JP2673163B2 - Mobile formwork construction method for arch concrete - Google Patents

Mobile formwork construction method for arch concrete

Info

Publication number
JP2673163B2
JP2673163B2 JP33029088A JP33029088A JP2673163B2 JP 2673163 B2 JP2673163 B2 JP 2673163B2 JP 33029088 A JP33029088 A JP 33029088A JP 33029088 A JP33029088 A JP 33029088A JP 2673163 B2 JP2673163 B2 JP 2673163B2
Authority
JP
Japan
Prior art keywords
concrete
arch
construction
support
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP33029088A
Other languages
Japanese (ja)
Other versions
JPH02176005A (en
Inventor
信之 松ケ下
Original Assignee
岡部株式会社
岡部テクノシステム株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 岡部株式会社, 岡部テクノシステム株式会社 filed Critical 岡部株式会社
Priority to JP33029088A priority Critical patent/JP2673163B2/en
Publication of JPH02176005A publication Critical patent/JPH02176005A/en
Application granted granted Critical
Publication of JP2673163B2 publication Critical patent/JP2673163B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、アーチ橋等におけるアーチコンクリートを
経済的に打設することのできる型枠移動式工法に関する
ものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a formwork moving method capable of economically placing arch concrete in an arch bridge or the like.

〔従来の技術〕[Conventional technology]

アーチ橋のようなコンクリート構造物の構築にあたっ
てはその施工面、特に橋脚(橋台を含む)間にわたるア
ーチ形コンクリートの施工に必要な型枠支保工の施設が
大きな問題となる。水平形スラブの支保工の様に多数の
垂直な支柱によって型枠を支保するのみでできるのであ
れば簡単であるが、アーチ形の場合斜面部を有するもの
なので水平形スラブのように簡単ではない。型枠に加わ
るコンクリートの荷重はどのような場合でも型枠面に垂
直な方向に作用するので、斜面部のアーチコンクリート
は支保工に対して垂直方向のみならず水平方向の荷重も
加えることになる。支保工支柱は普通垂直に立設される
から、アーチ支保工は水平方向に耐える構造を加えなけ
ればならない。これは必然的にトラス構造又はそれに類
似のものとなり、支保工は重構造物になって施工は繁雑
なものとなる。そして、アーチコンクリートのアーチ形
状が変われば、支保工はその都度その形状に合わせて製
作し組立てることになるから、多くの日時と多大の資材
を要し莫大な経費がかかることになっていた。
When constructing a concrete structure such as an arch bridge, a construction surface, particularly a form-supporting facility required for construction of an arch-type concrete spanning between piers (including abutments) becomes a major problem. It is easy if it can be done only by supporting the formwork with a large number of vertical columns like the support work of a horizontal slab, but it is not as easy as a horizontal slab because it has a sloped part in the case of an arch. . Since the concrete load applied to the formwork acts in a direction perpendicular to the formwork surface in any case, the arch concrete on the slope part applies not only vertical load but also horizontal load to the support work. . Since the support pillars are usually erected vertically, the arch support must have a structure that can withstand the horizontal direction. This inevitably results in a truss structure or the like, and the shoring becomes a heavy structure and the construction is complicated. If the arch shape of the arch concrete changes, the supporting work must be manufactured and assembled according to the shape each time, which requires a lot of time and a lot of materials and enormous cost.

本発明者は、かかる実状にかんがみ、特開昭62−1906
号、同62−78357号等の発明により、経済的で施工の容
易なアーチコンクリート型枠用支保工の開発を行ってき
た。この発明の支保工は、主杆と一対の側杆とによって
三角形の単位支保要素を形成し、その多数を互いに主杆
の端部でピン結合するとともに、両側杆の連結部におい
て互いに副杆により連結した構成としたもので、型枠を
支持するトラス構造の支保工が、強固でしかも組立て解
体が容易にできるとともに、副杆の長さだけを変更する
だけでアーチの形状を変化させることができ、したがっ
て、各種の大きさやアーチ形状の異なるアーチコンクリ
ートの施工にも反復して適用することが可能となり、さ
らに、このアーチ形状の支保工骨組の両下端部を橋台、
橋脚上部に支承させる方式をとることにより、資材の節
減施工の簡易化のみならず、工期の短縮、信頼性の向上
等、施工全般にわたって大巾な改善が図れることになっ
た。
In view of such a situation, the present inventor has disclosed Japanese Patent Application Laid-Open No. 62-1906.
With the inventions of No. 62-78357, etc., we have developed economical and easy-to-construct support for arch concrete formwork. According to the supporting work of the present invention, a triangular unit supporting element is formed by the main rod and the pair of side rods, and a large number of them are pin-coupled to each other at the ends of the main rod, and at the connecting portions of the both side rods are sub-latches. With the connected structure, the support of the truss structure that supports the formwork is strong and easy to assemble and disassemble, and the arch shape can be changed simply by changing the length of the auxiliary rod. Therefore, it becomes possible to repeatedly apply it to the construction of arch concrete of various sizes and arch shapes, and further, to the abutment at both lower ends of this arch-shaped supporting frame.
By adopting the method of supporting on the upper part of the pier, not only simplification of material saving construction but also shortening of construction period, improvement of reliability, etc. can be achieved over the whole construction.

〔発明が解決しようとする課題〕[Problems to be solved by the invention]

しかし、アーチコンクリートの施工においての型枠支
保工に要する経費は、それでもなおかなり高いものであ
る。特に、たとえば一径間だけを施工するような場合
は、型枠支保工の反覆使用がないので、アーチコンクリ
ートの施工単価が著しく増大することになる。
However, the cost of supporting the formwork in the construction of arch concrete is still quite high. In particular, for example, when only one span is constructed, since there is no repeated use of the form support, the construction unit cost of the arch concrete is significantly increased.

本発明は、このようなアーチコンクリートの施工にお
ける問題点を解決するためになされたもので、本発明者
が開発したアーチコンクリート施工用の移動型枠支保工
を用い、アーチコンクリートをその巾方向(横断方向)
に分割施工するようにし、特に分割施工において問題と
なる、各施工区分に打設のコンクリート相互の接続の難
点を解決して、アーチ型枠支保工の経費を大巾に軽減す
ると共に、アーチコンクリートの施工を能率よく確実に
行なうことのできる工法を提供しようとするものであ
る。
The present invention has been made to solve the problems in the construction of such arch concrete, and uses the movable formwork support for arch concrete construction developed by the present inventor to make arch concrete its width direction ( Transverse direction)
The construction work is divided into two parts, and in particular, the problem of connecting the concrete, which is a problem in the construction work, is solved by connecting the concrete to each other, and the cost of arch form support is greatly reduced. It is intended to provide a construction method capable of efficiently and reliably performing the construction of.

〔課題を解決するための手段〕[Means for solving the problem]

上記の目的を達成するための本発明の構成について、
実施例に対応する図面を参照して説明すると、本発明
は、主杆5と一対の側杆6、6とを結合して三角形状の
支保要素4を形成し、その多数を互いに主杆5の端部に
おいてピン結合7すると共に、各支保要素4における両
側杆6、6の連結部間を副杆8、8により連結して、全
体をアーチ形とした支保工10に型枠体9を取付けると共
に、両端下部に走行脚車12、12を取付けて構成したアー
チ形型枠支保工Aを、アーチコンクリートBを架構する
橋脚1、1の巾方向に沿って架設したレール3、3上に
載架し、前記アーチ形型枠支保工Aによる施工を、アー
チコンクリートBの巾方向に分割設定した施工区分毎に
順次行なうようにし、各施工区分においては、同区分の
アーチコンクリートBの巾方向に配設した横筋15の端部
を隣接した施工区分側に突出するようにしてコンクリー
トを打設し、各施工区分のコンクリートの養生後、各施
工区分のコンクリートより突出し横筋15の端部を互に結
着して、その施工区分間にコンクリートを打設すること
を特徴とするものである。
Regarding the configuration of the present invention to achieve the above object,
Referring to the drawings corresponding to the embodiments, in the present invention, the main rod 5 and a pair of side rods 6 and 6 are connected to each other to form a triangular supporting element 4, and a large number of them are connected to each other. The end portions of the support elements 4 are connected by pins 7 and the connecting portions of the two side rods 6, 6 of each supporting element 4 are connected by the auxiliary rods 8, 8 so that the formwork 9 is attached to the supporter 10 having an arc shape as a whole. On the rails 3 and 3 installed along the width direction of the bridge piers 1 and 1 on which the arch concrete B is installed, the arch form support A constructed by mounting the traveling casters 12 and 12 on the lower ends of both ends is attached. The construction is performed by sequentially mounting the arch formwork support A by the construction sections divided and set in the width direction of the arch concrete B. In each construction section, the arch concrete B of the same section in the width direction. The side of the horizontal streak 15 placed in After pouring concrete so that it projects, after curing the concrete of each construction section, project from the concrete of each construction section and bond the ends of the horizontal bars 15 to each other, and then pour concrete between the construction sections. It is characterized by that.

〔実施例〕〔Example〕

図において1、1は所要の間隔毎に並列に構築した橋
脚で、各橋脚1、1の相対向する側面には、埋込ボルト
を介してブラケット2、2が所定の高さに取付けられ、
それらブラケット2、2上には各橋脚1の側面すなわち
アーチコンクリートBの横断方向に沿った水平方向のレ
ール3を架設する。そして、橋脚1、1間には、レール
3、3上に載架してアーチ形型枠支保工Aを組立てる。
In the figure, reference numerals 1 and 1 denote bridge piers constructed in parallel at required intervals, and brackets 2 and 2 are mounted at predetermined heights on opposite side surfaces of the piers 1 and 1 via embedding bolts.
On the brackets 2 and 2, a horizontal rail 3 is erected along the side surface of each pier 1, that is, along the transverse direction of the arch concrete B. Then, between the piers 1, 1, the arched form support A is mounted on the rails 3, 3 and assembled.

このアーチ形型枠支保工Aは、特開昭63−78357号公
報等によりすでに知られたものである。すなわち、主杆
5と側杆6、6とにより三角形に架構した支保要素4の
多数を、互いに主杆5、5の端部でピン7により連結す
ると共に、側杆6、6の結合頂部間を互いに主杆5より
短かい副杆8によって連結して、図示のようにアーチ支
保工10を形成し、その上面にアーチ形の型枠体9を架設
した構成となっており、その奥行き(アーチコンクリー
トBの横断方向)の長さは、施工するアーチコンクリー
トBの巾L(第3〜7図参照)のほぼ数分の1の長さと
する。
This arched form support A is already known from Japanese Patent Application Laid-Open No. 63-78357. That is, a large number of supporting elements 4 which are framed in a triangle by the main rod 5 and the side rods 6 and 6 are connected to each other by the pins 7 at the ends of the main rods 5 and 5, and between the connecting tops of the side rods 6 and Are connected to each other by a sub-rod 8 shorter than the main rod 5, an arch support 10 is formed as shown in the figure, and an arch-shaped frame 9 is erected on the upper surface thereof, and its depth ( The length of the arch concrete B in the transverse direction) is approximately a fraction of the width L (see FIGS. 3 to 7) of the arch concrete B to be constructed.

そして、アーチ支保工10の下端部には、その主杆5の
下端に支持脚11、11設けると共に、この支持脚11には、
第8図矢印のように高さ方向及び横方向への移動調節が
行なえる走行脚車12が取付けられている。
At the lower end of the arch support structure 10, supporting legs 11, 11 are provided at the lower end of the main rod 5, and the supporting leg 11 is
As shown by the arrow in FIG. 8, a traveling caster 12 is mounted which can be adjusted in height and sideways.

このように構成されたアーチ形型枠支保工Aは、橋脚
1、1に架設のレール3、3に走行脚車12、12の車輪1
3、13を介して載架され、レール3、3上を走行して所
定の位置に移動できるようにされており、また、所定の
施工位置においては、ブラケット2に着脱自在に取付け
た支承体14、14に支持脚11、11の下端を係止してアーチ
形型枠支保工Aを支持するのである。
The arched form support A constructed as described above is mounted on the piers 1, 1 on the rails 3, 3 mounted on the piers 1, 1
The support body is mounted via the rails 3 and 13 and can be moved to a predetermined position by traveling on the rails 3 and 3. In a predetermined construction position, the support body is detachably attached to the bracket 2. The lower ends of the supporting legs 11 and 11 are locked to the and support the arched form support A.

なお、本実施例においては、アーチコンクリートBの
施工を、その巾方向にほぼ2分して行なうようにするの
で、アーチ形型枠支保工10の奥行きはアーチコンクリー
トBの巾のほぼ2分の1としているが、アーチコンクリ
ートBの施工を3分割或は4分割として行なうことも可
能であり、その場合には、アーチ形型枠支保工10の奥行
きは、その分割数に応じて短くすることができる。
In this embodiment, since the arch concrete B is constructed by performing the construction in approximately two minutes in the width direction, the depth of the arch-shaped form support 10 is approximately two-half the width of the arch concrete B. Although it is assumed to be 1, it is also possible to divide the arch concrete B into three or four parts, in which case the depth of the arched form support 10 should be shortened according to the number of divisions. Can be.

実施例によるアーチコンクリートの施工では、第3〜
7図に示すように、アーチコンクリートBの全巾Lを2
分割した施工区分a、bを設定して、その区分a、b毎
に型枠施工を行なうようにする。
In the construction of arch concrete according to the embodiment,
As shown in Fig. 7, the total width L of arch concrete B is 2
The divided construction divisions a and b are set, and formwork construction is performed for each of the divisions a and b.

それで、型枠設定に先立っては、各区分毎にアーチコ
ンクリートBの巾方向にわたる横筋15、15及び縦筋等
(図示を略す)の配筋を配設する。そして、まず、アー
チ形型枠支保工Aを第3図に示すように、一方の施工区
分aに対応して位置させ、走行脚車12の高さ及び横移動
の調節によって型枠体9の位置設定を行なった後、支持
脚11を支承体14に支持させ固定する。その際、側型枠
(図示を略す)は、その区分aの横筋15、15が隣接した
区分bの方に端部を所要長突出した状態にして仮設し、
それによって、その区分aの全巾より短い巾lがコンク
リートの打設巾となる。そして、型枠体9には図示を略
した外型枠を連結してコンクリートB1を打設する。その
コンクリートB1の硬化後は、第2図に示すように、支承
体14を除去して支保工Aを走行脚車12に支持させた後、
走行脚車12の高さを低くして支保工Aを硬化させ、型枠
体9をコンクリートB1より剥離する。ついで、第4図の
ように、支保工Aを車輪13、13を介してレール上を押進
走行させ、支保工Aを隣の施工区分bの位置まで移動す
る。上述のようにして形成されたアーチコンクリートB1
は、第4図に示すように、横筋15、15がその隣接施工区
分b側の端部がコンクリートB1より突出した状態とな
る。
Therefore, prior to setting the form, horizontal bars 15, 15 and vertical bars (not shown) in the width direction of the arch concrete B are arranged for each section. Then, first, as shown in FIG. 3, the arch-shaped frame support A is positioned corresponding to one construction section a, and the height and lateral movement of the traveling caster 12 are adjusted to adjust the shape of the frame 9. After setting the position, the support leg 11 is supported and fixed to the support body 14. At that time, the side formwork (not shown) is temporarily installed with the end portion projecting for a required length toward the section b adjacent to the horizontal stripes 15, 15 of the section a,
As a result, the width l, which is shorter than the entire width of the section a, becomes the concrete placement width. Then, an external mold (not shown) is connected to the mold body 9 and concrete B 1 is poured. After the concrete B 1 is hardened, as shown in FIG. 2, after removing the support body 14 and supporting the support work A on the traveling caster 12,
The height of the traveling caster 12 is lowered to cure the support A, and the formwork 9 is separated from the concrete B 1 . Then, as shown in FIG. 4, the supporting work A is pushed on the rails via the wheels 13 to move the supporting work A to the position of the adjacent construction section b. Arch concrete B 1 formed as described above
As shown in FIG. 4, the horizontal streaks 15 and 15 are in a state in which the end portion on the side of the adjacent construction section b projects from the concrete B 1 .

移動した支保工Aは、第5図に示すように、再度上記
のように型枠体9の位置決めを行ない支保工Aを固定す
る。その間、さきに打設したコンクリートB1は、養生が
進んでそのアーチ形状は高さ方向に縮小され、図示のよ
うにコンクリート打設当初より全体に降下した状態とな
る。この施工区分bにおける側型枠等の仮設もさきの場
合と同様に行なう。そして、同区分bのコンクリートB2
を打設し、その硬化後は、さきの施工と同様にして型枠
体9をコンクリートB2より剥離し、支保工Aを撤去し
て、コンクリートB2の養成が終わるのを待つ。この区分
bにおいても、そのアーチコンクリートの巾はさきの区
分aの場合と同様に短い巾lとなる。
As shown in FIG. 5, the moved support shovel A again positions the form frame body 9 as described above to fix the shovel support A. In the meantime, the concrete B 1 that has been poured earlier is cured and the arch shape is reduced in the height direction, and as shown in the figure, the concrete B 1 is in a state where the concrete B 1 has dropped down from the beginning of the concrete pouring. Temporary provision of side molds and the like in this construction section b is performed in the same manner as in the case of the above. And concrete B 2 of the same section b
After casting, the formwork 9 is peeled off from the concrete B 2 in the same manner as the previous construction, the support work A is removed, and the training of the concrete B 2 is waited. Also in this section b, the width of the arch concrete becomes a short width 1 as in the case of the section a.

コンクリートB2の養生後は、コンクリートB1とコンク
リートB2とは第6図のようにほぼ同形となり、両コンク
リートB1、B2の横筋15、15は互いに同一線上に並ぶこと
になる。この場合、横筋15、15の突出長さを充分長くし
ておけば、それら横筋15、15の端部は図示のように互い
に重複することになり、また、両コンクリートB1、B2
には、間隙部分dが形成されることになる。
After curing the concrete B 2 , the concrete B 1 and the concrete B 2 have almost the same shape as shown in FIG. 6, and the horizontal streaks 15 and 15 of the both concretes B 1 and B 2 are aligned on the same line. In this case, if the projecting length of the horizontal bars 15, 15 is made sufficiently long, the ends of the horizontal bars 15, 15 will overlap each other as shown in the figure, and between the concrete B 1 , B 2 Will form a gap portion d.

次に、両コンクリートB1、B2より突出した横筋15、15
を決着する。その場合、横筋15、15が重複していれば、
それを互いに溶接や結束等により直接結着し、また、重
複していなければ、他の鉄筋を介して結着する。そし
て、第6図のように、間隙部分dに適宜型枠17等を仮設
して、その部分dのコンクリートB3を打設するのであ
る。それによって、コンクリートB1、B2、B3が一体結合
となり、第2図、第7図に示すように、アーチコンクリ
ートBの全体が施工されることになるのである。
Next, the horizontal bars 15, 15 protruding from both concretes B 1 , B 2
Settle. In that case, if the horizontal stripes 15 and 15 overlap,
They are directly bound to each other by welding, binding, or the like, and if they do not overlap, they are bound via another reinforcing bar. Then, as shown in FIG. 6, the mold 17 and the like are temporarily installed in the gap portion d and the concrete B 3 in the portion d is placed. As a result, the concretes B 1 , B 2 and B 3 are integrally combined, and the entire arch concrete B is constructed as shown in FIGS. 2 and 7.

〔発明の効果〕〔The invention's effect〕

以上説明したように、本発明の工法は、主杆と一対の
側杆とを結合して三角形状の支保要素を形成し、その多
数を互いに主杆の端部においてピン結合すると共に、各
支保要素における両側杆の連結部間を副杆により連結し
て、全体をアーチ形とした支保工に型枠体を取付けると
共に、両端下部に走行脚車を取付けて構成したアーチ形
型枠支保工を、アーチコンクリートを架構する橋脚の巾
方向に沿って架設したレール上に載架し、前記アーチ形
型枠支保工による施工を、アーチコンクリートの巾方向
に分割設定した施工区分毎に順次行なうようにし、各施
工区分においては、同区分のアーチコンクリートの巾方
向に配設した横筋の端部を隣接した施工区分側に突出す
るようにしてコンクリートを打設し、各施工区分のコン
クリートの養生後、各施工区分のコンクリートより突出
した横筋の端部を互に結着して、その施工区分間にコン
クリートを打設するようにしたので、次のように優れた
効果を奏するものである。
As described above, in the construction method of the present invention, the main rod and the pair of side rods are connected to each other to form a triangular support element, and a large number of them are pin-connected to each other at the end of the main rod, and each support member is supported. By connecting the connecting parts of both side rods of the element with sub-rods, the arch frame support is constructed by attaching the formwork to the arch support which has the whole arch shape and the traveling casters at both lower ends. , The arch concrete is placed on the rails installed along the width direction of the bridge pier, and the construction by the arch form support is performed sequentially for each construction section divided and set in the width direction of the arch concrete. , In each construction section, the concrete is placed so that the end of the horizontal bar arranged in the width direction of the arch concrete of the same section projects toward the adjacent construction section side, and after curing the concrete of each construction section, By mutually binding the ends of the lateral stripes protruding from the concrete construction division, since as to concrete is between its construction division, in which excellent effects as follows.

(1)アーチコンクリートを、その巾方向に複数に分割
した施工区分毎に施工するので、これに使用するアーチ
形型枠支保工はその奥行きが数分の1の大きさのもので
足りることになり、型枠支保工の経費が大巾に低減で
き、工費の節約ができる。
(1) Since arch concrete is constructed for each construction section divided into multiple sections in the width direction, arch-shaped form supports used for this purpose need only be a fraction of the depth. As a result, the cost of supporting the formwork can be greatly reduced, and the construction cost can be saved.

(2)アーチ形型枠支保工は三角形の支保要素のピン結
合による構造であって、アーチコンクリートを架構する
橋脚のレール間に載架して移動自在のものであるから、
強度が大で簡易であると共に、区分毎の分割施工が能率
よくできる。
(2) The arch formwork support structure has a structure in which triangular support elements are connected by pins, and is movable between the rails of the bridge piers on which the arch concrete is framed.
The strength is large and simple, and the division work for each section can be performed efficiently.

(3)施工区分毎の施工は、施工した区分のコンクリー
トの養生終了をまって次の中間区分の施工を行なうた
め、施工時期の違いにより生ずるコンクリート相互のず
れ違いが防止でき、一体形状のアーチコンクリートの施
工ができる。
(3) Since the construction of each construction section is performed after the completion of curing of the concrete of the constructed section and the construction of the next intermediate section is performed, it is possible to prevent misalignment of concrete caused by the difference in construction time, and the arch of the integral shape Can be used for concrete construction.

(4)アーチコンクリート全体としては、その全巾にわ
たる横通し筋によって、強度を損なうことのない一体化
した構造物となる。
(4) The entire arch concrete becomes an integrated structure that does not impair the strength due to the horizontal streak over the entire width.

【図面の簡単な説明】[Brief description of the drawings]

図面は本発明工法の実施例を示したもので、第1図は橋
脚間にアーチ形型枠支保工セットした状態を示す正面
図、第2図はアーチ形型枠支保工の移動時の状態を示す
正面図、第3図は第1図の側断面図、第4図は第2図の
側断面図、第5図は次の施工区分においてアーチ形型枠
支保工をセットした状態を示す側断面図、第6図は間隙
部分の型枠施工を示す側断面図、第7図は分割施工した
アーチコンクリートの全体を示す側断面図、第8図は橋
脚間にセットしたアーチ形型枠支保工の要部を示す拡大
正面図。 A……アーチ形型枠支保工 B……アーチコンクリート 1……橋脚、2……ブラケット 3……レール、4……支保要素 9……型枠体、10……アーチ支保工 12……走行脚車、15……横通し筋 17……間隙部の型枠
The drawing shows an embodiment of the method of the present invention. Fig. 1 is a front view showing a state where the arch formwork support is set between the piers, and Fig. 2 is a state when the arch formwork support is moved. Fig. 3 is a side sectional view of Fig. 1, Fig. 4 is a side sectional view of Fig. 2, and Fig. 5 shows a state in which arch formwork supports are set in the next construction section. Side cross-sectional view, FIG. 6 is a side cross-sectional view showing the formwork construction in the gap portion, FIG. 7 is a side cross-sectional view showing the entire arch concrete that has been divided, and FIG. 8 is an arch formwork set between the piers. The enlarged front view which shows the principal part of support work. A: Arch formwork support B ... Arch concrete 1 ... Bridge pier, 2 ... Bracket 3 ... Rail, 4 ... Supporting element 9 ... Formwork, 10 ... Arch support 12 ... Running Castor, 15 ... Horizontal thread 17 ... Formwork of gap

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】主杆と一対の側杆とを結合して三角形状の
支保要素を形成し、その多数を互いに主杆の端部におい
てピン結合すると共に、各支保要素における両側杆の連
結部間を副杆により連結して、全体をアーチ形とした支
保工に型枠体を取付けると共に、両端下部に走行脚車を
取付けて構成したアーチ形型枠支保工を、アーチコンク
リートを架構する橋脚の巾方向に沿って架設したレール
上に載架し、前記アーチ形型枠支保工による施工を、ア
ーチコンクリートの巾方向に分割設定した施工区分毎に
順次行なうようにし、各施工区分においては、同区分の
アーチコンクリートの巾方向に配設した横筋の端部を隣
接した施工区分側に突出するようにしてコンクリートを
打設し、各施工区分のコンクリートの養生後、各施工区
分のコンクリートより突出し横筋の端部を互に結着し
て、その施工区分間にコンクリートを打設することを特
徴とする、アーチコンクリートの移動式型枠施工法。
Claim: What is claimed is: 1. A main rod and a pair of side rods are connected to each other to form a triangular supporting element, and a large number of them are pin-connected to each other at an end of the main rod, and a connecting portion of both side rods of each supporting element. A bridge pier with arch concrete is used to connect arches to the arched concrete frame support, which is constructed by connecting the connecting rods with auxiliary rods and attaching the formwork to the arched supportwork on the whole, and attaching traveling casters to both lower ends. Placed on a rail erected along the width direction of, the construction by the arch form support is carried out sequentially for each construction section divided and set in the width direction of arch concrete, in each construction section, Concrete is placed so that the end of the horizontal bar arranged in the width direction of the arch concrete of the same section projects to the adjacent construction section side, and after curing the concrete of each construction section, the concrete of each construction section Ri and mutually binding the ends of the projecting horizontal stripes, characterized in that concrete is cast between its construction division, movable formwork construction methods arch concrete.
JP33029088A 1988-12-27 1988-12-27 Mobile formwork construction method for arch concrete Expired - Lifetime JP2673163B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33029088A JP2673163B2 (en) 1988-12-27 1988-12-27 Mobile formwork construction method for arch concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33029088A JP2673163B2 (en) 1988-12-27 1988-12-27 Mobile formwork construction method for arch concrete

Publications (2)

Publication Number Publication Date
JPH02176005A JPH02176005A (en) 1990-07-09
JP2673163B2 true JP2673163B2 (en) 1997-11-05

Family

ID=18230999

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33029088A Expired - Lifetime JP2673163B2 (en) 1988-12-27 1988-12-27 Mobile formwork construction method for arch concrete

Country Status (1)

Country Link
JP (1) JP2673163B2 (en)

Also Published As

Publication number Publication date
JPH02176005A (en) 1990-07-09

Similar Documents

Publication Publication Date Title
JP2700162B2 (en) Mobile formwork construction method for arch concrete
JP2673163B2 (en) Mobile formwork construction method for arch concrete
JP2673164B2 (en) Mobile formwork construction method for arch concrete
JP2553357B2 (en) Support device for formwork support for arch concrete construction
JP2754265B2 (en) Traveling formwork support
JPH046450Y2 (en)
JPH03107098A (en) Travelling type molding frame support
JPH0730527B2 (en) Bridge and its construction method
JPH03194062A (en) Running type form timbering
JP2516358B2 (en) Form support for arch concrete construction
JP2553344B2 (en) Form support for arch concrete construction
JP2754256B2 (en) Traveling formwork support
JPH0849214A (en) Construction method for installing arch concrete bar arrangement body
JP2553349B2 (en) Form support for arch concrete construction
JPH049901B2 (en)
JP2819326B2 (en) Traveling formwork support
JPS5894504A (en) Mold frame moving type constructing process of high bridge slab
JPH0348302B2 (en)
JPH0415841B2 (en)
AU746805B2 (en) A structural element
JP2524488Y2 (en) Built slab forming unit
JP2553348B2 (en) Form support for arch concrete construction
JPS62189255A (en) Running and moving mold frame apparatus for constructing high bridge slab
JPH07116832B2 (en) Mobile formwork method for multiple viaducts in parallel
JPS649406B2 (en)