, and a field board 24 and a roof material 25 are roofed thereon. Reference numeral 26 denotes a crosspiece at the eaves, and 27 denotes a gable (see FIG. 1).
【0035】このように屋根部A1をコンクリート基礎
1の上で組み立てた後、建築用ジャッキ装置100A,
100Bを用いて組み立てた各部を順次上昇させて建屋
を構築する。建方の手順を図2ないし図9で示す外観の
正面図と、図10ないし図18で示す部分断面図とで説
明する。また、建築用ジャッキ装置100の動作は図2
0ないし図30で示す正面図で説明する。After assembling the roof A1 on the concrete foundation 1 in this manner, the building jack device 100A,
The building is constructed by sequentially assembling each part using 100B. The construction procedure will be described with reference to the front view of the appearance shown in FIGS. 2 to 9 and the partial cross-sectional views shown in FIGS. The operation of the construction jack device 100 is shown in FIG.
Description will be made with reference to the front views shown in FIGS.
【0036】まず、組み立てた屋根部A1を所定の高さ
まで上昇させる。小屋梁2および床梁3は少なくとも4
点が建築用ジャッキ装置100Aで支持されている(図
19参照)。First, the assembled roof portion A1 is raised to a predetermined height. Hut beam 2 and floor beam 3 are at least 4
The points are supported by the building jack device 100A (see FIG. 19).
【0037】制御装置202により、ピン111と係合
孔150が係合され、クロスビーム104と揚荷柱11
7が連結されていることを確認する。The control device 202 engages the pin 111 with the engagement hole 150, and causes the cross beam 104 and the unloading column 11 to engage.
Check that 7 is connected.
【0038】各油圧シリンダ101に作動油を供給して
ピストンロッド103を同期的に伸長駆動させる。ピス
トンロッド103が伸長するのに伴い、揚荷柱117を
押し上げ小屋梁2は屋根部A1とともに上昇する(図1
1、図20参照)。Hydraulic oil is supplied to each hydraulic cylinder 101 to synchronously extend and drive the piston rod 103. As the piston rod 103 extends, the lifting column 117 is pushed up, and the hut beam 2 rises together with the roof A1 (FIG. 1).
1, see FIG. 20).
【0039】こうしてピストンロッド103がいっぱい
に伸長したら、図12および図21に示すように、上昇
した揚荷柱117と床梁3上の台座160との間に第1
の継ぎ足し揚荷柱107を挿入する。このとき第1の継
ぎ足し揚荷柱107下端に形成した切り欠き凹部190
を台座160に形成した凸部162に係合させておけ
ば、継ぎ足し揚荷柱107の係合孔150はクロスビー
ム104のピン111と係合可能な位置に配設される。When the piston rod 103 is fully extended in this way, as shown in FIG. 12 and FIG.
Is inserted. At this time, the notch recess 190 formed at the lower end of the first additional loading column 107
Is engaged with the convex portion 162 formed on the pedestal 160, the engaging hole 150 of the reloading pillar 107 is arranged at a position where it can be engaged with the pin 111 of the cross beam 104.
【0040】継ぎ足し揚荷柱107はピストンロッド1
03の全ストローク量より若干短いので、先端のテーパ
部130を揚荷柱117のソケット131に嵌入し、基
端を床梁3上の台座160に載せればこの作業は容易に
行える。The additional loading column 107 is the piston rod 1
Since this is slightly shorter than the total stroke of 03, this operation can be easily performed by fitting the tapered portion 130 at the distal end into the socket 131 of the loading column 117 and placing the base end on the pedestal 160 on the floor beam 3.
【0041】なお、継ぎ足し揚荷柱107を支持する床
梁3は、たわみを防止するため床梁3とベース105と
の間に支持柱170が介装されている。The floor beam 3 supporting the additional loading column 107 has a supporting column 170 interposed between the floor beam 3 and the base 105 to prevent bending.
【0042】次にクロスビーム104のピン111を揚
荷柱117の係合孔150から引き抜いた後に、各油圧
シリンダ101をいっせいに収縮させる。これに伴っ
て、油圧シリンダ101で支持されていた屋根部A1の
荷重が第1の継ぎ足し揚荷柱107に加わることにな
る。第1の継ぎ足し揚荷柱107の下端は床梁3上に固
定した台座160と係合している。Next, after the pin 111 of the cross beam 104 is pulled out from the engagement hole 150 of the unloading column 117, the hydraulic cylinders 101 are contracted at the same time. Along with this, the load of the roof A1 supported by the hydraulic cylinder 101 is applied to the first additional loading column 107. The lower end of the first additional loading column 107 is engaged with a pedestal 160 fixed on the floor beam 3.
【0043】このようにして、油圧シリンダ101を図
22の位置まで収縮したら、クロスビーム104のピン
111を第1の継ぎ足し揚荷柱107の係合孔150に
突入係止させ、再び油圧シリンダ101を伸長させて小
屋梁2および屋根部A1を持ち上げる。When the hydraulic cylinder 101 is contracted to the position shown in FIG. 22 in this manner, the pin 111 of the cross beam 104 is pushed into the engaging hole 150 of the first extension column 107 and locked again. To elevate the hut beam 2 and the roof A1.
【0044】これにより、小屋梁2および屋根部A1は
油圧シリンダ101のストローク距離相当分だけさらに
上昇するので、上昇した第1の継ぎ足し揚荷柱107と
床梁3の台座160との間に第2の継ぎ足し揚荷柱10
7を継ぎ足す。As a result, the hut beam 2 and the roof A1 are further raised by an amount corresponding to the stroke distance of the hydraulic cylinder 101, so that the first ladder loading column 107 and the pedestal 160 of the floor beam 3 are raised. 2 additional loading columns 10
Add 7
【0045】なお、ピストンロッド103の最収縮位置
から第1の継ぎ足し揚荷柱107を上昇させる際にも、
制御装置202によりピン111と係合孔150との係
合状態を確認してから油圧シリンダ101に作動油を供
給する。When raising the first additional loading column 107 from the most contracted position of the piston rod 103,
After the control device 202 confirms the engagement state between the pin 111 and the engagement hole 150, the hydraulic oil is supplied to the hydraulic cylinder 101.
【0046】上記の作業を所定の本数の継ぎ足し揚荷柱
107が継ぎ足されるまで繰り返すことにより、小屋梁
2と屋根部A1は所定の高さに上昇される(図4、図1
5、図26参照)。By repeating the above operation until a predetermined number of extension columns 107 are added, the hut beam 2 and the roof A1 are raised to a predetermined height (FIGS. 4 and 1).
5, see FIG. 26).
【0047】この状態で小屋梁2と床梁3との間に建屋
上部A2(2階部分)の壁軸組50、外壁材51、小屋
根52、バルコニー53および窓枠サッシ54などを組
み付け施工を行う。In this state, the wall frame 50, the outer wall material 51, the small roof 52, the balcony 53, the window frame sash 54 and the like of the upper part A2 of the building (the second floor) are assembled between the hut beam 2 and the floor beam 3. I do.
【0048】建屋上部A2の施工が終了すると、小屋梁
2を支持していた全ての継ぎ足し揚荷柱107および揚
荷柱117を一旦取り外した後に、床梁3および建屋上
部A2を所定の高さまで持ち上げる。When the construction of the upper part A2 of the building is completed, all the additional loading columns 107 and 117 which support the hut beam 2 are once removed, and then the floor beam 3 and the upper part A2 of the building are raised to a predetermined height. lift.
【0049】小屋梁2を支持している継ぎ足し揚荷柱1
07を取り外すには、ジヤッキアップ時とは逆に、油圧
シリンダ101で上方の継ぎ足し揚荷柱107を支持し
た状態で最下段の継ぎ足し揚荷柱107を取り外す作業
を繰り返すことで行われる。その場合に、各継ぎ足し揚
荷柱107はテーパ部130とソケット131によって
結合しているので、油圧シリンダ101により小屋梁2
が支持され、下段の継ぎ足し揚荷柱107に対する荷重
が取り除かれれば、この下段の継ぎ足し揚荷柱107は
その上段の継ぎ足し揚荷柱107から簡単に切り離すこ
とができる。An additional loading column 1 supporting the hut beam 2
In order to remove 07, contrary to the jack-up operation, the work of removing the lowermost reloading column 107 while the upper reloading column 107 is supported by the hydraulic cylinder 101 is repeated. In this case, since each additional unloading column 107 is connected by the tapered portion 130 and the socket 131, the shed 2
Is supported, and when the load on the lower extension landing column 107 is removed, the lower extension landing column 107 can be easily separated from the upper extension landing column 107.
【0050】すなわち、まず油圧シリンダ101を最伸
長位置まで上昇させて、最下段の継ぎ足し揚荷柱107
への荷重を取り除いてから最下段の継ぎ足し揚荷柱10
7を取り外す。次に油圧シリンダ101を収縮させて下
から2段目の継ぎ足し揚荷柱107を床梁3上の台座1
60に当接させる。That is, first, the hydraulic cylinder 101 is raised to the most extended position, and the lowermost loading column 107 is extended.
After removing the load on the lowermost loading column 10
Remove 7. Next, the hydraulic cylinder 101 is contracted to add the second-stage additional unloading column 107 from the bottom to the pedestal 1 on the floor beam 3.
60.
【0051】油圧シリンダ101を伸長させてピン11
1をその上の継ぎ足し揚荷柱107の係合孔150に係
合させる。このとき油圧シリンダ101を伸長させるに
はピン111を台座160に当接している継ぎ足し揚荷
柱107の係合孔150から引き抜く必要がある。The hydraulic cylinder 101 is extended to
1 is engaged with the engaging hole 150 of the additional loading column 107 thereon. At this time, in order to extend the hydraulic cylinder 101, it is necessary to pull out the pin 111 from the engagement hole 150 of the reloading pillar 107 abutting on the pedestal 160.
【0052】ピン111を係合孔150から引き抜いた
後、制御装置202で全ての近接スイッチが非支持状態
であることを確認してから油圧シリンダ101を伸長さ
せる。After the pin 111 is pulled out from the engagement hole 150, the control device 202 confirms that all the proximity switches are not supported, and then extends the hydraulic cylinder 101.
【0053】油圧シリンダ101が所定の位置まで上昇
したら、ピン111を上方の継ぎ足し揚荷柱107の係
合孔150に係合させる。こうして、油圧シリンダ10
1を伸縮させながら、継ぎ足し揚荷柱107を最下段か
ら順次取り外す。When the hydraulic cylinder 101 is raised to a predetermined position, the pin 111 is engaged with the engaging hole 150 of the upper reloading column 107. Thus, the hydraulic cylinder 10
While expanding and contracting 1, the additional unloading columns 107 are sequentially removed from the lowermost stage.
【0054】次に床梁3を持ち上げるには、図16およ
び図27に示すように、クロスビーム104を床梁3の
下側に移動させる。すなわち、半割りのクロスビーム1
04同士の締結を緩めてシリンダチューブ102,10
2から取り外し、シリンダチューブ102,102の中
央部の所定の位置に設けられたフランジ180のところ
で再びクロスビーム104を締結し、シリンダチューブ
102同士を連結する。Next, in order to lift the floor beam 3, the cross beam 104 is moved below the floor beam 3, as shown in FIGS. In other words, the half cross beam 1
04 and loosen the cylinder tubes 102, 10
2, the cross beam 104 is fastened again at the flange 180 provided at a predetermined position in the center of the cylinder tubes 102, 102, and the cylinder tubes 102 are connected to each other.
【0055】このようにして、クロスビーム104を床
梁3の下方に移動し、床梁3を支持した支持柱170を
このクロスビーム104の通孔140に貫き通させる。In this way, the cross beam 104 is moved below the floor beam 3, and the support column 170 supporting the floor beam 3 is penetrated through the through hole 140 of the cross beam 104.
【0056】クロスビーム104のピン111を支持柱
170に形成した係合孔150に突入係止させた後、小
屋梁2および屋根部A1の持ち上げと同様に油圧シリン
ダ101を伸長させて支持柱170を上昇させる。上昇
した支持柱170とベース105上の台座106との間
に継ぎ足し支持柱171を挿入し、油圧シリンダ101
を収縮させて下方に継ぎ足した継ぎ足し支持柱171の
係合孔150にピン111を係合させ,再び油圧シリン
ダ101を伸長させる工程を繰り返して床梁3および建
屋上部A2を所定の高さまで持ち上げる。After the pins 111 of the cross beam 104 are pushed into and engaged with the engagement holes 150 formed in the support columns 170, the hydraulic cylinder 101 is extended similarly to the lifting of the hut beam 2 and the roof A1, and the support columns 170 are extended. To rise. The supporting column 171 is inserted between the raised supporting column 170 and the pedestal 106 on the base 105, and the hydraulic cylinder 101 is inserted.
Is contracted, the pin 111 is engaged with the engagement hole 150 of the extension support pillar 171 extended downward, and the step of extending the hydraulic cylinder 101 again is repeated to lift the floor beam 3 and the building upper part A2 to a predetermined height.
【0057】この建屋上部A2を所定の高さまで持ち上
げるとき、バルコニー部分等に建築用ジャッキ装置10
0Bを補充して大きな荷重に耐えることができるように
するとよい。When the upper part A2 of the building is lifted to a predetermined height, the building jack device 10 is mounted on a balcony or the like.
It is preferable to add 0B so as to be able to withstand a large load.
【0058】ところで、ジャッキアップ時に、各建築用
ジャッキ装置100A,100Bに加わる荷重が一定で
ない場合がある。また、建築用ジャッキ装置100A,
100Bごとに上昇速度が異なって建屋に傾きや歪みが
発生することがある。そこで、各建築用ジャッキ装置1
00A,100Bに設けたストロークセンサ120と制
御装置202やポンプ200によって各油圧シリンダ1
01の上昇速度を均一に保持し、建屋に傾きや歪みを生
じることなく全体を平衡させてジャッキアップする。By the way, the load applied to each of the architectural jack devices 100A and 100B at the time of jacking up may not be constant. Also, the architectural jack device 100A,
The ascending speed is different for each 100B, and the building may be tilted or distorted. Therefore, each jack device 1 for construction
Each hydraulic cylinder 1 is controlled by a stroke sensor 120 provided in the
01 is maintained at a uniform rate, and the entire building is balanced and jacked up without causing tilting or distortion in the building.
【0059】すなわち、油圧シリンダ101と同期して
伸縮するストロークセンサ120の近接スイッチは、油
圧シリンダ101が最収縮位置から上昇するとガイド1
21に所定のピッチで設けた検出孔123を上端から下
端に向けて順次検出する。この際に各ピッチ毎に各油圧
シリンダ101の上昇速度が一致するように、最初に近
接スイッチの検出信号を発生した油圧シリンダ101の
作動油の供給を停止して上昇を中止させ、他の油圧シリ
ンダ101の近接スイッチが全て検出信号を発生した後
に再び作動油を供給して油圧シリンダ101の上昇を再
開する。That is, the proximity switch of the stroke sensor 120 which expands and contracts in synchronism with the hydraulic cylinder 101 operates when the hydraulic cylinder 101 rises from the most contracted position.
The detection holes 123 provided at a predetermined pitch in the detection holes 21 are sequentially detected from the upper end to the lower end. At this time, the supply of the hydraulic oil of the hydraulic cylinder 101 that first generates the detection signal of the proximity switch is stopped to stop the increase so that the rising speed of each hydraulic cylinder 101 matches each pitch. After all the proximity switches of the cylinder 101 have generated the detection signals, the hydraulic oil is supplied again to restart the lifting of the hydraulic cylinder 101.
【0060】このように検出信号の発生位置では先行す
る油圧シリンダ101が一旦停止して全ての油圧シリン
ダ101が同一伸長量となり、この操作を所定の高さま
で繰り返すことにより建屋全体の平行を保持して持ち上
げる。As described above, at the position where the detection signal is generated, the preceding hydraulic cylinder 101 temporarily stops and all the hydraulic cylinders 101 have the same amount of extension. By repeating this operation up to a predetermined height, the parallelism of the entire building is maintained. And lift.
【0061】なお、1つのピッチ内で油圧シリンダ10
1の上昇速度に差を生じることもあるが、検出孔123
の配設ピッチを建屋の傾きまたは歪みに影響しない範囲
で定めることにより速度差の影響を無視できる。油圧シ
リンダ101の同期制御は他の制御手段を用いてもでき
る。Note that the hydraulic cylinder 10
1 may cause a difference in the ascending speed of the detection hole 123.
The influence of the speed difference can be neglected by setting the arrangement pitch in a range that does not affect the inclination or distortion of the building. The synchronous control of the hydraulic cylinder 101 may be performed using other control means.
【0062】建屋上部A2を図7、図17に示すように
所定の高さまで持ち上げた後に、床梁3とコンクリート
基礎1との間に建屋下部A3(1階部分)の壁軸組7
0、外壁材71、窓枠サッシ72および玄関ドア73な
どを組み付け施工して建屋A4を完成させる。After the upper part A2 of the building is raised to a predetermined height as shown in FIGS. 7 and 17, the wall frame 7 of the lower part A3 of the building (the first floor portion) is placed between the floor beam 3 and the concrete foundation 1.
0, the outer wall material 71, the window frame sash 72, the entrance door 73 and the like are assembled and constructed to complete the building A4.
【0063】上記した2階のある建屋の建方工法の実施
例において、建築用ジャッキ装置の揚荷柱は小屋梁のみ
を支持しておき、床梁3を持ち上げるとき、小屋梁を支
持していた揚荷柱を用いてジャッキアップするようにし
てもよい。また、平屋の建築にも本発明の建方工法を適
用できる。In the above-described embodiment of the construction method for a building with two floors, the landing column of the jack device for building supports only the hut beam, and supports the hut beam when the floor beam 3 is lifted. You may make it jack-up using the unloading pillar. The construction method of the present invention can be applied to a one-story building.
【0064】すなわち、コンクリート基礎1の上にスペ
ーサである仮設材4を介して小屋梁2を載置し、小屋梁
2の少なくとも4箇所を予め所定位置に設置した各建築
用ジャッキ装置100Aの揚荷柱117で支持する。建
築用ジャッキ装置100Aで小屋梁2を支持した後、小
屋梁2の上に屋根部A1を組み立てて完成させ、建築用
ジャッキ装置100Aの油圧シリンダ101を伸長させ
て屋根部A1および小屋梁2をクロスビーム104に連
結された揚荷柱117を介して持ち上げる。油圧シリン
ダ101が伸長したら、揚荷柱117と建築用ジャッキ
装置100Aのベース105に立設した支持柱170と
の間に油圧シリンダ101の全ストローク量より若干短
い第1の継ぎ足し揚荷柱107を接続する。That is, the cabin beam 2 is placed on the concrete foundation 1 through the temporary material 4 which is a spacer, and at least four places of the cabin beam 2 are lifted in advance in each jacking apparatus 100A for construction. It is supported by the load post 117. After supporting the shed beam 2 with the construction jack device 100A, the roof portion A1 is assembled on the shed beam 2 and completed, and the hydraulic cylinder 101 of the construction jack device 100A is extended to remove the roof portion A1 and the shed beam 2. It is lifted via the unloading column 117 connected to the cross beam 104. When the hydraulic cylinder 101 extends, the first additional loading column 107, which is slightly shorter than the total stroke of the hydraulic cylinder 101, is provided between the unloading column 117 and the supporting column 170 erected on the base 105 of the jack device 100A for construction. Connecting.
【0065】クロスビーム104のピン111を揚荷柱
117の係合孔150から引き抜き、各油圧シリンダ1
01をいっせいに縮小させて屋根部A1および小屋梁2
の荷重を揚荷柱117、第1の継ぎ足し揚荷柱107お
よび支持柱170を介して支持する。次いで、クロスビ
ーム104のピン111を第1の継ぎ足し揚荷柱107
の係合孔150に係止させた後、再び油圧シリンダ10
1を伸長させて、屋根部A1および小屋梁2を揚荷柱1
17および第1の継ぎ足し揚荷柱107を介して持ち上
げ、第1の継ぎ足し揚荷柱107と支持柱170との間
に第2の継ぎ足し揚荷柱107を接続する。このよう
な、継ぎ足し揚荷柱107の接続作業、クロスビーム1
04と継ぎ足し揚荷柱107とのピン111による連結
とその解除作業および油圧シリンダ101の伸縮作業を
繰り返して屋根部A1および小屋梁2を設定高さ位置ま
で上昇させた後、小屋梁2とコンクリート基礎1との間
に壁軸組70、外壁材71、窓枠サッシ、玄関ドアなど
の組み付けを行うものである。The pin 111 of the cross beam 104 is pulled out from the engagement hole 150 of the unloading column 117, and each hydraulic cylinder 1
01 together to reduce the roof part A1 and the shed beam 2
Of the load is supported via the unloading column 117, the first additional unloading column 107 and the supporting column 170. Then, the pin 111 of the cross beam 104 is added to the first extension unloading column 107.
After engaging with the engagement hole 150 of the hydraulic cylinder 10 again.
1 to extend the roof portion A1 and the hut beam 2 to the unloading column 1
17 and the first additional unloading column 107 are lifted, and the second additional unloading column 107 is connected between the first additional unloading column 107 and the support column 170. Such connecting work of the additional loading column 107, the cross beam 1
04 and the additional unloading column 107 are repeatedly connected and released by the pin 111 and the expansion and contraction work of the hydraulic cylinder 101 to raise the roof portion A1 and the shed beam 2 to the set height position, and then the shed beam 2 and the concrete. The wall shaft assembly 70, the outer wall material 71, the window frame sash, the entrance door, etc. are assembled with the foundation 1.
【0066】[0066]
【0067】[0067]
【発明の効果】以上のように本発明によれば、コンクリ
ート基礎上で屋根部を先行して完成させた後、建築用ジ
ャッキ装置を伸縮させるとともに、複数本の継ぎ足し揚
荷柱を接続して屋根部を設定高さ位置まで持ち上げ、持
ち上げた屋根部の下方空間に壁軸組や外壁材などを組み
付けることにより、クレーン車などの作業機械を使用す
る必要がなく、また、安全ネットや高所作業用足場など
の仮設設備が不要となり、狭小地であっても平屋建ての
家屋を建築することができる。As described above, according to the present invention, after the roof portion is completed on the concrete foundation in advance, the construction jack device is expanded and contracted, and a plurality of additional loading columns are connected. By lifting the roof to the set height position and assembling the wall frame and outer wall materials in the space below the lifted roof, it is not necessary to use work machines such as crane trucks, and safety nets and high places. Temporary equipment such as scaffolding for work is not required, and it is possible to build a one-story house even in a small land.
【0068】また、ほとんど地上およびその近傍での作
業となることから、作業者は安全に作業することができ
るとともに、高所作業用足場などの仮設設備が不要とな
り、建築費用を削減することができる。Further, since the work is carried out almost on the ground and in the vicinity thereof, the worker can work safely, and temporary equipment such as scaffolding for working at high places becomes unnecessary, and the construction cost can be reduced. it can.
【0069】しかも、屋根部を先行して完成させるた
め、風雨などによって資材が濡れて品質の低下を招くこ
とがなく、天候に左右されずに施行することが可能とな
り、工期を短縮することができる。Moreover, since the roof is completed first, the material does not get wet due to wind and rain and the quality is not deteriorated. It can be carried out regardless of the weather, and the construction period can be shortened. it can.
【0070】[0070]
【0071】[0071]
【0072】[0072]
【0073】[0073]
【図1】本発明建方工法の最初の工程を示す部分拡大断
面図である。FIG. 1 is a partially enlarged sectional view showing the first step of the construction method according to the present invention.
【図2】本発明建方工法により屋根部の形成を正面から
示した断面図である。FIG. 2 is a cross-sectional view showing the formation of a roof portion from the front according to the construction method of the present invention.
【図3】コンクリート基礎上で屋根部を仕上げた正面図
である。FIG. 3 is a front view showing a finished roof part on a concrete foundation.
【図4】仕上げた屋根部を建築用ジャッキ装置を用いて
所定の位置までジャッキアップした正面図である。FIG. 4 is a front view in which the finished roof is jacked up to a predetermined position using a building jack device.
【図5】所定の位置まで持ち上げられた小屋梁とコンク
リート基礎上に載置している床梁との間に2階の壁軸組
を組み付けた正面図である。FIG. 5 is a front view in which a second-story wall shaft assembly is assembled between a hut beam raised to a predetermined position and a floor beam placed on a concrete foundation.
【図6】コンクリート基礎上で2階の外装材を組み付け
た正面図である。FIG. 6 is a front view in which a second-floor exterior material is assembled on a concrete foundation.
【図7】屋根部と建屋上部を建築用ジャッキ装置を用い
て所定の位置までジャッキアップした正面図である。FIG. 7 is a front view in which the roof and the upper part of the building are jacked up to a predetermined position using a jacking device for construction.
【図8】所定の位置まで持ち上げられた床梁とコンクリ
ート基礎との間に1階の壁軸組を組み付けた正面図であ
る。FIG. 8 is a front view in which a wall shaft assembly on the first floor is assembled between a floor beam raised to a predetermined position and a concrete foundation.
【図9】1階の外装材を組み付けて完成した建屋の正面
図である。FIG. 9 is a front view of a building completed by assembling exterior materials on the first floor.
【図10】コンクリート基礎上で屋根部を形成した部分
断面図である。FIG. 10 is a partial sectional view in which a roof portion is formed on a concrete foundation.
【図11】仕上げた屋根部を建築用ジャッキ装置を用い
てジャッキアップする部分断面図である。FIG. 11 is a partial cross-sectional view in which the finished roof is jacked up using a building jack device.
【図12】揚荷柱の下に第1の継ぎ足し揚荷柱を挿入し
た部分断面図である。FIG. 12 is a partial sectional view in which a first additional loading column is inserted below the discharging column.
【図13】第1の継ぎ足し揚荷柱とクロスビームとを係
合させた部分断面図である。FIG. 13 is a partial cross-sectional view in which a first extension landing column is engaged with a cross beam.
【図14】複数本の継ぎ足し揚荷柱を継ぎ足して屋根部
を所定の位置までジャッキアップした部分断面図であ
る。FIG. 14 is a partial cross-sectional view in which a plurality of extension columns are added to jack up the roof to a predetermined position.
【図15】小屋梁と床梁との間に壁軸組を組み付けた部
分断面図である。FIG. 15 is a partial cross-sectional view in which a wall axle is assembled between a hut beam and a floor beam.
【図16】クロスビームをシリンダチューブの中央部に
着け換え、支持柱にクロスビームを係合させた部分断面
図である。FIG. 16 is a partial cross-sectional view in which a cross beam is replaced with a central portion of a cylinder tube, and the cross beam is engaged with a support column.
【図17】屋根部および建屋上部を所定の位置にジャッ
キアップした部分断面図である。FIG. 17 is a partial sectional view in which a roof and an upper part of a building are jacked up at predetermined positions.
【図18】所定の位置まで持ち上げられた床梁とコンク
リート基礎との間に1階の壁軸組を組み付けた部分断面
図である。FIG. 18 is a partial cross-sectional view in which the wall shaft assembly on the first floor is assembled between the floor beam lifted to a predetermined position and the concrete foundation.
【図19】建築用ジャッキ装置の作動と制御を示す概略
斜視図である。FIG. 19 is a schematic perspective view showing the operation and control of the building jack device.
【図20】建築用ジャッキ装置の揚荷柱をピストンロッ
ドのストロークいっぱいに上昇させた正面図である。FIG. 20 is a front view of the unloading column of the architectural jack device raised to the full stroke of the piston rod.
【図21】揚荷柱と床梁上の台座との間に第1の継ぎ足
し揚荷柱を挿入した正面図である。FIG. 21 is a front view in which the first additional loading column is inserted between the loading column and the pedestal on the floor beam.
【図22】ピストンロッドを収縮させてクロスビームの
ピンを第1の継ぎ足し揚荷柱に形成した係合孔に係合さ
せた正面図である。FIG. 22 is a front view in which the piston rod is contracted so that the cross beam pin is engaged with the engagement hole formed in the unloading column by the first addition.
【図23】第1の継ぎ足し揚荷柱をピストンロッドのス
トロークいっぱいに上昇させた正面図である。FIG. 23 is a front view in which the first additional loading column is raised to the full stroke of the piston rod.
【図24】第1の継ぎ足し揚荷柱と床梁上の台座との間
に第2の継ぎ足し揚荷柱を挿入した正面図である。FIG. 24 is a front view in which a second additional discharge column is inserted between the first additional discharge column and the pedestal on the floor beam.
【図25】ピストンロッドを収縮させてクロスビームの
ピンを第2の継ぎ足し揚荷柱に形成した係合孔に係合さ
せた正面図である。FIG. 25 is a front view in which a piston rod is contracted so that a pin of a cross beam is engaged with an engagement hole formed in a second reloading column.
【図26】小屋梁を所定の位置にジャッキアップした建
築用ジャッキ装置の正面図である。FIG. 26 is a front view of the architectural jack device in which a hut beam is jacked up to a predetermined position.
【図27】小屋梁と床梁との間に2階の壁軸組を組み付
け、クロスビームをシリンダチューブの中央部に着け換
え、クロスビームのピンを支持柱に係合させた正面図で
ある。FIG. 27 is a front view in which a wall shaft assembly on the second floor is assembled between a hut beam and a floor beam, a cross beam is replaced with a central portion of a cylinder tube, and pins of the cross beam are engaged with support columns. .
【図28】床梁を支持する支持柱をピストンロッドのス
トロークいっぱいに上昇させた正面図である。FIG. 28 is a front view in which a support column supporting a floor beam is raised to the full stroke of a piston rod.
【図29】ベース上の台座と支持柱との間に第1の継ぎ
足し支持柱を挿入した正面図である。FIG. 29 is a front view in which a first extension support column is inserted between a base on the base and the support column.
【図30】油圧シリンダを収縮させてクロスビームのピ
ンを第1の継ぎ足し支持柱に係合させた正面図である。FIG. 30 is a front view in which the hydraulic cylinder is contracted and the pin of the cross beam is engaged with the first extension support column.
【図31】床梁上の台座とベース上の台座を拡大して示
す正面図である。FIG. 31 is an enlarged front view showing a pedestal on a floor beam and a pedestal on a base.
【図32】継ぎ足しストラットおよび継ぎ足し支持柱の
断面図である。FIG. 32 is a cross-sectional view of a reinforced strut and a reinforced support column.
1 コンクリート基礎 2 小屋梁 3 床梁 4 仮設材 50,70 壁軸組 51,71 外壁材 52 小屋根 53 バルコニー 54,72 窓枠サッシ 73 玄関ドア 100 建築用ジャッキ装置 101 油圧シリンダ 102 シリンダチューブ 103 ピストンロッド 104 クロスビーム 105 ベース 106,160 台座 107 継ぎ足し揚荷柱 108,180 フランジ 111 ピン 117 揚荷柱 120 ストロークセンサ 130 テーパ部 131 ソケット 150 係合孔 170 支持柱 171 継ぎ足し支持柱 200 ポンプ 202 制御装置 203 制御コード A1 屋根部 A2 建屋上部 A3 建屋下部 A4 建屋 DESCRIPTION OF SYMBOLS 1 Concrete foundation 2 Hut beam 3 Floor beam 4 Temporary material 50, 70 Wall frame 51, 71 Exterior wall material 52 Roof 53 Balcony 54, 72 Window frame sash 73 Entrance door 100 Building jack device 101 Hydraulic cylinder 102 Cylinder tube 103 Piston Rod 104 cross beam 105 base 106,160 pedestal 107 extension landing column 108,180 flange 111 pin 117 lifting column 120 stroke sensor 130 taper portion 131 socket 150 engagement hole 170 support column 171 extension extension column 200 pump 202 control device 203 Control code A1 Roof A2 Upper building A3 Lower building A4 Building
Claims (1)
に並設して連結した2本の油圧シリンダと、これらの油
圧シリンダのシリンダチューブに連結されたクロスビー
ムとからなり、このクロスビームにピンを介して揚荷柱
を着脱自在に連結するとともに、ベースに支持柱を立設
して構成された複数個の建築用ジャッキ装置をそれぞれ
所定位置に設置し、コンクリート基礎の上に仮設材を介
して載置された小屋梁の小なくとも4箇所を各建築用ジ
ャッキ装置に連結された揚荷柱で支持した後、小屋梁の
上に屋根部を組み立てて完成され、次いで、建築用ジャ
ッキ装置の油圧シリンダを伸長させて屋根部および小屋
梁を揚荷柱を介して持ち上げた後、揚荷柱と支持柱との
間に第1の継ぎ足し揚荷柱を接続し、クロスビームと揚
荷柱との連結を解除して油圧シリンダを縮小させて屋根
部および小屋梁を揚荷柱、第1の継ぎ足し揚荷柱および
支持柱を介して支持し、次いで、クロスビームと第1の
継ぎ足し揚荷柱とを連結した後、再び油圧シリンダを伸
長させて屋根部および小屋梁を揚荷柱および第1の継ぎ
足し揚荷柱を介して持ち上げ、第1の継ぎ足し揚荷柱と
支持柱との間に第2の継ぎ足し揚荷柱を接続し、以上の
設定本数の継ぎ足し揚荷柱の接続作業、クロスビームと
継ぎ足し揚荷柱との連結とその解除作業および油圧シリ
ンダの伸縮作業を繰り返して屋根部および小屋梁を設定
高さ位置まで上昇させた後、小屋梁とコンクリート基礎
との間に壁軸組、外壁材、窓枠サッシ、玄関ドアなどの
組み付けを行うことを特徴とする建方工法。1. The base of each of the piston rod tips
And two hydraulic cylinders connected in parallel to each other and these oils.
Crossbee connected to cylinder tube of pressure cylinder
And a unloading column consisting of pins on this cross beam
While detachably connecting, support pillars are erected on the base.
Each of a plurality of construction jack devices configured by
Place it in place and put a temporary material on the concrete foundation.
The huts placed on the floor are installed in each of the 4
After supporting it by the unloading column connected to the jack device,
Completed by assembling the roof part on top, and then the building jar
The hydraulic cylinder of the kick device is extended to extend the roof and the hut.
After lifting the beam through the unloading column,
Connect the first additional unloading column between the
The roof is released by disconnecting the hydraulic cylinder from the load column.
Section and hut beam to the unloading column, the first extension unloading column and
Support through the support column, then cross beam and first
Extend the hydraulic cylinder again after connecting the additional loading column.
Lengthen roof part and shack beam to unloading column and first splice
Lifted via the additional unloading column and the first additional unloading column
Connect the second extension unloading column between the supporting column and
Connection work of additional unloading columns of set number, cross beam and
Connection with additional loading column and its release work and hydraulic series
Repeat roof expansion and contraction work to set roof and hut beams
After raising to the height position, the hut beam and concrete foundation
Between wall frame, outer wall material, window frame sash, entrance door, etc.
The erection method that is characterized by assembling .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4336332A JP2682778B2 (en) | 1992-12-16 | 1992-12-16 | Construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4336332A JP2682778B2 (en) | 1992-12-16 | 1992-12-16 | Construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06185212A JPH06185212A (en) | 1994-07-05 |
JP2682778B2 true JP2682778B2 (en) | 1997-11-26 |
Family
ID=18298027
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4336332A Expired - Fee Related JP2682778B2 (en) | 1992-12-16 | 1992-12-16 | Construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2682778B2 (en) |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS52120512A (en) * | 1976-04-03 | 1977-10-11 | Nat Jutaku Kenzai | Second story enlargement device in unit residence |
JPS57116848A (en) * | 1980-12-31 | 1982-07-21 | Nat Jutaku Kenzai | Construction of plural stairs building |
JP2678403B2 (en) * | 1991-02-02 | 1997-11-17 | 株式会社河原 | Construction method of building structure and connection method of pillar members |
JP3072176B2 (en) * | 1992-03-03 | 2000-07-31 | 日本鉱機株式会社 | Jack for construction work |
JP2672058B2 (en) * | 1992-07-27 | 1997-11-05 | 株式会社クボタ | Construction method of steel framed house |
-
1992
- 1992-12-16 JP JP4336332A patent/JP2682778B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH06185212A (en) | 1994-07-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4076778A (en) | Climbing formwork | |
US20200284026A1 (en) | Vertical slip form construction system with multi-function platform, and method of constructing a building therewith | |
JP2765790B2 (en) | Construction method | |
US4782634A (en) | Building construction | |
JP2682778B2 (en) | Construction method | |
JP3049402B2 (en) | Supporting type scaffold form lifting device and concrete skeleton construction method | |
JP2682779B2 (en) | Construction method | |
JP2682780B2 (en) | Construction method | |
JP3597034B2 (en) | How to build a house | |
JPH1061193A (en) | Method of building steel frame structure and device therefor | |
CN107419807B (en) | Building construction method | |
JPH11200631A (en) | Building method for house | |
JP3038076B2 (en) | Jack device for construction work | |
JP3110904B2 (en) | Telescopic stay columns for construction work | |
JP3028265B2 (en) | Driven floor advance lifting method | |
JPH11200503A (en) | Construction of house | |
JPH10292629A (en) | Method for constructing house | |
CN211421802U (en) | High-rise building construction machinery | |
JP2653630B2 (en) | How to raise the temporary roof | |
JPH08218628A (en) | Construction of roof for cylindrical structure | |
JP2653629B2 (en) | Jack-up device for temporary roof | |
CN114893022A (en) | Floor descending device for reverse building demolition and construction method | |
JP3190738B2 (en) | Jack for construction work | |
JP2696486B2 (en) | Building construction method | |
JPH06101280A (en) | Method of erection construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |