JP2677096B2 - Instruction method of cargo handling work - Google Patents

Instruction method of cargo handling work

Info

Publication number
JP2677096B2
JP2677096B2 JP4009429A JP942992A JP2677096B2 JP 2677096 B2 JP2677096 B2 JP 2677096B2 JP 4009429 A JP4009429 A JP 4009429A JP 942992 A JP942992 A JP 942992A JP 2677096 B2 JP2677096 B2 JP 2677096B2
Authority
JP
Japan
Prior art keywords
work
cargo handling
forklifts
work content
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP4009429A
Other languages
Japanese (ja)
Other versions
JPH05197425A (en
Inventor
隆司 林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toyota Industries Corp
Original Assignee
Toyota Industries Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyota Industries Corp filed Critical Toyota Industries Corp
Priority to JP4009429A priority Critical patent/JP2677096B2/en
Publication of JPH05197425A publication Critical patent/JPH05197425A/en
Application granted granted Critical
Publication of JP2677096B2 publication Critical patent/JP2677096B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Control Of Position, Course, Altitude, Or Attitude Of Moving Bodies (AREA)
  • Forklifts And Lifting Vehicles (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、全体の荷役作業を管
理する管理部から個々の作業内容を複数の荷役車両の各
々へ通信手段を使用して指示する荷役作業の指示方法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of instructing a cargo handling operation in which a management section for managing the entire cargo handling operation instructs each work content to each of a plurality of cargo handling vehicles using communication means. .

【0002】[0002]

【従来の技術】従来、荷役車両を使用した物流システム
においては、全体の荷役作業を管理する管理部にホスト
コンピュータ等が備え付けられている。そして、そのホ
ストコンピュータが各荷役車両から作業指示の要求を受
けたときに、作業内容を適宜に選択して、要求のあった
荷役車両へ指示するようにしている。この場合、荷役車
両と管理部との間の作業要求や作業指示のやりとりの方
法としては、例えば無線方式のLAN(ローカル・エリ
ア・ネットワーク)が採用されている。例えば、荷役車
両としてのフォークリフトに無線装置及びデータ端末機
を搭載し、管理部のホストコンピュータに接続された無
線装置を構内の適宜な位置に配置する。そして、フォー
クリフトから作業指示要求のデータをホストコンピュー
タへ送る場合には、その作業指示要求のデータをフォー
クリフトのデータ端末機から無線装置へ出力して電波を
介して発信させている。又、ホストコンピュータでは、
その作業要求のデータを受けて作業内容のデータをフォ
ークリフトへ送る場合に、その発信すべき作業内容のデ
ータをホストコンピュータから無線装置へ出力して電波
を介して発信させている。
2. Description of the Related Art Conventionally, in a physical distribution system using a cargo handling vehicle, a host computer or the like is provided in a management unit for managing the entire cargo handling work. Then, when the host computer receives a request for a work instruction from each cargo handling vehicle, the content of the work is appropriately selected and an instruction is given to the cargo handling vehicle that has made the request. In this case, as a method of exchanging work requests and work instructions between the cargo handling vehicle and the management unit, for example, a wireless LAN (local area network) is adopted. For example, a wireless device and a data terminal are mounted on a forklift as a cargo handling vehicle, and the wireless device connected to the host computer of the management unit is arranged at an appropriate position in the premises. When the data of the work instruction request is sent from the forklift to the host computer, the data of the work instruction request is output from the data terminal of the forklift to the wireless device and transmitted via a radio wave. In the host computer,
When the work request data is received and the work content data is sent to the forklift, the work content data to be transmitted is output from the host computer to the wireless device and transmitted via radio waves.

【0003】ここで、ホストコンピュータから複数のフ
ォークリフトへ個々の作業内容を指示する方法として
は、例えば図10に示すように、ホストコンピュータの
メモリ記憶領域30Aに登録されている全作業内容に関
わる作業内容テーブル31について、図11に示すよう
に、作業の対象となる荷の「種別」毎に担当フォークリ
フトの番号を種別テーブル32として予め定めてメモリ
記憶領域30Bに登録しておく。そして、ホストコンピ
ュータでは、フォークリフトから作業指示の要求があっ
た場合に、種別テーブル32からそのフォークリフトが
担当すべき荷の種別を参照する。次いで、ホストコンピ
ュータでは、種別テーブル32で参照した「種別」を対
象とした作業内容の指示を図10に示す作業内容テーブ
ル31から選択する。そして、ホストコンピュータは、
その選択された作業内容のデータを無線装置を介して、
要求のあったフォークリフトのデータ端末機へ送信す
る。
Here, as a method of instructing individual work contents from the host computer to a plurality of forklifts, for example, as shown in FIG. 10, works related to all work contents registered in the memory storage area 30A of the host computer. With respect to the content table 31, as shown in FIG. 11, the number of the forklift in charge for each "type" of the load to be worked is predetermined as a type table 32 and registered in the memory storage area 30B. Then, when a work instruction is requested from the forklift, the host computer refers to the type table 32 for the type of load to be handled by the forklift. Next, the host computer selects an instruction of the work content for the “type” referred to in the type table 32 from the work content table 31 shown in FIG. And the host computer
The data of the selected work content is transmitted via the wireless device,
The request is sent to the data terminal of the forklift.

【0004】或いは、ホストコンピュータにて、図10
に示す作業内容テーブル31について、図12に示すよ
うに、作業の対象となる荷の「置き場所」毎に担当フォ
ークリフトの番号を置き場所テーブル33として予め定
めてメモリ記憶領域30Cに登録しておき、各フォーク
リフトからの作業指示の要求を受けたときに、上記に準
ずるような手順で、要求のあったフォークリフトへ作業
内容の指示を行う。
Alternatively, in the host computer, as shown in FIG.
With respect to the work content table 31 shown in FIG. 12, as shown in FIG. 12, the number of the forklift in charge for each "placement" of the load to be worked is predetermined as the placement place table 33 and registered in the memory storage area 30C. When receiving a request for a work instruction from each forklift, the work content is instructed to the requested forklift in a procedure similar to the above.

【0005】[0005]

【発明が解決しようとする課題】ところが、前記従来技
術では、その日によっては、全作業内容のうち作業の対
象となる荷の「種別」や「置き場所」が異なることか
ら、特定のフォークリフトのみに作業が集中することが
あり、各フォークリフトで作業の忙しさにバラツキの生
じることがあった。又、荷の「種別」毎や「置き場所」
毎に決められた担当フォークリフトの一部が故障して抜
けた場合には、その担当フォークリフトに対応する作業
内容のみが残ってしまうことになった。そのため、一部
のフォークリフトが抜けた日には、残りのフォークリフ
トに対する作業指示の内容を応急的にいちいち追加変更
したり、或いは残された作業内容を後回しにして最後に
残りのフォークリフトで人為的に分担して処理しなけれ
ばならなかった。又、一部の作業内容が後回しになるこ
とから、その作業内容のみが大幅に遅れて処理されるこ
とになり問題となっていた。
However, in the above-mentioned prior art, since the "type" and "place" of the load to be worked out of all the work contents are different depending on the day, only the specific forklift is used. The work may be concentrated, and the busyness of the work may vary from one forklift to another. Also, for each "type" and "place"
If a part of the assigned forklift breaks down due to a breakdown, only the work corresponding to the assigned forklift remains. Therefore, on the day when some of the forklifts are removed, the contents of the work instructions for the remaining forklifts may be added or changed as soon as possible, or the remaining work contents may be postponed, and finally the remaining forklifts may be used artificially with the remaining forklifts. It had to be shared. Also, since some of the work contents are postponed, only the work contents are processed with a considerable delay, which has been a problem.

【0006】一方、前記従来技術では、フォークリフト
のオペレータにとって、その時々に指示された作業内容
の情報のみしか得ることができず、全作業内容の残量
や、自車の行うべき作業内容の残量を把握することがで
きなかった。そのため、個々のオペレータとしては、必
要に応じて自身の判断により自車の作業スピードを調節
することができず、全体の荷役作業の効率を上げること
に寄与できなかった。
On the other hand, in the above-mentioned prior art, the operator of the forklift can obtain only the information of the work contents instructed at that time, and the remaining work contents and the work contents to be performed by the own vehicle remain. I could not figure out the amount. Therefore, each operator cannot adjust the work speed of the own vehicle according to his / her own judgment as necessary, and cannot contribute to improving the efficiency of the overall cargo handling work.

【0007】この発明は前述した事情に鑑みてなされた
ものであって、その目的は、特定の荷役車両のみに作業
が集中することを防止すると共に、一部の荷役車両が抜
けた場合でも自動的に対処して作業の仕残しを防止する
ことが可能で、しかも個々の荷役車両がその作業スピー
ドを調節して全体の荷役作業の効率を向上させることの
可能な荷役作業の指示方法を提供することにある。
The present invention has been made in view of the above-mentioned circumstances, and an object thereof is to prevent the work from being concentrated on a specific cargo handling vehicle and to automatically operate even when a part of the cargo handling vehicle is pulled out. Providing a method of instructing cargo handling work that can prevent the work from being left unprocessed and that each cargo handling vehicle can adjust the work speed to improve the efficiency of the whole cargo handling work To do.

【0008】[0008]

【課題を解決するための手段】上記の目的を達成するた
めに、この発明においては、全体の荷役作業を管理する
管理部から個々の作業内容を複数の荷役車両の各々へ通
信手段を使用して選択的に指示する荷役作業の指示方法
において、管理部にて、全体の荷役作業に関わる荷の置
き場所を複数の荷役ゾーンに分類して予め定めておき、
同じく管理部にて、各荷役車両毎に担当すべき荷役ゾー
ンの優先順位を前記全荷役ゾーンについて予め定めてお
き、管理部にて、全作業内容をその作業の対象となる荷
の置き場所の違いに応じて各荷役ゾーン毎の複数の作業
集合として分類しておき、管理部が、各荷役車両から作
業指示の要求を受けたときに、空集合となっていない各
作業集合のうち作業指示の要求のあった荷役車両にとっ
て最も優先順位の高い荷役ゾーンに対応する作業集合の
中から未だ実行されていない作業内容を選択し、併せて
管理部が、その他の作業内容の残量を集計し、管理部
が、選択された作業内容とその他の作業内容の残量を通
信手段を使用して作業指示の要求のあった荷役車両へ指
示送信するようにしている。
In order to achieve the above-mentioned object, in the present invention, a communication means is used for each individual work content from a management unit for managing the overall cargo handling work to each of a plurality of cargo handling vehicles. In the method of instructing the cargo handling operation to selectively instruct, in the management unit, the place of placement of the load related to the overall cargo handling work is classified into a plurality of cargo handling zones and determined in advance,
Similarly, in the management unit, the priority order of the cargo handling zones to be in charge for each cargo handling vehicle is determined in advance for all the cargo handling zones, and the management unit specifies all the work contents of the loading place of the load as the target of the work. Depending on the difference, it is classified as multiple work sets for each cargo handling zone, and when the management unit receives a work instruction request from each cargo handling vehicle, the work instructions in each work set that are not empty The work content that has not yet been executed is selected from the work set corresponding to the cargo handling zone with the highest priority for the cargo handling vehicle for which the request is made, and at the same time, the management unit aggregates the remaining amount of other work content. The management unit uses the communication means to transmit the remaining amount of the selected work content and the remaining work content to the cargo handling vehicle that has requested the work instruction.

【0009】[0009]

【作用】上記の発明の構成によれば、管理部が各荷役車
両から作業指示の要求を受けたときには、空集合となっ
ていない各作業集合のうち要求のあった荷役車両にとっ
て最も優先順位の高い荷役ゾーンに対応する作業集合の
中から作業内容が選択される。併せて、その他の作業内
容の残量が集計される。そして、選択された作業内容と
その他の作業内容の残量とが要求のあった荷役車両へ指
示送信される。
According to the configuration of the invention described above, when the management unit receives a work instruction request from each cargo handling vehicle, it has the highest priority for the requested cargo handling vehicle among the respective work sets that are not empty sets. The work content is selected from the work set corresponding to the high cargo handling zone. At the same time, the remaining amount of other work contents is totaled. Then, the selected work content and the remaining amount of other work content are instructed and transmitted to the requested cargo handling vehicle.

【0010】そのため、個々の荷役車両では、優先順位
の高い荷役ゾーンに対応する作業内容から、優先順位の
低い荷役ゾーンに対応する作業内容へと順次に指示を受
けることになる。そして、各荷役ゾーンに属する作業内
容は高い優先順位で分担された個々の荷役車両の協働に
よって順次に処理され、作業内容の多い荷役ゾーンにつ
いてはその他の荷役車両によっても処理されることにな
る。従って、一部の荷役車両の抜けの有無にかかわら
ず、全作業内容が各荷役車両によって自動的に順次に処
理される。
Therefore, each cargo handling vehicle sequentially receives instructions from the work content corresponding to the cargo handling zone having a high priority to the work content corresponding to the cargo handling zone having a low priority. The work contents belonging to each cargo handling zone are sequentially processed by the cooperation of the individual cargo handling vehicles assigned with high priority, and the cargo handling zones with a large work content are also processed by other cargo handling vehicles. . Therefore, regardless of the presence or absence of some of the cargo handling vehicles, all the work contents are automatically and sequentially processed by each cargo handling vehicle.

【0011】又、その他の作業内容の残量が荷役車両へ
送信されることから、荷役車両では、その他の作業内容
の残量を自車の作業スピードの調節のために利用するこ
とが可能となる。
Further, since the remaining amount of the other work contents is transmitted to the cargo handling vehicle, the remaining amount of the other work contents can be used in the cargo handling vehicle for adjusting the working speed of the own vehicle. Become.

【0012】[0012]

【実施例】以下、上記の発明における荷役作業の指示方
法を無線方式のLANを使用したフォークリフトの物流
システムに具体化した一実施例を図1〜図9に基づいて
詳細に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment in which the method of instructing cargo handling work according to the above-mentioned invention is embodied in a forklift physical distribution system using a wireless LAN will be described in detail with reference to FIGS.

【0013】図1は無線方式のLANを使用したフォー
クリフトの物流システムを示す概略構成図である。構内
には複数台(この場合4台)の荷役車両としての有人式
フォークリフト1A,1B,1C,1Dが運行されてい
る。
FIG. 1 is a schematic configuration diagram showing a physical distribution system of a forklift truck using a wireless LAN. A plurality of (in this case, four) manned forklifts 1A, 1B, 1C, and 1D as cargo handling vehicles are operated on the premises.

【0014】各フォークリフト1A〜1Dには図2に示
すような移動局を構成する通信手段としての無線装置
2、データ端末機3及びプリンタ4が搭載されている。
この移動局側の無線装置2は所望のデータを含む電波の
送受信を行う装置であり、その送受信のために信号の変
調及び復調を行う。この無線装置2は同軸ケーブル5を
介してデータ端末機3に接続され、両者2,3の間でデ
ータのやりとりが行われる。データ端末機3は各種信号
を入出力する入出力インターフェイス、その入力信号に
基づいて所定の演算・制御を実行する中央処理装置(C
PU)、そのCPUでの演算結果等を記憶する各種メモ
リ等を備えたマイクロコンピュータにより構成されてい
る。又、データ端末機3はオペレータによるデータ入力
を行うためのキーボード6やデータ表示のためのディス
プレイ7を備えている。更に、データ端末機3は無線装
置2の作動を制御するための制御機能も備えている。併
せて、データ端末機3は同軸ケーブル8を介してプリン
タ4に接続され、データ端末機3に入力されたデータを
プリンタ4にて出力印字可能になっている。
Each of the forklifts 1A to 1D is equipped with a radio device 2 as a communication means, a data terminal 3 and a printer 4, which constitute a mobile station as shown in FIG.
The mobile station-side wireless device 2 is a device that transmits and receives radio waves including desired data, and performs modulation and demodulation of signals for the transmission and reception. The wireless device 2 is connected to a data terminal 3 via a coaxial cable 5, and data is exchanged between the two. The data terminal 3 has an input / output interface for inputting / outputting various signals, and a central processing unit (C) for executing a predetermined operation / control based on the input signals.
PU), and a microcomputer including various memories for storing calculation results and the like in the CPU. The data terminal 3 includes a keyboard 6 for inputting data by an operator and a display 7 for displaying data. Further, the data terminal 3 has a control function for controlling the operation of the wireless device 2. At the same time, the data terminal 3 is connected to the printer 4 via a coaxial cable 8 so that the data input to the data terminal 3 can be output and printed by the printer 4.

【0015】一方、図1において、構内の天井近くの適
宜な位置には、複数台(この場合3台)の固定局を構成
する通信手段としての無線装置9A,9B,9Cが分散
配置されている。ここで、この固定局側の無線装置9A
〜9Cは所望のデータを含む電波の送受信を行うと共
に、その送受信のために信号の変調及び復調を行う。
又、各無線装置9A〜9Cから発信されるべき電波は電
波法の規定に則って微弱な電波に制限されているので、
広い構内の全域に渡って固定局側と移動局側との間の通
信を可能にするために、各固定局側の無線装置9A〜9
Cの通信可能な範囲が相互に重ね合わされて構内全域に
広げられている。
On the other hand, in FIG. 1, wireless devices 9A, 9B and 9C as communication means which constitute a plurality of fixed stations (three in this case) are dispersedly arranged at appropriate positions near the ceiling in the premises. There is. Here, the fixed-station-side wireless device 9A
9C perform transmission and reception of radio waves including desired data, and also modulate and demodulate signals for the transmission and reception.
Also, radio waves to be transmitted from each of the wireless devices 9A to 9C are limited to weak radio waves in accordance with the provisions of the Radio Law.
In order to enable communication between the fixed station side and the mobile station side over the entire area of the wide premises, the radio equipment 9A to 9A at each fixed station side
The communicable range of C is superimposed on each other and is extended throughout the campus.

【0016】各固定局側の無線装置9A〜9Cは同軸ケ
ーブル10を介して無線コントローラ11に接続され、
その無線コントローラ11は同軸ケーブル12を介し、
指令用の事務所13内に設置されたホストコンピュータ
14に接続されている。無線コントローラ11及びホス
トコンピュータ14は、データ端末機3と同様に各種信
号を入出力する入出力インターフェイス、その入力信号
に基づいて所定の演算・制御を実行するCPU、そのC
PUでの演算結果等を記憶する各種メモリ等を備えたマ
イクロコンピュータにより構成されている。そして、無
線コントローラ11及びホストコンピュータ14により
管理部が構成されており、ホストコンピュータ14は各
フォークリフト1A〜1Dのデータ端末機3へ送るべき
所望のデータを管理し、無線コントローラ11はそのデ
ータを電波を介して発信させるために、各固定局側の無
線装置9A〜9Cの作動を制御する。
The wireless devices 9A to 9C on the fixed station side are connected to a wireless controller 11 via a coaxial cable 10,
The wireless controller 11 is connected via a coaxial cable 12,
It is connected to a host computer 14 installed in a command office 13. The wireless controller 11 and the host computer 14 include an input / output interface for inputting / outputting various signals, a CPU for executing predetermined arithmetic and control based on the input signals, and a C
It is constituted by a microcomputer provided with various memories for storing calculation results and the like in the PU. The wireless controller 11 and the host computer 14 constitute a management unit. The host computer 14 manages desired data to be sent to the data terminals 3 of the forklifts 1A to 1D, and the wireless controller 11 transmits the data by radio waves. The operation of the wireless devices 9A to 9C on each fixed station side is controlled in order to make the transmission via the wireless LAN.

【0017】又、この実施例において、ホストコンピュ
ータ14は、構内で各フォークリフト1A〜1Dによっ
て行われる全体の荷役作業を管理するものである。そし
て、ホストコンピュータ14は個々の作業内容とその他
の作業内容の残量を各フォークリフト1A〜Dのデータ
端末機3へ、無線装置9A〜9C及び無線装置2の間で
やりとりされる電波を使用して選択的に指示送信するよ
うになっている。
Further, in this embodiment, the host computer 14 manages the entire cargo handling work performed by each of the forklifts 1A to 1D on the premises. The host computer 14 then uses the remaining amount of each work content and other work contents to the data terminal 3 of each forklift 1A-D by using the radio waves exchanged between the wireless devices 9A-9C and the wireless device 2. It is designed to selectively send instructions.

【0018】この実施例では、構内で行われるべき全体
の荷役作業に関わる荷の「置き場所」を示す番号(「A
−01〜A−99」,「B−01〜B−99」,「C−
01〜C−99」)が複数(この実施例では3つ)の荷
役ゾーンA,B,Cに予め分類されている。そして、そ
れらの番号が、図3に示すように、ホストコンピュータ
14のメモリ記憶領域15Aに荷役ゾーンテーブル16
として予め登録されている。又、この実施例では、各フ
ォークリフト1A〜1D毎に担当すべき荷役ゾーンA〜
Cの優先順位、即ち「第1優先」、「第2優先」及び
「第3優先」が全ての荷役ゾーンA〜Cについて予め定
められている。そして、それらの優先順位が、図4に示
すように、ホストコンピュータ14のメモリ記憶領域1
5Bに優先順位テーブル17として予め登録されてい
る。
In this embodiment, the number ("A") indicating the "placement" of the load relating to the overall cargo handling work to be performed on the premises.
-01 to A-99 "," B-01 to B-99 "," C-
01-C-99 ") is pre-classified into a plurality (three in this embodiment) of cargo handling zones A, B, and C. Then, as shown in FIG. 3, those numbers are stored in the cargo storage zone table 16 in the memory storage area 15A of the host computer 14.
Is registered in advance. Further, in this embodiment, the cargo handling zone A to be in charge of each of the forklifts 1A to 1D.
The priority order of C, that is, “first priority”, “second priority”, and “third priority” is predetermined for all cargo handling zones A to C. Then, as shown in FIG. 4, the priority order of them is the memory storage area 1 of the host computer 14.
5B is registered in advance as the priority table 17.

【0019】又、この実施例において、構内で行うべき
その日の全作業内容のデータは、図1に示すように、フ
ロッピディスク18によりホストコンピュータ14に入
力されるようになっている。ここで、ホストコンピュー
タ14に入力された全作業内容のデータは、図5に示す
ように、ホストコンピュータ14のメモリ記憶領域15
Cに作業内容テーブル19として登録されるようになっ
ている。この作業内容テーブル19では、個々の作業内
容が「作業番号」によって分類されており、各「作業番
号」毎に荷の「種別」、「数量」、「置き場所」及びそ
の「移動先」が整理されている。そして、ホストコンピ
ュータ14は、その作業内容テーブル19のデータに基
づき、全作業内容をその作業の対象となる荷の「置き場
所」の違いに応じて、前述した各荷役ゾーンA〜C毎の
複数の「作業番号」の作業集合として分類し、図6に示
すように、メモリ記憶領域15Dにゾーン別作業内容テ
ーブル20A,20B,20Cとして登録するようにな
っている。
Further, in this embodiment, the data of all the work contents of the day to be performed on the premises are input to the host computer 14 by the floppy disk 18, as shown in FIG. Here, the data of all the work contents input to the host computer 14 are stored in the memory storage area 15 of the host computer 14 as shown in FIG.
C is registered as a work content table 19. In the work content table 19, each work content is classified by “work number”, and “type”, “quantity”, “place”, and “destination” of the load are provided for each “work number”. It is organized. Then, based on the data of the work content table 19, the host computer 14 converts all the work contents into a plurality of pieces for each of the above-mentioned cargo handling zones A to C according to the difference of the “place” of the load to be worked. 6 and are registered in the memory storage area 15D as zone-specific work content tables 20A, 20B, and 20C, as shown in FIG.

【0020】更に、この実施例において、各フォークリ
フト1A〜1Dから事務所13内のホストコンピュータ
14へ作業指示の要求を行うには、オペレータがデータ
端末機3のキーボード6をキー操作するようになってい
る。データ端末機3は作業指示要求のためのキー操作が
行われたときに、作業指示の要求であることを示す信号
を無線装置2を駆動させて固定局側の無線装置9A〜9
Cへ送信させる。
Further, in this embodiment, in order to request a work instruction from the forklifts 1A to 1D to the host computer 14 in the office 13, the operator operates the keyboard 6 of the data terminal machine 3 by keys. ing. When a key operation for requesting a work instruction is performed, the data terminal 3 drives the wireless device 2 to output a signal indicating a request for a work instruction, and transmits the signal to the fixed station side wireless devices 9A to 9A.
Send to C.

【0021】固定局側の無線装置9A〜9Cでは、これ
を受けて、その信号を無線コントローラ11を介してホ
ストコンピュータ14へ出力する。そして、ホストコン
ピュータ14ではその作業指示要求の信号を受けて、要
求のあったフォークリフト1A〜1Dへ荷役作業を指示
するための処理動作を実行するようになっている。
In response to this, the wireless devices 9A to 9C on the fixed station side output the signal to the host computer 14 via the wireless controller 11. Then, the host computer 14 receives the work instruction request signal and executes a processing operation for instructing the forklifts 1A to 1D that have requested the cargo handling operation.

【0022】又、各フォークリフト1A〜1Dのデータ
端末機3にホストコンピュータ14から指示送信すべき
作業内容及びその他の作業内容の残量が送られてきて入
力された場合には、データ端末機3がそれらのデータを
ディスプレイ7に表示させるようになっている。或い
は、必要に応じてキーボード6のキー操作が行われるこ
とにより、その作業内容等のデータがプリンタ4に出力
印字されるようになっている。
When the host computer 14 sends to the data terminal 3 of each of the forklifts 1A to 1D the amount of work to be transmitted and the remaining amount of other work, the data is sent to the data terminal 3. Is to display those data on the display 7. Alternatively, when the key operation of the keyboard 6 is performed as necessary, the data such as the work content is output and printed on the printer 4.

【0023】次に、上記のように構成した物流システム
において、ホストコンピュータ14により実行される荷
役作業の指示方法の処理動作について、図7,8のフロ
ーチャートに従って説明する。
Next, the processing operation of the method of instructing the cargo handling work executed by the host computer 14 in the physical distribution system configured as described above will be described with reference to the flowcharts of FIGS.

【0024】ここで、構内で行うべきその日の全作業内
容のデータは、既にホストコンピュータ14に入力され
て、図5に示すように、メモリ記憶領域15Cに作業内
容テーブル19として登録されているものとする。又、
その作業内容テーブル19のデータに基づき、全作業内
容が、図6に示すように、メモリ記憶領域15Dにゾー
ン別作業内容テーブル20A〜20Cとして登録されて
いるものとする。
Here, the data of all work contents of the day to be performed on the premises have already been input to the host computer 14 and registered in the memory storage area 15C as the work contents table 19 as shown in FIG. And or,
Based on the data of the work content table 19, it is assumed that all the work contents are registered in the memory storage area 15D as zone-specific work content tables 20A to 20C as shown in FIG.

【0025】処理がこのフローチャートのルーチンへ移
行すると、先ずステップ101において、固定局側の各
無線装置9A〜9Cにて受信される信号に基づき、各フ
ォークリフト1A〜1Dから作業指示の要求が来るのを
待つ。そして、その作業指示の要求があった場合には、
ステップ102において、図4に示す優先順位テーブル
17から、要求のあったフォークリフト1A〜1Dにつ
いて「第1優先」の荷役ゾーンA〜Cを参照する。続い
て、ステップ103において、図6に示す各ゾーン別作
業内容テーブル20A〜20Cから、「第1優先」の荷
役ゾーンA〜Cに対応する「作業番号」を小さい順に選
択する。
When the processing shifts to the routine of this flowchart, first, at step 101, a work instruction request comes from each of the forklifts 1A to 1D based on a signal received by each of the wireless devices 9A to 9C on the fixed station side. Wait for And when there is a request for the work instruction,
In step 102, the "first priority" cargo handling zones A to C for the requested forklifts 1A to 1D are referenced from the priority order table 17 shown in FIG. Subsequently, in step 103, "work numbers" corresponding to the "first priority" cargo handling zones A to C are selected in ascending order from the zone-specific work content tables 20A to 20C shown in FIG.

【0026】そして、ステップ104において、「作業
番号」を選択できたか否かを判断する。つまり、各ゾー
ン別作業内容テーブル20A〜20Cが空集合でなく、
選択すべき「作業番号」の選択が行われたか否かを判断
する。
Then, in step 104, it is determined whether or not the "work number" has been selected. That is, the work content tables 20A to 20C for each zone are not empty sets,
It is determined whether or not the “work number” to be selected has been selected.

【0027】ここで、ステップ104において、「作業
番号」を選択できた場合には、ステップ105におい
て、その選択された「作業番号」に対応する作業内容
を、図5に示す作業内容テーブル19を参照して確認す
る。即ち、「作業番号」に対応する荷の「種別」、「数
量」、「置き場所」及び「移動先」を確認する。次に、
ステップ106において、作業内容テーブル19、各ゾ
ーン別作業内容テーブル20A〜20Cから、全作業内
容の残量と荷役ゾーン別作業内容の残量をそれぞれ集計
する。そして、続くステップ107においては、その確
認された作業内容、全作業内容残量及び荷役ゾーン別作
業内容残量を、各無線装置9A〜9Cを駆動させて、要
求のあったフォークリフト1A〜1Dへ送信し、その後
の処理を一旦終了する。
If the "work number" can be selected in step 104, the work content corresponding to the selected "work number" is selected in step 105 by referring to the work content table 19 shown in FIG. Check and confirm. That is, the “type”, “quantity”, “place”, and “destination” of the load corresponding to the “work number” are confirmed. next,
In step 106, the remaining contents of all work contents and the remaining contents of work contents by cargo handling zone are totaled from the work contents table 19 and the work contents tables for each zone 20A to 20C. Then, in the subsequent step 107, the confirmed work contents, the total work contents remaining amount and the work contents remaining amount according to the cargo handling zone are driven to the requested forklifts 1A to 1D by driving the respective wireless devices 9A to 9C. The data is transmitted, and the subsequent processing is temporarily terminated.

【0028】一方、ステップ104において、「作業番
号」を選択できない場合には、ステップ108におい
て、図4に示す優先順位テーブル17から、要求のあっ
たフォークリフト1A〜1Dについて「第2優先」の荷
役ゾーンA〜Cを参照する。続いて、ステップ109に
おいて、図6に示す各ゾーン別作業内容テーブル20A
〜20Cから、「第2優先」の荷役ゾーンA〜Cに対応
する「作業番号」を小さい順に選択する。
On the other hand, when the "work number" cannot be selected in step 104, the "second priority" cargo handling is performed for the requested forklifts 1A to 1D from the priority table 17 shown in FIG. 4 in step 108. Refer to zones A-C. Then, in step 109, the work content table 20A for each zone shown in FIG.
20C, “work numbers” corresponding to the “second priority” loading zones A to C are selected in ascending order.

【0029】次に、ステップ110において、「作業番
号」を選択できたか否かを判断する。ここで「作業番
号」を選択できた場合には、前述したと同様にステップ
105へ移行し、そのステップ105〜ステップ107
の処理を実行することにより、選択された「作業番号」
に対応する作業内容、全作業内容残量及び荷役ゾーン別
作業内容残量を、要求のあったフォークリフト1A〜1
Dへ送信し、その後の処理を一旦終了する。
Next, in step 110, it is determined whether or not the "work number" has been selected. If the "work number" can be selected here, the process proceeds to step 105 in the same manner as described above, and the steps 105 to 107 are executed.
By executing the process of "selected work number"
For each of the requested forklifts 1A to 1 for the work content, the total work content remaining amount, and the work content remaining amount for each cargo handling zone
It is transmitted to D, and the subsequent processing is once ended.

【0030】又、ステップ110において、「作業番
号」を選択できない場合には、ステップ111におい
て、図4に示す優先順位テーブル17から、要求のあっ
たフォークリフト1A〜1Dについて「第3優先」の荷
役ゾーンA〜Cを参照する。続いて、ステップ112に
おいて、図6に示す各ゾーン別作業内容テーブル20A
〜20Cから、「第3優先」の荷役ゾーンA〜Cに対応
する「作業番号」を小さい順に選択する。
If the "work number" cannot be selected in step 110, then in step 111, the "third priority" cargo handling is performed for the requested forklifts 1A to 1D from the priority table 17 shown in FIG. Refer to zones A-C. Then, in step 112, the work content table 20A for each zone shown in FIG.
20C, the “work numbers” corresponding to the “third priority” loading zones A to C are selected in ascending order.

【0031】そして、ステップ113において、「作業
番号」を選択できたか否かを判断する。ここで「作業番
号」を選択できた場合には、前述したと同様にステップ
105へ移行し、同ステップ105〜ステップ107の
処理を実行することにより、選択された「作業番号」に
対応する作業内容、全作業内容残量及び荷役ゾーン別作
業内容残量を、要求のあったフォークリフト1A〜1D
へ送信し、その後の処理を一旦終了する。
Then, in step 113, it is determined whether or not the "work number" has been selected. If the "work number" can be selected here, the process corresponding to the selected "work number" is performed by shifting to step 105 and executing the processing of steps 105 to 107 as described above. Forklifts 1A to 1D that requested the contents, the remaining amount of all work contents, and the remaining amount of work contents by cargo handling zone
To end the subsequent processing.

【0032】一方、ステップ113において、「作業番
号」を選択できない場合には、各ゾーン別作業内容テー
ブル20A〜20Cに荷役ゾーンA〜Cに対応する「作
業番号」が残っていないものとして、即ち各ゾーン別作
業内容テーブル20A〜20Cが空集合であるものとし
て、ステップ114へ移行する。そして、ステップ11
4において、「指示すべき作業なし」のデータを、各無
線装置9A〜9Cを駆動させて、要求のあったフォーク
リフト1A〜1Dへ送信し、その後の処理を一旦終了す
る。
On the other hand, when the "work number" cannot be selected in step 113, it is assumed that the "work number" corresponding to the cargo handling zones A to C does not remain in the zone-specific work content tables 20A to 20C, that is, Assuming that the zone-specific work content tables 20A to 20C are empty sets, the process proceeds to step 114. And step 11
In 4, the data of "no work to be instructed" is transmitted to the requested forklifts 1A to 1D by driving the respective wireless devices 9A to 9C, and the subsequent processing is once ended.

【0033】このように、ホストコンピュータ14によ
り荷役作業の指示方法の処理動作が実行される。そし
て、各フォークリフト1A〜1Dでは、その無線装置2
が各無線装置9A〜9Cから送信された作業内容、全作
業内容残量及び荷役ゾーン別作業内容残量のデータを含
む信号を受信してデータ端末機3へ出力する。そして、
データ端末機3では、その信号を受けて、図9に示すよ
うに、作業内容のデータが、「作業番号」に対応する
「種別」、「数量」、「置き場所」及び「移動先」のデ
ータとして、それぞれディスプレイ7の左側領域に出力
表示される。併せて、ディスプレイ7の右側領域には、
全作業内容残量及び荷役ゾーン別作業内容残量のデータ
が、「荷役ゾーン」及び「全システム」に対応する数量
のデータとして、それぞれ出力表示される。よって、指
示すべき作業内容のデータ、全作業内容残量及び荷役ゾ
ーン別作業内容残量のデータがそれぞれオペレータへ知
らされる。従って、オペレータがその作業内容のデー
タ、全作業内容残量及び荷役ゾーン別作業内容残量のデ
ータに基づいて自車を運転することにより、指示された
作業内容に関する荷役作業が遂行される。
In this way, the host computer 14 executes the processing operation of the method for instructing the cargo handling work. In each of the forklifts 1A to 1D, the wireless device 2
Receives the signal including the work content, the total work content remaining amount, and the work content remaining amount for each cargo handling zone transmitted from each of the wireless devices 9A to 9C, and outputs the signal to the data terminal device 3. And
In response to the signal, the data terminal device 3 receives data indicating that the work content data includes "type", "quantity", "placement" and "movement destination" corresponding to the "work number". The data is output and displayed in the left area of the display 7, respectively. In addition, in the right side area of the display 7,
The data of the remaining amount of work contents and the remaining amount of work contents for each cargo handling zone are output and displayed as the data of the quantities corresponding to the "cargo handling zone" and the "total system", respectively. Therefore, the operator is informed of the data of the work content to be instructed, the total work content remaining amount, and the work content remaining amount by cargo handling zone. Therefore, the operator operates the vehicle based on the work content data, the total work content remaining amount, and the work content remaining amount data for each cargo handling zone, whereby the cargo handling work related to the instructed work content is performed.

【0034】上記のようにこの実施例における荷役作業
の指示方法によれば、事務所13内のホストコンピュー
タ14が各フォークリフト1A〜1Dから作業指示の要
求を受けると、空集合となっていない各ゾーン別作業内
容テーブル20A〜20Cにおける「作業番号」のう
ち、要求のあったフォークリフト1A〜1Dにとって最
も優先順位の高い荷役ゾーンA〜C、つまりは「第1優
先」に対応する荷役ゾーンA〜Cから順に「作業番号」
が選択される。又、その選択された「作業番号」に対応
する作業内容が作業内容テーブル19から参照される。
そして、その参照された作業内容のデータが、固定局側
の各無線装置9A〜9C及び移動局側の無線装置2を通
じて、要求のあったフォークリフト1A〜1Dへ指示す
べき作業内容として送られる。
As described above, according to the cargo handling work instruction method in this embodiment, when the host computer 14 in the office 13 receives a work instruction request from each of the forklifts 1A to 1D, each of them is not an empty set. Of the “work numbers” in the zone-specific work content tables 20A to 20C, the cargo handling zones A to C having the highest priority for the requested forklifts 1A to 1D, that is, the cargo handling zone A to which the “first priority” corresponds. "Work number" in order from C
Is selected. Further, the work content corresponding to the selected “work number” is referred to from the work content table 19.
Then, the data of the referenced work content is transmitted as the work content to be instructed to the requested forklifts 1A to 1D through the wireless devices 9A to 9C on the fixed station side and the wireless device 2 on the mobile station side.

【0035】よって、個々のフォークリフト1A〜1D
では、優先順位の高い「第1優先」の荷役ゾーンA〜C
に対応する作業内容から、優先順位の低い「第3優先」
の荷役ゾーンA〜Cに対応する作業内容へと、順次に指
示を受けることになる。そして、各荷役ゾーンA〜Cに
属する作業内容は「第1優先」で分担された個々のフォ
ークリフト1A〜1Dによって順次に処理される。この
ため、作業内容の多い荷役ゾーンA〜Cについては、
「第1優先」で分担されたフォークリフト1A〜1Dの
他に、「第2優先」や「第3優先」で分担されたその他
のフォークリフト1A〜1Dの協働によっても処理され
ることになる。
Therefore, each of the forklifts 1A-1D
Then, the "first priority" cargo handling zones A to C with high priority
"3rd priority" with lower priority from the work content corresponding to
Are sequentially received to work contents corresponding to the cargo handling zones A to C. The work contents belonging to each of the cargo handling zones A to C are sequentially processed by the individual forklifts 1A to 1D assigned with “first priority”. For this reason, for the cargo handling zones A to C with many work contents,
In addition to the forklifts 1A to 1D assigned by "first priority", the processing is also performed by cooperation of other forklifts 1A to 1D assigned by "second priority" or "third priority".

【0036】従って、全作業内容が各フォークリフト1
A〜1Dによって自動的に分担され、各フォークリフト
1A〜1Dの協働によって順次に処理されることにな
る。そして、その日によって全作業内容の作業の対象と
なる荷の「種別」や作業の対象となる荷の「置き場所」
が異なった場合でも、全作業内容が各フォークリフト1
A〜1Dの協働によって順次処理されることから、特定
のフォークリフト1A〜1Dのみに作業の集中すること
を防止することができ、各フォークリフト1A〜1Dの
間で作業の忙しさのバラツキを無くすことができる。
Therefore, all the work contents are for each forklift 1
A to 1D automatically share and are sequentially processed by cooperation of the forklifts 1A to 1D. Then, depending on the day, the “type” of the load that is the target of the work for all the work contents and the “place” of the load that is the target of the work
Even if they are different, all the work content is
Since the processes are sequentially performed by the cooperation of A to 1D, it is possible to prevent the work from being concentrated only on the specific forklifts 1A to 1D, and to eliminate the variation in the busyness of the work among the forklifts 1A to 1D. be able to.

【0037】更に、各フォークリフト1A〜1Dの一部
が故障して抜けた場合でも、その故障したフォークリフ
ト1A〜1Dに対応する作業内容が、残りのフォークリ
フト1A〜1Dに自動的に割り振られて分担され、それ
らの協働によって順次処理されることになる。従って、
残りのフォークリフト1A〜1Dに対する作業指示の内
容を応急的にいちいち追加変更することなく作業の仕残
しを防止することができる。或いは、残された作業を後
回しにして最後に残りのフォークリフト1A〜1Dで人
為的に割り振って分担することなく、作業の仕残しを防
止することができる。つまり、一部のフォークリフト1
A〜1Dが抜けた場合でも、そのことに自動的に対処し
て作業の仕残しを未然に防止することができるのであ
る。
Further, even if a part of each of the forklifts 1A to 1D fails and comes out, the work content corresponding to the failed forklift 1A to 1D is automatically assigned to the remaining forklifts 1A to 1D. And are processed sequentially by their cooperation. Therefore,
Unnecessary addition of the contents of the work instruction to the remaining forklifts 1A to 1D without any emergency change can prevent the remaining work. Alternatively, the leftover work can be postponed, and the remaining work can be prevented without being artificially allocated and shared by the remaining forklifts 1A to 1D. In other words, some forklifts 1
Even if A to 1D is missed, it is possible to automatically cope with that and prevent the work from being left behind.

【0038】又、一部のフォークリフト1A〜1Dが抜
けても、残りのフォークリフト1A〜1Dに全作業内容
を自動的に割り振って順次処理できることから、全作業
内容の作業量に応じて、フォークリフトの台数を任意に
増減することもできる。
Further, even if some of the forklifts 1A to 1D come out, all the work contents can be automatically assigned to the remaining forklifts 1A to 1D and can be processed sequentially. The number can be increased or decreased arbitrarily.

【0039】更に、この実施例では、全作業内容残量及
び荷役ゾーン別作業内容残量のデータがオペレータに知
らされることから、オペレータは、それら各作業内容残
量のデータを自車の作業スピードの調節のために利用す
ることが可能となる。
Further, in this embodiment, since the data of the total work content remaining amount and the work content remaining amount according to the cargo handling zone are notified to the operator, the operator can obtain the data of each work content remaining amount by the work of the own vehicle. It can be used to adjust the speed.

【0040】従って、各フォークリフト1A〜1Dのオ
ペレータとしては、その時々に自車に指示された作業内
容のデータの他に、全作業内容残量や、自車の行うべき
荷役ゾーン別作業内容残量を把握することができる。そ
の結果、個々のオペレータは、作業時間の配分を考えな
がら必要に応じて自車の作業スピードを調節することが
可能となる。よって、個々のフォークリフト1A〜1D
の作業効率を向上させることができ、もって各フォーク
リフト1A〜1Dのそれぞれが、全体の荷役作業の効率
を更に向上させるように積極的に寄与することができ
る。又、この効果から、全体の荷役作業の遅れ防止を図
ることもできる。
Therefore, as an operator of each of the forklifts 1A to 1D, in addition to the work content data instructed to the vehicle at that time, the remaining work content remaining amount and the work content remaining for each cargo handling zone to be performed by the own vehicle. You can figure out the quantity. As a result, each operator can adjust the work speed of the own vehicle as necessary while considering the distribution of work time. Therefore, the individual forklifts 1A-1D
The work efficiency can be improved, and thus each of the forklifts 1A to 1D can positively contribute to further improve the efficiency of the overall cargo handling work. Further, from this effect, it is possible to prevent the delay of the entire cargo handling work.

【0041】尚、この発明は前記実施例に限定されるも
のではなく、発明の趣旨を逸脱しない範囲で構成の一部
を適宜に変更して次のように実施することもできる。 (1)前記実施例では、物流システムとして4台のフォ
ークリフト1A〜1Dを使用した場合に具体化したが、
予めフォークリフトの数を適宜に変更することもでき
る。
The present invention is not limited to the above-described embodiment, but may be implemented as follows with a part of the configuration appropriately modified without departing from the spirit of the invention. (1) In the above embodiment, the case where four forklifts 1A to 1D are used as the physical distribution system has been embodied.
The number of forklifts can be appropriately changed in advance.

【0042】(2)前記実施例では、全体の荷役作業に
関わる荷の置き場所を合計3つの荷役ゾーンA〜Cに分
けて具体化したが、荷役ゾーンの数を適宜に変更しても
よい。但し、荷役ゾーンの数を変更した場合には、それ
に合わせて、各フォークリフト毎に担当すべき荷役ゾー
ンの優先順位の数は増減することになる。
(2) In the above-mentioned embodiment, the places for placing the loads involved in the entire cargo handling work are divided into three cargo handling zones A to C in total, but the number of cargo handling zones may be changed appropriately. . However, when the number of the cargo handling zones is changed, the number of the priority of the cargo handling zones to be assigned to each forklift increases or decreases accordingly.

【0043】(3)前記実施例では、その他の作業内容
の残量として、全作業内容残量と荷役ゾーン別作業内容
残量のデータを各フォークリフト1A〜1Dに送るよう
にしたが、それら両データのうちの何れか一方のデータ
のみを各フォークリフト1A〜1Dに送るようにしても
よい。
(3) In the above embodiment, as the remaining amount of the other work contents, the data of the total work amount remaining amount and the work content remaining amount for each cargo handling zone are sent to the forklifts 1A to 1D. Only one of the data may be sent to each forklift 1A-1D.

【0044】(4)前記実施例では、荷役車両としての
有人式のフォークリフト1A〜1Dを使用した物流シス
テムに具体化したが、自動的に操縦される無人フォーク
リフトや無人搬送車を使用した物流システムに具体化し
てもよい。
(4) In the above embodiment, the physical distribution system using the manned type forklifts 1A to 1D as the cargo handling vehicle is embodied. However, the physical distribution system using the automatically operated unmanned forklift and the automatic guided vehicle. May be embodied in.

【0045】[0045]

【発明の効果】以上詳述したように、この発明によれ
ば、各荷役ゾーンに対応する作業内容が各荷役車両の協
働によって処理されるので、特定の荷役車両のみに作業
が集中することを防止することができると共に、一部の
荷役車両が抜けた場合でも自動的に対処して作業の仕残
しを未然に防止することができるという優れた効果を発
揮する。併せて、その他の作業内容の残量が各荷役車両
へ送信されることから、個々の荷役車両がその作業スピ
ードを調節して全体の荷役作業の効率を更に向上させる
ことができるという優れた効果を発揮する。
As described above in detail, according to the present invention, since the work contents corresponding to each cargo handling zone are processed by the cooperation of each cargo handling vehicle, the work is concentrated only on a specific cargo handling vehicle. It is possible to prevent the above, and it is possible to prevent the unfinished work by automatically dealing with it even when a part of the cargo handling vehicle comes off. At the same time, since the remaining amount of other work content is transmitted to each cargo handling vehicle, the excellent effect that each cargo handling vehicle can adjust its work speed to further improve the efficiency of the overall cargo handling work Exert.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明を具体化した一実施例において、無線
方式のLANを使用したフォークリフトの物流システム
を示す概略構成図である。
FIG. 1 is a schematic configuration diagram showing a physical distribution system of a forklift truck using a wireless LAN in an embodiment embodying the present invention.

【図2】一実施例において、各フォークリフトに搭載さ
れたデータ端末機、無線装置及びプリンタ等を示す図で
ある。
FIG. 2 is a diagram illustrating a data terminal device, a wireless device, a printer, and the like mounted on each forklift according to an embodiment.

【図3】一実施例において、ホストコンピュータのメモ
リ記憶領域に登録された荷役ゾーンテーブルを説明する
図である。
FIG. 3 is a diagram illustrating a cargo handling zone table registered in a memory storage area of a host computer in an embodiment.

【図4】一実施例において、ホストコンピュータのメモ
リ記憶領域に登録された優先順位テーブルを説明する図
である。
FIG. 4 is a diagram illustrating a priority order table registered in a memory storage area of a host computer according to an embodiment.

【図5】一実施例において、ホストコンピュータのメモ
リ記憶領域に登録された作業内容テーブルを説明する図
である。
FIG. 5 is a diagram illustrating a work content table registered in a memory storage area of a host computer in an embodiment.

【図6】一実施例において、ホストコンピュータのメモ
リ記憶領域に登録された各ゾーン別作業内容テーブルを
説明する図である。
FIG. 6 is a diagram illustrating a zone-specific work content table registered in a memory storage area of a host computer in an embodiment.

【図7】一実施例において、ホストコンピュータにより
実行される荷役作業の指示方法の処理動作を説明するフ
ローチャートである。
FIG. 7 is a flowchart illustrating a processing operation of a cargo handling instruction method executed by a host computer according to an embodiment.

【図8】一実施例において、ホストコンピュータにより
実行される荷役作業の指示方法の処理動作の続きを説明
するフローチャートである。
FIG. 8 is a flowchart illustrating a continuation of the processing operation of the cargo handling work instruction method executed by the host computer in the embodiment.

【図9】一実施例において、データ端末機でのディスプ
レイの表示例を説明する図である。
FIG. 9 is a diagram illustrating a display example of a display in a data terminal according to an embodiment.

【図10】従来例において、ホストコンピュータのメモ
リ記憶領域に登録された作業内容テーブルを説明する図
である。
FIG. 10 is a diagram illustrating a work content table registered in a memory storage area of a host computer in a conventional example.

【図11】従来例において、ホストコンピュータのメモ
リ記憶領域に登録された種別テーブルを説明する図であ
る。
FIG. 11 is a diagram illustrating a type table registered in a memory storage area of a host computer in a conventional example.

【図12】従来例において、ホストコンピュータのメモ
リ記憶領域に登録された置き場所テーブルを説明する図
である。
FIG. 12 is a diagram illustrating a storage location table registered in a memory storage area of a host computer in a conventional example.

【符号の説明】[Explanation of symbols]

1A〜1D…荷役車両としてのフォークリフト、2,9
A〜9C…通信手段を構成する無線装置、11…無線コ
ントローラ、14…ホストコンピュータ(11,14は
管理部を構成している)、17…優先順位テーブル、1
9,21,22…作業内容テーブル、20A〜20C…
ゾーン別作業内容テーブル、A〜C…荷役ゾーン。
1A to 1D: Forklift as cargo handling vehicle, 2, 9
A to 9C: wireless devices constituting communication means, 11: wireless controller, 14: host computer (11 and 14 constitute a management unit), 17 ... priority table, 1
9, 21, 22, ... work contents table, 20A to 20C ...
Zone-specific work content tables, A to C ... cargo handling zones.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 全体の荷役作業を管理する管理部から個
々の作業内容を複数の荷役車両の各々へ通信手段を使用
して選択的に指示する荷役作業の指示方法において、 前記管理部にて、全体の荷役作業に関わる荷の置き場所
を複数の荷役ゾーンに分類して予め定めておき、 同じく前記管理部にて、前記各荷役車両毎に担当すべき
荷役ゾーンの優先順位を前記全荷役ゾーンについて予め
定めておき、 前記管理部にて、全作業内容をその作業の対象となる荷
の置き場所の違いに応じて前記各荷役ゾーン毎の複数の
作業集合として分類しておき、 前記管理部が、前記各荷役車両から作業指示の要求を受
けたときに、空集合となっていない前記各作業集合のう
ち前記作業指示の要求のあった荷役車両にとって最も優
先順位の高い荷役ゾーンに対応する作業集合の中から未
だ実行されていない作業内容を選択し、 併せて前記管理部が、その他の作業内容の残量を集計
し、 前記管理部が、選択された作業内容とその他の作業内容
の残量を前記通信手段を使用して前記作業指示の要求の
あった荷役車両へ指示送信するようにした荷役作業の指
示方法。
1. A cargo handling instruction method for selectively instructing each of a plurality of cargo handling vehicles to each of a plurality of cargo handling vehicles by using a communication unit from a management unit that manages the entire cargo handling work. In the same manner, in the management unit, the priority of the cargo handling zone to be assigned to each cargo handling vehicle is determined by the entire cargo handling area. Zones are determined in advance, and the management unit classifies all work contents as a plurality of work sets for each of the cargo handling zones according to a difference in a place where a load to be processed is placed. The unit, when receiving a request for a work instruction from each of the cargo handling vehicles, corresponds to a cargo handling zone having the highest priority for a cargo handling vehicle that has requested the work instruction among the work sets that are not empty sets. Do The work content that has not been executed is selected from the business group, and at the same time, the management unit aggregates the remaining amount of the other work content, and the management unit determines the selected work content and the other work content. A method of instructing a cargo handling operation, wherein the remaining amount is instructed and transmitted to the cargo handling vehicle that has requested the work instruction using the communication means.
JP4009429A 1992-01-22 1992-01-22 Instruction method of cargo handling work Expired - Lifetime JP2677096B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4009429A JP2677096B2 (en) 1992-01-22 1992-01-22 Instruction method of cargo handling work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4009429A JP2677096B2 (en) 1992-01-22 1992-01-22 Instruction method of cargo handling work

Publications (2)

Publication Number Publication Date
JPH05197425A JPH05197425A (en) 1993-08-06
JP2677096B2 true JP2677096B2 (en) 1997-11-17

Family

ID=11720095

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4009429A Expired - Lifetime JP2677096B2 (en) 1992-01-22 1992-01-22 Instruction method of cargo handling work

Country Status (1)

Country Link
JP (1) JP2677096B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6621724B2 (en) * 2016-09-09 2019-12-18 ヤンマー株式会社 Route generation system

Also Published As

Publication number Publication date
JPH05197425A (en) 1993-08-06

Similar Documents

Publication Publication Date Title
US7305287B2 (en) AGV control system and method
JP2677096B2 (en) Instruction method of cargo handling work
CN109995117B (en) Charging system and method based on robot
CN101123608A (en) Full frequency band and full duplex transmission power adjustable wireless network adapter and its implementation method
EP1396455B1 (en) Elevator system
JPH048046A (en) Method and apparatus for idle channel retrieval in system cordless telephone set
JP2606513B2 (en) Instruction method of cargo handling work
JPH05286511A (en) Instruction for loading work
EP0534716A2 (en) Cellular mobile telephone exchange system
JPH02288737A (en) Communication equipment for cargo vehicle truck
JPH03210833A (en) Method for discriminating position of travelling object in travelling object communication
JP2674412B2 (en) Mobile communication method
JPH0851427A (en) Radio lan equipment
JPS62247456A (en) Radio type inventory management system
JP3522722B2 (en) Radio base station control apparatus and control method for performing standby transfer control between multiple mobile radio communication systems
JP2002165272A (en) Communication method and communication terminal
CN112456260B (en) Elevator control method, system, electronic device and storage medium
JPH07177197A (en) Communication task management system
JP3093425B2 (en) Mobile station paging control system in AVM system
JPH05244163A (en) Data transfer method
JPH1058358A (en) Automatic guided transport device
JPH0619543A (en) Unmanned carriage system
JPH10187241A (en) Carrying command device for carrier
WO2001004741A1 (en) Automated work in process management system and method
EP1032232A2 (en) Mobile communication system and call control method in the mobile communication system