JP2024069959A - Transformer replacement method - Google Patents

Transformer replacement method Download PDF

Info

Publication number
JP2024069959A
JP2024069959A JP2022180278A JP2022180278A JP2024069959A JP 2024069959 A JP2024069959 A JP 2024069959A JP 2022180278 A JP2022180278 A JP 2022180278A JP 2022180278 A JP2022180278 A JP 2022180278A JP 2024069959 A JP2024069959 A JP 2024069959A
Authority
JP
Japan
Prior art keywords
transformer
replacement method
premises
installing
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2022180278A
Other languages
Japanese (ja)
Inventor
秀紀 粟井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chugoku Electric Power Co Inc
Original Assignee
Chugoku Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chugoku Electric Power Co Inc filed Critical Chugoku Electric Power Co Inc
Priority to JP2022180278A priority Critical patent/JP2024069959A/en
Publication of JP2024069959A publication Critical patent/JP2024069959A/en
Pending legal-status Critical Current

Links

Landscapes

  • Housings And Mounting Of Transformers (AREA)

Abstract

【課題】変電所等の構内に設置された変圧器を、短期間で取り替えることが可能な変圧器取替工法を提供する。【解決手段】変圧器引留鉄構が設置され、変圧器引留鉄構に隣接するように構内に設置された変圧器を取り替える変圧器取替工法は、構内の取替対象である第1の変圧器の近傍かつ変圧器引留鉄構の近傍であり、基礎工事がなされている空きスペースに、新たな第2の変圧器を設置するステップと、変圧器引留鉄構に対して第2の変圧器を設置するための所定の改造工事を行い、変圧器引留鉄構に配置されている主回路からのリード線を設置するための型取りを行うステップと、リード線の型取りに沿って、第2の変圧器に前記リード線を接続するステップと、主回路から第1の変圧器を切り離し、第1の変圧器を撤去するステップと、を含む。【選択図】図3[Problem] To provide a transformer replacement method that can replace a transformer installed in the premises of a substation or the like in a short period of time. [Solution] A transformer replacement method for replacing a transformer installed in the premises adjacent to a transformer retention steel structure includes the steps of: installing a new second transformer in an empty space in the vicinity of a first transformer to be replaced in the premises and in the vicinity of the transformer retention steel structure, where foundation work has been performed; performing a predetermined modification work on the transformer retention steel structure to install the second transformer, forming a shape for installing lead wires from a main circuit that is arranged in the transformer retention steel structure; connecting the lead wires to the second transformer according to the formed lead wires; and disconnecting the first transformer from the main circuit and removing the first transformer. [Selected Figure] Figure 3

Description

本発明は、変電所等の構内に設置された変圧器を取り替える変圧器取替工法に関する。 The present invention relates to a transformer replacement method for replacing a transformer installed within the premises of a substation or the like.

1次変電所等に設置されている変圧器は、交流電力を変圧する装置である。このような変圧器は、数メートル~数十メートル規模の大きさであり、通常、変電所等の構内施設に、基礎工事がなされてその上に設置されている。 Transformers installed in primary substations and other facilities are devices that transform AC power. Such transformers are several meters to several tens of meters in size, and are usually installed on foundations that have been laid within the premises of the substation or other facility.

変圧器は、故障時または経年等により取り替える必要がある場合、変圧器を取り替える工事のための期間を確保し、変圧器をその期間停止する必要がある。しかし、そのような停止期間の確保が困難な場合、構内の新たなスペースに基礎工事を行い、新たな変圧器を設置した上で、古い変圧器を撤去する工事を行う、というような運用をしている。 When a transformer needs to be replaced due to breakdowns or aging, a period of time must be secured for the work to replace the transformer and the transformer must be shut down for that period. However, when it is difficult to secure such a shutdown period, the usual procedure is to carry out foundation work in a new space within the premises, install a new transformer, and then carry out work to remove the old transformer.

このような設備に対して機器等の取替工事を行う技術として、新たな基礎を設置することなく機器(スイッチギア)の取替を可能にする工法が知られている(例えば、特許文献1参照。)。特許文献1に記載のスイッチギア取替工法は、基礎の余剰スペースに新設のスイッチギアの配変二次箱と所内GPTを設置して、既設のスイッチギアと並列に変圧器に接続し、既設のスイッチギアの配電線箱等を基礎から撤去し、新設のスイッチギアの配電線箱等を基礎に設置して変圧器に接続し、既設のスイッチギアの配変二次箱と所内GPT箱を基礎から撤去する、というものである。 As a technique for replacing equipment in such facilities, a construction method that enables equipment (switchgear) replacement without laying a new foundation is known (see, for example, Patent Document 1). The switchgear replacement method described in Patent Document 1 involves installing a secondary distribution box and in-house GPT of a new switchgear in the surplus space of the foundation, connecting it to a transformer in parallel with the existing switchgear, removing the distribution line box of the existing switchgear from the foundation, installing the distribution line box of the new switchgear on the foundation and connecting it to the transformer, and removing the secondary distribution box and in-house GPT box of the existing switchgear from the foundation.

特開2021-097482号公報JP 2021-097482 A

ところで、変圧器そのものを取り替える場合は、特許文献1に記載のスイッチギア取替工法を適用することはできず、短期間で変圧器を取り替えることが可能な工法が求められていた。 However, when replacing the transformer itself, the switchgear replacement method described in Patent Document 1 cannot be applied, and a method that allows the transformer to be replaced in a short period of time is required.

そこで本発明は、短期間で変圧器を取り替えることが可能な変圧器取替工法を提供することを目的とする。 The present invention aims to provide a transformer replacement method that allows for the replacement of transformers in a short period of time.

上記の課題を解決するために、請求項1の発明は、変圧器引留鉄構が設置され、前記変圧器引留鉄構に隣接するように構内に設置された変圧器を取り替える変圧器取替工法であって、前記構内の取替対象である第1の変圧器の近傍かつ前記変圧器引留鉄構の近傍であり、基礎工事がなされている空きスペースに、新たな第2の変圧器を設置するステップと、前記変圧器引留鉄構に対して前記第2の変圧器を設置するための所定の改造工事を行い、前記変圧器引留鉄構に配置されている主回路からのリード線を設置するための型取りを行うステップと、前記リード線の型取りに沿って、前記第2の変圧器に前記リード線を接続するステップと、前記主回路から前記第1の変圧器を切り離し、前記第1の変圧器を撤去するステップと、を含む工程を行うことを特徴とする変圧器取替工法である。 In order to solve the above problem, the invention of claim 1 is a transformer replacement method in which a transformer retention steel structure is installed and a transformer installed within the premises adjacent to the transformer retention steel structure is replaced, the transformer replacement method comprising the steps of: installing a new second transformer in an empty space in the premises adjacent to the first transformer to be replaced and adjacent to the transformer retention steel structure, where foundation work has been done; carrying out predetermined modification work for installing the second transformer on the transformer retention steel structure, making a mold for installing lead wires from the main circuit arranged on the transformer retention steel structure; connecting the lead wires to the second transformer according to the mold for the lead wires; and disconnecting the first transformer from the main circuit and removing the first transformer.

請求項2の発明は、請求項1に記載の変圧器取替工法における、前記第2の変圧器を設置するステップにおいて、前記第2の変圧器を、前記変圧器引留鉄構に隣接する前記第1の変圧器に対向するように、前記変圧器引留鉄構に隣接する位置に設置する、ことを特徴とする。 The invention of claim 2 is characterized in that in the step of installing the second transformer in the transformer replacement method described in claim 1, the second transformer is installed in a position adjacent to the transformer retaining steel structure so as to face the first transformer adjacent to the transformer retaining steel structure.

請求項3の発明は、請求項1に記載の変圧器取替工法における、前記変圧器引留鉄構に対して所定の改造工事を行うステップにおいて、前記変圧器引留鉄構に設置されている碍子を、前記第2の変圧器に対応するように変更する、ことを特徴とする。 The invention of claim 3 is characterized in that in the step of carrying out specified modification work on the transformer retaining steel structure in the transformer replacement method described in claim 1, the insulators installed on the transformer retaining steel structure are changed to correspond to the second transformer.

請求項4の発明は、請求項1から3のいずれか1項に記載の変圧器取替工法における、前記第2の変圧器を設置するステップの前工程において、前記第1の変圧器の2次側に基礎工事がなされて設置されている装置を移設し、前記空きスペースを確保するステップを行う、ことを特徴とする。 The invention of claim 4 is characterized in that, in the transformer replacement method described in any one of claims 1 to 3, in a process prior to the step of installing the second transformer, a step is carried out in which a device that has been installed on the secondary side of the first transformer and whose foundation has been laid is relocated to secure the free space.

請求項5の発明は、請求項4に記載の変圧器取替工法における、前記装置を移設するステップにおいて、前記装置は、前記構内に設置された分路リアクトル、中性点リアクトルのいずれかまたは両方を含む、ことを特徴とする。 The invention of claim 5 is characterized in that in the transformer replacement method described in claim 4, in the step of relocating the device, the device includes either or both of a shunt reactor and a neutral reactor installed within the premises.

請求項1に記載の発明によれば、取替対象である第1の変圧器の近傍かつ変圧器引留鉄構の近傍であり、基礎工事がなされている空きスペースに新たな第2の変圧器を設置し、変圧器引留鉄構に対して所定の改造工事を行い、主回路からのリード線を設置するための型取りを行い、第2の変圧器にリード線を接続し、第1の変圧器を撤去する。そのため、構内に既設の遮断器や断路器および母線鉄構等を流用することができる。これにより、短期間で変圧器を取り替えることが可能になる。 According to the invention described in claim 1, a new second transformer is installed in an empty space near the first transformer to be replaced and near the transformer retaining steel structure, where foundation work has been done, the specified modification work is carried out on the transformer retaining steel structure, a mold is made for installing lead wires from the main circuit, the lead wires are connected to the second transformer, and the first transformer is removed. This makes it possible to reuse the circuit breakers, disconnecting switches, busbar steel structure, etc. already installed on the premises. This makes it possible to replace the transformer in a short period of time.

請求項2に記載の発明によれば、第2の変圧器を、変圧器引留鉄構に隣接する第1の変圧器に対向するように、変圧器引留鉄構に隣接する位置に設置する。これにより、既設の変圧器の近傍で取替工事を行うことができるため、短期間で変圧器を取り替えることが可能になる。 According to the invention described in claim 2, the second transformer is installed adjacent to the transformer retaining steel structure so as to face the first transformer adjacent to the transformer retaining steel structure. This allows replacement work to be carried out near the existing transformer, making it possible to replace the transformer in a short period of time.

請求項3に記載の発明によれば、変圧器引留鉄構に設置されている碍子を、第2の変圧器に対応するように変更する。これにより、他の工程作業と並行して工事を行うことができるため、短期間で変圧器を取り替えることが可能になる。 According to the invention described in claim 3, the insulators installed on the transformer retaining steel structure are changed to accommodate the second transformer. This allows the work to be carried out in parallel with other process work, making it possible to replace the transformer in a short period of time.

請求項4及び5に記載の発明によれば、第1の変圧器の2次側に基礎工事がなされて設置されている装置、具体的には分路リアクトルまたは中性点リアクトルを移設し、空きスペースを確保する。そのため、構内に既設の遮断器や断路器および母線鉄構等を流用することができる。これにより、短期間で変圧器を取り替えることが可能になる。 According to the inventions described in claims 4 and 5, the equipment installed on the secondary side of the first transformer with foundation work done, specifically the shunt reactor or neutral point reactor, is relocated to secure free space. This makes it possible to reuse the circuit breakers, disconnectors, busbar ironwork, etc. already installed on the premises. This makes it possible to replace the transformer in a short period of time.

本発明の実施の形態1に係る変圧器取替工法を実施する対象となる変圧器10が設置された構内1の例を示す構内平面図である。1 is a plan view of a premises showing an example of a premises 1 in which a transformer 10 is installed, which is the subject of a transformer replacement method according to a first embodiment of the present invention. FIG. 図1の構内1を示す側面図である。FIG. 2 is a side view showing the premises 1 of FIG. 1. 本発明の実施の形態1に係る変圧器取替工法を示すフローチャートである。4 is a flowchart showing a transformer replacement method according to the first embodiment of the present invention. 図1に示す状態から、分路リアクトル40及び中性点リアクトル50が移設された状態を示す平面図である。2 is a plan view showing a state in which a shunt reactor 40 and a neutral point reactor 50 have been moved from the state shown in FIG. 1 . 図4に示す状態から、新たな変圧器60が設置された状態を示す平面図である。5 is a plan view showing a state in which a new transformer 60 has been installed, following the state shown in FIG. 4. FIG. 図4の構内1を示す側面図である。FIG. 5 is a side view showing the premises 1 of FIG. 4. 図5に示す状態から、変圧器10が撤去された状態を示す平面図である。6 is a plan view showing a state in which the transformer 10 has been removed from the state shown in FIG. 5. FIG. 図7の構内1を示す側面図である。FIG. 8 is a side view showing the premises 1 of FIG. 7.

以下、この発明を図示の実施の形態に基づいて説明する。 The present invention will be described below based on the illustrated embodiment.

(概要)
本発明の実施の形態に係る変圧器取替工法は、1次変電所等に設置されている変圧器を取り替えるための変圧器取替工法である。この変圧器取替工法は、変圧器の故障または経年等による取替の際、変圧器の長期停止が困難な場合であっても変圧器の連続停止期間を短期間にすることを可能にする工法である。
(overview)
The transformer replacement method according to the embodiment of the present invention is a transformer replacement method for replacing a transformer installed in a primary substation, etc. This transformer replacement method is a method that makes it possible to shorten the continuous shutdown period of a transformer even in cases where it is difficult to shut down the transformer for a long period of time when replacing the transformer due to its failure or aging.

図1は、本発明の実施の形態1に係る変圧器取替工法を実施する対象となる変圧器10が設置された構内1の例を示す構内平面図である。また、図2は、図1の構内1を示す側面図である。 Figure 1 is a plan view of a premises 1 showing an example of a premises in which a transformer 10 is installed, in which the transformer replacement method according to the first embodiment of the present invention is carried out. Also, Figure 2 is a side view showing the premises 1 of Figure 1.

図1に示す構内1は、例えば1次変電所のような施設の構内の抜粋を示す平面図である。構内1の例である変電所は、電力系統における電気の電圧の変換を行い、各電力系統の接続と開閉とを行って電力の流れを制御する1次変電所である。また、このような変電所は、発電所から送電されてきた電気の電圧を下げて、大きな工場等へ送電する。また、このような変電所は、2次変電所へ送られ、さらに電圧を下げて中小工場等へ送電するための設備である。 The premises 1 shown in FIG. 1 is a plan view showing an excerpt of the premises of a facility such as a primary substation. The substation, which is an example of the premises 1, is a primary substation that converts the voltage of electricity in a power system and controls the flow of power by connecting and opening and closing each power system. Such substations also reduce the voltage of electricity transmitted from power plants and transmit it to large factories, etc. Such substations are also facilities that send electricity to secondary substations, where the voltage is further reduced and transmitted to small and medium-sized factories, etc.

図1及び図2に示すように、構内1には、変圧器10と、変圧器引留鉄構20と、複数の高圧線(主回路)(図1では、高圧線31、高圧線32及び高圧線33を示している。以下、総称して「高圧線30」ということもある)と、分路リアクトル40と、中性点リアクトル50とが配置されている。変圧器10は、構内1の例である発電所から送電されてきた電圧を変圧(例えば、110,000Vから66,000Vへ)する施設である。変圧器引留鉄構20は、高圧線30を支持するためのゲート状の設備(図2ではタワー状に示されているが、奥行き方向に延びた形状になっている)であり、通常、数十メートル規模の鉄構構造物である。高圧線30は、変電所から出力された高圧電力(例えば、6,600Vの電力)を送電する送電線である。分路リアクトル(ShR)40は、交流回路の分路に接続され、高圧線30の遅れ無効電力を供給することで進み無効電力を補償する装置である。中性点リアクトル(NGL)50は、電力系統の中性点に接続され、電力系統の地絡事故の際に対地電圧が異常に上昇するのを防止すると共に、系統の対地静電容量を補償する装置である。 As shown in Figs. 1 and 2, the premises 1 includes a transformer 10, a transformer retaining steel structure 20, multiple high-voltage lines (main circuits) (high-voltage lines 31, 32, and 33 are shown in Fig. 1. Hereinafter, they may be collectively referred to as "high-voltage lines 30"), a shunt reactor 40, and a neutral point reactor 50. The transformer 10 is a facility that transforms the voltage transmitted from a power plant, which is an example of the premises 1 (e.g., from 110,000V to 66,000V). The transformer retaining steel structure 20 is a gate-shaped facility (shown as a tower in Fig. 2, but has a shape that extends in the depth direction) for supporting the high-voltage line 30, and is usually a steel structure of several tens of meters in length. The high-voltage line 30 is a power transmission line that transmits high-voltage power (e.g., 6,600V power) output from a substation. The shunt reactor (ShR) 40 is a device that is connected to the shunt of the AC circuit and compensates for the leading reactive power by supplying lagging reactive power of the high-voltage line 30. The neutral point reactor (NGL) 50 is a device that is connected to the neutral point of the power system and prevents an abnormal rise in the voltage to ground in the event of a ground fault in the power system, as well as compensating for the system's capacitance to ground.

図1及び図2に示すように、変圧器10は、変圧器引留鉄構20の近傍に隣接するように設置され、高圧線30から分岐したリード線が接続されている。分路リアクトル40及び中性点リアクトル50は、変圧器引留鉄構20の近傍に隣接し、変圧器10に対向する位置であり、変圧器10の2次側に設置されている。図2に示すように、高圧線30は、変圧器10、分路リアクトル40、及び中性点リアクトル50の上方を通り、変圧器引留鉄構20に支持されて設置されている。 As shown in Figures 1 and 2, the transformer 10 is installed adjacent to the transformer retaining iron structure 20, and a lead wire branching from the high-voltage line 30 is connected to it. The shunt reactor 40 and neutral point reactor 50 are installed adjacent to the transformer retaining iron structure 20, facing the transformer 10, and on the secondary side of the transformer 10. As shown in Figure 2, the high-voltage line 30 passes above the transformer 10, the shunt reactor 40, and the neutral point reactor 50, and is installed while being supported by the transformer retaining iron structure 20.

構内1において、変圧器10、変圧器引留鉄構20、分路リアクトル40、及び中性点リアクトル50は、基礎工事が行われた地面の上に設置される。ここで、基礎工事とは、地面の掘削を行ってアース工事、ケーブルピット付設等を行い、コンクリート打設を行って変圧器10等の各種機器を設置可能な状態にすることをいう。 In the premises 1, the transformer 10, the transformer retaining iron structure 20, the shunt reactor 40, and the neutral reactor 50 are installed on the ground on which foundation work has been performed. Here, foundation work refers to digging the ground to perform earthing work, installing cable pits, etc., and pouring concrete to prepare the various devices such as the transformer 10 for installation.

実施の形態1に係る変圧器取替工法は、変圧器10を取り替えるための工法であるが、取り替える新たな変圧器を設置する空きスペースが変圧器10の近傍にない場合、変圧器10から離隔した位置に設置せざるを得ない。そのため、新たな遮断器や断路器および母線鉄構等の設置、及びこれらの機器を設置する箇所に基礎工事がなされていない場合には基礎工事も必要になり、長期間の工期を確保する必要がある。 The transformer replacement method according to the first embodiment is a method for replacing transformer 10, but if there is no free space near transformer 10 to install a new replacement transformer, it must be installed at a location away from transformer 10. This requires the installation of new circuit breakers, disconnecting switches, busbar steel structures, etc., and foundation work if not done at the locations where these devices will be installed, so it is necessary to ensure a long construction period.

また、例えば配電用変電所における変圧器を取り替える場合は、移動用変圧器を仮設することで取替対象の変圧器を長期停止することは可能であるが、1次変電所おける変圧器の場合は容量が大きいため、移動用変圧器を仮設することによる対応はできない、という問題がある。 For example, when replacing a transformer at a distribution substation, it is possible to shut down the transformer to be replaced for an extended period of time by installing a temporary portable transformer. However, in the case of transformers at primary substations, the capacity is so large that installing a temporary portable transformer is not possible.

そこで、本実施の形態では、分路リアクトル40及び中性点リアクトル50を移設し、その空いたスペースに新たな変圧器を設置し、既存の施設を有効活用することで、短期間で変圧器を取り替えることを可能にし、変圧器の連続停止期間を短期間にすることを可能にしている。 In this embodiment, the shunt reactor 40 and neutral point reactor 50 are relocated, and a new transformer is installed in the space created, making effective use of existing facilities, which makes it possible to replace the transformer in a short period of time and shorten the period of continuous shutdown of the transformer.

なお、本実施の形態では、移設する機器の例として分路リアクトル40及び中性点リアクトル50を示しているが、これらの機器に限られず、構内1において移設可能な機器であれば他の機器であってもよい。 In this embodiment, the shunt reactor 40 and neutral point reactor 50 are shown as examples of equipment to be relocated, but the equipment is not limited to these, and other equipment that can be relocated within the premises 1 may be used.

(実施の形態1)
<工程の流れ>
図3~図8は、この実施の形態を示し、図3は、本発明の実施の形態1に係る変圧器取替工法を示すフローチャートである。図3~図8を参照しながら、本発明の実施の形態1に係る変圧器取替工法の流れの一例について説明する。
(Embodiment 1)
<Process flow>
3 to 8 show this embodiment, and Fig. 3 is a flowchart showing the transformer replacement method according to the first embodiment of the present invention. An example of the flow of the transformer replacement method according to the first embodiment of the present invention will be described with reference to Figs. 3 to 8.

ステップS101の工程は、分路リアクトル40及び中性点リアクトル50を、現状の変圧器(第1の変圧器)10に対向する位置から移設する。分路リアクトル40及び中性点リアクトル50を移設する位置は、それぞれの機器の機能を発揮できるような位置であればよく、配線等の状況から現状の位置より離隔していない位置であることが望ましい。 In step S101, the shunt reactor 40 and neutral point reactor 50 are relocated from their current positions facing the transformer (first transformer) 10. The shunt reactor 40 and neutral point reactor 50 may be relocated to any position that allows the respective devices to function, and it is preferable that they are not far from their current positions in terms of the wiring, etc.

図4は、図1に示す状態から、分路リアクトル40及び中性点リアクトル50が移設された状態を示す平面図である。図4に示すように、ステップS101の工程では、分路リアクトル40及び中性点リアクトル50を変圧器10と対向しない位置へ移設している。この位置は、分路リアクトル40及び中性点リアクトル50の元の設置位置からも近く、配線工事も容易であるため、望ましい位置といえる。 Figure 4 is a plan view showing the state in which the shunt reactor 40 and neutral point reactor 50 have been relocated from the state shown in Figure 1. As shown in Figure 4, in the process of step S101, the shunt reactor 40 and neutral point reactor 50 are relocated to a position that does not face the transformer 10. This position is close to the original installation positions of the shunt reactor 40 and neutral point reactor 50, and wiring work is also easy, so it is a desirable position.

なお、分路リアクトル40及び中性点リアクトル50の移設後の位置に基礎工事が行われていない場合は、当該位置に移設するための基礎工事も行う。ただし、あらかじめ基礎工事が行われていたとしても、分路リアクトル40及び中性点リアクトル50を設置するための改良工事は必要になる。また、ステップS101の工程では、配線工事も行うが、既設の遮断器や断路器が流用可能な場合は、流用してもよい。 If foundation work has not been done at the new location of the shunt reactor 40 and neutral point reactor 50, foundation work is also done to relocate them to that location. However, even if foundation work has been done beforehand, improvement work is required to install the shunt reactor 40 and neutral point reactor 50. In addition, wiring work is also done in the process of step S101, but if existing circuit breakers and disconnectors can be used, they may be used.

ステップS102の工程は、新たな変圧器(第2の変圧器)60を構内1に設置する。変圧器60は、現状の変圧器10の代わりとなる変圧器であり、変圧器10と同等の機能を備えている装置である。変圧器60を設置する位置は、例えば、分路リアクトル40及び中性点リアクトル50が設置されていた位置であり、分路リアクトル40及び中性点リアクトル50を移設したことにより確保された空きスペースである。 In step S102, a new transformer (second transformer) 60 is installed in the premises 1. The transformer 60 is a replacement for the current transformer 10, and is a device that has the same functions as the transformer 10. The location where the transformer 60 is installed is, for example, the location where the shunt reactor 40 and neutral point reactor 50 were installed, and is the vacant space secured by relocating the shunt reactor 40 and neutral point reactor 50.

図5は、図4に示す状態から、新たな変圧器60が設置された状態を示す平面図である。図5に示すように、ステップS102の工程では、変圧器60を、分路リアクトル40及び中性点リアクトル50がもともと設置されていた、変圧器10と対向する位置へ移設している。この位置は、変圧器10の近傍、かつ変圧器引留鉄構20の近傍であり、具体的には変圧器引留鉄構20に隣接して変圧器10に対向する位置であり、高圧線30にリード線を接続させるために望ましい位置といえる。 Figure 5 is a plan view showing the state in which a new transformer 60 has been installed, following the state shown in Figure 4. As shown in Figure 5, in the process of step S102, the transformer 60 is moved to a position opposite the transformer 10, where the shunt reactor 40 and neutral point reactor 50 were originally installed. This position is near the transformer 10 and near the transformer retaining iron structure 20, specifically, adjacent to the transformer retaining iron structure 20 and opposite the transformer 10, which is a desirable position for connecting the lead wires to the high voltage line 30.

なお、本実施の形態では、分路リアクトル40及び中性点リアクトル50を移設してその位置に変圧器60を設置しているが、同様の位置が空きスペースとなっている場合は、機器の移設を行わずに変圧器60を設置してもよい。 In this embodiment, the shunt reactor 40 and neutral point reactor 50 are relocated and the transformer 60 is installed in that position, but if there is vacant space in a similar position, the transformer 60 may be installed without relocating the equipment.

ステップS103の工程は、変圧器引留鉄構20に対して所定の改造を行う。変圧器引留鉄構20に対する改造は、具体的には例えば、変圧器引留鉄構20に設置されている碍子を、変圧器60に対応するように変更する工事をいうが、このような工事に限られず、変圧器60に対応するような改修工事全般をいう。 The process of step S103 involves making a specified modification to the transformer retaining steel structure 20. Modification to the transformer retaining steel structure 20 specifically refers to, for example, work to change the insulators installed on the transformer retaining steel structure 20 to accommodate the transformer 60, but is not limited to such work and refers to general refurbishment work to accommodate the transformer 60.

図6は、図4の構内1を示す側面図である。図6に示すように、ステップS103の工程では、変圧器引留鉄構20に設置されている碍子70を、変圧器60に対応するように、例えば110kV用の碍子に変更する。ステップS103の工程は、ステップS102の工程と並行して行ってもよい。 Figure 6 is a side view showing the premises 1 of Figure 4. As shown in Figure 6, in the process of step S103, the insulators 70 installed on the transformer retaining iron structure 20 are changed to insulators for 110 kV, for example, to correspond to the transformer 60. The process of step S103 may be performed in parallel with the process of step S102.

ステップS104の工程は、高圧線30からのリード線を変圧器60に接続して設置するための型取りを行う。図6に示すように、ステップS104の工程では、高圧線30から引き込むリード線80を設置するための型取りを行う。ステップS104の工程は、ステップS102,S103の工程と並行して行ってもよい。 In step S104, a mold is made for connecting and installing the lead wire from the high-voltage line 30 to the transformer 60. As shown in FIG. 6, in step S104, a mold is made for installing the lead wire 80 that is drawn from the high-voltage line 30. Step S104 may be performed in parallel with steps S102 and S103.

ステップS105の工程は、変圧器60に高圧線30からのリード線80を接続する。ステップS105の工程では、ステップS104で行った型取りに沿って、高圧線30から引き込むリード線80を変圧器60に接続する。ステップS105の工程は、ステップS102,S103の工程と並行して行ってもよい。 In step S105, the lead wire 80 from the high-voltage line 30 is connected to the transformer 60. In step S105, the lead wire 80 drawn from the high-voltage line 30 is connected to the transformer 60 according to the mold made in step S104. Step S105 may be performed in parallel with steps S102 and S103.

ステップS106の工程は、取り替えの対象である変圧器10を撤去する。このとき、変圧器10をリード線80から切り離す工事を行う。なお、ステップS106の工程は、ステップS105の工程と同時に行うが、説明のためにステップを分けている。 In step S106, the transformer 10 to be replaced is removed. At this time, work is performed to disconnect the transformer 10 from the lead wires 80. Note that step S106 is performed simultaneously with step S105, but is separated into separate steps for the sake of explanation.

図7は、図5に示す状態から、変圧器10が撤去された状態を示す平面図である。また、図8は、図7の構内1を示す側面図である。図7及び図8に示すように、ステップS106の工程では、図5及び図6に示されていた変圧器10を撤去する。 Figure 7 is a plan view showing the state after the transformer 10 has been removed from the state shown in Figure 5. Also, Figure 8 is a side view showing the premises 1 of Figure 7. As shown in Figures 7 and 8, in the process of step S106, the transformer 10 shown in Figures 5 and 6 is removed.

<効果>
実施の形態1に係る変圧器取替工法によれば、構内1に設置され、取替対象である変圧器(第1の変圧器)10の近傍、かつ変圧器引留鉄構20の近傍であり、(分路リアクトル40及び中性点リアクトル50の移設前の位置である)基礎工事がなされている空きスペースに、新たな変圧器(第2の変圧器)60を設置し、変圧器引留鉄構20に対して所定の改造工事を行い、高圧線(主回路)30からのリード線を設置するための型取りを行い、変圧器60にリード線を接続し、変圧器10を撤去する。そのため、構内1に既設の遮断器や断路器および母線鉄構等を流用することができる。これにより、短期間で変圧器10を変圧器60に取り替えることが可能になる。
<Effects>
According to the transformer replacement method of the first embodiment, a new transformer (second transformer) 60 is installed in an empty space installed in the premises 1, near the transformer (first transformer) 10 to be replaced and near the transformer dead-end ironwork 20, where foundation work has been done (the position before the shunt reactor 40 and neutral point reactor 50 are relocated), a predetermined modification work is performed on the transformer dead-end ironwork 20, a mold is made for installing lead wires from the high-voltage line (main circuit) 30, the lead wires are connected to the transformer 60, and the transformer 10 is removed. Therefore, it is possible to reuse the circuit breakers, disconnectors, busbar ironwork, etc. already installed in the premises 1. This makes it possible to replace the transformer 10 with the transformer 60 in a short period of time.

また、変圧器60を、変圧器引留鉄構20に隣接する変圧器10に対向するように、変圧器引留鉄構20に隣接する位置に設置する。これにより、既設の変圧器10の近傍で取替工事を行うことができるため、短期間で変圧器を取り替えることが可能になる。 The transformer 60 is also installed adjacent to the transformer retaining steel structure 20 so as to face the transformer 10 adjacent to the transformer retaining steel structure 20. This allows replacement work to be carried out near the existing transformer 10, making it possible to replace the transformer in a short period of time.

また、変圧器引留鉄構20に設置されている碍子70を、変圧器60に対応するように変更する。これにより、他の工程作業、例えば変圧器60の設置工程と並行して工事を行うことができるため、短期間で変圧器を取り替えることが可能になる。 The insulators 70 installed on the transformer retaining steel structure 20 are also changed to accommodate the transformer 60. This allows the work to be carried out in parallel with other process steps, such as the installation process of the transformer 60, making it possible to replace the transformer in a short period of time.

さらに、変圧器10の2次側に基礎工事がなされて設置されている装置である、分路リアクトル40及び中性点リアクトル50(いずれか一方のみでもよく、両方でもよい)を移設し、空きスペースを確保する。そのため、構内1に既設の遮断器や断路器および母線鉄構等を流用することができる。これにより、短期間で変圧器を取り替えることが可能になる。 Furthermore, the shunt reactor 40 and neutral point reactor 50 (either one or both may be used), which are devices installed on the secondary side of the transformer 10 after foundation work has been completed, are relocated to secure free space. This makes it possible to reuse the circuit breakers, disconnecting switches, busbar ironwork, etc. already installed on the premises 1. This makes it possible to replace the transformer in a short period of time.

以上、この発明の実施の形態を詳述してきたが、具体的な構成はこの実施の形態に限られるものではなく、この発明の要旨を逸脱しない範囲の設計の変更等があっても、この発明に含まれる。 Although the embodiment of the present invention has been described in detail above, the specific configuration is not limited to this embodiment, and even if there are design changes within the scope of the invention that do not deviate from the gist of the invention, they are still included in the invention.

1 :構内
10 :変圧器
20 :変圧器引留鉄構
30 :高圧線
31 :高圧線
32 :高圧線
33 :高圧線
40 :分路リアクトル
50 :中性点リアクトル
60 :変圧器
70 :碍子
80 :リード線
1: Premises 10: Transformer 20: Transformer dead-end iron structure 30: High-voltage line 31: High-voltage line 32: High-voltage line 33: High-voltage line 40: Shunt reactor 50: Neutral reactor 60: Transformer 70: Insulator 80: Lead wire

Claims (5)

変圧器引留鉄構が設置され、前記変圧器引留鉄構に隣接するように構内に設置された変圧器を取り替える変圧器取替工法であって、
前記構内の取替対象である第1の変圧器の近傍かつ前記変圧器引留鉄構の近傍であり、基礎工事がなされている空きスペースに、新たな第2の変圧器を設置するステップと、
前記変圧器引留鉄構に対して前記第2の変圧器を設置するための所定の改造工事を行い、前記変圧器引留鉄構に配置されている主回路からのリード線を設置するための型取りを行うステップと、
前記リード線の型取りに沿って、前記第2の変圧器に前記リード線を接続するステップと、
前記主回路から前記第1の変圧器を切り離し、前記第1の変圧器を撤去するステップと、
を含む工程を行うことを特徴とする変圧器取替工法。
A transformer replacement method in which a transformer retention iron structure is installed and a transformer installed in a premises adjacent to the transformer retention iron structure is replaced,
a step of installing a new second transformer in an empty space in the vicinity of the first transformer to be replaced and in the vicinity of the transformer dead-end steel structure in the premises, where foundation work has been carried out;
carrying out predetermined remodeling work for installing the second transformer on the transformer dead-end iron structure, and taking a mold for installing lead wires from a main circuit arranged on the transformer dead-end iron structure;
connecting the leads to the second transformer along the lead pattern;
disconnecting the first transformer from the main circuit and removing the first transformer;
A transformer replacement method comprising the steps of:
前記第2の変圧器を設置するステップにおいて、前記第2の変圧器を、前記変圧器引留鉄構に隣接する前記第1の変圧器に対向するように、前記変圧器引留鉄構に隣接する位置に設置する、
ことを特徴とする請求項1に記載の変圧器取替工法。
In the step of installing the second transformer, the second transformer is installed at a position adjacent to the transformer dead-end ironwork so as to face the first transformer adjacent to the transformer dead-end ironwork.
The transformer replacement method according to claim 1 .
前記変圧器引留鉄構に対して所定の改造工事を行うステップにおいて、前記変圧器引留鉄構に設置されている碍子を、前記第2の変圧器に対応するように変更する、
ことを特徴とする請求項1に記載の変圧器取替工法。
In a step of carrying out a predetermined modification work on the transformer retention iron structure, insulators installed on the transformer retention iron structure are changed to correspond to the second transformer.
The transformer replacement method according to claim 1 .
前記第2の変圧器を設置するステップの前工程において、
前記第1の変圧器の2次側に基礎工事がなされて設置されている装置を移設し、前記空きスペースを確保するステップを行う、
ことを特徴とする請求項1から3のいずれか1項に記載の変圧器取替工法。
In a process prior to the step of installing the second transformer,
a step of relocating a device installed on the secondary side of the first transformer with foundation work completed, and securing the free space;
The transformer replacement method according to any one of claims 1 to 3.
前記装置を移設するステップにおいて、前記装置は、前記構内に設置された分路リアクトル、中性点リアクトルのいずれかまたは両方を含む、
ことを特徴とする請求項4に記載の変圧器取替工法。
In the step of relocating the device, the device includes either or both of a shunt reactor and a neutral point reactor installed in the premises,
The transformer replacement method according to claim 4.
JP2022180278A 2022-11-10 2022-11-10 Transformer replacement method Pending JP2024069959A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2022180278A JP2024069959A (en) 2022-11-10 2022-11-10 Transformer replacement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2022180278A JP2024069959A (en) 2022-11-10 2022-11-10 Transformer replacement method

Publications (1)

Publication Number Publication Date
JP2024069959A true JP2024069959A (en) 2024-05-22

Family

ID=91122001

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2022180278A Pending JP2024069959A (en) 2022-11-10 2022-11-10 Transformer replacement method

Country Status (1)

Country Link
JP (1) JP2024069959A (en)

Similar Documents

Publication Publication Date Title
KR20100054948A (en) By-pass construction method for replacement of pole-top transformer (1phase/3phase) using 1phase portable transformer
KR100926445B1 (en) Uninterruptible bypassing method for underground power line using extension elbow
Magg et al. Connecting networks with VSC HVDC in Africa: Caprivi Link interconnector
Camm et al. Wind power plant collector system design considerations: IEEE PES wind plant collector system design working group
JP2024069959A (en) Transformer replacement method
CN105576528A (en) AC/DC power supply transfer box and comprehensive automation transformation method
JP2019122145A (en) Opening/closing unit group replacement method
Giorgi et al. The italy-greece HVDC link
US11848562B2 (en) Electric vehicle charging station for connecting to high or extra high voltage transmission line and operation method thereof
JP7347190B2 (en) Switchgear replacement method
D'Souza et al. Conversion of 230 kV Switchyard to Gas-Insulated Substation in a Gas Plant
CA3122917A1 (en) Electric vehicle charging station for connecting to high or extra high voltage transmission line and operation method thereof
Al Riyami et al. Impact of installation of 400 kV shunt reactors on Oman grid
Wehbring et al. Strategies to convert AC into DC Medium Voltage Grids
D'Souza et al. Conversion of 230 KV switchyard to gas insulated substation in a gas plant
Zimmermann et al. Comparison of GIS and AIS systems for urban supply networks
McVey et al. Mobile STATCOM Multi Tool for Transmission Operations, Construction and Rapid Restoration
RAGUŽ et al. Technical aspect of reconstructions of 35 kV and 10 (20) kV plants with an example
Page et al. Lessons from the installation and commissioning of novel power electronics for active response
Handel Design of the mica hydroelectric projectߞA major 500 kV SF 6 installation
Kiessling et al. Overall planning
JP2001161015A (en) Method for renewing and method for installing more transmission line
KR20230008551A (en) Manhole attached cable elbow junction box
KR20040064317A (en) Apparatus of uninterruptible power supply and control method thereof
Lonare et al. Installation of 11kV/440V Distribution Substation