JP2024082733A - Floor Band - Google Patents
Floor Band Download PDFInfo
- Publication number
- JP2024082733A JP2024082733A JP2022196788A JP2022196788A JP2024082733A JP 2024082733 A JP2024082733 A JP 2024082733A JP 2022196788 A JP2022196788 A JP 2022196788A JP 2022196788 A JP2022196788 A JP 2022196788A JP 2024082733 A JP2024082733 A JP 2024082733A
- Authority
- JP
- Japan
- Prior art keywords
- nut
- band
- support
- bridge
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000000758 substrate Substances 0.000 abstract description 3
- 230000002542 deteriorative effect Effects 0.000 abstract 1
- 238000009434 installation Methods 0.000 description 7
- 238000010276 construction Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000003754 machining Methods 0.000 description 1
- 239000011347 resin Substances 0.000 description 1
- 229920005989 resin Polymers 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Supports For Pipes And Cables (AREA)
- Connection Of Plates (AREA)
- Clamps And Clips (AREA)
Abstract
Description
本発明は、床面や壁面等の固定面に対して、パイプを一定の高さに支持固定する配管用フロアバンドに関する。 The present invention relates to a piping floor band that supports and fixes pipes at a fixed height to a fixed surface such as a floor or wall.
配管用フロアバンドの施工に際しては、先ず、床面等の固定面に基板を取付固定する。基板には工場出荷時から既に2本の支柱ボルトが立設し、支柱ボルトの各々には下ナットが適宜位置に螺合取付けされている。
次にパイプを抱持支持するための下ブリッジを支柱ボルトに挿通取付けした後、パイプをこの下ブリッジのバンド部上に載置して支持させる。パイプの配管高さ位置の調整は下ナットの螺合高さ位置を調整することにより行うことができる。
上ブリッジを支柱ボルトに挿通取付し、支柱ボルトの上端から上ナットを螺合し、この上ナットを緊締位置まで回動して緊締することにより、パイプは上下一対のブリッジのバンド部によって上下から抱持支持されることになる。
When installing a piping floor band, first the base plate is attached to a fixed surface such as a floor. Two support bolts are already installed on the base plate at the time of shipment from the factory, and lower nuts are screwed into each of the support bolts in appropriate positions.
Next, the lower bridge for supporting the pipe is inserted through the support bolt, and then the pipe is placed on the band of the lower bridge to support it. The pipe height can be adjusted by adjusting the screw-in height of the lower nut.
The upper bridge is inserted and attached to the support bolt, the upper nut is screwed onto the top end of the support bolt, and the upper nut is rotated to the tightening position and tightened, so that the pipe is supported from above and below by the band portions of the pair of upper and lower bridges.
上記の施工作業において、上ナットの支柱ボルトへの螺合はパイプを下ブリッジのバンド部上に載置させ、上ブリッジを支柱ボルトに挿通取付した後でなければならない。更に、上ナットの螺合は支柱ボルトの上端から螺合し、緊締位置まで回動させなければならず、施工現場に設置されるフロアバンドの数を考慮すると、この上ナットの螺合に相当時間を取られるため作業効率が低いものとなっている。 In the above construction work, the upper nut must be screwed onto the support bolt after the pipe has been placed on the band part of the lower bridge and the upper bridge has been inserted and attached to the support bolt. Furthermore, the upper nut must be screwed into the top end of the support bolt and then rotated to the tightening position. Considering the number of floor bands to be installed at the construction site, screwing in this upper nut takes a considerable amount of time, resulting in low work efficiency.
特許文献1~5には、上ブリッジの一方の取付部に設けられている支柱ボルト挿通用のボルト孔を配管方向に開放部を有する切込溝とすることによって、2本の支柱ボルトの両方に上ナットを予め螺合したままの状態でも配管作業を行うことができる技術が記載されている。
即ち、これらの技術では、パイプを下ブリッジに支持させた後、上ブリッジをセットしてから上ナットを螺合させて緊締するそれまでのものとは異なり、上ナットについても予め支柱ボルトに螺合させておくことができるため、現場で上ナットを落としたりすることなく作業を行うことができるという利点がある。
Patent documents 1 to 5 describe a technology in which the bolt holes for inserting the support bolts, which are provided in one mounting part of the upper bridge, are cut into grooves with an opening in the piping direction, so that piping work can be performed even when the upper nuts are already screwed onto both of the two support bolts.
In other words, unlike previous methods in which the pipe was supported by the lower bridge, the upper bridge was set, and then the upper nut was screwed on and tightened, with these techniques the upper nut can be screwed onto the support bolt in advance, which has the advantage that work can be carried out on site without dropping the upper nut.
しかし上記の特許文献1~5の技術では、取付部のボルト孔が切込溝であるため、ウォーターハンマー現象等によりナットが僅かに弛んだだけで切込溝の形成されている取付部が支柱ボルトから脱落してしまってパイプの保持ができなくなるという問題点を有している。ナットが弛まないように強く緊締し過ぎるとボルト孔の開放部が変形して拡張してしまうため、取付部の固定面積・強度が低下するという問題点を有している。 However, the technologies in Patent Documents 1 to 5 above have the problem that the bolt holes in the mounting part are cut grooves, and if the nut loosens even slightly due to the water hammer phenomenon or the like, the mounting part with the cut grooves will fall off the support bolt, making it impossible to hold the pipe. If the nut is tightened too much to prevent it from loosening, the open part of the bolt hole will deform and expand, resulting in a problem of reduced fixing area and strength of the mounting part.
そこで本発明の課題は、支柱ボルトに対する取付部の固定面積・強度を落とすことなく、作業効率が高い配管用フロアバンドを提供することにある。 The objective of the present invention is to provide a piping floor band that is highly efficient to use without compromising the fixing area and strength of the attachment part to the support bolt.
上記課題を解決する本発明は下記構成を有する。 The present invention, which solves the above problems, has the following configuration.
1.固定面に取りつけられる基板と、該基板に立設する2本の支柱ボルトと、パイプを抱持支持するバンド部と該バンド部の両端に支柱ボルトに挿通される透孔が形成された取付部とを有するブリッジと、前記支柱ボルトに螺合されて前記取付部を任意の高さ位置で下方から支持する下ナットと、前記支柱ボルトに挿通されて前記取付部を上方から押圧支持する上ナットと、を有して構成される配管用フロアバンドにおいて、
前記下ナットは、ナット本体部と、該ナット本体部の上面に立設すると共に外周に雄ネジが形成された雄ネジ柱部と、を有し、更に、雄ネジ柱部の上面からナット本体部の下面まで貫通する貫通孔が形成されると共に該貫通孔の内周面に前記支柱ボルトが挿通螺合する雌ネジが形成された構成であり、
前記上ナットは、雌ネジが前記下ナットの雄ネジ柱部の雄ネジに螺合する構成であり、
前記支柱ボルトの上端から挿通した上ナットは、該支柱ボルトの雄ネジ部分を通過し、前記下ナットの雄ネジ柱部の雄ネジに螺合し、この雄ネジ柱部に螺合された状態で緊締されることにより前記取付部を上方から押圧支持する構成であることを特徴とする配管用フロアバンド。
1. A floor band for piping, comprising a base plate attached to a fixed surface, two support bolts erected on the base plate, a bridge having a band portion for embracing and supporting a pipe and a mounting portion having holes formed at both ends of the band portion through which the support bolts are inserted, a lower nut screwed onto the support bolts to support the mounting portion from below at an arbitrary height position, and an upper nut inserted into the support bolts to press and support the mounting portion from above,
The lower nut has a nut body and a male threaded column part that is erected on the upper surface of the nut body and has a male thread formed on its outer periphery. Further, a through hole is formed that penetrates from the upper surface of the male threaded column part to the lower surface of the nut body, and a female thread is formed on the inner circumferential surface of the through hole, into which the support bolt is inserted and screwed.
The upper nut has a female thread that is screwed into the male thread of the male thread column of the lower nut,
This floor band for piping is characterized in that the upper nut inserted from the upper end of the support bolt passes through the male threaded portion of the support bolt and screws into the male threads of the male threaded column portion of the lower nut, and is tightened while screwed into this male threaded column portion to support the mounting portion from above.
2.前記下ナットが、ナット本体部と雄ネジ柱部とが一体構成であることを特徴とする上記1に記載の配管用フロアバンド。 2. The piping floor band described in item 1 above, characterized in that the lower nut has an integral structure of the nut body and male thread column.
3.前記ブリッジが上下一対から成り、下ブリッジのバンド部と上ブリッジのバンド部によってパイプを上下から抱持する構成であることを特徴とする上記1又は2に記載の配管用フロアバンド。 3. The floor band for piping described in 1 or 2 above, characterized in that the bridge consists of a pair of upper and lower bridges, and the pipe is held from above and below by the band portion of the lower bridge and the band portion of the upper bridge.
4.前記ブリッジのバンド部によってパイプの下方を支持すると共に、該ブリッジに両端が固定される帯状体を前記パイプの上方に架け渡して支持することにより、前記パイプを上下から抱持する構成であることを特徴とする上記1又は2に記載の配管用フロアバンド。 4. The floor band for piping described in 1 or 2 above is characterized in that the band portion of the bridge supports the lower part of the pipe, and a band-shaped body, both ends of which are fixed to the bridge, is supported above the pipe, thereby embracing the pipe from above and below.
請求項1に示す発明によれば、支柱ボルトに対する取付部の固定面積・強度を落とすことなく、作業効率が高い配管用フロアバンドを提供することができる。 According to the invention shown in claim 1, it is possible to provide a piping floor band that is highly efficient to work with, without compromising the fixing area and strength of the mounting part for the support bolt.
特に、上ナットの支柱ボルトへの螺合取付けは、上ナットと下ナットとから成る一般的な従来構成では、支柱ボルトの上端に螺合したナットを延々と回動させて緊締位置まで移動させる必要があるが、本発明によれば、上ナットは支柱ボルトの雄ネジ部分を通過し、下ナットの雄ネジ柱部の雄ネジに螺合し、この雄ネジ柱部に螺合された状態で緊締するだけでブリッジの取付部を上方から押圧支持することができる。従って、支柱ボルトが長い場合であっても上ナットを延々と回動させて移動させる必要がないので作業性が高い。 In particular, in the conventional configuration consisting of an upper nut and a lower nut, the screwing and attachment of the upper nut to the support bolt requires the nut screwed onto the upper end of the support bolt to be rotated endlessly and moved to the tightening position. However, according to the present invention, the upper nut passes through the male threaded portion of the support bolt and screws into the male threads of the male threaded column portion of the lower nut, and the bridge mounting portion can be supported by pressing from above simply by tightening it while screwed into this male threaded column portion. Therefore, even if the support bolt is long, there is no need to rotate and move the upper nut endlessly, making it easier to work with.
特にまた、パイプの配管高さを調整する際、上ナットと下ナットとから成る従来構成では、位置を下げる場合は先ず下ナットを回動させて任意の位置まで下げてから上ナットを下ナットと同じ分量だけ回動させて下げ、位置を上げる場合は先ず上ナットを回動させて任意の位置まで上げてから下ナットを上ナットと同じ分量だけ回動させて上げ、その後、いずれの場合においても上ナットと下ナットのいずれか一方又は両方の高さ位置を調整し緊締することにより位置調整を行うが、本発明によれば、位置を下げる場合も上げる場合も下ナットを回動させて任意の位置まで移動させるだけで該下ナットの雄ネジ柱部に螺合している上ナットも一緒に移動するので、上下のナットを別々に回動させて移動させる手間を省くことができる。従って、高さ調整時の作業性も高い。 In particular, when adjusting the piping height of a pipe, in the conventional configuration consisting of an upper nut and a lower nut, when lowering the position, the lower nut is first rotated to a desired position and then the upper nut is rotated the same amount as the lower nut to lower it, and when raising the position, the upper nut is first rotated to a desired position and then the lower nut is rotated the same amount as the upper nut to raise it, and in either case, the height position of either the upper nut or the lower nut or both are adjusted and tightened to adjust the position. However, according to the present invention, when lowering or raising the position, simply rotating the lower nut to the desired position also moves the upper nut that is screwed into the male threaded column of the lower nut, eliminating the need to rotate and move the upper and lower nuts separately. Therefore, the workability when adjusting the height is also high.
請求項2に示す発明によれば、一体構成により強く緊締してもナット本体部と雄ネジ柱部とが分離することなく緊締状態を安定して維持することができる。 According to the invention shown in claim 2, the integrated structure allows the nut body and the male threaded column to be stably maintained in a tightened state without separation even when tightened strongly.
請求項3に示す発明によれば、上下一対のブリッジから成る配管支持バンドを用いたフロアバンドに適用することができる。 The invention shown in claim 3 can be applied to a floor band using a piping support band consisting of a pair of upper and lower bridges.
請求項4に示す発明によれば、パイプを下ブリッジにより下方から支持し、パイプの上方からの支持は結束バンドや金属製又は樹脂製のホースバンドにより抱持支持するフロアバンドに適用することができる。 According to the invention shown in claim 4, the pipe is supported from below by a lower bridge, and the pipe is supported from above by a floor band that embraces and supports the pipe with cable ties or metal or plastic hose bands.
次に、本発明の詳細について図1~図12に示す実施例に基づき説明する。 Next, the details of the present invention will be described based on the embodiment shown in Figures 1 to 12.
本発明に係る配管用フロアバンド(以下、単にフロアバンドと言うこともある。)1は、
床面やスラブ面等の固定面(図示せず)に取りつけられる基板2と、該基板2に立設する2本の支柱ボルト3と、パイプPを抱持支持するバンド部41と該バンド部41の両端に支柱ボルト3に挿通される透孔42Aが形成された取付部42とを有する上下一対のブリッジ4と、前記支柱ボルト3に螺合されて前記取付部42を任意の高さ位置で下方から支持する下ナット5と、前記支柱ボルト3に挿通されて前記取付部を上方から押圧支持する上ナット6と、を有する構成において、
前記下ナット5は、図2及び図4に示すように、ナット本体部51と、該ナット本体部51の上面に立設すると共に外周に雄ネジ52Aが形成された雄ネジ柱部52と、を有し、更に、雄ネジ柱部52の上面からナット本体部51の下面まで貫通する貫通孔53が形成されると共に該貫通孔53の内周面に前記支柱ボルト3が挿通螺合する雌ネジ53Aが形成された構成であり、
前記上ナット6は、図3及び図4に示すように、雌ネジ61が前記下ナット5の雄ネジ柱部52の雄ネジ52Aに螺合する構成であり、
前記支柱ボルト3の上端から挿通した上ナット6は、該支柱ボルト3の雄ネジ部分を通過し、図9及び図10に示すように前記下ナット5の雄ネジ柱部52の雄ネジ52Aに螺合し、この雄ネジ柱部52に螺合された状態で図1並びに図11及び図12に示すように緊締されることにより前記取付部42を上方から押圧支持する構成であることを主構成とするものである。
The piping floor band (hereinafter, simply referred to as the floor band) 1 according to the present invention is
A structure having a base plate 2 to be attached to a fixed surface (not shown) such as a floor surface or a slab surface, two support bolts 3 erected on the base plate 2, a pair of upper and lower bridges 4 each having a band portion 41 for embracing and supporting a pipe P and a mounting portion 42 having a through hole 42A formed at both ends of the band portion 41 for inserting the support bolt 3, a lower nut 5 screwed onto the support bolt 3 to support the mounting portion 42 from below at an arbitrary height position, and an upper nut 6 inserted into the support bolt 3 to press and support the mounting portion from above,
As shown in Figs. 2 and 4, the lower nut 5 has a nut body 51, and a male threaded column 52 that is erected on the upper surface of the nut body 51 and has a male thread 52A formed on its outer periphery. Furthermore, a through hole 53 is formed that penetrates from the upper surface of the male threaded column 52 to the lower surface of the nut body 51, and a female thread 53A into which the support bolt 3 is inserted and screwed is formed on the inner circumferential surface of the through hole 53.
As shown in FIGS. 3 and 4, the upper nut 6 has a configuration in which a female thread 61 is screwed into the male thread 52A of the male thread column portion 52 of the lower nut 5.
The upper nut 6 inserted from the upper end of the support bolt 3 passes through the male thread portion of the support bolt 3 and screws into the male threads 52A of the male thread column portion 52 of the lower nut 5 as shown in Figures 9 and 10. In the screwed state into this male thread column portion 52, the upper nut 6 is tightened as shown in Figures 1, 11 and 12, thereby pressing and supporting the mounting portion 42 from above.
図中において、符号21は基板2の上面に取付固定された固定ナットであり、支柱ボルト3はこの固定ナット21に螺合取付けすることによって基板2に立設状態で固定することができる。 In the figure, the reference numeral 21 denotes a fixing nut attached and fixed to the top surface of the substrate 2, and the support bolt 3 can be fixed in an upright position to the substrate 2 by screwing it into the fixing nut 21.
本実施例では、ブリッジ4は上下一対から成り、下ブリッジ4のバンド部41と上ブリッジ4のバンド部41によってパイプPを上下から抱持する構成となっている。また、下ナット5は下ブリッジ4の取付部42を下方から支持し、上ナット6は上ブリッジの取付部42を上方から押圧支持する。 In this embodiment, the bridge 4 is made up of a pair of upper and lower bridges 4, and the band portion 41 of the lower bridge 4 and the band portion 41 of the upper bridge 4 embrace the pipe P from above and below. In addition, the lower nut 5 supports the mounting portion 42 of the lower bridge 4 from below, and the upper nut 6 presses and supports the mounting portion 42 of the upper bridge from above.
また、本実施例では、下ナット5はナット本体部51と雄ネジ柱部52とを一部材から削り出し加工等して一体的に形成した一体構成としているが、別体で形成したものを組合せた構成であってもよい。 In addition, in this embodiment, the lower nut 5 has an integrated structure in which the nut body 51 and the male threaded column 52 are integrally formed by machining or the like from a single member, but it may also be a structure in which separate pieces are combined.
次に、上記構成を有する本発明のフロアバンド1の施工手順の一例について説明する。 Next, an example of the installation procedure for the floor band 1 of the present invention having the above configuration will be described.
先ず、図5に示すように、基板2を床面やスラブ面等の固定面(図示せず)に固定する。該基板2には既に2本の支柱ボルト3が立設しており、支柱ボルト3の各々には下ナット5が螺合取付けされている。この立設する支柱ボルト3に、上下一対のブリッジ4の内、下ブリッジ4を取り付ける。尚、上下一対のブリッジ4の各々の取付部42に設けられている透孔42Aは、その直径が下ナット5の雄ネジ柱部52を挿通可能な大きさとなっている。 First, as shown in FIG. 5, the base plate 2 is fixed to a fixing surface (not shown) such as a floor surface or a slab surface. Two support bolts 3 are already installed on the base plate 2, and a lower nut 5 is screwed onto each of the support bolts 3. Of the pair of upper and lower bridges 4, the lower bridge 4 is attached to the installed support bolts 3. The through hole 42A provided in each mounting portion 42 of the pair of upper and lower bridges 4 has a diameter large enough to insert the male threaded column portion 52 of the lower nut 5.
次に、図6に示すように、下ブリッジ4のバンド部41上にパイプPを載置する。 Next, as shown in Figure 6, the pipe P is placed on the band portion 41 of the lower bridge 4.
次に、図7に示すように、支柱ボルト3に上ブリッジ4を取り付ける。この取付けによってパイプPは上下一対のブリッジ4によって上下から抱持支持される。 Next, as shown in FIG. 7, the upper bridge 4 is attached to the support bolt 3. With this attachment, the pipe P is supported from above and below by the pair of upper and lower bridges 4.
次に、図8から図9及び図10に示すように、上ナット6を支柱ボルト3の上端から挿通する。この際、上ナット6は支柱ボルト3の雄ネジ部分には螺合することなく通過し、下ナット5の雄ネジ柱部52の雄ネジ52Aに螺合する。 Next, as shown in Figures 8 to 9 and 10, the upper nut 6 is inserted from the upper end of the support bolt 3. At this time, the upper nut 6 passes through the male threaded portion of the support bolt 3 without being screwed into it, and is screwed into the male threads 52A of the male threaded column portion 52 of the lower nut 5.
次に、上ナット6を雄ネジ柱部52に螺合された状態で緊締することによって、図1並びに図11及び図12に示すように、下ナット5のナット本体部51が下ブリッジ4の取付部42を下方から支持すると共に、上ナット6が上ブリッジ4の取付部42を上方から押圧支持することによってパイプPが安定した状態で上下のバンド部41によって抱持支持されることになる。 Next, by tightening the upper nut 6 while it is screwed into the male threaded column portion 52, as shown in Figures 1, 11 and 12, the nut body portion 51 of the lower nut 5 supports the mounting portion 42 of the lower bridge 4 from below, and the upper nut 6 presses and supports the mounting portion 42 of the upper bridge 4 from above, so that the pipe P is embraced and supported by the upper and lower band portions 41 in a stable state.
上記したように、上ナット6の支柱ボルト3への螺合取付けは、上ナット6は支柱ボルト3の雄ネジ部分を通過し、下ナット5の雄ネジ柱部52の雄ネジ52Aに螺合し、この雄ネジ柱部52に螺合された状態で緊締するだけで上ブリッジ4の取付部42を上方から押圧支持することができる。従って、支柱ボルト3が長い場合であっても従来の一般的なナット構成のように上側に螺合するナットを延々と回動させて移動させる必要がないため、作業性が高い。 As described above, the upper nut 6 is screwed onto the support bolt 3 by passing through the male threads of the support bolt 3 and screwing into the male threads 52A of the male threaded column portion 52 of the lower nut 5, and simply tightening the nut while screwed into the male threaded column portion 52 to support the mounting portion 42 of the upper bridge 4 from above. Therefore, even if the support bolt 3 is long, there is no need to endlessly rotate and move the nut screwed onto the upper side as with conventional general nut configurations, which makes it easy to work with.
尚、パイプPの支持高さの調整は、上ナット6を緊締する前の状態、即ち、図9及び図10に示す状態で行う。本発明によれば、支持高さの位置を下げる場合も上げる場合も、下ナット5を回動させて任意の位置まで移動させるだけで該下ナット5の雄ネジ柱部52に螺合している上ナットも5一緒に移動するので、上下のナットを別々に回動させて移動させる手間を省くことができる。従って、高さ調整時の作業性も高い。 The support height of the pipe P is adjusted before the upper nut 6 is tightened, i.e., in the state shown in Figures 9 and 10. According to the present invention, whether the support height is to be lowered or raised, the upper nut 5 that is screwed into the male threaded column portion 52 of the lower nut 5 is moved together with the lower nut 5 simply by rotating the lower nut 5 to the desired position, eliminating the need to rotate and move the upper and lower nuts separately. This makes height adjustment easy to do.
以上、本発明に係る配管用フロアバンドの実施例について図1~図12に基づき説明したが、本発明は上記実施例に限定されず本発明の範囲内において他の態様を採ることもできる。 The above describes an embodiment of the piping floor band according to the present invention based on Figures 1 to 12, but the present invention is not limited to the above embodiment and other aspects may be adopted within the scope of the present invention.
例えば、バンド部41及び取付部42を有するブリッジ4は上記実施例の上下一対の構成に限らず、パイプPの下方側のみブリッジ4によって支持し、上方側は結束バンドや金属製又は樹脂製のホースバンドにより抱持支持する構成であってもよい。 For example, the bridge 4 having the band portion 41 and the mounting portion 42 is not limited to the upper and lower pair configuration of the above embodiment, but may be configured so that only the lower side of the pipe P is supported by the bridge 4, and the upper side is supported and embraced by a cable tie or a metal or resin hose band.
図13及び図14に示す態様は、下ブリッジ4の下向きに円弧するバンド部41の中央部に凹状部が形成されており、この凹状部の両端と左右の円弧部分との接点である2箇所の角部のみでパイプPを下方から2点支持すると共に、結束バンドから成る帯状体7をバンド部41に形成された被固定用スリット41Aを通して下ブリッジ4上に支持されるパイプPの上方に架け渡して抱持支持する構成である。
かかる構成によれば、パイプPは前記下2箇所の角部の2点で下方から支持されるため、ブリッジ4のバンド部41の円弧形状とパイプPの外径形状とが不一致形状であってもバンド部41の中央部分に固定した状態での配管支持が可能となる。従って、抱持支持するパイプPの直径に応じたバンド部41を有するブリッジ4を様々な直径のパイプPの支持が可能となる。
In the embodiment shown in Figures 13 and 14, a concave portion is formed in the center of the downwardly arcing band portion 41 of the lower bridge 4, and the pipe P is supported at two points from below only at two corners which are the contact points between both ends of this concave portion and the left and right arc portions, and a strip-shaped body 7 made of a cable tie is passed through a fixing slit 41A formed in the band portion 41 to span above the pipe P supported on the lower bridge 4 and support it.
According to this configuration, the pipe P is supported from below at two points at the two lower corners, so even if the arc shape of the band part 41 of the bridge 4 does not match the outer diameter shape of the pipe P, the pipe can be supported while being fixed to the center part of the band part 41. Therefore, the bridge 4 having the band part 41 according to the diameter of the pipe P to be embraced and supported can support pipes P of various diameters.
1 配管用フロアバンド
2 基板
21 固定ナット
3 支柱ボルト
4 ブリッジ
41 バンド部
41A 被固定用スリット
42 取付部
42A 透孔
5 下ナット
51 ナット本体部
52 雄ネジ柱部
52A 雄ネジ
53 貫通孔
53A 雌ネジ
6 上ナット
61 雌ネジ
7 帯状体
P パイプ
Reference Signs List 1 Piping floor band 2 Base plate 21 Fixing nut 3 Support bolt 4 Bridge 41 Band portion 41A Fixing slit 42 Mounting portion 42A Through hole 5 Lower nut 51 Nut body portion 52 Male threaded column portion 52A Male thread 53 Through hole 53A Female thread 6 Upper nut 61 Female thread 7 Belt-shaped body P Pipe
Claims (4)
前記下ナットは、ナット本体部と、該ナット本体部の上面に立設すると共に外周に雄ネジが形成された雄ネジ柱部と、を有し、更に、雄ネジ柱部の上面からナット本体部の下面まで貫通する貫通孔が形成されると共に該貫通孔の内周面に前記支柱ボルトが挿通螺合する雌ネジが形成された構成であり、
前記上ナットは、雌ネジが前記下ナットの雄ネジ柱部の雄ネジに螺合する構成であり、
前記支柱ボルトの上端から挿通した上ナットは、該支柱ボルトの雄ネジ部分を通過し、前記下ナットの雄ネジ柱部の雄ネジに螺合し、この雄ネジ柱部に螺合された状態で緊締されることにより前記取付部を上方から押圧支持する構成であることを特徴とする配管用フロアバンド。 A floor band for piping comprising a base plate attached to a fixed surface, two support bolts erected on the base plate, a bridge having a band portion for embracing and supporting a pipe and a mounting portion having holes formed at both ends of the band portion through which the support bolts are inserted, a lower nut screwed onto the support bolts to support the mounting portion from below at an arbitrary height position, and an upper nut inserted into the support bolts to support the mounting portion from above by pressing the mounting portion,
The lower nut has a nut body and a male threaded column part that is erected on the upper surface of the nut body and has a male thread formed on its outer periphery. Further, a through hole is formed that penetrates from the upper surface of the male threaded column part to the lower surface of the nut body, and a female thread is formed on the inner circumferential surface of the through hole, into which the support bolt is inserted and screwed.
The upper nut has a female thread that is screwed into the male thread of the male thread column of the lower nut,
This floor band for piping is characterized in that the upper nut inserted from the upper end of the support bolt passes through the male threaded portion of the support bolt and screws into the male threads of the male threaded column portion of the lower nut, and is tightened while screwed into this male threaded column portion to support the mounting portion from above.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2022196788A JP2024082733A (en) | 2022-12-09 | 2022-12-09 | Floor Band |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2022196788A JP2024082733A (en) | 2022-12-09 | 2022-12-09 | Floor Band |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2024082733A true JP2024082733A (en) | 2024-06-20 |
Family
ID=91539095
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2022196788A Pending JP2024082733A (en) | 2022-12-09 | 2022-12-09 | Floor Band |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2024082733A (en) |
-
2022
- 2022-12-09 JP JP2022196788A patent/JP2024082733A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110965652B (en) | Assembled building primary and secondary roof beam steel connected node structure | |
US20050055945A1 (en) | Industrial hanger | |
US7967272B2 (en) | Industrial hangers for framing and method of fabricating the same | |
JP2009203648A (en) | Irrotational implement | |
JP2024082733A (en) | Floor Band | |
JP2009281477A (en) | Piping pipe supporting level band | |
JP2009161938A (en) | Screwing mechanism and temporary assembling metal fixture for construction using the same | |
JP2006207286A (en) | Spiral pile with centering function | |
KR200332599Y1 (en) | pole supporter of street light | |
KR100532718B1 (en) | Pipe fixture | |
CN211371481U (en) | Small-size pipeline bracket of nuclear power station | |
CN1781002A (en) | Pipe fixing system | |
KR20170127690A (en) | Scaffold clamp for multiple support | |
US20070062019A1 (en) | Assembly for joining structural components without welding | |
JP2007016970A (en) | Vertical installation assisting tool for bolt body | |
EP0290097B1 (en) | Support leg joint construction with bracing | |
JP6627118B2 (en) | Bathroom floor frame | |
CN209283857U (en) | A kind of connector of greenhouse beam and arch tube | |
CN219510303U (en) | Pipeline hanger | |
CN208535324U (en) | One kind can turnover type height-adjustable discharge water pipe support | |
JP2018179179A (en) | Rubber-based support block | |
JP2001081745A (en) | Post of moving fence | |
JP4004493B2 (en) | Tube support | |
KR100641715B1 (en) | fixing structure of sprinkler | |
KR20230028045A (en) | Connecting unit |