Wire dodge tool

Info

Publication number
JP2513913Y2
JP2513913Y2 JP1990025385U JP2538590U JP2513913Y2 JP 2513913 Y2 JP2513913 Y2 JP 2513913Y2 JP 1990025385 U JP1990025385 U JP 1990025385U JP 2538590 U JP2538590 U JP 2538590U JP 2513913 Y2 JP2513913 Y2 JP 2513913Y2
Authority
JP
Japan
Prior art keywords
wire
opening
frame
vertical frame
overhead wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1990025385U
Other languages
Japanese (ja)
Other versions
JPH03117313U (en
Inventor
拓 西森
義純 西岡
Original Assignee
朝日金属精工株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 朝日金属精工株式会社 filed Critical 朝日金属精工株式会社
Priority to JP1990025385U priority Critical patent/JP2513913Y2/en
Publication of JPH03117313U publication Critical patent/JPH03117313U/ja
Application granted granted Critical
Publication of JP2513913Y2 publication Critical patent/JP2513913Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Emergency Lowering Means (AREA)
  • Electric Cable Installation (AREA)

Description

【考案の詳細な説明】 (産業上の利用分野) 本考案は、例えば架空配電線、架空通信線等の架空線
の架設において、既設の架空線を乗り越えて、新設する
架空線用ロープを架設するのに用いる線かわし用工具に
関するものである。
[Detailed Description of the Invention] (Industrial field of application) The present invention, for example, in erection of overhead lines such as overhead distribution lines and overhead communication lines, overcomes existing overhead lines and constructs a new overhead line rope. The present invention relates to a wire dodging tool used for cutting.

(従来の技術及び解決しようとする課題) 架空配電線、架空通信線を架設する場合、既設の架空
線の上を乗り越えて架設する必要がある時がある。この
ような場合、まずロープを既設架空線の上を乗り越えて
架設しておき、このロープの一端に新たに架設する架空
線の端部を接続して架設する。
(Prior Art and Problems to be Solved) When installing an overhead distribution line or an overhead communication line, it may be necessary to climb over an existing overhead line to install it. In such a case, first, the rope is laid over the existing overhead wire and installed, and the end of the new overhead wire is connected to one end of the rope.

このような既設架空線の上を乗り越えるためのいわゆ
る線かわし作業は、従来は作業員が梯子を既設架空線に
立掛け、梯子を昇ってロープを既設架空線の上を越させ
るか、あるいは作業員がロープを束状にして地上よりロ
ープ束を上へ投げて既設架空線の上を越させるようにし
ていた。
In the past, so-called wire shunting work for overcoming the existing overhead wire is performed by a worker standing a ladder on the existing overhead wire and climbing the ladder to pass the rope over the existing overhead wire. A member made the rope into a bundle and threw the rope bundle from the ground so that the rope could be passed over the existing overhead wire.

しかし、近時道路事情が交通渋滞を招き、又作業員や
通行者の安全確保等従来方法では、いくたの問題が存在
する。
However, recent road conditions cause traffic congestion, and there are some problems with the conventional methods such as ensuring the safety of workers and passers-by.

(課題を解決するための手段) 本考案は上述の問題点を解消した線かわし用工具を提
供するもので、その特徴は、一方の垂直フレームの中央
部に開口部を有するコの字状の本体フレームと、該フレ
ームの下部に一体に設けた操作桿連結部、及び上部隅に
ロープ取付け孔を有し、ガイド溝を開口部側垂直フレー
ムに係合することによって、該垂直フレーム上を既設架
空線に押されて上方へ移動し、自重により下方へ移動す
るスライド金物を備えており、該スライド金物はその長
さが上記垂直フレームの開口部長さより長く、かつ上記
垂直フレーム上を上方又は下方に移動したとき上記開口
部は既設架空線が通過できる開口代を有している線かわ
し用工具にある。
(Means for Solving the Problems) The present invention provides a wire dodging tool that solves the above-mentioned problems, and is characterized by a U-shaped tool having an opening at the center of one vertical frame. The main body frame, the operating rod connecting portion integrally provided in the lower portion of the frame, and the rope attaching hole in the upper corner are provided, and the guide groove is engaged with the opening side vertical frame, so that the vertical frame is already installed. It is equipped with a slide metal object which is pushed by an overhead wire and moves upward, and moves downward by its own weight. The slide metal object has a length longer than the opening length of the vertical frame and moves upward or downward on the vertical frame. The opening is located in a wire dodging tool having an opening allowance for passing an existing overhead wire when it is moved to.

(実施例) 第1図(イ)は本考案の線かわし用工具の具体例の斜
視図、同図(ロ)は本体フレームの正面図である。
(Embodiment) FIG. 1 (a) is a perspective view of a concrete example of the wire shaving tool of the present invention, and FIG. 1 (b) is a front view of a main body frame.

図面において、(1)は本体フレームで、一方の垂直
フレームの中央部に開口部(11)を有し、全体としてコ
の字状の形状をなしている。上記本体フレーム(1)の
下部には操作桿(4)を挿入する操作桿連結部(3)が
固着されており、本体フレーム(1)と一体をなしてい
る。(2)はスライド金物で、ガイド溝(22)を開口部
(11)側の垂直フレームに係合することによって、該フ
レーム上を既設架空線に押されて上方へ移動し、自重に
より下方向に移動するように構成されている。上記スラ
イド金物(2)の縦方向の長さ(L)は本体フレーム
(1)の開口部(11)の長さ(l)より長く、これによ
り、スライド金物(2)は開口部(11)から脱落するこ
となく、フレーム上を移動することが可能であり、かつ
スライド金物(2)がフレーム上を上方又は下方に移動
したとき、上記開口部(11)は既設架空線が通過できる
開口代を有している。スライド金物(2)の上部の隅に
はロープ取付け孔(21)があり、又下部には下前方へ突
出したガイド板(23)が設けられている。
In the drawings, (1) is a main body frame, which has an opening (11) at the center of one vertical frame and has a U-shape as a whole. An operation rod connecting portion (3) into which the operation rod (4) is inserted is fixed to the lower portion of the main body frame (1) and is integral with the main body frame (1). (2) is a slide metal fitting, and by engaging the guide groove (22) with a vertical frame on the opening (11) side, the frame is pushed upward by the existing overhead wire and moves downward by its own weight. Is configured to move to. The vertical length (L) of the slide hardware (2) is longer than the length (l) of the opening (11) of the main body frame (1), whereby the slide hardware (2) has the opening (11). It is possible to move on the frame without dropping from the frame, and when the slide hardware (2) moves up or down on the frame, the opening (11) is an opening allowance through which the existing overhead wire can pass. have. A rope mounting hole (21) is provided at the upper corner of the slide hardware (2), and a guide plate (23) projecting downward and forward is provided at the lower portion.

(作用) 次に上述した線かわし用工具を用いての線かわし作業
を第2図〜第5図に基づいて説明する。
(Operation) Next, the wire passing operation using the wire cutting tool described above will be described with reference to FIGS. 2 to 5.

本体フレーム(1)の下部の操作桿連結部(3)に操
作桿(4)を連結すると共に、スライド金物(2)に設
けたロープ取付け孔(21)に、既設の架空線(6)の上
を越えて新たに架空線を架線するためのロープ(5)の
一端を連結する。
The operation rod (4) is connected to the operation rod connection portion (3) at the bottom of the main body frame (1), and the existing overhead wire (6) is connected to the rope attachment hole (21) provided in the slide hardware (2). One end of the rope (5) for connecting a new overhead wire over the top is connected.

この状態において操作桿(4)を伸ばして本体フレー
ム(1)を持ち上げ、第2図に示すように、既設架空線
(6)の上部よりガイド板(23)に沿ってスライド金物
(2)の下端へ既設架空線(6)が位置するように、工
具を降下させる。スライド金物(2)の下端に既設架空
線(6)が当った状態で、なお操作桿(4)を下方へ降
ろすと、第3図に示すように、スライド金物(2)は既
設架空線(6)に押されて上方へ移動する。ここで、操
作桿(4)の下端で作業員が工具を移動することによ
り、既設架空線(6)はスライド金物(2)の下部に設
けた下前方へ突出したガイド板(23)に案内されて、開
口部(11)から本体フレーム(1)内に入り込む。
In this state, the operation rod (4) is extended to lift the main body frame (1), and as shown in FIG. 2, slide the metal fitting (2) from the upper part of the existing overhead wire (6) along the guide plate (23). The tool is lowered so that the existing overhead wire (6) is located at the lower end. When the operating rod (4) is still lowered with the existing overhead wire (6) hitting the lower end of the slide hardware (2), as shown in FIG. It is pushed by 6) and moves upward. Here, when the operator moves the tool at the lower end of the operation rod (4), the existing overhead wire (6) is guided to the guide plate (23) provided at the lower part of the slide metal fitting (2) and protruding downward. Then, it enters the main body frame (1) through the opening (11).

これと同時に、スライド金物(2)は、第4図に示す
ように、その自重により垂直フレームを滑ってその下端
まで落下する。これによりロープ(5)は既設架空線
(6)を越えて位置することになり、最後は第5図に示
すように、本体フレーム(1)の開口部(11)より既設
架空線(6)を逃がし、工具とロープ(5)を回収す
る。その時、ロープ(5)は既設架空線(6)を越えて
回収される。
At the same time, as shown in FIG. 4, the slide hardware (2) slides on the vertical frame due to its own weight and falls to the lower end thereof. As a result, the rope (5) is located beyond the existing overhead wire (6), and finally, as shown in FIG. 5, the rope (5) is opened through the opening (11) of the main body frame (1) to the existing overhead wire (6). Escape and collect the tool and rope (5). At that time, the rope (5) is recovered over the existing overhead wire (6).

かくて、ロープ(5)の終端に新たに架設する架空線
を接続して架設することにより、既設の架空線(6)の
上を越えて新たな架空線が架設される。
Thus, a new overhead wire is installed over the existing overhead wire (6) by connecting and installing a new overhead wire at the end of the rope (5).

(考案の効果) 以上説明したように、本考案の線かわし用工具によれ
ば、地上からの操作により容易に線かわし作業を実施す
ることが可能となり、作業者や通行者の安全が確保され
る。
(Effects of the Invention) As described above, the tool for wire shunting according to the present invention makes it possible to easily perform a wire shunting operation from the ground, ensuring the safety of workers and passers-by. It

【図面の簡単な説明】[Brief description of drawings]

第1図(イ)は本考案に係る線かわし用工具の具体例の
斜視図、同図(ロ)は本体フレームの正面図である。 第2図〜第5図は本考案の線かわし用工具による線かわ
し作業の手順の説明図である。 1…本体フレーム、11…フレーム開口部、2…スライド
金物、21…ロープ取付け孔、22…ガイド溝、23…ガイド
板、3…操作桿連結部、4…操作桿、5…ロープ、6…
既設架空線。
FIG. 1 (a) is a perspective view of a concrete example of the wire shaving tool according to the present invention, and FIG. 1 (b) is a front view of a main body frame. FIG. 2 to FIG. 5 are explanatory views of the procedure for the wire shaving operation by the wire shaving tool of the present invention. DESCRIPTION OF SYMBOLS 1 ... Main body frame, 11 ... Frame opening part, 2 ... Sliding metal object, 21 ... Rope mounting hole, 22 ... Guide groove, 23 ... Guide plate, 3 ... Operation rod connection part, 4 ... Operation rod, 5 ... Rope, 6 ...
Existing overhead line.

Claims (1)

(57)【実用新案登録請求の範囲】(57) [Scope of utility model registration request] 【請求項1】一方の垂直フレームの中央部に開口部を有
するコの字状の本体フレームと、該本体フレームの下部
に一体に設けた操作桿連結部、及び上部隅にロープ取付
け孔を有し、ガイド溝を開口部側垂直フレームに係合す
ることによって、該垂直フレーム上を既設架空線に押さ
れて上方へ移動し、自重により下方へ移動するスライド
金物を備えており、該スライド金物はその長さが上記垂
直フレームの開口部長さより長く、かつ上記垂直フレー
ム上を上方又は下方へ移動したとき上記開口部は既設架
空線が通過できる開口代を有していることを特徴とする
線かわし用工具。
1. A vertical U-shaped main body frame having an opening at the center of one vertical frame, an operating rod connecting portion integrally provided at a lower portion of the main body frame, and a rope attaching hole at an upper corner. By engaging the guide groove with the vertical frame on the opening side, the slide frame is pushed by the existing overhead wire on the vertical frame to move upward, and is moved downward by its own weight. Is a wire whose length is longer than the opening length of the vertical frame and has an opening allowance through which an existing overhead wire can pass when moving upward or downward on the vertical frame. Dodge tool.
JP1990025385U 1990-03-13 1990-03-13 Wire dodge tool Expired - Lifetime JP2513913Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1990025385U JP2513913Y2 (en) 1990-03-13 1990-03-13 Wire dodge tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1990025385U JP2513913Y2 (en) 1990-03-13 1990-03-13 Wire dodge tool

Publications (2)

Publication Number Publication Date
JPH03117313U JPH03117313U (en) 1991-12-04
JP2513913Y2 true JP2513913Y2 (en) 1996-10-09

Family

ID=31528319

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1990025385U Expired - Lifetime JP2513913Y2 (en) 1990-03-13 1990-03-13 Wire dodge tool

Country Status (1)

Country Link
JP (1) JP2513913Y2 (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5338152Y2 (en) * 1974-01-28 1978-09-14
JPS5338152U (en) * 1976-09-03 1978-04-04

Also Published As

Publication number Publication date
JPH03117313U (en) 1991-12-04

Similar Documents

Publication Publication Date Title
US7717231B2 (en) Ladder guard
US4332054A (en) Block and tackle window sash balance and installation method
JP2513913Y2 (en) Wire dodge tool
RU2704372C1 (en) Method of preventing a person falling when climbing and lowering on a high-rise object (versions)
CN106014178A (en) Safe ladder bed for park maintenance
JP3707792B2 (en) Window stay
CN207771778U (en) A kind of multifunction insulating cat ladder tool box
CN210530723U (en) Supplementary device of climbing of electric power tower with safety protection and shutting function
JPH07158367A (en) Expansion ladder having fall prevention device, and safety apparatus
CN217693370U (en) Gateway device for intelligent data acquisition
CN211008407U (en) Auxiliary climbing device
JPH01249073A (en) Elevation safety rope
CN217175626U (en) Climbing frame
CN212897523U (en) Protective device for window side structure of climbing frame
JPH0513795Y2 (en)
CN219587264U (en) Anti-falling protection structure for color steel roof
CN213144044U (en) Cement pole convenient to climbing
EP0080464B1 (en) Safety device for ladders
JP4106133B2 (en) Suspended scaffold assembly method and suspension scaffold fall prevention device and fall prevention tool used therefor
CN217500990U (en) Building is climbed and is hung straightness adjustment appurtenance that hangs down of frame guide rail
JP2576273Y2 (en) Parent rope anchor
CN213923875U (en) High altitude construction car with protection effect
CN216196422U (en) Construction frame
CN220886948U (en) Straight arm lifting equipment
JPH0649048Y2 (en) Communication cable protective cover installation tool

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees