JP2598314Y2 - Handrail unit for stairs - Google Patents

Handrail unit for stairs

Info

Publication number
JP2598314Y2
JP2598314Y2 JP1992071626U JP7162692U JP2598314Y2 JP 2598314 Y2 JP2598314 Y2 JP 2598314Y2 JP 1992071626 U JP1992071626 U JP 1992071626U JP 7162692 U JP7162692 U JP 7162692U JP 2598314 Y2 JP2598314 Y2 JP 2598314Y2
Authority
JP
Japan
Prior art keywords
stairs
inclination angle
border
handrail unit
handrail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1992071626U
Other languages
Japanese (ja)
Other versions
JPH0635472U (en
Inventor
清人 松波
Original Assignee
清人 松波
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 清人 松波 filed Critical 清人 松波
Priority to JP1992071626U priority Critical patent/JP2598314Y2/en
Publication of JPH0635472U publication Critical patent/JPH0635472U/en
Application granted granted Critical
Publication of JP2598314Y2 publication Critical patent/JP2598314Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【考案の詳細な説明】[Detailed description of the invention]

【0001】[0001]

【産業上の利用分野】本考案は、工場生産される階段用
手摺りユニット(階段用に既に組立られた手摺り)の改
良に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improvement of a handrail unit for stairs manufactured at a factory (handrails already assembled for stairs).

【0002】[0002]

【従来の技術】従来の階段手摺りは、現場で加工するに
は困難な作業を必要としていたが、階段用手摺りユニッ
ト(階段用に既に組立られた手摺り)は、施工能率の向
上の観点から、予め工場で製作され、施工現場では階段
に取付けるだけで良いようになっている。
2. Description of the Related Art Conventional stair handrails require difficult work to be processed on site. However, stair handrail units (handrails already assembled for stairs) are required to improve construction efficiency. From a viewpoint, it is manufactured in a factory in advance, and only needs to be attached to the stairs at the construction site.

【0003】しかし、現場で施工された階段には、種々
の傾斜角度があり、階段用手摺りユニットの傾斜角度と
一致しないことが多い。そこで、階段用手摺りユニット
もある一定の傾斜角度をカバーできる数タイプのものを
必要とし、施工現場において傾斜角度に関する調整作業
が必要となっていた。
However, stairs constructed on site have various inclination angles, and often do not coincide with the inclination angle of the handrail unit for stairs. Therefore, several types of handrail units for stairs that can cover a certain inclination angle are required, and adjustment work on the inclination angle is required at the construction site.

【0004】[0004]

【考案が解決しようとする課題】本考案は、上記の点に
鑑みてなされたものであって、その目的とするところは
傾斜角度の異なる各々階段に対して取付け調節を容易に
行って取付けすることができる階段用手摺りユニットを
提供することにある。
[Problems to be solved by the invention] The present invention has been made in view of the above points, and its purpose is to
Easy installation and adjustment for stairs with different inclination angles
An object of the present invention is to provide a handrail unit for stairs which can be mounted and mounted .

【0005】[0005]

【課題を解決するための手段】上記目的を達成するため
に本考案の階段用手摺りユニットは、一端部近傍を折曲
形成してなるボーダーの長手方向に複数本の柱部材を立
設し、これらの柱部材の上端に手摺りを取り付けると共
、上記ボーダーの裏面にボーダーの長さ方向の全長に
わたって、取付け階段傾斜角度に対する取付調節用の調
節溝を形成した構成にしてある。
SUMMARY OF THE INVENTION In order to achieve the above object, a handrail unit for stairs according to the present invention has a bent portion near one end.
It erected a plurality of column members in the longitudinal direction of the formed comprising border If you install the handrail to the upper end of the pillar members co
In, over the entire length in the length direction of the ball leader on the back of the border, adjustment for mounting adjustment to the mounting stairs inclination angle
It has a configuration in which a nodal groove is formed .

【0006】[0006]

【作用】本考案の階段用手摺りユニットによれば、階段
の側板の上縁部に嵌合する調節溝を上記ボーダーの裏面
に全長にわたって設けたので、階段の施工傾斜角度が階
段用手摺りユニットの傾斜角度よりも大きくなって、あ
らかじめ製作された階段用手摺りユニットの傾斜角度と
の間にズレが生じた場合には、上記ボーダーの下端がわ
に行く程、上記ボーダーの上記調節溝の奥面部と上記階
段の側板との間に隙間を大きくした状態で上記ボーダー
の上記調節溝を上記階段の側板に嵌合する。
According to the handrail unit for stairs of the present invention, since the adjusting groove to be fitted to the upper edge of the side plate of the stairs is provided on the entire back surface of the border, the construction inclination angle of the stairs is reduced. If the inclination angle of the stair handrail unit is larger than the inclination angle of the unit and there is a deviation from the inclination angle of the handrail unit for stairs manufactured in advance, the lower the lower end of the border, the more the adjustment groove of the border. The adjustment groove of the border is fitted to the side plate of the stairs in a state where a gap is increased between the back surface of the stairs and the side plate of the stairs.

【0007】一方、階段の施工傾斜角度が階段用手摺り
ユニットの傾斜角度よりも小さくなって、階段の設計傾
斜角度に合わせて製作された階段用手摺りユニットの傾
斜角度との間にズレが生じた場合には、上記ボーダーの
上端がわに行く程、上記ボーダーの上記調節溝の奥面部
と上記階段の側板との間に隙間を大きくした状態で上記
ボーダーの上記調節溝を上記階段の側板に嵌合する。
On the other hand, the construction inclination angle of the stairs is smaller than the inclination angle of the handrail unit for stairs, and there is a difference between the inclination angle of the handrail unit for stairs manufactured according to the design inclination angle of the stairs. If this occurs, as the upper end of the border goes all the way, the adjusting groove of the border is moved along the stairs in a state where the gap between the inner surface of the adjusting groove of the border and the side plate of the stairs is increased. Fit to side plate.

【0008】[0008]

【実施例】図1に示すように、階段用手摺りユニットA
は、ボーダー1から親柱2と子柱3を立設すると共に、
これらの柱部材2,3に手摺り4を固定して構成されて
おり、ボーダー1と手摺り4とは互いに平行となるよう
に配設されている。また、親柱2の足元部2Aにはボー
ダー垂設部10が固着されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS As shown in FIG .
Establishes the pillar 2 and the pillar 3 from the border 1,
A handrail 4 is fixed to these pillar members 2 and 3, and the border 1 and the handrail 4 are arranged so as to be parallel to each other. A border hanging portion 10 is fixed to the foot 2A of the main pillar 2.

【0009】ボーダー1のそれぞれのタイプの傾斜角度
Θは、あらゆる現場角度に対応できるように設定されて
いる。
[0009] The inclination angle Θ of each type of the border 1 is set so as to be compatible with any field angle.

【0010】図2に示すように、ボーダー1の裏面部に
はボーダー1の長さ方向の全長にわたって傾斜角度調整
溝5が設けられており、この傾斜角度調整溝5は全長に
わたって同じ深さに形成され、かつ階段Bの側板B1の
上縁部B2にある一定の調整範囲内で嵌合できるように
構成されている。傾斜角度調整溝5は、図6および図7
に示すように2条形成されており、一方の傾斜角度調整
溝5Aは、壁付き階段Bの左側取付け用であり、他方の
傾斜角度調整溝5Bは、壁付き階段Bの右側取付け用と
なっている。
As shown in FIG . 2, an inclined angle adjusting groove 5 is provided on the back surface of the border 1 over the entire length in the longitudinal direction of the border 1, and the inclined angle adjusting groove 5 has the same depth over the entire length. It is formed so that it can be fitted within a certain adjustment range on the upper edge B2 of the side plate B1 of the stairs B. The inclination angle adjusting groove 5 is shown in FIGS.
As shown in FIG. 5, one inclination angle adjusting groove 5A is for mounting the left side of the walled stairs B, and the other inclination angle adjusting groove 5B is for the right side mounting of the walled stairs B. ing.

【0011】なお、ボーダー垂設部10にもボーダー1
の傾斜角度調整溝5と連続する調整溝11(11A,1
1B)が形成されている。
The border hanging portion 10 also has a border 1
Adjustment groove 11 (11A, 1A)
1B) is formed.

【0012】階段用手摺りユニットAは、階段Bの傾斜
角度に合わせて43°,44°,45°・・・49°と
いう具合に1°間隔で傾斜角度の異なる複数のタイプの
ものがあり、施工現場に取付けられる階段Bの傾斜角度
に応じた階段用手摺りユニットAが施工現場に提供され
るのである。
There are a plurality of stair handrail units A having different inclination angles at intervals of 1 °, such as 43 °, 44 °, 45 °... 49 °, in accordance with the inclination angle of the stairs B. The stair handrail unit A corresponding to the inclination angle of the stairs B attached to the construction site is provided to the construction site.

【0013】しかし、施工された階段Bの現場傾斜角度
αは階段Bの設計傾斜角度に対して±0.5°の幅で誤
差が生じるために、階段用手摺りユニットAを階段Bに
取付ける際には傾斜角度の調整作業が必要となり、かか
る調整作業は、次のようにして行う。すなわち、
However, since the site inclination angle α of the constructed stairs B has an error within a range of ± 0.5 ° with respect to the designed inclination angle of the stairs B, the stair handrail unit A is attached to the stairs B. In such a case, it is necessary to adjust the inclination angle, and the adjustment is performed as follows. That is,

【0014】階段用手摺りユニットAの傾斜角度Θより
も階段Bの施工角度αが大きい場合には、図3に示すよ
うに、ボーダー1の下端がわに行く程、ボーダー1の傾
斜角度調整溝5の奥面部と階段Bの側板B1との間に隙
間qを大きくした状態で、ボーダー1の傾斜角度調整溝
5を階段Bの側板B1に嵌合する。
When the construction angle α of the stairs B is larger than the inclination angle Θ of the handrail unit A for stairs, as shown in FIG. With the gap q between the back surface of the groove 5 and the side plate B1 of the staircase B increased, the inclination angle adjusting groove 5 of the border 1 is fitted to the side plate B1 of the staircase B.

【0015】階段用手摺りユニットAの傾斜角度Θより
も階段Bの施工角度αが小さい場合には、図4に示すよ
うに、ボーダー1の下端がわに行く程、ボーダー1の傾
斜角度調整溝5の奥面部と階段Bの側板B1との間に隙
間qを小さくした状態で、ボーダー1の傾斜角度調整溝
5を階段Bの側板B1に嵌合する。
When the construction angle α of the stairs B is smaller than the inclination angle Θ of the handrail unit A for stairs, as shown in FIG. The inclination angle adjusting groove 5 of the border 1 is fitted to the side plate B1 of the staircase B in a state where the gap q is reduced between the inner surface of the groove 5 and the side plate B1 of the staircase B.

【0016】階段用手摺りユニットAの傾斜角度Θと階
段Bの施工角度αとが同角度の場合には、図5に示すよ
うに、隙間qを設けることなくボーダー1の傾斜角度調
整溝5を階段の側板1に嵌合すれば良い。なお、い
ずれの場合も調整溝11は階段Bの側板B1の前縁部B
3に嵌合する。
When the inclination angle の of the handrail unit A for stairs and the construction angle α of the stairs B are the same, as shown in FIG. 5, the inclination angle adjusting groove 5 of the border 1 is provided without providing a gap q. the may be fitted to the side plate B 1 staircase B. In each case, the adjustment groove 11 is formed at the front edge B of the side plate B1 of the stairs B.
3 is fitted.

【0017】このようにして階段Bに取付けられる階段
用手摺りユニットAは下地材C,D及びボーダー1から
階段Bの側板B1への取り付けにより支持固定されるの
である。
The stair handrail unit A attached to the stairs B in this way is supported and fixed by attaching the stairs B to the side plate B1 of the stairs B from the base materials C, D and the border 1.

【0018】図6は、図中の右側の側板B1が壁に付い
た階段Bの左側の側板B1に階段用手摺りユニットAを
取り付けた状態を示しており、この場合には傾斜角度調
整溝5Bに埋木Eを詰めるようにしている。図7は、
中の左側の側板B1が壁に付いた階段Bの左側の側板B
1に階段用手摺りユニットAを取り付けた状態を示して
おり、この場合には傾斜角度調整溝5Aに埋木Eを詰め
るようにしている。
FIG. 6 shows a state in which a handrail unit A for stairs is attached to a left side plate B1 of a staircase B having a right side plate B1 attached to a wall in the figure. In this case, an inclination angle adjusting groove is provided. 5B is filled with buried tree E. FIG .
Left side plate B of stairs B with left side plate B1 on the inside
FIG. 1 shows a state in which a stair handrail unit A is attached. In this case, the embedded tree E is packed in the inclination angle adjusting groove 5A.

【0019】なお、Fは覆いボードである。F is a covering board.

【0020】[0020]

【考案の効果】上記の説明から明らかなように、本考案
の階段用手摺りユニットによれば、階段の傾斜角度の施
工誤差を階段用手摺りユニットのボーダーの調節溝によ
って吸収することができるので、取付け傾斜角度の調整
作業が容易となり、現場作業時間が大幅に短縮すること
ができる。
As is clear from the above description, according to the handrail unit for stairs of the present invention, the construction error of the inclination angle of the stairs is controlled by the adjusting groove of the border of the handrail unit for stairs. Therefore, the work of adjusting the mounting inclination angle becomes easy, and the on-site work time can be greatly reduced.

【0021】[0021]

【図面の簡単な説明】[Brief description of the drawings]

【図1】本考案の階段用手摺りユニットの実施例を示す
正面図
FIG. 1 is a front view showing an embodiment of a handrail unit for stairs of the present invention.

【図2】本考案の階段用手摺りユニットの階段への取付
け動作を示す斜視図
FIG. 2 is a perspective view showing an operation of attaching the handrail unit for stairs to the stairs according to the present invention;

【図3】本考案の階段用手摺りユニットの施工状態を示
す正面図
FIG. 3 is a front view showing a construction state of the handrail unit for stairs of the present invention.

【図4】本考案の階段用手摺りユニットの施工状態を示
す正面図
FIG. 4 is a front view showing a construction state of the handrail unit for stairs of the present invention.

【図5】本考案の階段用手摺りユニットの施工状態を示
す正面図
FIG. 5 is a front view showing a construction state of the handrail unit for stairs of the present invention.

【図6】本考案の階段用手摺りユニットの施工状態を示
す側断面の説明図
FIG. 6 is an explanatory side sectional view showing a construction state of the handrail unit for stairs of the present invention .

【図7】本考案の階段用手摺りユニットの施工状態を示
す側断面の説明図
FIG. 7 is an explanatory side sectional view showing a construction state of the handrail unit for stairs of the present invention .

【符号の説明】[Explanation of symbols]

A 階段用手摺りユニット 1 ボーダー 2 柱部材(親柱) 3 柱部材(子柱) 4 手摺り Θ 階段用手摺りユニットの傾斜角度 B 階段 B1 階段の側板 B2 階段の上縁部 α 階段の傾斜角度 A Handrail unit for stairs 1 Border 2 Pillar member (main pillar) 3 Pillar member (child pillar) 4 Handrail 傾斜 Inclination angle of handrail unit for stairs B Stair B1 Side plate of stair B2 Top edge of stair α Slope of stair angle

Claims (1)

(57)【実用新案登録請求の範囲】(57) [Scope of request for utility model registration] 【請求項1】一端部近傍を折曲形成してなるボーダーの
長手方向に複数本の柱部材を立設し、これらの柱部材の
上端に手摺りを取り付けると共に、上記ボーダーの裏面
にボーダーの長さ方向の全長にわたって、取付け階段傾
斜角度に対する取付調節用の調節溝を形成したことを特
徴とする階段用手摺りユニット。
1. A border formed by bending a portion near one end.
Erected a plurality of column members longitudinally Rutotomoni attaching a handrail to the upper ends of the pillars members, the back surface of the border
Over the entire length in the length direction of the ball leader, the mounting stairs inclined
Stairs handrail unit, characterized in that the formation of the adjusting groove for mounting adjustment to oblique angles.
JP1992071626U 1992-10-14 1992-10-14 Handrail unit for stairs Expired - Lifetime JP2598314Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1992071626U JP2598314Y2 (en) 1992-10-14 1992-10-14 Handrail unit for stairs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1992071626U JP2598314Y2 (en) 1992-10-14 1992-10-14 Handrail unit for stairs

Publications (2)

Publication Number Publication Date
JPH0635472U JPH0635472U (en) 1994-05-13
JP2598314Y2 true JP2598314Y2 (en) 1999-08-09

Family

ID=13466056

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1992071626U Expired - Lifetime JP2598314Y2 (en) 1992-10-14 1992-10-14 Handrail unit for stairs

Country Status (1)

Country Link
JP (1) JP2598314Y2 (en)

Also Published As

Publication number Publication date
JPH0635472U (en) 1994-05-13

Similar Documents

Publication Publication Date Title
US5553421A (en) Structural building components
JPS58117166A (en) Module type support for stairs footboard
JP2598314Y2 (en) Handrail unit for stairs
JP3081170B2 (en) Railing support structure
JPS6025442Y2 (en) Girder cover mounting structure using molded material
JPH0417712Y2 (en)
JP7015435B2 (en) Glass railing
JP3318908B2 (en) Monsode Kasagi structure
JPH0519456Y2 (en)
JPS5912340Y2 (en) Mounting structure for handrail retaining pillars around the tower building
JPH0648030Y2 (en) Panel mounting structure for balconies, etc.
JPH069247Y2 (en) Inner wall formwork support for stairs
JPH10110511A (en) Spiral stair way
JPS6217547Y2 (en)
JPH0648029Y2 (en) Handrail wall
JPS5936587Y2 (en) Stair tread support structure
JPH0412917Y2 (en)
JP2001081927A (en) Wall-surface buried handrail
JP2551831Y2 (en) Baseboard mounting structure
JPS6143882Y2 (en)
JPH0642177A (en) Method for execution for concrete stairway
JPH0853915A (en) Stairs handrail connecting structure
KR0132119Y1 (en) Balustrade for stairway
JPS61120836U (en)
JPH0324753Y2 (en)

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080604

Year of fee payment: 9