JP2516272B2 - Mobile crane operation plan creation support device - Google Patents

Mobile crane operation plan creation support device

Info

Publication number
JP2516272B2
JP2516272B2 JP2147211A JP14721190A JP2516272B2 JP 2516272 B2 JP2516272 B2 JP 2516272B2 JP 2147211 A JP2147211 A JP 2147211A JP 14721190 A JP14721190 A JP 14721190A JP 2516272 B2 JP2516272 B2 JP 2516272B2
Authority
JP
Japan
Prior art keywords
crane
equipment
mobile
displaying
support device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2147211A
Other languages
Japanese (ja)
Other versions
JPH0441390A (en
Inventor
良平 宮原
美樹 吉田
茂 大越
俊昭 好永
澄雄 岩島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2147211A priority Critical patent/JP2516272B2/en
Publication of JPH0441390A publication Critical patent/JPH0441390A/en
Application granted granted Critical
Publication of JP2516272B2 publication Critical patent/JP2516272B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/18Control systems or devices
    • B66C13/48Automatic control of crane drives for producing a single or repeated working cycle; Programme control

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は。移動式クレーンの稼働計画作成を支援する
ための装置に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to: The present invention relates to a device for supporting the operation planning of a mobile crane.

〔従来の技術〕[Conventional technology]

移動式クレーンは、例えばビルや大型施設等の建設現
場において、資材、機器等の運搬に用いられるが、その
稼働に当っては運搬する物体やクレーンの部材が既設の
設備に衝突しないようにして安全で効率のよい運転を行
う必要がある。このためにクレーンの搬入位置、物体の
運搬経路とクリアランス(運搬物体と障害物との距
離)、運搬作業に要する時間などの稼働計画を予め作成
して運転が行われるが、この稼働計画の作成は従来、主
として人手により行われていた。また特開昭62−114063
号に記載のものでは、何かの設計を行うときに、その設
計物体と干渉する可能性のある点検体との干渉の有無を
コンピュータシミュレーションにより調べて表示する。
これはクレーン稼働中の衝突の検査に用いることができ
る。
Mobile cranes are used to transport materials and equipment at construction sites such as buildings and large-scale facilities, but when operating them, make sure that the objects to be transported and the members of the crane do not collide with existing equipment. It is necessary to drive safely and efficiently. For this purpose, operation plans are created in advance such as the loading position of the crane, the transportation route and clearance of the object (distance between the transported object and the obstacle), and the time required for the transportation work. In the past, this was mainly done manually. In addition, JP-A-62-114063
In the method described in No. 6, when performing some design, the presence or absence of interference with the inspection body that may interfere with the design object is checked by computer simulation and displayed.
It can be used to check for collisions while the crane is operating.

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

上記した従来技術は、その殆どが手作業によるもので
あるため、稼働計画作成に莫大な時間がかかり、作業性
が悪いという問題があった。
Since most of the above-described conventional techniques are manual work, there is a problem that it takes a huge amount of time to create an operation plan and the workability is poor.

本発明の目的は、移動式クレーンの稼働計画を効率よ
く作成できる稼働計画作成支援装置を提供するにある。
An object of the present invention is to provide an operation plan creation support device that can efficiently create an operation plan for a mobile crane.

〔課題を解決するための手段〕[Means for solving the problem]

上記の目的は、使用するクレーンに関する性能、規格
等のデータと、建屋等の作業環境や作業条件に関するデ
ータと、運搬する機材に関するデータとを格納したデー
タベースと、実際の作業条件・環境、使用クレーン及び
運搬する機材が指定されたときにこれらのデータベース
を参照して作業状況を示す画面を作成する手段と、運搬
する機材の搬入位置や組立の順序等の情報から機材の搬
入手順を定める手段と、クレーンブームと建屋との干渉
有無のチェック手段と、クレーンの接地圧計算手段と、
クレーン走行軌跡計算手段と、クレーンによる吊り込み
作業時間及び吊り込み可能作業半径の計算手段と、クレ
ーンの吊り込み動作最適化手段と、これら各手段による
処理結果を表示する手段とを設けることにより達成され
る。
The above-mentioned purpose is a database that stores data on the performance and standards of cranes used, data on the working environment and working conditions of buildings, etc., and data on the equipment to be transported, actual working conditions / environment, and cranes used. And means for creating a screen showing the work status by referring to these databases when the equipment to be transported is specified, and means for determining the equipment loading procedure from information such as the loading position of the equipment to be transported and the order of assembly. , Means for checking for interference between the crane boom and the building, means for calculating the ground pressure of the crane,
Achieved by providing crane traveling locus calculation means, means for calculating the hoisting work time and workable radius of the crane, hoisting operation optimization means for the crane, and means for displaying the processing results by these means. To be done.

〔作用〕[Action]

使う可能性のあるクレーン各種の情報と、建屋や設備
とそれが建設・組立てられていく時間経過に伴って変化
するクレーンの作業環境に関する情報と、クレーンで運
搬する可能性のある機器、部材等のデータとを予め作成
してデータベースへ入力し、必要に応じてこれらのデー
タを参照しながら搬入手順決定、干渉確認、接地圧、走
行軌跡、作業時間、可能な作業半径等の計算と表示、及
び稼働計画の最適化等を計算機により算出するから、ク
レーン作業が効率よくかつ安全に行える稼働計画を効率
よく作成できる。
Information on various types of cranes that may be used, information on the working environment of the building and equipment and the cranes that change over time as they are constructed and assembled, and equipment and parts that may be transported by the crane. , And input it to the database in advance, and referring to these data as needed, carry out procedure determination, interference confirmation, ground pressure, running locus, working time, calculation and display of possible working radius, etc., Also, since the optimization of the operation plan is calculated by a computer, it is possible to efficiently create an operation plan that allows the crane work to be performed efficiently and safely.

〔実施例〕〔Example〕

以下、本発明を実施例により説明する。以下では大型
移動式のクローラクレーン(キャタピラで走行するクレ
ーン)の稼働計画作成支援装置を例とし、その一実施例
を第2図に示す。演算処理装置5は、入力装置4からの
入力データと、大型移動式クレーンデータ記憶装置7、
搬入計画物データ記憶装置6、及び標準機器パターンデ
ータ記憶装置8を参照して処理を行い、作成した画像デ
ータを画像データ記憶装置3へ送る。その画像データは
画像表示制御装置2を介してディスプレイ装置1に表示
される。
Hereinafter, the present invention will be described with reference to examples. In the following, an operation plan creation support device for a large mobile crawler crane (a crane traveling on a caterpillar) is taken as an example, and one embodiment thereof is shown in FIG. The arithmetic processing unit 5 includes input data from the input unit 4, a large mobile crane data storage unit 7,
Processing is performed by referring to the carry-in plan data storage device 6 and the standard equipment pattern data storage device 8, and the created image data is sent to the image data storage device 3. The image data is displayed on the display device 1 via the image display control device 2.

第3図は、第2図の装置により大型移動式クレーン稼
働計画作成時のディスプレイ装置1の表示例を示してお
り、原子炉建物、タービン建物等の射体立上がり工程と
ヤード建築物との関連からクレーンの稼働エリアや作業
半径などを求めるときの画像である。以下ではこのよう
な稼働計画作成の動作を第1図、第4図〜第14図を用い
て説明する。これらの処理プログラムは演算処理装置5
内のメモリに格納されているとする。
FIG. 3 shows a display example of the display device 1 when the large mobile crane operation plan is created by the device of FIG. 2, and shows the relationship between the projectile rising process of the reactor building, turbine building, etc. and the yard building. It is an image when obtaining the operating area and working radius of the crane from. Hereinafter, such an operation plan creating operation will be described with reference to FIGS. 1 and 4 to 14. These processing programs are executed by the arithmetic processing unit 5
It is assumed that it is stored in the internal memory.

第1図は稼働計画作成手順の全体処理フローの一実施
例であり、まず処理100では使用クレーンに関するデー
タ及びクレーン使用環境の建物、設備等のレイアウトデ
ータを記憶装置7,6から取り出し、ディスプレイ装置1
に表示する。この詳細は第4図に示されており、ステッ
プ101で入力装置4から、第5図に示すように、使用す
るクレーンの型番(第5図の例ではCC10、TW20、TW30)
と、表示するレイアウトデータの条件データ(第5図の
例ではプラント名K4、建屋コードT,R,H,S,ヤード法面形
状YD03等)とを入力する。次にステップ102では、ステ
ップ101で入力したレイアウトデータの条件データに従
い、記憶装置6からレイアウトデータを、記憶装置7か
らクレーンデータを読み込み、これらのうち形状に関す
るデータをディスプレイ装置1へ表示する。ここでクレ
ーンデータには、その形状、寸法の他に、クレーンの稼
働、巻き上げ、旋回速度等の性能データも含まれ、これ
らは後の処理に用いられる。
FIG. 1 is an example of the overall processing flow of the operation plan creation procedure. First, in process 100, data regarding the crane used and layout data such as buildings and facilities in the crane use environment are retrieved from the storage devices 7 and 6, and the display device 1
To be displayed. The details are shown in FIG. 4, and in step 101, from the input device 4, as shown in FIG. 5, the model number of the crane to be used (CC10, TW20, TW30 in the example of FIG. 5).
And the condition data of the layout data to be displayed (plant name K4, building code T, R, H, S, yard slope YD03, etc. in the example of FIG. 5). Next, in step 102, the layout data is read from the storage device 6 and the crane data is read from the storage device 7 according to the condition data of the layout data input in step 101, and the data regarding the shape is displayed on the display device 1. Here, in addition to the shape and size of the crane, the crane data also includes performance data such as crane operation, hoisting, and turning speed, which are used for subsequent processing.

第1図の処理110は、機器搬入を大型移動式クレーン
を使用して行うときの諸条件データをキーボード、マウ
ス等の入力装置4から入力設定する。第6図はその具体
例を示しており、ステップ111では入力装置4から機器
搬入計画を実施するてめのヤード法面形状及び建設期間
中の道路である進入路データを入力し、その設定条件デ
ータを演算処理装置5内のメモリに書き込み記憶する。
ステップ112では搬入機器データのコード番号を入力
し、次のステップ113では、プラント構内に輸送された
機器の進入経路データ及び荷取り位置のデータを入力
し、ステップ114では機器を搬入する建屋内配置位置を
入力する。ここで、搬入位置と機器配置の位置とは、機
器配置位置に直接クレーンで運ぶときは一致するが搬入
口までクレーンで搬入する場合は一致しない。ステップ
115では、建物周辺で予め予定されている大型移動式ク
レーンの稼働エリアデータの入力を行う。
In process 110 of FIG. 1, various condition data for carrying in equipment using a large mobile crane are input and set from an input device 4 such as a keyboard and a mouse. FIG. 6 shows a concrete example thereof. In step 111, the yard slope shape for carrying out the equipment carry-in plan and the approach road data which is the road during the construction period are input from the input device 4 and the setting conditions are set. The data is written and stored in the memory in the arithmetic processing unit 5.
In step 112, enter the code number of the carried-in equipment data, in the next step 113, enter the entry route data and the data of the pickup position of the equipment transported to the plant premises, and in step 114, place the equipment in the building Enter the position. Here, the carry-in position and the equipment arrangement position are the same when the equipment is directly carried to the equipment arrangement position by the crane, but are not the same when the equipment is brought in by the crane. Step
At 115, the operation area data of the large mobile crane, which is scheduled around the building, is input.

第1図の処理120は、搬入機器データの検索を行うも
ので、その具体例を第7図に示す。まずステップ121で
第6図のステップ112で入力した搬入機器コード番号よ
り機器の形状パターンを記憶装置8から読み出し、ステ
ップ122で搬入時の機器の分割形状及び員数の設定を行
い、ステップ123で搬入時の機器重量の計算を行い、最
後にステップ124で吊り込み用治具の設定及びその計画
を行う。
The process 120 of FIG. 1 is to search the carried-in equipment data, and a specific example thereof is shown in FIG. First, in step 121, the shape pattern of the device is read from the storage device 8 from the carry-in device code number input in step 112 of FIG. 6, the divided shape and the number of members of the device at the time of carry-in are set in step 122, and the carry-in is carried out in step 123. The device weight at that time is calculated, and finally, in step 124, the hanging jig is set and its plan is performed.

第1図の処理130は、機器分割形状及び台数をもとに
搬入手順を定めてそのシミュレーションを実施する。第
8図はその具体例を示すもので、例えばタービン建屋の
復水器は、タービン1100MW出力の場合A,B,C3系列があ
り、かつ各復水器は下部胴、上部胴、水室に分かれる。
これらの搬入重量とクレーンの吊り能力、及び作業半径
から、搬入手順を定める必要がある。そこでステップ13
1ではまず搬入する材料の数よりその吊り込み手順の計
画を行い、ステップ132では据付位置の困難な機器、又
は次工程に影響しない(大型クレーンより遠くにある)
機器を先に搬入するように吊り込み計画を行う。さらに
ステップ133では機器の吊り込み員数及び作業半径の変
化により後部クローラのカウンタウェートの重量積変え
を実施する手順を計画し、ステップ134では一連の吊り
込み手順のシミュレーションを実施する。
The process 130 of FIG. 1 defines a carry-in procedure based on the device division shape and the number of devices, and executes the simulation. Fig. 8 shows a specific example. For example, the condenser of the turbine building has A, B, C3 series in the case of turbine 1100 MW output, and each condenser has a lower body, an upper body, and a water chamber. Divide.
It is necessary to determine the loading procedure based on the loading weight, crane lifting capacity, and working radius. So step 13
In 1), first plan the hoisting procedure based on the number of materials to be loaded, and in step 132, do not affect the equipment that is difficult to install or the next process (it is far from the large crane).
Plan to suspend the equipment so that it will be loaded first. Further, in step 133, a procedure for changing the weight product of the counterweight of the rear crawler is planned by changing the number of hanging members of the device and the working radius, and in step 134, a simulation of a series of hanging procedures is executed.

第1図の処理140は、大型移動式クレーンのブームと
建設中の建屋外壁立上り部との干渉チェックを行って、
クレーンの作業半径が機器設定位置まで届くかどうかの
確認を行う。第9図はその具体例を示すもので、ステッ
プ141では建設工期に従った建屋立上がり形状の表示を
行う。ステップ142では大型移動式クレーンの前部クロ
ーラの位置を設定し、ブームを倒伏したとき建屋に干渉
しないブーム角度を設定し表示する。ステップ143で設
定されたブーム角度で機器搬入に必要な作業半径が確保
されているか確認する。これは長さ100mのブームが、垂
直方向から30度傾けば水平方向に50m、60度傾けば86m離
れた位置に吊降することができるので、これが必要な距
離だけ確保できているかどうかを調べることである。ス
テップ144では、以上で求めたブーム角で動作させた状
態をシミュレートして画面上でその確認を行う。
The process 140 of FIG. 1 is to check the interference between the boom of the large mobile crane and the rising part of the outdoor wall under construction,
Check whether the working radius of the crane reaches the equipment setting position. FIG. 9 shows a specific example thereof, and in step 141, the building rising shape according to the construction period is displayed. In step 142, the position of the front crawler of the large mobile crane is set, and the boom angle that does not interfere with the building when the boom is laid down is set and displayed. Confirm that the working angle required for loading the equipment is secured at the boom angle set in step 143. This is because a 100m long boom can be hung at a distance of 50m horizontally when tilted 30 degrees from the vertical and 86m away when tilted 60 degrees, so check whether this is the required distance. That is. In step 144, a state in which the robot is operated at the boom angle obtained above is simulated and the confirmation is performed on the screen.

第1図の処理150はクレーン接地圧の計算を行うもの
で、大型移動式クローラクレーンの場合、総重量は3000
t程度にもなり、この接地圧の計算は地盤計画に必要と
なる。第10図はその具体例を示すもので、ステップ151
で吊荷重量と作業半径からモーメントを計算し、ステッ
プ152で後部クローラに必要なカウンタウェートの計画
を行い、ステップ153,154で吊荷を吊り上げ、吊降した
場合の前,後クローラの接地圧計算を行う。この接地圧
は最大80t/m2の超高層ビルのマット部荷重程度に達する
こともあり、これに応じた地盤計画の荷重条件を与え
る。ステップ155ではそれらの荷重の、稼働エリア内で
の分布を表示する。
The process 150 in Fig. 1 is to calculate the crane ground pressure, and in the case of a large mobile crawler crane, the total weight is 3000.
It will be about t and the calculation of this ground pressure will be necessary for the ground plan. FIG. 10 shows a concrete example thereof, and step 151
Calculate the moment from the suspended load amount and working radius in step 152, plan the counterweight required for the rear crawler in step 152, and lift the suspended load in steps 153 and 154, and calculate the ground pressure of the front and rear crawlers when suspended. To do. This ground contact pressure may reach the maximum load of 80t / m 2 on the mat part of a skyscraper, and the load condition of the ground plan corresponding to this can be given. In step 155, the distribution of those loads within the operating area is displayed.

第1図の処理160は、大型移動式クレーンの走行時の
軌跡を求め、作画するもので、第11図はその具体例を示
すフローチャートである。まずステップ161で荷取り時
の大型移動式クレーンの位置設定を行い、ステップ162
で後部クローラのピボットターン、ステップ163で後部
クローラの旋回、ステップ164で前部クローラのピボッ
トターンと大型移動式クレーンの前進、ステップ165で
後部クローラのピボットターンと旋回の各動作を、吊り
荷が所定位置へ移動するように定める。そして最後のス
テップ166で荷取り位置から荷降ろしに至るまでのクロ
ーラの軌跡図を作画し表示する。第12図は上記動作の例
を示しており、第11図ステップ162,163,164,及び165の
各動作が、第12図のa,b,cとd、及びeとfにそれぞれ
対応する。
The process 160 of FIG. 1 is to obtain and draw the trajectory of the large mobile crane during traveling, and FIG. 11 is a flowchart showing a specific example thereof. First, in step 161, the position of the large mobile crane at the time of unloading is set, and in step 162
At the rear crawler pivot turn, at step 163 the rear crawler swivel, at step 164 the front crawler pivot turn and the large mobile crane advance, and at step 165 the rear crawler pivot turn and swivel operation is performed. Determine to move to a predetermined position. Then, in the final step 166, a trajectory map of the crawler from the unloading position to the unloading is drawn and displayed. FIG. 12 shows an example of the above operation, and the operations of steps 162, 163, 164, and 165 in FIG. 11 correspond to a, b, c and d, and e and f in FIG. 12, respectively.

第1図の処理170は、大型移動式クレーンの吊荷開始
から吊降ろし設定完了に至るまでのクレーンの作業時間
を予測し表示するものである。第13図はその具体例を示
しており、まずステップ171でクレーンの所定位置から
荷取り位置までブームを倒す時間を計算する。これによ
ってフックが機器の真上に来るので、次はステップ172
でフックの下げ降ろし時間を計算し、ステップ173でフ
ックに搬入する機器を玉掛けする作業時間を計算する。
以下、ステップ174では機器吊り上げ時のフック巻き上
げ時間を計算し、ステップ175で大型移動式クレーン走
行時にその重心が安定するようブームを起伏させる時間
を計算し、ステップ176でクレーンが走行して吊荷を降
ろす位置に移動するまでの時間を計算し、ステップ177
及び178でブームを倒伏しフックを下げ降ろす時間を計
算する。さらにステップ179で荷降ろし及び微調整の時
間を計算して吊り荷から荷降ろしに至るまでのトータル
時間を算出する。
The process 170 of FIG. 1 is for predicting and displaying the working time of the crane from the start of hoisting of the large mobile crane to the completion of hoisting setting. FIG. 13 shows a specific example thereof. First, in step 171, the time for tilting the boom from the predetermined position of the crane to the unloading position is calculated. This will bring the hook directly above the device, so next step 172
In step 173, the time for lowering and lowering the hook is calculated, and in step 173, the working time for slinging the equipment to be carried into the hook is calculated.
Below, in step 174, the hook hoisting time for lifting the equipment is calculated, in step 175 the time for hoisting the boom to stabilize the center of gravity of the large mobile crane is calculated, and in step 176 the crane travels to suspend the load. Calculate the time required to move to the position where
At 178, calculate the time to lay down the boom and lower the hook. Further, in step 179, the time for unloading and fine adjustment is calculated to calculate the total time from hanging load to unloading.

第1図の処理180は大型移動式クレーンの吊降ろし可
能な作業半径を求めて表示するもので、その具体例を第
14図に示す。まずステップ181で大型移動式クレーンの
前部クローラの位置設定を行い、ステップ182で建設工
期による建屋立上がり寸法の計算を行い、ステップ183
でクレーン位置と建物立上がり寸法からブームの可能な
倒角角度を計算で求め、ステップ184で作業半径の計算
及びその表示を行う。
The process 180 of FIG. 1 is to find and display the working radius of the large mobile crane that can be hung and displayed.
Shown in Figure 14. First, in step 181, the position of the front crawler of the large mobile crane is set, and in step 182, the building rise dimension is calculated according to the construction period.
In step 184, the possible tilt angle of the boom is calculated from the crane position and the building rise dimension, and in step 184 the working radius is calculated and displayed.

第1図の処理190は、大型移動式クレーンの稼働計画
に当って、最適化動作シミュレーションを行うものであ
り、その具体例を第15図に示す。まずステップ191でク
レーンの吊込み時間を最小にするように補正する。これ
はフックの吊上げ、吊降ろし速度とブームの起伏速度の
組合せを替えることによって最小作業時間を計算するこ
とにより行われる。ステップ192では、クレーンの稼働
方法を再調整することにより、稼働エリアを最小にする
よう補正を行う。ステップ193ではクレーンの走行距
離、旋回、ターン回数等を、他の機器の吊り込み時期を
調整することにより最小とするよう補正する。最後にス
テップ194で、1台及び複数台のクレーンの最適化動作
シミュレーションを実施するとともに、プラントトータ
ルとしての最適化動作シミュレーションを行う。
The process 190 in FIG. 1 is to perform an optimized operation simulation in the operation plan of the large mobile crane, and a specific example thereof is shown in FIG. First, in step 191, correction is made to minimize the crane hoisting time. This is done by calculating the minimum working time by changing the combination of hook hoisting and hoisting speed and boom hoisting speed. In step 192, the operation method of the crane is readjusted to make a correction to minimize the operation area. In step 193, the traveling distance, turning, number of turns, etc. of the crane are corrected to be the minimum by adjusting the hoisting timing of other equipment. Finally, in step 194, an optimized operation simulation of one crane and a plurality of cranes is performed, and an optimized operation simulation of the plant as a whole is performed.

〔発明の効果〕〔The invention's effect〕

本発明によれば、使用するクレーンの性能等に関する
データと、建屋等の作業環境に関するデータ、及びクレ
ーンで運搬する対象物に関するデータとを予めデータベ
ースとして用意しておくことにより、クレーン稼働計画
の作成が容易となり、同時に作業の効率化と安全性の確
保、ならびに地盤養生施工費の低減を図ることが出来る
という効果があり、また事前にクレーンによる搬入操作
をシミュレーションにより運転員に示すことができるの
で、運転員がこれを見ることにより実際のクレーン運転
時の操作をより確実にかつ安全に行えるという効果もあ
る。
According to the present invention, a crane operation plan is created by preparing in advance a database of data regarding the performance of the crane to be used, data regarding the working environment of a building, etc., and data regarding the objects to be transported by the crane. It is easy to do, and at the same time, the work efficiency and safety can be secured, and the ground curing construction cost can be reduced, and since the loading operation by the crane can be shown to the operator in advance by a simulation. There is also an effect that the operator can perform the operation during the actual crane operation more reliably and safely by seeing this.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明の装置による大型移動式クローラクレー
ン稼働計画支援作成処理の一実施例を示すフローチャー
ト、第2図及び第3図は本発明の装置の一構成例を示す
ブロック図及びディスプレイ装置の表示画面例を示す
図、第4図〜第15図は第1図のフローチャートの各処理
の詳細を示す図とその説明図である。 1……ディスプレイ装置、4……入力装置、5……演算
処理装置、6……搬入計画物データ記憶装置、7……大
型移動式クレーンデータ記憶装置、8……標準機器パタ
ーンデータ記憶装置。
FIG. 1 is a flow chart showing an embodiment of a large-sized mobile crawler crane operation plan support creation process by the device of the present invention, and FIGS. 2 and 3 are block diagrams and display devices showing an example of the configuration of the device of the present invention. FIG. 4 is a diagram showing an example of the display screen of FIG. 1 ... Display device, 4 ... Input device, 5 ... Arithmetic processing device, 6 ... Carry-in plan data storage device, 7 ... Large mobile crane data storage device, 8 ... Standard equipment pattern data storage device.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 好永 俊昭 茨城県日立市幸町3丁目1番1号 株式 会社日立製作所日立工場内 (72)発明者 岩島 澄雄 茨城県日立市幸町3丁目1番1号 株式 会社日立製作所日立工場内 (56)参考文献 特開 昭61−145099(JP,A) 実公 昭60−20123(JP,Y2) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Toshiaki Yoshinaga 3-1-1, Saiwaicho, Hitachi, Ibaraki Hitachi Ltd. Hitachi factory (72) Inventor Sumio Iwashima 3-chome, Saiwaicho, Hitachi, Ibaraki No. 1 Inside Hitachi factory, Hitachi, Ltd. (56) References JP 61-145099 (JP, A) Jitsuko Sho 60-20123 (JP, Y2)

Claims (7)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】移動式クレーンに関する情報と移動式クレ
ーンを用いて作業を行う建屋もしくは設備に関する情報
と移動式クレーンにより運搬される機材に関する情報と
を格納したデータベースと、使用するクレーンと該クレ
ーンを用いて作業を行うとする建屋もしくは設備と上記
クレーンにより運搬される機材と該機材の仮置場位置及
び使用位置とを含む指定入力が与えられたときに上記デ
ータベースの情報を参照して上記指定入力により与えら
れた建屋もしくは設備、クレーン、及び機材の配置を示
す作業状況の画面を作成し、該作成した画面を表示手段
上に表示する作業状況作成表示手段と、上記作業状況の
もとでクレーンを運転したときのクレーンの動作をシミ
ュレートし表示するシミュレーション手段とを設けたこ
とを特徴とする移動式クレーンの稼働計画作成支援装
置。
1. A database that stores information about mobile cranes, a building or equipment that works using the mobile cranes, and information about equipment transported by the mobile cranes, a crane to be used, and the cranes to be used. When the designation input including the building or equipment to be used for the work, the equipment transported by the crane, the temporary storage position and the use position of the equipment is given, the designation input is made by referring to the information in the database. Created a work status screen showing the layout of the building or equipment, the crane, and the equipment, and displaying the created screen on the display means, and the crane under the above work status. And a simulation means for simulating and displaying the operation of the crane when the vehicle is operating. Operation plan creation support apparatus of formula crane.
【請求項2】前記シミュレーション手段は、前記作業状
況のもとでクレーンの運転方法を指定したときにクレー
ンのブームと建屋もしくは設備とのクリアランス距離及
び干渉の有無をしらべこれを表示する機能を有したこと
を特徴とする請求項1記載の移動式クレーンの稼働計画
作成支援装置。
2. The simulation means has a function of displaying the clearance distance between the boom of the crane and the building or equipment and the presence or absence of interference when the operating method of the crane is specified under the working condition. The operation plan creation support device for a mobile crane according to claim 1, characterized in that.
【請求項3】前記シミュレーション手段は、前記作業状
況のもとでクレーンの運転速度を指定したときに作業に
必要とする時間を求めてこれを表示する機能を有したこ
とを特徴とする請求項1記載の移動式クレーンの稼働計
画作成支援装置。
3. The simulation means has a function of obtaining and displaying a time required for work when the operating speed of the crane is specified under the work situation. 1. The mobile crane operation plan creation support device described in 1.
【請求項4】前記シミュレーション手段は、前記指定し
たクレーン及び運搬物体の重量に関する情報からクレー
ン下部に加わる接地圧を求めてこれを表示する機能を有
したことを特徴とする請求項1記載の移動式クレーンの
稼働計画作成支援装置。
4. The movement according to claim 1, wherein the simulation means has a function of obtaining a ground pressure applied to a lower portion of the crane from information on the weights of the designated crane and a conveyed object and displaying the ground pressure. Support system for operation planning of mobile cranes.
【請求項5】前記シミュレーション手段は、前記作業状
況のもとでクレーンの運転方法を指定したときに該運転
下でのクレーンの稼働する軌跡を求めてこれを表示する
機能を有したことを特徴とする請求項1記載の移動式ク
レーンの稼働計画作成支援装置。
5. The simulation means has a function of, when a method of operating a crane is specified under the working condition, obtaining a trajectory of a crane operating under the operation and displaying the trajectory. The operation plan creation support device for a mobile crane according to claim 1.
【請求項6】前記シミュレーション手段は、前記作業状
況のもとで運搬すべき機材の荷重とクレーンに関する情
報とからクレーンの稼働可能な作業半径を求めてこれを
表示する機能を有したことを特徴とする請求項1記載の
移動式クレーンの稼働計画作成支援装置。
6. The simulation means has a function of obtaining an operable work radius of the crane from the load of the equipment to be transported under the working condition and information about the crane and displaying the radius. The operation plan creation support device for a mobile crane according to claim 1.
【請求項7】前記シミュレーション手段は、前記作業状
況のもとで、クレーンの吊り込み時間、クレーンの稼働
エリア、クレーンの走行距離及び旋回もしくターン回数
を最小とするような運転方法を定めて該運転方法にもと
づく動作をシミュレートする機能を有したことを特徴と
する請求項1記載の移動式クレーンの稼働計画作成支援
装置。
7. The simulation means defines an operating method for minimizing the number of times the crane is hoisted, the operating area of the crane, the traveling distance of the crane, and the number of turns or turns under the working conditions. The operation planning preparation support device for a mobile crane according to claim 1, further comprising a function of simulating an operation based on the operating method.
JP2147211A 1990-06-07 1990-06-07 Mobile crane operation plan creation support device Expired - Lifetime JP2516272B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2147211A JP2516272B2 (en) 1990-06-07 1990-06-07 Mobile crane operation plan creation support device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2147211A JP2516272B2 (en) 1990-06-07 1990-06-07 Mobile crane operation plan creation support device

Publications (2)

Publication Number Publication Date
JPH0441390A JPH0441390A (en) 1992-02-12
JP2516272B2 true JP2516272B2 (en) 1996-07-24

Family

ID=15425083

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2147211A Expired - Lifetime JP2516272B2 (en) 1990-06-07 1990-06-07 Mobile crane operation plan creation support device

Country Status (1)

Country Link
JP (1) JP2516272B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180122236A (en) * 2017-05-02 2018-11-12 현대중공업 주식회사 An evaluation system for floating crane
JP2021042045A (en) * 2019-09-11 2021-03-18 コベルコ建機株式会社 Simulation device

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102616659B (en) * 2012-03-27 2014-09-10 三一汽车起重机械有限公司 Off-running method for crane and system
JP2015101414A (en) * 2013-11-21 2015-06-04 株式会社タダノ Mass display system of suspended load
US10636308B2 (en) * 2016-05-18 2020-04-28 The Boeing Company Systems and methods for collision avoidance
CN113620191A (en) * 2020-05-09 2021-11-09 徐州重型机械有限公司 Crane operation protection method, device and system and crane
JP7464094B1 (en) * 2022-09-30 2024-04-09 コベルコ建機株式会社 Construction planning support device and program

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180122236A (en) * 2017-05-02 2018-11-12 현대중공업 주식회사 An evaluation system for floating crane
KR102214273B1 (en) * 2017-05-02 2021-02-08 현대중공업 주식회사 An evaluation system for floating crane
JP2021042045A (en) * 2019-09-11 2021-03-18 コベルコ建機株式会社 Simulation device
WO2021049112A1 (en) * 2019-09-11 2021-03-18 コベルコ建機株式会社 Simulator
JP7184001B2 (en) 2019-09-11 2022-12-06 コベルコ建機株式会社 simulation device

Also Published As

Publication number Publication date
JPH0441390A (en) 1992-02-12

Similar Documents

Publication Publication Date Title
CN109074536B (en) Method and device for planning and/or controlling and/or simulating the operation of a construction machine
KR101595243B1 (en) Automatic modeling system for facility in field based building information modeling and method thereof
Liu et al. Real-time optimization of precast concrete component transportation and storage
JP7184001B2 (en) simulation device
JP4672028B2 (en) Work simulation system for plant construction
WO2013006625A2 (en) Crane maneuvering assistance
JP2516272B2 (en) Mobile crane operation plan creation support device
JP3337207B2 (en) Construction system support system
Zhang et al. A computer‐based model for optimizing the location of a single tower crane: Authors claim 20–40% of hook horizontal travelling time can be saved if located at the position recommended by the model
Wang et al. Integrating building information modelling and firefly algorithm to optimize tower crane layout
Han et al. Simulation of mobile crane operations in 3D space
EP4197956A1 (en) Information acquisition system
Osipov Chernenko, kv information Model of the process of Lifting Long-Span roof
JP2000048061A (en) Method for aiding design of temporary scaffold, system for realizing the method and recording medium recording program
Tommelein Materials handling and site layout control
CN109534184A (en) Cold rolling acid tandem rolling mill memorial archway hanging method based on BIM technology
JP2000247574A (en) Crane operating data origination system and crane operation control system
JP2001142926A (en) Yard planning support system for plant construction
Lin et al. An algorithm for optimizing the location and type selection of attached tower cranes based on value engineering
CN113938501A (en) Self-organizing internet-of-things communication system and method for intelligent tower crane cluster cooperation
Hosseini et al. A mathematical model for optimal tower crane layout planning
Ueno et al. Construction robots for site automation
JP7365738B1 (en) Crane operation simulation system and crane operation simulation method
JPS63147797A (en) Positioning control method of crane
WO2024070486A1 (en) Construction planning assistance device and program

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080430

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090430

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090430

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100430

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110430

Year of fee payment: 15

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110430

Year of fee payment: 15