JP2573621Y2 - Curb joint formwork - Google Patents
Curb joint formworkInfo
- Publication number
- JP2573621Y2 JP2573621Y2 JP1992043039U JP4303992U JP2573621Y2 JP 2573621 Y2 JP2573621 Y2 JP 2573621Y2 JP 1992043039 U JP1992043039 U JP 1992043039U JP 4303992 U JP4303992 U JP 4303992U JP 2573621 Y2 JP2573621 Y2 JP 2573621Y2
- Authority
- JP
- Japan
- Prior art keywords
- curb
- joint
- members
- construction
- contact
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Road Paving Structures (AREA)
- Road Repair (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Description
【考案の詳細な説明】
[0001]
[産業上の利用分野]本考案は、道路の側端等に設置す
るコンクリート製又は石材製の縁石の施工において、継
ぎ目に目地を張る際使用する縁石目地用型枠に関し、道
路工事等の縁石設置における目地施工に広く利用できる
型枠である。
[0002]
[従来の技術]従来、道路工事等における縁石施工は、
目地材を流し込み注入するために、縁石の継ぎ目の側面
に板材を当接したり、継ぎ目に縄材を押入したり、ある
いは継ぎ目の側面に紙製又は布製の粘着テープを貼り付
けて、上側から目地材を注入し、注入後、当て板、縄
材、粘着テープ等を除去し、目地用コテにより仕上げを
行っていた。
[0003]
[考案が解決しようとする課題]従来の縁石施工は上述
の通り目地材を注入するために継ぎ目に当て板や縄を使
用したり、布、紙製の粘着テープを貼り付けていた。従
って、当て板、縄材の使用の場合は手間がかかり作業能
率が著しく低下し、粘着テープの使用の場合は、粘着テ
ープが使い捨てになり費用が嵩むばかりでなく、粘着テ
ープの不完全接着が起因し、目地材の注入時に粘着テー
プが剥離して目地材の注入が不可能になることに問題が
あった。また、縁石に砂やほこりが付着していたり、水
に濡れていたり、あるいは湿っていると粘着テープは接
着不完全となるので、砂やほこりは施工前に除去する作
業が必要となり、湿りは乾くのを待たなければならない
ので工期遅延の1因でもあった。
[0004]
[課題を解決するための手段]本考案は、従来の問題点
を解決するために、当て板、縄材や粘着テープを全く使
用しないで縁石の目地施工を行うことのできるものであ
る。即ち、縁石の継ぎ目側面に対向面を当接させる断面
L形の2本の型材と、型村の適宜位置に連結される上下
2本の支持材と、縁石の上面に当接させる下側の支持材
に懸架した流し込み枠とにより構成し、前記2本の型材
と前記2本の支持材は連結位置を適宜移動し固定できる
ように、型材及び支持材にそれぞれ設けた長孔及び短孔
を貫通し適宜移動できるボルトと、ボルトを締め付ける
ナットを設けたことを特徴とする縁石の目地施工用型枠
である。
「0005]
[作用]図5及び図6により本考案の作用を説明する。
先ず2本の断面L形の型材1と2を縁石10の側面に当
て、2本の型材1,2と2本の支持材3,4の連結位置
を適宜移動させて、型材1,2と支持材3,4を縁石1
0の形状及び寸法に合わせ、断面L形の型材1,2の対
向寸る面を縁石10の継ぎ目11に当接させ、下側の支
持材4を縁石10の上面に当接させた位置で、ボルト8
とナット9を締め付けることにより連結を固定する。次
に下側の支持材4に懸架した流し込み枠5の開口上部か
らセメント等の目地材を流し込み、注入終了後、上側の
支持材3を把手にして持ち上げて抜くことにより、縁石
10から取り外す。この後、所定の目地用コテにより継
ぎ目の外面を仕上げる。
[0006]続いて行う次の縁石10の継ぎ目の施工
は、縁石10が同形状、同寸法であるから、そのままの
連結状態で型材1,2の下端側を次の縁石10の継ぎ目
の側面に挿し込んで当接すれば、下側の支持材4は縁石
10の上面に当接するので、前記同様に懸架してある流
し込み枠5から目地材を注入することができる。
[0007]
[実施例]図1及び図2、図3、図4に示す実施例によ
り説明する。縁石の継ぎ目の側面に対向する面を当接さ
せる2本の断面L形の型材1及び2と、その型材1,2
の適宜位置に略井桁場に連結された上下2本の支持材3
及び4と、縁石の上面に当接させる下側の支持材4に懸
架した流し込み枠5とにより構成する。型材1及び2の
縁石に当接させない面には、貫通するボルト8を移動さ
せるための長孔6を設け、支持材3及び4には、貫通す
るボルト8を移動させるための短孔7を設ける。この長
孔6と短孔7の長さは対象とする縁石の形状及び寸法に
応じて適宜設定し、貫通する各ボルト8の先端側には、
型材1,2と支持材3,4の連結位置を決定した後、締
め付けて固定するナット9を螺着する。下側の支持材4
に懸架する流し込み枠5は、図4に明示する如く支持材
4側に引掛け部5’を設けると共に、目地材が流入しや
すいように1側面を傾斜状に形成する。
[0008]従って、2本の型材1及び2と2本の支持
材3及び4は、それぞれ設けた長孔6及び短孔7を貫通
するボルト8を移動させ、適宜位置でナット9を締め付
けることにより、各種縁石の形状、寸法に合わせて使用
することができる。
[0009]図5及び図6は本考案を縁石の継ぎ目施工
に使用した場合を示し、型材1,2と支持材3,4はボ
ルト8、ナット9により連結位置に固定され、断面L形
の型材1,2の対向面は縁石10の継ぎ目11の側面に
当接し、下側の支持材4の下縁と流し込み枠5の傾斜側
面下縁は、図6に示す如く継ぎ目の隙間を挟さんで縁石
10の上面に当接する。従って、流し込み枠5から流し
込んだ目地材は、縁石10を汚損することなく、かつ無
駄なく継ぎ目11内に注入できる。また、継ぎ目11の
側面に当接する型材1,2は、下側の支持材4と上側の
支持材3により固定されているので、目地材の注入時に
拡がることがなく、かつ目地材の含有水を適度に排出さ
せるので目地施工能率が向上する。
[0010]
[考案の効果]本考案は、当初、対象縁石の形状及び寸
法に連結位置を合わせることにより、以後は縁石の継ぎ
目側面に簡単に挿し込んだ型材の対向面を縁石に当接さ
せるだけの操作で、目地材の注入が容易になり、縁石施
工作業の能率が著しく向上し、かつ、目地材の縁石への
付着が防止されて仕上がりが良好になる実効を有する。
また、ポルトとナットの操作で型材と支持材の連結位置
を適宜移動させることにより、あらゆる縁石の形状及び
寸法に適応させることができるので、各種縁石の施工に
繰り返し使用することができ、経済的にも有効なもので
ある。DETAILED DESCRIPTION OF THE INVENTION [0001] [Industrial application field] The present invention relates to a curb joint used for setting a joint at a joint in the construction of a concrete or stone curb installed on a side end of a road or the like. This is a formwork that can be widely used for joint construction in curb installation such as road construction. [0002] [Conventional technology] Conventionally, curb construction in road construction and the like,
In order to pour and inject the joint material, a plate material is brought into contact with the side of the seam of the curb, a rope material is pushed into the seam, or a paper or cloth adhesive tape is attached to the side of the seam, and the joint is joined from the top. The material was injected, and after the injection, the backing plate, the rope material, the adhesive tape, and the like were removed, and finishing was performed using a joint iron. [0003] [Problems to be Solved by the Invention] In the conventional curb construction, as described above, a patch plate or a rope is used at the joint to inject the joint material, or a cloth or paper adhesive tape is attached. . Therefore, when using a backing plate or a rope, it takes time and effort, and the work efficiency is remarkably reduced.When using an adhesive tape, the adhesive tape becomes disposable, which not only increases the cost, but also causes incomplete adhesion of the adhesive tape. For this reason, there is a problem that the adhesive tape is peeled off at the time of injection of the joint material, so that the joint material cannot be injected. Also, if the curb is sandy or dusty, wet or wet, the adhesive tape will be incompletely bonded, so it is necessary to remove sand and dust before construction. It had to wait for it to dry, which was one of the reasons for the delay in the construction period. [0004] [Means for Solving the Problems] The present invention is capable of performing curb joint construction without using any backing plate, rope material or adhesive tape in order to solve the conventional problems. is there. That is, two mold members having an L-shaped cross section for bringing the opposing surface into contact with the joint side surface of the curb, two upper and lower support members connected to appropriate positions of the mold village, and a lower side contacting the upper surface of the curb It is constituted by a casting frame suspended on a supporting material, and the two holes and the two holes are provided in the molding and the supporting material, respectively, so that the connecting position can be appropriately moved and fixed. It is a formwork for joint construction of a curb, which is provided with a bolt that can penetrate and move as needed and a nut for tightening the bolt. [0005] [Operation] The operation of the present invention will be described with reference to FIGS.
First, the two L-shaped cross-sections 1 and 2 are applied to the side surface of the curb 10, and the connection positions of the two cross-sections 1 and 2 and the two supports 3 and 4 are appropriately moved to form the cross-sections 1 and 2. Support materials 3 and 4 are curb 1
According to the shape and dimensions of the curb 10, the opposing surfaces of the L-shaped cross sections 1 and 2 are brought into contact with the seam 11 of the curb 10, and the lower support 4 is brought into contact with the upper surface of the curb 10. , Bolt 8
And the nut 9 are tightened to fix the connection. Next, a joint material such as cement is poured from above the opening of the pouring frame 5 suspended in the lower supporting member 4, and after the pouring, the upper supporting member 3 is grasped and lifted to be removed from the curb 10. Thereafter, the outer surface of the joint is finished with a predetermined joint iron. [0006] In the subsequent seam construction of the next curbstone 10, since the curbstones 10 have the same shape and the same size, the lower ends of the profiles 1 and 2 are connected to the side surfaces of the next curbstone 10 in the connected state. If it is inserted and abutted, the lower support member 4 abuts on the upper surface of the curb 10, so that the joint material can be injected from the pouring frame 5 suspended as described above. [Embodiment] An embodiment will be described with reference to FIGS. 1, 2, 3 and 4. Two L-shaped cross-sections 1 and 2 for abutting surfaces facing the side surfaces of the curb joints, and the cross-sections 1 and 2
Upper and lower two support members 3 connected to the approximate girder space at appropriate positions
And 4 and a pouring frame 5 suspended from a lower supporting member 4 which is brought into contact with the upper surface of the curb. A long hole 6 for moving the penetrating bolt 8 is provided on a surface of the moldings 1 and 2 that does not contact the curb, and a short hole 7 for moving the penetrating bolt 8 is provided in the supports 3 and 4. Provide. The lengths of the long hole 6 and the short hole 7 are appropriately set according to the shape and size of the curb to be processed.
After determining the connection positions of the mold members 1 and 2 and the support members 3 and 4, a nut 9 to be tightened and fixed is screwed. Lower support 4
As shown in FIG. 4, the pouring frame 5 is provided with a hooking portion 5 'on the support member 4 side, and has one side surface inclined so that the joint material can easily flow in. [0008] Accordingly, the two mold members 1 and 2 and the two support members 3 and 4 move the bolts 8 passing through the long holes 6 and the short holes 7 provided respectively, and tighten the nuts 9 at appropriate positions. Thereby, it can be used according to the shape and size of various curbs. [0009] FIGS. 5 and 6 show the case where the present invention is used for seam construction of a curbstone, wherein the shapes 1 and 2 and the supports 3 and 4 are fixed at a connection position by bolts 8 and nuts 9 and have an L-shaped cross section. The opposing surfaces of the mold members 1 and 2 abut against the side surface of the seam 11 of the curb 10, and the lower edge of the lower support member 4 and the lower edge of the inclined side surface of the casting frame 5 sandwich a gap between the seams as shown in FIG. Abuts on the upper surface of the curb 10. Therefore, the joint material poured from the casting frame 5 can be injected into the joint 11 without fouling the curb 10 and without waste. Further, since the mold members 1 and 2 abutting on the side surface of the joint 11 are fixed by the lower support member 4 and the upper support member 3, they do not spread when the joint material is injected, and the water content of the joint material does not increase. Is discharged appropriately, so that the joint construction efficiency is improved. [0010] [Effects of the Invention] In the present invention, the connection surface is initially adjusted to the shape and size of the target curb, and thereafter, the opposing surface of the mold material that is simply inserted into the joint side surface of the curb is brought into contact with the curb. With only this operation, the injection of the joint material is facilitated, the efficiency of the curb work is remarkably improved, and the adhesion of the joint material to the curb is prevented, so that the finish is improved.
In addition, by appropriately moving the connection position of the shape member and the support material by operating the port and the nut, it can be adapted to any shape and size of the curb, so that it can be repeatedly used for construction of various curbs, and is economical. It is also effective.
【図面の簡単な説明】 [図1]本考案の実施例の正面図である。 [図2]図1の右側面図である。 [図3]図1のA−A’部断面図である。 [図4]図1のB−B’部断面図である。 [図5]本考案の使用状態における正面図である。 [図6]図5のC−C’部断面図である。 [符号の説明] 1 型材 2 型材 3 支持材 4 支持材 5 流し込み枠 5’ 引掛け部 6 長孔 7 短孔 8 ボルト 9 ナット 10 縁石 11 継ぎ目[Brief description of the drawings] FIG. 1 is a front view of an embodiment of the present invention. FIG. 2 is a right side view of FIG. FIG. 3 is a sectional view taken along the line A-A ′ of FIG. FIG. 4 is a sectional view taken along the line B-B 'of FIG. FIG. 5 is a front view of the present invention in use. FIG. 6 is a sectional view taken along the line C-C 'of FIG. [Explanation of symbols] 1 type material 2 Mold material 3 support materials 4 Support materials 5 Filling frame 5 'hook 6 long hole 7 Short hole 8 volts 9 nuts 10 Curb 11 seams
Claims (1)
断面L形の2本の型材1及び2と、型材1及び2の適宜
位置に連結される上下2本の支持材3及び4と、縁石の
上面に当接させる下側の支持材4に懸架した流し込み枠
5とにより構成し、前記2本の型材1及び2と前記2本
の支持材3及び4は連結位置を適宜移動し固定できるよ
うに、型材1、2及び支持材3、4にそれぞれ設けた長
孔6及び短孔7を貫通し適宜移動できるボルト8と、ボ
ルト8を締め付けるナット9を設けたことを特徴とする
縁石の目地施工用型枠。(57) [Claims for Registering Utility Model] [Claim 1] Two mold members 1 and 2 having an L-shaped cross section for bringing the opposing surface into contact with the joint side surface of the curb, and are connected to appropriate positions of the mold members 1 and 2. Upper and lower support members 3 and 4 and a pouring frame 5 suspended on a lower support member 4 to be brought into contact with the upper surface of the curb, and the two mold members 1 and 2 and the two support members The bolts 8 and the bolts 8 that can be appropriately moved through the elongated holes 6 and the short holes 7 respectively provided in the mold members 1 and 2 and the support members 3 and 4 so that the members 3 and 4 can appropriately move and fix the connection position. A joint formwork for curb joints, comprising a nut 9 to be tightened.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1992043039U JP2573621Y2 (en) | 1992-05-12 | 1992-05-12 | Curb joint formwork |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1992043039U JP2573621Y2 (en) | 1992-05-12 | 1992-05-12 | Curb joint formwork |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0594305U JPH0594305U (en) | 1993-12-24 |
JP2573621Y2 true JP2573621Y2 (en) | 1998-06-04 |
Family
ID=12652770
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1992043039U Expired - Lifetime JP2573621Y2 (en) | 1992-05-12 | 1992-05-12 | Curb joint formwork |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2573621Y2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5361013B2 (en) * | 2012-02-23 | 2013-12-04 | 株式会社北友 | Form for waterway joint construction and waterway joint construction method using the formwork |
-
1992
- 1992-05-12 JP JP1992043039U patent/JP2573621Y2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH0594305U (en) | 1993-12-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8967588B2 (en) | Concrete sideform system | |
JP2573621Y2 (en) | Curb joint formwork | |
CN208899860U (en) | A kind of building template fastening kit | |
JPH065501Y2 (en) | Metal fitting for stealing | |
JPH0828045A (en) | Ready-mixed concrete leakage prevention metal fitting during construction of concrete retaining wall | |
JP2004300764A (en) | Decorative panel for form | |
JP2597851Y2 (en) | Adjustment mechanism for abandoned formwork | |
JPH0724483Y2 (en) | Soil concrete crack prevention device | |
JP2003314057A (en) | Form for gutter | |
JP3202101B2 (en) | Construction method of balustrade in concrete structure with balustrade | |
JPH0248495Y2 (en) | ||
KR200326859Y1 (en) | Height Height Adjustment Form | |
JPH0142602Y2 (en) | ||
JPH0799001B2 (en) | block | |
JPS585682Y2 (en) | expansion joint device | |
JPH1181209A (en) | Composite wooden brick of wooden material and concrete | |
JPH0826600B2 (en) | Concrete slab joint structure | |
JP3021412U (en) | Reinforcing bar receiver for construction slope | |
JPH0972029A (en) | Fixing work method for concrete placing form | |
JP2548446Y2 (en) | In-situ concrete casting type synthetic resin port curb | |
JP3048605U (en) | Flexible joint material for concrete pavement | |
JP3017169U (en) | Cement-based hardening material transfer formwork | |
JPH0734961Y2 (en) | Concrete formwork dam | |
JPS6235810Y2 (en) | ||
JPH0573563B2 (en) |