JP2023151915A - Execution timing determination system, execution timing determination method, and execution timing determination program - Google Patents

Execution timing determination system, execution timing determination method, and execution timing determination program Download PDF

Info

Publication number
JP2023151915A
JP2023151915A JP2022061789A JP2022061789A JP2023151915A JP 2023151915 A JP2023151915 A JP 2023151915A JP 2022061789 A JP2022061789 A JP 2022061789A JP 2022061789 A JP2022061789 A JP 2022061789A JP 2023151915 A JP2023151915 A JP 2023151915A
Authority
JP
Japan
Prior art keywords
power cost
execution timing
execution
timing determination
timing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2022061789A
Other languages
Japanese (ja)
Inventor
泰明 阿部
Yasuaki Abe
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Omron Corp
Original Assignee
Omron Corp
Omron Tateisi Electronics Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Omron Corp, Omron Tateisi Electronics Co filed Critical Omron Corp
Priority to JP2022061789A priority Critical patent/JP2023151915A/en
Priority to PCT/JP2023/007949 priority patent/WO2023189196A1/en
Publication of JP2023151915A publication Critical patent/JP2023151915A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks

Abstract

To provide an execution timing determination technology making it possible to minimize an electric power cost relating to one or plural processes.SOLUTION: An execution timing determination system determines the execution timing of one or plural processes, and includes a first acquisition unit (13) that can refer to an electric power cost prediction model (31) for use in predicting an electric power cost relating to the one or plural processes, and acquires execution period information on an execution period needed to execute an object process out of the one or plural processes, a second acquisition unit (15) that acquires electric power cost information on an electric power cost at a predetermined timing, an electric power cost prediction unit (17) that predicts an electric power cost of the object process on the basis of the execution period information, electric power cost information, and electric power cost prediction model (31), and an execution timing determination unit (19) that determines the execution timing of the object process on the basis of the predicted electric power cost.SELECTED DRAWING: Figure 4

Description

本発明は、実行タイミング判断装置、実行タイミング判断方法、及び、実行タイミング判断プログラムに関する。 The present invention relates to an execution timing determination device, an execution timing determination method, and an execution timing determination program.

特許文献1には、制御対象となる機器の運転スケジュールを最適化する運転計画最適化装置等が記載されている。運転計画最適化装置は、(1)制御対象機器について、プロセスデータに基づき将来の所定の期間における消費エネルギーもしくは供給エネルギーの予測値を設定するエネルギー予測部と、(2)予測値、制御対象機器の特性とプロセスデータに基づいて、所定の期間における制御対象機器の運転スケジュールを、所定の評価指標により最適化するスケジュール最適化部と、(3)予め定められた判定条件に基づいて最新の運転スケジュール承認の必要性を判定する承認依頼判定部と、(4)承認依頼判定部における判定結果を伝達する判定結果伝達部とを備える。 Patent Document 1 describes an operation plan optimization device and the like that optimizes the operation schedule of equipment to be controlled. The operation plan optimization device includes (1) an energy prediction unit that sets a predicted value of consumed energy or supplied energy for a predetermined period in the future for the controlled device based on process data; and (2) a predicted value and a predicted value of the controlled device. (3) a schedule optimization unit that optimizes the operation schedule of the controlled equipment in a predetermined period using a predetermined evaluation index based on the characteristics and process data; It includes an approval request determining section that determines the necessity of schedule approval, and (4) a determination result transmitting section that transmits the determination result of the approval request determining section.

特開2015-018374号公報Japanese Patent Application Publication No. 2015-018374

しかしながら、特許文献1に記載の運転計画最適化装置は、複数の制御対象機器の運転スケジュールを最適化することを目的としている。つまり、特許文献1に記載の運転計画最適化装置は、一又は複数の製造工程のうち、実行対象である対象工程に関する予測電力コストを踏まえた、対象工程の実行タイミングの調整については全く考慮していない。よって、当該運転計画最適化装置では、電力コストの高い時間帯(例えば電力コストのピーク時)に対象工程を実行してしまい、一又は複数の製造工程に関する電力コストが増加するおそれがある。 However, the operation plan optimization device described in Patent Document 1 aims at optimizing the operation schedule of a plurality of devices to be controlled. In other words, the operation plan optimization device described in Patent Document 1 does not consider at all the adjustment of the execution timing of the target process based on the predicted power cost for the target process to be executed among one or more manufacturing processes. Not yet. Therefore, in the operation plan optimization device, the target process is executed during a time period when the power cost is high (for example, during the peak time of the power cost), and the power cost related to one or more manufacturing processes may increase.

本発明は、このような事情に鑑みてなされたものであり、一又は複数の工程に関する電力コストを低減可能な実行タイミング判断技術を提供することを目的の1つとする。 The present invention has been made in view of such circumstances, and one of the objects is to provide an execution timing determination technique that can reduce power costs related to one or more processes.

本発明の一態様に係る実行タイミング判断装置は、一又は複数の工程の実行タイミングを判断する実行タイミング判断装置であって、一又は複数の工程に関する電力コストを予測するための電力コスト予測モデルを参照可能に構成されており、一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得する第1取得部と、所定タイミングの電力コストに関する電力コスト情報を取得する第2取得部と、実行期間情報と電力コスト情報と電力コスト予測モデルとに基づいて対象工程の電力コストを予測する電力コスト予測部と、予測した電力コストに基づいて対象工程の実行タイミングを判断する実行タイミング判断部と、を備える。 An execution timing determination device according to one aspect of the present invention is an execution timing determination device that determines the execution timing of one or more steps, and includes a power cost prediction model for predicting power costs related to the one or more steps. A first acquisition unit that is configured to be referenceable and that acquires execution period information regarding an execution period necessary to execute a target process among one or more processes, and acquires power cost information regarding power cost at a predetermined timing. a second acquisition unit that predicts the power cost of the target process based on the execution period information, power cost information, and the power cost prediction model; and a power cost prediction unit that predicts the power cost of the target process based on the predicted power cost. and an execution timing determination unit that makes a determination.

この態様によれば、実行タイミング判断装置は、一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得し、所定タイミングの電力コストに関する電力コスト情報を取得し、実行期間情報と、電力コスト情報と、一又は複数の工程に関する電力コストを予測するための電力コスト予測モデルと、に基づいて対象工程の電力コストを予測し、予測した電力コストに基づいて対象工程の実行タイミングを判断する。よって、電力コストの高い時間帯(例えば電力コストのピーク時)を避けて対象工程を実行すること(例えば電力コストのピークシフト)が可能となる。したがって、一又は複数の工程に関する電力コストを低減可能である。 According to this aspect, the execution timing determination device acquires execution period information regarding the execution period necessary for executing the target process among one or more processes, and acquires power cost information regarding the power cost at a predetermined timing. , the power cost of the target process is predicted based on the execution period information, the power cost information, and the power cost prediction model for predicting the power cost related to one or more processes, and the target process is performed based on the predicted power cost. Determine when to execute a process. Therefore, it is possible to execute the target process (for example, shift the peak power cost) while avoiding time periods when the power cost is high (for example, the peak time of the power cost). Therefore, power costs related to one or more steps can be reduced.

上記態様において、実行タイミング判断部は、予測した電力コストに基づく、対象工程の実行タイミングの判断結果が所定の条件を満たすか否かを判断してもよい。 In the above aspect, the execution timing determination unit may determine whether the determination result of the execution timing of the target process based on the predicted power cost satisfies a predetermined condition.

上記態様において、予測した電力コストに基づく、対象工程の実行タイミングの判断結果が所定の条件を満たすまで、(i)電力コスト予測部における、対象工程の電力コストを予測すること、及び、(ii)実行タイミング判断部における、対象工程の実行タイミングを判断することが繰り返し実行されてもよい。 In the above aspect, (i) the power cost prediction unit predicts the power cost of the target process until the judgment result of the execution timing of the target process based on the predicted power cost satisfies a predetermined condition; and (ii) ) The execution timing determination unit may repeatedly determine the execution timing of the target process.

上記態様において、実行タイミング判断部は、電力コスト予測部が予測した電力コストであって、第1タイミングから第1タイミングよりも後の第2タイミングに基づく所定期間における電力コストが所定の条件を満たす場合に、対象工程の実行タイミングを判断してもよい。 In the above aspect, the execution timing determining unit determines that the power cost predicted by the power cost predicting unit in a predetermined period from the first timing to a second timing after the first timing satisfies a predetermined condition. In this case, the execution timing of the target process may be determined.

上記態様において、実行タイミング判断部は、電力コスト予測部が予測した電力コストの積分値であって、第1タイミングから第1タイミングよりも後の第2タイミングに基づく所定期間における積分値が最小になる場合の第1タイミングを、対象工程の最適な実行タイミングとして判断してもよい。 In the above aspect, the execution timing determining unit determines that the integral value of the power cost predicted by the power cost predicting unit is the minimum integral value from the first timing to a predetermined period based on a second timing subsequent to the first timing. The first timing when this happens may be determined as the optimal execution timing for the target process.

上記態様において、対象工程が複数ある場合、複数の対象工程ごとに、(i)電力コスト予測部における、対象工程の電力コストを予測すること、及び、(ii)実行タイミング判断部における、対象工程の実行タイミングを判断することが実行されてもよい。 In the above aspect, when there are multiple target processes, (i) the power cost prediction unit predicts the power cost of the target process, and (ii) the execution timing determination unit predicts the power cost of the target process for each of the multiple target processes. may be performed.

上記態様において、実行タイミング判断装置は、所定タイミングにおけるバッテリの残量に基づいてバッテリの運転期間を算出するバッテリ消費予測モデルを参照可能に構成されており、第1取得部は、実行期間情報を、運転期間に関する情報に基づいて取得してもよい。 In the above aspect, the execution timing determination device is configured to be able to refer to a battery consumption prediction model that calculates the battery operating period based on the remaining amount of the battery at a predetermined timing, and the first acquisition unit acquires the execution period information. , may be acquired based on information regarding the operating period.

本発明の他の態様に係る実行タイミング判断方法は、一又は複数の工程の実行タイミングを判断する実行タイミング判断装置で実行される実行タイミング判断方法であって、一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得することと、所定タイミングの電力コストに関する電力コスト情報を取得することと、実行期間情報と、電力コスト情報と、一又は複数の工程に関する電力コストを予測するための電力コスト予測モデルと、に基づいて対象工程の電力コストを予測することと、予測した電力コストに基づいて対象工程の実行タイミングを判断することと、を含む。 An execution timing determination method according to another aspect of the present invention is an execution timing determination method that is executed by an execution timing determination device that determines the execution timing of one or more steps, and the method includes: Acquisition of execution period information regarding the execution period necessary for executing the process, acquisition of power cost information regarding the power cost at a predetermined timing, execution period information, power cost information, and information regarding one or more steps. The method includes predicting the power cost of the target process based on a power cost prediction model for predicting the power cost, and determining the execution timing of the target process based on the predicted power cost.

この態様によれば、実行タイミング判断装置は、一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得し、所定タイミングの電力コストに関する電力コスト情報を取得し、実行期間情報と、電力コスト情報と、一又は複数の工程に関する電力コストを予測するための電力コスト予測モデルと、に基づいて対象工程の電力コストを予測し、予測した電力コストに基づいて対象工程の実行タイミングを判断する。よって、電力コストの高い時間帯を避けて対象工程を実行することが可能となる。したがって、一又は複数の工程に関する電力コストを低減可能である。 According to this aspect, the execution timing determination device acquires execution period information regarding the execution period necessary for executing the target process among one or more processes, and acquires power cost information regarding the power cost at a predetermined timing. , the power cost of the target process is predicted based on the execution period information, the power cost information, and the power cost prediction model for predicting the power cost related to one or more processes, and the target process is performed based on the predicted power cost. Determine when to execute a process. Therefore, it is possible to execute the target process while avoiding time periods when power costs are high. Therefore, power costs related to one or more steps can be reduced.

本発明の他の態様に係る実行タイミング判断プログラムは、一又は複数の工程の実行タイミングを判断する実行タイミング判断装置を、一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得する第1取得部、所定タイミングの電力コストに関する電力コスト情報を取得する第2取得部、実行期間情報と、電力コスト情報と、一又は複数の工程に関する電力コストを予測するための電力コスト予測モデルと、に基づいて対象工程の電力コストを予測する電力コスト予測部、予測した電力コストに基づいて対象工程の実行タイミングを判断する実行タイミング判断部、として機能させる、実行タイミング判断プログラム。 An execution timing determination program according to another aspect of the present invention includes an execution timing determination device that determines the execution timing of one or more steps. A first acquisition unit that acquires execution period information; a second acquisition unit that acquires power cost information regarding power cost at a predetermined timing; and a second acquisition unit that predicts execution period information, power cost information, and power cost regarding one or more processes. an execution timing determination unit that functions as a power cost prediction unit that predicts the power cost of the target process based on the power cost prediction model; and an execution timing determination unit that determines the execution timing of the target process based on the predicted power cost. program.

この態様によれば、実行タイミング判断装置は、一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得し、所定タイミングの電力コストに関する電力コスト情報を取得し、実行期間情報と、電力コスト情報と、一又は複数の工程に関する電力コストを予測するための電力コスト予測モデルと、に基づいて対象工程の電力コストを予測し、予測した電力コストに基づいて対象工程の実行タイミングを判断する。よって、電力コストの高い時間帯を避けて対象工程を実行することが可能となる。したがって、一又は複数の工程に関する電力コストを低減可能である。 According to this aspect, the execution timing determination device acquires execution period information regarding the execution period necessary for executing the target process among one or more processes, and acquires power cost information regarding the power cost at a predetermined timing. , the power cost of the target process is predicted based on the execution period information, the power cost information, and the power cost prediction model for predicting the power cost related to one or more processes, and the target process is performed based on the predicted power cost. Determine when to execute a process. Therefore, it is possible to execute the target process while avoiding time periods when power costs are high. Therefore, power costs related to one or more steps can be reduced.

本発明によれば、一又は複数の工程に関する電力コストを低減可能である。 According to the present invention, power costs related to one or more steps can be reduced.

本発明の第1実施形態に係る工程制御システムのブロック構成を示す図である。1 is a diagram showing a block configuration of a process control system according to a first embodiment of the present invention. 第1実施形態に係る工程電力コスト予測プログラムの一例を示す図である。FIG. 2 is a diagram illustrating an example of a process power cost prediction program according to the first embodiment. 第1実施形態に係る材料投入指示プログラムの一例を示す図である。It is a figure showing an example of a material input instruction program concerning a 1st embodiment. 第1実施形態に係るMESの機能構成を示す図である。FIG. 3 is a diagram showing a functional configuration of an MES according to the first embodiment. 第1実施形態に係るMESの物理構成を示す図である。FIG. 2 is a diagram showing the physical configuration of an MES according to the first embodiment. 第1実施形態に係る工程制御システムのMESにより実行される工程制御処理のフローチャートである。It is a flowchart of the process control process performed by MES of the process control system based on 1st Embodiment. 第1実施形態に係るMESにより実行される対象工程のスケジュールの評価及び調整処理のフローチャートである。It is a flowchart of the evaluation and adjustment process of the schedule of the target process performed by MES based on 1st Embodiment. 第1実施形態に係るMESにより実行される電力コストの取得処理、及び、電力コストの推移の予測処理の一例を示す図である。FIG. 3 is a diagram illustrating an example of a power cost acquisition process and a power cost trend prediction process executed by the MES according to the first embodiment. 第1実施形態に係るMESにより実行される電力コストの取得処理の一例を示す図である。FIG. 3 is a diagram illustrating an example of a power cost acquisition process executed by the MES according to the first embodiment. 第1実施形態に係るMESにより実行される工程シミュレータによる対象工程の運転時間の導出処理の一例を示す図である。FIG. 3 is a diagram illustrating an example of a process for deriving the operating time of a target process by a process simulator executed by the MES according to the first embodiment. 第1実施形態に係るMESにより実行される電力コストの推移の予測処理及び最適な材料投入時刻の判断処理の一例を示す図である。It is a figure which shows an example of the process of predicting the transition of the electric power cost, and the process of determining the optimal material input time, which are performed by the MES according to the first embodiment. 第2実施形態に係る工程制御システムのブロック構成を示す図である。FIG. 2 is a diagram showing a block configuration of a process control system according to a second embodiment. 第3実施形態に係る工程制御システムのブロック構成を示す図である。FIG. 3 is a diagram showing a block configuration of a process control system according to a third embodiment. 第4実施形態に係る工程制御システムのブロック構成を示す図である。It is a diagram showing a block configuration of a process control system according to a fourth embodiment. 第4実施形態に係る工程電力コスト予測プログラムの一例を示す図である。It is a figure showing an example of a process electric power cost prediction program concerning a 4th embodiment.

添付図面を参照して、本発明の好適な実施形態について説明する。なお、各図において、同一の符号を付したものは、同一又は同様の構成を有する。 Preferred embodiments of the present invention will be described with reference to the accompanying drawings. In addition, in each figure, those with the same reference numerals have the same or similar configurations.

<第1実施形態>
図1は、本発明の実施形態に係る工程制御システム100のブロック構成を示す図である。工程制御システム100は、一又は複数の工程ごとに実行タイミングを判断し、最適な実行タイミングで工程を実行するための制御システムである。「工程」は、所定の材料又は部材を使用する工程であり、例えば、所定の中間品(例えば半導体チップ)から完成品(例えば所定のモジュール)を製造するための製造工程を含むがこれに限られない。「工程」は、部材等を洗浄する洗浄工程、又は、中間品もしくは完成品を分解する分解工程を含んでもよい。
<First embodiment>
FIG. 1 is a diagram showing a block configuration of a process control system 100 according to an embodiment of the present invention. The process control system 100 is a control system that determines execution timing for each one or more processes and executes the processes at optimal execution timing. A "process" is a process that uses a predetermined material or member, and includes, but is not limited to, a manufacturing process for manufacturing a finished product (e.g., a predetermined module) from a predetermined intermediate product (e.g., a semiconductor chip). I can't do it. The "process" may include a cleaning process for cleaning parts, etc., or a disassembly process for disassembling intermediate products or finished products.

工程制御システム100は、例示的に、電力コストサーバ1と、ERP(Enterprise Resource Planning:企業資源計画)2と、MES(Manufacturing Execution System:製造実行システム)10(実行タイミング判断装置)とを備える。本例では電力コストサーバ1、ERP2、及び、MES10は、一台のコンピュータで構成されてもよいし、複数のコンピュータが組み合わされて実現されてもよい。 The process control system 100 exemplarily includes a power cost server 1, an ERP (Enterprise Resource Planning) 2, and an MES (Manufacturing Execution System) 10 (execution timing determination device). In this example, the power cost server 1, ERP 2, and MES 10 may be configured by one computer, or may be realized by combining a plurality of computers.

電力コストサーバ1は、複数の製造工程A,B,Cを含む製造ラインLに関する所定時刻tの電力コストCtを測定してMES10に送信する。電力コストサーバ1は、製造ラインLに関する電力コストの他、当該製造ラインL及び他の製造装置を備える製造施設全体の所定時刻tの電力コストCtを測定してもよい。 The power cost server 1 measures the power cost Ct at a predetermined time t regarding a manufacturing line L including a plurality of manufacturing processes A, B, and C, and transmits it to the MES 10. In addition to the power cost related to the manufacturing line L, the power cost server 1 may measure the power cost Ct of the entire manufacturing facility including the manufacturing line L and other manufacturing equipment at a predetermined time t.

図1の例では、製造ラインLは、複数の製造工程A,B,Cを含む。例えば、製造工程Aは、中間品Waに基づいて中間品Wbを製造する工程であり、製造工程Bは、中間品Wbに基づいて中間品Wcを製造する工程であり、製造工程Cは、中間品Wcに基づいて完成品を製造する工程である。なお、製造ラインLは、図1の例では、一つであるが、複数でもよい。また、製造ラインLが含む製造工程は、三つに限られず、単一、二つ、又は、四つ以上でもよい。 In the example of FIG. 1, the manufacturing line L includes multiple manufacturing steps A, B, and C. For example, the manufacturing process A is a process of manufacturing an intermediate product Wb based on the intermediate product Wa, the manufacturing process B is a process of manufacturing an intermediate product Wc based on the intermediate product Wb, and the manufacturing process C is a process of manufacturing an intermediate product Wc based on the intermediate product Wb. This is a process of manufacturing a finished product based on the product Wc. In addition, although there is one manufacturing line L in the example of FIG. 1, there may be a plurality of manufacturing lines L. Further, the number of manufacturing steps included in the manufacturing line L is not limited to three, and may be one, two, or four or more.

ERP2は、製造ラインLの各工程A,B,Cで製造される中間品又は完成品の目標数量及び納期を設定して、MES10に送信する。 The ERP 2 sets target quantities and delivery dates for intermediate products or finished products produced in each process A, B, and C of the production line L, and transmits them to the MES 10.

MES10は、複数の製造工程A,B,Cごとに最適な実行タイミングを判断し、判断された実行タイミングで各製造工程を実行するように製造ラインLに指示を送信する。 The MES 10 determines the optimal execution timing for each of the plurality of manufacturing processes A, B, and C, and sends an instruction to the manufacturing line L to execute each manufacturing process at the determined execution timing.

MES10は、例示的に、工程電力コスト予測プログラム3と、材料投入指示プログラム4と、材料数量DB(データベース)5とを備える。 The MES 10 exemplarily includes a process power cost prediction program 3, a material input instruction program 4, and a material quantity DB (database) 5.

工程電力コスト予測プログラム3は、各工程において特定時刻に材料を投入する(工程を実行する)際の電力コストを予測するためのプログラムである。工程電力コスト予測プログラム3は、例えば、電力コスト予測モデル31と、工程シミュレータ33と含む。 The process power cost prediction program 3 is a program for predicting the power cost when introducing materials (executing a process) at a specific time in each process. The process power cost prediction program 3 includes, for example, a power cost prediction model 31 and a process simulator 33.

電力コスト予測モデル31は、一又は複数の工程に関する電力コストを予測するためのモデルである。電力コスト予測モデル31は、例えば、時刻ごとの電力コスト推移に基づく予測モデル、及び、気候等の外部因子情報を利用した予測モデルの少なくとも一方を含む。なお、電力コスト予測モデル31は参照可能であればよく、MES10、又は、工程制御システム100の外部に配置されてもよい。 The power cost prediction model 31 is a model for predicting power costs related to one or more processes. The power cost prediction model 31 includes, for example, at least one of a prediction model based on time-by-time power cost trends and a prediction model using external factor information such as the climate. Note that the power cost prediction model 31 only needs to be referenceable, and may be placed outside the MES 10 or the process control system 100.

工程シミュレータ33は、一又は複数の工程を実行する際に必要な実行期間に関する実行期間情報を算出するプログラムである。例えば、工程シミュレータ33は、対象工程で使用される材料に関する材料情報が入力されると、対象工程を実行する際に必要な実行期間に関する実行期間情報を算出する。 The process simulator 33 is a program that calculates execution period information regarding the execution period required when executing one or more processes. For example, when material information regarding materials used in the target process is input, the process simulator 33 calculates execution period information regarding the execution period required to execute the target process.

図2は、第1実施形態に係る工程電力コスト予測プログラムの一例を示す図である。図2に示すように、工程電力コスト予測プログラム3は、時刻tの電力コストCtと、予測時刻aと、製造工程で使用される材料数量とを取得して、時刻t+aに材料を投入する際の予測電力コストCt+aを算出する。より具体的には、工程シミュレータ33は、材料数量に基づいて対象製造工程の運転時間を算出して、電力コスト予測モデル31に出力する。電力コスト予測モデル31は、時刻tの電力コストCtと、予測時刻aと、工程シミュレータ33によって算出された対象工程の運転時間とに基づいて、予測電力コストCt+aを算出する。 FIG. 2 is a diagram illustrating an example of a process power cost prediction program according to the first embodiment. As shown in FIG. 2, the process power cost prediction program 3 acquires the power cost Ct at time t, the predicted time a, and the quantity of materials used in the manufacturing process, and when introducing the materials at time t+a. Calculate the predicted power cost Ct+a. More specifically, the process simulator 33 calculates the operating time of the target manufacturing process based on the material quantity and outputs it to the power cost prediction model 31. The power cost prediction model 31 calculates the predicted power cost Ct+a based on the power cost Ct at time t, the predicted time a, and the operation time of the target process calculated by the process simulator 33.

図1に戻り、材料投入指示プログラム4は、工程電力コスト予測プログラム3によって予測された電力コストに基づいて製造工程の実行タイミングを判断するプログラムである。材料投入指示プログラム4は、判断した実行タイミングで製造工程を実行するように、製造ラインLに実行指示を送信するプログラムである。材料投入指示プログラム4は、例えば、工程実行タイミング判断モデル41を含む。工程実行タイミング判断モデル41は、例えば、製造工程ごとに実行タイミングを判断する局所判断モデル、及び、製造工程全体の最適な実行スケジュールを判断する最適判断モデルの少なくとも一方を含む。なお、工程実行タイミング判断モデル41は参照可能であればよく、MES10、又は、工程制御システム100の外部に配置されてもよい。 Returning to FIG. 1, the material input instruction program 4 is a program that determines the execution timing of a manufacturing process based on the power cost predicted by the process power cost prediction program 3. The material input instruction program 4 is a program that sends an execution instruction to the manufacturing line L so that the manufacturing process is executed at the determined execution timing. The material input instruction program 4 includes, for example, a process execution timing determination model 41. The process execution timing determination model 41 includes, for example, at least one of a local determination model that determines the execution timing for each manufacturing process, and an optimal determination model that determines the optimal execution schedule for the entire manufacturing process. Note that the process execution timing judgment model 41 only needs to be referenceable, and may be placed outside the MES 10 or the process control system 100.

図3は、第1実施形態に係る材料投入指示プログラムの一例を示す図である。図3に示すように、工程実行タイミング判断モデル41は、実行指示と、実行デッドライン(例えば、最も遅い実行タイミング時刻)と、電力コスト予測モデル31によって算出された予測電力コストCt+aとを取得して、対象製造工程の最適な実行タイミングを判断する。工程実行タイミング判断モデル41は、判断した実行タイミングで対象製造工程を実行するように、製造ラインLに実行開始の指示、又は、待機の指示を送信する。 FIG. 3 is a diagram showing an example of a material input instruction program according to the first embodiment. As shown in FIG. 3, the process execution timing judgment model 41 obtains an execution instruction, an execution deadline (for example, the latest execution timing time), and a predicted power cost Ct+a calculated by the power cost prediction model 31. Then, determine the optimal execution timing for the target manufacturing process. The process execution timing determination model 41 transmits an execution start instruction or a standby instruction to the manufacturing line L so that the target manufacturing process is executed at the determined execution timing.

図1に戻り、材料数量DB5は、例えば、製造工程で使用される材料又は部品の数量(材料情報)を管理するデータベースである。例えば、材料数量DB5は、製造ラインLから送信される、各中間品Wa,Wb,Wcの数量に基づいて記録された材料情報を更新する。 Returning to FIG. 1, the material quantity DB5 is, for example, a database that manages the quantity (material information) of materials or parts used in the manufacturing process. For example, the material quantity DB 5 updates the recorded material information based on the quantity of each intermediate product Wa, Wb, Wc transmitted from the manufacturing line L.

図4は、第1実施形態に係るMESの機能構成を示す図である。MES10は、機能的に、一又は複数の工程の実行タイミングを判断するための処理を実行する情報処理部11と、電力コスト予測モデル31と、工程シミュレータ33と、工程実行タイミング判断モデル41と、材料数量DB5と、を備える。 FIG. 4 is a diagram showing the functional configuration of the MES according to the first embodiment. Functionally, the MES 10 includes an information processing unit 11 that executes processing for determining the execution timing of one or more processes, an electric power cost prediction model 31, a process simulator 33, a process execution timing determination model 41, A material quantity DB5 is provided.

情報処理部11は、例示的に、第1取得部13と、第2取得部15と、電力コスト予測部17と、実行タイミング判断部19とを備える。なお、情報処理部11の上記各部は、例えば、メモリやハードディスク等の記憶領域(例えば図5に示すRAM(Random Access Memory)10b及びROM(Read Only Memory)10c)を用いたり、記憶領域に格納されているプログラムをプロセッサ(例えば図5に示すCPU(Central Processing Unit)10a)が実行したりすることにより実現することができる。 The information processing unit 11 exemplarily includes a first acquisition unit 13, a second acquisition unit 15, a power cost prediction unit 17, and an execution timing determination unit 19. Note that each of the above-mentioned parts of the information processing unit 11 uses, for example, a storage area such as a memory or a hard disk (for example, a RAM (Random Access Memory) 10b and a ROM (Read Only Memory) 10c shown in FIG. 5), or is stored in a storage area. This can be realized by a processor (for example, a CPU (Central Processing Unit) 10a shown in FIG. 5) executing a program.

第1取得部13、第2取得部15、及び、電力コスト予測部17は、図1及び図2に示す工程電力コスト予測プログラム3に対応する。例えば、第1取得部13は、一又は複数の製造工程のうち対象製造工程を実行する際に必要な実行期間に関する実行期間情報を、対象製造工程で使用される材料に関する材料情報に基づいて取得する。第2取得部15は、所定タイミングの電力コストに関する電力コスト情報を取得する。電力コスト測定部17は、実行期間情報と、電力コスト情報と、図1及び図2に示す電力コスト予測モデル31と、に基づいて対象製造工程の電力コストを予測する。 The first acquisition unit 13, the second acquisition unit 15, and the power cost prediction unit 17 correspond to the process power cost prediction program 3 shown in FIGS. 1 and 2. For example, the first acquisition unit 13 acquires execution period information regarding an execution period necessary for executing a target manufacturing process among one or more manufacturing processes based on material information regarding materials used in the target manufacturing process. do. The second acquisition unit 15 acquires power cost information regarding the power cost at a predetermined timing. The power cost measuring unit 17 predicts the power cost of the target manufacturing process based on the execution period information, the power cost information, and the power cost prediction model 31 shown in FIGS. 1 and 2.

実行タイミング判断部19は、図1及び図3に示す材料投入指示プログラム4に対応する。実行タイミング判断部19は、電力コスト予測部17が予測した電力コストに基づいて対象製造工程の実行タイミングを判断する。 The execution timing determination unit 19 corresponds to the material input instruction program 4 shown in FIGS. 1 and 3. The execution timing determination unit 19 determines the execution timing of the target manufacturing process based on the power cost predicted by the power cost prediction unit 17.

図5は、第1実施形態に係るMES10の物理的な構成を例示する図である。MES10は、演算部に相当するCPU10aと、記憶部に相当するRAM10bと、記憶部に相当するROM10cと、通信部10dと、入力部10eと、表示部10fと、を有する。これらの各構成は、バスを介して相互にデータ送受信可能に接続される。なお、本例ではMES10が一台のコンピュータで構成される場合について説明するが、MES10は、複数のコンピュータが組み合わされて実現されてもよい。また、図5に示す構成は一例であり、MES10はこれら以外の構成を有してもよいし、これらの構成のうち一部を有さなくてもよい。 FIG. 5 is a diagram illustrating the physical configuration of the MES 10 according to the first embodiment. The MES 10 includes a CPU 10a corresponding to a calculation section, a RAM 10b corresponding to a storage section, a ROM 10c corresponding to a storage section, a communication section 10d, an input section 10e, and a display section 10f. These components are connected to each other via a bus so that they can transmit and receive data. In this example, a case will be described in which the MES 10 is composed of one computer, but the MES 10 may be realized by combining a plurality of computers. Further, the configuration shown in FIG. 5 is an example, and the MES 10 may have configurations other than these, or may not have some of these configurations.

CPU10aは、RAM10b又はROM10cに記憶されたプログラムを実行し、各種の制御やデータの演算及び加工を行う制御部として機能する。例えば、CPU10aは、工程の実行タイミングを判断するためのプログラム(実行タイミング判断プログラム)を実行する。また、CPU10aは、入力部10eや通信部10dから種々のデータを受け取り、データの演算結果を表示部10fに表示したり、RAM10bに格納したりする。 The CPU 10a functions as a control unit that executes programs stored in the RAM 10b or ROM 10c, and performs various controls and data calculations and processing. For example, the CPU 10a executes a program (execution timing determination program) for determining the execution timing of a process. Further, the CPU 10a receives various data from the input section 10e and the communication section 10d, and displays the results of data calculations on the display section 10f or stores them in the RAM 10b.

RAM10bは、記憶部のうちデータの書き換えが可能なものであり、例えば半導体記憶素子で構成されてよい。RAM10bは、例えばCPU10aが実行するプログラム、そのプログラムで用いるデータを記憶してよい。なお、これらは例示であって、RAM10bには、これら以外のデータが記憶されてもよいし、これらの一部が記憶されなくてもよい。 The RAM 10b is a storage unit in which data can be rewritten, and may be formed of, for example, a semiconductor storage element. The RAM 10b may store, for example, a program executed by the CPU 10a and data used in the program. Note that these are just examples, and data other than these may be stored in the RAM 10b, or some of them may not be stored.

ROM10cは、記憶部のうちデータの読み出しが可能なものであり、例えば半導体記憶素子で構成されてよい。ROM10cは、例えば実行タイミング判断プログラムや、書き換えが行われないデータを記憶してよい。 The ROM 10c is a storage section from which data can be read, and may be composed of, for example, a semiconductor storage element. The ROM 10c may store, for example, an execution timing determination program and data that will not be rewritten.

通信部10dは、MES10を他の機器に接続するインターフェースである。通信部10dは、LAN等の通信ネットワークに接続されてよい。 The communication unit 10d is an interface that connects the MES 10 to other devices. The communication unit 10d may be connected to a communication network such as a LAN.

入力部10eは、ユーザからデータの入力を受け付けるものであり、例えば、キーボード及びタッチパネルを含んでよい。 The input unit 10e receives data input from the user, and may include, for example, a keyboard and a touch panel.

表示部10fは、CPU10aによる演算結果を視覚的に表示するものであり、例えば、LCD(Liquid Crystal Display)により構成されてよい。表示部10fは、例えば、制御信号や物理量を時系列で表示してよい。 The display unit 10f visually displays the calculation results by the CPU 10a, and may be configured by, for example, an LCD (Liquid Crystal Display). The display unit 10f may display control signals and physical quantities in time series, for example.

実行タイミング判断プログラムは、RAM10bやROM10c等のコンピュータによって読み取り可能な記憶媒体に記憶されて提供されてもよいし、通信部10dにより接続される通信ネットワークを介して提供されてもよい。MES10では、CPU10aが実行タイミング判断プログラムを実行することにより、上記で説明した様々な動作が実現される。なお、これらの物理的な構成は例示であって、必ずしも独立した構成でなくてもよい。例えば、MES10は、CPU10aとRAM10bやROM10cが一体化したLSI(Large-Scale Integration)を備えてもよい。 The execution timing determination program may be provided by being stored in a computer-readable storage medium such as the RAM 10b or ROM 10c, or may be provided via a communication network connected by the communication unit 10d. In the MES 10, the various operations described above are realized by the CPU 10a executing the execution timing determination program. Note that these physical configurations are merely examples, and do not necessarily have to be independent configurations. For example, the MES 10 may include an LSI (Large-Scale Integration) in which a CPU 10a, a RAM 10b, and a ROM 10c are integrated.

<<工程制御処理>>
図6から図11を参照して、第1実施形態に係る工程制御システムのMESにより実行される工程制御処理を説明する。図6は、第1実施形態に係る工程制御システムのMESにより実行される工程制御処理のフローチャートである。図6に示すように、図1に示す工程制御システム100は、一又は複数の製造工程ごとに製造目標数量及び納期を設定する(S1)。工程制御システム100は、納期を評価する(S2)。
<<Process control processing>>
Process control processing executed by the MES of the process control system according to the first embodiment will be described with reference to FIGS. 6 to 11. FIG. 6 is a flowchart of process control processing executed by the MES of the process control system according to the first embodiment. As shown in FIG. 6, the process control system 100 shown in FIG. 1 sets a target manufacturing quantity and delivery date for each one or more manufacturing processes (S1). The process control system 100 evaluates the delivery date (S2).

工程制御システム100は、納期が適当か否かを判断する(S3)。納期が適当ではない場合(S3においてNoの場合)には、ステップS1に戻り、工程制御システム100は、納期を再設定する。納期が適当ではない場合とは、工程制御システム100が製造工程を即座に実行しても納期に間に合わない(例えば全製造工程が終了しない)場合を含む。納期が適当である場合(S3においてYesの場合)には、ステップS4に進む。 The process control system 100 determines whether the delivery date is appropriate (S3). If the delivery date is not appropriate (No in S3), the process returns to step S1, and the process control system 100 resets the delivery date. The case where the delivery date is not appropriate includes a case where the delivery date cannot be met even if the process control system 100 executes the manufacturing process immediately (for example, all the manufacturing processes are not completed). If the delivery date is appropriate (Yes in S3), the process advances to step S4.

工程制御システム100は、製造工程を分解する(S4)。工程制御システム100は、分解した製造工程ごとのスケジュールを作成する(S5)。製造工程ごとのスケジュールは、例えば、各製造工程の最も遅い材料投入時刻(実行タイミング)と、各製造工程に対して投入される材料の数量と、を含む。 The process control system 100 disassembles the manufacturing process (S4). The process control system 100 creates a schedule for each disassembled manufacturing process (S5). The schedule for each manufacturing process includes, for example, the latest material input time (execution timing) of each manufacturing process and the quantity of materials to be input for each manufacturing process.

工程制御システム100は、実行対象の対象製造工程のスケジュールを評価し、その評価に基づいて当該スケジュールを調整する(S6)。工程制御システム100は、例えば、複数の製造工程ごとに、最適な材料投入時刻(実行タイミング)と、予測終了時刻における電力コストと、を算出する。つまり、工程制御システム100は、ステップS6を一又は複数の製造工程ごとに実行する。ステップS6の処理の詳細については、図7から図11を参照して説明する。 The process control system 100 evaluates the schedule of the target manufacturing process to be executed, and adjusts the schedule based on the evaluation (S6). The process control system 100 calculates, for example, the optimal material input time (execution timing) and the power cost at the predicted end time for each of a plurality of manufacturing processes. That is, the process control system 100 executes step S6 for each one or more manufacturing processes. Details of the process in step S6 will be explained with reference to FIGS. 7 to 11.

工程制御システム100は、対象製造工程への材料の投入開始を指示する(S7)。工程制御システム100は、全製造工程が終了したか否かを判断する(S8)。全製造工程が終了していない場合(S8においてNoの場合)は、ステップS6に戻る。他方で、全製造工程が終了した場合(S8においてYesの場合)は、工程制御処理を終了する。 The process control system 100 instructs the start of inputting materials to the target manufacturing process (S7). The process control system 100 determines whether all manufacturing processes have been completed (S8). If all the manufacturing steps have not been completed (No in S8), the process returns to step S6. On the other hand, if all the manufacturing steps have been completed (Yes in S8), the process control process is ended.

図7は、第1実施形態に係るMESにより実行される対象工程のスケジュールの評価及び調整処理のフローチャートである。特に図7は、図6に示すステップS6の処理内容をより具体的に示す図である。図7に示すように、図1に示す工程制御システム100は、前製造工程の工程進捗を評価する(S61)。例えば、複数の製造工程A,B,Cが実行される場合に、実行対象が製造工程Bであるときは、前製造工程は、製造工程Aである。また、MES10は、例えば、複数の製造工程の工程順序等の情報を管理しているため、当該情報に基づいて、製造工程の実行順にしたがい、製造工程を評価する。 FIG. 7 is a flowchart of schedule evaluation and adjustment processing for a target process executed by the MES according to the first embodiment. In particular, FIG. 7 is a diagram showing more specifically the processing contents of step S6 shown in FIG. As shown in FIG. 7, the process control system 100 shown in FIG. 1 evaluates the process progress of the pre-manufacturing process (S61). For example, when a plurality of manufacturing processes A, B, and C are executed and manufacturing process B is to be executed, manufacturing process A is the pre-manufacturing process. Furthermore, since the MES 10 manages information such as the order of a plurality of manufacturing processes, for example, the manufacturing processes are evaluated in accordance with the order of execution of the manufacturing processes based on this information.

工程制御システム100は、製造工程Aの予測終了時刻が確定したか否かを判断する(S62)。製造工程Aの予測終了時刻が確定していない場合(Noの場合)は、ステップS61に戻る。他方で、製造工程Aの予測終了時刻が確定している場合(Yesの場合)は、ステップS63に進む。 The process control system 100 determines whether the predicted end time of the manufacturing process A has been determined (S62). If the predicted end time of manufacturing process A has not been determined (in the case of No), the process returns to step S61. On the other hand, if the predicted end time of manufacturing process A has been determined (in the case of Yes), the process advances to step S63.

工程制御システム100は、最も遅い材料投入時刻を評価する(S63)。工程制御システム100は、最も遅い材料投入時刻が現在時刻と(ほぼ)一致するか否かを判断する(S64)。最も遅い材料投入時刻が現在時刻と(ほぼ)一致する場合(Yesの場合)は、ステップS69に進む。他方で、最も遅い材料投入時刻が現在時刻と(ほぼ)一致しない場合(Noの場合)は、ステップS65に進む。 The process control system 100 evaluates the latest material input time (S63). The process control system 100 determines whether the latest material input time (almost) matches the current time (S64). If the latest material input time (almost) matches the current time (in the case of Yes), the process advances to step S69. On the other hand, if the latest material input time does not (almost) match the current time (in the case of No), the process advances to step S65.

図8は、第1実施形態に係るMESにより実行される電力コストの取得処理、及び、電力コストの推移の予測処理の一例を示す図である。図9は、第1実施形態に係るMESにより実行される電力コストの取得処理の一例を示す図である。図7から図9に示すように、工程制御システム100は、例えば図1に示す電力コストサーバ1から現在時刻の電力コストを取得する(S65)。 FIG. 8 is a diagram illustrating an example of a power cost acquisition process and a power cost transition prediction process executed by the MES according to the first embodiment. FIG. 9 is a diagram illustrating an example of a power cost acquisition process executed by the MES according to the first embodiment. As shown in FIGS. 7 to 9, the process control system 100 acquires the power cost at the current time, for example, from the power cost server 1 shown in FIG. 1 (S65).

図10は、第1実施形態に係るMESにより実行される工程シミュレータによる対象工程の運転時間の導出処理の一例を示す図である。図8及び図10に示すように、工程制御システム100は、例えば図1に示す工程シミュレータ33により製造ラインLに含まれる対象製造工程Bの運転時間Tpを算出する(S90)。また、図8に示すように、工程制御システム100は、前製造工程Aの終了予定時刻t+Taを算出する(S95)。 FIG. 10 is a diagram illustrating an example of a process for deriving the operating time of a target process by a process simulator executed by the MES according to the first embodiment. As shown in FIGS. 8 and 10, the process control system 100 calculates the operating time Tp of the target manufacturing process B included in the manufacturing line L using, for example, the process simulator 33 shown in FIG. 1 (S90). Further, as shown in FIG. 8, the process control system 100 calculates the scheduled end time t+Ta of the pre-manufacturing process A (S95).

図7及び図8に示すように、工程制御システム100は、現在時刻(又は前製造工程の予測終了時刻)から最も遅い投入時刻までの電力コストの推移を予測する(S66)。より具体的には、図8に示すように、例えば、工程制御システム100は、ステップS65の取得結果、ステップS90の算出結果、及び、ステップS95の算出結果に基づいて、当該電力コストの推移を予測する。次に、工程制御システム100は、最適な材料投入時刻を判断して更新する(S67)。図11を参照して、より具体的に、当該電力コストの推移の予測処理及び最適な材料投入時刻の判断処理を説明する。 As shown in FIGS. 7 and 8, the process control system 100 predicts the transition of the power cost from the current time (or the predicted end time of the previous manufacturing process) to the latest input time (S66). More specifically, as shown in FIG. 8, for example, the process control system 100 calculates the transition of the power cost based on the acquisition result of step S65, the calculation result of step S90, and the calculation result of step S95. Predict. Next, the process control system 100 determines and updates the optimal material input time (S67). With reference to FIG. 11, more specifically, the process of predicting the transition of the power cost and the process of determining the optimal material input time will be described.

図11は、第1実施形態に係るMESにより実行される電力コストの推移の予測処理及び最適な材料投入時刻の判断処理の一例を示す図である。図8及び図11に示すように、例えば、工程制御システム100(図4に示す電力コスト予測部17)は、現在時刻までの電力コスト推移(E[t-n,...,t])をもとに将来の推移(Te)を予測する。 FIG. 11 is a diagram illustrating an example of a power cost transition prediction process and an optimal material input time determination process executed by the MES according to the first embodiment. As shown in FIGS. 8 and 11, for example, the process control system 100 (power cost prediction unit 17 shown in FIG. 4) also calculates the power cost trend (E[t-n,...,t]) up to the current time. Predict future trends (Te).

次に、工程制御システム100(図4に示す実行タイミング判断部19)は、図4に示す電力コスト予測部17が予測する電力コストであって、例えば、現在時刻(又は前製造工程の予測終了時刻)(第1タイミング)から、最も遅い投入時刻(第2タイミング)に基づく所定期間における電力コスト(Ep)が所定の条件を満たす場合に、対象製造工程Bの実行タイミングを判断する。例えば、図11に示すように、実行タイミング判断部19は、幅Tpの時間ウィンドウを予測区間終端(t+Te)までスライドさせることによって、最小電力コストを探索する。より具体的には、実行タイミング判断部19は、電力コスト予測部17が予測した電力コストの積分値であって、第1タイミングから第2タイミングに基づく所定期間における積分値が最小になる場合の第1タイミングを、対象製造工程Bの最適な実行タイミング(例えば時刻「t+Ta+Tq」)として判断する。 Next, the process control system 100 (execution timing determination unit 19 shown in FIG. 4) determines the power cost predicted by the power cost prediction unit 17 shown in FIG. When the power cost (Ep) in a predetermined period based on the latest input time (second timing) from the time) (first timing) satisfies a predetermined condition, the execution timing of the target manufacturing process B is determined. For example, as shown in FIG. 11, the execution timing determination unit 19 searches for the minimum power cost by sliding a time window of width Tp to the end of the prediction interval (t+Te). More specifically, the execution timing determining unit 19 determines the integral value of the power cost predicted by the power cost predicting unit 17, when the integral value in a predetermined period based on the first timing to the second timing becomes the minimum. The first timing is determined as the optimal execution timing for the target manufacturing process B (for example, time "t+Ta+Tq").

この構成によれば、工程制御システム100は、所定期間における電力コストが所定の条件を満たす場合に、対象製造工程の実行タイミングを判断するから、対象製造工程の最適な実行タイミングをより適切に判断可能である。 According to this configuration, the process control system 100 determines the execution timing of the target manufacturing process when the power cost in the predetermined period satisfies the predetermined condition, so that the optimal execution timing of the target manufacturing process can be determined more appropriately. It is possible.

図7に戻り、工程制御システム100(図4に示す実行タイミング判断部19)は、予測した前記電力コストに基づく、前記対象工程の実行タイミングの判断結果が所定の条件を満たすか否かを判断する(S68)。例えば、実行タイミング判断部19は、最適な材料投入時刻の更新が収束したか否かを判断する。最適な材料投入時刻の更新が収束した場合(Yesの場合)は、ステップS69に進む。他方で、最適な材料投入時刻の更新が収束していない場合(Noの場合)は、ステップS63に戻る。 Returning to FIG. 7, the process control system 100 (execution timing determination unit 19 shown in FIG. 4) determines whether the determination result of the execution timing of the target process based on the predicted power cost satisfies a predetermined condition. (S68). For example, the execution timing determination unit 19 determines whether updating of the optimal material input time has converged. If the updating of the optimal material input time has converged (in the case of Yes), the process advances to step S69. On the other hand, if the update of the optimal material input time has not converged (in the case of No), the process returns to step S63.

上記のとおり、工程制御システム100では、予測した電力コストに基づく、対象製造工程Bの実行タイミングの判断結果が所定の条件を満たすまで(例えば最適な材料投入時刻の更新が収束するまで)、(i)電力コスト予測部17における、対象製造工程の電力コストを予測すること、及び、(ii)実行タイミング判断部19における、対象製造工程の実行タイミングを判断することが繰り返し実行される。 As described above, in the process control system 100, until the judgment result of the execution timing of the target manufacturing process B based on the predicted power cost satisfies a predetermined condition (for example, until the update of the optimal material input time is converged) ( i) predicting the power cost of the target manufacturing process by the power cost prediction unit 17; and (ii) determining the execution timing of the target manufacturing process by the execution timing determining unit 19 are repeatedly executed.

ここで、例えば、工程制御システム100では、上記した手法で最適な材料投入時刻が複数回(例えば10回程度)算出される。例えば、複数回算出された最適な材料投入時刻の誤差が所定期間以内に収まる(収束)する場合に、工程制御システム100は、複数回算出された最適な材料投入時刻の平均値を「最適な材料投入時刻」として「確定」させてもよい。なお、「確定」される「最適な材料投入時刻」は、上記の平均値に限られず、複数回算出された最適な材料投入時刻の中央値、又は、最頻値を含んでもよい。 Here, for example, in the process control system 100, the optimal material input time is calculated multiple times (for example, about 10 times) using the method described above. For example, when the error in the optimal material loading time calculated multiple times falls within a predetermined period (convergence), the process control system 100 sets the average value of the optimal material loading time calculated multiple times to the "optimal material loading time". It is also possible to ``confirm'' the time as ``material input time''. Note that the "optimum material introduction time" to be "determined" is not limited to the above-mentioned average value, but may include the median value or the mode of the optimum material introduction times calculated a plurality of times.

この構成によれば、工程制御システム100では、判断される最適な材料投入時刻が安定するまで待って、「最適な材料投入時刻」を「確定」させることが可能であるから、より適切に最適な材料投入時刻を導入可能である。 According to this configuration, in the process control system 100, it is possible to "determine" the "optimum material introduction time" by waiting until the determined optimum material introduction time becomes stable, so that the process control system 100 can more appropriately optimize the "optimum material introduction time". It is possible to introduce material input times.

図7に示すように、最後に工程制御システム100は、最適な材料投入時刻を確定して予測終了時刻及び予測電力コストを導出する(S69)。 As shown in FIG. 7, the process control system 100 finally determines the optimal material input time and derives the predicted end time and predicted power cost (S69).

第1実施形態によれば、図1及び図4に示すMES10(実行タイミング判断装置)は、一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を、対象工程で使用される材料に関する情報に基づいて取得し、所定タイミングの電力コストに関する電力コスト情報を取得し、実行期間情報と、電力コスト情報と、一又は複数の工程に関する電力コストを予測するための電力コスト予測モデル31と、に基づいて対象工程の電力コストを予測し、予測した電力コストに基づいて対象工程の実行タイミングを判断する。よって、電力コストの高い時間帯(例えば電力コストのピーク時)を避けて対象工程を実行すること(例えば電力コストのピークシフト)が可能となる。したがって、一又は複数の工程に関する電力コストを低減可能である。 According to the first embodiment, the MES 10 (execution timing determination device) shown in FIGS. 1 and 4 provides execution period information regarding the execution period necessary for executing a target process among one or more processes. Acquire power cost information about the power cost at a predetermined timing based on information about materials used in The power cost of the target process is predicted based on the cost prediction model 31, and the execution timing of the target process is determined based on the predicted power cost. Therefore, it is possible to execute the target process (for example, shift the peak power cost) while avoiding time periods when the power cost is high (for example, the peak time of the power cost). Therefore, power costs related to one or more steps can be reduced.

<第2実施形態>
図12を参照して、第2実施形態に係る工程制御システム100Aを説明する。図12は、第2実施形態に係る工程制御システムのブロック構成を示す図である。第2実施形態に係る工程制御システム100Aは、図1に示す第1実施形態に係る工程制御システム100では、MES10が備えていた電力コスト予測モデル31を、電力コストサーバ1に備える点で異なる。第2実施形態に係る工程制御システム100Aでは、MES10から時刻tの電力コストCtの予測要求を電力コストサーバ1に送信する。電力コストサーバ1は、電力コスト予測モデル31を用いて時刻tの電力コストCtを算出して、算出した電力コストCtをMES10に送信する。
<Second embodiment>
With reference to FIG. 12, a process control system 100A according to the second embodiment will be described. FIG. 12 is a diagram showing a block configuration of a process control system according to the second embodiment. The process control system 100A according to the second embodiment differs from the process control system 100 according to the first embodiment shown in FIG. 1 in that the power cost prediction model 31 provided in the MES 10 is provided in the power cost server 1. In the process control system 100A according to the second embodiment, the MES 10 transmits a request for predicting the power cost Ct at time t to the power cost server 1. The power cost server 1 calculates the power cost Ct at time t using the power cost prediction model 31, and transmits the calculated power cost Ct to the MES 10.

<第3実施形態>
図13を参照して、第3実施形態に係る工程制御システム100Bを説明する。図13は、第3実施形態に係る工程制御システムのブロック構成を示す図である。第1実施形態に係る工程制御システム100では、製造ラインLにおいて製造工程Bが製造工程Aに基づいて実行される一方で、第3実施形態に係る工程制御システム100Bでは、製造ラインLにおいて製造工程Bが製造工程Aと製造工程Dとに基づいて実行される点で、両実施形態は異なる。以下では、第3実施形態に関して、第1実施形態と異なる点について特に説明する。
<Third embodiment>
With reference to FIG. 13, a process control system 100B according to a third embodiment will be described. FIG. 13 is a diagram showing a block configuration of a process control system according to the third embodiment. In the process control system 100 according to the first embodiment, the manufacturing process B is executed on the manufacturing line L based on the manufacturing process A, while in the process control system 100B according to the third embodiment, the manufacturing process Both embodiments differ in that B is performed based on manufacturing process A and manufacturing process D. Below, regarding the third embodiment, points that are different from the first embodiment will be particularly described.

例えば、図7に示すステップS61において、第3実施形態に係る工程制御システム100B(MES10)は、例えば、複数の製造工程A,D,B,Cの工程順序等の情報を管理しているため、当該情報に基づいて、製造工程の実行順にしたがい、製造工程の進捗を評価する。また、例えば対象製造工程が製造工程Bである場合、前製造工程は、製造工程A及び製造工程Dであるから、工程制御システム100B(MES10)は、製造工程の進捗評価を、製造工程Aに関する評価、及び、製造工程Dに関する評価に基づいて実行する。つまり、工程制御システム100B(MES10)は、製造工程Aに関する評価、及び、製造工程Dに関する評価のいずれも良好である場合に、図7に示すステップS62に処理を進める。 For example, in step S61 shown in FIG. 7, the process control system 100B (MES 10) according to the third embodiment manages information such as the process order of a plurality of manufacturing processes A, D, B, and C. Based on the information, the progress of the manufacturing process is evaluated in the order in which the manufacturing process is performed. Further, for example, when the target manufacturing process is manufacturing process B, the previous manufacturing processes are manufacturing process A and manufacturing process D. It is executed based on the evaluation and the evaluation regarding manufacturing process D. That is, the process control system 100B (MES 10) advances the process to step S62 shown in FIG. 7 when both the evaluation regarding the manufacturing process A and the evaluation regarding the manufacturing process D are good.

第3実施形態によれば、工程制御システム100Bでは、製造ラインLにおいて対象製造工程Bが、複数の製造工程(例えば製造工程A及び製造工程D)に基づいて実行される。したがって、対象製造工程が複数の製造工程を前提する工程制御システムであっても、第1実施形態の工程制御システムと同様な効果、つまり、電力コストの高い時間帯(例えば電力コストのピーク時)を避けて対象工程を実行すること(例えば電力コストのピークシフト)が可能となり、一又は複数の工程に関する電力コストを低減可能である。 According to the third embodiment, in the process control system 100B, the target manufacturing process B is executed on the manufacturing line L based on a plurality of manufacturing processes (for example, manufacturing process A and manufacturing process D). Therefore, even if the target manufacturing process is a process control system that assumes a plurality of manufacturing processes, the same effect as the process control system of the first embodiment can be achieved, that is, during times when electricity costs are high (for example, during peak electricity costs). It becomes possible to execute the target process while avoiding (for example, peak shift of power cost), and it is possible to reduce the power cost related to one or more processes.

<第4実施形態>
図14及び図15を参照して、第4実施形態に係る工程制御システム100Cを説明する。図14は、第4実施形態に係る工程制御システムのブロック構成を示す図である。図15は、第4実施形態に係る工程電力コスト予測プログラムの一例を示す図である。
<Fourth embodiment>
A process control system 100C according to the fourth embodiment will be described with reference to FIGS. 14 and 15. FIG. 14 is a diagram showing a block configuration of a process control system according to the fourth embodiment. FIG. 15 is a diagram illustrating an example of a process power cost prediction program according to the fourth embodiment.

図14に示す第4実施形態に係る工程制御システム100Cと、図1に示す第1実施形態に係る工程制御システム100との相違点は以下のとおりである。 The differences between the process control system 100C according to the fourth embodiment shown in FIG. 14 and the process control system 100 according to the first embodiment shown in FIG. 1 are as follows.

(1)図14に示すように、工程制御システム100Cでは、工程制御システム100が備えない、MES10の外部電力としてのバッテリ8と、バッテリ8に接続された太陽光発電系統9とをさらに備える点
(2)図14に示すように、工程制御システム100Cでは、工程制御システム100が備えない、バッテリ8の残量を管理するバッテリ残量モニタDB7をさらに備える点
(3)図15に示すように、工程制御システム100Cの工程電力コスト予測プログラム3において、工程制御システム100が備えない、バッテリ消費予測モデル35をさらに備える点
(1) As shown in FIG. 14, the process control system 100C further includes a battery 8 as external power for the MES 10, which the process control system 100 does not have, and a solar power generation system 9 connected to the battery 8. (2) As shown in FIG. 14, the process control system 100C further includes a battery remaining amount monitor DB7 that manages the remaining amount of the battery 8, which the process control system 100 does not have. (3) As shown in FIG. , the process power cost prediction program 3 of the process control system 100C further includes a battery consumption prediction model 35, which the process control system 100 does not have.

以下では、第4実施形態に関して、第1実施形態と異なる点について特に説明する。上記のとおり、工程制御システム100Cは、所定タイミング(例えば時刻t)におけるバッテリ8の残量に基づいてバッテリ8の運転期間を算出するバッテリ消費予測モデルを参照可能である。なお、バッテリ消費予測モデル35は参照可能であればよく、MES10、又は、工程制御システム100Cの外部に配置されてもよい。バッテリ8は、製造ラインLを駆動するために製造ラインLに供給される。図14に示すバッテリ8の残量を管理するバッテリ残量モニタDB7は、時刻tのバッテリ残量をバッテリ消費予測モデル35に入力する。 Below, regarding the fourth embodiment, points that are different from the first embodiment will be particularly described. As described above, the process control system 100C can refer to the battery consumption prediction model that calculates the operating period of the battery 8 based on the remaining amount of the battery 8 at a predetermined timing (for example, time t). Note that the battery consumption prediction model 35 only needs to be referenceable, and may be placed outside the MES 10 or the process control system 100C. The battery 8 is supplied to the manufacturing line L to drive the manufacturing line L. The battery remaining amount monitor DB 7 that manages the remaining amount of the battery 8 shown in FIG. 14 inputs the remaining battery amount at time t to the battery consumption prediction model 35.

図15に示すように、工程制御システム100C(第1取得部)は、材料数量に基づく運転時間(工程シミュレータ33によって算出される運転時間/例えば10分間)と、バッテリ8の運転期間(バッテリ消費予測モデル35によって算出される運転時間/例えば3分間)とに基づいて「外部電力運転時間」(例えば7分間)としての実行期間情報を取得する。工程制御システム100C(電力コスト予測部)は、電力コスト予測モデル31に入力された、電力コストCtと、予測時刻aと、バッテリ消費予測モデル35からの外部電力運転時間と、バッテリ残量モニタDB7からの時刻tのバッテリ残量と、基づいて対象工程の電力コストを予測する。工程制御システム100C(実行タイミング判断部)は、予測された電力コストに基づいて対象工程の実行タイミングを判断する。 As shown in FIG. 15, the process control system 100C (first acquisition unit) calculates the operating time based on the material quantity (operating time calculated by the process simulator 33/for example, 10 minutes) and the operating period of the battery 8 (battery consumption Execution period information is acquired as the "external power operation time" (for example, 7 minutes) based on the operation time calculated by the prediction model 35/for example, 3 minutes. The process control system 100C (power cost prediction unit) inputs the power cost Ct input into the power cost prediction model 31, the predicted time a, the external power operation time from the battery consumption prediction model 35, and the battery remaining amount monitor DB7. The power cost of the target process is predicted based on the battery remaining amount at time t from . The process control system 100C (execution timing determination unit) determines the execution timing of the target process based on the predicted power cost.

第4実施形態によれば、工程制御システム100Cは、電力コスト予測モデル31に入力された、電力コストCtと、予測時刻aと、バッテリ消費予測モデル35からの外部電力運転時間と、基づいて対象工程の電力コストを予測する。したがって、バッテリ8の電力供給をさらに踏まえて予測された電力コストに基づいて対象工程の最適な実行タイミングを判断可能である。 According to the fourth embodiment, the process control system 100C targets targets based on the power cost Ct, the predicted time a, and the external power operation time from the battery consumption prediction model 35, which are input to the power cost prediction model 31. Predict power costs for your process. Therefore, it is possible to determine the optimal execution timing of the target process based on the predicted power cost, further taking into account the power supply of the battery 8.

以上説明した各実施形態は、あらゆる点において本発明の例示に過ぎない。本発明の範囲を逸脱することなく種々の改良や変形を行うことができることは言うまでもない。つまり、本発明の実施にあたって、実施形態に応じた具体的構成が適宜採用されてもよい。また、上述した各実施形態は、本発明の理解を容易にするためのものであり、本発明を限定して解釈するためのものではない。実施形態が備える各要素並びにその配置、材料、条件、形状及びサイズ等は、例示したものに限定されるわけではなく適宜変更することができる。 The embodiments described above are merely illustrative of the present invention in all respects. It goes without saying that various improvements and modifications can be made without departing from the scope of the invention. That is, in implementing the present invention, specific configurations depending on the embodiments may be adopted as appropriate. Further, each of the embodiments described above is for facilitating understanding of the present invention, and is not for construing the present invention in a limited manner. Each element included in the embodiment, as well as its arrangement, material, conditions, shape, size, etc., are not limited to those illustrated, and can be changed as appropriate.

[付記]
本実施形態における態様は、以下のような開示を含む。
(付記1)
一又は複数の工程の実行タイミングを判断する実行タイミング判断装置であって、
前記一又は複数の工程に関する電力コストを予測するための電力コスト予測モデル(31)を参照可能に構成されており、
前記一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得する第1取得部(13)と、
所定タイミングの電力コストに関する電力コスト情報を取得する第2取得部(15)と、
前記実行期間情報と前記電力コスト情報と前記電力コスト予測モデル(31)とに基づいて前記対象工程の電力コストを予測する電力コスト予測部(17)と、
予測した前記電力コストに基づいて前記対象工程の実行タイミングを判断する実行タイミング判断部(19)と、を備える、
実行タイミング判断装置。
(付記2)
一又は複数の工程の実行タイミングを判断する実行タイミング判断装置で実行される実行タイミング判断方法であって、
前記一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得することと、
所定タイミングの電力コストに関する電力コスト情報を取得することと、
前記実行期間情報と、前記電力コスト情報と、前記一又は複数の工程に関する電力コストを予測するための電力コスト予測モデル(31)と、に基づいて前記対象工程の電力コストを予測することと、
予測した前記電力コストに基づいて前記対象工程の実行タイミングを判断することと、を含む、
実行タイミング判断方法。
(付記3)
一又は複数の工程の実行タイミングを判断する実行タイミング判断装置を、
前記一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得する第1取得部(13)、
所定タイミングの電力コストに関する電力コスト情報を取得する第2取得部(15)、
前記実行期間情報と、前記電力コスト情報と、前記一又は複数の工程に関する電力コストを予測するための電力コスト予測モデル(31)と、に基づいて前記対象工程の電力コストを予測する電力コスト予測部(17)、
予測した前記電力コストに基づいて前記対象工程の実行タイミングを判断する実行タイミング判断部(19)、
として機能させる、実行タイミング判断プログラム。
[Additional notes]
Aspects of this embodiment include the following disclosures.
(Additional note 1)
An execution timing determination device that determines the execution timing of one or more steps,
is configured to be able to refer to a power cost prediction model (31) for predicting power costs related to the one or more processes,
a first acquisition unit (13) that acquires execution period information regarding an execution period necessary for executing a target process among the one or more processes;
a second acquisition unit (15) that acquires power cost information regarding the power cost at a predetermined timing;
a power cost prediction unit (17) that predicts the power cost of the target process based on the execution period information, the power cost information, and the power cost prediction model (31);
an execution timing determination unit (19) that determines the execution timing of the target process based on the predicted power cost;
Execution timing judgment device.
(Additional note 2)
An execution timing determination method executed by an execution timing determination device that determines the execution timing of one or more steps,
Obtaining execution period information regarding an execution period necessary for executing a target step among the one or more steps;
Obtaining power cost information regarding power cost at a predetermined timing;
Predicting the power cost of the target process based on the execution period information, the power cost information, and a power cost prediction model (31) for predicting the power cost regarding the one or more processes;
determining the execution timing of the target process based on the predicted power cost;
How to determine execution timing.
(Additional note 3)
An execution timing determination device that determines the execution timing of one or more steps,
a first acquisition unit (13) that acquires execution period information regarding an execution period necessary for executing a target process among the one or more processes;
a second acquisition unit (15) that acquires power cost information regarding power costs at a predetermined timing;
Power cost prediction that predicts the power cost of the target process based on the execution period information, the power cost information, and a power cost prediction model (31) for predicting the power cost regarding the one or more processes. Part (17),
an execution timing determination unit (19) that determines the execution timing of the target process based on the predicted power cost;
Execution timing judgment program that functions as an execution timing judgment program.

1…電力コストサーバ、2…ERP、3…工程電力コスト予測プログラム、4…材料投入指示プログラム、5…材料数量DB、7…バッテリ残量モニタDB、8…バッテリ、9…太陽光発電系統、10…MES、10a…CPU、10b…RAM、10c…ROM、10d…通信部、10e…入力部、10f…表示部、11…情報処理部、13…第1取得部、15…第2取得部、17…電力コスト予測部、19…実行タイミング判断装置、31…電力コスト予測モデル、33…工程シミュレータ、41…工程実行タイミング判断モデル、100,100A,100B,100C…工程制御システム 1... Electricity cost server, 2... ERP, 3... Process electricity cost prediction program, 4... Material input instruction program, 5... Material quantity DB, 7... Battery remaining amount monitor DB, 8... Battery, 9... Solar power generation system, 10...MES, 10a...CPU, 10b...RAM, 10c...ROM, 10d...communication section, 10e...input section, 10f...display section, 11...information processing section, 13...first acquisition section, 15...second acquisition section , 17... Power cost prediction unit, 19... Execution timing judgment device, 31... Electricity cost prediction model, 33... Process simulator, 41... Process execution timing judgment model, 100, 100A, 100B, 100C... Process control system

Claims (9)

一又は複数の工程の実行タイミングを判断する実行タイミング判断装置であって、
前記一又は複数の工程に関する電力コストを予測するための電力コスト予測モデルを参照可能に構成されており、
前記一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得する第1取得部と、
所定タイミングの電力コストに関する電力コスト情報を取得する第2取得部と、
前記実行期間情報と前記電力コスト情報と前記電力コスト予測モデルとに基づいて前記対象工程の電力コストを予測する電力コスト予測部と、
予測した前記電力コストに基づいて前記対象工程の実行タイミングを判断する実行タイミング判断部と、を備える、
実行タイミング判断装置。
An execution timing determination device that determines the execution timing of one or more steps,
configured to be able to refer to a power cost prediction model for predicting power costs related to the one or more steps,
a first acquisition unit that acquires execution period information regarding an execution period necessary for executing a target step among the one or more steps;
a second acquisition unit that acquires power cost information regarding the power cost at a predetermined timing;
a power cost prediction unit that predicts the power cost of the target process based on the execution period information, the power cost information, and the power cost prediction model;
an execution timing determination unit that determines the execution timing of the target process based on the predicted power cost;
Execution timing judgment device.
前記実行タイミング判断部は、予測した前記電力コストに基づく、前記対象工程の実行タイミングの判断結果が所定の条件を満たすか否かを判断する、
請求項1に記載の実行タイミング判断装置。
The execution timing determination unit determines whether a determination result of the execution timing of the target process based on the predicted power cost satisfies a predetermined condition.
The execution timing determination device according to claim 1.
予測した前記電力コストに基づく、前記対象工程の実行タイミングの判断結果が前記所定の条件を満たすまで、(i)前記電力コスト予測部における、前記対象工程の電力コストを予測すること、及び、(ii)前記実行タイミング判断部における、前記対象工程の実行タイミングを判断することが繰り返し実行される、
請求項2に記載の実行タイミング判断装置。
(i) predicting the power cost of the target process in the power cost prediction unit until the judgment result of the execution timing of the target process based on the predicted power cost satisfies the predetermined condition; ii) determining the execution timing of the target process in the execution timing determination unit is repeatedly executed;
The execution timing determination device according to claim 2.
前記実行タイミング判断部は、前記電力コスト予測部が予測した前記電力コストであって、第1タイミングから前記第1タイミングよりも後の第2タイミングに基づく所定期間における前記電力コストが所定の条件を満たす場合に、前記対象工程の実行タイミングを判断する、
請求項1に記載の実行タイミング判断装置。
The execution timing determination unit is configured to determine whether the power cost predicted by the power cost prediction unit in a predetermined period based on a first timing and a second timing subsequent to the first timing satisfies a predetermined condition. If the condition is satisfied, determining the execution timing of the target process;
The execution timing determination device according to claim 1.
前記実行タイミング判断部は、前記電力コスト予測部が予測した前記電力コストの積分値であって、第1タイミングから前記第1タイミングよりも後の第2タイミングに基づく所定期間における前記積分値が最小になる場合の前記第1タイミングを、前記対象工程の最適な実行タイミングとして判断する、
請求項1に記載の実行タイミング判断装置。
The execution timing determining unit determines that the integral value of the power cost predicted by the power cost predicting unit is the minimum in a predetermined period from a first timing to a second timing after the first timing. determining the first timing when
The execution timing determination device according to claim 1.
前記対象工程が複数ある場合、複数の前記対象工程ごとに、(i)前記電力コスト予測部における、前記対象工程の電力コストを予測すること、及び、(ii)前記実行タイミング判断部における、前記対象工程の実行タイミングを判断することが実行される、
請求項1に記載の実行タイミング判断装置。
When there are a plurality of target processes, (i) the power cost prediction unit predicts the power cost of the target process for each of the plurality of target processes; and (ii) the execution timing determination unit predicts the power cost of the target process. Determining the execution timing of the target process is executed,
The execution timing determination device according to claim 1.
所定タイミングにおけるバッテリの残量に基づいて前記バッテリの運転期間を算出するバッテリ消費予測モデルを参照可能に構成されており、
前記第1取得部は、前記実行期間情報を、前記運転期間に関する情報基づいて取得する、
請求項1から6のいずれか一項に記載の実行タイミング判断装置。
It is configured to be able to refer to a battery consumption prediction model that calculates the operating period of the battery based on the remaining amount of the battery at a predetermined timing,
The first acquisition unit acquires the execution period information based on information regarding the operation period.
The execution timing determination device according to any one of claims 1 to 6.
一又は複数の工程の実行タイミングを判断する実行タイミング判断装置で実行される実行タイミング判断方法であって、
前記一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得することと、
所定タイミングの電力コストに関する電力コスト情報を取得することと、
前記実行期間情報と、前記電力コスト情報と、前記一又は複数の工程に関する電力コストを予測するための電力コスト予測モデルと、に基づいて前記対象工程の電力コストを予測することと、
予測した前記電力コストに基づいて前記対象工程の実行タイミングを判断することと、を含む、
実行タイミング判断方法
An execution timing determination method executed by an execution timing determination device that determines the execution timing of one or more steps,
Obtaining execution period information regarding an execution period necessary for executing a target step among the one or more steps;
Obtaining power cost information regarding power cost at a predetermined timing;
Predicting the power cost of the target process based on the execution period information, the power cost information, and a power cost prediction model for predicting the power cost regarding the one or more processes;
determining the execution timing of the target process based on the predicted power cost;
How to determine execution timing
一又は複数の工程の実行タイミングを判断する実行タイミング判断装置を、
前記一又は複数の工程のうち対象工程を実行する際に必要な実行期間に関する実行期間情報を取得する第1取得部、
所定タイミングの電力コストに関する電力コスト情報を取得する第2取得部、
前記実行期間情報と、前記電力コスト情報と、前記一又は複数の工程に関する電力コストを予測するための電力コスト予測モデルと、に基づいて前記対象工程の電力コストを予測する電力コスト予測部、
予測した前記電力コストに基づいて前記対象工程の実行タイミングを判断する実行タイミング判断部、
として機能させる、実行タイミング判断プログラム。
An execution timing determination device that determines the execution timing of one or more steps,
a first acquisition unit that acquires execution period information regarding an execution period necessary for executing a target process among the one or more processes;
a second acquisition unit that acquires power cost information regarding power costs at a predetermined timing;
a power cost prediction unit that predicts the power cost of the target process based on the execution period information, the power cost information, and a power cost prediction model for predicting the power cost related to the one or more processes;
an execution timing determination unit that determines the execution timing of the target process based on the predicted power cost;
Execution timing judgment program that functions as an execution timing judgment program.
JP2022061789A 2022-04-01 2022-04-01 Execution timing determination system, execution timing determination method, and execution timing determination program Pending JP2023151915A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2022061789A JP2023151915A (en) 2022-04-01 2022-04-01 Execution timing determination system, execution timing determination method, and execution timing determination program
PCT/JP2023/007949 WO2023189196A1 (en) 2022-04-01 2023-03-03 Execution timing determination device, execution timing determination method, and execution timing determination program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2022061789A JP2023151915A (en) 2022-04-01 2022-04-01 Execution timing determination system, execution timing determination method, and execution timing determination program

Publications (1)

Publication Number Publication Date
JP2023151915A true JP2023151915A (en) 2023-10-16

Family

ID=88201226

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2022061789A Pending JP2023151915A (en) 2022-04-01 2022-04-01 Execution timing determination system, execution timing determination method, and execution timing determination program

Country Status (2)

Country Link
JP (1) JP2023151915A (en)
WO (1) WO2023189196A1 (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5799248B2 (en) * 2011-02-25 2015-10-21 パナソニックIpマネジメント株式会社 Device control apparatus, device control method, and device control program
JP2015141465A (en) * 2014-01-27 2015-08-03 株式会社日立製作所 Management device and method of electric vehicle

Also Published As

Publication number Publication date
WO2023189196A1 (en) 2023-10-05

Similar Documents

Publication Publication Date Title
US5691895A (en) Mechanism and architecture for manufacturing control and optimization
Vin et al. A new approach for efficient rescheduling of multiproduct batch plants
Wang et al. A possibilistic decision model for new product supply chain design
Sawik Coordinated supply chain scheduling
US5710700A (en) Optimizing functional operation in manufacturing control
Chen A fuzzy back propagation network for output time prediction in a wafer fab
Zhang et al. An agent-based approach for e-manufacturing and supply chain integration
Tang et al. A mathematical programming model and solution for scheduling production orders in Shanghai Baoshan Iron and Steel Complex
Gajjar et al. Application of actor-critic learning algorithm for optimal bidding problem of a Genco
US20030171829A1 (en) System and method for complex process optimization and control
Qiu et al. A robust optimization approach for multi-product inventory management in a dual-channel warehouse under demand uncertainties
Wee et al. Multi products single machine economic production quantity model with multiple batch size
Minguillon et al. Coupling of centralized and decentralized scheduling for robust production in agile production systems
JP2008518359A (en) Solution and system for optimization problem
Chen et al. Optimal short-term scheduling of multiproduct single-stage batch plants with parallel lines
Cheng et al. Scheduling flexible manufacturing cell with no-idle flow-lines and job-shop via Q-learning-based genetic algorithm
Boschian et al. Contribution of simulation to the optimization of maintenance strategies for a randomly failing production system
JP2007249440A (en) Shipment planning system
Zhou et al. Reinforcement learning for online optimization of job-shop scheduling in a smart manufacturing factory
WO2023189196A1 (en) Execution timing determination device, execution timing determination method, and execution timing determination program
JP2003058206A (en) Catalyst utilization supporting method and system therefor
Li et al. Mixed-model assembly line balancing problem considering learning effect and uncertain demand
Gharbi et al. Production rate control for stochastic remanufacturing systems
Zhou et al. A dynamic material handling scheduling method based on elite opposition learning self-adaptive differential evolution-based extreme learning machine (EOADE-ELM) and knowledge base (KB) for line-integrated supermarkets
Masmoudi et al. Fuzzy uncertainty modelling for project planning: application to helicopter maintenance